CN101209805A - Method and equipment for hanging iron tower - Google Patents
Method and equipment for hanging iron tower Download PDFInfo
- Publication number
- CN101209805A CN101209805A CNA2007103003054A CN200710300305A CN101209805A CN 101209805 A CN101209805 A CN 101209805A CN A2007103003054 A CNA2007103003054 A CN A2007103003054A CN 200710300305 A CN200710300305 A CN 200710300305A CN 101209805 A CN101209805 A CN 101209805A
- Authority
- CN
- China
- Prior art keywords
- lifting
- hoisting
- turricula
- rope
- lazy arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The invention provides a hoisting method for a turricula and the device thereof. A lifting pedestal and a lazy arm pedestal are arranged on a lifting working platform. A rotary lazy arm is hinged with the lazy arm pedestal. A lifting rope and a lifting winch form a lifting mechanism through a crown block and the rotary lazy arm of the lazy arm pedestal. A pulling rope and a pulling winch form a pulling mechanism through the crown block of the rotary lazy arm. A hoisting rope and a hoisting winch form a hoisting mechanism through a hoisting block of the rotary lazy arm and a block on the lazy arm pedestal. The other end of the hoisting rope is provided with a lifting hook. The invention uses the lifting winch to lift the lazy arm in the hoisting mechanism and simultaneously lift the turricula and prick as well as release the hoisting winch and the pulling winch to arrange the turricula on a preassemble tower seat, mount and construct thereof to finish the hoisting of the turricula. The invention solves the problems that the upright stanchion tower of a crane group in existing hoisting construction method and device for turricula is restricted by conditions and has the disadvantages of higher tower composing cost, needing men for measuring instruments, a plurality of anchor block pits and operating personnel as well as low efficiency, etc.
Description
Technical field:
The present invention relates to a kind of hanging method of iron tower, corresponding hanging device also is provided simultaneously, belong to the lifting equipment technical field.
Background technology
At present, electric power circuit group vertical rod tower has crane and two kinds of methods of pole.Adopt the crane integral basis to hang the vertical rod tower, need be in the place that transportation condition allows, specification according to shaft tower, 25~150 tons of cranes of general use, line construction is often remote, and large-scale crane generally is difficult in the locality rent, and crane group vertical rod tower is had relatively high expectations to road conditions, only be adapted at the higher place construction of region of no relief ground intensity, group vertical rod tower expense is higher; Adopt existing pole group vertical rod tower not limited by road and landform, but need Work tools such as a large amount of steel cable, the rope made of hemp, coaster, cucurbit and earth anchor, pole, the every at least base of split tower erection will dig 4 shakedown holes, with the upright iron tower of integral body group is example, with upright general 20~22 people that need of pole group, needs production time 16 hours, also not including ground prepares and the ground group tower time, the group vertical rod tower time is longer, needs more operating personnel, and the construction safety dangerous point is many.
Summary of the invention
The invention provides a kind of hanging method of iron tower, its objective is that will solve existing iron tower construction method for hanging crane group vertical rod tower is subjected to condition restriction, the higher and existing pole group of group tower expense vertical rod tower needs the people to measure problems such as Work tool, ground anchor pit and operating personnel are many, efficient is low.
Technical solution of the present invention is as follows:
On the lifting work platform, be respectively equipped with derricking gear, hoisting mechanism and trailer coupling, iron tower is fixed on arm two ends in the hoisting mechanism, by derricking gear with the arm pull-up, iron tower is promoted vertically, the twisted rope that discharges derricking gear and trailer coupling is placed on iron tower on the prepackage tower seat, the lifting of iron tower is finished in installation.
Concrete hoisting equipment structure is as follows:
Lifting pedestal and boom base are set on the lifting work platform, each pedestal be provided with fixed pulley, one end of rotary suspension arm and boom base hinge-coupled, lifting rope is fixed on the front end of rotary suspension arm, and constitutes derricking gear by the fixed pulley of boom base with the lifting capstan winch; One end of hauling rope constitutes trailer coupling through the fixed pulley and the towing capstan on the lifting platform at rotary suspension arm middle part, and the other end is provided with suspension hook and the bottom of iron tower can be fixed; The lifting rope constitutes hoisting mechanism through the fixed pulley and the lifting capstan winch on fixed pulley on the boom base and the lifting work platform on rotary suspension arm top, and the other end is provided with fishhook.
Described lifting work platform bottom is provided with the rotation of rotating mechanism may command platform.
When hanging device of the present invention uses,, select lifting work platform permanent seat to be connected the jig size, prepare basic discrepancy in elevation chock with the basis according to the key dimension and the site contour of prepackage column foot; Open and height according to the iron tower root, select arm and rise and fall pole joint number and size; According to iron tower weight, size and complete equipment parameter, check the lifting condition.
