CN107055322A - The erecting device and installation method of crane - Google Patents

The erecting device and installation method of crane Download PDF

Info

Publication number
CN107055322A
CN107055322A CN201710326708.XA CN201710326708A CN107055322A CN 107055322 A CN107055322 A CN 107055322A CN 201710326708 A CN201710326708 A CN 201710326708A CN 107055322 A CN107055322 A CN 107055322A
Authority
CN
China
Prior art keywords
supporting leg
girder
crane
sill
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710326708.XA
Other languages
Chinese (zh)
Inventor
刘继伟
崔丽
胡哲涛
范武军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Sinoko Cranes Ltd
Original Assignee
Henan Sinoko Cranes Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Sinoko Cranes Ltd filed Critical Henan Sinoko Cranes Ltd
Priority to CN201710326708.XA priority Critical patent/CN107055322A/en
Publication of CN107055322A publication Critical patent/CN107055322A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C19/00Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a kind of erecting device of crane and installation method, it is related to hoisting machinery technical field.The erecting device of crane includes the hanger on girder, the first axle device set located at the junction of girder and supporting leg and to the side away from girder and the second hinge device set located at the junction of supporting leg and sill and to the side close to girder, first axle device can be such that supporting leg is rotated relative to girder so that supporting leg is docked with girder, second hinge device can be such that supporting leg is rotated relative to sill so that supporting leg is docked with sill, solving the erecting device of crane present in prior art makes the stress of crane be deteriorated, it is easily reduced the technical problem of the security performance of crane, utilize girder and supporting leg, installation of the supporting leg with sill in itself is combined, it ensure that the design strength and stability of supporting leg, improve the security performance of crane.

