CN101135154A - Blasting pile forming method for two-stage bottom expanding prefabricated pile body - Google Patents

Blasting pile forming method for two-stage bottom expanding prefabricated pile body Download PDF

Info

Publication number
CN101135154A
CN101135154A CNA2007101572991A CN200710157299A CN101135154A CN 101135154 A CN101135154 A CN 101135154A CN A2007101572991 A CNA2007101572991 A CN A2007101572991A CN 200710157299 A CN200710157299 A CN 200710157299A CN 101135154 A CN101135154 A CN 101135154A
Authority
CN
China
Prior art keywords
pile
immersed tube
pile body
blasting
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007101572991A
Other languages
Chinese (zh)
Inventor
周亚萍
吴伟林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA2007101572991A priority Critical patent/CN101135154A/en
Publication of CN101135154A publication Critical patent/CN101135154A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to construction of building pile foundation engineering, and is especially blasting piling process of two-stage under-reamed prefabricated pile stem. The piling process includes the following steps: 1. immersing immersed tube with metal pile head into hardpan to design elevation; 2. taking out the metal pile head; 3. forming the lower base space through blasting and pouring the lower base with concrete; 4. setting the prefabricated solid lower pile stem with steel dowels into the immersed tube; 5. drawing upwards the immersed tube to designed distance, forming the upper base space, penetrating the steel dowels through the upper base space and connecting to the lower prefabricated pile stem, setting the prefabricated hollow upper pile stem into the immersed tube, and pouring the upper base; and 6. withdrawing the immersed tube and injecting cement mortar to the gap. The present invention has the advantages of high material strength utilizing rate, etc.

Description

The blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage
Technical field
The present invention relates to a kind of construction of building pile foundation engineering, the piling method of the bottom-enlarging prefabricated pile body of particularly a kind of two-stage.
Background technology
According to the national regulation whole body be cast-in-place (be the pile body Cast-in-place concrete, base also is a Cast-in-place concrete) its base diameter ratio maximum value of expanded bore pile is limited in 3-3.5, and pipe sinking prefabricated steel concrete club-footed pile, this stake is the prefabricated concrete of pile body, the base Cast-in-place concrete, obviously this ratio 3-3.5 is broken, generally 3.5-5 can be reached,, requirement of engineering can't be satisfied although bearing capacity is bigger, particularly, the opposite end bearing capacity to give a discount 0.9 when bellout diameter during greater than 1.5 meters.For this reason, immersed tube prefabricated multistage under-reamed pile has appearred again.Existing multiple bearing capacity dish stake technology has two common ground, and first all is to expand the end with positive crossover-circulating type method pore-forming; Second all carries out pile without immersed tube expands the end.This two point-to-points load dish (at the bottom of the multistage expansion) stake is quite unfavorable, in other words, bring two problems, 1), national building code requirement, expand the base end load at the end with positive crossover-circulating type method pile and will take advantage of 0.45 coefficient, because have mud existence and pile bottom sediment to clean out, (Zhejiang Province's standard is 0.24 discount) gives a discount too big, though a plurality of bases are arranged, loss end load is very big; 2); without immersed tube; condition of construction can not get protection; positive in addition crossover-circulating type method is operation under water; expand bottom application worker situation and cannot see, the difficult measurement noted down, when also usually taking place to expand the end under water; top soil body a slice situation that falls down also happens occasionally; also have because the multistage stake of prior art all is the whole body Cast-in-place concrete, and that the intensity of Cast-in-place concrete is done is not high, and difficult quality guarantee; and in water, water concrete; the difficult control of quality adds that the pile capacity of a plurality of bases is all bigger, and its pile body diameter of above factor must be done greatlyyer; and this a plurality of base is afraid of that pile body diameter is big most; development test shows that pile body diameter increases, and its bearing capacity decay is very serious.
Summary of the invention
The problem that the present invention is directed to the prior art existence provides the blasting pile-forming method of the bottom-enlarging prefabricated pile body of a kind of two-stage, purpose is to improve the utilization rate and the reduction coefficient of the strength of materials, pile body and base good concentricity, obviously improve single pile bearing capacity, the reliable degree height, and can reduce the pile foundation engineering cost.
The blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage of the present invention comprises following processing step: a, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, put into oil emulsion or tnt explosive from the immersed tube mouth, every 0.5m 3Consumption is the 1-5 kilogram, seals the immersed tube mouth behind the ignition charge, treat that explosive charge is finished after, open the article of sealing the immersed tube mouth and form lower base space, with inhaling indigenous equipment exhaustion hack, perfusion concrete cast lower bottom base; D, the lower end is had the following prefabricated solid pile body of joint bar, put into immersed tube until putting in place; E, on pull out immersed tube to setpoint distance H, expand end processing upper base space with extrusion equipment, joint bar is passed upper base space links to each other with following precast pile, last precast hollow pile body is put into the mesopore injection concrete of immersed tube from last precast pile, pour into a mould upper bed-plate; F, extract immersed tube, between the slit, inject cement paste.
Extrusion equipment among the described operation e is that hydraulic pressure props up disc shaping machine.
Setpoint distance H among the described operation e is 2-10 a times of base diameter.
The present invention is compared with prior art owing to do protection and rely on immersed tube, prefabricated in addition pile body up and down, and a series of technical measures such as upper bed-plate under the cast-in-place notes steel concrete, and have following advantage and good effect through evidence:
1, the ratio of base diameter and pile body diameter can reach 3.5-5, surpasses state-set standard;
2, the obvious raising of reduction coefficient can reach 0.9-1.0, improves strength of materials utilization rate;
3, do protection and rely on accurate positioning with immersed tube, make the Up/down base and the good concentricity of pile body up and down;
4, improve single pile bearing capacity, reliable degree height;
5, reduce the construction cost of building pile foundation engineering;
6, overcome the existing in prior technology defective.
Description of drawings
Fig. 1 a-Fig. 1 c is each operation status of processes schematic diagram of the present invention.
Among the figure 1, lower base space; 2, immersed tube; 3, following prefabricated solid pile body; 4, upper base space; 5, joint bar; 6, go up the precast hollow pile body.
The specific embodiment
Embodiments of the invention 1a-1c in conjunction with the accompanying drawings are described in detail.
The blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage of the present invention comprises following processing step:
A, the immersed tube 2 that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, put into oil emulsion or tnt explosive from the immersed tube mouth, every 0.5m 3Consumption is the 1-5 kilogram, seals the immersed tube mouth behind the ignition charge, treat that explosive charge is finished after, open the article of sealing the immersed tube mouth and form lower base space 1, with inhaling indigenous equipment exhaustion hack, perfusion concrete cast lower bottom base; D, the lower end is had the following prefabricated solid pile body 3 of joint bar, put into immersed tube until putting in place; E, on pull out immersed tube 2 to setpoint distance H, setpoint distance H is 2-10 a times of base diameter, propping up disc shaping machine with extrusion equipment hydraulic pressure expands the end and processes upper base space 4, joint bar 5 is passed upper base space 4 to link to each other with following prefabricated solid pile body 3 epimeres, then will go up precast hollow pile body 6 and put into the mesopore injection concrete cast upper bed-plate of immersed tube 2, as shown in Figure 1a from last precast pile; F, extract immersed tube, between the slit, inject cement paste.
The concrete steps of exhaustion hack are as follows among the above-mentioned operation c: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.

Claims (4)

1. the blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage is characterized in that it comprises following processing step: a, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, put into oil emulsion or tnt explosive from the immersed tube mouth, every 0.5m 3Consumption is the 1-5 kilogram, seals the immersed tube mouth behind the ignition charge, treat that explosive charge is finished after, open the article of sealing the immersed tube mouth and form lower base space, with inhaling indigenous equipment exhaustion hack, perfusion concrete cast lower bottom base; D, the lower end is had the following prefabricated solid pile body of joint bar, put into immersed tube until putting in place; E, on pull out immersed tube to setpoint distance H, expand end processing upper base space with extrusion equipment, joint bar is passed upper base space links to each other with following precast pile, last precast hollow pile body is put into the mesopore injection concrete of immersed tube from last precast pile, pour into a mould upper bed-plate; F, extract immersed tube, between the slit, inject cement paste.
2. the blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage according to claim 1 is characterized in that the extrusion equipment among the described operation e is that hydraulic pressure props up disc shaping machine.
3. the blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage according to claim 1, it is characterized in that setpoint distance H among the described operation e be base diameter 2-10 doubly.
4. the blasting pile-forming method of the bottom-enlarging prefabricated pile body of two-stage according to claim 1, the concrete steps that it is characterized in that exhaustion hack among the described operation c are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
CNA2007101572991A 2007-09-29 2007-09-29 Blasting pile forming method for two-stage bottom expanding prefabricated pile body Pending CN101135154A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007101572991A CN101135154A (en) 2007-09-29 2007-09-29 Blasting pile forming method for two-stage bottom expanding prefabricated pile body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007101572991A CN101135154A (en) 2007-09-29 2007-09-29 Blasting pile forming method for two-stage bottom expanding prefabricated pile body

Publications (1)

Publication Number Publication Date
CN101135154A true CN101135154A (en) 2008-03-05

Family

ID=39159462

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007101572991A Pending CN101135154A (en) 2007-09-29 2007-09-29 Blasting pile forming method for two-stage bottom expanding prefabricated pile body

Country Status (1)

Country Link
CN (1) CN101135154A (en)

Similar Documents

Publication Publication Date Title
CN101126237A (en) Blasting pile-forming method for three-stage bottom-enlarging prefabricated and cast-in-situ steel concrete combination pile body
CN101135154A (en) Blasting pile forming method for two-stage bottom expanding prefabricated pile body
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135153A (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101135147A (en) Blasting pile forming method for three-stage bottom expanding composite pile body
CN101135167A (en) Mechanical pile forming method for two-stage bottom expanding prefabricated pile body
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135160A (en) Mixed pile forming method for high-bearing one-stage club-footed pile
CN101130971A (en) Extruding mixing method for secondary expanding bottom prefabricated pile body with high bearing capacity
CN101135165A (en) Extrusion pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101130972A (en) Blasting pile-forming method for two-stage expanding bottom prefabricated pile body with high bearing capacity
CN101130970A (en) Blasting pile-forming method for secondary expanding bottom prefabricated pile body with high bearing capacity
CN101135150A (en) Mixed pile forming method for high-bearing prefabricated and cast-in-situs steel concrete composite pile body
CN101126236A (en) Blasting pile-forming method for multi-stage club-footed pile
CN101130958A (en) Blasting pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101135166A (en) Blasting pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101135151A (en) Blasting pile forming method for high-bearing prefabricated and cast-in-situs steel concrete composite pile body
CN101130962A (en) Blasting pile-forming method for primary expanding bottom pile with high bearing capacity
CN101135162A (en) Mixed pile forming method for multi-stage club-footed pile
CN101397781A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101130966A (en) Pile-forming method for two-level expanding bottom prefabricated pile body
CN101397791A (en) Pile-forming method of belled pile
CN101135152A (en) Mixed pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101135158A (en) Mechanical pile forming method for high-bearing multi-stage club-footed pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080305