CN100522793C - Installing method of portal crane - Google Patents

Installing method of portal crane Download PDF

Info

Publication number
CN100522793C
CN100522793C CNB2005100244863A CN200510024486A CN100522793C CN 100522793 C CN100522793 C CN 100522793C CN B2005100244863 A CNB2005100244863 A CN B2005100244863A CN 200510024486 A CN200510024486 A CN 200510024486A CN 100522793 C CN100522793 C CN 100522793C
Authority
CN
China
Prior art keywords
leg
crossbeam
lifting
installation
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2005100244863A
Other languages
Chinese (zh)
Other versions
CN1833988A (en
Inventor
卞永明
周贤周
秦利升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CNB2005100244863A priority Critical patent/CN100522793C/en
Publication of CN1833988A publication Critical patent/CN1833988A/en
Application granted granted Critical
Publication of CN100522793C publication Critical patent/CN100522793C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种门式起重机的安装方法,在整体提升钢结构大梁的过程中,刚性腿和柔性腿随着大梁的提升一起提升到位,实现整台门式起重机一次成形,安全、快捷、可靠。主梁现场拼接,同时将上小车和维修吊吊装在大梁上,然后竖立提升塔架,利用先进的液压同步提升技术提升大梁,刚性腿分段安装,柔性腿结构随大梁提升而自然就位。在大梁提升到位以后,完成刚性腿行走机构和柔性腿两根管腿的安装,最后完成整台龙门吊结构的安装。本发明使用两副提升塔架,缆风调整减少,安全可靠;刚性腿和柔性腿随着大梁的提升而逐渐到位,减少了单独安装刚性腿和柔性腿的工作量;使用提升油缸张拉塔架缆风,缆风受力准确,调整方便。

Figure 200510024486

An installation method of a gantry crane, in the process of overall lifting of a steel structure girder, rigid legs and flexible legs are lifted into place together with the lifting of the girder, realizing the one-time forming of the whole gantry crane, which is safe, fast and reliable. The main girder is spliced on site, and the trolley and maintenance crane are hoisted on the girder at the same time, and then the lifting tower is erected, and the girder is lifted by using advanced hydraulic synchronous lifting technology. The rigid legs are installed in sections, and the flexible leg structure is naturally in place with the lifting of the girder. After the girder is lifted in place, the installation of the two tube legs of the rigid leg walking mechanism and the flexible leg is completed, and finally the installation of the entire gantry crane structure is completed. The invention uses two pairs of lifting towers, the adjustment of the cable wind is reduced, and it is safe and reliable; the rigid legs and flexible legs are gradually in place with the lifting of the girder, which reduces the workload of separately installing the rigid legs and flexible legs; the lifting cylinder is used to stretch the tower The cable wind is installed, the force of the cable wind is accurate, and the adjustment is convenient.

Figure 200510024486

Description

门式起重机的安装方法 Installation method of gantry crane

技术领域 technical field

本发明涉及一种门式起重机的安装方法。The invention relates to a method for installing a gantry crane.

背景技术 Background technique

门式起重机主要用于造船工业中,目前它的安装方法也是各种各样。一般的方法是先将整个刚性腿竖立好,再将大梁提升到位,这种方法在大梁安装时刚性腿的重心很难调整所以安全性差;以前某某厂发生重大工程事故,与其提升方法有很大的关系。Gantry cranes are mainly used in the shipbuilding industry, and they are currently installed in various ways. The general method is to erect the entire rigid leg first, and then lift the girder into place. This method is difficult to adjust the center of gravity of the rigid leg when the girder is installed, so the safety is poor. In the past, a major engineering accident occurred in a certain factory. big relationship.

发明内容 Contents of the invention

本发明的目的在于提供一种新的安装方法,提高门式起重机安装过程的安全性、快捷性和可靠性。The purpose of the present invention is to provide a new installation method to improve the safety, quickness and reliability of the installation process of the gantry crane.

为达上述目的,本发明使用两副“门”字形塔架为提升塔架,钢结构大梁在地面拼装制作,刚性腿分段和柔性腿铰接在大梁上。在整体提升钢结构大梁的过程中,刚性腿和柔性腿随着大梁的提升一起提升到位,实现整台门式起重机一次成形,安全、快捷、可靠。In order to achieve the above-mentioned purpose, the present invention uses two pairs of "door"-shaped towers as lifting towers, the steel structure girders are assembled on the ground, and the rigid legs are segmented and the flexible legs are hinged on the girders. During the overall lifting of the steel structure girder, the rigid legs and flexible legs are lifted into place together with the lifting of the girder, realizing the one-time forming of the entire gantry crane, which is safe, fast and reliable.

本发明的优越性在于:第一,使用两副提升塔架,缆风调整减少,安全可靠;第二,刚性腿和柔性腿随着大梁的提升而逐渐就位,减少了单独安装刚性腿和柔性腿的工作量;第三,使用提升油缸张拉塔架缆风,缆风受力准确,调整方便。The advantages of the present invention are as follows: firstly, two sets of hoisting towers are used, the adjustment of cable wind is reduced, and it is safe and reliable; The workload of the flexible legs; third, use the lifting cylinder to tension the cable wind of the tower, the force of the cable wind is accurate, and the adjustment is convenient.

附图说明 Description of drawings

图1为门式起重机提升系统布置。Figure 1 shows the layout of the lifting system of the gantry crane.

图2为刚性腿安装图。Figure 2 is the rigid leg installation diagram.

图3为柔性腿安装图。Figure 3 is an installation diagram of the flexible legs.

具体实施方式 Detailed ways

结合附图对本发明作进一步描述。请参见图1、2、3所示,本发明由大梁1、刚性腿2、第一铰点3、滑块4、第二铰点5、提升油缸6、塔顶龙门梁7、塔架8、行走机构9、A字头10、第三铰点11、第四铰点12、柔性腿下横梁13、柔性腿14和滑移小车15等组成。The present invention will be further described in conjunction with the accompanying drawings. Please refer to Fig. 1, 2, and 3, the present invention consists of girder 1, rigid leg 2, first hinge point 3, slider 4, second hinge point 5, lifting cylinder 6, tower top gantry beam 7, tower frame 8 , walking mechanism 9, A prefix 10, the third hinge point 11, the fourth hinge point 12, the lower beam 13 of the flexible leg, the flexible leg 14 and the sliding trolley 15 etc. to form.

安装方法:installation method:

一、塔架和塔顶龙门梁的安装1. Installation of the tower frame and the gantry beam on the top of the tower

本发明使用两副塔架8为提升塔架,塔架8的有效高度根据具体门式起重机的不同而有所不同,一般可以高达一百多米,断面4米,钢管格构式结构,塔架8底部与地面基础使用螺栓连接。塔顶龙门梁7为箱型结构。每付塔架的载荷能力达两千多吨。横跨门式起重机大梁1的2根塔架中心距离为十几米,在二根塔架的顶部设有箱型结构的塔顶龙门梁即提升横梁,提升油缸6放置在塔顶龙门梁7上,见图2所示。塔架8和塔顶龙门梁7安装完成之后,使用经纬仪校准塔架的垂直度,满足要求后,用缆风绳把它们固定好,并使用夹头将缆风绳的活头夹紧。The present invention uses two pairs of towers 8 as lifting towers. The effective height of the towers 8 varies according to the specific gantry cranes. Generally, it can be as high as more than 100 meters, with a section of 4 meters. The steel pipe lattice structure, the tower The bottom of the frame 8 is connected with the ground foundation using bolts. The gantry beam 7 on the top of the tower is a box structure. Each pair of towers has a load capacity of more than 2,000 tons. The distance between the centers of the two towers across the girder 1 of the gantry crane is more than ten meters. On the top of the two towers, there is a box-shaped gantry beam at the top of the tower, that is, a lifting beam. The lifting cylinder 6 is placed on the gantry beam 7 at the top of the tower. , as shown in Figure 2. After the tower frame 8 and the tower top gantry beam 7 are installed, use the theodolite to calibrate the verticality of the tower frame. After meeting the requirements, fix them with the cable wind rope, and use the chuck to clamp the live head of the cable wind rope.

