CN100564697C - 水平顶管地基处理工法 - Google Patents

水平顶管地基处理工法 Download PDF

Info

Publication number
CN100564697C
CN100564697C CNB2008100478520A CN200810047852A CN100564697C CN 100564697 C CN100564697 C CN 100564697C CN B2008100478520 A CNB2008100478520 A CN B2008100478520A CN 200810047852 A CN200810047852 A CN 200810047852A CN 100564697 C CN100564697 C CN 100564697C
Authority
CN
China
Prior art keywords
foundation
push pipe
pipe
soil
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2008100478520A
Other languages
English (en)
Other versions
CN101280565A (zh
Inventor
刘术湘
吴晓云
罗晓辉
赵建海
万凯军
李大毛
万讯平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Original Assignee
CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co filed Critical CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING Co
Priority to CNB2008100478520A priority Critical patent/CN100564697C/zh
Publication of CN101280565A publication Critical patent/CN101280565A/zh
Application granted granted Critical
Publication of CN100564697C publication Critical patent/CN100564697C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

一种水平顶管地基处理工法,采用挖井、确定顶管顶进点及顶管轴线、装导轨、选择油缸、注浆、检测……。优点是:当上部结构已施工完毕,周边建筑物密集而不具备施工场地条件时,采用水平顶管工法可避免上述不足,该工法在已有建筑物基础下植入具有高变形模量的钢管形成水平增强体,利用地基土与拉筋(钢管)产生的摩擦力使土与加筋材料形成整体,减小整体变形和增强整体稳定,同时两端悬挑部分可扩大建筑物基础面积,减小基底附加压力;通过植入的花管向周围地基土中进行压力注浆形成复合地基,提高地基土承载能力,减小地基土压缩变形,达到改良基底下地基土性能的目的。

Description

水平顶管地基处理工法
技术领域
本发明涉及建筑施工技术领域,具体地说是一种水平顶管地基处理工法。
背景技术
目前,建筑物对基础沉降的要求越来越严格,特别是当上部结构施工完毕或者在使用过程中发生不均匀沉降或沉降过大,需进行地基处理,而现在常用的采用竖向受压的各种构件来提高基础的承载能力,如钢管静压桩、锚杆静压桩、灌注桩、树根桩等拖换方法,受场地条件限制时,不适宜采用常规方法进行处理。
发明内容
本发明的目的是研制一种针对建筑物基础不均匀沉降或过大沉降问题,在不适宜采用常规方法处理时,而采用融合顶管及土合成材料加筋、注浆法在基础下部空间形成一个空间支架扩大基础面积并有效改良地基土,预防并控制地面沉陷的水平顶管地基处理工法。
本发明水平顶管地基处理工法,包括:
1)根据周边构筑物的影响和最小施工长度开挖工作井;
2)根据设计水平顶管轴线位置确定顶管顶进点及顶管轴线;
3)根据不同边界条件选用库仑土压力理论中被动土压力计算相关公式计算所需被动土压力确定反力后背,要求后背反力大于顶管顶力;
4)安装导轨;
5)根据工程条件选择合适的油缸(主要参数为顶力、行程);顶管顶力可按《给水排水管道工程施工及验收规范》(GB50268-97)6.4.8公式确定;在适应工作井尺寸的情况下宜选用大行程油缸;
6)安装顶铁;
7)顶进--采用半闭口钢管挤密土层法顶管;
8)在顶进过程中加强测量、纠偏(纠偏原则:增加纠偏次数,减小纠偏角度);
9)注浆(主要参数为流量、压力和注浆量)--一般以不使地层结构破坏或仅发生局部的少量的破坏作为确定地基土容许注浆压力的基本原则,其具体参数值应在施工前通过现场试验确定,并在施工时根据地面变形的量测资料调整;
10)沉降监测与顶管注浆质量检测--监测对象主要是整个基础平台,方法有使用贴纸法或全站仪测量等手段,直接对监测实体进行宏观监测。注浆效果可通过管内取芯,从注浆体内取出原状样品,测定样品的密度、浆液充填率、剩余孔隙率、无侧限抗压强度、抗剪强度、渗透性及长期渗流稳定性等指标来检测效果;顶管质量检测主要通过低应变波速测定;
11)沉降计算分析--根据《建筑地基基础设计规范》(GB50007-2002)第5.3节估算处理前后天然基础沉降量,进行加固效果的比较分析。若存在动力设备基础则需按《动力机器基础设计规范》(GB50040-96)中有关章节进行基础振动状态下的沉降估算。
顶管法以往作为一种地下非开挖管道技术,管道既是掘进空间的支护,又是构筑物的本身,它将明挖改为暗挖是起特点。以水平顶管法为手段进行地基处理,充分发挥管道的力学性能,让水平管道和其周边被改良后的土体承受上部竖向荷载的水平顶管地基处理工法。
本发明水平顶管地基处理工法的优点是:当上部结构已施工完毕,周边建筑物密集而不具备施工场地条件时,采用水平顶管工法可避免上述不足,该工法在已有建筑物基础下植入具有高变形模量的钢管形成水平增强体,利用地基土与拉筋(钢管)产生的摩擦力使土与加筋材料形成整体,减小整体变形和增强整体稳定,同时两端悬挑部分可扩大建筑物基础面积,减小基底附加压力;通过植入的花管向周围地基土中进行压力注浆形成复合地基,提高地基土承载能力,减小地基土压缩变形,达到改良基底下地基土性能的目的。
具体实施方式
本发明水平顶管地基处理工法,包括:
1)根据周边构筑物的影响和最小施工长度开挖工作井;
2)根据设计水平顶管轴线位置确定顶管顶进点及顶管轴线;
3)根据不同边界条件选用库伦土压力理论中被动土压力计算公式计算所需被动土压力确定反力后背,要求后背反力大于顶管顶力;
4)安装导轨;
5)根据工程条件选择合适的油缸(主要参数为顶力、行程);顶管顶力可按《给水排水管道工程施工及验收规范》(GB50268-97)6.4.8公式确定;在适应工作井尺寸的情况下宜选用大行程油缸;
6)安装顶铁;
7)顶进--采用半闭口钢管挤密土层法顶管;
8)在顶进过程中加强测量、纠偏(纠偏原则:增加纠偏次数,减小纠偏角度);
9)注浆(主要参数为流量、压力和注浆量)--一般以不使地层结构破坏或仅发生局部的少量的破坏作为确定地基土容许注浆压力的基本原则;其具体参数值应在施工前通过现场试验确定,并在施工时根据地面变形的量测资料调整;
10)沉降监测与顶管注浆质量检测--监测对象主要是整个基础平台,方法有使用贴纸法或全站仪测量等手段,直接对监测实体进行宏观监测。注浆效果可通过管内取芯,从注浆体内取出原状样品,测定样品的密度、浆液充填率、剩余孔隙率、无侧限抗压强度、抗剪强度、渗透性及长期渗流稳定性等指标来检测效果;顶管质量检测主要通过低应变波速测定;
11)沉降计算分析--根据《建筑地基基础设计规范》(GB50007-2002)第5.3节估算处理前后天然基础沉降量,进行加固效果的比较分析。若存在动力设备基础则需按《动力机器基础设计规范》(GB50040-96)中有关章节进行基础振动状态下的沉降估算。