Description

The erecting device and installation method of crane
Technical field
The present invention relates to hoisting machinery technical field, more particularly, to the erecting device and installation method of a kind of crane.
Background technology
Economic construction is flourishing as never before since reform and opening-up, the prosperity of the industry such as building, the energy, electric power, petrochemical industry, to peace Dress engineering proposes higher requirement.Work essence based on hoisting machinery, masts type, operation type crane are often used for Installment work, gin pole, simple in construction, easy to assembly, lifting capacity is big, the requirement to construction site is low, using very wide General, the crane of the operation type such as truck mounted, rubber-tyred, crawler type is good due to its mobility, works together flexible, closely Quickly grown over year.
Size, volume of the operation according to lift heavy are commonly installed, condition of construction site etc. selects suitable equipment, by rising Hang the influence of ability, many equipment volumes are big, length length, from great, typically transported again after factory carries out segmentation manufacture to applying Work scene, is installed using crane and splices assembling, although can so solve, installation equipment size large volume is big etc. to ask Topic, but be due to need to carry out splicing assembling in the air when mounted, installation difficulty is larger, in order to solve this problem, at present may be used The method of use is to carry out the splicing operation of equipment in advance on ground, removes the installation accuracy problem of high-altitude splicing from, then will peace Fill equipment utilization synchronous ascending device and carry out integral lifting, install convenient, efficiency high is developed rapidly and extensive use.
At present, crane is realized using the hinge arrangement being arranged on supporting leg when synchronous ascending is installed, generally The top and bottom of supporting leg are segmented, top section is affixed with girder, bottom section is affixed with sill, hinge arrangement is set Put in the top section of supporting leg and the junction of medial section and the junction of medial section and bottom section, so that synchronous Lifting device when lifting girder, using hinge arrangement, by supporting leg, together install by raising, so that installation effectiveness is improved, still, due to Supporting leg segmentation is more, is especially segmented at the top and bottom of supporting leg so that the stress of supporting leg is deteriorated, due in segmentation Junction stress ratio is relatively concentrated, and is easily reduced the strength and stability of supporting leg, making the security performance of crane reduces.
The content of the invention
It is an object of the invention to provide a kind of erecting device of crane and installation method, to solve to deposit in the prior art The erecting device of crane the stress of crane is deteriorated, the technology for being easily reduced the security performance of crane is asked Topic.
The erecting device for the crane that the present invention is provided includes hanger on the girder, located at the girder and supporting leg Junction and the first axle device set to the side away from the girder and the connection located at the supporting leg and sill Place and the second hinge device set to the side close to the girder;
The first axle device supporting leg can be made to be rotated relative to the girder so that the supporting leg with it is described Girder is docked, and the supporting leg can be made to be rotated relative to the sill for the second hinge device so that the supporting leg and institute State sill docking.
Further, the first axle device includes free bearing on first on the girder, located at the supporting leg Top and rotate first time free bearing being connected with free bearing on described first;
The second hinge device include located at the supporting leg bottom second on free bearing, on the sill and with Free bearing rotates second time free bearing of connection on described second.
Further, the second hinge device also includes upper connector on the supporting leg and under described Lower connector on crossbeam.
Further, width of the upper connector along the supporting leg extends to both sides, also, the upper connector It is more than the width of the supporting leg in the width of bearing of trend;
Free bearing is respectively arranged on the width side of the upper connector provided with free bearing on two, two described second on described second To two ends;
The lower connector is provided with two, and two lower connectors are respectively arranged on the two of the width of the sill Side;
Second time free bearing is provided with two.
Further, quantity phase of the quantity of the first axle device and the second hinge device with the supporting leg Matching.
What the present invention was provided is applied to the installation of the erecting device of the crane as any one of above-mentioned technical scheme Method, comprises the following steps:
Lifting pylon and auxiliary equipment are installed, and lifting pylon and auxiliary equipment are checked and adjusted;
Girder is positioned over to the predetermined position of lifting pylon, and lifting pylon is connected with the hanger on girder;
Trolley is installed on girder and is fixedly connected;
Examination lifting is carried out to girder, the lifting state of lifting pylon and girder is checked;
Girder is once lifted, girder is promoted to predeterminated position;
Girder is connected with supporting leg by first axle device, supporting leg is connected with sill by second hinge device, Sill is fixedly connected with traveling mechanism of the larger traveller, traveling mechanism of the larger traveller is placed in running track;
Second lift is carried out to girder, girder is docked with supporting leg, supporting leg is docked with sill;
