CN100575504C - Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove - Google Patents

Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove Download PDF

Info

Publication number
CN100575504C
CN100575504C CN200610086925A CN200610086925A CN100575504C CN 100575504 C CN100575504 C CN 100575504C CN 200610086925 A CN200610086925 A CN 200610086925A CN 200610086925 A CN200610086925 A CN 200610086925A CN 100575504 C CN100575504 C CN 100575504C
Authority
CN
China
Prior art keywords
iron
parts
blast furnace
granularity
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200610086925A
Other languages
Chinese (zh)
Other versions
CN101092653A (en
Inventor
章荣会
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing United Rong Da engineering materials Limited by Share Ltd
Original Assignee
Beijing Allied Rongda Engineering Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Allied Rongda Engineering Material Co Ltd filed Critical Beijing Allied Rongda Engineering Material Co Ltd
Priority to CN200610086925A priority Critical patent/CN100575504C/en
Publication of CN101092653A publication Critical patent/CN101092653A/en
Application granted granted Critical
Publication of CN100575504C publication Critical patent/CN100575504C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Blast Furnaces (AREA)
  • Ceramic Products (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The present invention relates to a kind of be used for 1000 cubic metres of volumes with the iron notch blast furnace iron runner that places an order make lining exempt from toast iron runner castable and exempt to toast the processing method that iron runner castable is constructed the casting house ditch lining of Dan Tiekou blast furnace with this.Adopt the mould material of the present invention program's preparation to can be used in the cast-in-site of casting house liner, and after sclerosis, need not baking and can pass through molten iron, thereby realized that single iron notch blast furnace iron outlet groove liner employing mould material constructs or keep in repair.Adopt the casting construction to make lining, constructed ditch lining is all very fine and close from the surface to inside, do not exist ramming mass to have only the closely knit and inner loose problem in surface, so iron runner can prolong work-ing life significantly, the iron runner materials consumption of unit iron output also reduces significantly.This not only brings the raising of economic benefit, also has resources conservation and the benefit that reduces waste residue on the environment protection significance, and the labour intensity of stokehold workman's maintenance service also reduces significantly.

