CN101230753A CNA2008100264752A CN200810026475A CN101230753A CN 101230753 A CN101230753 A CN 101230753A CN A2008100264752 A CNA2008100264752 A CN A2008100264752A CN 200810026475 A CN200810026475 A CN 200810026475A CN 101230753 A CN101230753 A CN 101230753A
Authority
CN
China
Prior art keywords
building
steel truss
shield driving
shield
tunneling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008100264752A
Other languages
Chinese (zh)
Inventor
丁仕辉
詹杰民
林世友
张挺
汪永剑
吕付玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong No 2 Hydropower Engineering Co Ltd
National Sun Yat Sen University
Original Assignee
Guangdong No 2 Hydropower Engineering Co Ltd
National Sun Yat Sen University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No 2 Hydropower Engineering Co Ltd, National Sun Yat Sen University filed Critical Guangdong No 2 Hydropower Engineering Co Ltd
Priority to CNA2008100264752A priority Critical patent/CN101230753A/en
Publication of CN101230753A publication Critical patent/CN101230753A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a strengthening method of a top head frame building in the process of non rock foundation shield tunneling, and the method is characterized in that: with adopting a steel truss and a holt hoop iron top supporting frame column, a measuring instrument is used to observe the deformation condition of a building and the steel truss, and a mechanical or oil jack is used for adjustment to realize the height of each point of the whole building to be kept invariable during the construction process. When the shield tunneling is finished, if a ground foundation has excessive settlement, the grouting method is adopted for processing the ground foundation. The invention is characterized in that a temporary underpinning device for the steel truss is adopted for transferring the whole or a part of the weight of the building onto the ground foundation out of the influence of the shielding tunneling, and a column base of the prior building is not needed excavating and strengthening before the shielding tunneling. The invention has the remarkable improvements and the beneficial effects that the safety of an upper building is ensured during the shielding tunneling, the collapse of a casing layer which is arranged at the upper part of a shield caused by the stress of the building is prevented, the progress and the safety of the shielding tunneling is influenced, and the strengthening cost of the upper building is lowered.

Description

A kind of in non-batholith shield driving process the reinforcement means of loam cake frame building
Technical field
The present invention relates to city underground shield driving engineering, particularly a kind of in non-batholith the reinforcement means of loam cake frame building in the shield driving process.
Carry on the back technology
Metro construction adopts shield construction progressively to rise, in soft rock strata, and advantages such as speed of application is fast, ambient influnence is little, the loam cake building strengthening is simple that it has.Yet, shield driving in non-batholith, desirable method is not found in the reinforcing of loam cake frame building all the time, just takes measures such as pile foundation underpinning or increase raft foundation to reinforce the sedimentation of control building in the basis of loam cake building, this reinforcement means is a kind of passive reinforcement means, the expense height, the time is long, increases the building system load, can not implementation procedure control, easily cause the damage of loam cake building.
Summary of the invention
The present invention be intended to overcome the deficiencies in the prior art and provide a kind of ensure that the building safety construction costs is few and progress is fast a kind of in non-batholith shield driving process the reinforcement means of loam cake frame building.
The object of the present invention is achieved like this: a kind of in non-batholith shield driving process the reinforcement means of loam cake frame building, comprise and adopt steel truss and anchor ear jacking frame column, measuring instrument observation building and steel truss distortion situation, utilize machinery or hydraulic jack adjustment, realize that whole each point height of solitary building remains unchanged in work progress, after shield driving is finished, ground is if there is excessive sedimentation, then adopt the grouting means that ground is handled, it is characterized in that adopting the interim underpinning device of steel truss, the all or part of weight of building is transferred on the outer ground of shield driving influence, be need not before the shield driving base for post of existing building is excavated reinforcing.
The interim underpinning device of described steel truss is meant and utilizes anchor ear and load-bearing steel truss that all or part of the transferring to of building weight that first floor frame column is born is subjected on the outer ground of shield driving influence basin.
The shield driving overall process can be monitored building and foundation settlement, and adjusts the top lifting height of jack according to the sedimentation situation, guarantees that the elevation of building each point is constant.
By adopting the first floor frame column of steel truss, anchor ear and jack jacking building, measuring apparatus monitoring building and steel truss are out of shape situation when shield driving, utilize the jack adjustment, realize that dynamically each point height of building remains unchanged in work progress.After shield driving was finished, ground then adopted the grouting means that ground is handled if excessive depression is arranged.
Principle of the present invention is a principle of utilizing power to transmit, and all or part of the transferring to of the pressure of shield driving building that top cover bears is not subjected on the ground that shield driving influences; And use the sedimentation situation of measuring instrument monitoring building when shield driving, and utilize jack adjustment, reach the target that each point height of building remains unchanged at work progress.
Marked improvement of the present invention and beneficial effect are: the safety of upper building when having ensured shield driving, prevent that shield structure top overburden layer from subsiding under building weight, and influence shield driving progress and safety, reduce the reinforcing expense of upper building.
Adopt the steel truss support and change method, in the metro shield tunneling process, the loam cake building is underpined temporarily, guarantee the safety of building, use to building is disturbed little, avoid moving the social influence that causes, steel truss underpins at constructing tunnel and passes through the dismountable recycling in back, has reduced construction costs, has huge social and economic benefit.
Description of drawings:
Fig. 1 is a schematic diagram of the present invention.
Fig. 2 is a reinforcing flow chart of the present invention.
Among the figure: 1 for load-bearing steel truss, 2 is that jack, 3 is that anchor ear, 4 is the building frame post, and 5 is the building frame beam, and 6 is the tunnel of shield-tunneling construction.
The specific embodiment
1, detailed reinforcing flow process of readding shield structure loam cake frame building.
2, consult shield structure loam cake building design drawing, calculate the weight that each frame column of the building first floor is born.
3, according to the weight that each frame column held, design is also made load-bearing steel truss 1) and anchor ear 3), purchase suitable jack 2).
4, root pick result of calculation is handled the ground of supporting steel truss.
5, after ground is handled and had certain intensity, carry out strengthening construction.The steel truss of lifting load-bearing earlier 1), anchor ear 3 is installed on first floor frame column then) (can according to circumstances frame column be disconnected or not disconnect) in the anchor ear lower end, again at anchor ear 3) and load-bearing steel truss 1) between installation jack 2).In the shield driving process, by measuring instrument observation building and steel truss 1) the distortion situation, and steel truss 1) support the foundation settlement situation, adjust jack 2) top lifting height, each point height of building is remained unchanged;
6, if excessive sedimentation appears in ground, then after shield driving, ground is carried out grouting treatment, after the ground of handling has sufficient intensity, remove the hardened system of frame column.
Implementation
Outside the shield driving influence, support the ground of jack and steel truss, adopt upper berth, reinforcing bar basis steel plate to handle.
But jack adopts the jack of hydraulic pressure reading, and anchor ear adopts steel to make.
The load-bearing steel truss adopts steel to make or with the assembly unit of assembling shellfish thunder frame, the scene lifts with crane.

Claims (3)

1. the reinforcement means of loam cake frame building in the non-batholith shield driving process, comprise and adopt steel truss and anchor ear jacking frame column, measuring instrument observation building and steel truss distortion situation, utilize machinery or hydraulic jack adjustment, realize that whole each point height of solitary building remains unchanged in work progress, after shield driving is finished, ground is if there is excessive sedimentation, then adopt the grouting means that ground is handled, it is characterized in that adopting the interim underpinning device of steel truss, the all or part of weight of building is transferred on the outer ground of shield driving influence, be need not before the shield driving base for post of existing building is excavated reinforcing.
2. according to claim 1 a kind of in non-batholith shield driving process the reinforcement means of loam cake frame building, it is characterized in that the interim underpinning device of described steel truss is meant to utilize anchor ear and load-bearing steel truss that all or part of the transferring to of building weight that first floor frame column is born is subjected on the outer ground of shield driving influence basin.
3. the reinforcement means of a section according to claim 1 loam cake frame building in non-batholith shield driving process, it is characterized in that to monitor building and foundation settlement in the shield driving overall process, and adjust the top lifting height of jack according to the sedimentation situation, guarantee that the elevation of building each point is constant.
CNA2008100264752A 2008-02-26 2008-02-26 Method for reinforcing top cover frame buildings work in non-batholith shield excavation process Pending CN101230753A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008100264752A CN101230753A (en) 2008-02-26 2008-02-26 Method for reinforcing top cover frame buildings work in non-batholith shield excavation process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008100264752A CN101230753A (en) 2008-02-26 2008-02-26 Method for reinforcing top cover frame buildings work in non-batholith shield excavation process

Publications (1)

Publication Number Publication Date
CN101230753A true CN101230753A (en) 2008-07-30

Family

ID=39897534

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008100264752A Pending CN101230753A (en) 2008-02-26 2008-02-26 Method for reinforcing top cover frame buildings work in non-batholith shield excavation process

Country Status (1)

Country Link
CN (1) CN101230753A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611114A (en) * 2019-01-02 2019-04-12 山东科技大学 Crouch the Underground Space Excavation method of existing tunnel under a kind of soil rock compound stratum
CN113654748A (en) * 2021-10-19 2021-11-16 山东润龙轴承有限公司 Hang basket structure amount of deflection monitoring facilities

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611114A (en) * 2019-01-02 2019-04-12 山东科技大学 Crouch the Underground Space Excavation method of existing tunnel under a kind of soil rock compound stratum
CN113654748A (en) * 2021-10-19 2021-11-16 山东润龙轴承有限公司 Hang basket structure amount of deflection monitoring facilities

Similar Documents

Publication Publication Date Title
CN108086340B (en) Open caisson construction structure and construction method thereof
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN109630127B (en) Construction method of ultra-deep shield vertical shaft for water-rich weak stratum
CN102966122B (en) The method of bridge deformation is controlled when building tunnel near the basis of bridge
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN100439634C (en) Horizontal force transfer method for underground building modification
CN107524152A (en) A kind of foundation pit enclosure structure stress bringing device and its construction method
CN206635599U (en) A kind of road surface for caving in road, which is speedily carried out rescue work, fixes device
CN106948347B (en) Pile pulling method and pile pulling system
CN101177933B (en) Bridge rib hoisting and supporting rack integral construction method and device
CN106988333A (en) The prefabricated cushion cap and its construction technology of core are filled with joint bar
CN104032767A (en) Tower crane foundation in deep foundation pit and construction method of tower crane foundation
CN101929159B (en) Protective method of pipelines in natural gas pipeline full-section excavation construction
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN103572770A (en) Pile box hydraulic structure object and building method thereof
CN106480826B (en) The cast-in-place traversing construction engineering method of single line box beam pier top
CN101230753A (en) Method for reinforcing top cover frame buildings work in non-batholith shield excavation process
CN106592599B (en) Device for rapidly controlling foundation pit displacement and construction method
CN104929159B (en) A kind of pattern foundation pit supporting structure pressure-detecting device
CN203821399U (en) Deep foundation pit supporting structure
CN104846856B (en) Horizontal inclined independent bent frame column pushing correction method
CN206753488U (en) A kind of artificial digging pile reaming auxiliary equipment
CN109555129A (en) One kind is quickly met an urgent need diagonal brace and construction method for salvage of foundation pits
CN201972711U (en) Device for controlling deformation of near metro tunnel caused by super-deep foundation pit evacuation in soft soil areas
CN204590105U (en) A kind of pattern foundation pit supporting structure pressure-detecting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20080730