AU2004303436B2 - Cavity former - Google Patents

Cavity former Download PDF

Info

Publication number
AU2004303436B2
AU2004303436B2 AU2004303436A AU2004303436A AU2004303436B2 AU 2004303436 B2 AU2004303436 B2 AU 2004303436B2 AU 2004303436 A AU2004303436 A AU 2004303436A AU 2004303436 A AU2004303436 A AU 2004303436A AU 2004303436 B2 AU2004303436 B2 AU 2004303436B2
Authority
AU
Australia
Prior art keywords
cavity former
cavity
wall
hollow
hollow body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
AU2004303436A
Other versions
AU2004303436A1 (en
Inventor
James Francis O'grady
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Australian Steel Company Operations Pty Ltd
Original Assignee
Australian Steel Company Operations Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2003907151A external-priority patent/AU2003907151A0/en
Application filed by Australian Steel Company Operations Pty Ltd filed Critical Australian Steel Company Operations Pty Ltd
Priority to AU2004303436A priority Critical patent/AU2004303436B2/en
Priority claimed from PCT/AU2004/001806 external-priority patent/WO2005061804A1/en
Publication of AU2004303436A1 publication Critical patent/AU2004303436A1/en
Application granted granted Critical
Publication of AU2004303436B2 publication Critical patent/AU2004303436B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

WO 2005/061804 PCT/AU2004/001806 1 CAVITY FORMER Field of the Invention This invention relates generally to the formation of concrete slabs and foundations, and more particularly to structures for forming cavities or voids in a slab or 5 foundation. Background of the Invention It is known to use cavity or void formers as space filling elements in the preparation of a concrete slab or foundation, for reducing the volume of concrete required to form the slab or foundation. Such foundations are commonly known as 10 waffle slab foundations. While the reduction of concrete content in a slab as a result of having multiple cavities on its underside serves in turn to reduce the cost of the slab, it also advantageously allows the slab to be built on unstable soil as expanding soils will flow into the formed cavities. Such cavities also facilitate the placement of electrical and plumbing conduits through the slab. 15 As the cavity formers must be sufficiently strong to support, firstly, the weight of workers when the formers are in place prior to a pour and, secondly, the load of wet concrete when it is poured, the cavity formers are traditionally prefabricated remote from the building site in standard sizes and then delivered to the building site ready to be set in place prior to pouring of the concrete. Known cavity formers 20 include reinforced multiple web-cardboard or fibreboard boxes and so called pods of foamed polymeric material, such as polystyrene. Cardboard or fibreboard formers must have sufficient structural integrity to support a wet slab for a prescribed period, eg 3 hours, after a concrete pour, before they weaken through moisture absorption. Polystyrene pods overcome this limitation, 25 but have the disadvantage that, when larger pods are cut into smaller shapes for filling cavities of irregular or smaller shape, large quantities of fine polystyrene particles are often generated. Such polystyrene particles present an environmental problem because they are easily scattered by a breeze. Furthermore, polystyrene pods do not disintegrate to more completely form the cavity or void and this 30 presents a disposal and environmental problem when the slab is partially or wholly WO 2005/061804 PCT/AU2004/001806 2 demolished or reshaped. For these reasons, the use of polystyrene as a cavity former is being restricted in some locations. Typically, slab formation preparations involve levelling the ground on which the slab is to be formed, erecting shutters to define the perimeter of the slab, locating 5 reinforcement for edge beams of the building to be constructed, laying down building film, i.e. plastics sheets, onto the levelled ground, and then arranging multiple cavity formers in a spaced array on the building film. Bar chairs are then located at spaced intervals in the spaces between the cavity formers, and then reinforcement bars are placed on the bar chairs to form a lattice of reinforcement 10 bar surrounding the cavity formers. Bar chairs are also located on the tops of the cavity formers to support reinforcement mesh that is laid in a blanket covering. After these preparations, the wet concrete is poured about the cavity formers, and cures to form the concrete slab or foundation. A process along these lines is described, for example, in Australian patent 584769 to Koukourou & Partners Pty 15 Ltd. The process of laying plastic sheets, arranging the cavity formers and bar chairs, and then accurately locating the bar and mesh reinforcement on the bar chairs is time consuming and inconvenient. Australian petty patents 727681 and 727665 disclose cavity former modules 20 fabricated in recycled plastic. The modules have multiple box elements joined in an integral structure that also defines channels between the box elements. Reinforcing bars are supported in the channels on spaced integral bracket elements that each have an upper edge shaped to center the bar, while reinforcing mesh rests on upstanding ribs formed integrally on the top surfaces of the box 25 elements. Applicant has found that, while cavity former modules of this kind alleviate the environmental concerns of polystyrene pods and address the labour costs of foundation preparation, the modules require a volume of plastic that adversely affects their economics relative to cardboard and polystyrene. They are also bulky to transport.
3 Reference herein to any specific prior document is not to be taken as an admission or suggestion that the contents of the document constitute common general knowledge. Object of the Invention s It is the object of the present invention to substantially overcome or at least ameliorate one or more of the above disadvantages. Summary of the Invention There is disclosed herein a cavity former for forming one or more cavities in a concrete slab, including: 10 a hollow body about which, during use of the former, poured concrete flows and subsequently cures to form a concrete slab in which the hollow body defines a cavity; wherein said hollow body has a first wall having a periphery and an upper surface, a skirt wall depending from the periphery, and a pair of intersecting upstanding ribs formed integrally on the outer surface of said first wall for supporting reinforcing is mesh above said hollow body. The ribs are preferably a pair of crossed ribs. Preferably said hollow body includes a structure defining, within said periphery, at least one depending hollow pillar formation for in situ bracing said first wall to an underlying surface on which said skirt wall also rests. 20 In one embodiment, said structure comprises a plurality of valleys in said first wall that define said at least one hollow pillar formation at their intersection. In another embodiment, said structure comprises a hollow tubular structure which constitutes said pillar formation and preferably has its interior open at said first wall. Preferably, said hollow body is configured to allow nesting of said 25 cavity former with a second similar cavity former, and thereby to allow stacking of a multiplicity of said cavity formers. Preferably said skirt wall and said structure defining the hollow pillar formation are tapered to nest with the like features of a similar cavity former.
4 Preferably said skirt wall includes at least one outstanding, preferably upstanding, tab for interlocking with a skirt wall of a similar cavity former and thereby to inhibit relative movement of individual cavity formers during pouring of the wet concrete. Preferably such interlocking is such that the plural interlocked cavity formers s provide a moisture barrier between the concrete and an underlying ground surface.
WO 2005/061804 PCT/AU2004/001806 5 The hollow body may be a rectangular pod open on a lowermost side. In an embodiment, the cavity former has a plurality of hollow bodies or pods spaced apart by integrally formed channels that receive elongated slab-reinforcement. The supports are preferably arranged and spaced so that if the mesh reinforcement is 5 randomly dropped onto an array of cavity formers, the mesh reinforcement will rest on the supports above the bodies. Seats may be integrally formed in the channels to link adjacent pods and to support the elongated slab reinforcement located in the channel. Preferably, the seats automatically center the elongated slab reinforcement longitudinally within the respective channel. 10 The support for the slab reinforcement is preferably shaped (eg. parabolic) to enable automatic centering of the slab-reinforcement within the channels. Preferably, the supports for the mesh, in a cavity former including a plurality of bodies, are arranged and spaced to cover a corresponding location on each body. The supports may be located on the corresponding separable compartment of 15 each body. Brief Description of the drawings The invention will now be further described, by way of example only, with reference to the accompanying drawings, in which: Figure 1 is a perspective view of a pair of coupled four-pod cavity formers, 20 embodying several aspects of the invention and partially laid out with reinforcement bar and mesh in preparation for wet concrete to be poured to form a concrete waffle slab foundation with cavities defined by the pods of the cavity formers; Figure 2 is a cross-section of one of the cavity formers shown in Figure 1 along 25 the line 2-2, shown in a nesting configuration with a similar cavity former shown in dashed lines; Figure 3 is a view similar to Figure 2 but showing one of the cavity formers in full lines, and the other in dashed lines; WO 2005/061804 PCT/AU2004/001806 6 Figure 4 is a plan view of one of the cavity formers; and Figures 5 and 6 illustrate (with only two pods shown) an alternative structure for providing a pod with a central hollow pillar, Figure 6 being a cross-section on the line 6-6 in Figure 5. 