CN111691580A - Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall - Google Patents

Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall Download PDF

Info

Publication number
CN111691580A
CN111691580A CN202010537583.7A CN202010537583A CN111691580A CN 111691580 A CN111691580 A CN 111691580A CN 202010537583 A CN202010537583 A CN 202010537583A CN 111691580 A CN111691580 A CN 111691580A
Authority
CN
China
Prior art keywords
cavity
vertical
wall
prefabricated
steel bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010537583.7A
Other languages
Chinese (zh)
Inventor
肖明
韩文龙
郁银泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Institute of Building Standard Design and Research Co Ltd
Original Assignee
China Institute of Building Standard Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Institute of Building Standard Design and Research Co Ltd filed Critical China Institute of Building Standard Design and Research Co Ltd
Priority to CN202010537583.7A priority Critical patent/CN111691580A/en
Publication of CN111691580A publication Critical patent/CN111691580A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

一种空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱及预制墙,在预制混凝土壁板中仅配置小直径的边缘构件竖向构造钢筋与边缘构件箍筋、拉筋形成暗柱钢筋骨架,边缘构件竖向构造钢筋上下端均不伸出预制混凝土壁板、不参与结构受力计算;在空腔内配置单排大直径竖向钢筋作为边缘构件竖向受力钢筋,参与结构受力计算,上下层边缘构件竖向受力钢筋在空腔内采用钢筋接头连接,受力可靠,且不增加墙体竖向钢筋用量,现场浇筑空腔内后浇混凝土形成叠合暗柱。上述构造生产阶段可避免边缘构件竖向钢筋对预制墙产生干扰,便于预制墙生产;现场安装阶段可避免叠合暗柱内双排竖向连接钢筋对预制墙安装精度的影响,有助于提高预制墙安装效率和安装精度。

Figure 202010537583

A superimposed concealed column and a prefabricated wall in which a large-diameter edge member vertical stress steel bar is arranged in a cavity, and only a small-diameter edge member vertical structural steel bar, an edge member stirrup and a tie bar are arranged in a precast concrete wall panel. Concealed column steel skeleton, the upper and lower ends of the vertical structural steel bars of the edge members do not protrude from the precast concrete panels, and do not participate in the calculation of the structural stress; a single row of large-diameter vertical steel bars are arranged in the cavity as the vertical stress steel bars of the edge members. Participate in the calculation of the structural force. The vertical force steel bars of the upper and lower edge members are connected by steel joints in the cavity, and the force is reliable, and the amount of vertical steel bars in the wall is not increased. Concrete is poured in the cavity after pouring on site to form a superimposed dark layer. column. The above-mentioned structural production stage can avoid the interference of the vertical steel bars of the edge members on the prefabricated wall, which is convenient for the production of the prefabricated wall; in the field installation stage, the influence of the double-row vertical connecting steel bars in the superimposed hidden column on the installation accuracy of the prefabricated wall can be avoided, which is helpful to improve the installation accuracy of the prefabricated wall. Prefab wall installation efficiency and installation accuracy.

Figure 202010537583

Description

空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱及预 制墙Superimposed concealed column and prefab make walls

技术领域technical field

本发明属于建筑技术领域,涉及预制剪力墙,特别涉及一种空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱及预制墙。The invention belongs to the technical field of construction, and relates to a prefabricated shear wall, in particular to a superimposed concealed column and a prefabricated wall in which a large-diameter edge member vertical stress steel bar is arranged in a cavity.

背景技术Background technique

现有装配整体式剪力墙结构根据其采用的预制墙形式可分为全预制剪力墙结构和叠合剪力墙结构。叠合剪力墙结构采用内部带有空腔的预制剪力墙,两侧预制混凝土壁板通过钢筋桁架、混凝土纵肋或平面钢筋焊接网连接为整体,如双面叠合剪力墙、EVE预制空心墙板、SPCS钢筋焊接网叠合剪力墙及纵肋叠合剪力墙等。叠合剪力墙竖向钢筋采用间接搭接连接,相较全预制剪力墙,加工、安装精度要求低,可有效降低预制墙连接成本,连接质量可控,是一类符合当下中国国情的装配式混凝土结构体系。The existing assembled integral shear wall structure can be divided into a fully prefabricated shear wall structure and a superimposed shear wall structure according to the prefabricated wall form it adopts. The composite shear wall structure adopts a prefabricated shear wall with a cavity inside, and the prefabricated concrete panels on both sides are connected as a whole by steel trusses, concrete longitudinal ribs or plane steel welded mesh, such as double-sided composite shear walls, EVE Prefabricated hollow wall panels, SPCS reinforced welded mesh superimposed shear walls and longitudinal rib superimposed shear walls, etc. The vertical reinforcement of the superimposed shear wall adopts indirect lap connection. Compared with the full prefabricated shear wall, the processing and installation accuracy requirements are lower, which can effectively reduce the connection cost of the prefabricated wall, and the connection quality is controllable. Prefabricated concrete structural system.

实际工程中,预制墙采用叠合暗柱难以避免,目前叠合暗柱中预制墙边缘构件竖向钢筋设置于预制墙中,不伸出预制墙顶面、底面,在预制墙空腔内设置边缘构件附加竖向连接钢筋与上下层预制墙内边缘构件竖向钢筋间接搭接,实现上下层预制墙内边缘构件竖向钢筋的连接。采用上述叠合暗柱构造,将带来以下问题:1)国内住宅剪力墙厚度往往较小,叠合剪力墙空腔沿墙体厚度方向的尺寸多不大于100mm,在空腔内布设双排边缘构件附加竖向连接钢筋,加之其他水平钢筋,导致暗柱空腔内钢筋密集,现场浇筑混凝土时,叠合暗柱空腔内后浇混凝土无法振捣,实际工程中大范围采用自密实混凝土成本较高;2) 边缘构件竖向钢筋直径较大,预制墙预制加工困难、质量难以控制;3)在预制墙空腔内设置边缘构件附加竖向连接钢筋与上下层预制墙内边缘构件竖向钢筋间接搭接,导致钢筋用量增加。In actual engineering, it is unavoidable to use superimposed concealed columns for prefabricated walls. At present, vertical steel bars on the edge components of prefabricated walls in superimposed concealed columns are set in the prefabricated walls, instead of protruding from the top and bottom surfaces of the prefabricated walls, but in the cavity of the prefabricated walls. The additional vertical connecting steel bars of the edge members are indirectly overlapped with the vertical steel bars of the inner edge members of the upper and lower prefabricated walls, so as to realize the connection of the vertical steel bars of the inner edge members of the upper and lower prefabricated walls. The use of the above-mentioned superimposed hidden column structure will bring the following problems: 1) The thickness of domestic residential shear walls is often small, and the size of the superimposed shear wall cavity along the thickness direction of the wall is usually no more than 100mm, and the layout in the cavity The double-row edge members are attached with vertical connecting steel bars and other horizontal steel bars, resulting in dense steel bars in the cavity of the dark column. The cost of dense concrete is high; 2) The diameter of the vertical steel bars of the edge members is large, and the prefabricated wall is difficult to process and quality; The vertical reinforcement of the component is indirectly lapped, resulting in an increase in the amount of reinforcement.

发明内容SUMMARY OF THE INVENTION

为了克服上述现有叠合暗柱构造的缺点,本发明的目的在于提供一种空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱及预制墙,集成了叠合剪力墙连接成本低、连接质量易于控制、预制墙自重轻及现场安装效率高等优势,在预制墙暗柱空腔内配置单排大直径竖向钢筋作为墙体边缘构件竖向受力钢筋,预制墙暗柱内仅配置小直径竖向构造钢筋,可实现预制墙钢筋笼的标准化,有助于提高预制墙生产效率、便于质量控制,同时空腔内大直径边缘构件竖向受力钢筋采用钢筋接头直接连接,受力可靠,保证墙体竖向钢筋用量不增加,现场安装阶段可避免叠合暗柱内双排边缘构件附加竖向连接钢筋对预制墙安装精度的影响,有助于提高预制墙安装效率和安装精度。In order to overcome the above-mentioned shortcomings of the existing superimposed concealed column structure, the purpose of the present invention is to provide a superimposed concealed column and a prefabricated wall in which a large-diameter edge member vertical stress steel bar is arranged in a cavity, which integrates a superimposed shear wall. The advantages of low connection cost, easy control of connection quality, light weight of prefabricated walls and high efficiency of on-site installation. A single row of large-diameter vertical steel bars are arranged in the cavity of hidden columns of prefabricated walls as vertical stress steel bars for wall edge components. Only small-diameter vertical structural steel bars are arranged in the column, which can realize the standardization of prefabricated wall steel cages, help to improve the production efficiency of prefabricated walls, and facilitate quality control. Connection, reliable force, ensuring that the amount of vertical steel bars in the wall does not increase, and during the on-site installation stage, it can avoid the influence of the additional vertical connecting steel bars on the double-row edge members in the superimposed concealed column on the installation accuracy of the prefabricated wall, which helps to improve the installation of the prefabricated wall. Efficiency and installation accuracy.

为了实现上述目的,本发明采用的技术方案是:In order to achieve the above object, the technical scheme adopted in the present invention is:

空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,包括两侧的预制混凝土壁板11,两预制混凝土壁板11之间形成空腔12,在预制混凝土壁板11中仅配置小直径的边缘构件竖向构造钢筋13与边缘构件箍筋14、边缘构件拉筋 15形成暗柱钢筋骨架,边缘构件竖向构造钢筋13上下端均不伸出预制混凝土壁板11、不参与结构受力计算;在空腔12内配置单排大直径竖向钢筋作为边缘构件竖向受力钢筋16,参与结构受力计算,上下层边缘构件竖向受力钢筋16在空腔12内采用钢筋接头161连接,现场浇筑空腔12内后浇混凝土,形成叠合暗柱。A superimposed dark column with a large-diameter edge member vertically bearing steel reinforcement is arranged in the cavity, including prefabricated concrete panels 11 on both sides, and a cavity 12 is formed between the two precast concrete panels 11. In the precast concrete panel 11, only Small-diameter vertical structural steel bars 13 for edge members, edge member stirrups 14, and edge member tie bars 15 are arranged to form a dark-column steel skeleton. The upper and lower ends of the edge member vertical structural steel bars 13 do not protrude from the precast concrete panel 11 and do not participate in Structural stress calculation; configure a single row of large-diameter vertical steel bars in the cavity 12 as the edge member vertical stress steel bar 16 to participate in the structural stress calculation, and the upper and lower edge member vertical stress steel bars 16 are used in the cavity 12. The steel bar joints 161 are connected, and concrete is poured into the cavity 12 on site to form a superimposed dark column.

一般来说,所述小直径是指直径不大于10mm,大直径是指直径不低于18 mm。Generally speaking, the small diameter means that the diameter is not more than 10 mm, and the large diameter means that the diameter is not less than 18 mm.

优选地,所述边缘构件竖向受力钢筋16在空腔12内沿墙体厚度中线单排布置。Preferably, the vertical stress reinforcement bars 16 of the edge members are arranged in a single row along the center line of the wall thickness in the cavity 12 .

优选地,所述边缘构件竖向受力钢筋16配筋面积满足剪力墙正截面受压承载力验算要求,或按照同一强度等级钢筋等面积代换的原则代替传统剪力墙的多根边缘构件竖向钢筋,或满足现行规范对边缘构件竖向钢筋的最小配筋率要求。Preferably, the reinforcement area of the vertical stress-bearing steel bars 16 of the edge member meets the requirements for checking the compressive bearing capacity of the shear wall, or replaces multiple edges of the traditional shear wall according to the principle of equal-area replacement of steel bars of the same strength grade. The vertical reinforcement of the member, or meet the minimum reinforcement ratio requirements of the current code for the vertical reinforcement of the edge member.

优选地,在空腔12内,上下层边缘构件竖向受力钢筋16在同一高度采用钢筋接头161连接,即同一连接区段内接头百分率为100%;或者错开距离采用钢筋接头161连接,避免在同一连接区段100%连接,降低对接头性能的要求。Preferably, in the cavity 12, the vertical stress-bearing steel bars 16 of the upper and lower edge members are connected at the same height by steel joints 161, that is, the percentage of joints in the same connection section is 100%; 100% connection in the same connection section, reducing the requirements for joint performance.

优选地,当边缘构件竖向受力钢筋16直径大于28mm时,可在空腔12内配置三根或三根以上的边缘构件竖向受力钢筋16,以避免钢筋直径过大。Preferably, when the diameter of the vertical force-bearing steel bar 16 of the edge member is larger than 28 mm, three or more vertical force-bearing steel bars 16 of the edge member can be arranged in the cavity 12 to avoid the diameter of the steel bar being too large.

优选地,预制墙水平接缝构造与现有叠合剪力墙水平接缝构造一致,预制墙底部水平接缝31设置在楼面标高处,预制墙底面距楼板顶面的距离不小于50 mm,以为保证预制墙底部水平接缝31处后浇混凝土的密实性。Preferably, the horizontal joint structure of the prefabricated wall is consistent with the horizontal joint structure of the existing laminated shear wall, the horizontal joint 31 at the bottom of the prefabricated wall is set at the floor elevation, and the distance between the bottom surface of the prefabricated wall and the top surface of the floor slab is not less than 50 mm , in order to ensure the compactness of the post-cast concrete at the horizontal joint 31 at the bottom of the prefabricated wall.

本发明还提供了采用所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱的预制墙体,包括叠合暗柱区域1和墙身区域2,叠合暗柱区域1采用所述叠合暗柱,预制混凝土壁板11延伸形成墙身区域2。The present invention also provides a prefabricated wall using a superimposed concealed column in which the large-diameter edge member vertical stress steel bars are arranged in the cavity, including a superimposed concealed column area 1 and a wall body area 2, and a superimposed concealed column area 1 Using the superimposed hidden column, the prefabricated concrete wall panel 11 extends to form the wall body area 2 .

优选地,在本层空腔12内边缘构件竖向受力钢筋16与下层伸出的边缘构件竖向受力钢筋16采用钢筋接头161连接后吊装;或在预制墙体安装完成后,在叠合暗柱区域1的空腔12内穿设边缘构件竖向受力钢筋16,其中预制混凝土壁板11根部预留有缺口17作为安装手孔,在安装手孔内采用钢筋接头161实现上下层边缘构件竖向受力钢筋16的连接,缺口17可采用定型占位块占位形成。Preferably, the vertical stress steel bars 16 of the edge members in the cavity 12 of this layer and the vertical stress steel bars 16 of the edge members extending from the lower layer are connected by steel joints 161 and then hoisted; In the cavity 12 of the closed column area 1, the vertical stress steel bars 16 of the edge members are pierced, and a gap 17 is reserved at the root of the prefabricated concrete wall plate 11 as an installation hand hole, and the steel bar joint 161 is used in the installation hand hole to realize the upper and lower floors. For the connection of the vertical stress-bearing steel bars 16 of the edge members, the gap 17 can be formed by using a stereotyped spacer block.

优选地,所述预制混凝土壁板11采用钢筋桁架23连接,或采用混凝土纵肋或平面钢筋焊接网连接。Preferably, the prefabricated concrete wall panels 11 are connected by steel trusses 23, or connected by concrete longitudinal ribs or plane steel welded mesh.

进一步地,将预制混凝土壁板11、保温板4及预制混凝土外叶板5在工厂整体预制,形成预制夹心保温叠合墙,实现外墙装饰、保温及结构一体化;预制混凝土壁板11与预制混凝土外叶板5采用保温拉结件6拉结,仅在墙体内侧设置预制混凝土壁板11。Further, the prefabricated concrete wall panels 11, the thermal insulation panels 4 and the prefabricated concrete outer leaf panels 5 are prefabricated as a whole in the factory to form a prefabricated sandwich thermal insulation laminated wall to achieve exterior wall decoration, thermal insulation and structural integration; the prefabricated concrete wall panels 11 and The prefabricated concrete outer leaf plate 5 is tied by the thermal insulation tie member 6, and the precast concrete wall plate 11 is only provided on the inner side of the wall.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

(1)本发明预制墙空腔内布设单排大直径边缘构件竖向受力钢筋,大直径边缘构件竖向受力钢筋沿墙体厚度方向居中布置、与预制混凝土壁板净距大,可避免已有叠合暗柱构造中双排边缘构件附加竖向连接钢筋对预制墙安装精度的影响,有助于提高预制墙安装效率和安装精度。(1) A single row of large-diameter edge member vertical stress steel bars are arranged in the prefabricated wall cavity of the present invention, and the large-diameter edge member vertical stress steel bars are centrally arranged along the wall thickness direction, and the clear distance from the precast concrete panel is large, which can be It avoids the influence of the additional vertical connecting steel bars of the double-row edge members on the installation accuracy of the prefabricated wall in the existing superimposed concealed column structure, and helps to improve the installation efficiency and installation accuracy of the prefabricated wall.

(2)本发明叠合暗柱空腔内钢筋间距大,便于后浇混凝土的振捣,有助于保证后浇混凝土浇筑质量,同时不对空腔内其他钢筋的布设产生干扰。(2) The space between the reinforcing bars in the cavity of the superimposed concealed column of the present invention is large, which facilitates the vibration of the post-cast concrete, helps to ensure the quality of the post-cast concrete, and does not interfere with the layout of other steel bars in the cavity.

(3)本发明预制墙空腔内布设单排大直径边缘构件竖向受力钢筋采用钢筋直螺纹接头连接,连接技术成熟且传力性能好,可保证预制墙在大变形下的抗震性能,同时避免边缘构件竖向钢筋的间接搭接,有助于控制边缘构件竖向钢筋用量。(3) In the prefabricated wall cavity of the present invention, a single row of large-diameter edge member vertical stress steel bars are connected by steel straight thread joints. The connection technology is mature and the force transmission performance is good, which can ensure the seismic performance of the prefabricated wall under large deformation. At the same time, it avoids the indirect overlap of vertical steel bars of edge members, which helps to control the amount of vertical steel bars of edge members.

(4)本发明预制墙暗柱内仅配置小直径竖向构造钢筋,可实现预制墙钢筋笼的标准化,有助于提高预制墙生产效率、便于质量控制。(4) Only small-diameter vertical structural steel bars are arranged in the prefabricated wall concealed column of the present invention, which can realize the standardization of the prefabricated wall reinforcement cage, help to improve the production efficiency of the prefabricated wall and facilitate quality control.

(5)本发明空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱构造通用性强,可用于优化现有双面叠合剪力墙、EVE预制空心墙板、SPCS钢筋焊接网叠合剪力墙及纵肋叠合剪力墙等预制叠合剪力墙的暗柱构造。(5) The superimposed concealed column structure with the vertically stressed steel bars of the large-diameter edge members in the cavity of the present invention has strong versatility, and can be used to optimize the existing double-sided superimposed shear walls, EVE prefabricated hollow wall panels, and SPCS steel reinforcement welding. Concealed column structure of prefabricated superimposed shear walls such as mesh superimposed shear walls and longitudinal rib superimposed shear walls.

附图说明Description of drawings

图1为本发明一种空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱及预制墙的三维示意图。FIG. 1 is a three-dimensional schematic diagram of a superimposed concealed column and a prefabricated wall with a large-diameter edge member vertically bearing steel bars arranged in a cavity according to the present invention.

图2为图1所示预制空心叠合剪力墙的正视图。FIG. 2 is a front view of the prefabricated hollow composite shear wall shown in FIG. 1 .

图3为图2中A-A截面示意图。FIG. 3 is a schematic view of the section A-A in FIG. 2 .

图4为图2中B-B截面示意图。FIG. 4 is a schematic cross-sectional view of B-B in FIG. 2 .

图5为本发明上下层预制墙空腔内边缘构件竖向受力钢筋连接、水平接缝的构造示意图。FIG. 5 is a schematic structural diagram of the vertical stress steel bar connection and the horizontal joint of the inner edge members of the upper and lower prefabricated wall cavity according to the present invention.

图6为本发明空腔内边缘构件竖向受力钢筋错开一定距离采用钢筋接头连接的预制墙三维示意图。6 is a three-dimensional schematic diagram of a prefabricated wall in which the vertical force-bearing steel bars of the inner edge members of the cavity are staggered by a certain distance and connected by steel bar joints according to the present invention.

图7为本发明空腔内边缘构件竖向受力钢筋错开一定距离采用钢筋接头连接的预制墙正视图。FIG. 7 is a front view of a prefabricated wall in which the vertical force-bearing steel bars of the inner edge members of the cavity are staggered by a certain distance and connected by steel bar joints.

图8为叠合暗柱空腔内配置三根边缘构件竖向受力钢筋的预制墙三维示意图。Fig. 8 is a three-dimensional schematic diagram of a prefabricated wall with three vertical stress-bearing steel bars of edge members arranged in the cavity of the superimposed concealed column.

图9为图8中C-C截面示意图。FIG. 9 is a schematic cross-sectional view of C-C in FIG. 8 .

图10为图1、图2所示边缘构件箍筋采用普通135°弯钩箍筋的截面示意图。Fig. 10 is a schematic cross-sectional view of the edge member stirrups shown in Figs. 1 and 2 using common 135° hook stirrups.

图11为先吊装预制墙、后穿设空腔内边缘构件竖向受力钢筋的预制墙三维示意图。Figure 11 is a three-dimensional schematic diagram of the prefabricated wall in which the prefabricated wall is first hoisted, and then the vertical stress steel bars of the inner edge members of the cavity are passed through.

图12为先吊装预制墙、后穿设空腔内边缘构件竖向受力钢筋的预制墙正视图。Figure 12 is a front view of the prefabricated wall in which the prefabricated wall is hoisted first, and then the vertical stress steel bars of the inner edge members of the cavity are passed through.

图13为图12中D-D截面示意图。FIG. 13 is a schematic cross-sectional view of D-D in FIG. 12 .

图14为图11、图12、图13所示预制墙的水平接缝的构造示意图。FIG. 14 is a schematic structural diagram of the horizontal joint of the prefabricated wall shown in FIG. 11 , FIG. 12 and FIG. 13 .

图15为图1、图2所示预制墙的装饰、保温、结构一体化改进型,即预制夹心保温叠合墙的截面示意图。Fig. 15 is a schematic cross-sectional view of the prefabricated wall shown in Figs. 1 and 2, which is an improved decoration, thermal insulation, and structural integration, that is, a prefabricated sandwich thermal insulation laminated wall.

图16为叠合暗柱空腔内配置三根边缘构件竖向受力钢筋的预制夹心保温叠合墙的截面示意图。16 is a schematic cross-sectional view of a prefabricated sandwich thermal insulation laminated wall with three vertical stress-bearing steel bars for edge members arranged in the cavity of the superimposed concealed column.

图17为图1、图2所示预制墙的对比例,即现有边缘构件竖向钢筋搭接连接预制墙的三维示意图。Fig. 17 is a comparative example of the prefabricated wall shown in Fig. 1 and Fig. 2 , that is, a three-dimensional schematic diagram of the existing edge member's vertical steel bar lap connection to the prefabricated wall.

图18为图17中E-E截面示意图。FIG. 18 is a schematic cross-section E-E of FIG. 17 .

图19为图18所示对比例的上下层预制墙边缘构件竖向钢筋搭接连接、水平接缝的构造示意图。FIG. 19 is a schematic structural diagram of the vertical steel bar lap connection and the horizontal joint of the edge members of the upper and lower prefabricated walls of the comparative example shown in FIG. 18 .

图中:1-叠合暗柱区域;2-墙身区域;11-预制混凝土壁板;12-空腔;13- 边缘构件竖向构造钢筋;14-边缘构件箍筋;15-边缘构件拉筋;16-边缘构件竖向受力钢筋;161-钢筋接头;17-缺口;18-预制墙内边缘构件受力竖向钢筋;19- 边缘构件附加竖向连接钢筋;21-水平分布钢筋;22-竖向分布钢筋;23-钢筋桁架;31-预制墙底部水平接缝;32-预制墙顶部水平后浇带;33-预制楼板;4-保温板;5-预制混凝土外叶板;6-拉结件。In the figure: 1- superimposed concealed column area; 2- wall body area; 11- precast concrete siding; 12- cavity; 13- vertical structural reinforcement of edge members; 14- stirrups of edge members; 15- tension of edge members Reinforcing bar; 16 - vertical stress bar for edge members; 161 - bar joint; 17 - gap; 18 - stress vertical bar for edge members in prefabricated walls; 19 - additional vertical connection bar for edge members; 21 - horizontal distribution bar; 22- vertical distribution of steel bars; 23- steel bar trusses; 31- horizontal joints at the bottom of prefabricated walls; 32- horizontal post-casting strips at the top of prefabricated walls; 33- prefabricated floor slabs; 4- thermal insulation boards; - Knots.

具体实施方式Detailed ways

下面结合附图和实施例详细说明本发明的实施方式。The embodiments of the present invention will be described in detail below with reference to the accompanying drawings and examples.

如图1、图2、图3和图4所示,本发明首先提供了一种空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,其包括两侧的预制混凝土壁板11,两预制混凝土壁板11之间形成空腔12。在预制混凝土壁板11中仅配置小直径的边缘构件竖向构造钢筋13,边缘构件竖向构造钢筋13与边缘构件箍筋14、边缘构件拉筋15形成暗柱钢筋骨架,边缘构件竖向构造钢筋13上下端均不伸出预制混凝土壁板11、不参与结构受力计算;边缘构件箍筋14、边缘构件拉筋15构造可与普通现浇剪力墙保持一致。As shown in Fig. 1, Fig. 2, Fig. 3 and Fig. 4, the present invention first provides a superimposed concealed column with a large-diameter edge member vertically stressed steel bar in a cavity, which includes precast concrete wall panels on both sides 11. A cavity 12 is formed between the two precast concrete wall panels 11 . Only small-diameter vertical structural steel bars 13 for edge members are arranged in the precast concrete panel 11. The vertical structural steel bars 13 for edge members, stirrups 14 for edge members, and tie bars 15 for edge members form a dark column steel skeleton. The upper and lower ends of the steel bars 13 do not protrude from the precast concrete wall 11 and do not participate in the calculation of the structural force; the structure of the edge member stirrups 14 and the edge member tension bars 15 can be consistent with ordinary cast-in-place shear walls.

在空腔12内配置单排大直径竖向钢筋作为边缘构件竖向受力钢筋16,参与结构受力计算,上下层边缘构件竖向受力钢筋16在空腔12内采用钢筋接头161 直接连接,受力可靠,有助于控制钢筋用量。即,本发明采用布设于空腔12内的大直径的边缘构件竖向受力钢筋16代替现有叠合剪力墙布设于预制混凝土壁板11内的多根直径较小的预制墙内边缘构件受力竖向钢筋18。A single row of large-diameter vertical steel bars are arranged in the cavity 12 as the vertical stress-bearing steel bars 16 of the edge members to participate in the calculation of the structural force. , the force is reliable, and it helps to control the amount of steel bars. That is, the present invention uses the large-diameter edge member vertical stress reinforcement bars 16 arranged in the cavity 12 to replace the inner edges of a plurality of smaller-diameter prefabricated walls arranged in the prefabricated concrete panel 11 in the existing superimposed shear wall The component is subjected to vertical reinforcement 18.

本发明中,将小直径限定为直径不大于10mm,大直径限定为直径不低于 18mm。本领域技术人员应该知晓,可以根据上述功能要求,给出类似的参数限定。In the present invention, the small diameter is limited to a diameter of not more than 10 mm, and the large diameter is limited to a diameter of not less than 18 mm. Those skilled in the art should know that similar parameter definitions can be given according to the above functional requirements.

其中,参考图2、图3、图4和图5,边缘构件竖向受力钢筋16在空腔12 内可沿墙体厚度中线单排布置,其配筋面积满足剪力墙正截面受压承载力验算要求,或按照同一强度等级钢筋等面积代换的原则代替传统剪力墙的多根边缘构件竖向钢筋,或满足现行规范对边缘构件竖向钢筋的最小配筋率要求。2 , 3 , 4 and 5 , the vertical stress reinforcement bars 16 of the edge members can be arranged in a single row along the center line of the wall thickness in the cavity 12 , and the reinforcement area satisfies the compression force of the normal section of the shear wall. Bearing capacity check requirements, or replace the vertical reinforcement of multiple edge members of traditional shear walls according to the principle of equal-area replacement of steel bars of the same strength grade, or meet the minimum reinforcement ratio requirements of the current code for the vertical reinforcement of edge members.