二、大梁的提升2. Lifting of the girder

塔架8的塔顶龙门梁7安装完成之后,开始大梁1的提升。第1次提升,提升高度根据具体的情况而定,大约为十米左右时停下,装上刚性腿2上部结构和柔性腿A字头10,校准其水平位置,并将其固定好。第2次提升之前,使用第二铰点5将刚性腿2一端连到大梁1上,刚性腿2的另一端则放置在2辆滑移小车15上。这样,刚性腿2就随大梁1提升自动就位。就位后,校准轴线、用电焊连接。同时,在第2次提升之前,将柔性腿14使用第四铰点12连到A字头10上,这样大梁1到位,柔性腿14自动就位。After the installation of the tower top gantry beam 7 of the tower frame 8 is completed, the lifting of the girder 1 starts. Lifting for the 1st time, the lifting height is determined according to specific conditions, and stops when about ten meters, load onto rigid leg 2 superstructure and flexible leg A word head 10, calibrate its horizontal position, and fix it. Before the second lift, use the second hinge point 5 to connect one end of the rigid leg 2 to the girder 1, and place the other end of the rigid leg 2 on two sliding trolleys 15. In this way, the rigid legs 2 are automatically in place as the girder 1 is lifted. Once in place, calibrate the axis and connect with electric welding. Simultaneously, before lifting for the second time, the flexible leg 14 is connected to the A-head 10 using the fourth hinge point 12, so that the crossbeam 1 is in place, and the flexible leg 14 is automatically in place.

三、刚性腿的安装,见图2。第一步,刚性腿2分段放置预定位置,使用液压千斤顶调整两端上下位置,连接好第二铰点5和第一铰点3。第二步,刚性腿2分段一段随大梁提升而上升,另一端则使用卷扬机牵引,以克服水平摩擦力。第三步,将已组装好的行走机构9慢慢推入刚性腿2的下面。最后,大梁1下降,将分段处接口校准、焊接。3. Installation of rigid legs, see Figure 2. In the first step, the rigid leg 2 is placed at the predetermined position in sections, and the upper and lower positions of both ends are adjusted using a hydraulic jack, and the second hinge point 5 and the first hinge point 3 are connected. In the second step, the two rigid legs rise up with the lifting of the girder, and the other end is pulled by a hoist to overcome the horizontal friction. In the third step, the assembled walking mechanism 9 is slowly pushed under the rigid legs 2 . Finally, the girder 1 is lowered, and the joints at the sections are calibrated and welded.

四、柔性腿的安装,见图3。在龙门吊梁1第一次提升之后,柔性腿的A字头10下端两侧设对称的第四铰点12,两侧各一只。第一步,柔性腿14平放,腿管一端用第四铰点12与A字头10相连,另一端用第三铰点11与行走机构相连。第二步,大梁1提升,柔性腿14自然跟随、在柔性腿行走机构的水平方向上,施加一个水平牵引力,可以减小垂直提升力。第三步,大梁1到位,柔性腿14断口处自然合拢。Fourth, the installation of the flexible legs, see Figure 3. After the gantry suspension beam 1 is lifted for the first time, symmetrical fourth hinge points 12 are arranged on both sides of the lower end of the A-head 10 of the flexible leg, one on each side. In the first step, the flexible legs 14 are placed flat, and one end of the leg pipe is connected with the A-head 10 with the fourth hinge point 12, and the other end is connected with the running mechanism with the third hinge point 11. In the second step, the girder 1 is lifted, and the flexible legs 14 follow naturally. In the horizontal direction of the flexible leg walking mechanism, a horizontal traction force is applied to reduce the vertical lifting force. In the third step, the girder 1 is put in place, and the fracture of the flexible leg 14 is naturally closed.

由于本发明的刚性腿是分段逐步提升,所以很好的解决了重心不稳的问题,再加上使用提升油缸张拉塔架缆风,可以准确的调整和测量缆风的受力问题。本发明经试验,在两台600吨×182米龙门起重机整体提升工程的应用中取得了很大的成功。因此,该方法具有实质的特点和显著的先进性。Since the rigid legs of the present invention are lifted step by step, the problem of unstable center of gravity is well solved. In addition, the lifting cylinder is used to tension the cable wind of the tower, so that the force problem of the cable wind can be accurately adjusted and measured. After testing, the present invention has achieved great success in the application of two 600-ton * 182-meter gantry cranes in the overall lifting project. Therefore, this method has substantial characteristics and remarkable advancement.

Claims (1)

1, a kind of installation method of transfer crane, use two pairs " door " font pylon for promoting pylon, the steel structure crossbeam is made at installation on ground, segmentation of rigidity leg and flexible leg are hinged on the crossbeam, in the process of integrally hoisting steel structure crossbeam, rigidity leg and flexible leg put in place along with the lifting of crossbeam promotes together, it is characterized in that comprising the installation of pylon and cat head gantry beam, the lifting of crossbeam, the installation of rigidity leg and the installation of flexible leg, wherein
The installation of pylon and cat head gantry beam: with two secondary tower framves is to promote pylon, pylon bottom and basis, ground bolt together; The top of every secondary tower frame is provided with the cat head Long Menliang of box-structure, promptly promotes crossbeam, and elevating ram is placed on the beam of cat head gantry; With the squareness of theodolite calibration pylon, with guy steel strand fixed gantry, and with ground tackle that the head-clamp alive of guy steel strand is tight;
The lifting of crossbeam: promote for the first time, stop when promoting about ten meters left and right sides, load onto rigidity leg topside and flexible leg A prefix, the calibrated horizontal position, and fix, before promoting for the second time, with second hinge rigidity leg one end is linked on the crossbeam, the other end of rigidity leg is placed on two slippage dollies, and the rigidity leg promotes autofitting with crossbeam, the calibration axis connects with electric welding; Simultaneously, before promoting for the second time, flexible leg is linked on the A prefix with the 4th hinge;
The installation of rigidity leg: the first step, the desired location is placed in the segmentation of rigidity leg, adjusts the two ends upper-lower position with thousand tops, hydraulic pressure top, connects second hinge and first hinge; In second step, rigidity leg segmentation one end rises with crossbeam, and the other end uses the winch traction, to overcome horizontal friction force; The 3rd step, with the traveling gear that assembles slowly push the rigidity leg below, crossbeam descends, with the calibration of segmentation place interface, welding;
The installation of flexible leg: the first step: after crossbeam promoted for the first time, the 4th hinge that the both sides, A prefix lower end of flexible leg are provided with symmetry was connected with the A prefix, and the other end links to each other with traveling gear with tri-joint mechanism; In second step, crossbeam promotes, and flexible leg is followed naturally, on the horizontal direction of flexible leg walking mechanism, applies a horizontal drag force, with less vertical-lift power; In the 3rd step, crossbeam puts in place, and flexible leg incision position closes up naturally.
CNB2005100244863A 2005-03-18 2005-03-18 Installing method of portal crane Expired - Fee Related CN100522793C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100244863A CN100522793C (en) 2005-03-18 2005-03-18 Installing method of portal crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100244863A CN100522793C (en) 2005-03-18 2005-03-18 Installing method of portal crane

Publications (2)

Publication Number Publication Date
CN1833988A CN1833988A (en) 2006-09-20
CN100522793C true CN100522793C (en) 2009-08-05

Family

ID=37001916

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100244863A Expired - Fee Related CN100522793C (en) 2005-03-18 2005-03-18 Installing method of portal crane

Country Status (1)

Country Link
CN (1) CN100522793C (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101293599B (en) * 2007-04-27 2011-04-20 上海振华重工(集团)股份有限公司 Method for discharging boat to dock basin with dock yard trestle crane set
CN101628610B (en) * 2008-07-18 2012-08-22 上海船厂船舶有限公司 Method for positioning dockyard overbridge
CN103193163B (en) * 2012-01-10 2015-06-17 上海振华重工(集团)股份有限公司 Entrance dock installation method for gantry crane of shipyard
CN102785998A (en) * 2012-08-06 2012-11-21 河南起重机器有限公司 Variable-span manual hoist gantry crane
CN103072004B (en) * 2013-01-21 2015-05-06 湖南省第五工程有限公司 Installation method of electric hoist hanger
CN104759863B (en) * 2015-04-16 2017-02-22 南通振华重型装备制造有限公司 Fixed crane on-site general assembly technology
CN105236263B (en) * 2015-10-28 2017-07-25 上海振华重工(集团)股份有限公司 The installation method of gantry flexible leg
CN107055322A (en) * 2017-05-10 2017-08-18 河南新科起重机股份有限公司 The erecting device and installation method of crane
CN107838687B (en) * 2017-10-16 2019-06-11 武汉帝尔激光科技股份有限公司 A gantry structure installation method of a large gantry machine tool
CN108423560B (en) * 2018-03-19 2019-07-05 中铁十六局集团第三工程有限公司 A kind of gantry crane eminence integral installation method
CN108423565B (en) * 2018-04-18 2019-06-14 中铁十九局集团轨道交通工程有限公司 The erection and Demolition Construction method of U-shaped twin beams gantry crane with hook
CN109911770B (en) * 2019-03-06 2020-03-17 中建八局轨道交通建设有限公司 Construction method for hoisting gantry crane
CN110316662B (en) * 2019-05-06 2021-04-13 粤水电轨道交通建设有限公司 Installation and construction method of large-span portal crane
CN111453621A (en) * 2020-04-03 2020-07-28 丘声富 Be used for portal crane automated control anchor
CN114261901B (en) * 2021-12-30 2025-03-25 武汉武船重型装备工程有限责任公司 A method for installing a gantry crane
CN118164377A (en) * 2024-04-18 2024-06-11 中国港湾工程有限责任公司 Gantry crane installation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
靖江造船厂600t龙门式起重机安装技术. 史耀辉.建筑施工,第2001年第3期. 2001 *

Also Published As

Publication number Publication date
CN1833988A (en) 2006-09-20

Similar Documents

Publication Publication Date Title
CN100522793C (en) Installing method of portal crane
CN100537348C (en) An integral construction and hoisting method of an offshore platform and its special crane
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN209397501U (en) Deck crane
CN106320182B (en) The long hoist cable of suspension bridge bank slope beam section, which is swung, moves mounting device and method
CN205527429U (en) Self-jacking device for jib crane
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN102121273A (en) Hydraulic lifting inversion method for reinforced concrete chimney steel inner cylinder
CN105350459A (en) Large steel beam gliding device and construction method thereof
CN103967284B (en) The steel column installation method of reserved stigma docking
CN104803303A (en) Single-movable-arm grounded derrick with rocking balance arm
CN209618736U (en) Jacking apparatus is climbed in a kind of derrick crane
CN105781210B (en) A kind of conical tower and its tool section assist punching construction method for lifting whole
CN213169974U (en) Horizontal transportation and translation tool for large equipment in factory building
CN205421022U (en) Suspension bridge stiffening beam handing equipment that slides
CN108086169B (en) Installation and lifting method of mobile formwork used in bridge construction
CN110094577B (en) Device and method for installing oversized-diameter inclined dam rear open pipe under strong wind condition
CN204569237U (en) A kind of oscillating type pole equilibrium arm
CN119195004A (en) A prefabricated box girder installation construction structure and construction method under low clearance high-voltage line
CN204040598U (en) The two rocker pole of a kind of remote control hydraulic
CN206736726U (en) The device of the prefabricated arch ring of nose girder auxiliary erection
CN218619992U (en) Jacking device is changed in maintenance of bank bridge gate leg
CN107313444B (en) Double-slide rail beam type weight shifting device and shifting method
CN206438420U (en) The assembled equipment of fixed asymmetric bridge girder cantilever
CN117071440A (en) A self-propelled and hydraulically lifted steel pre-tied inner frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090805

Termination date: 20160318

CF01 Termination of patent right due to non-payment of annual fee