Each junction of crane is subjected to installation fixation;
The installment state of crane is checked, crane is unloaded.
Further, it is further comprising the steps of:
Girder segmentation is carried out into splicing to install to be combined into girder.
Further, it is further comprising the steps of:
Supporting leg segmentation is carried out into splicing to install to be combined into supporting leg;
Assemble traveling mechanism of the larger traveller.
Further, the lifting pylon includes hydraulic synchronizing lifting system.
Further, the examination lifting is specially that girder is promoted to apart from ground level is at 200mm, and to continue 24h.
The erecting device for the crane that the present invention is provided includes hanger, first axle device and second hinge device, hangs Ear is arranged on the girder of crane, for being connected with lifting device so as to which the girder of crane be lifted in order to carrying out lifting The installation exercise of machine, first axle device is located at crane located at the junction of crane girder and supporting leg, second hinge device The junction of supporting leg and sill, drives supporting leg to be lifted, utilizes carrying for supporting leg using the lifting of girder by first axle device Rise, drive sill to move horizontally by second hinge device, so that girder is docked with supporting leg, supporting leg is docked with sill, Realize that the installation of girder, supporting leg and sill is in place, greatly accelerate the erection schedule of crane, improve installation effectiveness.
Because girder drives supporting leg lifting, supporting leg rotates relative to girder, and first axle device should be along one away from girder Side is set, and supporting leg needs supporting leg being positioned over suitable position before lifting, facilitates the installation and connection of first axle device, just Supporting leg is driven to be rotated relative to girder by first axle device using the raising of girder in realizing, so as to realize rising for supporting leg Rise, finally realize docking for supporting leg and girder, girder and supporting leg synchronous ascending can be made by first axle device, greatly improved The installation effectiveness of crane, is installed so that girder and supporting leg while avoiding the high-altitude splicing that girder segmentation is segmented with supporting leg Raising, it is ensured that installation accuracy, reduces installation difficulty, greatly reduces installation cost, improve economic benefit.
Because first axle device is arranged at the junction of girder and supporting leg, it is not necessary to carry out the segmentation at the top of supporting leg, profit Combined with crane girder itself with the installation of supporting leg, compared in the prior art, it is necessary to first by girder and supporting leg top section Installed, finally again installed supporting leg top section with supporting leg middle section, reduce installation steps, installation accuracy energy Access guarantee, and substantially increase installation effectiveness, due to that will need not be segmented at the top of supporting leg so that on girder by Power is directly passed to supporting leg, it is to avoid the stress concentration of supporting leg top section stitching portion produces influence to the stress of supporting leg, So as to ensure that the design strength and stability of supporting leg, the security performance of crane is improved.
Because the raising of supporting leg drives moving horizontally for sill, supporting leg rotates relative to sill, second hinge device It should be set along the side close to girder, supporting leg needs sill being positioned over suitable position before raising, facilitates second hinge The installation and connection of device, are easy to implement and are revolved using the lifting of girder by first axle device drive supporting leg relative to girder Turn, so as to realize the raising of supporting leg, drive sill to move horizontally by second hinge device, during supporting leg raising, It is final to realize docking for supporting leg and girder and supporting leg and sill, girder can be made synchronous with supporting leg by second hinge device Sill sliding in place is driven while raising, girder, supporting leg, sill is synchronously reached defined design and installation position, makes Each primary structure for obtaining crane can be quickly in place, reaches installation site, it is achieved thereby that the Integral synchronous lifting of crane Install, and lifting process is simple, and the lifting appliance species used is few, and installation procedure is easy, substantially increases the peace of crane Efficiency is filled, while ensure that installation accuracy, installation difficulty is reduced, greatly reduces installation cost, improve economic benefit.
Because second hinge device is arranged at the junction of supporting leg and sill, it is not necessary to carry out the segmentation of supporting leg bottom, Combined using crane supporting leg itself with the installation of sill, compared in the prior art, it is necessary to first by supporting leg bottom section with Sill is installed, and is finally again installed supporting leg middle section with supporting leg bottom section, reduces installation steps, is installed Precision can be guaranteed, and substantially increase installation effectiveness, due to that need not be segmented supporting leg bottom so that supporting leg Stress be directly passed to sill, it is to avoid the stress concentration of supporting leg bottom section stitching portion is produced to the stress of supporting leg Influence, so as to ensure that the design strength and stability of supporting leg, improves the security performance of crane.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The accompanying drawing used required in embodiment or description of the prior art is briefly described, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the installation process of crane provided in an embodiment of the present invention;
Fig. 2 is the structural representation of the first axle device of the erecting device of crane provided in an embodiment of the present invention;
Fig. 3 is the structural representation of the second hinge device of the erecting device of crane provided in an embodiment of the present invention;
Fig. 4 is the structural representation after crane installation provided in an embodiment of the present invention.
Icon:100- hangers;200- first axle devices;300- second hinge devices;400- girders;500- supporting legs; 600- sills;700- lifts pylon;800- trolleys;900- traveling mechanism of the larger traveller;Free bearing on 210- first;220- first Lower free bearing;Free bearing on 310- second;Second time free bearing of 320-;311- upper connectors;Connector under 321-.
Embodiment
Technical scheme is clearly and completely described below in conjunction with accompanying drawing, it is clear that described implementation Example is a part of embodiment of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under the premise of creative work is not made, belongs to the scope of protection of the invention.
In the description of the invention, it is necessary to explanation, such as occur term " " center ", " on ", " under ", "left", "right", " vertical ", " level ", " interior ", " outer " etc., orientation or position relationship indicated by it are based on orientation shown in the drawings or position Relation, is for only for ease of the description present invention and simplifies description, rather than indicate or imply that the device or element of meaning must have There is specific orientation, with specific azimuth configuration and operation, therefore be not considered as limiting the invention.In addition, as occurred Term " first ", " second ", " the 3rd " are only used for describing purpose, and it is not intended that indicating or implying relative importance.
In the description of the invention, it is necessary to which explanation, unless otherwise clearly defined and limited, term " peace such as occurs Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integratedly Connection;Can be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected to by intermediary, It can be the connection of two element internals.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition The concrete meaning of language in the present invention.
Embodiment 1 and embodiment 2 are described in detail below in conjunction with the accompanying drawings:
Fig. 1 is the structural representation of the installation process of crane provided in an embodiment of the present invention;Fig. 2 is the embodiment of the present invention The structural representation of the first axle device of the erecting device of the crane of offer;Fig. 3 is lifting provided in an embodiment of the present invention The structural representation of the second hinge device of the erecting device of machine;Fig. 4 is crane installation provided in an embodiment of the present invention Structural representation afterwards.
Embodiment 1
Please with reference to Fig. 1-4, a kind of erecting device of crane is present embodiments provided, including on girder 400 Hanger 100, the first axle device that is set located at the junction of girder 400 and supporting leg 500 and to the side away from girder 400 200 and the second hinge device that is set located at the junction of supporting leg 500 and sill 600 and to the side close to girder 400 300, specifically:
Supporting leg 500 can be made to be rotated relative to girder 400 for first axle device 200 so that 400 pairs of supporting leg 500 and girder Connect, supporting leg 500 can be made to be rotated relative to sill 600 for second hinge device 300 so that 600 pairs of supporting leg 500 and sill Connect.
The erecting device of crane includes hanger 100, first axle device 200 and second hinge device 300, hanger 100 are arranged on the girder 400 of crane, for be connected with lifting device so as to by the girder 400 of crane lifted in order to The installation exercise of crane is carried out, first axle device 200 is located at the junction of crane girder 400 and supporting leg 500, the second hinge Chain apparatus 300 is filled located at the junction of crane support 500 and sill 600 using the lifting of girder 400 by first axle Put 200 drive supporting legs 500 to be lifted, using the lifting of supporting leg 500, drive the level of sill 600 to move by second hinge device 300 Dynamic, so that girder 400 is docked with supporting leg 500, supporting leg 500 is docked with sill 600, realizes girder 400, supporting leg 500 with The installation of crossbeam 600 is in place, greatly accelerates the erection schedule of crane, improves installation effectiveness.
Because girder 400 drives supporting leg 500 to be lifted, supporting leg 500 rotates relative to girder 400, and first axle device 200 should Set along the side away from girder 400, supporting leg 500 needs supporting leg 500 being positioned over suitable position before lifting, facilitates first The installation and connection of hinge means 200, are easy to implement and pass through the drive supporting leg of first axle device 200 using the raising of girder 400 500 rotate relative to girder 400, so as to realize the raising of supporting leg 500, finally realize docking for supporting leg 500 and girder 400, lead to Girder 400 and the synchronous ascending of supporting leg 500 can be made by crossing first axle device 200, substantially increase the installation effectiveness of crane, together When avoid the high-altitude splicing that the segmentation of girder 400 is segmented with supporting leg 500 and install so that girder 400 and supporting leg 500 being capable of synchronization onwards Rise, it is ensured that installation accuracy, reduce installation difficulty, greatly reduce installation cost, improve economic benefit.
Because first axle device 200 is arranged at the junction of girder 400 and supporting leg 500, it is not necessary to carry out supporting leg 500 and push up The segmentation in portion, is combined using crane itself girder 400 with the installation of supporting leg 500, compared in the prior art, it is necessary to first will be main Beam 400 is installed with the top section of supporting leg 500, is finally again pacified the top section of supporting leg 500 with the middle section of supporting leg 500 Dress, reduces installation steps, installation accuracy can be guaranteed, and substantially increases installation effectiveness, due to that will need not prop up The top of leg 500 is segmented so that the stress on girder 400 is directly passed to supporting leg 500, it is to avoid the top section of supporting leg 500 The stress concentration of stitching portion produces influence to the stress of supporting leg 500, so as to ensure that the design strength and stably of supporting leg 500 Property, improve the security performance of crane.
Because the raising of supporting leg 500 drives moving horizontally for sill 600, supporting leg 500 rotates relative to sill 600, Second hinge device 300 should be set along the side close to girder 400, and supporting leg 500 needs sill 600 being positioned over before raising Suitable position, facilitates the installation and connection of second hinge device 300, is easy to implement the lifting using girder 400 by first Hinge means 200 drives supporting leg 500 to be rotated relative to girder 400, so as to realize the raising of supporting leg 500, is filled by second hinge 300 drive sills 600 are put to move horizontally, during the raising of supporting leg 500, finally realize supporting leg 500 and girder 400 and Supporting leg 500 is docked with sill 600, can make girder 400 and the synchronous ascending of supporting leg 500 by second hinge device 300 The sliding in place of sill 600 is driven simultaneously, makes girder 400, supporting leg 500, sill 600 are synchronous to reach defined design and installation position Put so that each primary structure of crane can be quickly in place, installation site is reached, it is achieved thereby that the Integral synchronous of crane Erection & lift, and lifting process is simple, and the lifting appliance species used is few, and installation procedure is easy, substantially increases crane Installation effectiveness, while ensure that installation accuracy, reduce installation difficulty, greatly reduce installation cost, improve economic effect Benefit.
Because second hinge device 300 is arranged at the junction of supporting leg 500 and sill 600, it is not necessary to carry out supporting leg 500 The segmentation of bottom, is combined using crane itself supporting leg 500 with the installation of sill 600, compared in the prior art, it is necessary to first The bottom section of supporting leg 500 is installed with sill 600, finally again by the middle section of supporting leg 500 and the bottom section of supporting leg 500 Installed, reduce installation steps, installation accuracy can be guaranteed, and substantially increase installation effectiveness, due to being not required to The bottom of supporting leg 500 is segmented so that the stress of supporting leg 500 is directly passed to sill 600, it is to avoid supporting leg 500 bottom The stress concentration of segment section stitching portion produces influence to the stress of supporting leg 500, so as to ensure that the design strength of supporting leg 500 And stability, improve the security performance of crane.
In a kind of specific embodiment, first axle device 200 includes being located at free bearing 210 on first on girder 400 And first time free bearing 220 located at the top of supporting leg 500, and on first free bearing 210 rotated with first time free bearing 220 be connected with Realize and drive supporting leg 500 relative to the rotation raising of girder 400, specifically, free bearing 210 on first using the lifting of girder 400 It should be oppositely arranged with first time free bearing 220, and the quantity of free bearing 210 and first time free bearing 220 should match on first, to constitute Complete first axle device 200.Second hinge device 300 is including the free bearing 310 on the second of the bottom of supporting leg 500 and sets In second time free bearing 320 on sill 600, and on second, free bearing 310 is connected to realize profit with second time rotation of free bearing 320 Supporting leg 500 is rotated relative to sill 600 with the lifting of supporting leg 500, and drive moving horizontally for sill 600, specifically, Free bearing 310 should be oppositely arranged with second time free bearing 320 on second, and the quantity of free bearing 310 and second time free bearing 320 should on second Match, to constitute complete second hinge device 300.
Because second hinge device 300 is arranged at the junction of supporting leg 500 and sill 600, and towards close to girder 400 Side set, supporting leg 500 is before lifting, to facilitate lifting, and supporting leg 500 is positioned on sill 600 so that second hinge Device 300 is arranged at the outside of the width of sill 600, namely side of the supporting leg 500 along the length direction of girder 400, is Make second hinge device 300 that facility to be installed, upper connector 311 is additionally provided with supporting leg 500, under being additionally provided with sill 600 Connector 321 so that free bearing 310 and second time free bearing 320 can install facility on second, it is achieved thereby that second hinge device 300 function.
Specifically, upper connector 311 can be provided with one, and width of the upper connector 311 along supporting leg 500 is to both sides Extension, upper connector 311 is more than the width of supporting leg 500 in the width of bearing of trend, upper connector 311 is stretched out supporting leg 500 flat Face, free bearing 310 is at least provided with two on second, and is respectively arranged on the two ends of the width of upper connector 311, utilizes upper company Fitting 311 realizes the installation and fixation of free bearing 310 on second.Free bearing 310 is corresponding with second time free bearing 320 on second sets Put, for ease of the installation and fixation of second time free bearing 320, lower connector 321 is provided with two, and two lower 321 points of connectors Not She Yu the width of sill 600 both sides, second time free bearing 320 be respectively arranged under two and connect at least provided with two On fitting 321, the installation and fixation of second time free bearing 320 are realized using lower connector 321.With as lower connector 321, on Connector 311 can also be provided with two, and two upper connectors 311 are respectively arranged on free bearing on the both sides of the width of supporting leg 500, first 210 are respectively arranged on two upper connectors 311, make free bearing 310 and on second using upper connector 311 and lower connector 321 Two times free bearing 320 installs facility, it is achieved thereby that the function of second hinge device 300.
Because the structure of various cranes is different, the pattern of supporting leg 500 and quantity of crane are also not quite similar, first axle Quantity of the quantity of device 200 and second hinge device 300 with supporting leg 500 matches, and makes first axle device 200 and second The quantity of hinge means 300 adapts to the change of the structural shape of supporting leg 500 and quantity, so as to realize the Synchronous lifting of crane Install, make the applicability of erecting device wide, it is possible to increase the installation effectiveness of crane.
Embodiment 2
A kind of installation method of crane is present embodiments provided, this method is applied to the peace of the crane in embodiment 1 Assembling device.The installation method of crane comprises the following steps:
Lifting pylon 700 and auxiliary equipment are installed, and lifting pylon 700 and auxiliary equipment are checked and adjusted, really Surely the installation of lifting pylon 700 is solid and reliable, determines that auxiliary equipment installs connection errorless;
Girder 400 is positioned over to the predetermined position of lifting pylon 700, and pylon 700 and hanging on girder 400 will be lifted Ear 100 is connected;
Trolley 800 is installed on girder 400 and is fixedly connected, to ensure that trolley 800 is lifted in girder 400 During have fixed position, it is to avoid trolley 800, which is installed, insecure causes installation accident;
Examination lifting is carried out to girder 400, the lifting state of lifting pylon 700 and girder 400 is checked, it is ensured that in lifting process The stress for lifting pylon 700 and girder 400 is in normal scope;
Girder 400 is once lifted, girder 400 is promoted to predeterminated position, in order to by supporting leg 500 and sill 600 are positioned over suitable position, consequently facilitating the installation and connection of first axle device 200 and second hinge device 300;
Girder 400 is connected with supporting leg 500 by first axle device 200, supporting leg 500 and sill 600 are passed through the Two hinge device 300 is connected, and sill 600 is fixedly connected with traveling mechanism of the larger traveller 900, and traveling mechanism of the larger traveller 900 is placed in In running track, so that traveling mechanism of the larger traveller 900 can be moved in running track, installation effectiveness is improved, it is ensured that same Step erection & lift can be smoothed out;
Second lift is carried out to girder 400, girder 400 is docked with supporting leg 500, supporting leg 500 is docked with sill 600, In the lifting process of girder 400, supporting leg 500 is progressively mobile in place with sill 600, and lifting process terminates;
Each junction of crane is subjected to installation fixation;
The installment state of crane is checked, crane is unloaded.
Because the girder 400 and the normal length of supporting leg 500 of crane are longer, it is necessary to be carried out after being segmented in erecting bed Splicing is installed, therefore when carrying out specific crane installation, girder 400 should be also segmented to progress splicing and install to be combined into master Beam 400, is segmented progress splicing by supporting leg 500 and installs to be combined into supporting leg 500, meanwhile, also need to assemble traveling mechanism of the larger traveller 900, To ensure the complete of each part of crane.
Lift pylon 700 and use hydraulic synchronizing lifting system, lifting force is larger, also allows for realizing the control of lifting system, Ensure in lifting process, the lifting on girder 400 at each suspension centre can be synchronous.
The examination lifting of girder 400 is specially to be promoted to girder 400 to be apart from ground level at 200mm, and continues 24h, The stressing conditions of the observation lifting Each part such as pylon 700 and girder 400, it is ensured that second lift work can be carried out after stress is normal Industry, so that the lifting process of crane has good security.
Due to using first axle device 200 and second hinge device 300 so that the Integral synchronous erection & lift of crane It is possibly realized, greatly accelerates installation effectiveness, and installation accuracy can be guaranteed, and reduce installation difficulty, greatly reduce Installation cost, improves economic benefit.
Finally it should be noted that:Various embodiments above is merely illustrative of the technical solution of the present invention, rather than its limitations;To the greatest extent The present invention is described in detail with reference to foregoing embodiments for pipe, it will be understood by those within the art that:Its according to The technical scheme described in foregoing embodiments can so be modified, or which part or all technical characteristic are entered Row equivalent substitution;And these modifications or replacement, the essence of appropriate technical solution is departed from various embodiments of the present invention technology The scope of scheme.