The on-the-spot layout: the basis and the lifting work platform permanent seat that connect prepackage iron tower base; The lifting work platform is installed on lifting work platform permanent seat; Weight-lifting equipments such as lifting pedestal, boom base, lifting capstan winch, lifting capstan winch, towing capstan are installed on the lifting work platform; Connect arm along the iron tower bottom to the tower head direction, state is lifted by crane on the ground of seeing Fig. 1 of putting of iron tower and rotary suspension arm; Hauling rope, lifting rope, rotary suspension arm are connected with iron tower; Tighten hauling rope and lifting rope, the lifting rope fixation side is trivial dead; Start the lifting capstan winch, the pull-up rotary suspension arm is checked the stressed and device situation of each by the lifting regulation; By the weight line, iron tower is winched to basic on a line of centers; Open the fixed pulley of iron tower bottom and rotary suspension arm, iron tower is vertically dropped down onto iron tower foundation, aim at holding-down bolt, iron tower lower margin side is gone in the holding-down bolt last anchor bolt; Unclamp lifting rope, put down the weight line, rotation lifting work platform is to the iron tower side; Start winch, put down the installation that rotary suspension arm is finished iron tower.
Advantage and progressive being that the present invention has with respect to prior art: be respectively equipped with derricking gear, hoisting mechanism and trailer coupling on the lifting work platform, by lifting by crane capstan winch with the arm pull-up in the hoisting mechanism, iron tower and the lifting of arm one, the iron tower lifting is holded up, discharging lifting capstan winch and towing capstan is placed on iron tower on the prepackage tower seat, the lifting of iron tower is finished in installation.The invention solves existing iron tower construction method for hanging, crane group vertical rod tower is subjected to condition restriction, the higher and existing pole group of group tower expense vertical rod tower needs the people to measure problems such as Work tool, ground anchor pit and operating personnel are many, efficient is low.Overcome in the crane lifting iron tower leg scrape and the wayward problem of swinging, must professional driver not cooperate in the lifting.Improve work efficiency, reduced power off time.Not limited by the road landform, need not excavate cat hole, ground, scope of work is little, reduces labour intensity, reduces construction costs, and the group column efficiency can improve more than 75%.
Description of drawings
Fig. 1 is an invention hoisting equipment structure schematic diagram.
Fig. 2 is a mode of operation schematic diagram of the present invention.
1, lifting capstan winch; 2, lifting work platform; 3, lifting pedestal; 4, lifting fixed pulley; 5, towing capstan; 6, boom base; 7, rotary suspension arm; 8, lifting pulley; 9, iron tower; 10, hauling block; 11, lifting fixed pulley; 12, lifting capstan winch; 13, hauling rope; 14, lifting rope; 15, lifting rope.
The specific embodiment
According to key dimension and site contour, select lifting work platform permanent seat to be connected the jig size with the basis, prepare basic discrepancy in elevation chock; Open and height according to the iron tower root, select arm and rise and fall pole joint number and size; According to iron tower weight, size and complete equipment parameter, check the lifting condition.
As shown in Figure 1, lifting pedestal 3, boom base 6, lifting capstan winch 1, towing capstan 5, lifting capstan winch 12 are installed on lifting work platform 2, arm 7 is hinged on the boom base 6, and lifting rope 14 is captiveed joint with arm 7 through lifting capstan winch 1, lifting fixed pulley 4; State is lifted by crane on the ground of seeing Fig. 2 of putting of iron tower 9 and arm 7; Towing capstan 5, hauling rope 13 are captiveed joint with the bottom of iron tower 9 by traction wheel 10; Lifting rope 15 is through lifting capstan winch 12, lifting fixed pulley 11, lifting the top captive joint of pulley 8 with iron tower 9.
Utilize hanging method of the present invention and the device just will commander responsible official 1 people, ground and operation electrician 2 people, power worker 2~4 people can finish the lifting work of iron tower.
Claims (2)
1. the hanging method of a turricula, it is characterized in that: on the lifting work platform, be respectively equipped with derricking gear, hoisting mechanism and trailer coupling, turricula is fixed on arm two ends in the hoisting mechanism, by derricking gear with the arm pull-up, the turricula lifting is holded up, the twisted rope that discharges derricking gear and trailer coupling is placed on turricula on the prepackage tower seat, and the lifting of turricula is finished in installation.
