CN100522793C - Installing method of portal crane - Google Patents
Installing method of portal crane Download PDFInfo
- Publication number
- CN100522793C CN100522793C CNB2005100244863A CN200510024486A CN100522793C CN 100522793 C CN100522793 C CN 100522793C CN B2005100244863 A CNB2005100244863 A CN B2005100244863A CN 200510024486 A CN200510024486 A CN 200510024486A CN 100522793 C CN100522793 C CN 100522793C
- Authority
- CN
- China
- Prior art keywords
- leg
- crossbeam
- lifting
- installation
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000009434 installation Methods 0.000 claims abstract description 19
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 8
- 239000010959 steel Substances 0.000 claims abstract description 8
- 238000003466 welding Methods 0.000 claims description 3
- 241000282326 Felis catus Species 0.000 claims 4
- 230000001737 promoting effect Effects 0.000 claims 4
- 230000011218 segmentation Effects 0.000 claims 4
- 230000003028 elevating effect Effects 0.000 claims 1
- 238000012423 maintenance Methods 0.000 abstract 1
- 230000001360 synchronised effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 238000007429 general method Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种门式起重机的安装方法,在整体提升钢结构大梁的过程中,刚性腿和柔性腿随着大梁的提升一起提升到位,实现整台门式起重机一次成形,安全、快捷、可靠。主梁现场拼接,同时将上小车和维修吊吊装在大梁上,然后竖立提升塔架,利用先进的液压同步提升技术提升大梁,刚性腿分段安装,柔性腿结构随大梁提升而自然就位。在大梁提升到位以后,完成刚性腿行走机构和柔性腿两根管腿的安装,最后完成整台龙门吊结构的安装。本发明使用两副提升塔架,缆风调整减少,安全可靠;刚性腿和柔性腿随着大梁的提升而逐渐到位,减少了单独安装刚性腿和柔性腿的工作量;使用提升油缸张拉塔架缆风,缆风受力准确,调整方便。
An installation method of a gantry crane, in the process of overall lifting of a steel structure girder, rigid legs and flexible legs are lifted into place together with the lifting of the girder, realizing the one-time forming of the whole gantry crane, which is safe, fast and reliable. The main girder is spliced on site, and the trolley and maintenance crane are hoisted on the girder at the same time, and then the lifting tower is erected, and the girder is lifted by using advanced hydraulic synchronous lifting technology. The rigid legs are installed in sections, and the flexible leg structure is naturally in place with the lifting of the girder. After the girder is lifted in place, the installation of the two tube legs of the rigid leg walking mechanism and the flexible leg is completed, and finally the installation of the entire gantry crane structure is completed. The invention uses two pairs of lifting towers, the adjustment of the cable wind is reduced, and it is safe and reliable; the rigid legs and flexible legs are gradually in place with the lifting of the girder, which reduces the workload of separately installing the rigid legs and flexible legs; the lifting cylinder is used to stretch the tower The cable wind is installed, the force of the cable wind is accurate, and the adjustment is convenient.
Description
技术领域 technical field
本发明涉及一种门式起重机的安装方法。The invention relates to a method for installing a gantry crane.
背景技术 Background technique
门式起重机主要用于造船工业中,目前它的安装方法也是各种各样。一般的方法是先将整个刚性腿竖立好,再将大梁提升到位,这种方法在大梁安装时刚性腿的重心很难调整所以安全性差;以前某某厂发生重大工程事故,与其提升方法有很大的关系。Gantry cranes are mainly used in the shipbuilding industry, and they are currently installed in various ways. The general method is to erect the entire rigid leg first, and then lift the girder into place. This method is difficult to adjust the center of gravity of the rigid leg when the girder is installed, so the safety is poor. In the past, a major engineering accident occurred in a certain factory. big relationship.
发明内容 Contents of the invention
本发明的目的在于提供一种新的安装方法,提高门式起重机安装过程的安全性、快捷性和可靠性。The purpose of the present invention is to provide a new installation method to improve the safety, quickness and reliability of the installation process of the gantry crane.
