CN101054799A - Post-grouting construction method for long helical bore grouting pile and its grouting device - Google Patents
Post-grouting construction method for long helical bore grouting pile and its grouting device Download PDFInfo
- Publication number
- CN101054799A CN101054799A CN 200710200046 CN200710200046A CN101054799A CN 101054799 A CN101054799 A CN 101054799A CN 200710200046 CN200710200046 CN 200710200046 CN 200710200046 A CN200710200046 A CN 200710200046A CN 101054799 A CN101054799 A CN 101054799A
- Authority
- CN
- China
- Prior art keywords
- grouting
- pile
- stake
- grouting pipe
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007102000468A CN100476082C (en) | 2007-01-12 | 2007-01-12 | Post-grouting construction method for long helical bore grouting pile and grouting device thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007102000468A CN100476082C (en) | 2007-01-12 | 2007-01-12 | Post-grouting construction method for long helical bore grouting pile and grouting device thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101054799A true CN101054799A (en) | 2007-10-17 |
CN100476082C CN100476082C (en) | 2009-04-08 |
Family
ID=38794829
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2007102000468A Active CN100476082C (en) | 2007-01-12 | 2007-01-12 | Post-grouting construction method for long helical bore grouting pile and grouting device thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100476082C (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561360A (en) * | 2012-02-06 | 2012-07-11 | 化学工业岩土工程有限公司 | Deep foundation pit supporting method |
CN103174135A (en) * | 2011-12-23 | 2013-06-26 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN103184738A (en) * | 2012-10-20 | 2013-07-03 | 二十二冶集团第一建设有限公司 | Grouting guide pipe restraint ring mounting structure and method for mounting grouting guide pipes by using restraint rings |
CN104711975A (en) * | 2015-03-24 | 2015-06-17 | 北京中岩大地工程技术有限公司 | Construction technology for long spiral cast-in-situ bored pile |
CN106337417A (en) * | 2016-08-30 | 2017-01-18 | 十四冶建设云南勘察设计有限公司 | Post-grouting method for pile end of rotary excavation pile |
CN106638607A (en) * | 2016-11-24 | 2017-05-10 | 中航勘察设计研究院有限公司 | Connecting method for grouting pipe and reinforcement cage in pile foundation post grouting construction |
CN108716216A (en) * | 2018-05-22 | 2018-10-30 | 四川城凯特建设工程有限公司 | Long auger guncreting pile molding construction method and its additional reinforcement device |
CN108867625A (en) * | 2018-07-20 | 2018-11-23 | 四川锦城智信建设工程有限公司 | Long auger guncreting pile grouting behind shaft or drift lining handles construction method and its postposition grouting device |
CN110153335A (en) * | 2019-04-28 | 2019-08-23 | 云南建投第一勘察设计有限公司 | A kind of processing method of long screw auger drilling deposited pile steel reinforcement cage |
CN110397027A (en) * | 2018-04-25 | 2019-11-01 | 上海城地建设股份有限公司 | The compound pile constructing process of Stiffened Soil |
CN112281824A (en) * | 2020-10-30 | 2021-01-29 | 黄淮学院 | Post-grouting construction method for pile bottom of post-inserted reinforcement cage of cast-in-place concrete pile |
-
2007
- 2007-01-12 CN CNB2007102000468A patent/CN100476082C/en active Active
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103174135A (en) * | 2011-12-23 | 2013-06-26 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN103174135B (en) * | 2011-12-23 | 2015-06-03 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN102561360B (en) * | 2012-02-06 | 2015-04-29 | 化学工业岩土工程有限公司 | Deep foundation pit supporting method |
CN102561360A (en) * | 2012-02-06 | 2012-07-11 | 化学工业岩土工程有限公司 | Deep foundation pit supporting method |
CN103184738A (en) * | 2012-10-20 | 2013-07-03 | 二十二冶集团第一建设有限公司 | Grouting guide pipe restraint ring mounting structure and method for mounting grouting guide pipes by using restraint rings |
CN103184738B (en) * | 2012-10-20 | 2015-02-04 | 二十二冶集团第一建设有限公司 | Grouting guide pipe restraint ring mounting structure and method for mounting grouting guide pipes by using restraint rings |
CN104711975A (en) * | 2015-03-24 | 2015-06-17 | 北京中岩大地工程技术有限公司 | Construction technology for long spiral cast-in-situ bored pile |
CN106337417B (en) * | 2016-08-30 | 2019-05-24 | 云南建投第一勘察设计有限公司 | A kind of rotary digging stake pile-end post-grouting method |
CN106337417A (en) * | 2016-08-30 | 2017-01-18 | 十四冶建设云南勘察设计有限公司 | Post-grouting method for pile end of rotary excavation pile |
CN106638607A (en) * | 2016-11-24 | 2017-05-10 | 中航勘察设计研究院有限公司 | Connecting method for grouting pipe and reinforcement cage in pile foundation post grouting construction |
CN110397027A (en) * | 2018-04-25 | 2019-11-01 | 上海城地建设股份有限公司 | The compound pile constructing process of Stiffened Soil |
CN108716216A (en) * | 2018-05-22 | 2018-10-30 | 四川城凯特建设工程有限公司 | Long auger guncreting pile molding construction method and its additional reinforcement device |
CN108867625A (en) * | 2018-07-20 | 2018-11-23 | 四川锦城智信建设工程有限公司 | Long auger guncreting pile grouting behind shaft or drift lining handles construction method and its postposition grouting device |
CN110153335A (en) * | 2019-04-28 | 2019-08-23 | 云南建投第一勘察设计有限公司 | A kind of processing method of long screw auger drilling deposited pile steel reinforcement cage |
CN110153335B (en) * | 2019-04-28 | 2021-09-03 | 云南建投第一勘察设计有限公司 | Processing method of long spiral drilling cast-in-place pile reinforcement cage |
CN112281824A (en) * | 2020-10-30 | 2021-01-29 | 黄淮学院 | Post-grouting construction method for pile bottom of post-inserted reinforcement cage of cast-in-place concrete pile |
Also Published As
Publication number | Publication date |
---|---|
CN100476082C (en) | 2009-04-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101054799A (en) | Post-grouting construction method for long helical bore grouting pile and its grouting device | |
CN103510510B (en) | A kind of enhancement mode long auger cast-with-pressure concrete pile and construction method | |
CN102206939B (en) | Method for processing soft soil foundation of high vacuum drainage filter pipe capable of being grouted | |
CN101736738B (en) | Production method of pressure resistance and pull-out resistance grouted gravel pile | |
CN100371537C (en) | Novel method for reinforcing deep soft foundition-cencrete core sand stone pile compound foundition method | |
CN102011399B (en) | PHC pile-based multiple high jet pedestal pile construction method | |
CN1851148A (en) | Screw-thread bored concrete pile piling method | |
CN101525880A (en) | Plastic sleeve concrete pile and method thereof for reinforcing soft soil foundation | |
CN1928251A (en) | Pipe pile hole maker with concrete bottom sealing, pipe cover and wings and construction process thereof | |
CN114517472B (en) | Construction method of carrier pile | |
CN1219945C (en) | High-pressure rotary spraying and core inserting process to form pedestal pile | |
CN102808407A (en) | Construction method of soft-foundation reinforced concrete cast-in-place pile | |
CN1195130C (en) | Sand concrete free small pile foundation consolidation process by stone throwing and squeezing | |
CN105780766A (en) | Drilling backfill end bearing pile foundation and construction method thereof | |
CN203594023U (en) | Enhanced type long auger drilling pressure-grouting concrete pile | |
CN1051349C (en) | Pile head grouting and supersonic detecting combined process for filling long pile in saturated soil | |
CN1793524A (en) | Method for construction of large head expanding combined pile | |
CN1279247C (en) | Multi-layer assembled steel pipe embedding rock piling method | |
CN1189628C (en) | Extradeep extruding and ramming method | |
CN105421446B (en) | A kind of construction method of composite soil extruding solidification prefabricated pile for treatment of soft foundation | |
CN1066511C (en) | After-grouting pile composite foundation and construction method thereof | |
CN1676763A (en) | Boring-tamping cement-soil compacting pile construction method | |
CN101892665A (en) | Construction method for grouting and vibro-replacement stone pile composite foundation | |
CN1209489A (en) | Construction method for composite foundation by tamping expanding piles and compacting soil around piles | |
CN1598166A (en) | Hollow artificial hole digging bored concrete pile and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20071017 Assignee: Beijing Geotechnical Engineering Association Assignor: Jianyan Foundation Engineering LLC Contract record no.: 2015990000889 Denomination of invention: Post-grouting construction method for long helical bore grouting pile and its grouting device Granted publication date: 20090408 License type: Exclusive License Record date: 20151026 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
EC01 | Cancellation of recordation of patent licensing contract | ||
EC01 | Cancellation of recordation of patent licensing contract |
Assignee: Beijing Geotechnical Engineering Association Assignor: CABR FOUNDATION ENGINEERING Co.,Ltd. Contract record no.: 2015990000889 Date of cancellation: 20201120 |
|
EE01 | Entry into force of recordation of patent licensing contract | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20071017 Assignee: Beijing Geotechnical Engineering Association Assignor: CABR FOUNDATION ENGINEERING Co.,Ltd. Contract record no.: X2020990000617 Denomination of invention: Construction method of post grouting treatment of Long Auger Bored Pile and its post grouting device Granted publication date: 20090408 License type: Exclusive License Record date: 20201120 |