现场浇筑空腔12内后浇混凝土,即形成叠合暗柱。借助上述构造,可实现预制墙钢筋笼的标准化,有助于提高预制墙生产效率、便于质量控制。Concrete is poured into the cavity 12 after pouring on site, that is, a superimposed dark column is formed. With the aid of the above structure, the standardization of the reinforcement cage of the prefabricated wall can be realized, which is helpful to improve the production efficiency of the prefabricated wall and facilitate the quality control.

在空腔12内,上下层边缘构件竖向受力钢筋16可在同一高度采用钢筋接头161连接,即同一连接区段内接头百分率为100%,此时钢筋接头161性能应满足现行规范的要求;也可错开距离采用钢筋接头161连接,避免在同一连接区段100%连接,降低对钢筋接头161性能的要求,如图6和图7所示。In the cavity 12, the vertical stress steel bars 16 of the upper and lower edge members can be connected at the same height by the steel bar joints 161, that is, the percentage of joints in the same connection section is 100%. At this time, the performance of the steel bar joints 161 should meet the requirements of the current specification. ; It is also possible to stagger the distance and use the steel bar joint 161 to connect, avoid 100% connection in the same connection section, and reduce the performance requirements of the steel bar joint 161, as shown in Figure 6 and Figure 7.

当满足剪力墙正截面受压承载力验算要求所需配筋面积较大时,按照图1、图2配置两根边缘构件竖向受力钢筋16会导致钢筋直径较大,不利于钢筋接头 161施工及空腔12内后浇混凝土浇筑,此时,如图8和图9所示,可在空腔12 内配置三根或三根以上的边缘构件竖向受力钢筋16以控制其直径,配筋原则同前。When the reinforcement area required to meet the requirements for checking the compressive bearing capacity of the normal section of the shear wall is large, the arrangement of the two vertical stress reinforcement bars 16 of the edge members according to Figure 1 and Figure 2 will lead to a larger diameter of the reinforcement bar, which is not conducive to the reinforcement joints. 161 Construction and post-cast concrete pouring in the cavity 12. At this time, as shown in Figures 8 and 9, three or more vertical stress steel bars 16 for edge members can be arranged in the cavity 12 to control its diameter. The principle of tendons is the same as before.

本发明中边缘构件箍筋14可采用焊接封闭箍,考虑到空腔12内配置边缘构件竖向受力钢筋16后,空腔12内部钢筋较少,钢筋相互干扰较小,如图10 所示,边缘构件箍筋14也可采用普通135°弯钩箍筋。In the present invention, the edge member stirrups 14 can be welded closed hoop. Considering that after the edge member vertical stress steel bars 16 are arranged in the cavity 12, there are fewer steel bars in the cavity 12, and the mutual interference between the steel bars is small, as shown in FIG. 10 . , the edge member stirrups 14 can also use ordinary 135° hook stirrups.

钢筋接头161宜优先采用直螺纹接头,在技术可靠的前提下,也可采用其他形式的钢筋接头。The steel bar joint 161 should preferably use straight thread joints, and other forms of steel bar joints can also be used under the premise of reliable technology.

参考图1、图2、图3、图4,本发明还提供了采用所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱的预制墙体,包括叠合暗柱区域1和墙身区域2,叠合暗柱区域1采用所述叠合暗柱,预制混凝土壁板11延伸形成墙身区域2。墙身区域2构造与现有叠合剪力墙构造一致,上下层预制墙的竖向分布钢筋22采用间接搭接连接。Referring to Figures 1, 2, 3, and 4, the present invention also provides a prefabricated wall of a superimposed concealed column with a large-diameter edge member vertically stressed steel bar in the cavity, including a superimposed concealed column area. 1 and the wall body area 2, the superimposed dark column area 1 adopts the superimposed dark column, and the precast concrete wall panel 11 extends to form the wall body area 2. The structure of the wall body area 2 is consistent with the structure of the existing superimposed shear wall, and the vertically distributed steel bars 22 of the upper and lower prefabricated walls are connected by indirect lap joints.

本发明预制墙水平接缝构造与现有叠合剪力墙水平接缝构造一致,预制墙底部水平接缝31应设置在楼面标高处,为保证预制墙底部水平接缝31处后浇混凝土的密实性,预制墙底面距楼板顶面的距离不宜小于50mm。The horizontal joint structure of the prefabricated wall of the present invention is consistent with the horizontal joint structure of the existing superimposed shear wall. The horizontal joint 31 at the bottom of the prefabricated wall should be set at the floor elevation. In order to ensure that the horizontal joint 31 at the bottom of the prefabricated wall is poured concrete The distance between the bottom surface of the prefabricated wall and the top surface of the floor slab should not be less than 50mm.

本发明预制墙两侧的预制混凝土壁板11可采用钢筋桁架23连接,也可采用混凝土纵肋或平面钢筋焊接网连接,即本发明进一步优化、改进在于叠合暗柱区域1的构造可用于现有双面叠合剪力墙、EVE预制空心墙板、SPCS钢筋焊接网叠合剪力墙及纵肋叠合剪力墙等多种叠合剪力墙,通用性强。The prefabricated concrete wall panels 11 on both sides of the prefabricated wall of the present invention can be connected by steel trusses 23, and can also be connected by concrete longitudinal ribs or plane steel welded meshes. The existing double-sided superimposed shear walls, EVE prefabricated hollow wall panels, SPCS reinforced welded mesh superimposed shear walls and longitudinal rib superimposed shear walls and other superimposed shear walls have strong versatility.

本发明预制墙的预制生产工艺与现有预制墙一致,推荐的现场施工安装工艺包括如下:将本层空腔12内边缘构件竖向受力钢筋16与下层伸出的边缘构件竖向受力钢筋16采用钢筋接头161连接,之后吊装,需注意控制本层空腔12 内边缘构件竖向受力钢筋16的位置,防止其干扰预制墙下落,调整预制墙垂直度、水平度;支设水平接缝31模板,浇筑预制墙空腔12内后浇混凝土,养护拆模。The prefabricated production process of the prefabricated wall of the present invention is consistent with that of the existing prefabricated wall, and the recommended on-site construction and installation process includes the following: the vertical stress steel bar 16 of the inner edge member of the cavity 12 of this layer and the edge member extended from the lower layer are vertically stressed Reinforcing bars 16 are connected by reinforcing bar joints 161, and then hoisted. Care should be taken to control the position of the vertical stress bars 16 of the inner edge members of the cavity 12 on this floor to prevent them from interfering with the falling of the prefabricated wall, and adjust the verticality and levelness of the prefabricated wall; Joints 31 formwork, pour concrete into the cavity 12 of the prefabricated wall, and then maintain and remove the formwork.

若空腔12内的边缘构件竖向受力钢筋16数量较多,不便采用上述现场施工安装工艺时,此时可按图11、图12、图13和图14所示,也可先吊装预制墙,然后穿设本层边缘构件竖向受力钢筋16,此时需在预制混凝土壁板11根部预留缺口17作为安装手孔,在安装手孔内采用钢筋接头161实现上下层边缘构件竖向受力钢筋16的连接,钢筋接头161宜布置在同一高度,以控制预留的缺口17 的大小、便于现场支模。If the number of vertical stress-bearing steel bars 16 of the edge members in the cavity 12 is large, and it is inconvenient to use the above-mentioned on-site construction and installation process, at this time, as shown in Figure 11, Figure 12, Figure 13 and Figure 14, it is also possible to hoist prefabricated steel bars first. Wall, and then wear the vertical stress steel bars 16 of the edge members of this layer. At this time, a gap 17 should be reserved at the root of the precast concrete wall panel 11 as an installation hand hole, and the reinforcement joint 161 is used in the installation hand hole to realize the vertical edge members of the upper and lower layers. For the connection to the stressed steel bar 16, the steel bar joints 161 should be arranged at the same height to control the size of the reserved gap 17 and facilitate on-site formwork support.

如图11、图12、图13所示,缺口17可采用定型占位块占位形成,尺寸应满足空腔12内钢筋接头161的安装施工要求;缺口17范围内,边缘构件竖向构造钢筋3截断,边缘构件箍筋14及水平分布钢筋连续。As shown in Fig. 11, Fig. 12, Fig. 13, the gap 17 can be formed by a shaped spacer block, and the size should meet the installation and construction requirements of the steel bar joint 161 in the cavity 12; within the range of the gap 17, the edge member vertically constructs the steel bar 3 truncation, the edge member stirrups 14 and the horizontal distribution steel bars are continuous.

如图15和图16所示,本发明的预制墙为结构墙,可用于建筑外墙或内墙。还可将预制混凝土壁板11、保温板4及预制混凝土外叶板5在工厂整体预制,形成预制夹心保温叠合墙,实现预制外墙装饰、保温及结构一体化,此时可仅在墙体内侧设置预制混凝土壁板11;预制混凝土壁板11与预制混凝土外叶板5 采用拉结件6拉结。As shown in Fig. 15 and Fig. 16, the prefabricated wall of the present invention is a structural wall, which can be used for an exterior wall or an interior wall of a building. The prefabricated concrete wall panel 11, the thermal insulation panel 4 and the prefabricated concrete outer leaf panel 5 can also be prefabricated as a whole in the factory to form a prefabricated sandwich thermal insulation laminated wall to realize the integration of prefabricated exterior wall decoration, thermal insulation and structure. The inner side of the body is provided with a prefabricated concrete wall plate 11;

在本发明的一个具体实施例中,空腔12内配置两根边缘构件竖向受力钢筋 16,按照同一强度等级钢筋等面积代换的原则代替时,建议的替代原则为1根直径22mm和1根直径20mm的边缘构件竖向受力钢筋16代替6根直径12mm 的钢筋,1根直径28mm和1根直径20mm的边缘构件竖向受力钢筋16代替6 根直径14mm的钢筋,2根直径28mm的边缘构件竖向受力钢筋16代替6根直径的16mm钢筋,2根直径32mm的边缘构件竖向受力钢筋16代替6根直径 18mm的钢筋。In a specific embodiment of the present invention, two vertical stress-bearing steel bars 16 for edge members are arranged in the cavity 12. When replacing them according to the principle of equal-area replacement of steel bars of the same strength grade, the recommended replacement principle is one with a diameter of 22 mm and a 1 vertical stress bar 16 of edge member with diameter of 20mm replaces 6 bars of 12mm diameter, 1 vertical stress bar 16 of edge member with diameter of 28mm and 1 diameter of 20mm replaces 6 bars of 14mm diameter, 2 bars of diameter The 28mm edge member vertical stress steel bar 16 replaces 6 16mm diameter steel bars, and the 2 32mm diameter edge member vertical stress bar 16 replaces the 6 18mm diameter steel bar.

图17、图18、图19为现有边缘构件竖向钢筋搭接连接预制墙的构造,即本发明优选的对比例。将本发明与对比例进行了对比,见表1。Figure 17, Figure 18, Figure 19 show the structure of the existing edge member vertical steel bar lap connection to the prefabricated wall, that is, a preferred comparative example of the present invention. The present invention is compared with the comparative example, see Table 1.

表1Table 1

Figure BDA0002537577620000091
Figure BDA0002537577620000091

综上,本发明暗柱内仅配置箍筋及竖向构造钢筋,竖向构造钢筋上下端均不伸出预制墙、不参与结构受力计算;在空腔内配置单排大直径竖向钢筋作为墙体边缘构件竖向受力钢筋,参与结构受力计算,上下层边缘构件竖向受力钢筋在空腔内采用钢筋接头连接。相较已有构造,采用上述构造预制墙生产阶段可避免边缘构件竖向钢筋对预制墙生产的干扰,便于预制墙生产;现场安装阶段,可避免叠合暗柱内双排竖向连接钢筋对预制墙安装精度的影响,有助于提高预制墙安装效率和安装精度;空腔内大直径边缘构件竖向受力钢筋采用钢筋接头直接连接,受力可靠,且不增加墙体竖向钢筋用量。To sum up, only stirrups and vertical structural steel bars are arranged in the dark column of the present invention, and the upper and lower ends of the vertical structural steel bars do not protrude from the prefabricated wall and do not participate in the calculation of structural force; a single row of large-diameter vertical steel bars are arranged in the cavity. As the vertical stress reinforcement of the wall edge members, it participates in the calculation of the structural stress. The vertical stress reinforcement of the upper and lower edge members is connected by steel joints in the cavity. Compared with the existing structure, the prefabricated wall with the above structure can avoid the interference of the vertical steel bars of the edge components on the production of the prefabricated wall, which is convenient for the production of the prefabricated wall. The influence of the installation accuracy of the prefabricated wall helps to improve the installation efficiency and installation accuracy of the prefabricated wall; the vertical force steel bars of the large-diameter edge members in the cavity are directly connected by steel bar joints, and the force is reliable, and the amount of vertical steel bars in the wall is not increased. .

以上,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到的变化和替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应该以权利要求的保护范围为准。The above are only preferred specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes and substitutions within the technical scope disclosed by the present invention, All should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be subject to the protection scope of the claims.

Claims (10)

1.空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,包括两侧的预制混凝土壁板(11),两预制混凝土壁板(11)之间形成空腔(12),其特征在于,在预制混凝土壁板(11)中仅配置小直径的边缘构件竖向构造钢筋(13)与边缘构件箍筋(14)、边缘构件拉筋(15)形成暗柱钢筋骨架,边缘构件竖向构造钢筋(13)上下端均不伸出预制混凝土壁板(11)、不参与结构受力计算;在空腔(12)内配置单排大直径竖向钢筋作为边缘构件竖向受力钢筋(16),参与结构受力计算,上下层边缘构件竖向受力钢筋(16)在空腔(12)内采用钢筋接头(161)直接连接,现场浇筑空腔(12)内后浇混凝土,形成叠合暗柱。1. A superimposed concealed column with a large-diameter edge member vertically bearing steel reinforcement is arranged in the cavity, including prefabricated concrete panels (11) on both sides, and a cavity (12) is formed between the two prefabricated concrete panels (11), It is characterized in that, in the precast concrete wall plate (11), only small-diameter vertical structural steel bars (13) for edge members, edge member stirrups (14), and edge member tension bars (15) are arranged to form a dark column steel skeleton, and the edge The upper and lower ends of the vertical structural steel bars (13) of the members do not protrude from the prefabricated concrete wall plate (11) and do not participate in the calculation of the structural force; a single row of large-diameter vertical steel bars is arranged in the cavity (12) as the edge member for the vertical support. The force steel bar (16) is involved in the calculation of the structural force. The vertical force steel bar (16) of the upper and lower edge members is directly connected with the steel bar joint (161) in the cavity (12). Concrete, forming superimposed dark columns. 2.根据权利要求1所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,其特征在于,所述小直径是指直径不大于10mm,大直径是指直径不低于18mm。2. The superimposed concealed column with a large-diameter edge member vertically stressed steel bar in the cavity according to claim 1, characterized in that, the small diameter means that the diameter is not greater than 10 mm, and the large diameter means that the diameter is not less than 10 mm. 18mm. 3.根据权利要求1所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,其特征在于,所述边缘构件竖向受力钢筋(16)在空腔(12)内沿墙体厚度中线单排布置。3. The superimposed concealed column with a large-diameter edge member vertically stressed steel bar arranged in the cavity according to claim 1, wherein the edge member vertically stressed steel bar (16) is in the cavity (12) Arranged in a single row along the midline of the wall thickness. 4.根据权利要求1或3所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,其特征在于,所述边缘构件竖向受力钢筋(16)配筋面积满足剪力墙正截面受压承载力验算要求,或按照同一强度等级钢筋等面积代换的原则代替传统剪力墙的多根边缘构件竖向钢筋,或满足现行规范对边缘构件竖向钢筋的最小配筋率要求。4. The superimposed concealed column according to claim 1 or 3, wherein the vertical force-bearing steel bar of the large-diameter edge member is arranged in the cavity, wherein the reinforcement area of the vertical force-bearing steel bar (16) of the edge member is sufficient to meet the shearing requirements. The requirements for checking the compressive bearing capacity of the normal section of the shear wall, or replace the vertical steel bars of multiple edge members of the traditional shear wall according to the principle of equal-area replacement of steel bars of the same strength grade, or meet the minimum allocation of vertical steel bars for edge members in the current code. Muscle rate requirements. 5.根据权利要求1所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,其特征在于,在空腔(12)内,上下层边缘构件竖向受力钢筋(16)在同一高度采用钢筋接头(161)连接,即同一连接区段内接头百分率为100%;或者错开距离采用钢筋接头(161)连接,避免在同一连接区段100%连接,降低对接头性能的要求。5. The superimposed concealed column with a large-diameter edge member vertically stressed steel bar in the cavity according to claim 1, characterized in that, in the cavity (12), the upper and lower edge member vertical stress steel bars (16) ) Use steel bar joints (161) to connect at the same height, that is, the percentage of joints in the same connection section is 100%; or use steel bar joints (161) to connect at staggered distances to avoid 100% connection in the same connection section and reduce the performance of the joints. Require. 6.根据权利要求1所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱,其特征在于,当边缘构件竖向受力钢筋(16)直径大于28mm时,在空腔(12)内配置三根或三根以上的边缘构件竖向受力钢筋(16),以避免钢筋直径过大。6. The superimposed concealed column with a large-diameter edge member vertically stressed steel bar in the cavity according to claim 1, characterized in that, when the edge member vertical stress steel bar (16) diameter is greater than 28mm, in the cavity (12) Three or more vertical stress-bearing steel bars (16) of edge members are arranged in the interior to avoid excessively large diameter of the steel bars. 7.采用权利要求1所述空腔内配置大直径边缘构件竖向受力钢筋的叠合暗柱的预制墙,包括叠合暗柱区域(1)和墙身区域(2),叠合暗柱区域(1)采用所述叠合暗柱,预制混凝土壁板(11)延伸形成墙身区域(2)。7. Adopt the prefabricated wall of the superimposed hidden column with the vertical stress steel bar of the large diameter edge member in the cavity according to claim 1, including the superimposed hidden column area (1) and the wall body area (2). The column area (1) adopts the superimposed dark column, and the prefabricated concrete wall plate (11) extends to form the wall body area (2). 8.根据权利要求7所述预制墙,其特征在于,在本层空腔(12)内边缘构件竖向受力钢筋(16)与下层伸出的边缘构件竖向受力钢筋(16)采用钢筋接头(161)连接后吊装;或在预制墙安装完成后,在叠合暗柱区域(1)的空腔(12)内穿设边缘构件竖向受力钢筋(16),其中预制混凝土壁板(11)根部预留有缺口(17)作为安装手孔,在安装手孔内采用钢筋接头(161)实现上下层边缘构件竖向受力钢筋(16)的连接。8. The prefabricated wall according to claim 7, characterized in that, the vertical stress steel bars (16) of edge members in the cavity (12) of this layer and the vertical stress steel bars (16) of edge members protruding from the lower layer are adopted. The steel bar joint (161) is connected and then hoisted; or after the installation of the prefabricated wall is completed, the vertical stress steel bar (16) of the edge member is penetrated in the cavity (12) of the superimposed concealed column area (1), wherein the prefabricated concrete wall is A gap (17) is reserved at the root of the plate (11) as an installation hand hole, and a steel bar joint (161) is used in the installation hand hole to realize the connection of the vertically stressed steel bars (16) of the upper and lower edge members. 9.根据权利要求7所述预制墙,其特征在于,所述预制混凝土壁板(11)采用钢筋桁架(23)连接,或采用混凝土纵肋或平面钢筋焊接网连接。9 . The prefabricated wall according to claim 7 , wherein the prefabricated concrete wall panels ( 11 ) are connected by steel trusses ( 23 ), or connected by concrete longitudinal ribs or plane steel welded mesh. 10 . 10.根据权利要求7所述预制墙,其特征在于,将预制混凝土壁板(11)、保温板(4)及预制混凝土外叶板(5)在工厂整体预制,形成预制夹心保温叠合墙,实现外墙装饰、保温及结构一体化;预制混凝土壁板(11)与预制混凝土外叶板(5)采用保温拉结件(6)拉结,仅在墙体内侧设置预制混凝土壁板(11)。10. The prefabricated wall according to claim 7, wherein the prefabricated concrete wall panel (11), the thermal insulation panel (4) and the prefabricated concrete outer leaf panel (5) are prefabricated as a whole in a factory to form a prefabricated sandwich thermal insulation composite wall , to realize the integration of exterior wall decoration, heat preservation and structure; the precast concrete wall panel (11) and the precast concrete outer leaf plate (5) are tied by the heat preservation tie member (6), and only the precast concrete wall panel ( 11).
CN202010537583.7A 2020-06-12 2020-06-12 Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall Pending CN111691580A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010537583.7A CN111691580A (en) 2020-06-12 2020-06-12 Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010537583.7A CN111691580A (en) 2020-06-12 2020-06-12 Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall

Publications (1)

Publication Number Publication Date
CN111691580A true CN111691580A (en) 2020-09-22

Family

ID=72480665

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010537583.7A Pending CN111691580A (en) 2020-06-12 2020-06-12 Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall

Country Status (1)

Country Link
CN (1) CN111691580A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112376801A (en) * 2020-12-04 2021-02-19 中国建筑标准设计研究院有限公司 Coincide shear wall edge member of high-efficient configuration vertical reinforcement
CN113323273A (en) * 2021-06-15 2021-08-31 三一筑工科技股份有限公司 Steel reinforcement cage and processing method thereof
TWI777811B (en) * 2021-10-13 2022-09-11 潤弘精密工程事業股份有限公司 Tie bar for shear wall, shear wall and method for constructing the same
CN117403801A (en) * 2023-12-05 2024-01-16 金茂慧创建筑科技(北京)有限公司 Fully prefabricated shear wall equipped with large-diameter vertical load-bearing steel bars

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453013A (en) * 2014-03-11 2015-03-25 朱彤 Prefabricated wall component and fabricated reinforced concrete shear wall
CN204266415U (en) * 2014-10-08 2015-04-15 绍兴宝业西伟德混凝土预制件有限公司 The vertical antidetonation connected node of the prefabricated overlapped shear wall of L-type
CN105937275A (en) * 2016-06-21 2016-09-14 华东建筑设计研究院有限公司 T-shaped shear wall edge member connecting structure
CN108086582A (en) * 2016-11-21 2018-05-29 济南汇富建筑工业有限公司 A kind of prefabricated assembled concrete wallboard for fabricated construction
CN108951955A (en) * 2018-02-06 2018-12-07 中国建筑第八工程局有限公司 An Assembled Integral Reinforced Concrete Combined Shear Wall Structure with Keyway
CN109610684A (en) * 2018-12-03 2019-04-12 清华大学 An efficient reinforcement and connection prefabricated shear wall
CN111119378A (en) * 2020-01-14 2020-05-08 韩静 Prefabricated hollow superposed shear wall with vertical steel bars penetrating through edge members
CN210713390U (en) * 2019-06-25 2020-06-09 美好建筑装配科技有限公司 Vertical through long rib connecting structure of prefabricated double-sided superposed wall
CN212562033U (en) * 2020-06-12 2021-02-19 中国建筑标准设计研究院有限公司 Superposed embedded column with large-diameter vertical stress reinforcing steel bars arranged in cavity and prefabricated wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453013A (en) * 2014-03-11 2015-03-25 朱彤 Prefabricated wall component and fabricated reinforced concrete shear wall
CN204266415U (en) * 2014-10-08 2015-04-15 绍兴宝业西伟德混凝土预制件有限公司 The vertical antidetonation connected node of the prefabricated overlapped shear wall of L-type
CN105937275A (en) * 2016-06-21 2016-09-14 华东建筑设计研究院有限公司 T-shaped shear wall edge member connecting structure
CN108086582A (en) * 2016-11-21 2018-05-29 济南汇富建筑工业有限公司 A kind of prefabricated assembled concrete wallboard for fabricated construction
CN108951955A (en) * 2018-02-06 2018-12-07 中国建筑第八工程局有限公司 An Assembled Integral Reinforced Concrete Combined Shear Wall Structure with Keyway
CN109610684A (en) * 2018-12-03 2019-04-12 清华大学 An efficient reinforcement and connection prefabricated shear wall
CN210713390U (en) * 2019-06-25 2020-06-09 美好建筑装配科技有限公司 Vertical through long rib connecting structure of prefabricated double-sided superposed wall
CN111119378A (en) * 2020-01-14 2020-05-08 韩静 Prefabricated hollow superposed shear wall with vertical steel bars penetrating through edge members
CN212562033U (en) * 2020-06-12 2021-02-19 中国建筑标准设计研究院有限公司 Superposed embedded column with large-diameter vertical stress reinforcing steel bars arranged in cavity and prefabricated wall

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112376801A (en) * 2020-12-04 2021-02-19 中国建筑标准设计研究院有限公司 Coincide shear wall edge member of high-efficient configuration vertical reinforcement
CN113323273A (en) * 2021-06-15 2021-08-31 三一筑工科技股份有限公司 Steel reinforcement cage and processing method thereof
CN113323273B (en) * 2021-06-15 2023-08-04 三一筑工科技股份有限公司 Reinforcement cage and processing method thereof
TWI777811B (en) * 2021-10-13 2022-09-11 潤弘精密工程事業股份有限公司 Tie bar for shear wall, shear wall and method for constructing the same
CN117403801A (en) * 2023-12-05 2024-01-16 金茂慧创建筑科技(北京)有限公司 Fully prefabricated shear wall equipped with large-diameter vertical load-bearing steel bars

Similar Documents

Publication Publication Date Title
CN103015565B (en) Prefabricated and assembled type integrated reinforced concrete load bearing wall and building construction method
CN207878747U (en) A kind of laminated floor slab prefabricated board
CN111691580A (en) Superposed embedded column with large-diameter edge member vertical stress reinforcing steel bars arranged in cavity and prefabricated wall
CN202865991U (en) Assembled monolithic shear wall building structure
CN209397804U (en) A kind of assembled steel frame-composite slim floor
CN104179250B (en) Light-board house system and construction method thereof
WO2013166658A1 (en) Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork
CN101845852A (en) Light steel and light concrete structural system and construction method thereof
CN101503892B (en) Connection nodes between steel reinforced concrete full prefabricated assembly structural shear wall and beam
CN104929294A (en) Concrete composite plate with built-in cross hollow square steel pipes
CN202125104U (en) Residential building system formed by cast-in-place beam columns and prefabricated sandwich concrete wall slabs
CN204370562U (en) A kind of frame structure, frame structure body
CN205171846U (en) Light -duty prefabricated compound roof boarding
CN114075855A (en) Large-span bidirectional prestressed concrete multi-ribbed sandwich composite floor slab
CN201395870Y (en) Connection node between reinforced concrete fully pre-fabricated assembly structural shear wall and beam
CN210713385U (en) Superposed wall provided with hidden beams for connection
CN212562033U (en) Superposed embedded column with large-diameter vertical stress reinforcing steel bars arranged in cavity and prefabricated wall
CN111691583A (en) Vertical post-cast section concentrates superimposed shear wall vertical and horizontal wall connected node structure of arrangement of reinforcement
CN205976215U (en) Compound box roof beam of assembled concrete
CN112695914A (en) Assembly type shear wall structure system and construction method thereof
CN210288698U (en) Core tube structure system with conversion layer
CN212562032U (en) Take entrance to a cave superimposed shear wall to go out muscle connected node structure in side of indulging and violently wall
CN110805165A (en) Assembled row steel pipe concrete composite wall building structure
CN115478609A (en) A prefabricated monolithic concrete space box structure system
CN102733544B (en) Pretension prestress composite beam prefabricated component having gaps and corbels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination