CN100580219C - 一种煤矿井下无煤柱回收方法 - Google Patents

一种煤矿井下无煤柱回收方法 Download PDF

Info

Publication number
CN100580219C
CN100580219C CN200710061688A CN200710061688A CN100580219C CN 100580219 C CN100580219 C CN 100580219C CN 200710061688 A CN200710061688 A CN 200710061688A CN 200710061688 A CN200710061688 A CN 200710061688A CN 100580219 C CN100580219 C CN 100580219C
Authority
CN
China
Prior art keywords
coal
along
boring
pillar
empty
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200710061688A
Other languages
English (en)
Other versions
CN101033689A (zh
Inventor
闫振东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LANGFANG JINGLONG HEAVY MACHINERY CO Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN200710061688A priority Critical patent/CN100580219C/zh
Publication of CN101033689A publication Critical patent/CN101033689A/zh
Application granted granted Critical
Publication of CN100580219C publication Critical patent/CN100580219C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明提供了一种煤矿井下无煤柱回收方法,包括以下工艺:留设煤柱、沿空钻孔、垂空钻孔、回采煤柱、通风系统、衔接措施、安全和运输措施;其主要是沿空钻孔在工作面机尾沿着已采工作面的采空边缘施工钻圆孔,沿着顶板进行钻孔,并设置1~3个圆孔作为回采工作面的回风孔;垂空钻孔是在轨道巷内垂直钻孔与沿空钻孔贯通,钻孔数量与沿空钻孔数量相同。本发明优点是沿采空区边缘布置通风钻孔,可避开和削弱固定支撑压力的影响,取代沿空留巷和沿空掘巷,提高煤炭资源回收率,不仅大大减少了巷道掘进工程量和维护量,而且沿空钻孔具有安全、高效、低耗。

Description

一种煤矿井下无煤柱回收方法
技术领域
本发明属于煤矿井下机械采煤技术,特别涉及一种煤矿井下无煤柱回收方法。
背景技术
在我国煤矿中煤柱回收技术不够成熟,大部分矿井使用留煤柱开采方法进行采煤,这样势必造成了资源回收率低,使煤炭资源浪费十分严重。目前,区段无煤柱护巷(沿空留巷和沿空掘巷)方法在部分矿井推广使用,但由于安全系数低,掘进速度慢,留巷、掘巷成本高,从而使得这种采煤方法难以普遍推广。
发明内容
本发明对上述现有无煤柱采煤技术存在的问题进行了研究,其目的是提供一种提高煤炭资源回收率,掘进速度较快,安全可靠的煤矿井下无煤柱回收方法。
为了实现上述目的本发明的技术方案是:
一种煤矿井下无煤柱回收方法,沿采空区边缘布置通风钻孔,其特征是:
(1)、留设煤柱:为使下区段轨道平巷避开较大支撑压力的影响,要留设区段煤柱,由于区段煤柱最终要回收,为便于巷道维护,煤柱尺寸宽应为25~30m;
(2)、沿空钻孔:在工作面机尾沿着已采工作面的采空边缘施工钻1~3个圆孔,圆孔作为回采工作面的回风孔,并沿着顶板进行钻孔;
(3)、垂空钻孔:在轨道巷内垂空钻孔与沿空钻孔贯通,钻孔数量与沿空钻孔数量相同;
(4)、回采煤柱:在下区段工作面回采过程中,工作面支架和溜子铺设在区段采空区边缘,割煤机割煤至采空区边缘,完全回收留设的煤柱;
(5)、通风系统:在轨道巷近工作面处设置风帘挡风,保证工作面机尾上隅角的风流沿着通风钻孔流向轨道回风巷,确保上隅角瓦斯不超限。
所述的一种煤矿井下无煤柱回收方法,其特征是:所还有衔接措施,即沿空钻孔必须在采空区顶板岩石活动稳定后开始钻孔,钻孔滞后回采时间的间隔时间在3个月内。
所述的一种煤矿井下无煤柱回收方法,其特征是:还有安全和运输措施,即工作面确保了皮带运输巷和轨道运输巷两个安全出口,运料仍利用轨道巷运料。
本发明一种煤矿井下无煤柱回收方法与现有的煤矿掘进工艺方法相比,其优点是:沿采空区边缘布置通风钻孔,可避开和削弱固定支撑压力的影响,取代沿空留巷和沿空掘巷,提高煤炭资源回收率,不仅大大减少了巷道掘进工程量和维护量,而且沿空钻孔具有安全、高效、低耗。
附图说明
图1是一种煤矿井下无煤柱回收方法的巷道布置图。
其中:采空区1、工作面2、留设区段煤柱3
具体实施方式
以下结合附图详细说明本发明的具体实施方式:
如图1所示,本发明一种煤矿井下无煤柱回收方法的巷道布置图。沿采空区1边缘布置通风钻孔,可避开和削弱固定支撑压力的影响,取代沿空留巷和沿空掘巷。该方法:
1、留设煤柱:为了使下区段轨道平巷避开较大支撑压力的影响,要留设区段煤柱3,由于留设区段煤柱最终要回收,为了便于巷道维护、煤柱尺寸可以较大,宽为25~30m;
2、沿空钻孔:在工作面机尾沿着已采工作面的采空边缘施工直径1000mm的圆孔1~3个作为回采工作面的回风孔,这种方法利用采空区边缘压力较小的特点,沿着顶板进行钻孔,钻孔深度35m;
3、垂空钻孔:在轨道巷内垂空钻孔施工圆孔为直径1000mm,并与沿空钻孔贯通,钻孔数量与沿空钻孔数量相同;
4、回采煤柱:下区段工作面2回采时,工作面支架和溜子铺设在区段采空区边缘,割煤机割煤至采空区边缘,完全回收留设的煤柱;如图1箭头所示割煤机割煤走向4;
5、通风系统:首先在轨道巷近工作面处设置风帘6挡风,保证工作面机尾上隅角的风流沿着通风钻孔流向轨道回风巷,确保上隅角瓦斯不超限;
6、衔接措施:沿空钻孔必须在采空区顶板岩石活动稳定后开始钻孔,否则受到支撑压力的剧烈影响,钻孔容易塌落,因此掌握好钻孔滞后回采时间的间隔是十分重要的,一般情况下间隔时间不少于三个月;
7、安全和运输措施:工作面2确保了皮带运输巷和轨道运输巷两个安全出口,运料仍利用轨道巷运料。如果钻孔困难和造成塌孔时,可留窄小煤柱进行钻孔和补打钻孔。
以上所述的沿空钻孔、垂空钻孔工艺的实施采用钻孔机械。本发明适用于大、中型煤矿。

