AU2019407321A1 - Method for producing a wall of a structure made of concrete, and a wall of a structure made of concrete - Google Patents

Method for producing a wall of a structure made of concrete, and a wall of a structure made of concrete Download PDF

Info

Publication number
AU2019407321A1
AU2019407321A1 AU2019407321A AU2019407321A AU2019407321A1 AU 2019407321 A1 AU2019407321 A1 AU 2019407321A1 AU 2019407321 A AU2019407321 A AU 2019407321A AU 2019407321 A AU2019407321 A AU 2019407321A AU 2019407321 A1 AU2019407321 A1 AU 2019407321A1
Authority
AU
Australia
Prior art keywords
wall
duct
layers
concrete
filling material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
AU2019407321A
Inventor
Alexander Kuhn
Peter Weber
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ed Zueblin AG
Original Assignee
Ed Zueblin AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ed Zueblin AG filed Critical Ed Zueblin AG
Publication of AU2019407321A1 publication Critical patent/AU2019407321A1/en
Abandoned legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B33ADDITIVE MANUFACTURING TECHNOLOGY
    • B33YADDITIVE MANUFACTURING, i.e. MANUFACTURING OF THREE-DIMENSIONAL [3-D] OBJECTS BY ADDITIVE DEPOSITION, ADDITIVE AGGLOMERATION OR ADDITIVE LAYERING, e.g. BY 3-D PRINTING, STEREOLITHOGRAPHY OR SELECTIVE LASER SINTERING
    • B33Y10/00Processes of additive manufacturing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/383Connection of concrete parts using adhesive materials, e.g. mortar or glue
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Panels For Use In Building Construction (AREA)

Abstract

A method for producing a wall (1) of a structure made of concrete provides that the wall (1) is produced by applying concrete in layers (4) lying above one another without lateral formwork, wherein the layers (4) extend over at least half the length (g) of the wall (1) from one longitudinal side (2) of the wall to the opposite longitudinal side (2) of the wall. At least one reinforcing bar (7, 8) which penetrates through at least some of the layers is introduced into the wall (1) after at least partial hardening of the layers (4). In a wall (1) of a structure made of concrete, with said wall being built up from layers (4) of concrete arranged above one another, there is provision that the wall (1) has extending therein at least one duct (5) which traverses a plurality of layers (4) and in which at least one reinforcing bar (7, 8) is arranged, wherein the duct (5) is filled with a casting compound (17) having a composition which differs from the composition of the concrete of the layers (4).

