CH291599A - Telescopic mast crane. - Google Patents

Telescopic mast crane.

Info

Publication number
CH291599A
CH291599A CH291599DA CH291599A CH 291599 A CH291599 A CH 291599A CH 291599D A CH291599D A CH 291599DA CH 291599 A CH291599 A CH 291599A
Authority
CH
Switzerland
Prior art keywords
mast
crane according
sub
crane
elements
Prior art date
Application number
Other languages
French (fr)
Inventor
Potain Faustin
Original Assignee
Potain Faustin
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Potain Faustin filed Critical Potain Faustin
Publication of CH291599A publication Critical patent/CH291599A/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/28Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
    • B66C23/30Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels with frameworks composed of telescopic elements
    • B66C23/305Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels with frameworks composed of telescopic elements with locking devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/34Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes
    • B66C23/342Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes with telescopic elements

Description

  

      Grue    à mât     télescopique.       La présente invention se réfère aux grues,  telles que celles utilisées sur les chantiers de  construction, dans lesquelles le mât de la       grue    est vertical et réglable en hauteur au  fur et à mesure des besoins.  



  On connaît des grues comportant un mât  télescopique constitué par des éléments tubu  laires coulissant les uns dans les autres, ces  éléments pouvant être élevés hydraulique  ment. Une telle construction est extrêmement  compliquée et coûteuse et de plus, à moins de  donner aux éléments inférieurs un diamètre  inadmissible, elle ne     permet    pas d'assurer au  mât une rigidité suffisante. On doit le ren  forcer par des haubans nombreux, ce qui gêne  considérablement les     manceuvres    ait voisinage  de la     grue.     



  La grue suivant l'invention est caracté  risée en ce que son mât est constitué par des  éléments en forme de parallélépipèdes creux  coulissant les uns dans les autres, pourvus de  moyens de guidage respectifs sur leurs arêtes  verticales.  



  Le dessin annexé montre, à titre d'exem  ple, une forme d'exécution de l'invention.       Fig.    1 est une vue générale en élévation  de cette forme d'exécution, à la position de  hauteur maximum de son mât.  



       Fig.    2 représente un mât à trois éléments  à la position repliée.  



  Fi-. 3 le montre à la position totalement  développée.  



  Fi-. 4 est une vue en plan à     phis    grande  échelle cl u mât suivant     fig.    1 et 2.         Fig.    5 est une coupe de détail à grande  échelle par un plan vertical passant par la  diagonale du carré du profil horizontal du  mât.  



       Fig.    6 à 8 sont des coupes suivant VI-VI,       VII-VII,        VIII-VIII        (fig.    5<B>)</B> respective  ment, le plan de coupe de     fig.    5 étant indiqué  en     V-V    en     fig.    8.  



       Fig.    9 à 11 sont des vues de détails en  coupe par un plan horizontal indiquant trois  variantes possibles dans le guidage respectif  des éléments télescopiques les uns sur les  autres.  



       Fig.    12 montre le mât télescopique de la  grue à l'état entièrement replié et couché  horizontalement sur une remorque attelée.  



       Fig.    13 montre de même façon le socle de  cette grue monté sur un essieu routier et  attelé derrière un camion tracteur.  



       Fig.    14 représente la première phase du  montage, le mât ayant été articulé au socle et  ayant reçu la contre-flèche, mais cette der  nière n'ayant pas encore été dressée perpendi  culairement au mât.  



       Fig.    15 montre les pièces après dressage  de la contre-flèche.  



       Fig.    16 représente les pièces après articu  lation de la flèche au mât.  



       Fig.    17 les montre après relevage partiel  du mât et fixation de la flèche.  



       Fig.    18 montre l'ensemble de la grue  montée, le mât étant resté à la position la  plus basse.           Fig.    19 indique très schématiquement la  position respective des pièces à, la position de  hauteur maximum du mât.  



  La grue représentée en     fig.    1 comporte un  socle 1, monté sur roues, comme figuré, ou  supporté de toute autre manière. Sur ce socle  est monté un premier élément de charpente  en fer 2, à. section carrée, constitué par quatre  montants réunis les uns aux antres par des  croisillons appropriés. A l'intérieur de l'élé  ment 2 peut coulisser un second élément 3, de  construction semblable, mais de dimensions  horizontales un peu plus faibles. De même,  dans l'élément 3 peut coulisser un élément 4  dans lequel peut à son tour coulisser un élé  ment 5. L'ensemble des éléments 2, 3, 4, 5  réalise Lin mât télescopique au sommet du  quel est articulée la flèche 6 de la grue.

   Tous  ces éléments sont convenablement guidés les  uns dans les autres, de telle sorte que leur       ensemble    présente la rigidité latérale voulue,  sans qu'il soit nécessaire pour cela de le     hau-          banner.    En outre, il est prévu des     moyens    per  mettant de soulever chacun des éléments par  rapport à l'autre lors du dépliage du mât,  sans avoir besoin pour cela de recourir à un  monteur grimpé sur le mât et contraint  d'exercer un effort de levée à une grande  hauteur au-dessus du sol.  



  On comprend que le nombre des éléments  2 à 5 puisse être quelconque. En     fig.    1 on a  représenté quatre éléments, mais il pourrait  en être prévu moins ou davantage. Dans les       fig.    2 à 4, pour simplifier le dessin, on n'a.  au contraire représenté que trois éléments  seulement, mais toutes les explications qui  peuvent être données en référence à ces  figures vaudraient également  mutatis mu  tandis  pour un autre nombre quelconque de  tels éléments. Dans ces     fig.    2 à 4 l'élément  inférieur 2 comporte à sa partie supérieure  deux poulies 7, tandis que l'élément suivant  3 comporte à sa partie inférieure deux pou  lies 8.

   De même, l'élément 3 porte à sa     partie     supérieure deux poulies 9, tandis que l'élé  ment 4 porte une poulie unique 10 et un  point d'attache 11 pour un câble 12 qui, pas  sant alternativement sur     une    poulie 9, sous    la poulie 10 et sur la seconde poulie 9, des  cend, passe sous une poulie 8, sur une poulie  7, sous la seconde poulie 8, sur la seconde  poulie 7 et. redescend pour passer sur une  poulie de renvoi fixe 13 d'où il se rend à un  treuil de     manoeuv        re    approprié non représenté.  



  Tout. cet agencement de poulies et de  câbles décrit en référence à l'un des côtés du  mât est exactement répété sur le côté opposé  comme le montre     fig.    4. Les deux câbles se  rendent à un treuil double qui permet de les       manoeuvrer    en     synchronisme    rigoureux.  



  La traction du câble 12 oblige sur chaque  élément les poulies     mouflées    en zigzag à se  rapprocher les unes des autres. En     d'autres     termes, si l'on considère les éléments 2 et 3,  la traction du câble 12 tend à -rapprocher les  poulies 8 des poulies 7, c'est-à-dire à soulever  l'élément 3 par rapport à l'élément 2.  



  Finalement donc la     manoeuvre    des deux  câbles 12 permet d'assurer le développement  du mât tout entier à. partir du sol sans avoir  à grimper sur celui-ci, comme dans des dis  positions connues.  



  Pour éviter que les éléments successifs ne  se développent dans un ordre quelconque, on  prévoit des moyens permettant de les ver  rouiller les uns avec les autres et. de les libérer  au fur et à mesure des besoins. Par exemple  on pourra tout d'abord verrouiller l'élément 2  à l'élément 3 et laisser se développer l'élé  ment 4 seul. Une fois ce développement ter  miné, on verrouillera. ledit élément 4 à l'élé  ment 3 et on déverrouillera les éléments 2 et  3 l'un d'avec l'autre. On pourra alors faire  monter l'ensemble des éléments 3 et 4 par  rapport. à l'élément. 2, puis verrouiller finale  ment l'élément 2 avec l'élément 3 lorsque le  mouvement de développement sera terminé.  De cette manière tous les verrouillages s'ef  fectuent au sol, sans qu'il soit nécessaire  d'avoir recours à. un spécialiste de la char  pente.  



  Bien entendu, il est nécessaire que les di  vers éléments     télescopiques    soient exactement  guidés les uns par rapport aux autres, que  leur mouvement de développement respectif  soit limité, de manière à éviter tout incident,      et enfin que les dispositifs de verrouillage  susceptibles de les lier les uns aux autres  contribuent à assurer la rigidité du mât. Dans  l'exemple représenté tout ceci est obtenu de  la façon suivante     (fig.    5 à 8).  



  Si l'on considère l'élément inférieur du  mât. il est constitué par quatre montants en  forme de     cornière,    qu'on a désignés par 2 en       fig.    5 à 8 de façon à correspondre à     fig.    1 à  5. Ces cornières 2 présentent l'angle de leur  profil en direction du centre du profil de  l'élément. Chacune d'entre elles est associée  à deux autres fers 14 présentant un profil en  forme d'angle droit avec l'extrémité     14a    de  l'un des côtés rabattu extérieurement à 90 .  Si l'on considère un de ces fers 14 (fi-. 6).  son aile à extrémité non rabattue est appli  quée contre une aile de la cornière 2 et lui  est fixée par des rivets tels que 15.

   Son autre  aile s'étend dans le prolongement de la  seconde aile de la cornière 2, tandis que le  bord rabattu     14a    de cette autre aile est di  rigé vers l'intérieur du profil de l'élément.  



  Les montants 14 sont réunis les uns aux  antres par des croisillons 16 susceptibles de  présenter toute disposition appropriée, par  exemple en oblique et de se croiser les uns les  autres, comme montré en     fig.    1 à 5, ou bien  au contraire en se croisant en forme de X, à  la façon connue dans la charpente métal  lique.  



  Le second élément du mât est constitué  exactement comme le précédent. On a     désigné     par 3 ses montants: longitudinaux en forme  de cornière, ses autres parties portant exacte  ment les mêmes références que pour le pre  mier élément, ce qui dispense de toute expli  cation complémentaire. Il est dimensionné de  telle manière que les extrémités de chaque fer  cornière 3 viennent glisser par leurs faces  intérieures contre les bords rabattus     14u    cor  respondants de l'élément 2. On comprend  qu'ainsi on assure un guidage parfait de l'élé  ment 3 à l'intérieur de l'élément 2, par des       movens    simples, ne nécessitant aucun usinage  mécanique.  



  Vers le haut de l'élément. extérieur 2 on a       sondé    dans l'espace libre situé entre les deux    fers 14 de chaque angle de l'élément une  petite tôle horizontale 17     (fig.    5 et 7), cepen  dant que vers le bas de l'élément suivant 3  on a soudé dans l'angle intérieur de la cor  nière 3 un fer 18 propre à venir buter contre  la tôle<B>17.</B> On comprend que lorsque l'élément  3 s'élève par rapport à l'élément 2, son  mouvement se trouve limité par butée du fer  1.8 contre la tôle 17, ce qui évite tout risque  de dégagement intempestif d'un élément par  rapport à l'autre. En outre, tout au sommet  de l'élément extérieur 2, on a soudé entre les  fers 14 un bloc 19     (fig.    5 et 8) dont la face  libre est taillée en biseau incliné vers le bas.

    Dans la cornière 3 du second élément on a  également soudé un bloc 20 profilé de ma  nière à venir s'ajuster exactement contre le  bloc 19 lorsque la butée 18 est venue porter  contre la tôle 17. En raison du     taillage    en  biseau, les deux blocs 19 et 20 réalisent une  sorte de coinçage     assurant    le centrage des  deux éléments l'un par rapport à l'autre et  absorbant les jeux inévitables. Les deux blocs  19 et 20 sont en outre perforés pour recevoir  un même boulon transversal 21 qui assure le  verrouillage des deux éléments considérés l'un  avec l'autre à la position de développement  maximum.  



  Bien entendu le bloc 20 est dimensionné  de manière à pouvoir passer au droit de la  tôle 17 afin de ne pas gêner le mouvement de  coulissement des deux éléments.  



  On peut prévoir une disposition analogue  pour permettre le verrouillage des deux élé  ments à la position repliée.  



  Dans la variante de     fig.    9 les montants<B>2</B>  sont des fers profilés en escalier (profil cons  titué par la juxtaposition de deux angles  droits     successifs).        Les    fers 14 qui leur sont  associés :sont de simples cornières dont une  aile est serrée contre     l'une    des ailes exté  rieures du fer 2, tandis que l'autre aile se  développe dans le prolongement du côté de  l'angle droit du profil du fer 2 le plus voi  sin.

   Le second élément est établi de même  façon, mais sur l'une des ailes intermédiaires  du fer 3 est soudé un goujon 22 sur lequel  est monté fou un galet 23 dont la     péripbérig         roule contre l'une des ailes     intermédiaires    du  fer 2, tandis que la face bute contre l'autre  aile intermédiaire de ce fer. On     comprend     que là encore les quatre galets 23 associés au  second élément assurent le guidage de cet élé  ment à frottement réduit, puisqu'une bonne  partie des efforts est. transmise par des sur  faces à roulement.    La disposition de     fig.    10 permet de trans  mettre la totalité des efforts entre les deus  éléments par des galets.

   Dans cette dispo  sition le montant 2 présente un profil com  plexe constitué par deux ailes extérieures à  90  et une sorte de<B>U</B> intermédiaire dont le  voile est à 45  des deux ailes précitées. Le  galet 23 est monté autour d'un axe 22 porté  par un étrier 24 disposé à 45  par     rapport          aux    côtés des deux éléments considérés, de  telle manière que ce galet 23 vienne rouler  au fond de la partie en<B>U</B> du profil du fer 2.  



  Fi(. 11 montre une disposition dans la  quelle le guidage des deux éléments s'effec  tue par des     surfaces    de glissement. Le mon  tant 2 considéré est constitué par un ensem  ble de     deux    cornières à. 45" associées de     faeoil     à réaliser un angle droit, les deux ailes inter  médiaires     serrant    entre elles un fer plat 25  destiné à. jouer le rôle de rail.

   Comme montré,  le fer 25 ne s'étend que sur environ la. moitié  de la. longueur des deux ailes obliques et ces  ailes divergent légèrement. au-delà. du fer, de  manière à constituer une sorte de guide laté  ral qui, en ce qui concerne le second élé  ment, sert pour retenir le fer 25 du premier  élément, les deux fers 25 en présence glis  sant ainsi l'un contre l'autre, comme le fait  bien comprendre la figure.  



       Quelle    que soit la façon dont est réalisé le  guidage des éléments, à l'état monté (fi-. 12  et 13) la. grue est divisée en deux éléments  principaux, savoir, d'une part, le mât, télesco  pique 2, 3, 4, 5, constitué par un certain nom  bre d'éléments (quatre dans l'exemple repré  senté), d'autre part, le socle 1.  



  Le mât 2, 3, 4, 5     (fig.    12) est couché  horizontalement sur une remorque 26, ses élé  ments     étant    à la. disposition rentrée les uns    dans les     autres,    c'est-à-dire à la position d'en  combrement minimum. Au     mât    se rattachent  la flèche et la     contre-flèelie    de la grue, qu'on  peut supposer portées par le camion 27 au  quel la remorque 26 est attelée. Bien entendu  le mât 2, 3, 4, 5 est. pourvu d'un système de  câbles de levage du genre     sus-décrit    en réfé  rence aux<U>fi-.</U> 2 à 4, et qu'on n'a pas repré  senté pour ne pas compliquer inutilement le  dessin.  



  Le socle 1. est pourvu de     roues    à menton  net 28 (fi-. 13) afin de pouvoir rouler sur  une voie appropriée prévue sur le chantier,  niais pour permettre le transport sur route,  on le monte sur un essieu routier 29, par  exemple pourvu de roues à pneumatiques 30,  et on l'attelle à. un camion 31. Ce socle com  porte des dispositifs, non représentés, de blo  cage sur les rails sur lesquels les roues 28  sont appelées à, rouler. Il renferme également  les treuils appropriés pour assurer le levage  des     charges    et la levée du mât.

   Il comporte à  une extrémité le coffre usuel 32 destiné à  être rempli de matériaux lourds     pour    former  contrepoids lors de l'utilisation de la grue  montée, ce coffre pouvant recevoir une  chèvre de levage (qu'on     petit    supposer  portée par le camion 31) et dont. on verra  plus loin l'utilisation. Enfin il comporte en  core, bien entendu, une embase pour recevoir  le mât 2, 3, 4, 5 et cette embase est confor  mée de telle manière que le mât puisse pi  voter sur elle autour d'un axe     transversal;     par exemple la. fixation du mât à l'embase  peut être assurée par des boulons transver  saux dont deux au moins se trouvent dans le  prolongement, l'un de l'autre au voisinage im  médiat du côté transversal de l'embase opposé  au coffre 32.  



  Pour monter en place la grue ainsi cons  tituée, on amène le socle 1 sur la voie sur la  quelle la grue devra se déplacer, on l'y sou  tient par des vérins, on démonte les roues 30  et on descend le socle jusqu'à le faire reposer  sur les rails 33     (fig.    14) de la voie par le  moyen des roues 28. On monte en place une  chèvre 34 sur le coffre 32. Puis on amène la  remorque 26 portant le mât 2, 3, 4, 5 de ma-           nière    à     engager    l'extrémité inférieure du pre  mier élément de ce mât sur le socle et on  articule cette extrémité à l'embase portée par  ledit socle.  



  On présente     alors    la     contre-flèclie    35 à  l'état     renversé    et on l'articule au sommet du  mât par un boulon transversal. On amarre à,  l'extrémité de la chèvre un câble 36 qu'on  fait passer sur la chèvre 34 et qu'on attache  à l'un des treuils du socle. En mettant en  marche ce treuil, on assure le relevage de la       contre-flèche    35     qu'on    peut dresser perpen  diculairement au mât (position de     fig.    15).  A ce moment on la fixe en position par ses  haubans tels que 37 et on peut détacher le  câble 36.  



  On amène alors la flèche 38     (fig.        1.6)    et  on l'articule au sommet du mât par Lin bou  lon transversal.  



  On a, d'autre part, solidement,     mouflé    le  haut du mât 2, 3, 4, 5 à la chèvre 34 par le  moyen d'un câble 39 dont on attelle l'extré  mité à. un treuil du socle 1. En mettant en  marche ce treuil, on peut relever progres  sivement. le mât. Quand ce relevage a atteint  un certain degré     (fig.    17), la flèche 38, dont  l'extrémité libre glissait sur le sol, se trouve  perpendiculaire au mât encore fortement  oblique. On arrête alors le mouvement de  relevage et on fixe la flèche en position par  un hauban tel que 40. On peut, d'autre part,       dégager    la remorque 26 devenue inutile.  



  On reprend alors le mouvement de     rele-          vabe    du mât qu'on amène     progressivement    à  la. verticale     (fig.    18). On l'y fixe par des  haubans tels que 41. La grue est alors prête  à entrer en service. Dans le cas le plus cou  rant où on l'amène     sur    le chantier au début  (le la construction, on peut commencer à  l'utiliser à la position basse du mât et monter       eelui-ei    au fur et à mesure des besoins, ce qui  présente l'avantage que les limitations de  charge et de portée provenant de la hauteur  du mât n'interviennent pratiquement pas pen  dant toute la première partie du travail.  



       I'ig.    19 montre, à titre d'indication, la  grue avec le mât à sa     plus    grande hauteur et  elle fait bien ressortir les divers plans hori-         zontattx    A,     B,   <I>C" et D</I> dans lesquels on peut  situer la flèche au fur et à mesure de  l'avancement de la construction en     élévant    le  mât élément par élément.



      Telescopic mast crane. The present invention relates to cranes, such as those used on construction sites, in which the mast of the crane is vertical and adjustable in height as and when required.



  Cranes are known comprising a telescopic mast consisting of tubular elements sliding one inside the other, these elements being able to be lifted hydraulically. Such a construction is extremely complicated and expensive and, moreover, unless the lower elements are given an inadmissible diameter, it does not make it possible to ensure sufficient rigidity for the mast. It must be reinforced by numerous shrouds, which considerably hinders maneuvers in the vicinity of the crane.



  The crane according to the invention is characterized in that its mast is formed by elements in the form of hollow parallelepipeds sliding one inside the other, provided with respective guide means on their vertical edges.



  The accompanying drawing shows, by way of example, an embodiment of the invention. Fig. 1 is a general elevational view of this embodiment, at the maximum height position of its mast.



       Fig. 2 shows a mast with three elements in the folded position.



  Fi-. 3 shows it in the fully developed position.



  Fi-. 4 is a plan view on a large scale cl u mast according to FIG. 1 and 2. Fig. 5 is a detail section on a large scale through a vertical plane passing through the diagonal of the square of the horizontal profile of the mast.



       Fig. 6 to 8 are sections along VI-VI, VII-VII, VIII-VIII (fig. 5 <B>) </B> respectively, the sectional plane of fig. 5 being indicated at V-V in fig. 8.



       Fig. 9 to 11 are detail views in section through a horizontal plane indicating three possible variants in the respective guiding of the telescopic elements on one another.



       Fig. 12 shows the telescopic mast of the crane in the fully folded state and lying horizontally on a hitched trailer.



       Fig. 13 similarly shows the base of this crane mounted on a road axle and coupled behind a tractor truck.



       Fig. 14 shows the first phase of assembly, the mast having been articulated to the base and having received the counter-jib, but the latter having not yet been erected perpendicular to the mast.



       Fig. 15 shows the parts after dressing the counter-jib.



       Fig. 16 shows the parts after articu lation of the jib to the mast.



       Fig. 17 shows them after partial lifting of the mast and fixing of the jib.



       Fig. 18 shows the entire mounted crane, the mast having remained in the lowest position. Fig. 19 very schematically indicates the respective position of the parts at the maximum height position of the mast.



  The crane shown in fig. 1 comprises a base 1, mounted on wheels, as shown, or supported in any other way. On this base is mounted a first iron frame element 2, to. square section, consisting of four uprights joined to each other by appropriate braces. Inside the element 2 can slide a second element 3, of similar construction, but of slightly smaller horizontal dimensions. Likewise, in the element 3 can slide an element 4 in which can in turn slide an element 5. The set of elements 2, 3, 4, 5 carries out the telescopic mast at the top of which the boom 6 is articulated. of the crane.

   All these elements are suitably guided one inside the other, so that their whole has the desired lateral rigidity, without it being necessary for this to be haubanner. In addition, means are provided for raising each of the elements relative to the other during the unfolding of the mast, without needing to resort to a fitter climbed on the mast and forced to exert a lifting force. at a great height above the ground.



  It is understood that the number of elements 2 to 5 can be arbitrary. In fig. 1 shows four elements, but less or more could be provided. In fig. 2 to 4, to simplify the drawing, we do not have. on the contrary shown only three elements, but all the explanations which can be given with reference to these figures would also apply mutatis mu while for any other number of such elements. In these figs. 2 to 4 the lower element 2 comprises at its upper part two pulleys 7, while the next element 3 comprises at its lower part two pulleys 8.

   Likewise, element 3 carries two pulleys 9 at its upper part, while element 4 carries a single pulley 10 and an attachment point 11 for a cable 12 which, not alternately on a pulley 9, under the pulley 10 and on the second pulley 9, ash, passes under a pulley 8, over a pulley 7, under the second pulley 8, over the second pulley 7 and. descends to pass over a fixed return pulley 13 from where it goes to an appropriate maneuvering winch not shown.



  All. this arrangement of pulleys and cables described with reference to one of the sides of the mast is exactly repeated on the opposite side as shown in fig. 4. The two cables go to a double winch which allows them to be maneuvered in strict synchronism.



  The traction of the cable 12 forces the zigzag pulleys on each element to come closer to one another. In other words, if we consider the elements 2 and 3, the traction of the cable 12 tends to bring the pulleys 8 of the pulleys 7, that is to say to raise the element 3 relative to the 'item 2.



  Finally, therefore, the maneuvering of the two cables 12 ensures the development of the entire mast. from the ground without having to climb on it, as in known positions.



  To prevent the successive elements from developing in any order, means are provided for locking them with rust with each other and. to release them as and when needed. For example, we can first lock element 2 to element 3 and let element 4 develop alone. Once this development is complete, we will lock. said element 4 to element 3 and elements 2 and 3 will be unlocked from one another. We can then raise all of the elements 3 and 4 in relation. to the element. 2, then finally lock element 2 with element 3 when the development movement is complete. In this way all the locks are done on the ground, without having to resort to. a slope tank specialist.



  Of course, it is necessary for the various telescopic elements to be exactly guided with respect to each other, for their respective development movement to be limited, so as to avoid any incident, and finally for the locking devices liable to bind them together. to each other help to ensure the rigidity of the mast. In the example shown, all this is obtained as follows (fig. 5 to 8).



  If we consider the lower element of the mast. it consists of four uprights in the form of an angle, which have been designated by 2 in FIG. 5 to 8 so as to correspond to fig. 1 to 5. These angles 2 have the angle of their profile in the direction of the center of the profile of the element. Each of them is associated with two other irons 14 having a profile in the form of a right angle with the end 14a of one of the sides folded outwardly at 90. If we consider one of these 14 irons (fig. 6). its wing with a non-folded end is applied against a wing of the angle iron 2 and is fixed to it by rivets such as 15.

   Its other wing extends in the extension of the second wing of the angle iron 2, while the folded edge 14a of this other wing is directed towards the inside of the profile of the element.



  The uprights 14 are joined to each other by braces 16 capable of having any suitable arrangement, for example obliquely and of crossing one another, as shown in FIG. 1 to 5, or on the contrary by crossing each other in the shape of an X, in the manner known in the metal framework.



  The second part of the mast is made exactly like the previous one. Its uprights have been designated by 3: longitudinal in the form of an angle iron, its other parts bearing exactly the same references as for the first element, which dispenses with any additional explanation. It is dimensioned in such a way that the ends of each angle iron 3 slide by their inner faces against the corresponding folded edges 14u of the element 2. It is understood that this ensures perfect guidance of the element 3 to the interior of the element 2, by simple means, requiring no mechanical machining.



  Up the item. outside 2 we probed in the free space located between the two bars 14 of each corner of the element a small horizontal plate 17 (fig. 5 and 7), however that towards the bottom of the next element 3 we have welded in the interior angle of the horn 3 a clean iron 18 to abut against the sheet <B> 17. </B> It is understood that when the element 3 rises relative to the element 2, its movement is limited by the stop of the iron 1.8 against the sheet 17, which avoids any risk of untimely release of one element from the other. In addition, at the very top of the outer element 2, a block 19 (FIGS. 5 and 8) has been welded between the irons 14, the free face of which is cut in a bevel inclined downwards.

    In the angle 3 of the second element, a profiled block 20 has also been welded so as to fit exactly against the block 19 when the stop 18 has come to bear against the sheet 17. Due to the bevel cutting, the two blocks 19 and 20 perform a kind of wedging ensuring the centering of the two elements relative to each other and absorbing the inevitable games. The two blocks 19 and 20 are also perforated to receive the same transverse bolt 21 which ensures the locking of the two elements considered with one another at the position of maximum development.



  Of course, the block 20 is dimensioned so as to be able to pass in line with the sheet 17 so as not to hinder the sliding movement of the two elements.



  A similar arrangement can be provided to allow locking of the two elements in the folded position.



  In the variant of fig. 9 the uprights <B> 2 </B> are shaped stepped bars (profile constituted by the juxtaposition of two successive right angles). The irons 14 associated with them: are simple angles, one wing of which is tight against one of the outer wings of the iron 2, while the other wing develops in the extension of the side of the right angle of the profile of the closest iron 2.

   The second element is established in the same way, but on one of the intermediate wings of the iron 3 is welded a pin 22 on which is mounted a roller 23 whose peripbérig rolls against one of the intermediate wings of the iron 2, while the face abuts against the other intermediate wing of this shoe. It is understood that here again the four rollers 23 associated with the second element ensure the guiding of this element with reduced friction, since a good part of the forces is. transmitted by rolling faces. The arrangement of fig. 10 allows all of the forces to be transferred between the two elements by rollers.

   In this arrangement, the upright 2 has a complex profile consisting of two outer wings at 90 and a sort of intermediate <B> U </B>, the veil of which is at 45 from the two aforementioned wings. The roller 23 is mounted around an axis 22 carried by a bracket 24 arranged at 45 relative to the sides of the two elements considered, so that this roller 23 comes to roll at the bottom of the part in <B> U </ B > the profile of the iron 2.



  Fi (. 11 shows an arrangement in which the guiding of the two elements is effected by sliding surfaces. Item 2 considered is constituted by a set of two angles at. 45 "associated so as to achieve an angle straight, the two intermediate wings clamping between them a flat iron 25 intended to act as a rail.

   As shown, iron 25 extends only about 1a. half of the. length of the two oblique wings and these wings diverge slightly. beyond. iron, so as to constitute a sort of lateral guide which, as regards the second element, serves to retain the iron 25 of the first element, the two irons 25 in presence thus sliding against each other , as can be seen from the figure.



       Whatever the way in which the guiding of the elements is carried out, in the assembled state (fig. 12 and 13) the. crane is divided into two main elements, namely, on the one hand, the mast, telescope 2, 3, 4, 5, consisting of a certain number of elements (four in the example shown), on the other part, the base 1.



  The mast 2, 3, 4, 5 (Fig. 12) is lying horizontally on a trailer 26, its elements being at the. layout tucked into each other, that is to say in the minimum space requirement. To the mast are attached the jib and the crane against the boom, which can be assumed to be carried by the truck 27 to which the trailer 26 is coupled. Of course the mast 2, 3, 4, 5 is. provided with a system of lifting cables of the type described above with reference to <U> fi-. </U> 2 to 4, and which has not been shown so as not to unnecessarily complicate the drawing.



  The pedestal 1. is provided with wheels with clear chin 28 (fig. 13) in order to be able to drive on a suitable track provided on the site, but to allow transport on the road, it is mounted on a road axle 29, for example. provided with pneumatic wheels 30, and it is hitched to. a truck 31. This base com carries devices, not shown, blocking cage on the rails on which the wheels 28 are called to roll. It also contains the appropriate winches to ensure the lifting of the loads and the lifting of the mast.

   It comprises at one end the usual box 32 intended to be filled with heavy materials to form a counterweight when using the mounted crane, this box being able to receive a lifting goat (which one small suppose carried by the truck 31) and whose. we will see the use later. Finally it also comprises, of course, a base for receiving the mast 2, 3, 4, 5 and this base is shaped so that the mast can vote on it around a transverse axis; for example the. Fixing of the mast to the base can be ensured by transverse bolts of which at least two are in the extension, one of the other in the immediate vicinity of the transverse side of the base opposite to the box 32.



  To assemble the crane thus constituted, the base 1 is brought onto the track on which the crane will have to move, it is supported there by jacks, the wheels 30 are removed and the base is lowered to make it rest on the rails 33 (fig. 14) of the track by means of the wheels 28. A goat 34 is mounted in place on the trunk 32. Then the trailer 26 is brought carrying the mast 2, 3, 4, 5 so as to engage the lower end of the first element of this mast on the base and this end is articulated to the base carried by said base.



  The counter-beam 35 is then presented in the inverted state and it is articulated at the top of the mast by a transverse bolt. A cable 36 is moored at the end of the goat which is passed over the goat 34 and which is attached to one of the winches of the base. By starting this winch, the counter-jib 35 is raised which can be raised perpendicularly to the mast (position of FIG. 15). At this moment it is fixed in position by its shrouds such as 37 and the cable 36 can be detached.



  We then bring the jib 38 (fig. 1.6) and we articulate it at the top of the mast by a transverse bolt.



  We have, on the other hand, firmly, the top of the mast 2, 3, 4, 5 to the goat 34 by means of a cable 39, the end of which is harnessed to. a winch from the base 1. By starting this winch, you can raise it gradually. the mast. When this lifting has reached a certain degree (fig. 17), the boom 38, the free end of which slipped on the ground, is perpendicular to the still strongly oblique mast. The lifting movement is then stopped and the jib is fixed in position by a shroud such as 40. On the other hand, the trailer 26 can be released, which has become unnecessary.



  We then resume the lifting movement of the mast which is gradually brought to the. vertical (fig. 18). It is fixed to it by guy ropes such as 41. The crane is then ready to enter service. In the most common case where it is brought to the site at the start (during construction, we can start using it in the low position of the mast and raise it as and when required). has the advantage that the load and reach limitations due to the height of the mast are hardly involved during the whole first part of the work.



       I'ig. 19 shows, as an indication, the crane with the mast at its greatest height and it clearly shows the various horizontal planes A, B, <I> C "and D </I> in which one can locate the boom as the construction progresses by raising the mast element by element.

 

Claims (1)

REVENDICATION: Grue à mât télescopique vertical, notam ment pour chantiers de construction, caracté risée en ce que son mât est constitué par des éléments en forme de parallélépipèdes creux coulissant les uns dans les autres et pourvus de moyens de guidage respectifs disposés sur leurs arêtes verticales. SOUS-REVENDICATIONS 1. Grue suivant la revendication, caracté risée en ce que chaque élément comporte quatre montants verticaux réunis par des croisillons latéraux. 2. CLAIM: Vertical telescopic mast crane, in particular for construction sites, characterized in that its mast consists of elements in the form of hollow parallelepipeds sliding one inside the other and provided with respective guide means arranged on their vertical edges . SUB-CLAIMS 1. Crane according to claim, characterized in that each element comprises four vertical uprights joined by lateral braces. 2. Grue suivant la revendication, caracté risée en ce que les éléments portent sur au moins deux faces des poulies de renvoi entre lesquelles un même câble circule en zigzag, en partant du bas du mât pour aller s'accro cher à l'élément supérieur, de telle manière que la traction de ce câble tende à provo quer la levée de chaque élément par rapport au précédent. 3. Grue suivant la revendication, caracté risée en ce que chaque élément comporte une butée coopérant avec une butée correspon dante portée par l'élément qui le précède, de manière que lors de la levée du mât l'élément considéré ne puisse se dégager entièrement de l'élément précédent. 4. Crane according to claim, characterized in that the elements bear on at least two faces of the deflection pulleys between which the same cable runs in zigzag, starting from the bottom of the mast to hang on to the upper element, such that the traction of this cable tends to cause the lifting of each element with respect to the previous one. 3. Crane according to claim, character ized in that each element comprises a stop cooperating with a corresponding stop carried by the element which precedes it, so that when the mast is raised, the element in question cannot be released entirely. of the previous item. 4. Grue suivant la revendication, caracté risée en ce que chaque élément comporte des surfaces obliques qui, en fin de levée de l'élé ment considéré, viennent coopérer avec des surfaces correspondantes portées par l'élé ment précédent de manière à centrer le pre mier dans le second en absorbant le jeu mé nagé entre les organes de guidage. 5. Grue suivant la revendication et la sous-revendication 1, caractérisée en ce que l'arête de chaque élément est constituée par un fer cornière s'ouvrant vers l'extérieur et en ce que les ailes de ce fer sont guidées par des ferrures fixées à l'intérieur des arêtes de l'élément précédent. 6. Crane according to claim, characterized in that each element comprises oblique surfaces which, at the end of the lifting of the element in question, cooperate with corresponding surfaces carried by the preceding element so as to center the first in the second by absorbing the clearance between the guide members. 5. Crane according to claim and sub-claim 1, characterized in that the edge of each element is constituted by an angle iron opening outwards and in that the wings of this iron are guided by fittings fixed inside the edges of the previous element. 6. Grue suivant la -revendication et la sous-revendication 1, caractérisée en ce que l'arête de chaque élément est constituée par un rail creux dans lequel roulent des galets portés par les arêtes de l'élément suivant. 7. Grue suivant la revendication et la sous-revendication 1, caractérisée en ce que l'arête de chaque élément est constituée par une glissière s'ouvrant dans un sens pour recevoir la glissière de l'élément précédent. 8. Crane according to claim and sub-claim 1, characterized in that the edge of each element is constituted by a hollow rail in which rollers carried by the edges of the following element roll. 7. Crane according to claim and sub-claim 1, characterized in that the edge of each element is constituted by a slide opening in one direction to receive the slide of the preceding element. 8. Grue suivant la revendication et la sous-revendication 1, caractérisée en ce que l'extrémité inférieure du premier élément, de son mât est, articulé de fa.eon démontable sur un socle, de telle sorte qu'il soit possible de dresser ledit mât. sur ce socle après y avoir fixé la flèche et la contre-flèche, et avant de procéder à la levée du mât. Crane according to claim and sub-claim 1, characterized in that the lower end of the first element, of its mast, is articulated in a removable manner on a base, so that it is possible to raise said mast . on this base after fixing the jib and the counter-jib to it, and before lifting the mast.
CH291599D 1951-06-18 1951-06-18 Telescopic mast crane. CH291599A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH291599T 1951-06-18

Publications (1)

Publication Number Publication Date
CH291599A true CH291599A (en) 1953-06-30

Family

ID=4487518

Family Applications (1)

Application Number Title Priority Date Filing Date
CH291599D CH291599A (en) 1951-06-18 1951-06-18 Telescopic mast crane.

Country Status (1)

Country Link
CH (1) CH291599A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1077847B (en) * 1956-03-21 1960-03-17 Krupp Ardelt Gmbh Dismountable gantry crane
US3045837A (en) * 1959-12-23 1962-07-24 Liebherr Hans Rotary tower crane
US20140144860A1 (en) * 2012-11-27 2014-05-29 Kuo Po Hsuan Telescopic tower crane system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1077847B (en) * 1956-03-21 1960-03-17 Krupp Ardelt Gmbh Dismountable gantry crane
US3045837A (en) * 1959-12-23 1962-07-24 Liebherr Hans Rotary tower crane
US20140144860A1 (en) * 2012-11-27 2014-05-29 Kuo Po Hsuan Telescopic tower crane system

Similar Documents

Publication Publication Date Title
FR2481248A1 (en) LIGHTWEIGHT AND RESISTANT ARROW ELEMENTS FOR TELESCOPIC CRANE ARROW AND CRANE ARROW SHAPED OF SUCH ELEMENTS
FR2653478A1 (en) Device for driving and displacing support elements for tarpaulins constituting a movable cover
EP3146131B1 (en) Assembly system and method for assembling a tower for a wind generator
WO2009125127A1 (en) Giant gantry
CH291599A (en) Telescopic mast crane.
FR2560864A1 (en) Bearings for telescopic crane jib
EP0360702B1 (en) Collapsible crane with a jib comprising two or three elements articulating upon one another
LU85595A1 (en) CONSTRUCTION ELEMENT IN THE FORM OF A TRANSPORTABLE CONTAINER AND CONSTRUCTION FORMED BY ASSEMBLY OF SUCH ELEMENTS
FR2597129A1 (en) Folding lightweight bridge-support enabling so-called heavy vehicles, particularly armoured vehicles, to cross gaps
EP2191744B1 (en) Load taking profile
BE504079A (en)
FR2577584A1 (en) Length-adjustable rigid structure, particularly for an oil rig
FR1465110A (en) Gantry crane and beam for this one
EP1013848B1 (en) Roof-scaffold
FR2732323A1 (en) BALLAST BLOCKS FOR CRANES AND ASSOCIATED FIXING DEVICE
CA2296756C (en) Installation for laser welding of overlapping parts
FR2761971A1 (en) AUTOMATED CRANE WITH FOLDABLE BOOM, WITH LATERAL FOLDING FOR TRANSPORT
FR2724920A1 (en) Swingletree for handling of heavy aircraft engines
FR2464351A1 (en) Climbing hoist for building construction - uses horizontal jib on portal carriage on two vertical rails and jib pivots vertical for transit
FR1264688A (en) Double Girder Overhead Crane
FR2608532A1 (en) Towed load-bearing assembly with a manoeuvring assembly for folding and unfolding a deck
FR2665917A1 (en) Deployable modular structure
FR2577863A1 (en) Autonomous bridge-laying vehicle for gaps of twenty to forty metres
FR3025232A1 (en) METHOD OF INSTALLING PREFABRICATED FACADE PANELS
FR2581185A1 (en) Weighbridge which can be transported without dismantling