CN101214848A - Method for mounting air guide sleeve - Google Patents

Method for mounting air guide sleeve Download PDF

Info

Publication number
CN101214848A
CN101214848A CNA2007100329428A CN200710032942A CN101214848A CN 101214848 A CN101214848 A CN 101214848A CN A2007100329428 A CNA2007100329428 A CN A2007100329428A CN 200710032942 A CN200710032942 A CN 200710032942A CN 101214848 A CN101214848 A CN 101214848A
Authority
CN
China
Prior art keywords
streamlined reefer
reefer housing
moulding bed
segmentation
air guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007100329428A
Other languages
Chinese (zh)
Inventor
陈楚明
张晓勇
李善波
李玉亭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Wenchong Shipyard Co Ltd
Original Assignee
Guangzhou Wenchong Shipyard Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Wenchong Shipyard Co Ltd filed Critical Guangzhou Wenchong Shipyard Co Ltd
Priority to CNA2007100329428A priority Critical patent/CN101214848A/en
Publication of CN101214848A publication Critical patent/CN101214848A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Artificial Fish Reefs (AREA)

Abstract

The present invention discloses an installing method of an air guide sleeve. The air guide sleeve is hung and welded directly at a branch segment but not inside a boatyard after a ship body is welded and shaped, which shortens the dock-using period occupied by installing the air guide sleeve inside the boatyard, effectively shortens the dock-using period for manufacturing the whole ship, improves the efficiency of shipbuilding and accordingly improves the shipbuilding capability of the dockyard.

Description

A kind of installation method of streamlined reefer housing
Technical field:
The present invention relates to the installation method of the streamlined reefer housing of the installation method of streamlined reefer housing, particularly a kind of dredger.
Background technology:
Dock quantity and single the depressed place phase that ship building is shared, directly reflect the shipbuilding capacity of shipyard.It is long more that single ship building takies the depressed place phase, and the shipbuilding capacity of shipyard is just restricted more.The stern screw propeller external demand of dredger is installed streamlined reefer housing, be subjected to the restriction of screw propeller position and serviceability, the streamlined reefer housing periphery arrives the position of screw propeller outer rim because of basic identical, this requires the setting accuracy of streamlined reefer housing higher, in a single day deviation appears in the streamlined reefer housing installation site, the running of screw propeller will directly be influenced, even may be because of the position deviation of streamlined reefer housing but screw propeller can't turn round, in order to guarantee the setting accuracy of streamlined reefer housing, the installation phase of streamlined reefer housing is often very long, and the streamlined reefer housing of dredger is all installed in dock at present, because the time that streamlined reefer housing is installed is long, make the whole manufacture process of dredger, the time of shared dock is also long especially, has had a strong impact on the shipbuilding capacity of shipyard.
Summary of the invention:
The object of the present invention is to provide a kind of installation method of new streamlined reefer housing, install in the segmentation of its streamlined reefer housing before hull enters dock, and in dock, do not carry out, shortened dredger effectively to build the shared depressed place phase, improved the shipbuilding capacity of shipyard.
The installation method of streamlined reefer housing of the present invention comprises the step of following order:
A, set up the plane moulding bed;
B, lay the moulding bed plate, and mark level reference at the moulding bed skirt piles;
C, segmentation is inverted on the moulding bed, makes the platform of segmentation concordant with level reference or parallel;
D, auxiliary mould is set in that segmentation is other, draws the installation site boost line of establishing the streamlined reefer housing line of centers by auxiliary mould;
E, lifting streamlined reefer housing are adjusted the streamlined reefer housing position, make the streamlined reefer housing central axis consistent with the installation site boost line;
F, welding streamlined reefer housing.
The installation method of streamlined reefer housing of the present invention, its streamlined reefer housing directly do not carry out in dock installing in the segmentation, have shortened the depressed place phase that dredger is built, thereby have improved the shipbuilding capacity of shipyard.
Description of drawings:
Fig. 1 is a kind of scheme of installation of streamlined reefer housing.
The specific embodiment:
A kind of installation method of streamlined reefer housing is at first set up plane moulding bed 1; On moulding bed 1, lay the moulding bed plate, and mark level reference 2 at the skirt piles of moulding bed 1; Segmentation 3 is inverted on the moulding bed 1, adjusts the position, make the platform 4 of segmentation 2 parallel with level reference 2; A side or both sides at plane moulding bed 1 are provided with auxiliary mould 5, draw by auxiliary mould 5 and establish the installation boost line, the central lines of the position that the position of boost line and streamlined reefer housing need be installed; Lifting streamlined reefer housing 6, the position of adjustment streamlined reefer housing 6 makes its line of centers overlap with drawing the boost line of establishing; Weld streamlined reefer housing 6, thereby finish the installation of streamlined reefer housing 6.By adopting said method that streamlined reefer housing is installed, streamlined reefer housing can directly not need to carry out in dock installing in the segmentation, and it has shortened the depressed place phase that streamlined reefer housing is built, and has improved the shipbuilding capacity of shipyard.

Claims (1)

1. the installation method of a streamlined reefer housing comprises the step of following order:
A, set up plane moulding bed (1);
B, lay the moulding bed plate, and mark level reference (2) at moulding bed (1) skirt piles;
C, segmentation (3) is inverted on the moulding bed (1), makes the platform (4) of segmentation (3) concordant or parallel with level reference (2);
D, auxiliary mould (5) is set in that segmentation (3) is other, draws the installation site boost line of establishing the streamlined reefer housing line of centers by auxiliary mould (5);
E, lifting streamlined reefer housing (6), the position of adjustment streamlined reefer housing (6) makes the streamlined reefer housing central axis consistent with the installation site boost line;
F, welding streamlined reefer housing (6).
CNA2007100329428A 2007-12-27 2007-12-27 Method for mounting air guide sleeve Pending CN101214848A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007100329428A CN101214848A (en) 2007-12-27 2007-12-27 Method for mounting air guide sleeve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007100329428A CN101214848A (en) 2007-12-27 2007-12-27 Method for mounting air guide sleeve

Publications (1)

Publication Number Publication Date
CN101214848A true CN101214848A (en) 2008-07-09

Family

ID=39621376

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007100329428A Pending CN101214848A (en) 2007-12-27 2007-12-27 Method for mounting air guide sleeve

Country Status (1)

Country Link
CN (1) CN101214848A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101962065A (en) * 2010-10-20 2011-02-02 武昌船舶重工有限责任公司 Installation process and tooling of impeller casing of marine water jet propulsion device
CN103129701A (en) * 2011-11-22 2013-06-05 上海船厂船舶有限公司 Positioning method of stream guidance cover on segmentation
CN103661807A (en) * 2013-11-29 2014-03-26 大连船舶重工集团有限公司 Positioning method for broadside block assembling of pre-mounting pressure guide rail bracket
CN104590521A (en) * 2015-01-06 2015-05-06 舟山欣臻船舶设计有限公司 Installation process for fairing of bulk cargo ship
CN104625447A (en) * 2014-12-19 2015-05-20 华泰重工(南通)有限公司 Technology for mounting fan-shaped guide tube
CN110466494A (en) * 2019-08-22 2019-11-19 中船黄埔文冲船舶有限公司 A kind of aircushion vehicle pod and its processing method
CN111703555A (en) * 2020-06-05 2020-09-25 友联船厂(蛇口)有限公司 Method for building ship tail guide pipe and installing ship tail guide pipe in dock

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101962065A (en) * 2010-10-20 2011-02-02 武昌船舶重工有限责任公司 Installation process and tooling of impeller casing of marine water jet propulsion device
CN101962065B (en) * 2010-10-20 2012-10-31 武昌船舶重工有限责任公司 Installation process and tooling of impeller casing of marine water jet propulsion device
CN103129701A (en) * 2011-11-22 2013-06-05 上海船厂船舶有限公司 Positioning method of stream guidance cover on segmentation
CN103661807A (en) * 2013-11-29 2014-03-26 大连船舶重工集团有限公司 Positioning method for broadside block assembling of pre-mounting pressure guide rail bracket
CN103661807B (en) * 2013-11-29 2016-06-08 大连船舶重工集团有限公司 The localization method of the side sectional folding of pressure guide rail bracket is installed in advance
CN104625447A (en) * 2014-12-19 2015-05-20 华泰重工(南通)有限公司 Technology for mounting fan-shaped guide tube
CN104625447B (en) * 2014-12-19 2016-08-24 华泰重工(南通)有限公司 A kind of fan-shaped conduit mounting process
CN104590521A (en) * 2015-01-06 2015-05-06 舟山欣臻船舶设计有限公司 Installation process for fairing of bulk cargo ship
CN110466494A (en) * 2019-08-22 2019-11-19 中船黄埔文冲船舶有限公司 A kind of aircushion vehicle pod and its processing method
CN111703555A (en) * 2020-06-05 2020-09-25 友联船厂(蛇口)有限公司 Method for building ship tail guide pipe and installing ship tail guide pipe in dock

Similar Documents

Publication Publication Date Title
CN101214848A (en) Method for mounting air guide sleeve
CN102336250B (en) Method for installing rudder horn
CN101367426A (en) Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN101817392A (en) Thwartship bulkhead subsection guide rail frame preassembling process
CN103661807A (en) Positioning method for broadside block assembling of pre-mounting pressure guide rail bracket
CN101264790A (en) Method for mounting stern herringbone bracket
CN104960625A (en) Mounting method of single-bearing shaft system of large-scale ship
CN101962065B (en) Installation process and tooling of impeller casing of marine water jet propulsion device
CN202226032U (en) Anchor platform with knee plate
CN103693170A (en) Floating type offshore wind power assembly platform and method using floating type offshore wind power assembly platform for assembly offshore wind turbine
CN109292040B (en) Multidirectional full-rotation rudder propeller main section installation method
CN201538420U (en) Integrated pouring stern tube system
CN113978649A (en) Openable side push cover mounting method on ship
CN102632965A (en) Combined type module ship and module connecting way thereof
CN101481000B (en) Fiberglass boat neck bearing and shafting mounting technique
CN101817393A (en) Shipbuilding method by utilizing floating dock
CN100415596C (en) Tech. for carrying super building on oil ship
CN209905028U (en) Deep water installation nacelle type electric propeller
CN202225997U (en) Rudder horn
CN104787246A (en) Anchor mouth
CN104443334A (en) High-precision mounting method for auxiliary component of full-rotating device
CN102975834A (en) Method for changing depth finder under water
CN111806653B (en) Pre-assembling method for side block of cruise ship
CN202642031U (en) Ship body section middle closure structure
CN107757820A (en) A kind of unmanned boat dynamical system positioning tool

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080709