Description

METHOD FOR PRODUCING A WALL OF A STRUCTURE MADE OF CONCRETE, AND A WALL OF A STRUCTURE MADE OF CONCRETE
The invention relates to a method for producing a wall of a
structure made of concrete and a wall of a structure made of
concrete.
It is known to produce walls by applying concrete in layers
lying above one another. This production method is also known
LO as 3D printing. The concrete layers are successively produced
by pouring concrete onto the top layer of the section of the
wall that has already been produced using a print head moving
in the longitudinal direction over the wall. In this case, a
formwork is not first produced, as in conventional methods,
L5 into which the liquid concrete is poured for a certain wall
section, but the concrete is applied without lateral formwork
as a layer with a comparatively low height. Since the
individual layers of the concrete bulge outwards between
application and hardening due to the weight of the concrete, a
wavy structure is created on the outside of the wall.
In the case of conventionally produced walls, the
reinforcement is introduced, for example in the form of
reinforcing bars, reinforcement mats or the like, before the
concrete is introduced into the formwork. Then the formwork is
filled with concrete. In doing so, the reinforcements are
embedded in the concrete. In the case of a wall produced using
the 3D printing process, it must be possible for the print
head to move over the wall in order to apply the individual
layers. The vertical reinforcement must not hinder the
movement of the print head over the wall.
In order to be able to produce reinforcement in 3D-printed
walls, different methods are already known. From CN 106193368
A it is known to produce the outer wall sections in 3D
printing processes, then to introduce horizontal and vertical
reinforcements between the wall sections produced in 3D
printing and then to fill the space between the wall sections
with concrete. In order to be able to guide the print head
over the vertical reinforcement, it is also known to design
the print head with two feed openings which each apply
concrete to one side of the reinforcement. The design of the
print head is therefore comparatively complex, and the length
LO of the vertical reinforcement is limited by the construction
of the print head.
The invention is based on the object of specifying a method
for producing a wall of a structure made of concrete, with
L5 which the wall can be produced simply and economically.
Another object of the invention is to specify a wall that can
be produced simply and economically.
With regard to the method, this object is achieved by a method
having the features of claim 1. With regard to the wall, the
object is achieved by a wall having the features of claim 9.
There is provision that at least one reinforcement bar is
introduced into the wall, the reinforcement bar penetrating
through at least part of the layers. The part of the layers
into which the reinforcing bar is introduced is at least
partially hardened when the reinforcing bar is introduced. The
introduction of the reinforcing bar after the layers have at
least partially hardened simplifies the production of the wall
in the 3D printing process, since the print head can be moved
over the top layer of the wall unhindered by vertical
reinforcement. The layers can initially be applied at a height
corresponding to the length of the reinforcement bar. Because
the reinforcing bar is introduced when at least part of the layers has at least partially hardened, there is no rush to apply the layers, and a plurality of layers can be applied before the reinforcing bar is introduced. This allows a reinforcing bar of great length to be used. The at least one reinforcing bar can penetrate through a plurality of layers.
The layers extend over at least half the length of the wall
from one longitudinal side of the wall to the other. The
layers applied in the 3D printing process therefore do not
LO just form a formwork for conventionally poured concrete.
One or more reinforcing bars are preferably arranged in such a
way that at least one reinforcing bar penetrates through all
layers of the wall.
L5
The at least one reinforcing bar is advantageously introduced
at an angle of less than 30°, in particular less than 100,
relative to the vertical. Preferably, the at least one
reinforcing bar is introduced in the vertical direction within
the scope of the usual manufacturing tolerances. The
reinforcing bar is therefore a vertical reinforcement.
Provision can be made for the reinforcement bar to be provided
with pre-tensioning as pre-tensioned reinforcement.
Reinforcement is preferably provided without pre-tensioning.
The concrete is preferably applied in layers in a longitudinal
direction of the wall. The wall has at least one transverse
side extending transversely to the longitudinal direction. A
plurality of reinforcing bars are advantageously arranged at
different horizontal distances from one another in the wall.
The reinforcement bars are preferably arranged adjacent to the
transverse sides and adjacent to wall openings such as door
openings or window openings with a small distance from one
another. In areas that are at a large distance from the transverse sides or from wall openings, the vertical reinforcement can be omitted or the vertical reinforcing bars can be arranged at a large distance from one another. Accordingly, the reinforcement is arranged in the wall adapted to the loads that occur. The reinforcement is advantageously provided in the form of zone reinforcement. In this case, zone reinforcement is reinforcement that is only arranged locally or in areas in an otherwise unreinforced component.