Claims (1)

1、一种水平顶管地基处理工法,其特征在于:包括:
1)根据周边构筑物的影响和最小施工长度开挖工作井;
2)根据设计水平顶管轴线位置确定顶管顶进点及顶管轴线;
3)根据不同边界条件选用库仑土压力理论中被动土压力计算公式计算所需被动土压力确定反力后背,要求后背反力大于顶管顶力;
4)安装导轨;
5)根据工程条件选择合适的油缸,其主要参数为顶力、行程;顶管顶力可按《给水排水管道工程施工及验收规范》(GB50268-97)6.4.8公式确定;在适应工作井尺寸的情况下宜选用大行程油缸;
6)安装顶铁;
7)顶进--采用半闭口钢管挤密土层法顶进;
8)在顶进过程中加强测量、纠偏,其纠偏原则:增加纠偏次数,减小纠偏角度;
9)注浆,其主要参数为流量、压力和注浆量;一般以不使地层结构破坏或仅发生局部的少量的破坏作为确定地基土容许注浆压力的基本原则;其具体参数值应在施工前通过现场试验确定,并在施工时根据地面变形的量测资料调整;
10)沉降监测与顶管注浆质量检测--监测对象主要是整个基础平台,方法有使用贴纸法或全站仪测量手段,直接对监测实体进行宏观监测,注浆效果是通过管内取芯,从注浆体内取出原状样品,测定样品的密度、浆液充填率、剩余孔隙率、无侧限抗压强度、抗剪强度、渗透性及长期渗流稳定性指标来检测效果;顶管质量检测主要通过低应变波速测定;
11)沉降计算分析--根据《建筑地基基础设计规范》(GB50007-2002)第5.3节估算处理前后天然基础沉降量,进行加固效果的比较分析,若存在动力设备基础则需按《动力机器基础设计规范》(GB50040-96)中有关章节进行基础振动状态下的沉降估算。
CNB2008100478520A 2008-05-28 2008-05-28 水平顶管地基处理工法 Active CN100564697C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2008100478520A CN100564697C (zh) 2008-05-28 2008-05-28 水平顶管地基处理工法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2008100478520A CN100564697C (zh) 2008-05-28 2008-05-28 水平顶管地基处理工法

Publications (2)

Publication Number Publication Date
CN101280565A CN101280565A (zh) 2008-10-08
CN100564697C true CN100564697C (zh) 2009-12-02

