CN100416287C CNB2004100525805A CN200410052580A CN100416287C CN 100416287 C CN100416287 C CN 100416287C CN B2004100525805 A CNB2004100525805 A CN B2004100525805A CN 200410052580 A CN200410052580 A CN 200410052580A CN 100416287 C CN100416287 C CN 100416287C
Authority
CN
China
Prior art keywords
signal
ups
control module
test
measured
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2004100525805A
Other languages
Chinese (zh)
Other versions
CN1786728A (en
Inventor
周江玲
郭宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinjiang high and new technology development office
Original Assignee
ZTE Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZTE Corp filed Critical ZTE Corp
Priority to CNB2004100525805A priority Critical patent/CN100416287C/en
Publication of CN1786728A publication Critical patent/CN1786728A/en
Application granted granted Critical
Publication of CN100416287C publication Critical patent/CN100416287C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The present invention relates to a method for testing a UPS control unit so as to accelerate the developing and adjusting progress of UPS control software and a system and cause the test to have high safety. The method comprises the processes that a UPS control unit to be tested and a UPS simulating complete machine simulating various working states of a UPS complete machine are provided; the UPS control unit to be tested is arranged on the UPS simulating complete machine; the UPS simulating complete machine executes testing examples and complete the test to the UPS control unit to be tested. The present invention simultaneously discloses a device testing the UPS control unit.