Description

Iron runner exempts to toast mould material and the lining processing method is made in the cast of single iron mouth blast furnace iron outlet groove
Technical field
The present invention relates to iron runner and exempt to toast the cast of mould material and single iron mouth blast furnace iron outlet groove and make the lining processing method, belong to the Dan Tiekou blast furnace iron outlet groove that taps a blast furnace and make lining technology and make lining material therefor technical field.
Background technology
Modern big blast furnace iron outlet groove generally uses fine Al2O3-SiC-C matter to hang down cement deposit material.Because mould material pouring density height, with respect to the fire-resistance rammed mass with material, refractory castable is more anti-to be washed away, thereby longer service life.But the iron runner of traditional Al2O3-SiC-C matter low-cement refractory pouring material cast must just can come into operation through processes such as maintenance sclerosis, baking dryings, and iron runner needs (1 day even pitch time a couple of days) for a long time from beginning cast (repairing) to come into operation (beginning to tap a blast furnace).
General big blast furnace all has the casting house more than 2, therefore when iron runner wherein must be made lining again and maybe must repair, as long as block behind the iron notch of this iron runner to this iron runner pour into a mould, maintenance sclerosis, baking be dry.Meanwhile, other iron notchs tap a blast furnace normally, do not influence the ordinary production of blast furnace.
But volume is the medium and small blast furnace below 1000 cubic metres generally is designed to single iron notch.Owing to have only an iron notch, to tap a blast furnace normally and have only about 1~3 hour at interval, the plan damping down time generally also has only 8~10 hours, can not guarantee if having time therefore that general mould material is made to serve as a contrast needed maintenance, storing time.Therefore, the blast furnace that Dan Tiekou taps a blast furnace generally adopts ramming mass to construct the iron runner liner because ramming mass generally adopts resin or tar combination, needn't toast after the ramming construction or slightly the short period of time baking can directly immediately cross molten iron.
But there is too short problem in work-ing life in ramming mass, and the ramming mass that is used for main casting house generally has only 1~15 day work-ing life, and major part is all at 3~5 days.This be because the ditch lining refractories of ramming generally just ditch basal surface one deck is closely knit relatively, and the top layer is following and ditch group position is all very loose, not anti-washing away.And because the iron runner of ramming is too short work-ing life, it is too frequent to cause casting house to repair, and the stokehold labor strength is too big, makes lining ramming quality and is difficult to especially guarantee.
Therefore how effectively solving the problem in single iron mouth blast furnace iron outlet groove life-span receives much concern.But up to the present, also be not fit to iron runner make lining or repair exempt to toast mould material, do not have single iron mouth blast furnace iron runner to adopt yet and exempt to toast process program and the practice that mould material is made lining.
Summary of the invention
The technical problem to be solved in the present invention is, proposition can be constructed with casting, setting and harden speed is fast, and do not need baking or only need utmost point short period of time baking (in 1 hour) promptly can by molten iron exempt from toast the preparation of iron runner castable and use this to exempt to toast the technical scheme that iron runner castable is constructed single iron notch blast furnace iron runner refractory lining.
The technical solution adopted for the present invention to solve the technical problems is:
One of purpose of the present invention exempts to toast iron runner castable with what the iron notch blast furnace iron runner that places an order was made lining for above 1000 cubic metres for a kind of volume 500 of being used for is provided, and is composed of the following components:
18~25 parts in the brown corundum of granularity 8~5mm,
10~18 parts in the brown corundum of granularity 5~3mm,
15~25 parts in the brown corundum of granularity 3~1mm,
3~9 parts in the brown corundum of granularity 1~0mm,
955~8 parts of the SiC of granularity 1~0mm,
95 10~15 parts of granularity 325 purpose SiC,
3~8 parts of granularity 325 purpose fused white corundums,
2~4 parts of the hard pitches of granularity 0.5mm,
2~4 parts of silicon powders,
2~4 parts of raw claies,
97 2~3 parts of Pure Silicon Metals,
0.05~0.15 part of polypropylene fibre,
0.5~1 part of activated magnesia,
2~5 parts of industrial phosphoric acid solution,
5~8 parts in resol.
Purpose of the present invention two for providing a kind of 500 cubic metres of volumes of being used for to exempt to toast iron runner castable with what the iron notch blast furnace iron runner that places an order was made lining, composed of the following components:
18~25 parts of the alumines of granularity 8~5mm,
10~18 parts of the alumines of granularity 5~3mm,
15~25 parts of the alumines of granularity 3~1mm,
3~9 parts of the alumines of granularity 1~0mm,
5~8 parts of the SiC90 of granularity 1~0mm,
10~15 parts of granularity 325 purpose SiC90,
3~8 parts in granularity 325 purposes palm fibre corundum,
2~4 parts of the hard pitches of granularity 0.5mm,
2~4 parts of silicon powders,
2~4 parts of raw claies,
972~3 parts of Pure Silicon Metals,
0.05~0.15 part of polypropylene fibre,
0.5~1 part of activated magnesia,
2~5 parts of industrial phosphoric acid solution,
5~8 parts in resol.
Purpose of the present invention three for a kind of processing method that single iron notch blast furnace iron outlet groove is made lining that is used for is provided, for the blast furnace that has only an iron notch, adopt and exempt to toast the casting house liner that blast furnace was constructed or repaired to mould material, as follows in steps; At first the bottom of trench residue is cleaned out; Propped up mould in advance; Exempting from of to stirring then toasted the iron runner castable mortar and is distributed in the mould; Smash mould material with the shake of insert vibrating head again, bubble is fully closely knit to mould material in the discharge mould material.
The particular content of technical solution of the present invention is, selecting corundum or high-alumina refractory aggregate for use is aggregate, SiC, fused white corundum powder, raw clay, hard pitch powder, metal Si powder are powder, with anhydrous low viscosity resol and industrial phosphoric acid solution is mobility donor, do stiffening agent with active magnesia powder, preparation can be used in cast-in-site and need not long-time baking can be by the refractory castable of molten iron.Exempt to toast mould material to 1000m with this 3Serve as a contrast or repair with integrated poured the making of the casting house of the iron mouth blast furnace that places an order.
Preceding 13 kinds of material mixing in the above-mentioned batching evenly become Preblend standby, during use the industrial phosphoric acid solution of Preblend and the 14th and 15 indication and resol are mixed into mortar and pour into a mould.
Adopt and above-mentionedly exempt to toast iron runner castable to carry out the technology that single iron mouth blast furnace iron outlet groove makes lining as follows:
Iron runner is made lining or is repaired, and can be arranged in twice pitch time of tapping a blast furnace to implement, and also can be arranged in the special maintenance downtime and construct.
Iron runner ditch type profile figure as shown in Figure 1.1 is template among Fig. 1, the 2nd, exempt to toast castable in main trough, and the 3rd, bottom of trench permanent layer refractory brick.
During the iron runner casting and constructing, at first the bottom of trench residue is cleaned out; Propped up mould (wooden model or punching block, the template inwall should be brushed machine oil in advance so that the demoulding) in advance, then the mortar that stirs has been distributed in the mould, smash mould material with the shake of insert vibrating head again, bubble is fully closely knit to mould material in the discharge mould material.Iron runner bottom of trench and ditch outer leaf thickness arrange that according to on-site actual situations general bottom of trench cast thickness is 400~550mm, and the furrow bank gauge control is more than 300mm.
Behind the casting, under the effect of iron runner waste heat, or under the effect of solidifying agent, mould material was promptly hardened through very short time (in 1 hour), got final product the demoulding this moment.
Substantially there is not moisture in the lining because newly make, so do not need baking can directly lead to iron (cold ditch is made lining or ditch lining when thicker, if conditions permit can be considered to carry out the suitable short period of time and be toasted).
Employing exempts to toast iron runner castable, and to carry out the technology that single iron mouth blast furnace iron outlet groove repairs as follows:
Repair the position particular case as required, can select the formwork cover to water and repair or manually smear (ramming) repairing.
Cover waters method for repairing and mending and tap drain and makes that to serve as a contrast technology similar, as shown in Figure 2.1 is mould among Fig. 2, the 2nd, and the residual lining of iron runner, the 3rd, be bottom of trench permanent layer refractory brick.The filled with mortar that stirs between the residual lining, is smash mould material with the shake of insert vibrating head again in mould and ditch, bubble is fully closely knit to mould material in the discharge mould material.Behind the casting, under the effect of the residual lining waste heat of iron runner, or under the effect of solidifying agent, mould material was promptly hardened through very short time (in 1 hour), and get final product the demoulding this moment, and the iron runner after the demoulding can come into operation immediately.
If iron runner is local damage, need the scope of repairing less, can adopt above-mentioned mould material, the method that employing is manually smeared or spade is patted is carried out sectional repair, does not need to use mould.The iron runner of repairing after neat can come into operation immediately.
The invention has the advantages that:
1, according to environment for use (furnace volume size) requirement, material batching material can be adjusted;
2, mould material cast back is under the effect of stiffening agent, very soon can self-hardening;
3, mould material can be hardened under the effect of iron runner waste heat faster;
4, the mould material after the sclerosis does not need just can directly cross molten iron through special baking;
5, mould material does not need special baking, has shortened the time that iron runner is made lining or repaired greatly, thereby has made to have only the medium and small blast furnace iron runner of an iron notch can use mould material to construct the iron runner liner;
6, owing to adopt the casting construction to make lining, constructed ditch lining is all very fine and close from the surface to inside, does not exist ramming mass to have only the closely knit and inner loose problem in surface, so iron runner can prolong work-ing life significantly, and can reach 3~6 months work-ing life;
7, because the ditch that mould material is constructed serves as a contrast the ditch lining of constructing much larger than ramming mass work-ing life, so the labour intensity of stokehold workman's maintenance service reduces significantly.
8, because the ditch that mould material is constructed serves as a contrast the ditch lining of constructing much larger than ramming mass work-ing life, therefore the iron runner materials consumption of unit iron output also reduces significantly, not only bring the raising of economic benefit, also have resources conservation and the benefit that reduces waste residue on the environment protection significance.
Description of drawings
Fig. 1 is a synoptic diagram of the present invention.
Fig. 2 is a synoptic diagram of the present invention.
The present invention is further described below in conjunction with drawings and Examples.
Embodiment
Embodiment one
For volume at 500m 3~1000m 3Between blast furnace, the material mixture ratio that is used for tap drain cast is as follows:
Figure C20061008692500101
Preceding 13 kinds of material mixing in the above-mentioned batching evenly become Preblend standby, during use the industrial phosphoric acid solution of Preblend and the 14th and 15 indication and resol are mixed into mortar and pour into a mould.
Employing is exempted to toast iron runner castable and is carried out iron runner to make the technology of lining as follows:
Iron runner ditch type profile figure as shown in Figure 1.1 is template among Fig. 1, the 2nd, exempt to toast castable in main trough, and the 3rd, bottom of trench permanent layer refractory brick.
During the iron runner casting and constructing, at first the bottom of trench residue is cleaned out; Propped up mould (wooden model or punching block, the template inwall should be brushed machine oil in advance so that the demoulding) in advance, then the mortar that stirs has been distributed in the mould, smash mould material with the shake of insert vibrating head again, bubble is fully closely knit to mould material in the discharge mould material.Iron runner bottom of trench and ditch outer leaf thickness arrange that according to on-site actual situations general bottom of trench cast thickness is 400~550mm, and the furrow bank gauge control is more than 300mm.
Behind the casting, under the effect of iron runner waste heat, or under the effect of solidifying agent, mould material was promptly hardened through very short time (in 1 hour), got final product the demoulding this moment.
Substantially there is not moisture in the lining because newly make, so do not need baking can directly lead to iron (cold ditch is made lining or ditch lining when thicker, if conditions permit can be considered to carry out the suitable short period of time and be toasted).
Employing exempts to toast iron runner castable, and to carry out the technology that iron runner repairs as follows:
Repair the position particular case as required, can select the formwork cover to water and repair or manually smear (ramming) repairing.
Cover waters method for repairing and mending and tap drain and makes that to serve as a contrast technology similar, as shown in Figure 2.1 is mould among Fig. 2, the 2nd, and the residual lining of iron runner, the 3rd, be bottom of trench permanent layer refractory brick.The filled with mortar that stirs between the residual lining, is smash mould material with the shake of insert vibrating head again in mould and ditch, bubble is fully closely knit to mould material in the discharge mould material.Behind the casting, under the effect of the residual lining waste heat of iron runner, or under the effect of solidifying agent, mould material was promptly hardened through very short time (in 1 hour), and get final product the demoulding this moment, and the iron runner after the demoulding can come into operation immediately.
If iron runner is local damage, need the scope of repairing less, can adopt above-mentioned mould material, the method that employing is manually smeared or spade is patted is carried out sectional repair, does not need to use mould.The iron runner of repairing after neat can come into operation immediately.
Embodiment two
For furnace volume at 500m 3Following blast furnace, the material mixture ratio that is used for the tap drain cast is as follows:
Figure C20061008692500111
Preceding 13 kinds of material mixing in the above-mentioned batching evenly become Preblend standby, during use the industrial phosphoric acid solution of Preblend and the 14th and 15 indication and resol are mixed into mortar and pour into a mould.
Employing is exempted to toast iron runner castable and is carried out iron runner to make the technology of lining as follows:
Iron runner ditch type profile figure as shown in Figure 1.1 is template among Fig. 1, the 2nd, exempt to toast castable in main trough, and the 3rd, bottom of trench permanent layer refractory brick.
During the iron runner casting and constructing, at first the bottom of trench residue is cleaned out; Propped up mould (wooden model or punching block, the template inwall should be brushed machine oil in advance so that the demoulding) in advance, then the mortar that stirs has been distributed in the mould, smash mould material with the shake of insert vibrating head again, bubble is fully closely knit to mould material in the discharge mould material.Iron runner bottom of trench and ditch outer leaf thickness arrange that according to on-site actual situations general bottom of trench cast thickness is 400~550mm, and the furrow bank gauge control is more than 300mm.
Behind the casting, under the effect of iron runner waste heat, or under the effect of solidifying agent, mould material was promptly hardened through very short time (in 1 hour), got final product the demoulding this moment.
Substantially there is not moisture in the lining because newly make, so do not need baking can directly lead to iron (cold ditch is made lining or ditch lining when thicker, if conditions permit can be considered to carry out the suitable short period of time and be toasted).
Employing exempts to toast iron runner castable, and to carry out the technology that iron runner repairs as follows:
Repair the position particular case as required, can select the formwork cover to water and repair or manually smear (ramming) repairing.
Cover waters method for repairing and mending and tap drain and makes that to serve as a contrast technology similar, as shown in Figure 2.1 is mould among Fig. 2, the 2nd, and the residual lining of iron runner, the 3rd, be bottom of trench permanent layer refractory brick.The filled with mortar that stirs between the residual lining, is smash mould material with the shake of insert vibrating head again in mould and ditch, bubble is fully closely knit to mould material in the discharge mould material.Behind the casting, under the effect of the residual lining waste heat of iron runner, or under the effect of solidifying agent, mould material was promptly hardened through very short time (in 1 hour), and get final product the demoulding this moment, and the iron runner after the demoulding can come into operation immediately.
If iron runner is local damage, need the scope of repairing less, can adopt above-mentioned mould material, the method that employing is manually smeared or spade is patted is carried out sectional repair, does not need to use mould.The iron runner of repairing after neat can come into operation immediately.

Claims (7)

1. one kind is used for volume 500 and exempts to toast iron runner castable with what the iron notch blast furnace iron runner that places an order was made lining for above 1000 cubic metres, it is characterized in that composed of the following components:
18~25 parts in the brown corundum of granularity 8~5mm,
10~18 parts in the brown corundum of granularity 5~3mm,
15~25 parts in the brown corundum of granularity 3~1mm,
3~9 parts in the brown corundum of granularity 1~0mm,
5~8 parts of the SiC95 of granularity 1~0mm,
10~15 parts of granularity 325 purpose SiC95,
3~8 parts of granularity 325 purpose fused white corundums,
2~4 parts of the hard pitches of granularity 0.5mm,
2~4 parts of silicon powders,
2~4 parts of raw claies,
97 2~3 parts of Pure Silicon Metals,
0.05~0.15 part of polypropylene fibre,
0.5~1 part of activated magnesia,
2~5 parts of industrial phosphoric acid solution,
5~8 parts in resol.
2. one kind is used for volume 500m 3Exempt to toast iron runner castable with what the iron notch blast furnace iron runner that places an order was made lining, it is characterized in that composed of the following components:
18~25 parts of the alumines of granularity 8~5mm,
10~18 parts of the alumines of granularity 5~3mm,
15~25 parts of the alumines of granularity 3~1mm,
3~9 parts of the alumines of granularity 1~0mm,
5~8 parts of the SiC90 of granularity 1~0mm,
10~15 parts of granularity 325 purpose SiC90,
3~8 parts in granularity 325 purposes palm fibre corundum,
2~4 parts of the hard pitches of granularity 0.5mm,
2~4 parts of silicon powders,
2~4 parts of raw claies,
97 2~3 parts of Pure Silicon Metals,
0.05~0.15 part of polypropylene fibre,
0.5~1 part of activated magnesia,
2~5 parts of industrial phosphoric acid solution,
5~8 parts in resol.
3. according to claim 1 and 2ly exempt to dry by the fire the roasting mould material of iron runner, it is characterized in that: industrial phosphoric acid in the said components and resol are the used wedding agent of mould material, this has guaranteed that mould material is when having flowability, basic moisture-free in the material, thereby guarantee that constructed iron runner ditch lining can exempt baking coming into operation before, directly the mistake molten iron.
4. one of a use such as above-mentioned claim are described exempts to toast iron runner castable and is used for the processing method that single iron notch blast furnace iron outlet groove is made lining, it is characterized in that: for the blast furnace that has only an iron notch, adopt the above-mentioned casting house liner of exempting to toast iron runner castable cast blast furnace, as follows in steps; At first the bottom of trench residue is cleaned out; Propped up mould in advance; Exempting from of to stirring then toasted the iron runner castable mortar and is distributed in the mould; Smash mould material with the shake of insert vibrating head again, bubble is fully closely knit to mould material in the discharge mould material.
5. blast furnace iron outlet groove according to claim 4 is made the processing method of lining, it is characterized in that: exempt to toast iron runner castable when employing and carry out iron runner when repairing, adopt the cover that keeps residual lining to water method, or the method that employing is manually smeared or spade is patted is carried out sectional repair and is not needed to use mould.
6. make the processing method of lining according to claim 4 or 5 described blast furnace iron outlet grooves, it is characterized in that: cast newly or the casting house of repairing do not need directly to come into operation through overbaking.
7. make the processing method of lining according to claim 4 or 5 described blast furnace iron outlet grooves, it is characterized in that: have only the iron runner of the blast furnace of an iron notch to make lining or patch work and be arranged in twice pitch time of tapping a blast furnace and implement, or be arranged in the maintenance downtime and construct.
CN200610086925A 2006-06-19 2006-06-19 Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove Active CN100575504C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200610086925A CN100575504C (en) 2006-06-19 2006-06-19 Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200610086925A CN100575504C (en) 2006-06-19 2006-06-19 Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove

Publications (2)

Publication Number Publication Date
CN101092653A CN101092653A (en) 2007-12-26
CN100575504C true CN100575504C (en) 2009-12-30

Family

ID=38991086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200610086925A Active CN100575504C (en) 2006-06-19 2006-06-19 Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove

Country Status (1)

Country Link
CN (1) CN100575504C (en)

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101497930A (en) * 2008-12-05 2009-08-05 北京联合荣大工程材料有限责任公司 Single taphole blast furnace tapping channel iron storing type improving technology
CN102041334B (en) * 2009-10-19 2012-07-18 河南方圆炭素集团有限公司 High-thermal conductivity carbon ramming compound for large blast furnace
CN101693625B (en) * 2009-10-22 2012-05-23 攀枝花学院 Smashing and hitting material for blast furnace iron outlet groove
CN101892337B (en) * 2010-06-22 2011-11-16 武汉威林炉衬材料有限责任公司 Method for maintaining blast furnace taphole
CN102134620B (en) * 2010-10-19 2012-05-23 新兴铸管股份有限公司 Blast furnace shaft upper part rapid heating for producing lining by wet method
CN102091765A (en) * 2010-12-24 2011-06-15 高平市泫氏铸管有限公司 Novel fall slot
CN102757242A (en) * 2011-04-26 2012-10-31 三和耐火工业股份有限公司 Casting material used for repairing blast furnace main runner
CN102351465A (en) * 2011-07-22 2012-02-15 郑州京华耐火材料实业有限公司 Cooling wall inlaying material
CN102531655B (en) * 2012-03-06 2013-07-10 长兴煤山新型炉料有限公司 ASC self-flow main channel castable
CN102531654B (en) * 2012-03-06 2013-07-10 长兴煤山新型炉料有限公司 Aluminum nitrogen demanganization swing spout castable
CN102601329B (en) * 2012-03-19 2013-07-10 鞍山市星火特种耐火材料有限公司 Novel composite current stabilizer and manufacturing method of the novel composite current stabilizer
CN102672154B (en) * 2012-04-17 2014-01-15 莱芜钢铁集团有限公司 Continuous-casting tundish comprehensive permanent liner and preparation method thereof
CN103482987A (en) * 2012-06-14 2014-01-01 天津振普筑炉衬里工程有限公司 Wear resistance casting material for ladle
CN102839247A (en) * 2012-09-27 2012-12-26 鞍钢股份有限公司 Method for improving service life of iron-storage main iron runner
CN103553654B (en) * 2013-10-14 2014-12-10 上海利尔耐火材料有限公司 Al2O3-Si2N2O-C castable for blast furnace iron tap channel and preparation method thereof
CN105174980B (en) * 2015-08-24 2018-09-07 武汉科技大学 A kind of blast furnace iron tap channel refractory pour material and preparation method thereof
CN107445629A (en) * 2017-08-31 2017-12-08 云南濮耐昆钢高温材料有限公司 A kind of environment-friendly type composite dry material bonding agent and its application method
CN109252007A (en) * 2018-11-19 2019-01-22 云南玉溪仙福钢铁(集团)有限公司 A kind of blast furnace iron storage type major groove
CN110195137A (en) * 2019-05-14 2019-09-03 鞍钢股份有限公司 A kind of new masonry iron mouth pore passage preparation method
CN111302776A (en) * 2020-04-26 2020-06-19 河南兴亚能源有限公司 Oxide coating modified homogenized alumina castable and preparation method thereof
CN112174682A (en) * 2020-10-10 2021-01-05 鞍钢股份有限公司 Baking-free self-hardening tundish working lining repairing material and using method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
添加氧化镁对Al2O3-SiC-C浇注料的影响. 冯艳,译.国外耐火材料,第1999年第2期. 1999
添加氧化镁对Al2O3-SiC-C浇注料的影响. 冯艳,译.国外耐火材料,第1999年第2期. 1999 *

Also Published As

Publication number Publication date
CN101092653A (en) 2007-12-26

Similar Documents

Publication Publication Date Title
CN100575504C (en) Iron runner exempts to toast mould material and lining technology is made in the cast of single iron mouth blast furnace iron outlet groove
CN101497930A (en) Single taphole blast furnace tapping channel iron storing type improving technology
CN102491765B (en) Main ditch self-flowing anti-blowout pour material of main channel and construction method thereof
CN100389911C (en) Casing patch method for ladle brickwork neck bush
CN106083110B (en) High strength steel ladle-lining castable
CN100519771C (en) Ladle lining structure and slag preventing paint
CN101723689A (en) Baking -free castable and method for making tapping hole by using same
CN108503373A (en) Blast furnace taphole reparation castable refractory
CN101693624A (en) Fireproof material for blast furnace iron outlet
CN101700572B (en) Method for building container bottom of carbon-containing molten steel container
CN104493150B (en) A kind of alumina-silica drainage agent and preparation method thereof
CN102249698A (en) Blast furnace cooling wall laying brick
CN104193370B (en) A kind of preparation method of ladle carbon free precast block
CN102898151A (en) Iron-storage type casting material for iron tapping channel, and preparation method thereof
CN105195723A (en) Repairing method for steel ladle wall permanent layer
CN103011858B (en) Stemming for blast furnace tap hole
CN1821178A (en) Method for preparing middle ladle dry vabrative material
CN104529485B (en) Two-layer compound refractory material and two-layer compound refractory material ditch cover and its manufacture method and application
CN104193353B (en) A kind of plate diamond spar matter stuffing sand and preparation method thereof
CN100519483C (en) Iron outlet channel and method for preparing the same
CN104829242A (en) Preparation method of tertiary air duct curve prefabricated component used for cement kiln
CN109439825B (en) Method for prolonging service life of blast furnace main channel
CN107010965A (en) Fast gravity die blast furnace crucibe repairing material and preparation method thereof
CN201367433Y (en) Single iron notch blast furnace iron storage type iron runner
CN106345990A (en) Preparation method of composite intermediate wall for continuous casting tundish

Legal Events

Date Code Title Description
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Zhang Ronghui

Document name: Correction notice

C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20081219

Address after: Beijing, Huairou District, North Housing Development Zone, No. 9, Liuzhou Road, zip code: 101400

Applicant after: Beijing United Rong Da Engineering Material Technology Research Institute Co Ltd

Address before: Room 1006, building 15, sun garden, Beijing, Haidian District: 101400

Applicant before: Zhang Ronghui

ASS Succession or assignment of patent right

Owner name: BEIJING UNITED RONGDA ENGINEERING MATERIALS TECHNO

Free format text: FORMER OWNER: ZHANG RONGHUI

Effective date: 20081219

ASS Succession or assignment of patent right

Owner name: BEIJING LIANHERONGDA ENGINNERING MATERIAL CO.,LTD.

Free format text: FORMER OWNER: BEIJING UNITED RONGDA ENGINEERING MATERIALS TECHNOLOGY INSTITUTE CO., LTD.

Effective date: 20090508

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090508

Address after: Beijing, Huairou District, North Housing Development Zone, No. 9, Liuzhou Road, zip code: 101400

Applicant after: Beijing Allied Rongda Engineering Material Co., Ltd.

Address before: Beijing, Huairou District, North Housing Development Zone, No. 9, Liuzhou Road, zip code: 101400

Applicant before: Beijing United Rong Da Engineering Material Technology Research Institute Co Ltd

C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Nanjing United Rongda Engineering Material Co., Ltd.

Assignor: Beijing Allied Rongda Engineering Material Co., Ltd.

Contract record no.: 2011320000833

Denomination of invention: Liner making technique for casting lander of blast furnace with single iron notch, and free from baking casting material for iron notch

Granted publication date: 20091230

License type: Exclusive License

Open date: 20071226

Record date: 20110614

C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 101400, No. 9, Long Yun Road, Jingwei Industrial Zone, North Housing Town, Huairou District, Beijing

Patentee after: Beijing United Rong Da engineering materials Limited by Share Ltd

Address before: 101400, No. 9, Long Yun Road, North Housing Development Zone, Huairou District, Beijing

Patentee before: Beijing Allied Rongda Engineering Material Co., Ltd.