LO The individual layers of the wall are comparatively thin. Preferably, each layer is produced with a thickness of 2 cm to 10 cm. The thickness of all layers of the wall is preferably the same within the scope of the manufacturing tolerances. The layers are in particular produced with a thickness of about 4 L5 cm to about 8 cm, preferably with a thickness of about 5 cm.
The at least one reinforcing bar is advantageously not introduced directly into the concrete, but rather subsequently into a duct penetrating through the layers of the wall. It is known to provide empty pipes in concrete walls, for example for the subsequent laying of cables or the like. However, such empty pipes are smooth on their inside and can therefore not absorb forces in their longitudinal direction. In order to enable a force transmission from the reinforcing bar into the layers of the wall, provision is made for areas lying above one another of layers of the wall lying above one another to be left blank when the concrete is applied in such a way that a duct penetrating through the layers is created. The duct is preferably closed on its circumference over at least part of its length. When a layer is applied, the concrete bulges outwards due to its weight on the outside of the wall. The outside of a wall that was produced by applying concrete in layers therefore has a wavy contour. The fact that the duct is also produced by leaving blank concrete within the layers means that the surface of the duct is also wavy. After at least one section of the wall has been produced, at least one reinforcing bar is introduced into the duct and the free cross section formed between the wall of the duct and the at least one reinforcing bar is filled with filling material. Due to the waviness of the surface of the duct, a good interlocking of the filling material with the layers of the wall is achieved. Even if the surface of the duct is slightly wavy, the direct contact of the filling material with the concrete
LO of the wall results in a good connection between the concrete
of the wall and the filling material. An area of the layers
can be left blank in an automated manner in a simple manner
when the layer is produced, so that the duct can be produced
in a simple manner and in an automated method when the wall is
L5 produced. The reinforcing bar advantageously has a surface
provided with elevations in the usual way, so that good
interlocking of the reinforcing bar with the filling material
is achieved. As a result, comparatively large forces can be
transmitted between the layers of the wall and the at least
one reinforcing bar.
A material different than the one used for the layers of the
wall is preferably used as the filling material.
If a plurality of reinforcing bars have to be arranged
distributed over the height of the wall, it is advantageously
provided to arrange the reinforcing bars with overlapping
joint. The length of the overlap depends on the strength of
the filling material. If a material with very high strength is
used for the filling material, the required overlapping length
and thus the required amount of reinforcing steel can be
reduced. Alternatively, the reinforcing bars can also be
connected to one another, in particular screwed to one
another.
To introduce the filling material, it is advantageously
provided that a connection is established from the duct to the
outside of the wall, and the filling material is pressed into
the duct via the connection. In order to avoid air inclusions
remaining in the duct, provision is preferably made for the
connection to be introduced comparatively far down in the wall
and for the filling material to be pressed into the duct from
below. The connection is preferably established in the area
below the tenth layer of the wall, in particular below the
LO fourth layer of the wall. A simple configuration is obtained
when a pipe leading from the duct to the outside of the wall
is inserted at least partially, in particular up to about
halfway into a layer to produce the connection in the
production of the wall, and then another layer is applied that
L5 covers the pipe at least partially. As a result, a connection
can be established into the duct in a simple manner, via which
the remaining free space in the duct can be filled with
filling material after the introduction of the at least one
reinforcing bar. Alternatively, the connection can also be
established in another way, for example by subsequently
introducing a connection, for example by drilling a duct, or
by leaving blank the connection when applying the concrete to
the corresponding layers. Advantageously, all of the
reinforcing bars to be arranged in the duct are arranged in
the duct before filling material is fed into the duct.
However, provision can also be made for the filling material
to be introduced into the duct in sections. For this purpose,
a plurality of connections are advantageously arranged
distributed over the length of the duct. Alternatively, it can
also be provided that the filling material is poured into the
duct from above.
In the case of a wall of a building made of concrete, which
wall is built up from layers arranged above one another, it is provided that the wall has extending therein at least one duct which traverses multiple layers and in which at least one reinforcing bar is arranged, wherein the duct is filled with filling material having a composition of which differs from that of the concrete of the layers. Such a wall can be produced in a simple manner in a 3D printing process, the duct being left blank in the production of the wall, then the reinforcement being introduced and only then the duct being filled with filling material. As a result, vertical LO reinforcement can easily be introduced even in a wall made of concrete using a 3D printing process.
The material of the filling material preferably has a higher strength than the concrete of the layers. This is particularly L5 advantageous when arranging a plurality of reinforcing bars one above the other, which overlap in an overlap area and thus form an overlapping joint. The required overlapping length depends, among other things, on the strength of the filling material. A high strength of the filling material reduces the required overlapping length. The filling material preferably has at least strength grade C60, in particular at least strength grade C75. The filling material is preferably a mortar. Due to the smaller maximum grain diameter of the mortar compared to concrete, the diameter of the duct can be made comparatively small. This reduces the amount of filling material needed to make the wall. At least two reinforcing bars are preferably arranged in the duct. The reinforcing bars preferably overlap in the height direction of the wall on a section of their length. However, a connection of the reinforcement bars, for example a screw connection, can also be advantageous.
The duct is preferably formed with a comparatively small diameter. The extension of the duct in the longitudinal direction of the wall is preferably less than twice the extension of the duct in the transverse direction of the wall.
The extension of the duct in the transverse direction is
limited by the smallest wall thickness to be produced. The
duct preferably has a distance of at least 5 cm from the long
sides of the wall.
An exemplary embodiment of the invention is explained below
with reference to the drawing.
L0
Fig. 1 shows a schematic illustration of a wall of a
structure,
Fig. 2 shows a schematic illustration of the wall from Fig. 1
L5 in longitudinal section, the layers being shown without
hatching and the position of a further reinforcing bar being
shown schematically,
Fig. 3 shows the detail III from Fig. 2 in an enlarged
illustration,
Fig. 4 shows the detail IV from Fig. 2 in an enlarged
illustration,
Fig. 5 shows in parts a schematic sectional illustration
through the duct.
Fig. 1 shows schematically a wall 1 of a structure. The wall 1
is produced from a plurality of layers 4 of concrete lying
above one another. To produce the wall 1, a schematically
illustrated concrete application device 12 is used, which is
connected to a concrete outlet opening 13 via a movement and
feed device 14. The concrete application device 12 is a so
called 3D printing device for concrete. The concrete outlet opening 13 is also referred to as a print head. The structural design can be any suitable design. In the prior art, for example, concrete application devices 12 in the form of portal arrangements or with a robot arm are known.
The wall 1 has two opposite longitudinal sides 2 which extend
in parallel to a longitudinal direction 9 of the wall 1. In
the exemplary embodiment, the wall 1 is flat. The wall 1 can,
however, also have a curved, angled shape or a shape deviating
LO in some other way from the straight shape. The longitudinal
direction 9 is the direction in which the concrete outlet
opening 13 is to be moved over the wall 1 in order to produce
a layer 4. The wall 1 has two transverse sides 3 which each
extend transversely, in particular perpendicular to the
L5 longitudinal direction 9 in a transverse direction 21.
The concrete outlet opening 13 can be moved by means of the
movement and feed device 14 in an application direction 10
and/or an oppositely directed application direction 11 for
applying a layer 4 over the top of the previously produced
wall section of the wall 1. The application directions 10 and
11 run in the longitudinal direction 9 of the wall 1.
Application of concrete in the transverse direction 21 can
also be provided.
The wall 1 has a height a, which is usually several meters.
The height a can, for example, be the room height of a
structure of which the wall 1 forms a part. The wall 1 has a
width b which is significantly less than the height a. The
width b can, for example, be in the range from 20 cm to 50 cm.
The wall 1 has a length g, which is measured in the
longitudinal direction 9. The wall 1 consists of a plurality
of layers 4 lying above one another. Each of the layers has a
thickness r which is, for example, 2 cm to 10 cm, in particular 4 cm to 8 cm. A thickness r of about 5 cm is particularly preferred. The wall 1 is produced without the use of a formwork on the long sides 2. The layers 4 extend over at least half, advantageously over at least 75% of the length g of the wall 1 over the entire width b of the wall 1 from one longitudinal side 2 to the opposite longitudinal side 2. The thickness r of all layers 4 is dimensioned in such a way that the concrete of the respective uppermost layer 4 does not run down the side of the layer 4 below. The individual layers,
LO however, bulge outwards due to the weight of the concrete, so
that the outside of the wall 1 is not a smooth surface, as
shown schematically in Fig. 1, but a wavy surface.
In the case of conventionally manufactured walls, formwork is
L5 produced first, and horizontal and vertical reinforcements,
for example, reinforcement mats or the like are arranged in
the formwork. Then, concrete is poured into the formwork. As
Fig. 1 shows, the concrete outlet opening 13 extends on the
upper side of the wall 1. A concrete outlet opening 13
designed in this way cannot easily move over a reinforcing bar
7 projecting from the top layer 4. In the case of the wall 1
shown in Fig. 1, provision is therefore made for a duct 5 to
be produced in the production of the layers 4. The duct 5 is
advantageously produced in that no concrete is applied in the
area in which the duct 5 is to be produced, so that a hole is
created in the respective layer 4. The areas left blank are
produced lying above one another, so that a continuous duct 5
is created inside the wall 1. In the exemplary embodiment, the
duct 5 is completely closed on its circumference. However, it
can also be advantageous for the duct 5 to be partially open
on its circumference.
It can be provided that the wall 1 is produced with a
plurality of ducts 5. At least one duct 5 is preferably arranged in the area of a transverse side 3. The duct 5 is at a distance k from the transverse side 3. Tensile loads are to be expected in particular on the transverse sides 3 of the wall 1. Reinforcing bars 7 are preferably only arranged in the areas in which tensile loads are to be expected. Otherwise, the wall 1 is preferably unreinforced. The wall 1 accordingly has zone reinforcement. As Fig. 1 shows, the reinforcing bars
7, 8 have ribs 19.
LO The duct 5 has a free internal diameter d which is
significantly larger than the diameter c of the reinforcing
bar 7. After the production of at least a section of the wall
4, the reinforcing bar 7 is introduced into the duct 5. The
concrete of the wall 1 is already at least partially hardened.
L5 In particular, the lower layers of the section of the wall 4
are already partially hardened. Accordingly, it is provided to
introduce the reinforcement after at least partial hardening
of the concrete and not, as in the production of a wall with
conventional methods, by means of formwork, to arrange the
reinforcement in the formwork before the concrete is fed.
In the exemplary embodiment, the diameter d of the duct 5 is
significantly smaller than the width b. The diameter d is
advantageously at most 80% of the width b, preferably less
than 70% of the width b. The duct 5 has a distance e to a
longitudinal side 2 and a distance f to the other longitudinal
side 2. The distances e and f can be the same. However,
distances e and f of different sizes can also be advantageous.
The distances e and f are advantageously at least 5 cm.
In the exemplary embodiment, the duct 5 is formed with a
circular diameter d within the scope of the manufacturing
tolerances. However, a different cross section of the duct 5
can also be advantageous. The extension of the duct 5 in the longitudinal direction 9 of the wall 1 is advantageously less than twice the extension of the duct 5 in the transverse direction 21 of the wall 1.
In the exemplary embodiment, the duct 5 runs vertically. A
slightly inclined arrangement of the duct 5 and thus also of
the reinforcement bar 7 can, however, be advantageous. The
reinforcing bar 7 is advantageously arranged at an angle of
less than 30%, in particular at an angle of less than 10%
LO relative to the vertical. The reinforcing bar 7 is preferably
arranged vertically within the scope of the manufacturing
tolerances.
Fig. 2 shows the wall 1 after a first reinforcing bar 7 has
L5 been installed in the duct 5. In the exemplary embodiment, the
reinforcement bar 7 has a length p which corresponds
approximately to the height a (Fig. 1) of the wall 1. As a
result, the reinforcing bar 7 does not project beyond the wall
1 on the upper side of the wall 1. On the upper side of the
wall 1, a ceiling plate 20 arranged on the upper side of the
wall 1 and, above it, a further wall 1 are illustrated
schematically in Fig. 2 with a dashed line. For the wall 1
arranged above the ceiling plate 20 is provided to arrange a
second reinforcement bar 8 in the duct 5. The two
reinforcement bars 7 and 8 form an overlapping joint. The
reinforcing bar 8 has a length q. The length q can be exactly
as large as the length p or larger or smaller. The reinforcing
bars 7 and 8 overlap with their ends over an overlapping
length m. The upper end of the reinforcing bar 7 and the lower
end of the reinforcing bar 8 overlap.
As Fig. 2 shows, the wall 1 has a connection 15 in the lower
area, which connection 15 connects the interior of the duct 5
to the outside of the wall 1. In the exemplary embodiment, the connection 15 joins a transverse side 3 of the wall 1. In the exemplary embodiment the connection 15 is formed in a pipe 16 which is embedded between a layer 4 and a layer 4' of the wall
1 immediately above it. Filling material 17 can be pressed
into the duct 5 via the connection 15, as Fig. 4 shows. As
Fig. 4 shows, the filling material 17 is fed through the pipe
16 and into the duct 5 via a feed nozzle 18 illustrated
schematically. The connection 15 can also be formed by a duct
drilled into the wall 1 or be formed by an area to which no
LO concrete is fed to at least one layer 4 when the layers 4 are
applied. Other possibilities for producing the duct 4 can also
be advantageous.
Fig. 3 shows the arrangement of the reinforcement bar 7 in the
L5 duct 5. As Fig. 3 shows, an intermediate space is formed
between the reinforcing bar 7 and the wall 6 of the duct 5,
which intermediate space is filled with the filling material
17. In the exemplary embodiment, the connection 16 is arranged
between the third layer 4 and the fourth layer 4'. The
connection 15 is preferably arranged below the tenth layer 4
of the wall 1, preferably below the fourth layer 4 of the wall
1. It can thereby be ensured that the section of the duct 5
projecting downward from the mouth opening of the connection
15 can also be completely filled by the filling material 17.
Because the filling material 17 is mainly filled into the duct
5 from below, it can be ensured in a simple manner that no air
bubbles are trapped in the duct 5.
As Fig. 5 shows, the layers 4 form a wavy course of the wall 6
of the duct 5. Each layer 4 bulges outward in the central
area. The smallest diameter d of the duct 5 is measured in the
middle area of a layer 4. A largest diameter i is measured in
the area in which two successive layers 4 lie next to one
another. The difference between the diameters i and d is advantageously at least 1 mm, preferably at least 2 mm.
Accordingly, the waviness of each wall is advantageously at
least 0.5 mm, in particular at least 1 mm. Due to the waviness
of the wall 6, a good interlocking of the filling material 17
with the wall 6 and thus a good transmission of the tensile
forces absorbed by the reinforcement bars 7 and 8 into the
layers 4 is made possible.
When producing the wall 1, a plurality of layers 4 are first
LO produced one lying above another. For this purpose, the
concrete outlet opening 13 (Fig. 1) moves in the application
direction 10 and/or application direction 11 over the floor or
an already produced layer 4 and thereby applies concrete. In
the area of the duct 5 no concrete is applied. In the same
L5 way, further layers 4 are applied over the first layer 4, the
concrete being left blank in the area of the duct 5 in such a
way that a continuous, preferably vertical duct is created. In
the exemplary embodiment, after the third layer 4 has been
applied, the pipe 16 is placed on the third layer 4 and
partially, in particular up to halfway, pressed into the third
layer 4. It can also be provided that less concrete is fed to
the layer 4 in the area in which the pipe 16 is to be
arranged. After the pipe 16 has been inserted, the layer 4' is
applied. As a result, the pipe 16 is surrounded by concrete
over its entire circumference. The pipe 16 is advantageously
inserted below the tenth layer 4, in particular below the
fourth layer 4. After creating at least a section of the wall
1, a reinforcement bar 7 is arranged in the duct 5. The height
of the section of the wall 1 preferably corresponds to at
least the length p of the reinforcing bar 7, so that the
reinforcing bar 7 does not project from the top layer 4 at the
top of the wall 1.
If the total height of the wall 1 has not yet been reached
after the reinforcement bar 7 has been installed, further
layers 4 are applied. After a further section of the wall 1
has been produced or after the wall 1 has been completed, one
or more further reinforcing bars 8 can be arranged in the duct
5. Due to the dimensions of the duct 5, the reinforcing bars
7, 8 tilt in the duct 5, so that the reinforcing bars 7, 8
cannot slip unintentionally in the duct 5. If all the
reinforcing bars 7, 8 are arranged with the desired overlap in
LO the duct 5, then filling material 17 is pressed via the pipe
16 into the duct 5 until the duct 15 is completely filled with
filling material 17. Alternatively, the lower reinforcing bar
7 is arranged in the duct and the duct 5 is filled with
filling material 17 up to a height which is less than the
L5 length p of the reinforcing bar 7 by the overlapping length m.
The ceiling plate 20 is then arranged and further layers 4 are
applied to create the wall 1 extending above the ceiling plate
20. If the height of the wall 1 corresponds to the length q of
the reinforcing bar 8 minus the overlapping length m minus the
thickness of the ceiling plate 20, the reinforcing bar 8 is
arranged in the duct 5 and the duct 5 is further filled with
filling material 17, in particular via a further connection
13. The further connection 13 is advantageously at most less
than ten layers 4, preferably less than four layers 4, above
the lower end of the reinforcing bar 8.
In the exemplary embodiment, the filling material 17 is
mortar. The filling material 17 advantageously has a higher
strength than the concrete 4. Particularly preferably the
filling material 17 is mortar with a strength grade of at
least C60, in particular at least C75. The smallest diameter d
of the duct 5 is preferably at least 50 mm. Advantageously,
the diameter d is aligned with the diameter c of the reinforcing bars 7, 8 (Fig. 1) and the maximum grain diameter of the filling material 17.
The smallest diameter d of the duct 5 is preferably at least
the sum of ten times the largest grain diameter of the filling
material 17 and twice the diameter of a reinforcing bar 7, 8.
This ensures that even in the overlapping area there is
sufficient installation space for the largest grain of the
filling material 17 to pass through.
LO Instead of being placed in a duct 5, the reinforcements 7, 8
can also be introduced into the wall 1 subsequently in other
ways. For example, the reinforcement bars can be pressed or
screwed into the only partially hardened concrete of the
layers 4.
L5
It can also be provided that the reinforcing bars 7, 8 are
formed as pre-tensioned reinforcements.
Advantageously, the reinforcing bars 7 and 8 are only
connected to the concrete of the wall 1 via the filling
material 17. Preferably, no stirrups for anchoring the
reinforcement bar 7, 8 and no reinforcement mats are provided,
since these elements would hinder the application of the
layers 4 by means of 3D printing processes or require a
complex, fork-shaped print head that can feed the concrete on
both sides of a reinforcement mat.

Claims (14)

Claims
1. A method for producing a wall of a structure made of
concrete, the wall (1) being produced by applying concrete in
layers (4) lying above one another without lateral formwork,
wherein the layers (4) extend over at least half the length
(g) of the Wall (1) from one longitudinal side (2) of the wall
(1) to the opposite longitudinal side (2) of the wall (1),
characterized in that at least one reinforcing bar (7, 8)
which penetrates through at least part of the layers (4) is
introduced into the wall (1), wherein this part of the layers
(4) is at least partially hardened when the reinforcing bar
(7, 8) is introduced.
2. The method according to claim 1,
characterized in that the reinforcing bar (7, 8) is introduced
at an angle of less than 30°, in particular less than 100
relative to the vertical, preferably vertically.
3. The method according to claim 1 or 2,
characterized in that each layer (4) is produced with a
thickness (r) of 2 cm to 10 cm.
4. The method according to any one of claims 1 to 3,
characterized in that areas lying above one another of layers
(4) of the wall (1) lying above one another are left blank
when the concrete is applied in such a way that a duct (5)
penetrating through the layers (5) is created, and in that
after the production of at least a section of the wall (1) at
least one reinforcing bar (7, 8) is introduced into the duct
(5) and the free cross section formed between the wall (6) of
the duct (5) and the at least one reinforcing bar (7, 8) is
filled with filling material (17).
5. The method according to any one of claims 1 to 4,
characterized in that a different material is used as the
filling material (17) than for the production of the layers
(4) of the wall (1).
6. The method according to any one of claims 1 to 5,
characterized in that a connection (15) is established from
the duct (5) to the outside of the wall (1) and the filling
material (17) is pressed into the duct (5) via the connection
(15).
7. The method according to claim 6,
characterized in that the connection (15) is established in
the area below the tenth layer (4) of the wall (1).
8. The method according to claim 6 or 7,
characterized in that in order to establish the connection
(15) in the production of the wall (1), a pipe (16) leading
from the duct (5) to the outside of the wall (1) is partially
pressed into a layer (4) and then a another layer (4') is
applied which at least partially covers the pipe (16).
9. A wall of a structure made of concrete, the wall (1)
being constructed from layers (4) of concrete arranged above
one another,
characterized in that the wall (1) has extending therein at
least one duct (5) which traverses multiple layers (4) and in
which at least one reinforcing bar (7, 8) is arranged, the
duct (5) being filled with filling material (17), the
composition of which differs from the composition of the
concrete of the layers (4).
10. The wall according to claim 9,
characterized in that the material of the filling material
(17) has a higher strength than the concrete of the layers
(4).
11. The wall according to claim 10,
characterized in that the filling material (17) has at least
strength grade C60.
12. The wall according to any one of claims 9 to 11,
characterized in that the filling material (17) is mortar.
13. The wall according to any one of claims 9 to 12,
characterized in that at least two reinforcing bars (7, 8) are
arranged in the duct (5) which overlap in the height direction
of the wall (1) on a section (19) of their length (p, q).
14. The wall according to any one of claims 10 to 13,
characterized in that the extension of the duct (5) in the
longitudinal direction (9) of the wall (1) is less than twice
the extension of the duct (5) in the transverse direction (21)
of the wall (1).
AU2019407321A 2018-12-17 2019-12-10 Method for producing a wall of a structure made of concrete, and a wall of a structure made of concrete Abandoned AU2019407321A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP18212899.1A EP3670775B1 (en) 2018-12-17 2018-12-17 Method for producing a wall of a structure made of concrete and a wall of a concrete structure
EP18212899.1 2018-12-17
PCT/EP2019/084505 WO2020126701A1 (en) 2018-12-17 2019-12-10 Method for producing a wall of a structure made of concrete, and a wall of a structure made of concrete

Publications (1)

Publication Number Publication Date
AU2019407321A1 true AU2019407321A1 (en) 2021-06-24

Family

ID=64900755

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2019407321A Abandoned AU2019407321A1 (en) 2018-12-17 2019-12-10 Method for producing a wall of a structure made of concrete, and a wall of a structure made of concrete

Country Status (4)

Country Link
EP (1) EP3670775B1 (en)
CN (1) CN113348287A (en)
AU (1) AU2019407321A1 (en)
WO (1) WO2020126701A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP4321315A1 (en) * 2022-08-09 2024-02-14 Sika Technology AG Reinforced three-dimensional objects produced by additive manufacturing and relevant method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102021101138A1 (en) 2021-01-20 2022-07-21 Technische Universität Dresden, Körperschaft des öffentlichen Rechts Process for the extrusion-based production of a reinforced concrete component

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002046545A1 (en) * 2000-12-08 2002-06-13 Hajime Yauchi Concrete building construction form unit and manufacturing devicetherefor, and concrete building constructed by using concrete building construction form
US7832459B2 (en) * 2007-08-30 2010-11-16 Phillips Plastics Corporation Methods, tools, and products for molded ordered porous structures
KR101400801B1 (en) * 2013-04-18 2014-05-29 평 임 Multifunctional tool for measuring
KR101616308B1 (en) * 2014-06-17 2016-04-28 조선대학교 산학협력단 Concrete structure and method for manufacturing the same using 3d printing
CA2867964C (en) * 2014-10-16 2016-04-12 Emin Buzimkic Prefabricated modular rebar modules and methods of using the same
CN106003365B (en) 2014-11-14 2018-05-08 中国建筑第八工程局有限公司 Insulation construction based on 3D printing reinforced masonry
EP3067484B1 (en) * 2015-03-12 2017-05-10 MERK Timber GmbH Wooden panel for a wood-cement composite structure, wood-cement composite structure and method for its preparation
SG11201901805TA (en) * 2016-09-14 2019-04-29 Armatron Systems Llc Method of reinforced cementitious construction by high speed extrusion printing and apparatus for using same
KR101914524B1 (en) * 2017-01-19 2018-11-02 연세대학교 산학협력단 Mobile Concrete Building 3D Printing System
CN108412204A (en) * 2017-02-10 2018-08-17 盈创建筑科技(上海)有限公司 The rack construction of live building 3D printer
CN107901185B (en) * 2017-11-02 2019-10-22 中国建筑股份有限公司 The method and its application on 3D printing concrete wall surface

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP4321315A1 (en) * 2022-08-09 2024-02-14 Sika Technology AG Reinforced three-dimensional objects produced by additive manufacturing and relevant method
WO2024033086A1 (en) * 2022-08-09 2024-02-15 Sika Technology Ag Reinforced three-dimensional objects produced by additive manufacturing and relevant method

Also Published As

Publication number Publication date
WO2020126701A1 (en) 2020-06-25
CN113348287A (en) 2021-09-03
EP3670775B1 (en) 2022-01-26
EP3670775A1 (en) 2020-06-24

Similar Documents

Publication Publication Date Title
CN111622374B (en) Composite structural wall and method of construction thereof
CN104847014A (en) Vertical connection structure for precast concrete shear walls and construction method
AU2019407321A1 (en) Method for producing a wall of a structure made of concrete, and a wall of a structure made of concrete
KR102010144B1 (en) A PC slab structure having a hollow portion
US11002004B2 (en) Method for erecting framework of structures
CN106948514B (en) Construction method of ultrahigh masonry wall anti-seismic structure
CN110552461A (en) Prefabricated constructional column of masonry infilled wall and construction method thereof
CN103103977A (en) Partially-prestressed reinforced concrete solid square pile lower segment and manufacturing method thereof
CN216690087U (en) Core column is irritated to bellows through-hole
CN102619330A (en) Method for floating-resistant positioning construction on high-strength hollow inner bead core mold pipe (GBF) of hollow floor
AT523599B1 (en) Process for producing a composite element and composite element
CN109881776A (en) A kind of assembling prefabricated reinforced concrete tubular column structure and construction method
CN207260378U (en) A kind of assembled frame-shear structure curved scissors type combines keyway connection structure
EP2707550B1 (en) Method for constructing a building
CN208037775U (en) A kind of positioning member for the positioning of elevator rail holder
CN111255163A (en) A restraint steel pipe overlap joint structure for prefabricating vertical member
CN108018877B (en) Prefabricated assembly type pipe gallery assembling device and assembling method
JP4355694B2 (en) Precast material
CN113863679A (en) Construction method of prefabricated house structure
EP1558822A1 (en) A building element arrangement
CN106320530A (en) Interlayer connection node
JP5661292B2 (en) Precast concrete block for earthquake-resistant wall, earthquake-resistant wall and earthquake-resistant wall construction method
CN220580619U (en) Multi-ribbed floor slab composite reinforcing structure based on precast slab and steel strand wires
US8333045B2 (en) Architectural structure
CN106121051A (en) A kind of interlayer connection node

Legal Events

Date Code Title Description
DA3 Amendments made section 104

Free format text: THE NATURE OF THE AMENDMENT IS: TO ADD THE NAME OF CO-INVENTOR WEBER, PETER

MK1 Application lapsed section 142(2)(a) - no request for examination in relevant period