CN101131007A CNA2006100154293A CN200610015429A CN101131007A CN 101131007 A CN101131007 A CN 101131007A CN A2006100154293 A CNA2006100154293 A CN A2006100154293A CN 200610015429 A CN200610015429 A CN 200610015429A CN 101131007 A CN101131007 A CN 101131007A
Authority
CN
China
Prior art keywords
mortar
wall
brick
water
face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2006100154293A
Other languages
Chinese (zh)
Inventor
张新旺
王桂云
王文华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd
Original Assignee
TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd filed Critical TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd
Priority to CNA2006100154293A priority Critical patent/CN101131007A/en
Publication of CN101131007A publication Critical patent/CN101131007A/en
Pending legal-status Critical Current

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The method of preventing leakage in outer wall with facing tile includes reasonable design before construction, sorting qualified materials and the following construction steps: 1. controlling the density and saturation degree of mortar and the size of mortar joint; 2. increasing one outer wall port and one inner wall port in the joint between the top of masonry and the ring beam; 3. plastering the wall surface to raise the adhesion between the bottom mortar and the base; 4. preparing door and window openings; 5. constructing flashing in parapet and bearing wall; 6. cleaning and soaking the facing tile; and 7. pointing the exposed joints. The method of preventing leakage in outer wall with facing tile is feasible and convenient in construction.

