BR112012019203A2 - construção de torre de concreto, método para erguer uma construção de torre, elemento de torre de concreto, e, elemento interligante. - Google Patents

construção de torre de concreto, método para erguer uma construção de torre, elemento de torre de concreto, e, elemento interligante.

Info

Publication number
BR112012019203A2
BR112012019203A2 BR112012019203A BR112012019203A BR112012019203A2 BR 112012019203 A2 BR112012019203 A2 BR 112012019203A2 BR 112012019203 A BR112012019203 A BR 112012019203A BR 112012019203 A BR112012019203 A BR 112012019203A BR 112012019203 A2 BR112012019203 A2 BR 112012019203A2
Authority
BR
Brazil
Prior art keywords
tower
construction
concrete
concrete tower
erecting
Prior art date
Application number
BR112012019203A
Other languages
English (en)
Inventor
Hangel Jorgen
Original Assignee
Conelto Aps
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Conelto Aps filed Critical Conelto Aps
Publication of BR112012019203A2 publication Critical patent/BR112012019203A2/pt

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/62Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
    • B66C1/66Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled for engaging holes, recesses, or abutments on articles specially provided for facilitating handling thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/39Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/12Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/16Prestressed structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/342Arrangements for stacking tower sections on top of each other
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2103/00Material constitution of slabs, sheets or the like
    • E04B2103/02Material constitution of slabs, sheets or the like of ceramics, concrete or other stone-like material
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2230/00Manufacture
    • F05B2230/60Assembly methods
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Sustainable Energy (AREA)
  • Sustainable Development (AREA)
  • Materials Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Bridges Or Land Bridges (AREA)
  • Wind Motors (AREA)
  • Foundations (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

construção de torre de concreto, método para erguer uma construção de torr, elemento de torre de concreto, e, elemento interligante. uma construção de torre de concreto (10) compreendendo: uma fundação (12), uma pluralidade de elementos de torre de concreto pré-fabricados (24), cada um tendo uma lado externo (32), um lado interno (34), uma espessura de material (36) provida no meio e superfícies de topo (38) e de base (40), dito elemento de torre tendo um centro oco, ditos elementos de torre (24) são arranjados um elemento de torre (24) no topo de outro formando uma coluna (22) no topo da fundação (12), uma pluralidade de tendões (28) dispostos no centro oco, para aplicar uma força de tração à coluna (22), em que a construção de torre (10) compreende adicionalmente um elemento de distribuição de força superior (26) disposto no topo da coluna (22) e um elemento de distribuição de força inferior (18) disposto na fundação (12), em que cada tendão (28) é conectado no elementode distribuição de força superior (18) e ao elemento de distribiução de força inferior (26) por meios de ligação cooperantes (30,30). além disso. é descrito um método de erigir dita construção de torre (10), um elemento de torre e um elemento de fundação.
BR112012019203A 2010-02-01 2011-01-31 construção de torre de concreto, método para erguer uma construção de torre, elemento de torre de concreto, e, elemento interligante. BR112012019203A2 (pt)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DKPA201070030 2010-02-01
DKPA201070284 2010-06-22
PCT/DK2011/050022 WO2011091799A1 (en) 2010-02-01 2011-01-31 A tower construction and a method for erecting the tower construction

Publications (1)

Publication Number Publication Date
BR112012019203A2 true BR112012019203A2 (pt) 2018-03-27

Family

ID=44318682

Family Applications (1)

Application Number Title Priority Date Filing Date
BR112012019203A BR112012019203A2 (pt) 2010-02-01 2011-01-31 construção de torre de concreto, método para erguer uma construção de torre, elemento de torre de concreto, e, elemento interligante.

Country Status (7)

Country Link
US (2) US9021757B2 (pt)
EP (1) EP2531674B1 (pt)
CN (2) CN104595126A (pt)
BR (1) BR112012019203A2 (pt)
CA (1) CA2787932C (pt)
DK (1) DK2531674T3 (pt)
WO (1) WO2011091799A1 (pt)

Families Citing this family (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2339094B1 (en) * 2009-12-23 2016-06-15 Soletanche Freyssinet Tower having a pre-stressed concrete column and construction method
BR112015002426A2 (pt) * 2012-08-03 2017-07-04 D Lockwood James torre de turbina de vento segmentada protendida de concreto pré-moldado
DK2893187T3 (da) 2012-09-03 2021-02-08 X Tower Constructions Gmbh Tårnstruktur af et vindkraftværk og metode til stabilisering af et tårnstruktur af et vindkraftværk
EP2925942A4 (en) * 2012-11-27 2016-10-05 Marmen Inc LIFT SYSTEM FOR WIND TURBINE TOWERS AND METHOD FOR SETTING A WIND TURBINE TOWER
US9062662B1 (en) * 2013-03-27 2015-06-23 Ebert Composites Corporation Hybrid pole structure and method of assembly
DE102013105512A1 (de) * 2013-05-29 2014-12-04 Max Bögl Wind AG Betonfundament und Verfahren zur Herstellung eines Betonfundaments für einen Windkraftturm sowie Positioniervorrichtung zur Positionierung von Hüllrohren in einem Betonfundament
CN104234491B (zh) * 2013-06-21 2017-01-04 韩国海洋科学技术院 由合成柱和墙体构成的风塔结构及利用该结构的风塔的施工方法
DE102013225128A1 (de) * 2013-12-06 2015-06-11 Wobben Properties Gmbh Windenergieanlage und Windenergieanlagen-Turm
CN103821676A (zh) * 2014-02-12 2014-05-28 北京金风科创风电设备有限公司 风力发电机组的塔架基础
EP3111022B1 (en) 2014-02-28 2019-07-31 University of Maine System Board of Trustees Hybrid concrete - composite tower for a wind turbine
US9371663B2 (en) * 2014-05-07 2016-06-21 Us Tower Corporation Internally keyed extruded mast system
ES2558025B1 (es) * 2014-07-30 2016-11-11 Acciona Windpower, S.A. Procedimiento de montaje de torres de hormigón de sección decreciente para aerogeneradores y aerogenerador asociado
AU2014410349B2 (en) * 2014-10-31 2020-02-20 Soletanche Freyssinet Method for manufacturing concrete construction blocks for a wind-turbine tower and associated system
FR3029231B1 (fr) * 2014-12-01 2016-12-30 Lafarge Sa Section en beton
CA2973391A1 (en) * 2015-01-09 2016-07-14 Tindall Corporation Tower and method for constructing a tower
PT3277952T (pt) * 2015-04-02 2019-06-05 Arcelormittal Troço de torre de turbina eólica, torre de turbina eólica e procedimento de montagem
WO2017039975A1 (en) * 2015-08-31 2017-03-09 Siemens Energy, Inc. System and method for installing a tensioning tendon in a wind turbine tower
CN105179183A (zh) * 2015-09-11 2015-12-23 中国航空规划设计研究总院有限公司 一种预应力混凝土风电塔架体系及其施工方法
CN105332342B (zh) * 2015-10-30 2017-01-11 中交第二航务工程局有限公司 桥塔悬臂梯度混凝土同步施工方法
CN105781205B (zh) * 2015-11-30 2018-02-06 中国化学工程第三建设有限公司 一种重型塔器设备分段吊装空中组对的就位导向装置
ES2911709T3 (es) * 2016-02-26 2022-05-20 Nordex Energy Spain S A Procedimiento de fabricación de torres de hormigón para aerogeneradores
RU169486U1 (ru) * 2016-08-17 2017-03-21 Общество с ограниченной ответственностью "ГАЛЕН" Армобетонная стойка опоры контактной сети
CN106089596B (zh) * 2016-08-23 2019-06-07 江苏金海新能源科技有限公司 一种钢-预应力混凝土混合式风机直塔筒
ES2922889T3 (es) * 2016-10-24 2022-09-21 Nordex Energy Spain S A Torre de turbina eólica sobre cimentación
CN106762445A (zh) * 2017-01-06 2017-05-31 佛山科学技术学院 一种不锈钢钢筋混凝土海上风电机组塔筒结构
JP6793558B2 (ja) * 2017-01-20 2020-12-02 五洋建設株式会社 水上風力発電施設支持構造物およびその施工方法
EP3683383A1 (en) * 2017-08-02 2020-07-22 Pacadar S.A. Support structure for wind-driven power generators and verticality corrective method thereof
RU178875U1 (ru) * 2017-12-12 2018-04-20 Владимир Васильевич Галайко Композитобетонная стойка опор линии электропередач
EP3521535B1 (en) * 2018-02-05 2020-06-17 Metalvix Engenharia e Consultoria Ltda Wind turbine tower and respective foundation base
US20190292803A1 (en) * 2018-03-26 2019-09-26 General Electric Company Additively manufactured tower structure and method of fabrication
US10570889B2 (en) * 2018-04-23 2020-02-25 General Electric Company Adaptor for wind turbine refurbishment and associated methods
RU182932U1 (ru) * 2018-05-29 2018-09-06 Владимир Васильевич Галайко Композитобетонная стойка опор линии электропередач
RU183088U1 (ru) * 2018-06-13 2018-09-11 Владимир Васильевич Галайко Железобетонная стойка опор линии электропередач
RU185734U1 (ru) * 2018-09-19 2018-12-17 Людмила Николаевна Макеева Стойка опоры контактной сети
CN109139386B (zh) * 2018-09-30 2019-08-23 北京金风科创风电设备有限公司 塔筒段、塔筒、分割方法及风力发电机组
DE102018131443A1 (de) * 2018-12-07 2020-06-10 Wobben Properties Gmbh Fundamentanordnung, Adapterelement, Spannvorrichtung und Turm einer Windenergieanlage sowie Verfahren zum Vorspannen eines Turms einer Windenergieanlage
CN110259246B (zh) * 2019-06-27 2024-03-19 柳州欧维姆机械股份有限公司 一种风塔用钢绞线体外拉索结构体系及其制作安装方法
BR112023027432A2 (pt) * 2021-07-22 2024-03-12 Windtechnic Eng S L Torre de concreto possuindo múltiplas seções
CN114319660A (zh) * 2022-01-21 2022-04-12 中建二局装饰工程有限公司 一种基于垃圾综合处理的烟囱幕墙系统及其施工工艺
EP4273326A1 (en) * 2022-05-06 2023-11-08 Optum Computational Engineering ApS Foundation for a superstructure, particularly for a wind turbine, wind turbine with the foundation, method of forming a wind turbine foundation

Family Cites Families (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US455888A (en) 1891-07-14 Combined flower-holder and fly-trap
US1553158A (en) * 1922-08-23 1925-09-08 Henderson Corp Concrete pole
US5038540A (en) * 1981-11-20 1991-08-13 Krautz Alfons O Sectional smokestack
US4818146A (en) * 1985-01-23 1989-04-04 Texhoma Contractors, Inc. Wellhead and conductor stabilized by a cable and anchor system
CN2272926Y (zh) * 1996-11-01 1998-01-21 同济大学科学技术开发公司 预应力管塔
CN2387201Y (zh) * 1999-01-26 2000-07-12 海城市光源集团有限公司水泥制品厂 一种侧壁带孔水泥预制电杆
DE10031683A1 (de) 2000-06-29 2002-01-24 Aloys Wobben Spannbetonturm für eine Windenergieanlage sowie Windenergieanlage
US6948290B2 (en) * 2000-12-13 2005-09-27 Ritz Telecommunications, Inc. System and method for increasing the load capacity and stability of guyed towers
DE10126912A1 (de) * 2001-06-01 2002-12-19 Oevermann Gmbh & Co Kg Hoch Un Turmbauwerk aus Spannbeton
NL1019953C2 (nl) * 2002-02-12 2002-12-19 Mecal Applied Mechanics B V Geprefabriceerde toren of mast, alsmede een methode voor het samenvoegen en/of naspannen van segmenten die één constructie moeten vormen, alsmede een werkwijze voor het opbouwen van een toren of mast bestaande uit segmenten.
JP2004011210A (ja) 2002-06-05 2004-01-15 Fuji Ps Corp 風力発電施設用主塔
DK1654460T3 (da) * 2003-08-09 2007-05-21 Gen Electric Tårnfundament, især til en vindmölle
JP4113110B2 (ja) * 2003-12-22 2008-07-09 三井住友建設株式会社 コンクリートタワー
ES1058539Y (es) * 2004-10-11 2005-04-01 Inneo21 S L Estructura perfeccionada de torre modular para turbinas eolicas y otras aplicaciones.
ES2246734B1 (es) * 2005-04-21 2007-04-16 STRUCTURAL CONCRETE & STEEL, S.L. Torre modular prefabricada.
EP1767729A1 (de) * 2005-09-23 2007-03-28 Sika Technology AG Turmkonstruktion
CN2851632Y (zh) * 2005-09-30 2006-12-27 珠海互翔软件技术有限公司 组合式风力发电塔筒
US8104242B1 (en) * 2006-06-21 2012-01-31 Valmont Industries Inc. Concrete-filled metal pole with shear transfer connectors
AP2620A (en) * 2007-05-07 2013-03-18 Ericsson Telefon Ab L M Antenna tower structure with installation shaft
US20090178352A1 (en) * 2008-01-15 2009-07-16 Innovate International, Limited Composite Structural Member
CA2730679A1 (en) * 2008-07-15 2010-01-21 Siemens Aktiengesellschaft Method for the assembly of a tower and tower
EP2483490A1 (en) * 2009-09-29 2012-08-08 Keystone Retaining Wall Systems, Inc. Wall blocks, veneer panels for wall blocks and method of constructing walls
EP2339094B1 (en) * 2009-12-23 2016-06-15 Soletanche Freyssinet Tower having a pre-stressed concrete column and construction method
US20110239564A1 (en) * 2011-04-15 2011-10-06 General Electric Company Apparatus, Composite Section, and Method for On-Site Tower Formation

Also Published As

Publication number Publication date
EP2531674A4 (en) 2015-09-16
US9021757B2 (en) 2015-05-05
US20150252580A1 (en) 2015-09-10
DK2531674T3 (en) 2017-02-27
CN102834572A (zh) 2012-12-19
CA2787932A1 (en) 2011-08-04
CN102834572B (zh) 2015-01-14
EP2531674B1 (en) 2016-12-14
CN104595126A (zh) 2015-05-06
CA2787932C (en) 2016-08-16
EP2531674A1 (en) 2012-12-12
US20120311948A1 (en) 2012-12-13
WO2011091799A1 (en) 2011-08-04

Similar Documents

Publication Publication Date Title
BR112012019203A2 (pt) construção de torre de concreto, método para erguer uma construção de torre, elemento de torre de concreto, e, elemento interligante.
TN2011000580A1 (en) Support structure for a wind turbine and procedure to erect the support structure
CL2020000259A1 (es) Cimentación para una estructura.
HRP20170111T1 (hr) Nosiva struktura za vjetroturbine i kalup za izradu takvih struktura
BR112018015971A2 (pt) ?alicerce para um moinho de vento e turbina eólica?
WO2013075023A3 (en) Non-bearing modular construction system
BR112012018901A2 (pt) segmentos de torre de instalações de energia eólica, torre de instalações de energia eólica, instalação de energia eólica, método para a produção de vários segmentos de torre, corpo de conexão, e, par de corpos de conexão
BR112019002137A2 (pt) estrutura de suporte para geradores de energia eólica
BR112012014852A2 (pt) "seção de edificação, painel estrutural e método de construção de uma edificação"
EP3827134A4 (en) TOWER FOUNDATION WITH CONCRETE BOX BEAMS
ES2636437T8 (es) Procedimiento para la erección de una torre
AR069632A1 (es) Metodo para construir una edificacion con cimentacion de pilares poco profundos aislados
BR112018017083A2 (pt) plataforma de piso para edifícios de múltiplos andares usando treliças de parede de aço estrutural empilhadas
BR112014001152A2 (pt) sistema de suporte em forma de torre e processo para a sua produção
NZ580011A (en) Light gauge sheet metal channel and concrete composite floor slab and support structures
WO2012044013A3 (ko) 개단면 상현재를 갖는 트러스구조물과 이의 제작방법 및 개단면 상현재를 갖는 트러스구조물을 이용한 트러스교와 이의 시공방법
CU20120105A7 (es) Instalación posicionadora de anclajes en la prefabricación de paneles de mortero de cemento armado
KR20110123883A (ko) 콘크리트 박스거더 및 이의 시공방법
WO2010102021A8 (en) Roof truss system for long span and method of assembly thereof
FR2934192B1 (fr) Presse vibrante pour la production d'elements de construction et procede de production d'elements de construction
BR112022010918A2 (pt) Estrutura de fundação de turbina eólica e método para fabricar uma estrutura de fundação de turbina eólica
PT1346111E (pt) Construção para um telhado e tecto de intradorso plano, com pré-esforço duplo destinado a edifícios industriais de grandes dimensões
RU2008126103A (ru) Плотина из укатанного бетона с противофильтрационной диафрагмой
AR112429A1 (es) Torre y procedimiento para su construcción
CN206438661U (zh) 一种新型楼层板

Legal Events

Date Code Title Description
B06F Objections, documents and/or translations needed after an examination request according [chapter 6.6 patent gazette]
B06T Formal requirements before examination [chapter 6.20 patent gazette]
B11E Dismissal acc. art. 34 of ipl - requirements for examination incomplete
B11T Dismissal: dismissal of application maintained