CN100501000C - Track plate concrete pouring method - Google Patents

Track plate concrete pouring method Download PDF

Info

Publication number
CN100501000C
CN100501000C CNB2006100207483A CN200610020748A CN100501000C CN 100501000 C CN100501000 C CN 100501000C CN B2006100207483 A CNB2006100207483 A CN B2006100207483A CN 200610020748 A CN200610020748 A CN 200610020748A CN 100501000 C CN100501000 C CN 100501000C
Authority
CN
China
Prior art keywords
concrete
model
track plate
perfusion
vibration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2006100207483A
Other languages
Chinese (zh)
Other versions
CN1851126A (en
Inventor
钱振地
江成
肖俊恒
刘振民
王智勇
吴海涛
张雷
白昆华
吴利清
杨先凤
王江
张志红
龚斯昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CNB2006100207483A priority Critical patent/CN100501000C/en
Publication of CN1851126A publication Critical patent/CN1851126A/en
Application granted granted Critical
Publication of CN100501000C publication Critical patent/CN100501000C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a rail plate concrete pouring method, comprising the steps of: checking before pouring; arranging a pouring hopper above a mould, where the pouring hopper holds concrete meeting the design requirements; controlling operating temperature at 10-35 deg.C; pouring and vibrating; vibrating a flat vibrator in the direction of vertical guide rails on the mould to assure inner sides and corners of the mould close to the peripheral concrete of the prefabricated part; compacting and leveling the concrete surface until the surface is suffused with pulp and no stones are exposed; after vibration, screeding the concrete surface and paying attention to filling sides and filling corners, and meeting the rail plate surface finish not over 5 mm/m; and the poured rail plate has good surface finish and compactness, and high intensity can continuously bear loads, and has high production efficiency and high yield.

Description

Track plate conerete pouring method
Technical field
The present invention relates to railroad track, especially relate to a kind of track board concrete method for filling.
Background technology
Along with Chinese economic development, railway traffic as the urban traffic system has become the important tie that big and medium-sized cities connect, the application of ballastless track and tunnel, roadbed are different, the TERM DEFORMATION of ballastless track under elastic deformation under the mobile load effect and dead load effect all can directly have influence on stressed, ride comfort and the traffic safety and the comfortableness of track structure, thereby the shop of ballastless track just becomes the key of ballastless track prestressed concrete design.
The vibration of Rail Transit System is mainly produced by the following aspects: when train moves with certain speed, the gravity of rail is loaded the impact of generation; When train moves on rails, wheel and rail structural vibrations that wheel-rail interaction produces; When cartwheel roll is crossed rail joint, wheel and rail structural vibrations that wheel-rail interaction produces; The irregularity of track and the damage of wheel also are the vibration sources of system vibration.Thereby track planarization and density are required is that track normally moves, and the assurance that reduces to vibrate for this reason, has been developed a kind of track plate conerete pouring method specially.
Summary of the invention
Based on above-mentioned need of practice, it is good to the purpose of this invention is to provide a kind of track plate density, planarization of making, and the high track plate conerete pouring method of intensity.
In order to achieve the above object, the present invention adopts following technical scheme: a kind of track plate conerete pouring method comprises the steps:
The first step, check before the perfusion:
Steel mesh reinforcement in track template die type and the model is laid correctly; All built-in fittings of track plate are laid correctly, and must be closely connected with the model surface of its permanent position, do not allow the slit and exist; Evenly be furnished with the bottom vibrator in the model bottom, on the longitudinal rail of model upper edge, lay plate vibrator;
In second step, infusion funnel is arranged on the model top, and the concrete that meets design requirement is housed in the infusion funnel;
In the 3rd step, the control operating ambient temperature is in 10~35 ℃ of scopes;
The 4th step, perfusion and vibration:
Perfusion: the concrete spouting in the infusion funnel of will packing into is gone in the model, and the perfusion of monoblock track plate should be finished before concrete initial set;
Vibration: in perfusion, adopt the end to shake and assist the vibratory process of the combination of shaking with top, promptly
With the perfusion of model inner concrete, open the vibrator of model bottom successively; When the end, shake the power deficiency, in concrete, insert vibrating head from top and vibrate, each vibrating head should be inserted to the model bottom, and vibrating head does not hit all built-in fittings and the reinforcing bar in the movable model during vibration; Being vibrated to concrete surface no longer emits bubble, surperficial bleeding and nothing significantly to sink to being as the criterion;
The 5th step made plate vibrator along model upper edge longitudinal rail direction vibration, to guarantee the concrete compaction of corner and built-in fitting periphery in the model; And concrete surface caught up with the real and leveling of densification, cause surperficial bleeding and no stone and expose and be as the criterion;
In the 6th step, the floating concrete surface in vibration back is noted filling out the limit fillet, and satisfies track plate surface finish and be no more than 5mm/m.
Described each vibrating head inserts once every about 0.15~0.25 meter, vibrates 26~35 seconds at every turn.
The perfusion of monoblock track plate should once be finished.
Behind summer floating concrete surface, in time concrete surface is covered, avoid making the quick dehydration of concrete to cause thousand to split.
The present invention checks before perfusion, be because: the making of track plate is to build to finish in model, at first places the steel mesh reinforcement in track template die type and the model, guarantees the physical dimension and the intensity of track plate; All built-in fittings of track plate are laid correctly, and must be closely connected with the model surface of its permanent position, do not allow the slit and exist, in order to guarantee the surfacing of track plate; Evenly be furnished with the bottom vibrator in model bottom, on the longitudinal rail of model upper edge, lay plate vibrator, be for concrete spouting closely knit and smooth.
Infusion funnel is arranged on the appropriate location of model top among the present invention, and general infusion funnel is about 1m apart from the height of model; The concrete that mixes and stirs by designing requirement should be cleaned out infusion funnel is inside and outside before the infusion funnel of packing into, and the moistening infusion funnel inwall of spraying water; In infusion funnel is fed into model the time, the staff notes controlling the swing of infusion funnel, and is even to guarantee blanking with concrete, and guarantees safety, and the amount of blanking is simultaneously wanted appropriateness, flushes the model end face and is as the criterion to vibrate the back concrete.
The present invention controls operating ambient temperature in 10~35 ℃ of scopes, is in order to guarantee concrete various performance, and the quality of track plate and technical indicator.
The perfusion of monoblock track plate of the present invention should be finished before concrete initial set, and as far as possible once perfusion finish, be to prevent to pour into the designing requirement of arriving of the inhomogeneous quality that causes the track plate and technical indicator.The present invention adopts the end to shake in perfusion and assists the vibratory process of the combination of shaking with top, is in order to get rid of bubble in the concrete, to make that simultaneously concrete spouting is closely knit.
The function of middle plateform vibrator of the present invention is concrete to be carried out face shake, and concrete grout is shaken, and guarantees that concrete surface is smooth, and planeness reaches requirement, and the error range of controlling the track plate height simultaneously is within 0~3mm.
Beneficial effect of the present invention: the track plate that pours into out by the present invention not only planarization, density is good, and the intensity height, high load capacity carrying continuously; Utilize the present invention to pour into the track plate, not only production efficiency height, and yield rate height.
The specific embodiment
Preferred embodiment is as follows:
A kind of track plate conerete pouring method, carry out as follows:
The first step, check before the perfusion:
Steel mesh reinforcement in track template die type and the model is laid correctly, guarantees the physical dimension and the intensity of track plate; All built-in fittings of track plate are laid correctly, and must be closely connected with the model surface of its permanent position, do not allow the slit and exist, and guarantee the surfacing of track plate; Evenly be furnished with the bottom vibrator in the model bottom, on the longitudinal rail of model upper edge, lay plate vibrator;
In second step, infusion funnel is arranged on the model top, and the concrete that meets design requirement is housed in the infusion funnel;
In the 3rd step, the control operating ambient temperature is in 10~35 ℃ of scopes;
The 4th step, perfusion and vibration
Perfusion: the concrete spouting in the infusion funnel of will packing into is gone in the model, and the perfusion of monoblock track plate should be finished before concrete initial set, and the perfusion of monoblock track plate is once finished;
Vibration: in perfusion, adopt the vibratory process that the end shakes, the combination of shaking is assisted on top,, open the vibrator of model bottom successively with the perfusion of model inner concrete; When the end, shake the power deficiency, insert vibrating head from top in concrete and vibrate, each vibrating head should be inserted to the model bottom, and vibrating head does not hit all built-in fittings and the reinforcing bar in the movable model during vibration, each vibrating head inserts once every about 0.15~0.25 meter, vibrates 26~35 seconds at every turn;
The 5th step made plate vibrator along model upper edge longitudinal rail direction vibration, to guarantee the concrete compaction of corner and built-in fitting periphery in the model; And concrete surface caught up with the real and leveling of densification, cause surperficial bleeding and no stone and expose and be as the criterion; The function of this plate vibrator is concrete to be carried out face shake, and concrete grout is shaken, and guarantees that concrete surface is smooth, and planeness reaches requirement, and the error range of controlling the track plate height simultaneously is within 0~3mm; Being vibrated to concrete surface no longer emits bubble, surperficial bleeding and nothing significantly to sink to being as the criterion;
In the 6th step, the floating concrete surface in vibration back is noted filling out the limit fillet, and satisfies track plate surface finish and be no more than 5mm/m.Behind summer floating concrete surface, in time concrete surface is covered, avoid making the quick dehydration of concrete to cause dry and cracked.
Infusion funnel is arranged on the appropriate location of model top among the present invention, and general infusion funnel is about 1m apart from the height of model; The concrete that mixes and stirs by designing requirement should be cleaned out infusion funnel is inside and outside before the infusion funnel of packing into, and the moistening infusion funnel inwall of spraying water; In infusion funnel is fed into model the time, the staff notes controlling the swing of infusion funnel, and is even to guarantee blanking with concrete, and guarantees safety, and the amount of blanking is simultaneously wanted appropriateness, flushes the model end face and is as the criterion to vibrate the back concrete.
The present invention controls operating ambient temperature in 10~35 ℃ of scopes, is in order to guarantee concrete various performance, and the quality of track plate and technical indicator.
The perfusion of monoblock track plate of the present invention should be finished before concrete initial set, and as far as possible once perfusion finish, be to prevent to pour into the designing requirement of arriving of the inhomogeneous quality that causes the track plate and technical indicator.The present invention adopts the end to shake in perfusion, top is auxiliary shakes and the shake vibratory process of combination of face, be in order to get rid of bubble in the concrete, make that simultaneously concrete spouting is closely knit, concrete grout is shaken, the assurance concrete surface is smooth, planeness reaches requirement, and the error range of controlling the track plate height simultaneously is within 0~3mm.

Claims (5)

1, a kind of track plate conerete pouring method is characterized in that: this method comprises the steps:
The first step, check before the perfusion:
Steel mesh reinforcement in track template die type and the model is laid correctly; All built-in fittings of track plate are laid correctly, and must be closely connected with the model surface of its permanent position, do not allow the slit and exist; Evenly be furnished with the bottom vibrator in the model bottom, on the longitudinal rail of model upper edge, lay plate vibrator;
In second step, infusion funnel is arranged on the model top, and the concrete that meets design requirement is housed in the infusion funnel;
In the 3rd step, the control operating ambient temperature is in 10~35 ℃ of scopes;
The 4th step, perfusion and vibration:
Perfusion: the concrete spouting in the infusion funnel of will packing into is gone in the model, and the perfusion of monoblock track plate should be finished before concrete initial set;
Vibration: in perfusion, adopt the end to shake and assist the vibratory process of the combination of shaking with top, promptly
With the perfusion of model inner concrete, open the vibrator of model bottom successively; When the end, shake the power deficiency, in concrete, insert vibrating head from top and vibrate, each vibrating head should be inserted to the model bottom, and vibrating head does not hit all built-in fittings and the reinforcing bar in the movable model during vibration; Being vibrated to concrete surface no longer emits bubble, surperficial bleeding and nothing significantly to sink to being as the criterion;
The 5th step made plate vibrator along model upper edge longitudinal rail direction vibration, to guarantee the concrete compaction of corner and built-in fitting periphery in the model; And concrete surface caught up with the real and leveling of densification, cause surperficial bleeding and no stone and expose and be as the criterion;
The 6th step, the floating concrete surface in vibration back.
2, track plate conerete pouring method according to claim 1 is characterized in that: described each vibrating head every 0.15~0.25 meter insertion once vibrates 26~35 seconds at every turn.
3, track plate conerete pouring method according to claim 1 is characterized in that: the perfusion of monoblock track plate should once be finished.
4, track plate conerete pouring method according to claim 1 and 2 is characterized in that: track plate surface finish≤5mm/m.
5, track plate conerete pouring method according to claim 1 and 2 is characterized in that: behind summer floating concrete surface, in time concrete surface is covered, avoid making the quick dehydration of concrete to cause dry and cracked.
CNB2006100207483A 2006-04-21 2006-04-21 Track plate concrete pouring method Expired - Fee Related CN100501000C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100207483A CN100501000C (en) 2006-04-21 2006-04-21 Track plate concrete pouring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100207483A CN100501000C (en) 2006-04-21 2006-04-21 Track plate concrete pouring method

Publications (2)

Publication Number Publication Date
CN1851126A CN1851126A (en) 2006-10-25
CN100501000C true CN100501000C (en) 2009-06-17

Family

ID=37132627

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100207483A Expired - Fee Related CN100501000C (en) 2006-04-21 2006-04-21 Track plate concrete pouring method

Country Status (1)

Country Link
CN (1) CN100501000C (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101758557B (en) * 2009-12-30 2012-07-18 中铁二十三局集团有限公司 Producing method of track slabs
CN102826803B (en) * 2012-07-31 2014-04-16 湖北中桥科技有限公司 Ballastless track self-compaction concrete and filling construction method thereof
ES2592568R1 (en) * 2015-05-29 2017-01-27 Tecsa Empresa Constructora, S.A. PROCEDURE AND RAILWAY CONCRETE SYSTEM IN PLATE.
CN105398275A (en) * 2015-12-15 2016-03-16 天津银龙预应力材料股份有限公司 Concrete plate bottom coining device

Also Published As

Publication number Publication date
CN1851126A (en) 2006-10-25

Similar Documents

Publication Publication Date Title
CN204000469U (en) A kind of pile formula box road structure
CN201305795Y (en) Rail board
CN206982969U (en) Automatic storage, transport, pour, the complete set of equipments of vibrated concrete
CN207452594U (en) A kind of urban track traffic prestressing force slab track
CN105839850B (en) Precompressed construction method is poured into a mould after basement top-down method shaft
CN103352400B (en) Prefabricated embedded tracks plate
CN107268348B (en) Subway column check pit construction method
CN100501000C (en) Track plate concrete pouring method
KR100838227B1 (en) Structure of high-strength and rapidly-hardening prepacked concrete track for carrying out mechanization and working method thereof
CN107190583A (en) Urethane cures railway roadbed and preparation method thereof
KR20160001011U (en) Precast Concrete Panel for Concrete Ballast of the Railway
CN105401958A (en) Prefabricating construction method with movable prefabricating trolley for tunnel cable trench cover plate
CN104532754B (en) A kind of prestressed concrete box girder end-blocking template construction method
CN106436495A (en) Wide sleeper plate sticking type ballast track
CN107354826B (en) The rapid constructing method of tunnel built-in type rail system
CN105274912B (en) Construction method for hardening monolithic track bed of tramcar
CN102425110A (en) Cast-in-situ concrete construction method for full section of urban overpass box girder
JP2002227101A (en) Sleeper-integrated concrete ballast structure for railway line
CN100552135C (en) Concrete-pouring method for double-block type ballastless track
CN207314043U (en) Urethane cures railway roadbed
CN1970886A (en) Water-utilization vibration construction method and device
CN203755164U (en) Special hanging bracket for construction of post-pouring flange plates of acoustic barrier T-shaped beam
CN107083726A (en) The plate-type fragment-free track slab self-compacting concretes four of CRTS III connect block constructing device and method
CN104532691A (en) Ballastless track connected-block sleeper
CN207919848U (en) Top plate of underground parking garage is combined the unit with plastics diaphragm capsule

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090617