Claims (10)

1. a kind of erecting device of crane, it is characterised in that including the hanger (100) on girder (400), located at described The junction of girder (400) and supporting leg (500) and the first axle device set to the side away from the girder (400) (200) and located at the junction of the supporting leg (500) and sill (600) and to the side close to the girder (400) set The second hinge device (300) put;
The first axle device (200) can be such that the supporting leg (500) is rotated relative to the girder (400) so that described Supporting leg (500) is docked with the girder (400), and the second hinge device (300) can make the supporting leg (500) relative to institute Sill (600) rotation is stated so that the supporting leg (500) is docked with the sill (600).
2. the erecting device of crane according to claim 1, it is characterised in that first axle device (200) bag Include free bearing (210) on first on the girder (400), located at the top of the supporting leg (500) and with described first Free bearing (210) rotates first time free bearing (220) of connection;
The second hinge device (300) includes being located at free bearing (310) on the second of the supporting leg (500) bottom, located at described The second time free bearing (320) being connected is rotated on sill (600) and with free bearing (310) on described second.
3. the erecting device of crane according to claim 2, it is characterised in that the second hinge device (300) is also Including the upper connector (311) on the supporting leg (500) and the lower connector on the sill (600) (321)。
4. the erecting device of crane according to claim 3, it is characterised in that the upper connector (311) is along described The width of supporting leg (500) extends to both sides, also, the upper connector (311) be more than in the width of bearing of trend it is described The width of supporting leg (500);
Free bearing (310) is respectively arranged on the upper connector provided with free bearing (310) on two, two described second on described second (311) two ends of width;
The lower connector (321) is provided with two, and two lower connectors (321) are respectively arranged on the sill (600) The both sides of width;
Second time free bearing (320) is provided with two.
5. the erecting device of crane according to claim 1, it is characterised in that the first axle device (200) with Quantity of the quantity of the second hinge device (300) with the supporting leg (500) matches.
6. a kind of installation method for the erecting device for being applied to the crane according to any one of claim 1-5, it is special Levy and be:Comprise the following steps:
Lifting pylon (700) and auxiliary equipment are installed, and lifting pylon (700) and auxiliary equipment are checked and adjusted;
Girder (400) is positioned over to the predetermined position of lifting pylon (700), and will be lifted on pylon (700) and girder (400) Hanger (100) be connected;
Trolley (800) is installed on girder (400) and is fixedly connected;
Examination lifting is carried out to girder (400), the lifting state of lifting pylon (700) and girder (400) is checked;
Girder (400) is once lifted, girder (400) is promoted to predeterminated position;
Girder (400) is connected with supporting leg (500) by first axle device (200), by supporting leg (500) and sill (600) Connected by second hinge device (300), sill (600) is fixedly connected with traveling mechanism of the larger traveller (900), cart is run Mechanism (900) is placed in running track;
Second lift is carried out to girder (400), girder (400) is docked with supporting leg (500), supporting leg (500) and sill (600) Docking;
Each junction of crane is subjected to installation fixation;
The installment state of crane is checked, crane is unloaded.
7. installation method according to claim 6, it is characterised in that further comprising the steps of:
Girder (400) segmentation is carried out into splicing to install to be combined into girder (400).
8. installation method according to claim 7, it is characterised in that further comprising the steps of:
Supporting leg (500) segmentation is carried out into splicing to install to be combined into supporting leg (500);
Assemble traveling mechanism of the larger traveller (900).
9. installation method according to claim 6, it is characterised in that the lifting pylon (700) carries including hydraulic synchronization The system of liter.
10. installation method according to claim 6, it is characterised in that the examination lifting is specially to lift girder (400) To being at 200mm, and to continue 24h apart from ground level.
CN201710326708.XA 2017-05-10 2017-05-10 The erecting device and installation method of crane Pending CN107055322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710326708.XA CN107055322A (en) 2017-05-10 2017-05-10 The erecting device and installation method of crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710326708.XA CN107055322A (en) 2017-05-10 2017-05-10 The erecting device and installation method of crane

