CN101235647B - Drilling filling integrated drilling filling equipment and technique - Google Patents

Drilling filling integrated drilling filling equipment and technique Download PDF

Info

Publication number
CN101235647B
CN101235647B CN2007100539233A CN200710053923A CN101235647B CN 101235647 B CN101235647 B CN 101235647B CN 2007100539233 A CN2007100539233 A CN 2007100539233A CN 200710053923 A CN200710053923 A CN 200710053923A CN 101235647 B CN101235647 B CN 101235647B
Authority
CN
China
Prior art keywords
drilling
grouting
drill rod
aperture
drilling filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2007100539233A
Other languages
Chinese (zh)
Other versions
CN101235647A (en
Inventor
缪绪樟
易学文
王栋
杨裕恩
曹雪然
周晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GEOLOGICAL EXPLORATION INSTITUTE OF HUANGHE INSTITUTE OF SURVEY PLANNING DESIGN
Original Assignee
GEOLOGICAL EXPLORATION INSTITUTE OF HUANGHE INSTITUTE OF SURVEY PLANNING DESIGN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GEOLOGICAL EXPLORATION INSTITUTE OF HUANGHE INSTITUTE OF SURVEY PLANNING DESIGN filed Critical GEOLOGICAL EXPLORATION INSTITUTE OF HUANGHE INSTITUTE OF SURVEY PLANNING DESIGN
Priority to CN2007100539233A priority Critical patent/CN101235647B/en
Publication of CN101235647A publication Critical patent/CN101235647A/en
Application granted granted Critical
Publication of CN101235647B publication Critical patent/CN101235647B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

A drilling and grouting tool which integrates the drilling and the grouting has a drive drill rod, a short drill rod (1) and a connector (2), wherein the upper end of the short drill rod is connected with the drive drill rod and a driller, and the lower end is connected with a guide tube (3) through the connector, the lower end of the guide tube is connected with a full-face drill head (4), and a swing-up type aperture sealer is connected on an aperture tube on the ground. The drilling and grouting technology comprises the steps that firstly tripped into the drilling and grouting tool, driving the drilling head to crack rocks with the axial pressure and the radial torque force of the driller through the drive drill rod, the short drill rod and the guide tube, moving the drilling and grouting tool a certain distance from the bottom of the hole, cleaning the drill hole with pure water which has certain pressure and is provided by a water pump, and finally moving the drilling and grouting tool a certain distance from the bottom of the hole, connecting the swing-up type aperture sealer with the aperture tube, then rotating with a gland (5), compressing and expanding with a sealing ring (8) to contact with a grouting tube, namely the drive drill rod, thereby realizing the enclosure of the aperture. Slurry can be grouted into the grouting sections according to the different grouting designs, and the circulating slurry in the aperture can be returned from a recycle slurry pipe (7).

Description

A kind of drilling filling integrated drilling filling equipment and technology
Technical field:
The invention belongs to the based process technical field, particularly relate to a kind of drilling filling integrated drilling filling equipment and technology.
Background technology:
Grouting technique is one of extremely important technology of based process, and nearly 200 years history is arranged, and now is widely used in various based process and the engineering protection.
In present grouting works, the grouting hole depth is general<100m, minority has 100~160m, and grout compartment length generally is designed to 5m, and its main brill is irritated technological process and is: " grout compartment creeps into--grout compartment flushing--, and grout compartment is in the milk " three process.Grout compartment creeps into operation, needs a plurality of round trips that creep into, and each creeps into round trip, all needs down drilling tool, creeps into, salvages rock core, promotes drilling tool, goes round and begins again to finish a grout compartment and creep into; Grout compartment flushing operation, grout compartment creep into finish after, be lowered to drilling tool and wash; The grout compartment grouting procedure after finishing the grout compartment flushing, proposes drilling tool, is lowered to the grouting facility, is in the milk.
The conventional grout technology, pore-forming technique is taked core-drilling, needs to put repeatedly drilling tool and Grout-jetting pipe in pore-forming, flushing, each operation of being in the milk, and the deficiency of its existence mainly contains the following aspects:
A. grout hole is except that minority pilot hole, inspection eye, and do not require core drilling.The conventional grout technology is underused this technological accumulation and inheritance of non-core drilling;
B. effective time, utilization rate was low, high material consumption, and efficiency of construction is low, and operation labor intensity is big.Because construction is long non-cutting time, effectively bores the filling time availability and have only 45%~50% according to statistics; See Table 1:
Table 1 Different Strata is bored and is irritated efficient and cost consumption data
The stratum Bore and irritate efficient (m/ platform day) Cost consumption (unit/m)
Pile up broken formation 3~4m 280~320
V~VII basement rock 5~7m 210~260
The above basement rock of VII 4~6m 240~280
C. so the hole is the rate height.Owing to need in creeping into repeatedly drilling tool and Grout-jetting pipe to be proposed boring, easily cause hole wall collapse on the one hand, especially all the more so in broken scall; Pipe rate height admittedly in filling process on the other hand.
Summary of the invention:
For overcoming the problem that the conventional grout technical matters exists, the purpose of this invention is to provide a kind of drilling filling integrated drilling filling equipment and technology, utilize full-face drilling and aperture to seal full hole cycle grouting and finish pore-forming, flushing and grouting, integrate the linking side chain between each operation, realize boring the filling process optimization, improve and bore the linking ability of irritating operation, reduce cost, raise the efficiency.
For achieving the above object, the present invention adopts following technical scheme:
A kind of drilling filling integrated drilling filling equipment, it has kelly, short drill pipe, joint, guide pipe and full section drill bit, and the short drill pipe upper end is connected with rig with kelly, and the lower end is connected with guide pipe by joint, and the guide pipe lower end is connected with full section drill bit; On the orifice tube on ground, be connected with and revolve lift-type aperture sealer.
Described drilling filling integrated drilling filling equipment, its guide pipe that plays the correcting drilling action adopts thick walled steel tube.
Described drilling filling integrated drilling filling equipment, it revolves lift-type aperture sealer is made up of gland, overcoat and sealing ring, gland is connected with sleeve thread, the gland lower end contacts with sealing ring, sealing ring and gland contact site are provided with pad, sealing ring places overcoat inside, is welded with return pipe in the overcoat bottom.
Described drilling filling integrated drilling filling equipment, its sealing ring material of revolving lift-type aperture sealer is an elastomeric material.
A kind of brill is irritated incorporate brill and is irritated technology, and its processing step is:
1, grout compartment creeps into: be lowered to drilling filling integrated drilling filling equipment, axial compression that rig is given and torsional forces radially pass to full section drill bit by kelly, short drill pipe and guide pipe, drive the drill bit fractured rock;
2, grout compartment flushing: drilling filling integrated drilling filling equipment is lifted from certain distance at the bottom of the hole, and the clear water with certain pressure with water pump provides carries out bore flushing;
3, grout compartment grouting: drilling filling integrated drilling filling equipment is lifted from certain distance at the bottom of the hole, be connected with orifice tube revolving lift-type aperture sealer, revolve the gland of lift-type aperture sealer, press the sealing ring that expands, make sealing ring and Grouting Pipe, i.e. kelly contact realizes the aperture sealing, just can be according to different grouting designs to the grout compartment reperfusion serosity, loop slurry is returned by return pipe in the hole.
Because adopt aforesaid technical scheme, the present invention has following superiority:
This drilling filling integrated drilling filling equipment has complex function, when creeping into, can be used as drilling tool, and gram is got fractured rock and realized drilling depth; When the flushing grout compartment, can be used as the bore flushing utensil, carry out bore flushing; When grouting, can be used as the grouting facility again, bored a grout compartment, do not need to propose boring, and only lift from the bottom of the hole, can be to the grout compartment reperfusion serosity.This drilling filling integrated drilling filling equipment, lift-type aperture sealer is revolved in employing, realized that the aperture seals the cycle grouting technological break-through of full hole, can guarantee effectively that Grouting Pipe can gyration in filling process, can move up and down again, make grout pipe the most thorny in the grouting construction manage fault admittedly, welded tube fault just, incidence drops to below 1% by 5%.
This drilling filling integrated drilling filling equipment and technology, linking side chain between each operation in traditional grouting process is integrated, formation boring and flushing crack, packer permeability test, filling process are controlled integrated new technology, therefore improve grouting construction efficient and quality greatly, have reduced cost.Prove through engineering practice, in similar engineering, compare that the grouting pore-forming efficiency on average improves 60% with the conventional grout method; Bore filling efficient and on average improve 90%, direct cost descends 20~30% for single meter, and effective brill is irritated time availability and reached 60~75%, has obtained remarkable economic efficiency.
Prove through application in practice: in the Xiao Langdi grouting works, the above basement rock grouting of VII level is bored filling efficient and is reached 11.4m/ platform day, bores filling efficient and improves 62%; Engineering direct cost expense reduces by 38%; In the reservoir grouting works of the little South Sea, Chongqing, the boring average efficiency improves 60~80%; Bore and irritate average efficiency raising 70~90%.
The present invention can be applied in any grouting works, and especially in loose, broken, the bad ground such as cave in that tradition bore to irritate that technology is difficult to ensure the quality of products, effect is more remarkable, and drilling depth is big more, and economic benefit and efficient raising are obvious more.
Description of drawings:
Fig. 1 is the drilling filling integrated drilling filling equipment structural representation;
Fig. 2 is the section of structure that revolves lift-type aperture sealer.
Among the figure: the 1-short drill pipe; The 2-joint; The 3-guide pipe; The full section drill bit of 4-; The 5-gland; The 6-overcoat; The 7-return pipe; The 8-sealing ring.
The specific embodiment:
As shown in Figure 1, 2, this drilling filling integrated drilling filling equipment, have kelly, short drill pipe (1), joint (2), guide pipe (3) and full section drill bit (4), short drill pipe (1) upper end is connected with rig with kelly, the lower end is connected with guide pipe (3) by joint (2), and guide pipe (3) lower end is connected with full section drill bit (4); On the orifice tube on ground, be connected with and revolve lift-type aperture sealer.
Described drilling filling integrated drilling filling equipment, its guide pipe (3) that plays the correcting drilling action adopts thick walled steel tube.
Described drilling filling integrated drilling filling equipment, it revolves lift-type aperture sealer is made up of gland (5), overcoat (6) and sealing ring (8), gland (5) is threaded with overcoat (6), gland (5) lower end contacts with sealing ring (8), sealing ring (8) is provided with pad with gland (5) contact site, sealing ring (8) places overcoat (6) inside, is welded with return pipe (7) in overcoat (6) bottom.
Described drilling filling integrated drilling filling equipment, its sealing ring (8) material of revolving lift-type aperture sealer is an elastomeric material.
This brill is irritated incorporate brill and is irritated concrete processing step: at first, grout compartment creeps into, and is lowered to drilling filling integrated drilling filling equipment, axial compression that rig is given and torsional forces radially, pass to full section drill bit (4) by kelly, short drill pipe (1) and guide pipe (3), drive the drill bit fractured rock; Secondly, the grout compartment flushing is lifted from certain distance at the bottom of the hole with drilling filling integrated drilling filling equipment, and the clear water with certain pressure with water pump provides carries out bore flushing; At last, grout compartment grouting, drilling filling integrated drilling filling equipment is lifted from certain distance at the bottom of the hole, be connected with orifice tube, revolve the gland (5) of lift-type aperture sealer revolving lift-type aperture sealer, press the sealing ring (8) that expands, make sealing ring (8) and Grouting Pipe, i.e. kelly contact realizes the aperture sealing, just can be according to different grouting designs to the grout compartment reperfusion serosity, loop slurry is returned by return pipe (7) in the hole.

Claims (1)

1. drilling filling integrated drilling filling equipment, it has kelly, short drill pipe (1), joint (2), the short drill pipe upper end is connected with rig with kelly, on the orifice tube on ground, be connected with and revolve lift-type aperture sealer, it is characterized in that: described brill is irritated facility, its short drill pipe lower end is connected with guide pipe (3) by joint, and the guide pipe lower end is connected with full section drill bit (4); The guide pipe (3) that plays the correcting drilling action adopts thick walled steel tube.
CN2007100539233A 2007-01-31 2007-01-31 Drilling filling integrated drilling filling equipment and technique Active CN101235647B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007100539233A CN101235647B (en) 2007-01-31 2007-01-31 Drilling filling integrated drilling filling equipment and technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007100539233A CN101235647B (en) 2007-01-31 2007-01-31 Drilling filling integrated drilling filling equipment and technique

Publications (2)

Publication Number Publication Date
CN101235647A CN101235647A (en) 2008-08-06
CN101235647B true CN101235647B (en) 2010-12-15

Family

ID=39919529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007100539233A Active CN101235647B (en) 2007-01-31 2007-01-31 Drilling filling integrated drilling filling equipment and technique

Country Status (1)

Country Link
CN (1) CN101235647B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839651B (en) * 2012-09-19 2014-11-05 中国电建集团中南勘测设计研究院有限公司 Drilling and grouting integrated top-down high-pressure impact extrusion grouting method
CN105457997B (en) * 2015-12-18 2018-10-02 浙江博世华环保科技有限公司 A kind of method and apparatus of original position injection
CN107165659A (en) * 2017-07-17 2017-09-15 中国电建集团华东勘测设计研究院有限公司 Water-bed tunnel meets shear-zone front pre-grouting construction method
CN110374083A (en) * 2019-07-11 2019-10-25 长沙理工大学 A kind of double pressure-controlled impact extrusion grouting system and its construction method
CN114059544B (en) * 2021-12-10 2023-12-22 重庆电讯职业学院 Underwater cement pouring system based on Internet of things

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2042109U (en) * 1988-10-21 1989-08-02 煤炭工业部煤炭科学研究院重庆研究所 All-hydraulic drilling machine
CN2260820Y (en) * 1996-04-22 1997-08-27 华北电力设计院 Pile-forming drilling machine for pump concrete-pouring pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2042109U (en) * 1988-10-21 1989-08-02 煤炭工业部煤炭科学研究院重庆研究所 All-hydraulic drilling machine
CN2260820Y (en) * 1996-04-22 1997-08-27 华北电力设计院 Pile-forming drilling machine for pump concrete-pouring pile

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
段新胜等.水库大坝坝基岩石灌浆不提钻钻灌工艺.西部探矿工程 总第81期.2003,(总第81期),第24-25页.
段新胜等.水库大坝坝基岩石灌浆不提钻钻灌工艺.西部探矿工程 总第81期.2003,(总第81期),第24-25页. *
王栋等.小浪底深孔帷幕灌浆工程施工技术探讨.探矿工程 2005年增刊.2005,(2005年增刊),第138-141页.
王栋等.小浪底深孔帷幕灌浆工程施工技术探讨.探矿工程 2005年增刊.2005,(2005年增刊),第138-141页. *

Also Published As

Publication number Publication date
CN101235647A (en) 2008-08-06

Similar Documents

Publication Publication Date Title
CN102080526B (en) Method for extracting gas from bedding level fractured well of ground coal seam roof
CN102877857B (en) Deep hole pre-grouting top plate reinforcement method for large-mining height working face under special geological conditions
CN101818644B (en) Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method
CN100560937C (en) A kind of thin basic rock shallow buried coal seam longwall face water retaining exploitation method
CN103835651B (en) A kind of single hole directional drilling local slip casting mine shaft rising boring technique
CN104863629A (en) Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole
CN101235647B (en) Drilling filling integrated drilling filling equipment and technique
CN102022133A (en) Regional gas underground high-pressure jet hole digging, pressure relief and outburst prevention method
CN106246099A (en) Spiral soil compaction down-the-hole embedding rock device and pile making method
CN103953386A (en) Upstream-blocking and downstream-seepage method for extracting gas in mining area
CN202673154U (en) Drill bit used for mixing pile machine and mixing pile machine
CN101985836B (en) Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN205605151U (en) Rock bottom cutting coring bit
CN102767332B (en) Screw pile machine and cast-in place pile construction method
CN105649563A (en) Application of steel strand in multi-angle drilling and coring process
CN203960941U (en) A kind of artesian water water intake well
CN204530674U (en) The one formula forward that fetches earth becomes twist bit lamps structure and varying pitch screw pile body
CN103362541B (en) High gassy and low permeability coal seam regionality increases the method for gas permeability of coal seam
CN209724227U (en) The double high-pressure stirring-spraying piles of reducing
CN204626390U (en) A kind of drilling tool current divider for quadruple high-pressure rotary-spray
CN202688987U (en) Spiral pile machine
CN205297636U (en) Anti -reflection drainage system in coal seam in drilling
CN109610494B (en) Rock-socketed construction process for large-diameter pile foundation
CN203080528U (en) Drilling and spraying integrated foundation treating special drilling tool assembly
CN105134125A (en) Construction process for blocking bottom end of annular space behind gas vertical well wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant