CH336337A - Process for the production of a driven pile with a concrete coating - Google Patents

Process for the production of a driven pile with a concrete coating

Info

Publication number
CH336337A
CH336337A CH336337DA CH336337A CH 336337 A CH336337 A CH 336337A CH 336337D A CH336337D A CH 336337DA CH 336337 A CH336337 A CH 336337A
Authority
CH
Switzerland
Prior art keywords
pile
concrete
cavity
shaft
shoe
Prior art date
Application number
Other languages
German (de)
Inventor
Mueller Ludwig Ing Dr
Original Assignee
Mueller Ludwig
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mueller Ludwig filed Critical Mueller Ludwig
Publication of CH336337A publication Critical patent/CH336337A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

  

  Verfahren zum Herstellen eines Rammpfahles mit Betonummantelung    Die Erfindung betrifft ein Verfahren zum Her  stellen eines Rammpfahls mit Betonummantelung  durch Einrammen eines mit einem     Verdrängerpfahl-          sehuh    versehenen Pfahlschaftes und Einpressen von  Beton vom untern Teil des Pfahls aus in den vom  Pfahlschuh im Baugrund um den Pfahlschaft herum  erzeugten Hohlraum. Durch den in diesem Hohlraum  unter Überdruck emporsteigenden Beton wird das den  Hohlraum umgebende Erdreich verdichtet und der  Hohlraum entsprechend dem unterschiedlichen Wi  derstand der     durchrammten    Bodenschichten ungleich  förmig erweitert.

   Die nach einem solchen Verfahren  hergestellten Rammpfähle zeichnen sich durch eine  grosse Tragfähigkeit und hohen Zugwiderstand aus,  weil ausser dem Schaft des Pfahls auch der Beton  mantel mit seinem ungleichförmigen Querschnitt eben  falls trägt und den Pfahl fest im Baugrund einspannt.  



  Die Erfindung bezweckt, das Verfahren weiter  auszubilden, so dass es besonders auch bei nachgie  bigen und bei stark wasserführenden Böden mit Vor  teil anwendbar ist.  



  Die Erfindung besteht darin, dass während des       Rammens    ein fliessfähiger Beton unter geringem  Druck zum fortlaufenden Ausfüllen des entstehenden  Hohlraumes zugeführt, gegen Ende des Rammvor  ganges der gefüllte Hohlraum oben abgeschlossen und  weiterhin Beton unter höherem Druck     eingepresst     wird.  



  Es gibt an sich Böden, in denen der beim Ein  rammen des Pfahls um den Schaft herum geschaffene  Hohlraum infolge Nachgiebigkeit des Bodens nach  drängt, wie es z. B. bei moorigen oder     schlammigen     Böden der Fall ist, so dass der Hohlraum bei weiterem  Rammen unter Einfluss der Erschütterungen sich  wieder verringert und zum Teil sogar zusammenfällt.  Da nach dem erfindungsgemässen Verfahren der Hohl  raum durch den während des     Rammens    am untern    Teil des Pfahlschaftes austretenden fliessfähigen Beton  sogleich ausgefüllt wird, kann weder Boden noch  Grundwasser in den Hohlraum eindringen.  



  Das erfindungsgemässe Verfahren wird im folgen  den anhand der Zeichnung beispielsweise näher er  läutert:  In der Zeichnung zeigen:       Fig.    1 einen eingerammten Pfahl mit dem im  Schnitt veranschaulichten Betonmantel und       Fig.    2 in grösserem     Massstabe    im Längsschnitt den  untern Teil des Pfahls mit ausgefülltem Hohlraum  bald nach Beginn des     Einrammens    sowie das obere  Ende des vollständig eingerammten Pfahls.  



       Fig.    3 und 4 zeigen Querschnitte nach den Linien       11I-III    und     IV-IV    der.     Fig.    2.  



  In     Fig.    5 ist ein Längsschnitt durch eine andere  Ausführung des Pfahlkopfes dargestellt.  



  Am untern Ende des dargestellten hohlen Pfahl  schaftes 61 ist ein hohler, keilförmiger     Verdränger-          pfahlschuh    62 befestigt. Nach oben ist der Pfahl  schuh offen, seine obere     Querschnittsfläche    ist grösser  als der Querschnitt des Pfahlschaftes. In diesem       Verdrängerpfahlschuh    ist in der     Achsenebene    des  Schaftes 61 ein Flachmeissel 63 so eingesetzt, dass er  unten aus dem Pfahlschuh herausragt und mit sei  nem stumpfen obern Ende gegen den untern Rand  des Pfahlschaftes anliegt.

