CN100453750C - Box-type section beam-column node structure and welding method - Google Patents

Box-type section beam-column node structure and welding method Download PDF

Info

Publication number
CN100453750C
CN100453750C CNB2006102010427A CN200610201042A CN100453750C CN 100453750 C CN100453750 C CN 100453750C CN B2006102010427 A CNB2006102010427 A CN B2006102010427A CN 200610201042 A CN200610201042 A CN 200610201042A CN 100453750 C CN100453750 C CN 100453750C
Authority
CN
China
Prior art keywords
steel
box
column
welding
electroslag welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2006102010427A
Other languages
Chinese (zh)
Other versions
CN1936207A (en
Inventor
郭海山
束伟农
李黎明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SANJIE INTERNATIONAL STRUCTURE CO Ltd BEIJING
Original Assignee
SANJIE INTERNATIONAL STRUCTURE CO Ltd BEIJING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SANJIE INTERNATIONAL STRUCTURE CO Ltd BEIJING filed Critical SANJIE INTERNATIONAL STRUCTURE CO Ltd BEIJING
Priority to CNB2006102010427A priority Critical patent/CN100453750C/en
Publication of CN1936207A publication Critical patent/CN1936207A/en
Application granted granted Critical
Publication of CN100453750C publication Critical patent/CN100453750C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a box section beam column node structure and sintering method that is sintered from box steel column and girder steel. Enforcing internal partition board is set in the steel column. Two sides of each horizontal steel board sinter clearance between steel column board and make the enhanced internal partition board with steel column to integrity. The total thickness of the two or three boards of horizontal steel boards matches to the external steel girder steel flange thickness that always larger or equal to the thickness of external steel girder steel flange. The invention ensures the sintering quality and saves producing cost.

Description

A kind of box-type section beam-column node structure and welding method thereof
Technical field:
The present invention relates to a kind of construction steel structure joint structure and processing method thereof.
Background technology:
Domestic in recent years high-rise steel structure building is on the increase, and its pillar also adopts box-type section more and more, and much bigger steel box column is general is welded with four block plates, and also the employing is rigidly connected more between the Liang Yuzhu.For guarantee with girder steel that post links to each other between internal force transmit continuously, generally in the steel box column of the position corresponding, internal partition is set with plane, bottom flange on the beam.And require internal partition and beam flange plate uniform thickness and and column wall four limit full penetrations welding.During making, internal partition can get up with two wallboards weldering earlier of box post, internal partition and other two wallboards be connected to hidden weld seam, adopt electroslag welding to realize usually.
For the node of diaphragm relatively thin (less than 40mm), adopt electroslag welding to be easy to realize.But recently high-rise, stride in the structure with heavy load greatly, the application of slab steel is increasingly extensive, the frange plate thickness of crossbeam that is connected with steel column or huge transfer truss etc. usually surpasses 40mm, some structure even reach more than the 80mm, this just requires the thickness of the internal partition of the box post that is attached thereto also will reach 40mm even more than the 80mm.Node for this internal partition thicker (more than or equal to 40mm), roomy because of the molten bath, general electroslag welding easily produces incomplete fusion or fire check quality problems such as (mariages), and the process implementing difficulty is big, success rate is low, and speed of welding is slow, weld properties is poor, and weldquality is difficult to guarantee.The present invention takes appropriate measures from the structure construction angle exactly, has solved the application difficult problem of super thick dividing plate electroslag welding in box steel member connected node well.
Summary of the invention
The objective of the invention is to propose a kind of box-type section beam-column node structure and welding method thereof, solve the difficult problem that the interior thicker situation lower node of the diaphragm internal partition electroslag welding of steel box column is difficult for realization and difficult quality guarantee, thick dividing plate replaces the thick dividing plate of spy in two because of adopting in the present invention simultaneously, also reduces material cost and cost of production.
The object of the present invention is achieved like this: this box-type section beam-column node structure, intersect with girder steel by steel box column and to be welded, the horizontal internal partition of putting more energy into of welding in steel box column, it is characterized in that: the above-mentioned internal partition of putting more energy into is clipped between the horizontal steel plate to the three block-shaped sizes horizontal steel plate identical with cross section in the box post and three to four by two, and the stacked spot welding of steel filler strip interleaved that is positioned at horizontal steel plate both ends forms, the termination, both sides of every block of horizontal steel plate is apart from reserving the electroslag welding welded gaps between the steel box column wallboard, make put more energy into internal partition and steel box column integrally welded by electroslag welding.
The gross thickness of above-mentioned two or three blocks horizontal steel plates requires to be complementary with external girder steel edge of a wing thickness, gets usually more than or equal to external girder steel edge of a wing thickness.
The welding position of above-mentioned put more energy into internal partition and steel box column is in a side, both sides, three sides or four sides of the internal partition of putting more energy into.
Above-mentioned box-type section beam-column node can be cross king post joint, T-shaped king post joint or corner post node.
Above-mentioned girder steel and steel column can be chord member or web members in the truss.
Above-mentioned girder steel can be box-shaped, H type, T type or hollow circular-tube cross section.
A kind of welding method of above-mentioned box-type section beam-column node structure is characterized in that:
Step 1: the horizontal steel plate that two block-shaped sizes are identical with cross section in the steel box column and three stacked points of steel filler strip interleaved are welded into the internal partition of putting more energy into, and between per two steel filler strips and the termination, both sides of horizontal steel plate is apart from the reservation electroslag welding welded gaps that forms strip between the steel box column wallboard;
Step 2: the put more energy into internal partition good group is welded on the steel box column bottom wing listrium by preposition;
Step 3: steel box column two coxostermums and the welding of bottom wing listrium are formed the temporary transient box post that opens wide of one side, the not steely filler strip both sides of the internal partition of will putting more energy into then and the welding of column web full penetration;
Step 4: cover the top flange plate of steel box column, and finish the casing welding of box post;
Step 5: bore the electroslag welding hole with respect to the electroslag welding welded gaps from steel box column two web outside, the electroslag welding hole is communicated with the electroslag welding welded gaps;
Step 6: the used scolder of electroslag welding is sent in electroslag welding hole and the electroslag welding welded gaps, carried out the electroslag welding welding;
Step 7: at last at the precalculated position welded steel beam.
Above-mentioned steps 6 described scolders are welding wire or welded tube.
The welding method of another kind of box-type section beam-column node structure is characterized in that:
Step 1: three blocks of horizontal steel plates identical with cross section in the steel box column and four stacked points of steel filler strip interleaved are welded into the internal partition of putting more energy into, and between per two steel filler strips and the termination, both sides of horizontal steel plate is apart from the reservation electroslag welding welded gaps that forms strip between the box post steel wallboard;
Step 2: the put more energy into internal partition good group is welded on the steel box column bottom wing listrium by preposition;
Step 3: steel box column two coxostermums and the welding of bottom wing listrium are formed the temporary transient box post that opens wide of one side, the not steely filler strip both sides of the internal partition of will putting more energy into then and the welding of column web full penetration;
Step 4: cover the top flange plate of steel box column, and finish the casing welding of box post;
Step 5: bore the electroslag welding hole with respect to the electroslag welding welded gaps from steel box column two web outside, the electroslag welding hole is communicated with the electroslag welding welded gaps;
Step 6: the used scolder of electroslag welding is sent in electroslag welding hole and the electroslag welding welded gaps, carried out the electroslag welding welding;
Step 7: at last at the precalculated position welded grider.
Above-mentioned steps 6 described scolders are welding wire or welded tube.
Bean column node of the present invention is made up of box post, girder steel and the polylith internal partition of putting more energy into, and the internal partition of putting more energy into is arranged on corresponding position, flange of beam plane, is stacked by two or the horizontal steel plate of polylith and forms, and horizontal steel plate thickness is generally less than the edge of a wing thickness of slab of external girder steel.The present invention is under the prerequisite that does not weaken bearing capacity, guaranteed the welding quality of electroslag welding, globality is strong, reliability is high, it is excessive because of the molten bath to have solved ultra-thick plate (thickness of slab is greater than 40mm) electroslag welding well, the technology difficulty height, the success rate that cause are low, shortcomings such as speed of welding is slow, weld properties difference; Adopt simultaneously that thick dividing plate replaces the thick dividing plate of spy in two or the polylith, also reduced material cost and cost of production.The present invention is applicable to the beam column rigid joint that the box post connects, the beam-column node structure of girder steel edge of a wing thickness more than 40mm that especially links to each other with the box post.
Description of drawings:
Fig. 1 is a three-dimensional sectional view of the present invention;
Fig. 2 is the internal partition schematic diagram of putting more energy among Fig. 1;
Fig. 3 is the internal construction schematic diagram of the invention process example one;
Fig. 4 is the internal construction schematic diagram of the invention process example two.
Fig. 5 is the schematic diagram of step 2 of the present invention;
Fig. 6 is the schematic diagram of step 3 of the present invention;
Fig. 7 is the schematic diagram of step 4 of the present invention and step 5.
Among the figure: 1-steel box column, 2-girder steel, the 3-internal partition of putting more energy into, 4-steel filler strip, 5-electroslag welding welded gaps, the horizontal steel plate of 6-, 7-electroslag welding hole, 8-steel box column bottom wing listrium, 9-steel box column web, 10-steel box column top flange plate, 11-solder fusing zone.
The specific embodiment:
Embodiment sees in Fig. 1~3, this box-type section beam-column node structure, intersect with box girder steel 2 by steel box column 1 and to be welded, the horizontal internal partition 3 of putting more energy into of welding in steel box column, the above-mentioned internal partition 3 of putting more energy into is clipped between the horizontal steel plate by the two block-shaped sizes horizontal steel plate 6 and three identical with cross section in the box post, and the stacked spot welding of steel filler strip 4 interleaved that is positioned at horizontal steel plate both ends forms, the termination, both sides of every block of horizontal steel plate is apart from electroslag welding welded gaps 5 between the box post steel wallboard, welded gaps adopts the welding of electroslag welding penetration, makes the internal partition 3 of putting more energy into integrally welded with steel box column 1.The gross thickness of above-mentioned two blocks of horizontal steel plates is more than or equal to external girder steel edge of a wing thickness.
The welding concrete steps of embodiment one are as follows:
Step 1: horizontal steel plate 6 and three stacked points of steel filler strip 4 interleaved that two block-shaped sizes are identical with cross section in the steel box column 1 are welded into the internal partition 3 of putting more energy into, and between per two steel filler strips 4 and termination, both sides of horizontal steel plate 6 is apart from the reservation electroslag welding welded gaps 5 that forms strip between the steel box column wallboard.
Step 2: referring to Fig. 5, the put more energy into internal partition 3 good group is welded on the steel box column bottom wing listrium 8 by preposition.
Step 3:, steel box column both sides steel box column web 9 and 8 welding of steel box column bottom wing listrium are formed the temporary transient box post that opens wide of one side, the not steely filler strip both sides of the internal partition 3 of will putting more energy into then and the welding of steel box column web 9 full penetrations referring to Fig. 6.
Step 4: referring to Fig. 7, cover steel box column top flange plate 10, and finish the casing welding of box post.
Step 5:,, electroslag welding hole 7 is communicated with electroslag welding welded gaps 5 with respect to electroslag welding welded gaps 5 sidetracking electroslag welding hole 7 outside steel box column two webs 9 referring to Fig. 7.
Step 6: the used scolder of electroslag welding is sent in electroslag welding hole 7 and the electroslag welding welded gaps 5, carried out the electroslag welding welding, form solder fusing zone 11 (referring to Fig. 3).
Step 7: at last at precalculated position welded steel beam 2.
Above-mentioned steps 6 described scolders are welding wire or welded tube.
Embodiment two is seen Fig. 4, and the internal partition 3 of putting more energy into is divided into three blocks of horizontal steel plates 6, has adopted four blocks of steel filler strips 4.
The welding concrete steps of embodiment two are as follows:
Step 1: three horizontal steel plate 6 and four piece steel filler strip 4 interleaved stacked points identical with cross section in the steel box column 1 are welded into the internal partition 3 of putting more energy into, and between per two steel filler strips 4 and termination, both sides of horizontal steel plate 6 is apart from the electroslag welding welded gaps 5 that forms the reservation of strip between the box post steel wallboard.
Step 2: the put more energy into internal partition 3 good group is welded on the steel box column bottom wing listrium 8 by preposition.
Step 3: steel box column both sides steel box column web 9 and the welding of steel box column bottom flange 8 plates are formed the temporary transient box post that opens wide of one side, the not steely filler strip both sides of the internal partition 3 of will putting more energy into then and the welding of column web 9 full penetrations.
Step 4: cover steel box column top flange plate 10, and finish the casing welding of box post.
Step 5:, electroslag welding hole 7 is communicated with the electroslag welding welded gaps of reserving 5 with respect to electroslag welding welded gaps 5 sidetracking electroslag welding hole 7 outside steel box column two webs 9.
Step 6: the used scolder of electroslag welding is sent in electroslag welding hole 7 and the electroslag welding welded gaps 5, carried out the electroslag welding welding.
Step 7: at last at precalculated position welded steel beam 2.
Above-mentioned steps 6 described scolders are welding wire or welded tube.
The bean column node of steel work has cross king post joint, T-shaped king post joint and corner post node etc., the through node of some box-type section members is also arranged in the huge trussed construction, the interior diaphragm of these box-type section members all can adopt the mentioned structure of the present invention, to improve the weldquality of electroslag welding, the convenient making.

Claims (8)

1. box-type section beam-column node structure, intersect with girder steel by steel box column and to be welded, the horizontal internal partition of putting more energy into of welding in steel box column, it is characterized in that: the above-mentioned internal partition of putting more energy into is clipped between the horizontal steel plate by two to three appearance and size horizontal steel plate identical with cross section in the box post and three to four and the stacked spot welding of steel filler strip interleaved that is positioned at horizontal steel plate end forms, the termination, both sides of every block of horizontal steel plate is apart from reserving the electroslag welding welded gaps between the box post steel wallboard, make put more energy into internal partition and steel box column integrally welded by electroslag welding.
2. box-type section beam-column node structure according to claim 1 is characterized in that: the gross thickness of above-mentioned two or three blocks horizontal steel plates and external girder steel edge of a wing thickness are complementary, and get more than or equal to external girder steel edge of a wing thickness.
3. box-type section beam-column node structure according to claim 1 is characterized in that: the welding position of above-mentioned put more energy into internal partition and steel box column is in a side, both sides, three sides or four sides of the internal partition of putting more energy into.
4. according to claim 1 or 2 or 3 described box-type section beam-column node structures, it is characterized in that: above-mentioned box-type section beam-column node is cross king post joint, T-shaped king post joint or corner post node.
5. according to claim 1 or 2 or 3 described box-type section beam-column node structures, it is characterized in that: above-mentioned girder steel is chord member or a web member in the truss.
6. box-type section beam-column node structure according to claim 5 is characterized in that: above-mentioned girder steel is not a box-type section, but H type, T type or hollow circular-tube cross section.
7. the welding method of the described box-type section beam-column node structure of claim 1 is characterized in that:
Step 1: the horizontal steel plate that two block-shaped sizes are identical with cross section in the steel box column and three stacked points of steel filler strip interleaved are welded into the internal partition of putting more energy into, and between per two steel filler strips and the termination, both sides of horizontal steel plate is apart from the reservation electroslag welding welded gaps that forms strip between the steel box column wallboard;
Step 2: the put more energy into internal partition good group is welded on the steel box column bottom wing listrium by preposition;
Step 3: steel box column both sides steel box column web and the welding of steel box column bottom wing listrium are formed the temporary transient box post that opens wide of one side, the not steely filler strip both sides of the internal partition of will putting more energy into then and the welding of column web full penetration;
Step 4: cover the steel box column top flange plate, and finish the casing welding of box post;
Step 5: bore the electroslag welding hole with respect to the electroslag welding welded gaps from steel box column two web outside, the electroslag welding hole is communicated with the electroslag welding welded gaps;
Step 6: the used scolder of electroslag welding is sent in electroslag welding hole and the electroslag welding welded gaps, carried out the electroslag welding welding;
Step 7: at last at the precalculated position welded steel beam.
8. the welding method of the described box-type section beam-column node structure of claim 1 is characterized in that:
Step 1: three blocks of horizontal steel plates identical with cross section in the steel box column and four stacked points of steel filler strip interleaved are welded into the internal partition of putting more energy into, and between per two steel filler strips and the termination, both sides of horizontal steel plate is apart from the reservation electroslag welding welded gaps that forms strip between the box post steel wallboard;
Step 2: the put more energy into internal partition good group is welded on the steel box column bottom wing listrium by preposition;
Step 3: steel box column both sides steel box column web and the welding of steel box column bottom wing listrium are formed the temporary transient paper tinsel type post that opens wide of one side, the not steely filler strip both sides of the internal partition of will putting more energy into then and the welding of column web full penetration;
Step 4: cover the steel box column top flange plate, and finish the casing welding of box post;
Step 5: bore the electroslag welding hole with respect to the electroslag welding welded gaps from steel box column two web outside, the electroslag welding hole is communicated with the electroslag welding welded gaps;
Step 6: the used scolder of electroslag welding is sent in electroslag welding hole and the electroslag welding welded gaps, carried out the electroslag welding welding;
Step 7: at last at the precalculated position welded steel beam.
CNB2006102010427A 2006-10-30 2006-10-30 Box-type section beam-column node structure and welding method Expired - Fee Related CN100453750C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006102010427A CN100453750C (en) 2006-10-30 2006-10-30 Box-type section beam-column node structure and welding method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006102010427A CN100453750C (en) 2006-10-30 2006-10-30 Box-type section beam-column node structure and welding method

Publications (2)

Publication Number Publication Date
CN1936207A CN1936207A (en) 2007-03-28
CN100453750C true CN100453750C (en) 2009-01-21

Family

ID=37953914

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006102010427A Expired - Fee Related CN100453750C (en) 2006-10-30 2006-10-30 Box-type section beam-column node structure and welding method

Country Status (1)

Country Link
CN (1) CN100453750C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103088998A (en) * 2013-01-31 2013-05-08 朱宏宇 Combination palace lattice scaffold and installing and dismantling method thereof

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100545073C (en) * 2007-06-06 2009-09-30 中国核工业华兴建设有限公司 Method for assembling and welding cased crane-beam in circular rail of nuclear-power station
CN102240863B (en) * 2011-07-13 2014-04-02 宝钢钢构有限公司 Method for welding box-shaped column
CN102489945B (en) * 2011-11-30 2013-11-27 中冶天工集团有限公司 Manufacture method of anti-deformation water beam in sintering system
CN103015331A (en) * 2013-01-04 2013-04-03 中国人民解放军军事交通学院 Transition structure for main beam and longitudinal beam of platform slab
CN103088916B (en) * 2013-01-31 2014-12-17 朱宏宇 Clamping plate joint, structural frame and installation method
CN103934693B (en) * 2014-02-28 2018-03-27 青山 The processing technology of box-structure post/beam shaping
CN104674952B (en) * 2015-03-01 2017-02-22 长安大学 Connection joint and connection method for box girder and box column
CN104863266B (en) * 2015-04-24 2019-06-18 清华大学 The prefabricated assembled high-ductility girder Column border node of box column-I-beam
CN104988988B (en) * 2015-07-10 2017-10-27 安徽富煌钢构股份有限公司 Corner structure and its processing method
CN105297917A (en) * 2015-10-20 2016-02-03 张跃 Pillar-beam connecting structure
CN106736271B (en) * 2016-11-28 2018-08-03 中冶天工集团有限公司 A kind of production method of rolling/compacting rectangle steel tubing string
CN106759858B (en) * 2016-12-29 2017-11-10 山东科技大学 A kind of connecting node and preparation method of H profile steel beam and rectangular steel-tube concrete column
CN106988486B (en) * 2017-05-08 2019-03-29 山东科技大学 A kind of space lattice fashioned iron pipe concrete column connecting node and method
CN107695620A (en) * 2017-09-11 2018-02-16 江西峰辉钢结构有限公司 A kind of processing method of steel member
CN110253167B (en) * 2019-06-26 2022-01-14 浙江精工钢结构集团有限公司 Manufacturing method of beam-column conversion node
CN115194274A (en) * 2021-04-09 2022-10-18 株式会社神户制钢所 Method for manufacturing reinforced pipe and reinforced pipe
CN114396193B (en) * 2022-02-25 2024-03-29 江苏沪宁钢机股份有限公司 Transverse and longitudinal partition plate intensive support platform node and manufacturing method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0663738A (en) * 1992-08-18 1994-03-08 Kawatetsu Metal Fuaburika Kk Welding method of built in diaphragm of square steel tube column
JPH07323380A (en) * 1994-06-02 1995-12-12 Nippon Steel Corp Welding method for steel
JP2004162340A (en) * 2002-11-12 2004-06-10 Nippon Steel Corp Column beam joint structure of welding built-in box sectional column and h-shaped section beam
CN2693848Y (en) * 2004-05-20 2005-04-20 上海拜特钢结构设计有限公司 Perforated diaphragm plate type quadrate column beam connection node structure
CN2780401Y (en) * 2005-03-14 2006-05-17 北京工业大学 Connecting nodal point of box-shaped steel column and I-steel beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0663738A (en) * 1992-08-18 1994-03-08 Kawatetsu Metal Fuaburika Kk Welding method of built in diaphragm of square steel tube column
JPH07323380A (en) * 1994-06-02 1995-12-12 Nippon Steel Corp Welding method for steel
JP2004162340A (en) * 2002-11-12 2004-06-10 Nippon Steel Corp Column beam joint structure of welding built-in box sectional column and h-shaped section beam
CN2693848Y (en) * 2004-05-20 2005-04-20 上海拜特钢结构设计有限公司 Perforated diaphragm plate type quadrate column beam connection node structure
CN2780401Y (en) * 2005-03-14 2006-05-17 北京工业大学 Connecting nodal point of box-shaped steel column and I-steel beam

Non-Patent Citations (12)

* Cited by examiner, † Cited by third party
Title
建筑钢结构箱形构件隔板的电渣焊接. 边振义.焊接技术,第5期. 1998
建筑钢结构箱形构件隔板的电渣焊接. 边振义.焊接技术,第5期. 1998 *
瑞丰国际商务大厦高层钢结构制作与安装. 陈国津,单银木.建筑结构,第33卷第7期. 2003
瑞丰国际商务大厦高层钢结构制作与安装. 陈国津,单银木.建筑结构,第33卷第7期. 2003 *
电渣焊在箱型柱制造中的应用. 姜树良,刘兆庆,李学慧,吕建华.钢结构,第13卷第2期. 1998
电渣焊在箱型柱制造中的应用. 姜树良,刘兆庆,李学慧,吕建华.钢结构,第13卷第2期. 1998 *
箱型钢梁(柱)隔板管极电渣焊纵缝焊接的工艺性能改善. 杨军,李大军,佟文宗.电焊机,第33卷第11期. 2003
箱型钢梁(柱)隔板管极电渣焊纵缝焊接的工艺性能改善. 杨军,李大军,佟文宗.电焊机,第33卷第11期. 2003 *
箱形薄壁构件内隔板电渣焊技术. 张亚军.钢结构,第20卷第1期. 2005
箱形薄壁构件内隔板电渣焊技术. 张亚军.钢结构,第20卷第1期. 2005 *
钢框架梁柱节点连接方式的介绍与分析. 杨强跃,郑悦.建筑结构,第34卷第6期. 2004
钢框架梁柱节点连接方式的介绍与分析. 杨强跃,郑悦.建筑结构,第34卷第6期. 2004 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103088998A (en) * 2013-01-31 2013-05-08 朱宏宇 Combination palace lattice scaffold and installing and dismantling method thereof

Also Published As

Publication number Publication date
CN1936207A (en) 2007-03-28

Similar Documents

Publication Publication Date Title
CN100453750C (en) Box-type section beam-column node structure and welding method
CN101260720B (en) Connection construction method for network frame prefabricated composite board
CN105951991B (en) A kind of assembling type steel structure frame system
CN104712089A (en) Open web composite shear connector construction
CN103061410B (en) Building assembled with prefabricated space frame substructures and construction method thereof
CN107386446B (en) It is a kind of for faced wall-pillar cold formed steel structure beam-column connection and connection method
CN106978854A (en) Can the friction lasso trick of multistage detection be combined energy-dissipating type assembled steel post and lintel system
CN102995756A (en) Concrete-filled rectangular steel tube column-box girder full-bolt connection node and construction method
CN107503442A (en) A kind of assembled connecting node of steel core concrete column and girder steel
CN107476446A (en) The banding heavier-duty node that H profile steel beam is connected with wide steel core concrete column short side
CN106894543A (en) The light steel of half assembled-foam concrete assembled wall and its application method
CN107083807A (en) A kind of endplate connections node
CN105735526B (en) Mountable double-deck steel plate with ductility energy consumption connector waves wall
CN215166607U (en) Assembled square steel tube concrete column and girder steel concatenation muffjoint
CN204919805U (en) A bundled tube steel framework composition structure that is used for industrialization assembled steel construction house
CN207314550U (en) The banding heavier-duty node that H profile steel beam is connected with wide steel core concrete column short side
CN106436926A (en) Square steel tube column-H-shaped steel beam end-plate connecting node
CN201224946Y (en) Prefabricated net frame sandwich wall board
CN211285977U (en) Tapered weakening beam column joint for high-strength steel beam flange
CN111691580A (en) Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall
CN209457263U (en) A kind of assembling type steel structure beam slab connecting structure
CN110670732A (en) Connection node of steel truss with inverted V-shaped section and reinforced concrete structure and construction method
CN106245819A (en) Cellular steel case concrete walls plate module and preparation method thereof and body of wall
CN115749059A (en) Buckling-restrained steel plate concrete composite wall
CN205776898U (en) Overall assembled reinforced concrete shear wall structure system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090121

Termination date: 20091130