Family

ID=40013221

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2008100478520A Active CN100564697C (zh) 2008-05-28 2008-05-28 水平顶管地基处理工法

Country Status (1)

Country Link
CN (1) CN100564697C (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104215748B (zh) * 2014-08-19 2015-04-22 山东大学 一种地下工程破碎围岩注浆加固效果的综合定量检测方法
CN104455726A (zh) * 2014-11-20 2015-03-25 广州市市政集团有限公司 一种管道底部注浆加固的顶管施工方法
CN106703063B (zh) * 2016-12-13 2017-08-25 中国地质大学(武汉) 一种加固软土地层中桩基础的顶管施工方法
CN115095353B (zh) * 2022-07-08 2023-08-15 山东建筑大学 一种利用注浆顶升既有结构的沉降控制设计方法

Non-Patent Citations (10)

* Cited by examiner, † Cited by third party
Title
大口径顶管工程的施工. 张庆华.广东建材,第4期. 2006
大口径顶管工程的施工. 张庆华.广东建材,第4期. 2006 *
浅议顶管施工技术及在某工程中的应用. 莫筠,刘勇.山西建筑,第33卷第5期. 2007
浅议顶管施工技术及在某工程中的应用. 莫筠,刘勇.山西建筑,第33卷第5期. 2007 *
软土地基顶管施工的关键问题. 王芳.施工技术,第35卷第S2期. 2006
软土地基顶管施工的关键问题. 王芳.施工技术,第35卷第S2期. 2006 *
顶管施工技术. 周民强.甘肃水利水电技术,第41卷第1期. 2005
顶管施工技术. 潘波.科学之友(B版),第5期. 2007
顶管施工技术. 周民强.甘肃水利水电技术,第41卷第1期. 2005 *
顶管施工技术. 潘波.科学之友(B版),第5期. 2007 *

Also Published As

Publication number Publication date
CN101280565A (zh) 2008-10-08

Similar Documents

Publication Publication Date Title
Tan et al. Measured performance of a 26 m deep top-down excavation in downtown Shanghai
Schweiger et al. Numerical modelling of settlement compensation by means of fracture grouting
CN204491626U (zh) 拉森钢板桩与预应力锚杆组合的基坑围护结构
CN204199335U (zh) 一种减小phc管桩施工挤土效应的泄压井
CN102635113A (zh) 一种液压振动沉管灌注桩施工方法
CN105953078B (zh) 高压燃气管道的保护装置及保护方法
AU2020100838A4 (en) A kind of stress adjustment system for side walls of foundation pit in deep and unstable strata
Fan et al. Water pressure evolution and structural failure characteristics of tunnel lining under hydrodynamic pressure
CN110438999A (zh) 一种地下水丰富的深基坑放坡开挖施工方法
CN100564697C (zh) 水平顶管地基处理工法
Xu et al. Shanghai center project excavation induced ground surface movements and deformations
Hung et al. Practice and experience in deep excavations in soft soil of Ho Chi Minh City, Vietnam
CN102134861B (zh) 土体内预制桩试桩方法
CN104652411B (zh) 一种基于砂性土的强化预处理加强夯的复合地基处理方法
Long et al. Retaining walls in dublin boulder clay, Ireland
CN102817349B (zh) 精细强夯置换加固软土地基的方法
Shi et al. Ground surface settlement caused by foundation pit excavation and dewatering.
CN207109805U (zh) 一种隧道侧穿桥桩的复合隔离桩
CN105178331A (zh) 深基坑及超深基坑桩锚支护方法
CN106337418A (zh) 一种狭小区域深基坑的支护结构及支护方法
Tang et al. Experimental study on the mechanical and deformation properties of pipe and soil in rectangular pipe jacking construction with controllable cement grouting technology
CN113221418B (zh) 一种修正的Tschebotarioff土压力模型
Jia et al. Research and design on top-down method for large scale podium basement excavation of Shanghai Tower
Jin-Wei et al. Deformation monitoring and numerical simulation of retaining structure in subway station deep foundation pit
TW463011B (en) Ground base modification: horizontal compaction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: WUHAN SURVEYING-GEOTECHNICAL RESEARCH INSTITUTE OF

Free format text: FORMER OWNER: CHINA METALLURGY GROUP WUKAN GROUND FOUNDATIONAL ENGINEERING COMPANY

Effective date: 20110920

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20110920

Address after: 430080 Wuhan, Heilongjiang Province, Qingshan District, metallurgical Road, No. 177, No.

Patentee after: Wuhan Surveying-Geotechnical Research Institute of China Metallurgical Science and Industry Group Co

Address before: 430080 Wuhan, Heilongjiang Province, Qingshan District, metallurgical Road, No. 177, No.

Patentee before: China Metallurgy Group Wukan Ground Foundational Engineering Company