2. turricula hanging device, it is characterized in that: lifting pedestal and boom base are set on the lifting work platform, each pedestal be provided with fixed pulley, one end of rotary suspension arm and boom base hinge-coupled, lifting rope is fixed on the front end of rotary suspension arm, and constitutes derricking gear by the fixed pulley of boom base with the lifting capstan winch; One end of hauling rope constitutes trailer coupling through the fixed pulley and the towing capstan on the lifting platform at rotary suspension arm middle part, and the other end is provided with suspension hook and the bottom of turricula can be fixed; The lifting rope constitutes hoisting mechanism through the fixed pulley and the lifting capstan winch on fixed pulley on the boom base and the lifting work platform on rotary suspension arm top, and the other end is provided with fishhook.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007103003054A CN101209805A (en) | 2007-12-21 | 2007-12-21 | Method and equipment for hanging iron tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007103003054A CN101209805A (en) | 2007-12-21 | 2007-12-21 | Method and equipment for hanging iron tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101209805A true CN101209805A (en) | 2008-07-02 |
Family
ID=39610088
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2007103003054A Pending CN101209805A (en) | 2007-12-21 | 2007-12-21 | Method and equipment for hanging iron tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101209805A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103510742A (en) * | 2013-10-15 | 2014-01-15 | 国家电网公司 | Multifunctional rotary derrick |
CN104132037A (en) * | 2014-07-18 | 2014-11-05 | 国家电网公司 | Hoisting point fixing device for emergency repair tower |
CN106044582A (en) * | 2016-07-01 | 2016-10-26 | 国网冀北电力有限公司迁西县供电分公司 | Integral hoisting method for super-long tower |
CN109610922A (en) * | 2018-12-17 | 2019-04-12 | 国网西藏电力有限公司 | A kind of typical case's landform tower erection construction equipment |
CN109607406A (en) * | 2019-01-09 | 2019-04-12 | 中国人民解放军海军航空大学 | One kind point hangs Superimposed hoisting apparatus and hoisting method |
CN115324416A (en) * | 2022-03-14 | 2022-11-11 | 中铁一局集团电务工程有限公司 | Integral hoisting construction process for iron tower |
CN116835455A (en) * | 2023-09-04 | 2023-10-03 | 河南省中原矿山设备有限公司 | Barrier-free hoisting device for farmland erection electric power iron tower |
-
2007
- 2007-12-21 CN CNA2007103003054A patent/CN101209805A/en active Pending
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103510742A (en) * | 2013-10-15 | 2014-01-15 | 国家电网公司 | Multifunctional rotary derrick |
CN103510742B (en) * | 2013-10-15 | 2016-04-27 | 国家电网公司 | Multifunctional rotary derrick |
CN104132037A (en) * | 2014-07-18 | 2014-11-05 | 国家电网公司 | Hoisting point fixing device for emergency repair tower |
CN104132037B (en) * | 2014-07-18 | 2016-02-03 | 国家电网公司 | Be used in the suspension centre fixing device on emergency first-aid repair tower |
CN106044582A (en) * | 2016-07-01 | 2016-10-26 | 国网冀北电力有限公司迁西县供电分公司 | Integral hoisting method for super-long tower |
CN109610922A (en) * | 2018-12-17 | 2019-04-12 | 国网西藏电力有限公司 | A kind of typical case's landform tower erection construction equipment |
CN109607406A (en) * | 2019-01-09 | 2019-04-12 | 中国人民解放军海军航空大学 | One kind point hangs Superimposed hoisting apparatus and hoisting method |
CN109607406B (en) * | 2019-01-09 | 2024-03-29 | 中国人民解放军海军航空大学 | Separate-hanging stacked lifting device and lifting method |
CN115324416A (en) * | 2022-03-14 | 2022-11-11 | 中铁一局集团电务工程有限公司 | Integral hoisting construction process for iron tower |
CN116835455A (en) * | 2023-09-04 | 2023-10-03 | 河南省中原矿山设备有限公司 | Barrier-free hoisting device for farmland erection electric power iron tower |
CN116835455B (en) * | 2023-09-04 | 2024-01-19 | 河南省中原矿山设备有限公司 | Barrier-free hoisting device for farmland erection electric power iron tower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201176373Y (en) | Hoisting device for pylon | |
CN101209805A (en) | Method and equipment for hanging iron tower | |
CN201901539U (en) | Internal climbing type and external climbing type tower crane with luffing jib | |
CN105692470B (en) | Inner climbing crane tower and its operating method | |
CN201924360U (en) | Multifunctional hydraulic static pile press | |
CN201495048U (en) | Double movable-arm crane used for iron tower installation | |
CN201971572U (en) | Movable arm type tower crane with suspension arm possible of being folded for dismounting | |
CN101077763B (en) | Manned lift truck | |
CN103630416B (en) | Test platform of hoisting mechanism | |
CN101214908A (en) | Gin pole integrated dismounting method for tower crane | |
CN108910730B (en) | Installation and construction method of large horizontal tower crane | |
CN110130346A (en) | Hammer the prefabricated pile pile-sinking device and construction method in conjunction with static pressure | |
CN201757714U (en) | Ground anchor type static load testing device | |
CN109441361A (en) | A kind of pile frame and its vertical mast method | |
CN106245984B (en) | Jack up Multifunctional creeping gin pole | |
CN201280718Y (en) | Complete-hydraulic anchor rod grouting trolley | |
CN104942564B (en) | A kind of offshore vessel carries the installation method of the large-tonnage bearing pin on jib-type crane arm support | |
CN101016827A (en) | 18 m hydraulic pressure rise and fall retractable drill tower | |
CN202499663U (en) | Wellhead vertical lifting machine | |
CN209163736U (en) | A kind of pile frame | |
CN108545629B (en) | Utilize the construction method of tower crane lifting girder truss | |
CN101074087A (en) | Self-raising tower crane | |
CN202785385U (en) | Simple and easy hoisting combination body hanger rod used for replacing inoperative parts of tower crane | |
CN206769526U (en) | Jack up Multifunctional creeping gin pole | |
CN208361796U (en) | For cooperating the device of tower crane lifting girder truss |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |