CN100376750C - High-property cement earth pile construction method - Google Patents
High-property cement earth pile construction method Download PDFInfo
- Publication number
- CN100376750C CN100376750C CNB2004100611980A CN200410061198A CN100376750C CN 100376750 C CN100376750 C CN 100376750C CN B2004100611980 A CNB2004100611980 A CN B2004100611980A CN 200410061198 A CN200410061198 A CN 200410061198A CN 100376750 C CN100376750 C CN 100376750C
- Authority
- CN
- China
- Prior art keywords
- hole
- cement earth
- cement soil
- property
- slurry
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The present invention relates to a high-property cement earth pile construction method which is characterized in that the method comprises the following steps: 1) forming a hole or a groove by a hole forming device; 2) blending mud, solidifying agents and external mixing agents outside the hole to form high-property cement earth slurry; 3) filling or pressing the high-property cement earth slurry into the hole or the groove by a slurry filling pump. The present invention thoroughly changes a traditional cement earth forming technology, namely changing the mode of mixing cement earth at home position in an underground hole to form piles into the mode of mixing mud and solidifying agents outside the hole to form piles. A high-property cement earth pile formed by the method has higher intensity, better performance and lower cost than a traditional cement earth pile. The present invention is suitable for the underground engineering in the fields of civil engineering and construction.
Description
Technical field
The present invention relates to the underground construction of building and building field, specifically a kind of job practices of high-performance cement soil stake.
Background technology
In building and building engineering field, cement earth pile has powder spray piling, slurry spray stake and high-pressure rotary jet grouting pile at present, and there is the following problem in these cement earth piles:
1, powder spray piling, slurry spray stake all are cement mixing methods, and its moulding process is that original position stirs in underground stake hole, and limit spraying cement or cement paste limit promote drilling rod, and jet velocity and hoisting velocity are difficult to coupling, thereby easily cause the common quality defect of " multi-layer steamed bread ".
2, since when powder spray piling and slurry spray pile driving construction the cement amount of the cement-soil in the drill pipe diameter seldom also be difficult to stir, promptly pile body is outer soft in hard, is commonly called as in the industry to be " egg core ", this common quality defect also is masty.
3, owing to above reason, quality problems often appear in a lot of powder spray pilings and a slurry spray stake engineering, some area even forbidden adopting this two kinds of stake types.
4, high-pressure rotary-spray cement earth pile, be by water under high pressure, gas, slurry, can pass through single tube, dual pipe, triple pipe, rely on the high-pressure rotary-spray jet in underground hole, to carry out the original position pile, the pile body diameter can differ bigger according to soil property situation difference, and also occurs dried layer cake phenomenon and the expanded diameter quality problems less than intended diameter easily.
Summary of the invention
The present invention seeks to propose a kind of job practices of high-performance cement soil stake, make it can solve " egg core " and the common quality defect of " multi-layer steamed bread " that the conventional soil cement stake produces in order to solve the problem that the above-mentioned background technology exists.
For achieving the above object, the present invention adopts following technical scheme:
1. the job practices of a high-performance cement soil stake is characterized in that this method adopts following steps:
1) adopts pore-forming equipment pore-forming or grooving;
2) outside the hole, utilize mud and curing compound and additive to stir into the high-performance cement soil paste;
3) with grouting pump above-mentioned high-performance cement soil paste is injected or be pressed in above-mentioned hole or the groove.
The present invention has thoroughly changed the moulding process of conventional soil cement, is promptly changed into by original position stirring concrete earth pile in the underground hole and utilizes mud and curing compound to stir outside the hole, and it has following advantage:
1, the moulding process of cement-soil is stirred to change into outside the hole by original position in the underground hole and stirs, and soil cement slurry stirs, and can make the high-performance cement soil that satisfies different resistance to compressions, anti-permeability performance according to different needs.
2, can utilize discarded slurry, turn waste into wealth, reduce pollution environment.
3, good with the high-performance cement soil stake strength ratio of this method construction traditional cement earth pile height, anti-permeability performance, cost is low, and it is applicable to the underground construction of building and building field.
Description of drawings
Fig. 1 is the schematic diagram of high-performance cement soil stake.
In the drawings, 1-hole, the stake of 2-high-performance cement soil, 3-core, 4-soil layer.
The specific embodiment
The present invention adopts following steps:
1, adopts rig or long spiral equipment or revolve and dig equipment pore-forming or grooving;
2, utilizing mud and cement outside the hole is that curing compound and additive stir into the high-performance cement soil paste;
3, with grouting pump above-mentioned high-performance cement soil paste is injected or be pressed in above-mentioned hole or the groove;
4, in above-mentioned high-performance cement soil stake, insert steel work or concrete structure core.
Claims (3)
1. the job practices of a high-performance cement soil stake is characterized in that this method is made up of following steps:
1) adopts long spiral equipment or revolve and dig equipment pore-forming or grooving;
2) outside the hole, utilize mud and curing compound and additive to stir into the high-performance cement soil paste;
3) with grouting pump above-mentioned high-performance cement soil paste is injected or be pressed in above-mentioned hole or the groove.
2. according to the job practices of the described high-performance cement soil stake of claim 1, it is characterized in that described curing compound is that cement is curing compound.
3. according to the job practices of claim 1 or 2 described high-performance cement soil stakes, it is characterized in that in above-mentioned steps 3) then in the high-performance cement soil stake, insert core.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100611980A CN100376750C (en) | 2004-11-26 | 2004-11-26 | High-property cement earth pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100611980A CN100376750C (en) | 2004-11-26 | 2004-11-26 | High-property cement earth pile construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1641111A CN1641111A (en) | 2005-07-20 |
CN100376750C true CN100376750C (en) | 2008-03-26 |
Family
ID=34868794
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2004100611980A Expired - Fee Related CN100376750C (en) | 2004-11-26 | 2004-11-26 | High-property cement earth pile construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100376750C (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831907A (en) * | 2010-05-05 | 2010-09-15 | 山东省机械施工有限公司 | Construction method of cement mixing pile |
CN109137899A (en) * | 2018-08-29 | 2019-01-04 | 衡水京坤岩土工程有限公司 | A kind of compound tube pile construction engineering method of soil cement |
CN112030940B (en) * | 2020-06-23 | 2022-04-19 | 武汉谦诚桩工科技股份有限公司 | Construction process of in-situ premixed cement soil cast-in-place pile of marine soft soil |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5423636A (en) * | 1992-12-10 | 1995-06-13 | Kencho Kobe Co., Ltd. | Cement soil apparatus of underground borer |
CN1274788A (en) * | 2000-05-24 | 2000-11-29 | 王平 | Continuous wall constructing method including drilling holes and late grouting |
JP2001146739A (en) * | 1999-11-24 | 2001-05-29 | Sato Kogyo Co Ltd | Construction method for impervious wall |
CN2587933Y (en) * | 2002-12-25 | 2003-11-26 | 曾毅学 | Reinforced cement composite pile |
CN1482307A (en) * | 2002-09-10 | 2004-03-17 | 周同和 | Sand concrete free small pile foundation consolidation process by stone throwing and squeezing |
-
2004
- 2004-11-26 CN CNB2004100611980A patent/CN100376750C/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5423636A (en) * | 1992-12-10 | 1995-06-13 | Kencho Kobe Co., Ltd. | Cement soil apparatus of underground borer |
JP2001146739A (en) * | 1999-11-24 | 2001-05-29 | Sato Kogyo Co Ltd | Construction method for impervious wall |
CN1274788A (en) * | 2000-05-24 | 2000-11-29 | 王平 | Continuous wall constructing method including drilling holes and late grouting |
CN1482307A (en) * | 2002-09-10 | 2004-03-17 | 周同和 | Sand concrete free small pile foundation consolidation process by stone throwing and squeezing |
CN2587933Y (en) * | 2002-12-25 | 2003-11-26 | 曾毅学 | Reinforced cement composite pile |
Also Published As
Publication number | Publication date |
---|---|
CN1641111A (en) | 2005-07-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104929114A (en) | High pressure jet grouting pile waterproof curtain construction device and method | |
CN101581093B (en) | Composite high performance soil cement mortar pile construction method | |
CN103556631B (en) | The one-tenth pile operation method of agitation pile | |
CN104863131A (en) | Polygonal cement-soil stirring pile and formation method thereof | |
CN1487150A (en) | Combined grouting construction process of reinforcing foundation | |
CN204753574U (en) | High pressure jet grouting pile stagnant water curtain construction equipment | |
CN102900079A (en) | High-frequency hydraulic vibratory construction method for cement-soil core-inserted combined pile | |
CN201395793Y (en) | Long spiral high-pressure spraying mud injecting stirring pile-forming device | |
CN102011399A (en) | PHC pile-based multiple high jet pedestal pile construction method | |
CN100386483C (en) | High-performance cement soil continuous wall construction method | |
CN110387877A (en) | A kind of stiff composite pile construction technology | |
CN106284295A (en) | Multichannel high-pressure vibro-grouting jet groutinl construction method | |
CN110468828A (en) | A kind of construction method of pattern foundation pit supporting structure water-stop continuous wall | |
CN104153381A (en) | Waterproof curtain pile, waterproof curtain and construction method of waterproof curtain pile | |
CN105672329B (en) | The large size prefabricated building enclosure of deep basal pit and construction method | |
CN100376750C (en) | High-property cement earth pile construction method | |
CN100374657C (en) | Construction method employing threaded stirring shaft to decrease ambient foundation deformation | |
CN103603345B (en) | Cement mixing grouting pile foundations and forming method | |
CN103603363B (en) | Cement mixing-filling convex joint pile foundation and manufacturing process | |
CN110318392A (en) | A kind of major diameter cement earth pile method of construction | |
CN101793024B (en) | Construction method for multi-head small-diameter deep mixing and high-pressure jet combined anti-seepage wall of foundation pit | |
CN109537612A (en) | A kind of porous impact stirring diaphram wall Barrier Technology and its construction method | |
CN105178858A (en) | Drilling rig for double-tube high pressure jet grouting technology | |
CN206034417U (en) | A integrated system is split in high extrusion of deep soft base drilling cream thick liquid | |
CN100363562C (en) | Preventing plate with spreading and deep layer rotating spraying mixture head with diffusion preventing plate and guniting mouth |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080326 Termination date: 20201126 |
|
CF01 | Termination of patent right due to non-payment of annual fee |