   Zur festen Verbindung des       Pfahlschuhes    62 mit dem Pfahlschaft 61 dienen       Stegbleche    64, die mit dem Pfahlschaft und den Wän  den des Pfahlschuhes verschweisst sind. Im untern  Teil des Pfahlschaftes können, wie das gezeichnete  Beispiel zeigt, nach aussen führende Öffnungen 65  vorgesehen sein, die aber meist     entbehrlich    sind. Oben  ist der Pfahlschaft durch     eine    Kopfplatte 66 abge  schlossen. Unterhalb der Kopfplatte ist an eine     öff-          nung    67 des Pfahlschaftes ein Rohrstutzen 68 ange  setzt, an den eine     Betonzuführungsleitung    69 ange-      schlossen werden kann.

   In der Nähe des     obern     Schaftendes ist an dem Pfahlschaft 61 eine     Abschluss-          glocke    70 aufgeschweisst. Die Glocke kann auch  abnehmbar ausgeführt werden, so dass sie einige Stun  den nach     Verpressung    eines Pfahls abgenommen und  bei     einem    der nächsten Pfähle wieder verwandt wer  den kann.  



  Beim Einrammen des     Pfahlschaftes    erzeugt der  Pfahlschuh 62 um den Pfahlschaft herum einen Hohl  raum 71 im Baugrund. Während des     Einrammens     wird durch die Leitung 69 und den Stutzen 68 dünn  flüssiger Beton 72 unter geringem Druck in den Pfahl  schaft 61 und in den Pfahlschuh 62     eingepresst.     



  Aus dem oben     offenen    Pfahlschuh 21 tritt der       eingepresste    flüssige Beton aus und steigt in den vom  Pfahlschuh um den Pfahlschaft geschaffenen Hohl  raum 71 hoch. Auf diese Weise wird der Hohlraum  71 fortlaufend mit der Betonmasse ausgefüllt. Diese  Vorgänge finden statt, bis am Ende des Rammvor  ganges die     Absclilussglocke    70 in den Baugrund ein  dringt und den gefüllten Hohlraum 71 nach oben ab  schliesst. Die Betonmasse kann dann nur noch bis  zur Glocke 70 hochsteigen. Beim     Einrammen    des       Pfahlschaftes    und Einpressen der Betonfüllung wird  darauf geachtet, dass der Betonspiegel nahe unter  der     Baugrundoberfläche    gehalten wird.  



  Nachdem der Pfahl bis zur gewünschten Tiefe ein  gerammt und der vom     Verdrängerpfahlschuh    er  zeugte Hohlraum 71 durch den unter geringem Druck       eingeführten    fliessfähigen Beton ausgefüllt ist und  Hohlraum und Füllung nach oben abgeschlossen sind,  wird der Zuführungsdruck des Betons     wesentlich    ge  steigert.

   Der mit dem höheren Druck zugeführte Be  ton hat dabei     eine    geeignete breiige oder körnige Be-         schaffenheit.    Unter weiterer Verdichtung des den       ursprünglichen    Hohlraum 71 umschliessenden     Erd-          reiches    wird auf diese Weise die fertige Betonumman  telung 73     (Fig.    1) erzeugt.  



       Fig.    5 zeigt anstelle der Kopfplatte 66 ein Kopf  stück 74 zum obern Abschluss des Pfahlschaftes 61.  In diesem Kopfstück ist eine winkelförmige Boh  rung 75 vorgesehen, an deren waagrechten Teil der  Rohrstutzen 68 angesetzt ist.  



  Anstelle des beispielsweise dargestellten Schaft  rohres kann als Pfahlschaft 61 auch ein Vollprofil  verwandt werden. In diesem Falle wird der flüssige  Beton durch ein oder mehrere     aussen    am Pfahlschaft  angeordnete Zuleitungen (Rohre) dem Pfahlschuh 62  zugeleitet.



  Method for producing a driven pile with concrete casing The invention relates to a method for producing a driven pile with concrete casing by ramming in a pile shaft provided with a displacement pile and pressing in concrete from the lower part of the pile into the created by the pile shoe in the ground around the pile shaft Cavity. Due to the concrete rising up in this cavity under excess pressure, the soil surrounding the cavity is compacted and the cavity is expanded unevenly according to the different resistance of the rammed-through soil layers.

   The driven piles produced by such a method are characterized by a high load-bearing capacity and high tensile resistance, because in addition to the shaft of the pile, the concrete jacket with its non-uniform cross-section also carries and clamps the pile firmly in the ground.



  The aim of the invention is to develop the method further, so that it can also be used in part with vorgie-bigen and highly water-bearing soils.



  The invention consists in that, during the ramming, a flowable concrete is fed under low pressure to continuously fill the resulting cavity, towards the end of the ramming process the filled cavity is closed at the top and concrete continues to be pressed in under higher pressure.



  There are soils in which the cavity created when ramming the pile around the shaft due to the flexibility of the soil pushes as it is, for. B. is the case with boggy or muddy soils, so that the cavity is reduced again with further ramming under the influence of the vibrations and sometimes even collapses. Since, according to the method according to the invention, the cavity is immediately filled by the flowable concrete emerging during the ramming on the lower part of the pile shaft, neither soil nor groundwater can penetrate into the cavity.



  The inventive method is explained in more detail in the following with reference to the drawing, for example: In the drawing: Fig. 1 shows a rammed pile with the concrete shell illustrated in section and Fig. 2 on a larger scale in longitudinal section the lower part of the pile with the cavity filled soon after the start of driving and the top of the fully driven pile.



       3 and 4 show cross-sections along the lines 11I-III and IV-IV of. Fig. 2.



  In Fig. 5 is a longitudinal section through another embodiment of the pile head is shown.



  At the lower end of the illustrated hollow pile shaft 61, a hollow, wedge-shaped displacement pile shoe 62 is attached. The pole shoe is open at the top, its upper cross-sectional area is larger than the cross-section of the pole shaft. In this displacement pile shoe, a flat chisel 63 is inserted in the axial plane of the shaft 61 so that it protrudes from the bottom of the pile shoe and rests with its blunt upper end against the lower edge of the pile shaft.

   For the fixed connection of the pole shoe 62 with the pole shaft 61, web plates 64 are used, which are welded to the pole shaft and the walls of the pole shoe. As the example shown shows, openings 65 leading to the outside can be provided in the lower part of the pile shaft, but these are mostly dispensable. Above the pile shaft is closed by a head plate 66 abge. Below the top plate, a pipe socket 68 is attached to an opening 67 in the pile shaft, to which a concrete feed line 69 can be connected.

   In the vicinity of the upper end of the shaft, a capping bell 70 is welded onto the pile shaft 61. The bell can also be made removable so that it can be removed a few hours after a pile has been grouted and used again on one of the next piles.



  When driving the pile shaft, the pile shoe 62 creates a hollow space 71 around the pile shaft in the ground. During the ramming, thin liquid concrete 72 is pressed into the pile shaft 61 and into the pile shoe 62 under low pressure through the line 69 and the nozzle 68.



  The pressed-in liquid concrete emerges from the pole shoe 21, which is open at the top, and rises into the cavity 71 created by the pole shoe around the pole shaft. In this way, the cavity 71 is continuously filled with the concrete mass. These processes take place until, at the end of the Rammvor course, the closing bell 70 penetrates the subsoil and closes the filled cavity 71 upwards. The concrete mass can then only rise up to bell 70. When driving in the pile shaft and pressing in the concrete filling, care is taken to ensure that the concrete level is kept close to the subsoil surface.



  After the pile is rammed to the desired depth and the cavity 71 generated by the displacement pile shoe is filled by the pourable concrete introduced under low pressure and the cavity and filling are completed at the top, the feed pressure of the concrete is significantly increased.

   The concrete supplied with the higher pressure has a suitable pulpy or granular quality. With further compaction of the soil surrounding the original cavity 71, the finished concrete casing 73 (FIG. 1) is produced in this way.



       5 shows, instead of the head plate 66, a head piece 74 for the upper end of the pile shaft 61. In this head piece an angular borehole 75 is provided, on whose horizontal part the pipe socket 68 is attached.



  Instead of the shaft tube shown for example, a full profile can also be used as the pile shaft 61. In this case, the liquid concrete is fed to the pile shoe 62 through one or more feed lines (pipes) arranged on the outside of the pile shaft.

 

Claims (1)

PATENTANSPRUCH Verfahren zum Herstellen eines Rammpfahls mit Betonummantelung durch Einrammen eines mit einem Verdrängerpfahlschuh versehenen Pfahlschaftes und Einpressen von Beton vom untern Teil des Pfahls aus in den vom Pfahlschuh im Baugrund um den Pfahlschaft herum erzeugten Hohlraum, da durch gekennzeichnet, dass während des Rammens ein fliessfähiger Beton unter geringem Druck zum fortlaufenden Ausfüllen des entstehenden Hohlraumes zugeführt, gegen Ende des Rammvorganges der ge füllte Hohlraum oben abgeschlossen und weiterhin Beton unter höherem Druck eingepresst wird. PATENT CLAIM A method for producing a driven pile with a concrete casing by driving in a pile shaft provided with a displacement pile shoe and pressing concrete from the lower part of the pile into the cavity created by the pile shoe in the ground around the pile shaft, characterized in that during the driving a flowable concrete fed under low pressure for continuous filling of the resulting cavity, towards the end of the ramming process the filled cavity is completed at the top and concrete continues to be pressed in under higher pressure. UNTERANSPRUCH Verfahren nach Patentanspruch, dadurch ge kennzeichnet, dass beim Einrammen der Spiegel des eingepressten Betons nahe unter der Baugrundober- fläche gehalten wird. SUBSTANTIAL CLAIM Method according to patent claim, characterized in that when driving in the level of the pressed-in concrete is held close to the subsoil surface.
CH336337D 1955-10-07 1956-10-03 Process for the production of a driven pile with a concrete coating CH336337A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE336337X 1955-10-07

Publications (1)

Publication Number Publication Date
CH336337A true CH336337A (en) 1959-02-15

Family

ID=6220257

Family Applications (1)

Application Number Title Priority Date Filing Date
CH336337D CH336337A (en) 1955-10-07 1956-10-03 Process for the production of a driven pile with a concrete coating

Country Status (1)

Country Link
CH (1) CH336337A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1297044B (en) * 1964-11-11 1969-06-04 Atlas Copco Ab Injection tie rods for earth and rocky ground and methods of its use
EP0989241A1 (en) * 1998-09-24 2000-03-29 Hareninvest Method for forming concrete piles in the ground

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1297044B (en) * 1964-11-11 1969-06-04 Atlas Copco Ab Injection tie rods for earth and rocky ground and methods of its use
EP0989241A1 (en) * 1998-09-24 2000-03-29 Hareninvest Method for forming concrete piles in the ground

Similar Documents

Publication Publication Date Title
DE1634470A1 (en) Foundation stake
DE2233732A1 (en) PROCEDURE FOR SOLIDIZING LOOSE EARTH AND PROCESSING FASTENING PILES
DE69121419T2 (en) Process for the production of tubular foundations
DE1110092B (en) Method and device for the production of reinforced in-situ concrete foundation piles
DE2260473C3 (en) Process for producing material columns in the ground, such as drains, tamping compaction or unreinforced concrete piles and apparatus for carrying out the process
DE2229383C3 (en)
DE1129895B (en) Method and device for the production of a foundation pile with concrete casing
CH336337A (en) Process for the production of a driven pile with a concrete coating
DE655614C (en) Process for the production of place posts from concrete
AT200512B (en) Process for the production of a driven pile with a concrete coating
DE2217485A1 (en) METHOD AND APPARATUS FOR MAKING A PILE FROM CONCRETE PAST INTO THE GROUND
DE2120691A1 (en) Method of manufacturing a composite pile
DE541673C (en) Process for the production of place posts with club feet
DE2101298A1 (en) Method and device for compacting loose layers of soil
DE2948879C2 (en) Process for the production of in-situ concrete driven piles
DE974458C (en) Method for producing a tunnel or tunnel pipe by driving a jacking pipe that remains in the ground and is provided with a shield cutter
DE923601C (en) Method for consolidating boreholes in loose rock
DE3210186C2 (en)
DE723903C (en) Process for compaction of natural or artificial, water-saturated, loose soil masses
DE609976C (en) Process for the production of a watertight construction pit enclosure
DE580215C (en) Method and device for the production of columns of filler in natural or artificial deposits
AT87260B (en) Method and device for the production of concrete cast-in posts in a driving pipe with a mortar feed screw
WO2003091503A1 (en) Method and device for the production of subterranean material columns
DE1484515A1 (en) Method and device for the production of a foundation pile with concrete casing
DE2501415A1 (en) Foundation piles production using localised concrete placement - involves driving thrust pipe with lost head into ground and filling it with concrete