AT46833B - Procedure for lowering groundwater in construction pits. - Google Patents

Procedure for lowering groundwater in construction pits.

Info

Publication number
AT46833B
AT46833B AT46833DA AT46833B AT 46833 B AT46833 B AT 46833B AT 46833D A AT46833D A AT 46833DA AT 46833 B AT46833 B AT 46833B
Authority
AT
Austria
Prior art keywords
procedure
construction pits
groundwater
posts
lowering
Prior art date
Application number
Other languages
German (de)
Original Assignee
Siemens Ag
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens Ag filed Critical Siemens Ag
Application granted granted Critical
Publication of AT46833B publication Critical patent/AT46833B/en

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

  

   <Desc/Clms Page number 1> 
 



  Verfahren zum Absenken von Grundwasser in Baugruben. 
 EMI1.1 
 Pfosten, die allein oder in Verbindung mit zwischen ihnen angeordneten Baugrubenwäuden zum   Zurückhalten   des Erdreiches dienen, Brunnenrohre zur   Entwässerung   der Baugrube oder zur Senkung des Grundwasserspiegels eingesetzt werden.'
Fig. 1 und 2 zeigen den Schnitt und den Grundriss der Baugrube einer Untergrundbahn, deren Aussteifung gemäss dem neuen Verfahren erfolgt ist.

   Die in Fig. 3 bis n näher dargestellten, für den vorliegenden Zweck besonders geeigneten Pfosten bestehen je aus zwei U-Eisen   c.   dz die durch ein Flacheisengitterwerk e miteinander verbunden sind und deren Zwischenraum derart mit Betonmasse ausgefüllt ist. dass innen die Bohrung c verbleibt und dass an den Seitenflächen die Zwischenräume zwischen den Flacheisen c bündig ausgefüllt sind. 
 EMI1.2 
 so werden die Schellen entfernt und das Bohrrohr allein weitergesenkt, bis die für den Brunnen nötige Tiefe erreicht ist. 
 EMI1.3 
 versteifen. 



   Sofern es, wie bei dem Ausführungsbeispiel a angenommen, nötig ist, die die Brunnenrohre miteinander verbindende Saugleitung k tiefer als die Köpfe der Pfosten   anzuordnen,   werden zweckmässig in dem die U-Eisen verbindenden Gitterwerk Zwischenräume o vorgesehen. An diesen Stellen wird nach dem Ausschachten die Betonwand des Pfostens   zertrümmert,   so dass durch die entstehende Öffnung das in der   Baugrube angebrachte   
 EMI1.4 
 verbunden werden kann. 



   Die beschriebene Anordnung wird mit besonderem Vorteil dann verwendet, wenn mit Rücksicht auf benachbarte Gebäude ein Einrammen von Pfosten gefährlich ist und die Pfosten daher nach Art von Brunnen eingesenkt werden. Alsdann wird beim Einbringen eines Pfostens bereits ein wesentlicher Teil der Bohrarbeit für den Brunnen   geleistet und   
 EMI1.5 




   <Desc / Clms Page number 1>
 



  Procedure for lowering groundwater in construction pits.
 EMI1.1
 Posts which serve alone or in connection with building pit walls arranged between them to hold back the soil, well pipes are used to drain the building pit or to lower the groundwater level. '
1 and 2 show the section and the floor plan of the excavation of an underground railway, the stiffening of which was carried out according to the new method.

   The posts shown in more detail in Fig. 3 to n, which are particularly suitable for the present purpose, each consist of two U-irons c. dz which are connected to each other by a flat iron lattice and the space between them is filled with concrete mass. that inside the hole c remains and that the spaces between the flat iron c are filled flush on the side surfaces.
 EMI1.2
 so the clamps are removed and the drill pipe is lowered further until the depth required for the well is reached.
 EMI1.3
 stiffen.



   If, as assumed in embodiment a, it is necessary to arrange the suction line k connecting the well pipes to one another lower than the heads of the posts, spaces o are expediently provided in the latticework connecting the U-bars. After excavation, the concrete wall of the post is smashed at these points, so that the opening that has been made in the excavation pit
 EMI1.4
 can be connected.



   The arrangement described is used with particular advantage when, with consideration for neighboring buildings, it is dangerous to ram posts and the posts are therefore sunk in the manner of a well. Then a substantial part of the drilling work for the well is already done when a post is inserted
 EMI1.5


 

Claims (1)

PATENT. ANSPRUCH : Verfahren zum Absenken von Grundwasser in Baugruben, dadurch gekennzeichnet, dass die Rrunnenrohre in den die Baugrubenwände absteifenden Pfosten untergebracht worden. EMI2.1 PATENT. CLAIM : Method for lowering groundwater in construction pits, characterized in that the runner pipes have been accommodated in the posts bracing the construction pit walls. EMI2.1
AT46833D 1908-09-08 1909-09-01 Procedure for lowering groundwater in construction pits. AT46833B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE46833X 1908-09-08

Publications (1)

Publication Number Publication Date
AT46833B true AT46833B (en) 1911-03-10

Family

ID=5625420

Family Applications (1)

Application Number Title Priority Date Filing Date
AT46833D AT46833B (en) 1908-09-08 1909-09-01 Procedure for lowering groundwater in construction pits.

Country Status (1)

Country Link
AT (1) AT46833B (en)

Similar Documents

Publication Publication Date Title
DE112016002341B4 (en) Arrangement of several tubular piles arranged next to one another with a heat transfer pipe arrangement embedded in at least one prefabricated tubular pile and a pump unit
EP2374942B1 (en) Device and method for generating heat from the environment
DE10202261A1 (en) Heat source or heat sink system with thermal earth coupling
DE2434200B2 (en) METHOD OF CREATING UNDERGROUND CAVITIES
EP0017783A1 (en) Device for utilizing terrestrial heat and process for producing this device
AT46833B (en) Procedure for lowering groundwater in construction pits.
EP1530662A1 (en) Foundation for water structures
DE102005001422A1 (en) Sinking pits or wells involves filling concrete in shell, compressing, removing soil to let concrete lower, introducing/compressing more concrete, removing more soil to let concrete, repeating until shaft at required depth, removing shell
AT376263B (en) DEVICE AND METHOD FOR HITING A FOUNTAIN
DE593664C (en) Installation on caissons for the foundation of structures
AT241362B (en) Procedure for the foundation of structures below the water table
DE3123063C1 (en) Method of producing a watertight excavation side which in the bottom part can be partly re-opened to restore the free flow of groundwater
DE2514363A1 (en) INJECTION VALVE PIPE ROD
DE841427C (en) Foundation construction method
DE2528028A1 (en) Building consideration during hydro-electric dam construction - bridging connecting pipes are provided during construction to take away flood water
DE2030259C3 (en) Process for the production of a structure below the water table
DD150793A5 (en) DEVICE FOR RECEIVING EARTH WARM AND METHOD FOR MANUFACTURING THIS DEVICE
AT136050B (en) Methods of building underground railways.
DE2364925A1 (en) Sinking building foundation components - by division and supplementing with mounting walls with lining walls directed against impact
AT70928B (en) Method for inserting a girder for bracing construction pits, in particular for building underground railways.
DE3307392A1 (en) METHOD FOR CONSTRUCTION OF CONCRETE LINED UNDER CONCRETE
DE804183C (en) Underwater tunnel
AT69455B (en) Method of making well bores and pile holes.
AT44549B (en) Process for the waterproof lining of boreholes under water.
DE557509C (en) Process for the production of wells and shafts within sheet piling