5 Detailed description of embodiments of the Invention Figure 1 shows a pair of four-pod cavity formers 10 arranged with reinforcing products, such as reinforcement mesh 12 and reinforcement bar 14, supported by the cavity formers 10, in preparation for pouring of wet concrete to form a slab foundation. Each cavity former 10 includes four hollow bodies, ie. pods, 20, 10 arranged in a rectangular configuration and separated by channels in the form of orthogonal intersecting trenches 40. It will be appreciated that the wet concrete is poured about the cavity formers such that the cured concrete slab has cavities or voids defined by the respective pods 20. The pods 20 and trenches 40 are integrally formed to space the pods 20 apart 15 such that reinforcement bar 14 is receivable within the trenches 40 to reinforce the formed concrete slab. The integrally formed cavity formers 10 comprising pods 20 and trenches 40 are moulded in any appropriate plastics or other suitable material. A suitable material is a recycled polypropylene, virgin or recycled. Other possible alternates include polyethylene, cross-linked polyethylene and PET. The material 20 is preferably selected to provide an effective moisture barrier, as well as the necessary structural properties. Each pod 20 includes a first, planar top wall 27 and a depending skirt wall 22 about the periphery of wall 27. Wall 27 is normally horizontal in situ and has a top surface 28 on which is provided an integrally formed support, in the form of a pair 25 of hollow outstanding ribs 30, for supporting reinforcement mesh 12 placed on the cavity former 10. Reinforcement mesh 12 supported on the ribs 30 is held in a spaced relationship above the pod 20. The ribs 30 intersect to define a cruciform shape such that the reinforcement mesh 12 is supported above the pod 20 for any given orientation of the mesh 12 relative to the pod 20, whereby reinforcement 30 mesh randomly dropped onto an array of the cavity formers will rest on the WO 2005/061804 PCT/AU2004/001806 7 supports above the bodies of the cavity formers, without any need for separate bar chairs on the pods. Peripheral skirt walls 22 taper downwardly and outwardly relative to top surface 28 such that multiple cavity formers 10 may nest, when stacked, to provide a reduced 5 volume to facilitate transport to a construction site. Nesting is further aided by the ridges 30 being hollow in order to receive the ridges 30' of an underlying nesting cavity former 10' (Figure 2). Intersecting minor channels, in the form of valleys 24, are formed in each pod to provide separate hollow compartments 26 and to define, within peripheral skirt 10 wall 22 and at the centre of the pod, a tapered hollow depending pillar formation 25 for in situ bracing wall 27 to an underlying surface on which the skirt wall 22 also rests. Pillar formation 25 comprises the four intersecting corners of the side walls of valleys 24, bounding a cavity 31 open at 33 in top wall 27. This structure provides the pods with greater strength for supporting the weight of workers prior 15 to the wet concrete being poured, the mesh when laid and the weight of wet concrete once poured. The compartments 26 are selectively separable from pods 20 at valleys 24 to customise the shape of the cavity former 10 as required. The valleys 24 extend the height of the walls 22 to ensure that the ability of the compartments 26, 20 remaining after one or more compartments 26 have been removed, to form cavities in the poured concrete is not compromised. While the valleys 24 are arranged in a cruciform shape, it will be appreciated that the valleys 24 may be arranged in other configurations to provide differently shaped separable compartments 26. 25 Figures 5 and 6, in which like features are indicated by like primed reference numerals, illustrate an alternative structure for defining hollow pillar formation 25' in each pod 20', ie. a hollow tapered tubular structure with its interior cavity 31' open at 33' in wall 27'.
WO 2005/061804 PCT/AU2004/001806 8 The underside or interior of each pod 20 may typically include integral fins 39 (Figures 2 and 3), corrugations or other formations for increasing the strength and rigidity of the pod. It will be appreciated that the presence of pillar formation 25, 25', and the provision 5 of strengthening fins 39 and the like, allows wall thickness, and thereby material usage per pod, to be kept as small as possible. The support ribs 30 are arranged and spaced to be located at a corresponding compartment 26 on each pod 20. In Figures 1 and 4, the supports are shown on corresponding separable compartments 26 of each pod 20. 10 An alternative embodiment of cavity former 10 comprises a single pod 20 and integrated crossed ribs 30 as described above with or without the valleys 24. This embodiment has the same advantages as described above, i.e. enabling the reinforcement mesh to be supported on the pod 20 in any orientation relative to the cavity former 10 and avoiding the necessity for separate bar chairs to support 15 the mesh. The pods 20 are linked by seats for supporting reinforcement bar 14. The seats are integrally formed in the trenches 40. In one embodiment (not illustrated), the seats are provided by the floor of the trench 40 having a shape, eg. parabolic, that automatically aligns and centers the reinforcement bar 14 longitudinally within the 20 trench 40. In the preferred embodiment, as illustrated, however, the seats are provided in the form of saddles 42 integrally formed in the trenches 40 to link opposed pods 20 (Figures 2 and 4). The top edge 43 of each saddle 42, is formed with a parabolic shape to enable automatic centering of a reinforcement bar dropped into the trenches 40. 25 The saddles 42 respectively located in the perpendicularly arranged trenches 40 are vertically offset to ensure that reinforcement bar 14 in one trench 40 does not interfere with reinforcement bar 14' located in a perpendicular trench 40 at the point where the trenches 40 intersect. While the upper edges of saddles 42 may have a parabolic profile, it will be 30 appreciated that any other shape suitable for automatically centering WO 2005/061804 PCT/AU2004/001806 9 reinforcement bar 14 in a trench 40 may alternatively be adopted. For example, the saddles may have a v-shaped profile spanning substantially the whole width of the trenches 40. A pair of upwardly turned tabs 50 are located on two adjacent sides of the cavity 5 former 10 to interlock adjacently arranged cavity formers in situ (Figure 3). By interlocking adjacent cavity formers 10 together, individual cavity formers 10 are prevented from relatively shifting during the pouring of the wet concrete. Accordingly, the cavity formers of an array of interlocked cavity formers 10 maintain their original positioning during the concrete pour. 10 Rounded depressions 52 are formed in the upper sides of one or more of the pods 20 to provide hook points for attachments to lift the cavity former 10 or a plurality of nesting cavity formers 10 when they are upturned. Typically, nesting cavity formers 10 are turned upside down for transport as the ribs 30 on the lowermost cavity former 10 provide a clearance between the upper surface 28 of the pods 20 15 and the ground. This clearance enables suitable lifting means, such as a fork lift, to slide underneath the nesting cavity formers 12 and pick them up. Slab formation preparations, using the cavity formers 10, involve first delivering a required number of the cavity formers 10, in a nested stack, to the construction site. At the construction site, the ground on which the slab is to be formed is 20 levelled and prepared, shutters are erected to define the perimeter of the slab, and reinforcement elements are positioned for edge beams of the building to be constructed. One or two workers then place individual cavity formers 10 in an array on the levelled ground such that they are interlocked by the upturned tabs 50. Customised shaping of some cavity formers 10 may be necessary at the 25 margins of the slab site. The interlocked cavity formers 10 should provide blanket coverage over the levelled ground such that, during pouring and curing, the ground is not exposed to the wet concrete: the cavity formers are thereby able to take the place of traditional ground sheeting both in its short term role in containing moisture within the concrete gel matrix during curing of the concrete, 30 and in its longer term role as a vapour barrier between the ground and the finished slab during the life of the slab.
WO 2005/061804 PCT/AU2004/001806 10 Once positioned, the trenches 40 of adjacent cavity formers 10 will be in alignment, thereby enabling reinforcement bar 14 to be dropped directly into the trenches for automatic centering on saddles 42. Accordingly, separate spacers are not required to achieve the correct spacing between adjacent pods 20 and, 5 moreover, the use and positioning of bar chairs in the trenches 40 is not required. Substantial time is thereby saved in preparing for the wet concrete to be poured. Reinforcement mesh 12 is then located on the cavity formers 10 for support by the ribs 30. As the cruciform arrangement of the ribs 30 enables the reinforcement mesh 12 to be located on the cavity formers in any orientation relative thereto, 10 more time is saved because neither bar chairs nor specific mesh orientations are required. Typically the cavity formers 10 are square and having side lengths in the range of 800-1600 millimetres, but preferably 1000-1200 millimetres. They may be formed with a height in the range of 150-400 millimetres, but specifically may be 15 fabricated with 175, 225, 300 or 375 millimetre heights for different slab depths. The cavity formers 10 are composed of a suitable plastics material to support the weight of wet concrete bearing down on the cavity former during curing, or the weight of a person standing on the cavity former. For example, the cavity formers are formed to support a 150 kilogram point load. For the concrete curing process, 20 the cavity formers 10 are able to support about 280 kilograms per square metre.

Claims (11)

1. A cavity former for forming one or more cavities in a concrete slab, including: 5 a hollow body about which, during use of the former, poured concrete flows and subsequently cures to form a concrete slab in which the hollow body defines a cavity; wherein said hollow body has a first wall having a periphery and an upper surface, a skirt wall depending from the periphery, and a pair of intersecting upstanding ribs formed integrally on the outer surface of said first wall for supporting reinforcing 10 mesh above said hollow body.
2. A cavity former according to claim I wherein said ribs are a pair of crossed ribs. Is
3. A cavity former according to either claim 1 or claim 2 wherein said hollow body includes a structure defining, within said periphery, at least one depending hollow pillar formation for in situ bracing said first wall to an underlying surface on which said skirt wall also rests. 20
4. A cavity former according to claim 3, wherein said structure comprises a plurality of valleys in said first wall that define said at least one hollow pillar formation at their intersection.
5. A cavity former according to claim 3, wherein said structure comprises 25 a hollow tubular structure which constitutes said pillar formation.
6. A cavity former according to claim 5 wherein said hollow tubular structure has its interior open at said first wall. 30
7. A cavity former according to any one of claims 3 to 6, wherein said hollow body is configured to allow nesting of said cavity former with a second similar cavity former, and thereby to allow stacking of a multiplicity of said cavity formers. 12
8. A cavity former according to claim 7 wherein said skirt wall and said structure defining the hollow pillar formation are tapered to nest with the like features of a similar cavity former. s
9. A cavity former according to any one of preceding claims wherein said hollow body is a rectangular pod open on a lowermost side.
10. A cavity former according to any one of the preceding claims wherein said cavity former has a plurality of hollow bodies or pods spaced apart by integrally io formed channels that receive elongated slab-reinforcement.
11. A cavity former substantially as hereinbefore described with reference to the accompanying drawings. is Dated 4 February, 2011 The Australian Steel Company (Operations) Pty Ltd Patent Attorneys for the Applicant/Nominated Person SPRUSON & FERGUSON
AU2004303436A 2003-12-23 2004-12-22 Cavity former Active AU2004303436B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2004303436A AU2004303436B2 (en) 2003-12-23 2004-12-22 Cavity former