Description

A kind of method and apparatus of testing the UPS control module
[technical field]
The invention belongs to uninterrupted power source (Uninterruptible Power Supply, following abbreviation UPS) technical field, especially relate to a kind of method and apparatus of the UPS of test control module.
[background technology]
The UPS control module is the core ingredient of control UPS entire work process, it mainly is made up of main control chip and some peripheral circuits. and main control chip and software thereof are the cores of UPS control module, mainly finish UPS power part voltage, the collection of data volume such as electric current and temperature, and the simulated data of gathering carried out computing and processing, and the digital signal of gathering carried out logic determines and processing, and send control signal and give power section, action in order to each device of power controlling part, finish the conversion of operation state of UPS, receive and send the human-machine interactive information input simultaneously, the signal output of processing and demonstration etc.
In order to ensure UPS machine system function and performance, often need carry out special test for the UPS control module. test is mainly carried out at its main control chip in house software, comprise the collection of software to UPS complete machine data, computing, whether correctly handle, whether the control to the UPS course of work is correct. but for the programming of UPS control module hardware and Control Software, debugging and test, the conventional at present method of each UPS producer is Control Software all to be write finish, then control module is installed on the UPS complete machine and debugs and test, done following shortcoming like this:
(1) in the UPS initial stage of development stage; the UPS hardware components is not usually also finished design; the UPS Control Software does not just have suitable debug platform like this. therefore; the software developer must wait for after the UPS hardware design is finished just can carry out software debugging, thereby has incured loss through delay the exploitation and the debugging progress of UPS Control Software and total system.
When (2) debugging in the UPS Control Software initial stage of development stage, owing to be just to have finished writing of software, be difficult to guarantee the correctness of Control Software. and that the UPS control module plays a part in complete machine is very crucial, in case the inaccurate or logic error of software sequential takes place, the danger that is easy to cause UPS complete machine components from being damaged even blast is arranged.
(3) because the UPS complete machine usually is to be operated in normal condition, just become difficult to achieve for the test of some abnormal protection states. for example,, utilize actual UPS machine system to test for the detection and the defencive function of faults such as internal components overvoltage.
(4) it is very big to carry out the randomness of software test of control module on the UPS complete machine, may be for different testers, and its method of testing, content measurement be difference to some extent all. and therefore, the comparability of test result is just very poor.
(5) the UPS Control Software is after development﹠ testing finishes, enter maintenance phase, after software is made an amendment, need carry out regression test. and very big in the workload of the enterprising line retrace test of complete machine, the all functions of UPS all must be tested one time, could guarantee the correctness behind this software modification. therefore, this method will spend a large amount of regression test time, and testing efficiency is very low.
(6) test at present all is that the developer finishes disposable the writing of UPS Control Software, and then debug and test. a lot of problems will be left over test phase like this. even some fault that is easy to search at initial stage of development, owing in time do not find, become very hidden to test phase, even can't find, stayed very big hidden danger to software.
(7) in the past when producing for the debugging of control module, produce it to be installed on the complete machine after good to debug if be. owing to the reason of producing causes control module wrong, but producing the commissioning staff does not find, debug in case be installed on the UPS complete machine, just might cause consequences such as complete machine damage, and utilize machine debugging, time-consuming effort again.
[summary of the invention]
For this reason, the present invention will solve the method that first technical matters provides a kind of UPS of test control module.This method can be accelerated the exploitation and the debugging progress of UPS Control Software and system, and has test safety preferably.
Second technical matters that the present invention will solve provides a kind of exploitation and the debugging progress that can accelerate UPS Control Software and system, and has the device of the test UPS control module of test safety preferably.
For solving first technical matters, the invention provides a kind of method of the UPS of test control module, it comprises the steps:
(a) device that provides a UPS control module to be measured and to test the UPS control module is called for short UPS simulation complete machine;
(b) UPS control module to be measured is installed to this UPS simulation complete machine;
(c) use this UPS simulation complete machine implementation of test cases, finish test this UPS control module to be measured.
Wherein, in step (c), said method uses the test main control unit in the UPS simulation complete machine to carry out corresponding test case, to produce and to control three-phase alternating current input voltage pwm signal, corresponding inverter output voltage, current controling signal, DC simulation pwm signal.This three-phase alternating current input voltage pwm signal produces the three-phase alternating voltage signal of required amplitude and is delivered to UPS control module to be measured in order to control three-phase alternating current input voltage generation circuit.This inverter output voltage, current controling signal are in order to the amplitude of the inverter voltage of controlling an inverter output voltage, current generating circuit and electric current and be delivered to UPS control module to be measured.This DC simulation pwm signal produces the DC simulation signal of required level and is delivered to UPS control module to be measured in order to control a DC simulation signal generating circuit.
In addition, in step (c), this method is to send order by serial ports to the test main control unit, so that it carries out corresponding test case.The test main control unit sends to a display unit with test result by serial ports. and this three-phase alternating current input voltage produces the pwm signal that circuit receives the three-phase alternating current input voltage of self-test main control unit, through isolated drive circuit, digital signal and simulating signal are isolated, by low-pass filter pwm signal filtering is become the three-phase alternating voltage signal again, remove direct current component in the above-mentioned signal by block isolating circuit then, through signal amplification circuit the amplitude of the required three-phase alternating voltage signal of signal amplitude and control module to be measured is consistent again, and then sends this control module to be measured to.This inverter output voltage, current generating circuit receives the inverter output voltage of control module to be measured, current controling signal, through isolation drive, filtering, after straight and amplification, obtain an ac voltage signal, this ac voltage signal is divided into some equal portions through a potential-divider network with ac voltage signal, deliver to two multichannels respectively and select the input end of one analog switch, the signal controlling that analog switch is produced by the test main control unit, be used to produce different output voltages and different load currents, send output voltage signal and current signal to control module to be measured again. the DC simulation pwm signal that this DC simulation signal generating circuit acceptance test main control unit sends, pass through isolation drive, filtering, boost and decompression transformation, produce the level identical DC simulation signal required, send this DC simulation signal to control module to be measured again with control module to be measured.
For solving above-mentioned second technical matters, the invention provides a kind of device of the UPS of test control module. it comprises that a test main control unit, a three-phase alternating current input voltage produce circuit, an inverter output voltage, current generating circuit, a DC simulation signal generating circuit.Wherein to test main control unit and be used to carry out corresponding test case, to produce three-phase alternating current input voltage pwm signal, corresponding inverter output voltage, current controling signal, DC simulation pwm signal. this three-phase alternating current input voltage pwm signal produces circuit in order to control three-phase alternating current input voltage and produces the three-phase alternating voltage signal of required amplitude and be delivered to UPS control module to be measured.This inverter output voltage, current controling signal are in order to the amplitude of the inverter voltage of control inverter output voltage, current generating circuit output and electric current and be delivered to UPS control module to be measured, and this DC simulation pwm signal produces the DC simulation signal of required level and is delivered to UPS control module to be measured in order to control DC simulation signal generating circuit.
This device further comprises serial interface circuit, so that the tester sends order by serial interface circuit to the test main control unit, so that it carries out corresponding test case. this test main control unit comprises that three-phase alternating current input voltage PWM ripple generation and control module are to produce above-mentioned three-phase alternating current input voltage pwm signal, generation of one DC PWM ripple and control module are to produce the DC simulation pwm signal, the signal amplitude control module is to produce corresponding inverter output voltage, current controling signal and a control signal produce and processing module is carried out logic determines and processing in order to the control signal that receives UPS control module to be measured and send.
The method and apparatus of above-mentioned test UPS control module has following beneficial effect:
(1) in the UPS initial stage of development stage, the UPS software developer can use this method to fulfil the debugging and the test of UPS Control Software ahead of schedule with this proving installation as the software debugging platform, shortens the construction cycle of UPS Control Software and total system.
(2) carry out regression test for the UPS Control Software, then can utilize the autorun of this device, all test cases are all carried out one time, and test result is shown, can shorten the regression test time, improve testing efficiency.
(3) when producing, can utilize this proving installation to carry out the production debugging of UPS control module, can avoid production mistake because of control module to cause debugging the burning of complete machine of usefulness like this, can also alleviate simultaneously the workload of producing the commissioning staff, shorten debug time, improve the production efficiency of UPS.
[description of drawings]
Fig. 1 is the theory diagram that the present invention tests the device of UPS control module.
Fig. 2 is the functional block diagram of the test main control unit shown in Fig. 1.
Fig. 3 is the UPS three-phase alternating voltage signal generating circuit block diagram shown in Fig. 1.
Fig. 4 is that the UPS inverter output voltage shown in Fig. 1, electric current produce and the control circuit block diagram.
Fig. 5 is the DC simulation signal generating circuit block diagram shown in Fig. 1.
[embodiment]
The main design of the method for test UPS control module of the present invention is to provide a UPS simulation complete machine of simulating the various duties of UPS complete machine, to be used for testing UPS control module to be measured; By using this UPS simulation complete machine implementation of test cases, finish test to this UPS control module to be measured.
Below in conjunction with accompanying drawing the embodiment of the invention is elaborated.
As shown in Figure 1, the device of the test UPS control module of present embodiment mainly comprises the human and machine interface unit that a test main control unit, a UPS three-phase alternating current input voltage produce circuit, a UPS inverter output voltage, electric current generation and control signal circuit, a DC simulation signal generating circuit and be made up of display circuit and serial interface circuit. the test result that this man-machine interface acceptance test main control unit sends by serial ports, be shown to the backstage, and, on LCD and LED, show corresponding content measurement according to the control signal that the test main control unit sends.
Above-mentioned test main control unit is the core of this proving installation.Please refer to Fig. 2, the test main control unit is a DSP signal processing chip in the present embodiment, mainly comprises following functional module: three-phase alternating current PWM ripple generation and control module, signal amplitude control module, the generation of DC PWM ripple and control module, control signal generation and processing module and display module. it is mainly used in finishes following function: the generation and the control of (1) UPS three-phase alternating current input voltage PWM ripple; (2) generation of UPS inverter output voltage current amplitude control signal; (3) generation and the control of UPS DC simulation signal PWM ripple; (4) receive the control signal that UPS control module to be measured sends and carry out logic determines and processing; (5) demonstration of man-machine interface and control comprise demonstration and the control of serial communication, LCD, LED.
During test, test the order of main control unit reception, carry out and the corresponding test case of order from serial ports. promptly, at first produce UPS three-phase alternating current input voltage pwm signal, give three-phase alternating current input voltage generation circuit and handle; Simultaneously produce corresponding UPS inverter output voltage, current controling signal, give UPS inverter output voltage, electric current generation and control signal circuit and carry out the control of inverter voltage and current amplitude according to test case; Also according to test case, produce several roads DC simulation pwm signal simultaneously, give the DC simulation signal generating circuit and handle; The tester gives an order for the test main control unit by the serial communication of man-machine interface, and main control unit provides serial ports to send to the backstage test result after carrying out corresponding test case, and shows on LCD and LED by display circuit.
As shown in Figure 2, in the present embodiment, three-phase alternating current PWM ripple produces and control module is mainly used in the PWM ripple that produces and control the required three-phase alternating current input voltage of UPS control module. and it is imported from serial port command, and output three-phase alternating current PWM ripple: when PWMA, PWMB, PWMC. test, after the order of test main control unit reception from serial ports, call this module and calculate and handle, produce the three-phase alternating current pwm signal consistent with order.
The DC PWM ripple produces and control module is mainly used in the PWM ripple that produces and control the required several DC simulation signals of UPS control module.Its input is from serial port command, and output DC PWM ripple: when PWM1, PWM2, PWM3, PWM4. test, after the order of test main control unit reception from serial ports, call this module and calculate and handle, produce several DC PWM signals consistent with order.
The signal amplitude control module is mainly used in the signal that produces the control of UPS inverter output voltage current amplitude. and it is imported from serial port command, and the output amplitude control signal, i.e. voltage control signal, current controling signal.During test, the test main control unit receives the order from serial ports, calls this module judgement and handles the signal of the UPS inverter output voltage current amplitude control that generation is consistent with order.
Control signal generation and processing module are mainly used in carries out analysis and judgement to the signal from the UPS control module, and produces correct or wrong signal of test and serial ports transmission signal, produces the required control signal of UPS control module simultaneously.Its input is from the digital signal of UPS control module, and the signal of the correctness that outputs test result. during test, behind the signal of test main control unit reception from the UPS control module, call this module, these signals are analyzed and judged according to serial port command, draw the conclusion of test correctness, transmit a signal to LED and LCD display circuit, test process is shown to the backstage by serial ports then; Produce the required control signal of UPS control module simultaneously.
Display module is mainly used in the module that the test process of proving installation and test result are shown by LCD, LED and backstage. and its input produces from control signal and the signal of processing module, and pass through LCD, LED display circuit and daemon software demonstration test and whether pass through. during test, the control signal of test main control unit produces and processing module is sent the signal whether test is passed through, call this module, show by LCD and LED, also show on the backstage by serial ports.
This proving installation receives the test command from serial communication, carry out corresponding test case, output and the corresponding UPS three-phase alternating current of test case input voltage PWM ripple, UPS inverter output voltage current amplitude control signal, UPS DC simulation signal PWM ripple, and reception is from the control signal of UPS control module to be measured, analyze and judge, compare with test case, outputing test result at last shows to man-machine interface.
Please refer to Fig. 3, the input of UPS three-phase alternating current input voltage generation circuit comes the pwm signal of the UPS three-phase alternating current input voltage of self-test main control unit, i.e. three signals of PWMA, PWMB and PWMC.These three signals are given isolated drive circuit, to guarantee the isolation of digital signal and simulating signal; By low-pass filter pwm signal filtering is become the three-phase alternating voltage signal again; Remove direct current component in the signal by block isolating circuit then; Through signal amplification circuit the amplitude of the required three-phase alternating voltage signal of signal amplitude and UPS control module is consistent again; The U that will obtain at last by connector, V, W three road three-phase alternating voltage signals are given the control module to be measured of UPS then.
Please refer to Fig. 4, UPS inverter output voltage, electric current produce and the input of control circuit is inverter output voltage, the current controling signal that the UPS control module sends, and through behind the isolated drive circuit digital signal and simulating signal are isolated fully; Wave circuit advanced filtering after filtration again, and original pwm signal is filtered into AC signal; Pass through again every straight and amplifying circuit, remove the direct current component in the signal, and this signal amplitude is amplified.This ac voltage signal is converted into two signals after through a potential-divider network, i.e. a voltage signal and a current signal. these two signals are delivered to the input end that a multichannel is selected one analog switch respectively. analog switch is used to produce different output voltages and different load currents by the signal controlling that the test main control unit of this device produces.At last output voltage signal and current signal are given the control module of UPS by connector.
Please refer to Fig. 5, the DC simulation pwm signal that UPS DC simulation signal generating circuit acceptance test main control unit sends is by after the isolation drive isolating digital signal and simulating signal; Pass through filtering again, pwm signal is converted into direct current signal; Again with these direct current signals through boosting and a series of amplitude conversion such as step-down, produce the level identical DC simulation signal required at last with the UPS control module; Then these DC simulation signals are given the control module of UPS by connector.
Therefore, when debugging, utilize this proving installation, can carry out the debugging and the test of UPS control module safely, needn't worry to cause the components from being damaged of complete machine because of the BUG that software exists in the UPS Control Software initial stage of development stage.In addition, for some abnormity protection functions of UPS, simulation test can be carried out like a cork, the defective of having avoided complete machine to test on this proving installation.Because this proving installation has intrinsic test case, different testers, used method of testing and test case all are consistent, can guarantee not tested person personnel's influence of test result, therefore test result has very strong comparability. utilize this method of testing and device in addition, can finish the procedural test and the unit testing of UPS Control Software, can write software on one side, debug and test on one side, finish writing of a module, just can carry out the debugging and the test of this module, the BUG in the software is just found at initial stage of development, stay hidden danger to software in the time of need not waiting until end-of-development.
Need to prove; above-mentioned explanation only is the detailed description to preferred embodiment of the present invention; narration only is explanation realizability of the present invention and outstanding effect thereof; concrete feature can not be used as the restriction to technical scheme of the present invention, and protection scope of the present invention should be as the criterion with appended claims of the present invention.

Claims (10)

1. device of testing the UPS control module, it is characterized in that it comprises that a test main control unit, a three-phase alternating current input voltage produce circuit, an inverter output voltage, current generating circuit, a DC simulation signal generating circuit, wherein test main control unit and be used to carry out corresponding test case, to produce three-phase alternating current input voltage pwm signal, corresponding inverter output voltage, current controling signal, DC simulation pwm signal; This three-phase alternating current input voltage pwm signal produces circuit in order to control three-phase alternating current input voltage and produces the three-phase alternating voltage signal of required amplitude and be delivered to UPS control module to be measured, this inverter output voltage, current controling signal are in order to the amplitude of the inverter voltage of control inverter output voltage, current generating circuit output and electric current and be delivered to UPS control module to be measured, and this DC simulation pwm signal produces the DC simulation signal of required level and is delivered to UPS control module to be measured in order to control DC simulation signal generating circuit.
2. device as claimed in claim 1 is characterized in that this device further comprises serial interface circuit, so that the tester should send order to the test main control unit by serial interface circuit, so that it carries out corresponding test case.
3. device as claimed in claim 1, it is characterized in that this test main control unit comprises that a three-phase alternating current input voltage PWM ripple produces and control module with produce above-mentioned three-phase alternating current input voltage pwm signal, a DC PWM ripple produces and control module is carried out logic determines and processing to produce corresponding inverter output voltage, current controling signal and control signal generation and processing module in order to the control signal that receives UPS control module to be measured and send to produce DC simulation pwm signal, signal amplitude control module.
4. a method that adopts the described device to test UPS of claim 1 control module is characterized in that it comprises the steps:
(a) provide the described test of a UPS control module to be measured and claim 1 UPS the device of control module;
(b) device of UPS control module to be measured to this test UPS control module is installed;
(c) use the device implementation of test cases of this test UPS control module, finish test this UPS control module to be measured.
5. method as claimed in claim 4, it is characterized in that in step (c), use the test main control unit in the device of this test UPS control module to carry out corresponding test case, to produce and control three-phase alternating current input voltage pwm signal, corresponding inverter output voltage, current controling signal, DC simulation pwm signal; This three-phase alternating current input voltage pwm signal produces the three-phase alternating voltage signal of required amplitude and is delivered to UPS control module to be measured in order to control three-phase alternating current input voltage generation circuit, this inverter output voltage, current controling signal are in order to the amplitude of the inverter voltage of controlling an inverter output voltage, current generating circuit and electric current and be delivered to UPS control module to be measured, and this DC simulation pwm signal produces the DC simulation signal of required level and is delivered to UPS control module to be measured in order to control a DC simulation signal generating circuit.
6. method as claimed in claim 5 is characterized in that in step (c), sends order by serial ports to the test main control unit, so that it carries out corresponding test case.
7. method as claimed in claim 5 is characterized in that in step (c), and the test main control unit sends to a display unit with test result by serial ports.
8. method as claimed in claim 5, it is characterized in that in step (c), this three-phase alternating current input voltage produces the pwm signal that circuit receives the three-phase alternating current input voltage of self-test main control unit, through isolated drive circuit, digital signal and simulating signal are isolated, by low-pass filter pwm signal filtering is become the three-phase alternating voltage signal again, remove direct current component in the above-mentioned signal by block isolating circuit then, through signal amplification circuit the amplitude of the required three-phase alternating voltage signal of signal amplitude and control module to be measured is consistent again, and then sends this control module to be measured to.
9. method as claimed in claim 5, it is characterized in that in step (c), this inverter output voltage, current generating circuit receives the inverter output voltage of control module to be measured, current controling signal, this inverter output voltage, current controling signal is through isolation drive, filtering, after straight and amplification, obtain an ac voltage signal, this ac voltage signal is divided into some equal portions after through a potential-divider network, deliver to two multichannels respectively and select the input end of one analog switch, the signal controlling that this analog switch is produced by the test main control unit, to produce different output voltages and different load currents, send output voltage signal and current signal to control module to be measured again.
10. method as claimed in claim 5, it is characterized in that in step (c), the DC simulation pwm signal that this DC simulation signal generating circuit acceptance test main control unit sends, by isolation drive, filtering, boost and decompression transformation, produce the level identical DC simulation signal required, send this DC simulation signal to control module to be measured again with control module to be measured.
CNB2004100525805A 2004-12-08 2004-12-08 Method and apparatus for testing UPS control unit Expired - Fee Related CN100416287C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100525805A CN100416287C (en) 2004-12-08 2004-12-08 Method and apparatus for testing UPS control unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100525805A CN100416287C (en) 2004-12-08 2004-12-08 Method and apparatus for testing UPS control unit

Publications (2)

Publication Number Publication Date
CN1786728A CN1786728A (en) 2006-06-14
CN100416287C true CN100416287C (en) 2008-09-03

Family

ID=36784267

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100525805A Expired - Fee Related CN100416287C (en) 2004-12-08 2004-12-08 Method and apparatus for testing UPS control unit

Country Status (1)

Country Link
CN (1) CN100416287C (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101452060B (en) * 2007-11-30 2011-01-12 上海市电力公司 UPS dynamic test method
CN102129046B (en) * 2011-03-01 2016-04-13 艾默生网络能源有限公司 A kind of automatic testing equipment of uninterrupted power source
CN102890247B (en) * 2011-07-18 2014-12-17 旭隼科技股份有限公司 Testing system of uninterruptible power supply and testing method thereof
CN104076270B (en) * 2013-03-25 2016-09-28 德律科技股份有限公司 The tester table set for voltage
TWI468710B (en) 2013-03-25 2015-01-11 Test Research Inc Testing apparatus for providing per pin level setting
CN107543995B (en) * 2017-09-07 2020-08-28 欣旺达电子股份有限公司 Detection method and device for control panel of direct-current brushless motor
CN110095734B (en) * 2019-03-25 2021-10-22 深圳市商宇电子科技有限公司 UPS automatic test system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2131238Y (en) * 1992-09-11 1993-04-28 北京铁路局计量管理所 In-line uninterrupted power
US6236226B1 (en) * 1997-11-05 2001-05-22 Nec Corporation Test method and system for uninterruptible power supply
JP2001339873A (en) * 2000-05-25 2001-12-07 Shin Kobe Electric Mach Co Ltd Inspection system of microcomputer board for uninterrupted power supply apparatus
JP2002017054A (en) * 2000-06-30 2002-01-18 Yamatake Building Systems Co Ltd Automatic power interruption/restoration testing device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2131238Y (en) * 1992-09-11 1993-04-28 北京铁路局计量管理所 In-line uninterrupted power
US6236226B1 (en) * 1997-11-05 2001-05-22 Nec Corporation Test method and system for uninterruptible power supply
JP2001339873A (en) * 2000-05-25 2001-12-07 Shin Kobe Electric Mach Co Ltd Inspection system of microcomputer board for uninterrupted power supply apparatus
JP2002017054A (en) * 2000-06-30 2002-01-18 Yamatake Building Systems Co Ltd Automatic power interruption/restoration testing device

Also Published As

Publication number Publication date
CN1786728A (en) 2006-06-14

Similar Documents

Publication Publication Date Title
CN106650072B (en) Semi-physical simulation-based virtual grid-connected detection system and method for same generator
CN100589587C (en) Automatic test system for handset single-plate and its method
CN106597142B (en) A kind of automatic testing equipment of SVG power module
US8994388B2 (en) Low-voltage testing device for high-voltage frequency converter of serial superposition voltage type
CN102692598B (en) Electric cabinet logic tester device of railway vehicle
CN102722107A (en) Intelligent integrated development and test system for high-voltage frequency converter and establishment method thereof
CN106405286B (en) The automatic test approach and system of quality monitoring device of electrical energy
CN104360835B (en) A kind of sequence operation ticket automatic generation method based on topological mode
CN103412203B (en) Motor variable-frequency driver ageing tester and method of testing thereof
CN112327082B (en) Method, device and system for testing complete set of energy consumption device of flexible direct current engineering
CN100416287C (en) Method and apparatus for testing UPS control unit
CN109613418A (en) Thyristor valves high potential board test device and test method
CN108595299A (en) The test system of terminal device
CN112505529A (en) Board-level automatic test system
Deda et al. Designing a battery emulator/tester from scratch to prototyping to automated testing within a HIL digital twin environment
CN208937976U (en) A kind of drilling machine electric control product test macro
CN107703440B (en) Automatic test circuit of power converter
CN112798939B (en) Testing device
CN111025062A (en) SVG power module test system and method
CN109324592B (en) Drilling machine electric control product testing system
CN210109234U (en) Output signal simulation device and secondary on-load test system
CN105866663B (en) Test fixture and test macro
Yang et al. Automated test system design of body control module
CN204882817U (en) General if converting circuit test system
CN210666476U (en) Test system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JINJIANG HIGH-TECH DEVELOPMENT OFFICE

Free format text: FORMER OWNER: ZTE CORPORATION

Effective date: 20131107

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 518057 SHENZHEN, GUANGDONG PROVINCE TO: 362200 QUANZHOU, FUJIAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20131107

Address after: Jinjiang City, Fujian province 362200 Chongde road Quanzhou City No. 283 friends Jade Technology Building

Patentee after: Jinjiang high and new technology development office

Address before: 518057 Nanshan District science and Technology Industrial Park, Guangdong high tech Industrial Park, ZTE building

Patentee before: ZTE Corporation

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080903

Termination date: 20161208