Claims (4)

1、一种煤矿井下无煤柱回收方法,沿采空区边缘布置通风钻孔,其特征是:
(1)、留设煤柱:为使下区段轨道平巷避开较大支撑压力的影响,要留设区段煤柱,由于区段煤柱最终要回收,为便于巷道维护,煤柱尺寸宽应为25~30m;
(2)、沿空钻孔:在工作面机尾沿着已采工作面的采空边缘施工钻1~3个圆孔,圆孔作为回采工作面的回风孔,并沿着顶板进行钻孔;
(3)、垂空钻孔:在轨道巷内垂空钻孔与沿空钻孔贯通,钻孔数量与沿空钻孔数量相同;
(4)、回采煤柱:在下区段工作面回采过程中,工作面支架和溜子铺设在区段采空区边缘,割煤机割煤至采空区边缘,完全回收留设的煤柱;
(5)、通风系统:在轨道巷近工作面处设置风帘挡风,保证工作面机尾上隅角的风流沿着通风钻孔流向轨道回风巷,确保上隅角瓦斯不超限。
2、根据权利要求1所述的一种煤矿井下无煤柱回收方法,其特征是:还有衔接措施,即沿空钻孔必须在采空区顶板岩石活动稳定后开始钻孔,钻孔滞后回采时间的间隔时间在3个月内。
3、根据权利要求1或2所述的一种煤矿井下无煤柱回收方法,其特征是:还有安全和运输措施,即工作面确保了皮带运输巷和轨道运输巷两个安全出口,运料仍利用轨道巷运料。
4、根据权利要求1所述的一种煤矿井下无煤柱回收方法,其特征是:所述的沿空钻孔与垂空钻孔施工圆孔直径为1000mm。
CN200710061688A 2007-04-10 2007-04-10 一种煤矿井下无煤柱回收方法 Expired - Fee Related CN100580219C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710061688A CN100580219C (zh) 2007-04-10 2007-04-10 一种煤矿井下无煤柱回收方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710061688A CN100580219C (zh) 2007-04-10 2007-04-10 一种煤矿井下无煤柱回收方法

Publications (2)

Publication Number Publication Date
CN101033689A CN101033689A (zh) 2007-09-12
CN100580219C true CN100580219C (zh) 2010-01-13

Family

ID=38730411

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710061688A Expired - Fee Related CN100580219C (zh) 2007-04-10 2007-04-10 一种煤矿井下无煤柱回收方法

Country Status (1)