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
AU2003907151 2003-12-23
AU2003907151A AU2003907151A0 (en) 2003-12-23 Cavity former
AU2004303436A AU2004303436B2 (en) 2003-12-23 2004-12-22 Cavity former
PCT/AU2004/001806 WO2005061804A1 (en) 2003-12-23 2004-12-22 Cavity former

Publications (2)

Publication Number Publication Date
AU2004303436A1 AU2004303436A1 (en) 2005-07-07
AU2004303436B2 true AU2004303436B2 (en) 2011-03-24

Family

ID=36686166

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2004303436A Active AU2004303436B2 (en) 2003-12-23 2004-12-22 Cavity former

Country Status (1)

Country Link
AU (1) AU2004303436B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930456A (en) * 2017-03-28 2017-07-07 扬州大学 A kind of assembled wood bamboo lightweight aggregate reinforced concrete combination floor

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5105595A (en) * 1989-03-31 1992-04-21 Shimizu Construction Co., Ltd. Mold panel unit and spring-water processing structure using mold panel units
US5787230A (en) * 1994-12-09 1998-07-28 Lee; Lin-Shan System and method of intelligent Mandarin speech input for Chinese computers
US6550207B1 (en) * 1999-03-03 2003-04-22 Valerio Pontarolo Modular element for crawl spaces and floor structures

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5105595A (en) * 1989-03-31 1992-04-21 Shimizu Construction Co., Ltd. Mold panel unit and spring-water processing structure using mold panel units
US5787230A (en) * 1994-12-09 1998-07-28 Lee; Lin-Shan System and method of intelligent Mandarin speech input for Chinese computers
US6550207B1 (en) * 1999-03-03 2003-04-22 Valerio Pontarolo Modular element for crawl spaces and floor structures

Also Published As

Publication number Publication date
AU2004303436A1 (en) 2005-07-07

Similar Documents

Publication Publication Date Title
US20070214740A1 (en) Cavity Former
US20080035830A1 (en) Cavity Former
EP1325991B1 (en) Method for manufacturing a floor of concrete and shuttering slab for use therein
US4831803A (en) Foundation form work
US20090151298A1 (en) Method of Making Monolithic Concrete Structures
WO2003048471A1 (en) Embedment-type mould for manufacturing building slab structures
AU2005240674B2 (en) Cavity former
US20050011152A1 (en) Cavity former
AU2004303436B2 (en) Cavity former
AU2015238916B2 (en) Closed void former for inclusion in concrete slabs
EP0265262B1 (en) Improvements relating to building foundation form work
AU2019101738B4 (en) A void forming module and system therefor
US20040237432A1 (en) Foundation structure, components therefor and method of constructing a foundation
AU778630B2 (en) A formwork component
AU727681B3 (en) A formwork module for a waffle slab foundation
JPS6012011Y2 (en) embedding material
US10435892B2 (en) Spacing element for making structural, aerated heat-insulation crawl spaces
AU2020238616A1 (en) Void former and modular formwork system
JPH03212547A (en) Synthetic resin panel and constructing method of double slab structure
JP3016148U (en) Drainage panel
CA2119296C (en) Modular concrete floor slab
JPS6018782B2 (en) On-site construction method for concrete slabs
JP2004176384A (en) Hollow pressure slab and its construction method
AU735297B2 (en) Bar chair
AU2004203236A1 (en) Cavity former

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)