CL2019000859A1 - Explosives distribution methodology and delays for drilling diagrams with long shots over 4 [m] in tandem - Google Patents
Explosives distribution methodology and delays for drilling diagrams with long shots over 4 [m] in tandemInfo
- Publication number
- CL2019000859A1 CL2019000859A1 CL2019000859A CL2019000859A CL2019000859A1 CL 2019000859 A1 CL2019000859 A1 CL 2019000859A1 CL 2019000859 A CL2019000859 A CL 2019000859A CL 2019000859 A CL2019000859 A CL 2019000859A CL 2019000859 A1 CL2019000859 A1 CL 2019000859A1
- Authority
- CL
- Chile
- Prior art keywords
- delay
- tandem
- drilling
- explosives
- delays
- Prior art date
Links
Landscapes
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
- Earth Drilling (AREA)
Abstract
La metodología busca generar con un doble retardo en la columna explosiva de las perforaciones de un diagrame de disparo, las condiciones para que la roca removida por el explosivo en la primera etapa iniciado con un retardo X, sea expulsada con facilidad hacia el frente de la labor con la voladura de la carga explosiva de la segunda etapa iniciado con un retardo Y, generando un TANDEM; y donde el retardo X tiene un tiempo de activación menor al retardo Y. El objetivo es maximizar el avance efectivo de la tronadura de un diagrama de perforación pera construir túneles o galerías subterráneas en roca horizontales a sub horizontales hecho con tiros largos sobre 4m.The methodology seeks to generate with a double delay in the explosive column of the perforations of a shot diagram, the conditions so that the rock removed by the explosive in the first stage, initiated with a delay X, is easily expelled towards the front of the work with the blasting of the explosive charge of the second stage started with a delay Y, generating a TANDEM; and where the X delay has a lower activation time than the Y delay. The objective is to maximize the effective advance of the blast of a drilling diagram to build tunnels or underground tunnels in horizontal to sub horizontal rock made with long shots over 4m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CL2019000859A CL2019000859A1 (en) | 2019-03-29 | 2019-03-29 | Explosives distribution methodology and delays for drilling diagrams with long shots over 4 [m] in tandem |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CL2019000859A CL2019000859A1 (en) | 2019-03-29 | 2019-03-29 | Explosives distribution methodology and delays for drilling diagrams with long shots over 4 [m] in tandem |
Publications (1)
Publication Number | Publication Date |
---|---|
CL2019000859A1 true CL2019000859A1 (en) | 2019-12-06 |
Family
ID=69057785
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CL2019000859A CL2019000859A1 (en) | 2019-03-29 | 2019-03-29 | Explosives distribution methodology and delays for drilling diagrams with long shots over 4 [m] in tandem |
Country Status (1)
Country | Link |
---|---|
CL (1) | CL2019000859A1 (en) |
-
2019
- 2019-03-29 CL CL2019000859A patent/CL2019000859A1/en unknown
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Golik et al. | Improving the effectiveness of explosive breaking on the bade of new methods of borehole charges initiation in quarries | |
ECSP12012159A (en) | UNDERGROUND MINING | |
CN105937395B (en) | A kind of comprehensive dig of coal mine big cross section hard-rock tunnel combines rapidly and efficiently driving method with big gun pick | |
CN103615941A (en) | Method for blasting shallow section of modernization railway tunnel | |
PE20001581A1 (en) | PROCESS TO BLOW ROCK MASSES | |
PE20230205A1 (en) | BLASTING TECHNIQUE | |
CL2021001972A1 (en) | Apparatus, method and computer program product for designing the order of blasting. | |
CL2019000859A1 (en) | Explosives distribution methodology and delays for drilling diagrams with long shots over 4 [m] in tandem | |
CN115655037B (en) | Tunnel near-connection expansion excavation blasting vibration reduction construction method | |
KR100536609B1 (en) | Controlled rock blasting method for protection of rock slope face in bench blasting | |
KR101511223B1 (en) | Open-cut blasting using 6 freeface | |
RU2634597C1 (en) | Method for developing mine workings and conducting stoping operations | |
AR111797A1 (en) | METHOD OF DEVELOPMENT OF UNDERGROUND WELLS | |
AR118920A1 (en) | REACTIVE PIERCING GUN TO REDUCE REDUCTION | |
CN103967522B (en) | Reserved roadway surrounding rock control comprehensive processing method | |
RU2445459C1 (en) | Method for underground development of high-ore deposits | |
RU2540750C2 (en) | Complex method of preliminary degassing of working coal bed, worked-out area and accompanying beds and controlled caving of heavy roof | |
CL2021002511A1 (en) | New method to quickly and safely excavate tunnels of large section and length | |
UA126862U (en) | METHOD OF DRUG EXPLORATION OF PRODUCTS IN GASESATED COAL AND MOUNTAINS | |
UA126863U (en) | METHOD OF DRILLING FOR PRODUCTION OF COAL AND MOUNTAIN OUTPUTS | |
UA129041U (en) | METHOD OF DRUG EXPLORATION OF PRODUCTS IN GASESATED COAL AND MOUNTAINS | |
RU2646152C2 (en) | System for explosive blasting of bump hazard rocks | |
CN114251099B (en) | Blasting excavation method for cross grotto | |
RU2725721C1 (en) | Method for formation of charge in well combined open-underground mining | |
RU2304219C1 (en) | Method for development entry protection |