Description

A kind of method of preventing and treating of exterior wall leakage of face tile
(1) technical field:
The present invention relates to the method for preventing and treating of a kind of construction techniques, particularly a kind of exterior wall leakage of face tile.
(2) background technology:
In recent years, along with the raising of architectural decoration standard, outer eaves furring brick is decorated general day by day, and still, some buildings come into operation soon, and metope begins to occur seepage.The reason that causes has following several respects situation:
1. design aspect
Some engineering construction figure designs are relatively simplified, the detail structure that has is lacked detailed explanation and drawing, architectural image is novel day by day at present in addition, wall structure changes complicated, but there is not corresponding antiseepage processing node figure in the design, the constructor lacks experience, so that waterproof construction technology is not right, and weak link seeps water easily.
2. material aspect
Brick that has and face brick quality are loose, water absorption rate is excessive, through rain drop erosion and alternate freezing and thawing, causes face brick cracking, blistering, comes off, rainwater easily infiltrates body of wall, present sand is second-rate in addition, and mud content is big, and particle is less than normal, make the masonry mortar label on the low side, the intensity of plastering does not reach requirement yet, causes metope hollowing, cracking to occur, causes seepage.
3. construction aspect
(1) brick works carelessness: along with the raising of architectural decoration, the designer has put on beautiful " overcoat " for building, and people have ignored the function that the masonry antiseepage is divulged psychologically, not too payes attention to laying bricks quality.The mortar that has in the construction is not full; Leading to appears in the masonry that has, empty, blind seam; The pin trick hole that has, cable wind rope and builder's jack drawknot silk are crossed the wall hole and install to be reserved pore etc. and do not stop up tightly etc., cause the body of wall inadequate natural endowment, cause seepage.
(2) jointing is unreal: according to the constructing operation rules, and after brickwork and furring brick have been constructed, must be with the careful jointing of mortar, but some units in charge of construction often deduct this procedure artificially, think that rough ash can replace colluding brickwork joint at the bottom of the face brick.Though the face brick jointing is finished, there are not tight quality problems, water directly infiltrates brick wall from the slit, make indoor formation sheet dark and damp.
(3) base treatment is bad: before plastering, dirts such as the floating ash of surface of wall, incrustation, tongue spot are not removed totally, or the concrete surface interleaving agent do not disposed etc., cause setting course not firm, form sky, split, even face brick comes off, when rainwater jumps on metope, run into body of wall space or fine cracks, just immerse gradually, cause seepage.
(4) it is not careful that thin portion handles the practice: wall concavo-convex position such as the Door and window frame periphery pointing is not closely knit with body of wall, the drip of the stringcourse end opening of balcony, rain cover, the lintel of window, windowsill line, cornice and outstanding metope is not done or is done badly, and parapet, flexible wall, shrinkage joint etc. to locate the flashing node processing improper, all can cause seepage.
(3) summary of the invention:
The objective of the invention is to design a kind of method of preventing and treating of exterior wall leakage of face tile, it is overcome the above contradiction of exterior wall leakage that causes, and is a kind of practical and reliable construction techniques.
Technical scheme of the present invention: a kind of method of preventing and treating of exterior wall leakage of face tile, comprise reasonable design before construction and select qualified material, it is characterized in that construction may further comprise the steps:
(1) denseness, plumpness and the mortar joint size of control mortar: reinforcement or add the reinforced concrete soil zone in masonry in accordance with regulations, and conscientiously carry out masonry and add the slurry jointing, its jointing mortar should be mixed with fine sand and make the waterproofing mortar that again adds 5% waterproof powder at 1: 1.5, vertically carry out jointing after the first level from top to bottom;
(2) at the masonry top with the collar tie beam binding site set up the wall collar extension with within the walls mouthful: wall collar extension 15mm, mouthful 30mm within the walls, the wall center is the impermeable screed of tongue and groove shape, and match ratio is 1: 3 a cement mortar, admixture 3% waterproof powder is built reinforced concrete circle beam then;
(3) wall plastering is to improve the adhesion stress of bottom mortar and matrix: before scraping rough ash, should remove the dust on surface earlier, dirt, pick the flat outstanding too much position of metope, after watering the water-wet metope, brush 107 glue mud one time, its match ratio is preferably cement: 107 glue: water=1: 0.3: 5, and with brushing with the bottom mortar, make it smear into crude, the middle level mortar should not be smeared too thickly, when surpassing 15mm as local thickness, answers layering to fill levelling, its planeness should meet senior quality requirement of plastering, constructed and should in time carry out water seasoning, curing time should not be less than 3d, inlays furring brick again, facing tile should be with polymer cement mortar or polymer water mud as cementitious materials, and colludes full seam and obturage;
(4) reserving the door and window hole size will get ready: promptly should not adopt the polymer cement mortar levelling to wipe one's face greater than 10mm with every limit, gap all around, and smear to metope and be no less than 50mm, the interior outside window sill discrepancy in elevation should be more than or equal to 20mm, a sliding sash device of should limiting;
(5) construction of the flashing on parapet and the load bearing wall: be about to parapet constructional column cage of reinforcement and dwindle 40mm along wall thickness, outer partially the setting, can on constructional column, reserve groove with 40mm * 40mm lumps of wood during formwork like this, when waterproof coiled material is received head on load bearing wall, stay the flashing groove to influence structure, can be by concrete wall coiled material flashing practice construction in the standard;
(6) clean, soak after should matching during furring brick: the furring brick that apolegamy is good should be cleaned earlier and be put into clear water again and soak 2~3h, take out treat that the surface is dried after, water the water-wet metope to paste again, mortar should be with transferring with usefulness, mortar joint must be crowded with;
(7) collude outseam: the waterproofing materials that the face brick waterproofing materials colludes outseam is 1: 1 cement mortar or organosilicon moisture repellent brushing; Use cement mortar and collude outseam, that the jointing slurry should drag is flat, compacting, receipts light, uses the organosilicon moisture repellent brushing more than twice.
Above-mentioned said appropriate design is recommended the thin portion waterproof practice, and to all external wall structures, corresponding waterproof scheme all should be made in all positions that easily causes seepage;
Above-mentionedly saidly select qualified material must meet the requirements to intensity, severe, water absorption rate and hardness number, the presentation quality of the used brick of brickwork, avoid under-burned brick, crisp brick or bolt line brick, sand will be controlled the mud content grating, and cement must detect and could use after qualified; Described qualified brick material should not comprise crackle, spot, collides with, shells the limit, glaze bubble, deformation extent surpass the stipulator.
The concrete construction sequence of above-mentioned said step (2) for be treat masonry build by laying bricks or stones the top after water moistening, auxiliary seepage proof screed then, the surface is with spreading troweling conveniently, treat under the normal temperature behind the maintenance 24h, make the antiseepage screed reach certain intensity, can carry out reinforcing bar binding and form erecting operation, build reinforced concrete circle beam then, prevent to shrink inequality, the crack occurs, body of wall eyelet and big calixconcavity place, must stop up tightly with cement mortar, and need to note in operation earlier the residual pool of the mortar in the hole to be rejected clean, and water water-wet, layering pointing mortar carefully can adopt the sealing compound pointing to less hole again.
The timber window is used cement mortar that embedding is filled out in the slit layering is closely knit in the above-mentioned said step (4); It is tight that the aluminium alloys doorframe should adopt mineral wool or the layering of glass wool felt rug to stop up, and 5mm * 8mm deep trouth mouth is stayed on the surface, in the lower frame spilled water hole must be arranged, and is smooth with glass cement or other similar waterproof material pointing.
Will there be 3%~5% the outer low and inner high flowing water gradient or ceramic tile drip in windowsill, canopy place in the above-mentioned said step (5), windowsill plane face brick should be lower than window frame, and puts in sash position, all upright, corners, plane, answer the end face face brick to press the facade face brick, in case rainwater infiltrates in upright seam.
Superiority of the present invention is: this programme forms a kind of method of preventing and treating of exterior wall leakage of face tile of system, and is effective, is convenient to constructing operation, and the exterior wall control that improves building is leaked with dissemination.
(4) specific embodiment:
Embodiment: the method for preventing and treating that a kind of external wall with facing bricks infiltration is leaked, comprise reasonable design before construction and select qualified material, said appropriate design to recommend the thin portion waterproof practice, to all external wall structures, corresponding waterproof scheme all should be made in all positions that easily causes seepage; Saidly select qualified material must meet the requirements to intensity, severe, water absorption rate and hardness number, the presentation quality of the used brick of brickwork, avoid under-burned brick, crisp brick or bolt line brick, sand will be controlled the mud content grating, and cement must detect and could use after qualified; Described qualified brick material should not comprise crackle, spot, collides with, shells the limit, glaze bubble, deformation extent surpass the stipulator.
It is characterized in that construction may further comprise the steps:
(1) denseness, plumpness and the mortar joint size of control mortar: reinforcement or add the reinforced concrete soil zone in masonry in accordance with regulations, and conscientiously carry out masonry and add the slurry jointing, its jointing mortar should be mixed with fine sand and make the waterproofing mortar that again adds 5% waterproof powder at 1: 1.5, vertically carry out jointing after the first level from top to bottom;
(2) at the masonry top with the collar tie beam binding site set up the wall collar extension with within the walls mouthful: wall collar extension 15mm, mouthful 30mm within the walls, the wall center is the impermeable screed of tongue and groove shape, and match ratio is 1: 3 a cement mortar, admixture 3% waterproof powder is built reinforced concrete circle beam then;
(3) wall plastering is to improve the adhesion stress of bottom mortar and matrix: before scraping rough ash, should remove the dust on surface earlier, dirt, pick the flat outstanding too much position of metope, after watering the water-wet metope, brush 107 glue mud one time, its match ratio is preferably cement: 107 glue: water=1: 0.3: 5, and with brushing with the bottom mortar, make it smear into crude, the middle level mortar should not be smeared too thickly, when surpassing 15mm as local thickness, answers layering to fill levelling, its planeness should meet senior quality requirement of plastering, constructed and should in time carry out water seasoning, curing time should not be less than 3d, inlays furring brick again, facing tile should be with polymer cement mortar or polymer water mud as cementitious materials, and colludes full seam and obturage;
(4) reserving the door and window hole size will get ready: promptly should not adopt the polymer cement mortar levelling to wipe one's face greater than 10mm with every limit, gap all around, and smear to metope and be no less than 50mm, the interior outside window sill discrepancy in elevation should be more than or equal to 20mm, a sliding sash device of should limiting;
(5) construction of the flashing on parapet and the load bearing wall: be about to parapet constructional column cage of reinforcement and dwindle 40mm along wall thickness, outer partially the setting, can on constructional column, reserve groove with 40mm * 40mm lumps of wood during formwork like this, when waterproof coiled material is received head on load bearing wall, stay the flashing groove to influence structure, can be by concrete wall coiled material flashing practice construction in the standard;
(6) clean after should matching during furring brick, put into clear water again and soak 2~3h, take out treat that the surface is dried after, water the water-wet metope and paste again, mortar should be with transferring with usefulness, mortar joint must be crowded with;
(7) collude outseam: the waterproofing materials that the face brick waterproofing materials colludes outseam is 1: 1 cement mortar or organosilicon moisture repellent brushing; Use cement mortar and collude outseam, that the jointing slurry should drag is flat, compacting, receipts light, uses the organosilicon moisture repellent brushing more than twice.
The concrete construction sequence of above-mentioned said step (2) for be treat masonry build by laying bricks or stones the top after water moistening, auxiliary seepage proof screed then, the surface is with spreading troweling conveniently, treat under the normal temperature behind the maintenance 24h, make the antiseepage screed reach certain intensity, can carry out reinforcing bar binding and form erecting operation, build reinforced concrete circle beam then, prevent to shrink inequality, the crack occurs, body of wall eyelet and big calixconcavity place, must stop up tightly with cement mortar, and need to note in operation earlier the residual pool of the mortar in the hole to be rejected clean, and water water-wet, layering pointing mortar carefully can adopt the sealing compound pointing to less hole again.
The timber window is used cement mortar that embedding is filled out in the slit layering is closely knit in the above-mentioned said step (4); It is tight that the aluminium alloys doorframe should adopt mineral wool or the layering of glass wool felt rug to stop up, and 5mm * 8mm deep trouth mouth is stayed on the surface, in the lower frame spilled water hole must be arranged, and is smooth with glass cement or other similar waterproof material pointing.
Will there be 3%~5% the outer low and inner high flowing water gradient or ceramic tile drip in windowsill, canopy place in the above-mentioned said step (5), windowsill plane face brick should be lower than window frame, and puts in sash position, all upright, corners, plane, answer the end face face brick to press the facade face brick, in case rainwater infiltrates in upright seam.

Claims (6)

1. the method for preventing and treating of an exterior wall leakage of face tile comprises reasonable design before construction and selects qualified material, it is characterized in that construction may further comprise the steps:
(1) denseness, plumpness and the mortar joint size of control mortar: reinforcement or add the reinforced concrete soil zone in masonry in accordance with regulations, and conscientiously carry out masonry and add the slurry jointing, its jointing mortar should be mixed with fine sand and make the waterproofing mortar that again adds 5% waterproof powder at 1: 1.5, vertically carry out jointing after the first level from top to bottom;
(2) at the masonry top with the collar tie beam binding site set up the wall collar extension with within the walls mouthful: wall collar extension 15mm, mouthful 30mm within the walls, the wall center is the impermeable screed of tongue and groove shape, and match ratio is 1: 3 a cement mortar, admixture 3% waterproof powder is built reinforced concrete circle beam then;
(3) wall plastering is to improve the adhesion stress of bottom mortar and matrix: before scraping rough ash, should remove the dust on surface earlier, dirt, pick the flat outstanding too much position of metope, after watering the water-wet metope, brush 107 glue mud one time, its match ratio is preferably cement: 107 glue: water=1: 0.3: 5, and with brushing with the bottom mortar, make it smear into crude, the middle level mortar should not be smeared too thickly, when surpassing 15mm as local thickness, answers layering to fill levelling, its planeness should meet senior quality requirement of plastering, constructed and should in time carry out water seasoning, curing time should not be less than 3d, inlays furring brick again, facing tile should be with polymer cement mortar or polymer water mud as cementitious materials, and colludes full seam and obturage;
(4) reserving the door and window hole size will get ready: promptly should not adopt the polymer cement mortar levelling to wipe one's face greater than 10mm with every limit, gap all around, and smear to metope and be no less than 50mm, the interior outside window sill discrepancy in elevation should be more than or equal to 20mm, a sliding sash device of should limiting;
(5) construction of the flashing on parapet and the load bearing wall: be about to parapet constructional column cage of reinforcement and dwindle 40mm along wall thickness, outer partially the setting, can on constructional column, reserve groove with 40mm * 40mm lumps of wood during formwork like this, when waterproof coiled material is received head on load bearing wall, stay the flashing groove to influence structure, can be by concrete wall coiled material flashing practice construction in the standard;
(6) clean, soak after should matching during furring brick: the furring brick that apolegamy is good should be cleaned earlier and be put into clear water again and soak 2~3h, take out treat that the surface is dried after, water the water-wet metope to paste again, mortar should be with transferring with usefulness, mortar joint must be crowded with;
(7) collude outseam: the waterproofing materials that the face brick waterproofing materials colludes outseam is 1: 1 cement mortar or organosilicon moisture repellent brushing; Use cement mortar and collude outseam, that the jointing slurry should drag is flat, compacting, receipts light, uses the organosilicon moisture repellent brushing more than twice.
2. according to the method for preventing and treating of the said a kind of exterior wall leakage of face tile of claim 1, it is characterized in that said appropriate design recommends the thin portion waterproof practice, to all external wall structures, corresponding waterproof scheme all should be made in all positions that easily causes seepage.
3. according to the method for preventing and treating of the said a kind of exterior wall leakage of face tile of claim 1, it is characterized in that saidly selecting qualified material must meet the requirements to intensity, severe, water absorption rate and hardness number, the presentation quality of the used brick of brickwork, avoid under-burned brick, crisp brick or bolt line brick, sand will be controlled the mud content grating, could use after the detection of cement palpus is qualified; Described qualified brick material should not comprise crackle, spot, collides with, shells the limit, glaze bubble, deformation extent surpass the stipulator.
4. according to the method for preventing and treating of the said a kind of exterior wall leakage of face tile of claim 1, the concrete construction sequence that it is characterized in that said step (2) for be treat masonry build by laying bricks or stones water behind the top moistening, auxiliary seepage proof screed then, the surface is with spreading troweling conveniently, treat under the normal temperature behind the maintenance 24h, make the antiseepage screed reach certain intensity, can carry out reinforcing bar binding and form erecting operation, build reinforced concrete circle beam then, prevent to shrink uneven, the crack occurs, body of wall eyelet and big calixconcavity place must stop up tight with cement mortar, and need to note in operation rejecting the residual pool of the mortar in the hole clean earlier, and watering water-wet, layering pointing mortar carefully can adopt the sealing compound pointing to less hole again.
5. according to the method for preventing and treating of the said a kind of exterior wall leakage of face tile of claim 1, it is characterized in that in the said step (4) using cement mortar by the timber window, that embedding is filled out in the slit layering is closely knit; It is tight that the aluminium alloys doorframe should adopt mineral wool or the layering of glass wool felt rug to stop up, and 5mm * 8mm deep trouth mouth is stayed on the surface, in the lower frame spilled water hole must be arranged, and is smooth with glass cement or other similar waterproof material pointing.
6. according to the method for preventing and treating of the said a kind of exterior wall leakage of face tile of claim 1, it is characterized in that will there be 3%~5% the outer low and inner high flowing water gradient or ceramic tile drip in windowsill, canopy place in the said step (5), windowsill plane face brick should be lower than window frame, and put in sash position, all upright, corners, plane, answer the end face face brick to press the facade face brick, in case rainwater infiltrates in upright seam.
CNA2006100154293A 2006-08-23 2006-08-23 Preventing method for exterior wall leakage of face tile Pending CN101131007A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2006100154293A CN101131007A (en) 2006-08-23 2006-08-23 Preventing method for exterior wall leakage of face tile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2006100154293A CN101131007A (en) 2006-08-23 2006-08-23 Preventing method for exterior wall leakage of face tile

Publications (1)

Publication Number Publication Date
CN101131007A true CN101131007A (en) 2008-02-27

Family

ID=39128403

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2006100154293A Pending CN101131007A (en) 2006-08-23 2006-08-23 Preventing method for exterior wall leakage of face tile

Country Status (1)

Country Link
CN (1) CN101131007A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926482A (en) * 2012-11-26 2013-02-13 大连共益建设集团有限公司 External waterproof structure of exterior wall of building and construction method thereof
CN103306383A (en) * 2013-06-30 2013-09-18 二十二冶集团第一建设有限公司 Infiltration prevention method for bolt hole in outer wall of reinforced concrete shear wall
CN104153485A (en) * 2014-07-17 2014-11-19 天津二十冶建设有限公司 Outer-wall tongue groove capable of preventing water seepage of window and construction method of outer-wall tongue groove
CN111287387A (en) * 2020-03-01 2020-06-16 中铁十八局集团有限公司 Construction process of groove of parapet wall
CN111777355A (en) * 2019-04-04 2020-10-16 南京理工大学 Composite brick for monitoring leakage condition of diversion canal dike and manufacturing method
CN112127564A (en) * 2020-09-04 2020-12-25 闫山 Anti-permeability ceramic tile for building exterior wall and using method thereof
CN112554589A (en) * 2020-10-22 2021-03-26 无锡飞轩机电科技有限公司 Wall repairing device for building construction

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926482A (en) * 2012-11-26 2013-02-13 大连共益建设集团有限公司 External waterproof structure of exterior wall of building and construction method thereof
CN103306383A (en) * 2013-06-30 2013-09-18 二十二冶集团第一建设有限公司 Infiltration prevention method for bolt hole in outer wall of reinforced concrete shear wall
CN104153485A (en) * 2014-07-17 2014-11-19 天津二十冶建设有限公司 Outer-wall tongue groove capable of preventing water seepage of window and construction method of outer-wall tongue groove
CN111777355A (en) * 2019-04-04 2020-10-16 南京理工大学 Composite brick for monitoring leakage condition of diversion canal dike and manufacturing method
CN111287387A (en) * 2020-03-01 2020-06-16 中铁十八局集团有限公司 Construction process of groove of parapet wall
CN112127564A (en) * 2020-09-04 2020-12-25 闫山 Anti-permeability ceramic tile for building exterior wall and using method thereof
CN112127564B (en) * 2020-09-04 2021-11-02 孙超 Anti-permeability ceramic tile for building exterior wall and using method thereof
CN112554589A (en) * 2020-10-22 2021-03-26 无锡飞轩机电科技有限公司 Wall repairing device for building construction

Similar Documents

Publication Publication Date Title
CN104018598B (en) A kind of external wall structure and construction installation method
CN101131007A (en) Preventing method for exterior wall leakage of face tile
CN103821296A (en) Wall plastering technique for aerated concrete block filler wall
CN201224933Y (en) Frame beam preventing water seepage and crack and wall stuffing structure
CN107338967A (en) A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform
CN204826464U (en) Waterproof construction of parapet
CN111042570B (en) Repairing construction method for fresh water brick wall of ancient building
CN106013509A (en) Dry-method construction method for high-performance autolaved aerated concrete block wall
CN104088416A (en) Gypsum heat preservation painting mortar construction process
CN102758504A (en) Method for constructing wet-operation details of completely-decorated housings
CN103195218B (en) Wall ceramic sand mortar external plastering construction method
Orlenko The system approach as a means of restoration activity effectiveness
CN112575979A (en) Construction method of plastering waterproof mortar for building exterior wall
CN103850362A (en) GHB (Glazed Hollow Bead) heat preservation and heat insulation building wall body and construction technology
CN110306819B (en) Method for repairing red brick outer wall of historic building
CN101545269B (en) Method for rigid waterproof construction of beam and slab type basement
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN102344278B (en) Permeable crystallization type cement-based waterproof mucilage
CN207194353U (en) A kind of prefabricated thermal insulation water-proof decorative external wall panel structure
CN207194343U (en) The tapestry brick paving structure of autoclave aerated concrete building block exterior wall
CN209509431U (en) A kind of facing paving structure of wet area
Reichel et al. Plaster, render, paint and coatings: details, products, case studies
CN207063141U (en) A kind of thermal-insulating waterproof building structure
CN114575620A (en) Formwork-supporting-free reinforcement high-ductility concrete construction method for masonry reinforcement
CN108708563A (en) It is a kind of to keep the ceramic tile of ceramic tile original state, stone facing point face to reinforce repairing engineering method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice

Addressee: Wang Lige

Document name: Notification of Passing Examination on Formalities

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080227