为达上述目的,本发明使用两副“门”字形塔架为提升塔架,钢结构大梁在地面拼装制作,刚性腿分段和柔性腿铰接在大梁上。在整体提升钢结构大梁的过程中,刚性腿和柔性腿随着大梁的提升一起提升到位,实现整台门式起重机一次成形,安全、快捷、可靠。In order to achieve the above-mentioned purpose, the present invention uses two pairs of "door"-shaped towers as lifting towers, the steel structure girders are assembled on the ground, and the rigid legs are segmented and the flexible legs are hinged on the girders. During the overall lifting of the steel structure girder, the rigid legs and flexible legs are lifted into place together with the lifting of the girder, realizing the one-time forming of the entire gantry crane, which is safe, fast and reliable.
本发明的优越性在于:第一,使用两副提升塔架,缆风调整减少,安全可靠;第二,刚性腿和柔性腿随着大梁的提升而逐渐就位,减少了单独安装刚性腿和柔性腿的工作量;第三,使用提升油缸张拉塔架缆风,缆风受力准确,调整方便。The advantages of the present invention are as follows: firstly, two sets of hoisting towers are used, the adjustment of cable wind is reduced, and it is safe and reliable; The workload of the flexible legs; third, use the lifting cylinder to tension the cable wind of the tower, the force of the cable wind is accurate, and the adjustment is convenient.
附图说明 Description of drawings
图1为门式起重机提升系统布置。Figure 1 shows the layout of the lifting system of the gantry crane.
图2为刚性腿安装图。Figure 2 is the rigid leg installation diagram.
图3为柔性腿安装图。Figure 3 is an installation diagram of the flexible legs.
具体实施方式 Detailed ways
结合附图对本发明作进一步描述。请参见图1、2、3所示,本发明由大梁1、刚性腿2、第一铰点3、滑块4、第二铰点5、提升油缸6、塔顶龙门梁7、塔架8、行走机构9、A字头10、第三铰点11、第四铰点12、柔性腿下横梁13、柔性腿14和滑移小车15等组成。The present invention will be further described in conjunction with the accompanying drawings. Please refer to Fig. 1, 2, and 3, the present invention consists of
安装方法:installation method:
一、塔架和塔顶龙门梁的安装1. Installation of the tower frame and the gantry beam on the top of the tower
本发明使用两副塔架8为提升塔架,塔架8的有效高度根据具体门式起重机的不同而有所不同,一般可以高达一百多米,断面4米,钢管格构式结构,塔架8底部与地面基础使用螺栓连接。塔顶龙门梁7为箱型结构。每付塔架的载荷能力达两千多吨。横跨门式起重机大梁1的2根塔架中心距离为十几米,在二根塔架的顶部设有箱型结构的塔顶龙门梁即提升横梁,提升油缸6放置在塔顶龙门梁7上,见图2所示。塔架8和塔顶龙门梁7安装完成之后,使用经纬仪校准塔架的垂直度,满足要求后,用缆风绳把它们固定好,并使用夹头将缆风绳的活头夹紧。The present invention uses two pairs of towers 8 as lifting towers. The effective height of the towers 8 varies according to the specific gantry cranes. Generally, it can be as high as more than 100 meters, with a section of 4 meters. The steel pipe lattice structure, the tower The bottom of the frame 8 is connected with the ground foundation using bolts. The gantry beam 7 on the top of the tower is a box structure. Each pair of towers has a load capacity of more than 2,000 tons. The distance between the centers of the two towers across the
二、大梁的提升2. Lifting of the girder
塔架8的塔顶龙门梁7安装完成之后,开始大梁1的提升。第1次提升,提升高度根据具体的情况而定,大约为十米左右时停下,装上刚性腿2上部结构和柔性腿A字头10,校准其水平位置,并将其固定好。第2次提升之前,使用第二铰点5将刚性腿2一端连到大梁1上,刚性腿2的另一端则放置在2辆滑移小车15上。这样,刚性腿2就随大梁1提升自动就位。就位后,校准轴线、用电焊连接。同时,在第2次提升之前,将柔性腿14使用第四铰点12连到A字头10上,这样大梁1到位,柔性腿14自动就位。After the installation of the tower top gantry beam 7 of the tower frame 8 is completed, the lifting of the
三、刚性腿的安装,见图2。第一步,刚性腿2分段放置预定位置,使用液压千斤顶调整两端上下位置,连接好第二铰点5和第一铰点3。第二步,刚性腿2分段一段随大梁提升而上升,另一端则使用卷扬机牵引,以克服水平摩擦力。第三步,将已组装好的行走机构9慢慢推入刚性腿2的下面。最后,大梁1下降,将分段处接口校准、焊接。3. Installation of rigid legs, see Figure 2. In the first step, the
四、柔性腿的安装,见图3。在龙门吊梁1第一次提升之后,柔性腿的A字头10下端两侧设对称的第四铰点12,两侧各一只。第一步,柔性腿14平放,腿管一端用第四铰点12与A字头10相连,另一端用第三铰点11与行走机构相连。第二步,大梁1提升,柔性腿14自然跟随、在柔性腿行走机构的水平方向上,施加一个水平牵引力,可以减小垂直提升力。第三步,大梁1到位,柔性腿14断口处自然合拢。Fourth, the installation of the flexible legs, see Figure 3. After the
由于本发明的刚性腿是分段逐步提升,所以很好的解决了重心不稳的问题,再加上使用提升油缸张拉塔架缆风,可以准确的调整和测量缆风的受力问题。本发明经试验,在两台600吨×182米龙门起重机整体提升工程的应用中取得了很大的成功。因此,该方法具有实质的特点和显著的先进性。Since the rigid legs of the present invention are lifted step by step, the problem of unstable center of gravity is well solved. In addition, the lifting cylinder is used to tension the cable wind of the tower, so that the force problem of the cable wind can be accurately adjusted and measured. After testing, the present invention has achieved great success in the application of two 600-ton * 182-meter gantry cranes in the overall lifting project. Therefore, this method has substantial characteristics and remarkable advancement.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNB2005100244863A CN100522793C (en) | 2005-03-18 | 2005-03-18 | Installing method of portal crane |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNB2005100244863A CN100522793C (en) | 2005-03-18 | 2005-03-18 | Installing method of portal crane |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN1833988A CN1833988A (en) | 2006-09-20 |
| CN100522793C true CN100522793C (en) | 2009-08-05 |
Family
ID=37001916
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNB2005100244863A Expired - Fee Related CN100522793C (en) | 2005-03-18 | 2005-03-18 | Installing method of portal crane |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN100522793C (en) |
Families Citing this family (16)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101293599B (en) * | 2007-04-27 | 2011-04-20 | 上海振华重工(集团)股份有限公司 | Method for discharging boat to dock basin with dock yard trestle crane set |
| CN101628610B (en) * | 2008-07-18 | 2012-08-22 | 上海船厂船舶有限公司 | Method for positioning dockyard overbridge |
| CN103193163B (en) * | 2012-01-10 | 2015-06-17 | 上海振华重工(集团)股份有限公司 | Entrance dock installation method for gantry crane of shipyard |
| CN102785998A (en) * | 2012-08-06 | 2012-11-21 | 河南起重机器有限公司 | Variable-span manual hoist gantry crane |
| CN103072004B (en) * | 2013-01-21 | 2015-05-06 | 湖南省第五工程有限公司 | Installation method of electric hoist hanger |
| CN104759863B (en) * | 2015-04-16 | 2017-02-22 | 南通振华重型装备制造有限公司 | Fixed crane on-site general assembly technology |
| CN105236263B (en) * | 2015-10-28 | 2017-07-25 | 上海振华重工(集团)股份有限公司 | The installation method of gantry flexible leg |
| CN107055322A (en) * | 2017-05-10 | 2017-08-18 | 河南新科起重机股份有限公司 | The erecting device and installation method of crane |
| CN107838687B (en) * | 2017-10-16 | 2019-06-11 | 武汉帝尔激光科技股份有限公司 | A gantry structure installation method of a large gantry machine tool |
| CN108423560B (en) * | 2018-03-19 | 2019-07-05 | 中铁十六局集团第三工程有限公司 | A kind of gantry crane eminence integral installation method |
| CN108423565B (en) * | 2018-04-18 | 2019-06-14 | 中铁十九局集团轨道交通工程有限公司 | The erection and Demolition Construction method of U-shaped twin beams gantry crane with hook |
| CN109911770B (en) * | 2019-03-06 | 2020-03-17 | 中建八局轨道交通建设有限公司 | Construction method for hoisting gantry crane |
| CN110316662B (en) * | 2019-05-06 | 2021-04-13 | 粤水电轨道交通建设有限公司 | Installation and construction method of large-span portal crane |
| CN111453621A (en) * | 2020-04-03 | 2020-07-28 | 丘声富 | Be used for portal crane automated control anchor |
| CN114261901B (en) * | 2021-12-30 | 2025-03-25 | 武汉武船重型装备工程有限责任公司 | A method for installing a gantry crane |
| CN118164377A (en) * | 2024-04-18 | 2024-06-11 | 中国港湾工程有限责任公司 | Gantry crane installation method |
-
2005
- 2005-03-18 CN CNB2005100244863A patent/CN100522793C/en not_active Expired - Fee Related
Non-Patent Citations (1)
| Title |
|---|
| 靖江造船厂600t龙门式起重机安装技术. 史耀辉.建筑施工,第2001年第3期. 2001 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN1833988A (en) | 2006-09-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100522793C (en) | Installing method of portal crane | |
| CN100537348C (en) | An integral construction and hoisting method of an offshore platform and its special crane | |
| CN101537976B (en) | Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof | |
| CN209397501U (en) | Deck crane | |
| CN106320182B (en) | The long hoist cable of suspension bridge bank slope beam section, which is swung, moves mounting device and method | |
| CN205527429U (en) | Self-jacking device for jib crane | |
| CN201376848Y (en) | Large-scale double-tower automatic-elevation hoisting equipment | |
| CN102121273A (en) | Hydraulic lifting inversion method for reinforced concrete chimney steel inner cylinder | |
| CN105350459A (en) | Large steel beam gliding device and construction method thereof | |
| CN103967284B (en) | The steel column installation method of reserved stigma docking | |
| CN104803303A (en) | Single-movable-arm grounded derrick with rocking balance arm | |
| CN209618736U (en) | Jacking apparatus is climbed in a kind of derrick crane | |
| CN105781210B (en) | A kind of conical tower and its tool section assist punching construction method for lifting whole | |
| CN213169974U (en) | Horizontal transportation and translation tool for large equipment in factory building | |
| CN205421022U (en) | Suspension bridge stiffening beam handing equipment that slides | |
| CN108086169B (en) | Installation and lifting method of mobile formwork used in bridge construction | |
| CN110094577B (en) | Device and method for installing oversized-diameter inclined dam rear open pipe under strong wind condition | |
| CN204569237U (en) | A kind of oscillating type pole equilibrium arm | |
| CN119195004A (en) | A prefabricated box girder installation construction structure and construction method under low clearance high-voltage line | |
| CN204040598U (en) | The two rocker pole of a kind of remote control hydraulic | |
| CN206736726U (en) | The device of the prefabricated arch ring of nose girder auxiliary erection | |
| CN218619992U (en) | Jacking device is changed in maintenance of bank bridge gate leg | |
| CN107313444B (en) | Double-slide rail beam type weight shifting device and shifting method | |
| CN206438420U (en) | The assembled equipment of fixed asymmetric bridge girder cantilever | |
| CN117071440A (en) | A self-propelled and hydraulically lifted steel pre-tied inner frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20090805 Termination date: 20160318 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