Country Link
CN (1) CN100580219C (zh)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392642A (zh) * 2011-11-02 2012-03-28 王晓利 一种无煤柱回采工作面的巷道布置方法
PL2801697T3 (pl) * 2012-01-06 2020-06-15 He, Manchao Sposób wybierania roboczego przodka ścianowego bez filarowania
CN103527197B (zh) * 2013-10-28 2016-01-06 中国矿业大学 一种特厚煤层固体胶结充填巷式开采方法
CN104763434B (zh) * 2015-01-31 2016-09-28 太原理工大学 一种无煤柱双巷掘进方法
CN105275487B (zh) * 2015-10-27 2017-07-18 何满潮 长臂开采n00工法通风系统
CN109882174B (zh) * 2019-04-04 2022-04-01 中国矿业大学(北京) 工作面旋转开采上山煤柱与贯通上山交替协同开采方法
CN110454187B (zh) * 2019-07-04 2021-08-24 内蒙古科技大学 一种提高平硐开拓矿井煤炭资源采出率的巷道布置方法
CN111119903B (zh) * 2019-12-16 2022-04-08 西安中铁工程装备有限公司 一种煤矿沿空掘巷的方法
CN113738360B (zh) * 2021-09-08 2023-09-22 国家能源集团宁夏煤业有限责任公司 一种煤矿井下综采工作面开采方法
CN116971817B (zh) * 2023-09-25 2023-12-12 太原理工大学 一种平巷交替进回风的高瓦斯工作面通风方法
CN117027921B (zh) * 2023-09-28 2023-12-12 太原理工大学 一种防治高瓦斯采空区对临近工作面影响的方法

Also Published As

Publication number Publication date
CN101033689A (zh) 2007-09-12

Similar Documents

Publication Publication Date Title
CN100580219C (zh) 一种煤矿井下无煤柱回收方法
CN101725352B (zh) 一种固体充填综采回收房式煤柱方法
CN103775085B (zh) 急倾斜中厚煤层柔性掩护支架采掘一体支护无煤柱采煤法
CN100554642C (zh) 一种长壁综采回收房式开采煤柱的方法
CN101737047A (zh) 一种急倾斜薄煤层的采煤方法
CN103104260B (zh) 复杂地质条件下综—机对拉面采煤方法
CN101509377B (zh) 急倾斜矿体房柱采矿方法
CN105240013A (zh) 长壁开采n00工法
CN107060760A (zh) 一种煤矿回撤巷道预裂爆破放顶卸压的方法
CN103939135B (zh) 一种综采工作面撤架通道快速施工方法
CN101942999A (zh) 一种急倾斜薄煤层采煤方法
CN110259451A (zh) 一种缓倾斜中厚矿体预控顶高效采矿方法
CN101368482B (zh) 缓倾斜矿体全面采矿法的新工艺
CN104533416A (zh) 极厚大矿体大规模机械化无底柱分段崩落采矿方法
CN101353963B (zh) 急倾斜煤层长孔爆破无人作业工作面空场采煤法
CN103485786B (zh) 一种急倾斜煤层走向长壁机械化开采方法
CN104088643A (zh) 一种急倾斜极近距离煤层放顶煤采煤方法
CN105298496A (zh) 设置预留工作面煤柱的全采全充采煤方法
CN101881167B (zh) 煤矿回采工作面小煤柱开采方法
CN103174424B (zh) 一种长壁布置下的房柱式采煤法
CN106285770A (zh) 一种开采煤层底板泥岩作为保护层增加近距离突出煤层群透气性的方法
CN108505999A (zh) 一种高突煤层工作面多巷布置方法
CN104343453B (zh) 一种缓倾斜中厚矿床充填采矿方法
CN104612692B (zh) 分段崩矿底部结构跟随形成连续充填采矿法
CN101737051A (zh) 一种盲矿体覆盖层形成方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: LANGFANG JINGLONG HEAVY INDUSTRIAL MACHINERY CO.,

Free format text: FORMER OWNER: YAN ZHENDONG

Effective date: 20120110

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 048000 JINCHENG, SHAANXI PROVINCE TO: 065300 LANGFANG, HEBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120110

Address after: 065300 Baihe Industrial Zone, Dachang County, Hebei, Langfang

Patentee after: Langfang Jinglong Heavy Machinery Co., Ltd.

Address before: 048000 Jincheng coal industry group, Shanxi, Jincheng

Patentee before: Yan Zhendong

EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20070912

Assignee: Shanxi Jincheng Anthracite Mining Group Prospecting Design Institute Co., Ltd.

Assignor: Yan Zhendong

Contract record no.: 2011990000388

Denomination of invention: Underground no pillar recovery method of coal mine

Granted publication date: 20100113

License type: Exclusive License

Record date: 20110523

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100113

Termination date: 20210410

CF01 Termination of patent right due to non-payment of annual fee