Publications (1)

Publication Number Publication Date
CN107055322A true CN107055322A (en) 2017-08-18

Family

ID=59596786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710326708.XA Pending CN107055322A (en) 2017-05-10 2017-05-10 The erecting device and installation method of crane

Country Status (1)

Country Link
CN (1) CN107055322A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107673202A (en) * 2017-11-13 2018-02-09 无锡华东重型机械股份有限公司 A kind of track crane installation method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2252910C2 (en) * 2003-02-04 2005-05-27 Государственное предприятие Специализированное конструкторско-технологическое бюро "Краностроитель" Gantry crane
CN1654306A (en) * 2005-01-24 2005-08-17 史胜海 Method for hoisting and loading giant-scale gantry crane by following-carrying method
CN1833988A (en) * 2005-03-18 2006-09-20 同济大学 Installing method of portal crane
CN201376848Y (en) * 2009-03-20 2010-01-06 史胜海 Large-scale double-tower automatic-elevation hoisting equipment
RO130105A0 (en) * 2014-05-16 2015-03-30 Mihai Dumbravă Portal truck crane for interventions
CN105236263A (en) * 2015-10-28 2016-01-13 上海振华重工(集团)股份有限公司 Installation method for flexible leg of gantry crane
CN205257791U (en) * 2015-08-28 2016-05-25 河南省大河重型机械有限公司 Quick assembly and disassembly formula gantry crane frame construction
CN205709569U (en) * 2016-05-12 2016-11-23 崔会梓 A kind of hinged door crane

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2252910C2 (en) * 2003-02-04 2005-05-27 Государственное предприятие Специализированное конструкторско-технологическое бюро "Краностроитель" Gantry crane
CN1654306A (en) * 2005-01-24 2005-08-17 史胜海 Method for hoisting and loading giant-scale gantry crane by following-carrying method
CN1833988A (en) * 2005-03-18 2006-09-20 同济大学 Installing method of portal crane
CN201376848Y (en) * 2009-03-20 2010-01-06 史胜海 Large-scale double-tower automatic-elevation hoisting equipment
RO130105A0 (en) * 2014-05-16 2015-03-30 Mihai Dumbravă Portal truck crane for interventions
CN205257791U (en) * 2015-08-28 2016-05-25 河南省大河重型机械有限公司 Quick assembly and disassembly formula gantry crane frame construction
CN105236263A (en) * 2015-10-28 2016-01-13 上海振华重工(集团)股份有限公司 Installation method for flexible leg of gantry crane
CN205709569U (en) * 2016-05-12 2016-11-23 崔会梓 A kind of hinged door crane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107673202A (en) * 2017-11-13 2018-02-09 无锡华东重型机械股份有限公司 A kind of track crane installation method
CN107673202B (en) * 2017-11-13 2019-04-09 无锡华东重型机械股份有限公司 A kind of track crane installation method

Similar Documents

Publication Publication Date Title
CN104608112B (en) Power line inspection robot and its obstacle surmounting method
CN106698208B (en) A kind of hanging device and hanging method for being transported outside high-rise building
CN105443871A (en) Novel support hanger and construction process for butting connection of horizontal multiple pipelines
CN102251486B (en) A jacking support system and its construction technology for segmental installation of bridge towers
CN104234200B (en) A kind of suspen-shell structure rope leverage is by ring lifting installation method
CN103882811A (en) Bridge floor crane for cable-stayed bridge
CN104674668A (en) Method for hoisting construction girder sections through cables
CN104925672B (en) The all-hydraulic self-crawling type two-sided tower crane of suspension
CN105970819A (en) Installation construction method for steel anchor beams
CN110562850B (en) Main tower integral hoisting system and method
CN105019664A (en) High-altitude sliding installation method for box room type electric room
CN107055322A (en) The erecting device and installation method of crane
CN105752826A (en) Movable lifting platform and construction method thereof
CN103964300B (en) Jacking type increases equipment
CN107697812A (en) A kind of cantilever crane set up for bridge subsection transport
CN103574158A (en) Super-large diameter pressure steel tube inclined shaft three-hanging-point installation method
CN102849626A (en) Indoor non-standard crane installation method
CN103663172B (en) A kind of comprehensive get beam partly turn round cantilever crane
CN206052577U (en) A kind of bridge local deviation correcting device
CN107190860A (en) The automatic lifting system of Steel Structure Installation
CN207293976U (en) A kind of cantilever crane set up for bridge subsection transport
CN110040638A (en) A kind of deck unit erection gantry device and installation method for installing suspension bridge stiff beam
CN211496634U (en) Main tower integral hoisting system
CN210480628U (en) Rotatory hoist of two-way self-balancing
CN106012830B (en) A kind of Super Long Tunnel anchor utilizes the horizontal hole in the tunnel method that laterally transhipment reinforcing pull rod is constructed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication