CN101240661A - Large steel girder member bar turning device and its member bar turning method - Google Patents

Large steel girder member bar turning device and its member bar turning method Download PDF

Info

Publication number
CN101240661A
CN101240661A CNA2007101690502A CN200710169050A CN101240661A CN 101240661 A CN101240661 A CN 101240661A CN A2007101690502 A CNA2007101690502 A CN A2007101690502A CN 200710169050 A CN200710169050 A CN 200710169050A CN 101240661 A CN101240661 A CN 101240661A
Authority
CN
China
Prior art keywords
turning
over
steel girder
steel
member bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007101690502A
Other languages
Chinese (zh)
Other versions
CN100560918C (en
Inventor
佘巧宁
张维
张露
邓永峰
张红心
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CNB2007101690502A priority Critical patent/CN100560918C/en
Publication of CN101240661A publication Critical patent/CN101240661A/en
Application granted granted Critical
Publication of CN100560918C publication Critical patent/CN100560918C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

A large-scale steel girder truss lever turning-over device and a method for turning over the lever relates to the equipment for turning-over the large-scale girder truss lever and the turning-over method. The turning-over device is composed of a concrete pedestal, a turning-over wheel body, a steel supporting leg, an end rotating buckle, a locking device and the like. The turning-over course comprises the following steps: connecting the steel girder truss lever, installing the turning-over wheel body locking device and fixing, installing the underlay, when the steel girder truss lever to be turned over is lifted and installed to the position, screwing the bolt and installing the steel wire cable and windlass, releasing the locking device, when the steel girder truss is turned to the right position, releasing the connecting bolt of the turning-over wheel body, and the turning over of the steel girder truss lever is completed. The turning-over device can better protect the steel girder lever, can sufficiently guarantee the reliability and security of the steel girder lever in the turning-over process thereby better protecting the steel girder lever and increasing the turning-over work efficiency; and the steel girder truss is not deformed and damaged in the turning-over course. The turning-over device has the advantages of simple structure, suitability for on-site manufacturing, reliable and safe turning-over course, high efficiency, simple and convenient turning-over operation.

Description

Large steel girder member bar turning device and member bar turning method thereof
Technical field
The present invention relates to be used in the steel truss girder erection construction equipment and the method for turning of large steel girder member bar turning.
Background technology
Steel truss girder is that the rod member spelling by one group of group forms, each rod member of steel truss girder after steel truss girder professional production producer completes, through the water route or the land route be transported to bridge site, piece together lifting, depositing and piecing together in advance then in advance in the building site.
Steel truss girder needs rod member is pieced together in advance before installation, and its purpose is exactly to reduce the number of times of the lifting when setting a roof beam in place and the workload of work high above the ground assembly unit, accelerating construction progress.The pre-method of piecing together of steel girder member bar is exactly before steel truss girder sets up, the part rod member that is associated in advance on ground (pre-piece together) with dashing the nail location and the bolted on connection of working is in the same place.
Because of the certain directionality of setting up of upper and lower chord member, again because of the condition restriction of water route or land route transportation, the direction of the rod member of coming over is not necessarily with to set up direction consistent, so we must be provided with a supporting equipment for supporting patient with burn in the pre-field of piecing together according to the needs that set up, with this reliability and safety of satisfying the construction needs and guaranteeing steel girder member bar turning.
Along with construction requirements is also more and more higher, the scale of construction of single steel girder member bar is also more done bigger, and because of the employing of new technologies such as orthotropic plate makes that attached a lot of other primary structural components are (thiner on the single rod member, fragile), in order to adapt to this variation, in steel girder member bar assembly process in advance, adopt special equipment for supporting patient with burn to stand up, avoid unnecessary deformation and damage in the process of standing up with regard to requiring.
Now standing up of steel girder member bar generally is on the ground or directly utilizes lifting appliance to stand up in the sand pit, because of the rod member scale of construction big, it is very dangerous standing up operation as direct employing loop wheel machine, moreover the rod member accessory structure is many, is easy to also cause that the plastic strain of rod member and application pull-up fall.Carry out the research of steel truss girder equipment for supporting patient with burn, be intended to satisfy the construction needs, the better protection steel girder member bar, thus satisfy the quality requirement that steel truss girder sets up.
Summary of the invention
The objective of the invention is at above-mentioned present situation, aim to provide a kind of safe and reliable large steel girder member bar turning device and member bar turning method.
The implementation of purpose of the present invention is, large steel girder member bar turning device, single steel leg 3 is installed on the end concrete pedestal 1, on single steel leg 3 the end rotary buckle 5 that can connect steel girder member bar 7 is installed, on the middle part concrete pedestal 2 two steel legs 4 that can connect steel girder member bar 7 are installed, the upset wheel disc 6 that can connect steel girder member bar 7 is blocked on two steel legs 4 tops, and upset wheel disc 6 bottoms are by locking device 8 lockings.
The large steel girder member bar turning device member bar turning method, switching process is as follows:
1) earlier end rotary buckle 5 and steel girder member bar 7 ends are connected;
2) wherein half of wheel disc 6 of will overturning is installed on the steel leg on concrete pedestal 2 tops, middle part, by the locking device 8 wheel disc fixation of will overturning, installs the pad thing then;
3) utilize lifting appliance that steel girder member bar 7 to be flipped is in place, half upset wheel disc 6 in addition is installed, the good pad thing 11 of pad is bolted on;
4) wire rope and hoist engine are installed;
5) device 8 that unlocks utilizes hoist engine to make steel girder member bar 7 overturn together in company with upset wheel discs 8 and end rotary buckle 5 and puts in place;
6) untie upset wheel disc connecting bolt, the steel girder member bar upset is finished.
Adopt this equipment for supporting patient with burn, steel girder member bar 7 one ends are positioned on the end rotary buckle 5, and the centre is installed on two steel legs 4.
This equipment for supporting patient with burn can better protect the girder steel rod member, can fully guarantee reliability and safety in the girder steel member bar turning process, thus the good girder steel rod member of better protection, and can improve the upset work efficiency; Steel girder member bar is indeformable in the process of standing up, do not damage.This equipment for supporting patient with burn is simple in structure, is fit to the field machining manufacturing, overturn reliable and secure, efficient is high, turning operation is simple, make things convenient for.
Description of drawings
Fig. 1 large steel girder member bar turning device facade arrangement diagram
Fig. 2 is that the A-A of Fig. 1 is to view
Fig. 3 is that the B-B of Fig. 1 is to view
The specific embodiment
With reference to Fig. 1,2,3, single steel leg 3 is installed on the end concrete pedestal 1 of this equipment for supporting patient with burn, on single steel leg 3 the end rotary buckle 5 that can connect steel girder member bar 7 is installed, on the middle part concrete pedestal 2 two steel legs 4 that can connect steel girder member bar 7 are installed, the upset wheel disc 6 that can connect steel girder member bar 7 is blocked on two steel legs 4 tops, and upset wheel disc 6 bottoms are by locking device 8 lockings.
Large steel girder member bar upset, by two independently pedestal finish, its pedestal is that concrete is built and formed.One of them is provided in a side of the end concrete pedestal 1 of Rod end, and another is located at the middle part concrete pedestal 2 at rod member middle part, thereby can adapt to the rod member of different length.Determine two pedestals height separately according to the height of all rod members, determine distance between the pedestal according to the length of all rod members, the external force of being born by pedestal is determined planar dimension separately then.
The large steel girder member bar end is connected with end rotary buckle 5, is bearing on the single steel leg 3 on the end pedestal top; The girder steel middle part is connected with upset wheel disc 6, between copy with wooden unit and rubber pad thing 11 real fixing, thereby the rod member that adapts to different cross section is on the two steel legs 4 in the middle part of the upset wheel disc is bearing on the pedestal top, fixing by locking device 8 between upset wheel disc and the middle part concrete pedestal 2.Determine the size of end rotary buckle and upset wheel disc according to the cross section of rod member, and determine the size of steel leg according to stressing conditions;
With wire rope around the upset wheel disc on, be divided into initiatively haulage cable 9 and brake wire 10, utilize 2 hoist engines to control its upset then, a hoist engine initiatively draws the girder steel upset, and another hoist engine loosens wire rope and controls its velocity of rotation or braking.
Switching process of the present invention is as follows:
1) earlier end rotary buckle 5 and steel girder member bar 7 ends are connected;
2) wherein half of wheel disc 6 of will overturning is installed on the steel leg on concrete pedestal 2 tops, middle part, by the locking device 8 wheel disc fixation of will overturning, installs the pad thing then;
3) utilize lifting appliance that steel girder member bar 7 to be flipped is in place, half upset wheel disc 6 in addition is installed, the good pad thing 11 of pad is bolted on;
4) wire rope and hoist engine are installed;
5) device 8 that unlocks utilizes hoist engine to make steel girder member bar 7 overturn together in company with upset wheel discs 8 and end rotary buckle 5 and puts in place;
6) untie upset wheel disc connecting bolt, the steel girder member bar that upset is good lifts by crane the formulation position and deposits.

Claims (2)

1, large steel girder member bar turning device, it is characterized in that upward installation single steel leg (3) of end concrete pedestal (1), single steel leg (3) is gone up the end rotary buckle (5) that installation can connect steel girder member bar (7), middle part concrete pedestal (2) is gone up two steel legs (4) that installation can connect steel girder member bar (7), the upset wheel disc (6) that can connect steel girder member bar (7) is blocked on two steel legs (4) top, and upset wheel disc (6) bottom is locked by locking device (8).
2, the described large steel girder member bar turning device member bar turning method of claim 1 is characterized in that switching process is as follows:
1) earlier end rotary buckle (5) and steel girder member bar (7) end are connected;
2) wherein half of wheel disc (6) of will overturning is installed on the steel leg on middle part concrete pedestal (2) top, by locking device (8) the wheel disc fixation of will overturning, installs the pad thing then;
3) utilize lifting appliance that steel girder member bar to be flipped (7) is in place, half upset wheel disc (6) in addition is installed, the good pad thing of pad (11) is bolted on;
4) wire rope and hoist engine are installed;
5) device (8) that unlocks utilizes hoist engine to make steel girder member bar (7) overturn together in company with upset wheel disc (8) and end rotary buckle (5) and puts in place;
6) untie upset wheel disc connecting bolt, the steel girder member bar upset is finished.
CNB2007101690502A 2007-12-28 2007-12-28 Large steel girder member bar turning device and member bar turning method thereof Active CN100560918C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007101690502A CN100560918C (en) 2007-12-28 2007-12-28 Large steel girder member bar turning device and member bar turning method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007101690502A CN100560918C (en) 2007-12-28 2007-12-28 Large steel girder member bar turning device and member bar turning method thereof

Publications (2)

Publication Number Publication Date
CN101240661A true CN101240661A (en) 2008-08-13
CN100560918C CN100560918C (en) 2009-11-18

Family

ID=39932453

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007101690502A Active CN100560918C (en) 2007-12-28 2007-12-28 Large steel girder member bar turning device and member bar turning method thereof

Country Status (1)

Country Link
CN (1) CN100560918C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102127898A (en) * 2010-12-22 2011-07-20 中铁大桥局集团第四工程有限公司 Device and method for turning over steel truss girder member
CN102162302A (en) * 2011-04-08 2011-08-24 浙江东南网架股份有限公司 Turnover device for processing large-sized steel member
CN102220811A (en) * 2011-04-18 2011-10-19 武船重型工程有限公司 Truss arching-erecting splicing method of extra-large-pan steel pipe
CN103321213A (en) * 2013-05-31 2013-09-25 中交第二航务工程局有限公司 Integral installation device and method for water reinforcement cage

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102127898A (en) * 2010-12-22 2011-07-20 中铁大桥局集团第四工程有限公司 Device and method for turning over steel truss girder member
CN102162302A (en) * 2011-04-08 2011-08-24 浙江东南网架股份有限公司 Turnover device for processing large-sized steel member
CN102162302B (en) * 2011-04-08 2012-07-04 浙江东南网架股份有限公司 Turnover device for processing large-sized steel member
CN102220811A (en) * 2011-04-18 2011-10-19 武船重型工程有限公司 Truss arching-erecting splicing method of extra-large-pan steel pipe
CN102220811B (en) * 2011-04-18 2012-09-05 武船重型工程股份有限公司 Truss arching-erecting splicing method of extra-large-pan steel pipe
CN103321213A (en) * 2013-05-31 2013-09-25 中交第二航务工程局有限公司 Integral installation device and method for water reinforcement cage
CN103321213B (en) * 2013-05-31 2015-08-12 中交第二航务工程局有限公司 Reinforcing cage integral installation device waterborne and mounting method

Also Published As

Publication number Publication date
CN100560918C (en) 2009-11-18

Similar Documents

Publication Publication Date Title
CN102777030A (en) Method for building up formwork construction platform of lift shaft
CN113966435A (en) Wind driven generator mounting and dismounting device and construction method using same
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN105908761A (en) Construction technology of hanging basket moving platform for high slope
CN100560918C (en) Large steel girder member bar turning device and member bar turning method thereof
CN105692470A (en) Internal climbing tower crane and operating method thereof
CN106801511A (en) A kind of super large reserved opening hanging mould structure and its construction method
CN102912981B (en) Gate type high-rise building connected structure construction device
CN103216103A (en) Pre-deformation construction method for mounting oblique-arc-shaped combined steel-structured column of annular roof
CN113348289B (en) Multi-column wind turbine tower and erection method
CN108862081A (en) A kind of chain block crane boom and the application in the adjusting of beam steel protective layer thickness
CN209456892U (en) Cable-stayed bridge steel overhangs structure of sidewalk
CN205444975U (en) Large -scale room lid steel construction construction braced system with view platform
CN202945798U (en) Overhanging type scaffold corner device
CN205474862U (en) Wet seam template operation platform of portable case roof beam
CN201144523Y (en) Turn over device for heavy sectional steel girder rod
CN112177309A (en) Assembled protection platform used in building elevator shaft
CN209603163U (en) A kind of tower crane bearing platform ruggedized construction
CN107720652B (en) A kind of construction method for hanging of frame structure large scale equipment
CN208686053U (en) A kind of elevator well sizing climbing platforms device
CN202519621U (en) Steel hoop used for suspending support system
CN205294694U (en) Independent gin pole hoist device of movable
CN208347285U (en) A kind of construction and decoration high-altitude construction supporting structure
CN203638979U (en) Device for mounting tank floor in low-temperature storage tank
CN203113226U (en) Formwork support system with towering asymmetric concrete cantilever structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: No. 5 Enginering Co., Ltd. Of China Zhongtie Major Bridge Engineering

Assignor: China Zhongtie Major Bridge Engineering Co., Ltd.

Contract record no.: 2010420000041

Denomination of invention: Large steel girder member bar turning device and its member bar turning method

Granted publication date: 20091118

License type: Exclusive License

Open date: 20080813

Record date: 20100505

ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150205

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150205

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 430050 No. 38, Hanyang Avenue, Wuhan, Hubei

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.