JP2002146761A - Method for executing and planning of construction work for road occupation - Google Patents

Method for executing and planning of construction work for road occupation

Info

Publication number
JP2002146761A
JP2002146761A JP2000345245A JP2000345245A JP2002146761A JP 2002146761 A JP2002146761 A JP 2002146761A JP 2000345245 A JP2000345245 A JP 2000345245A JP 2000345245 A JP2000345245 A JP 2000345245A JP 2002146761 A JP2002146761 A JP 2002146761A
Authority
JP
Japan
Prior art keywords
construction
road
traffic
plan
application
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000345245A
Other languages
Japanese (ja)
Inventor
Eiji Matsuyama
英治 松山
Tsuyoshi Mizukami
剛志 水上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP2000345245A priority Critical patent/JP2002146761A/en
Publication of JP2002146761A publication Critical patent/JP2002146761A/en
Pending legal-status Critical Current

Links

Landscapes

  • Instructional Devices (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Traffic Control Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To predict traffic congestion and apply for a road-use permission. SOLUTION: In the method for executing construction works for the exclusive use of a road in which construction works to the road are executed according to predetermined basic specifications 41, the method has a traffic simulation process 30 in which a traffic simulation containing the prediction of a traffic situation in a construction section 44 at a time when roadworks are executed is conducted on the basis of traffic volume 38 measured under the state, in which roadworks are not executed, traffic conditions 40 in the periphery of the construction section 44, in which road works are executed, and the execution conditions 42 and 43 of roadworks, an execution-planning preparation process 31 in which an execution planning is prepared on the basis of the execution conditions and basic specifications of the roadworks when traffic congestion information satisfies a criterion as the result of the traffic simulation, and an execution process 29 in which roadworks are executed on the basis of the prepared execution planning.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、交通規制を伴う道
路占用工事における施工方法、施工計画方法、施工計画
支援方法、申請支援方法、及び施工計画を行うコンピュ
ータ読取可能なプログラムを記録した記録媒体に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method, a construction planning method, a construction planning support method, an application support method, and a recording medium storing a computer-readable program for performing a construction plan in a road occupation construction with traffic regulation. About.

【0002】[0002]

【従来の技術】主に都市におけるインフラ整備のため
に、交通規制を伴う道路占用工事が頻繁に実施されてい
る。この道路占用工事には、舗装の補修等の道路自体の
維持管理のための工事以外にも、上下水道工事、電力線
や、電話線や、ガス管の新規敷設、交換等の工事があ
る。
2. Description of the Related Art Road occupation work involving traffic regulation is frequently performed mainly for infrastructure development in cities. This road occupying work includes works for maintenance of the road itself such as pavement repair, water and sewage works, new laying and replacement of power lines, telephone lines, and gas pipes.

【0003】図9は例えば道路にガス管を敷設する工事
現場の見取り図である。道路の車道に一般車両の通行を
排除する工事区間1が設けられ、この工事区間1内にお
いて、掘削2、配管・溶接3、検査・埋め戻し4の合計
3つの作業工程が存在する。すなわち、これらの各作業
工程を実施する作業帯と車両通行を誘導する導流帯とを
工事区間1と称する。
FIG. 9 is a schematic view of a construction site where a gas pipe is laid on a road, for example. A construction section 1 for excluding traffic of general vehicles is provided on the roadway of the road. In this construction section 1, there are a total of three work processes of excavation 2, piping and welding 3, and inspection and backfilling 4. That is, a work zone for performing each of these work processes and a diversion zone for guiding vehicle traffic are referred to as a construction section 1.

【0004】掘削2工程においては、掘削機6で溝7を
堀り、堀り出した土砂をダンプトラック5で排出する。
配管・溶接3工程においては、溝7内にクレーン車8で
例えば6m又は12m長の管を順番に敷設し、溶接車9
に搭載した溶接機器で管の継ぎ目を溶接していく。検査
・埋め戻し4工程においては、検査車10に搭載した検
査機器で溶接部分を検査し、図示しない埋め戻し機で溝
7を埋め戻し、舗装を行う。以上の一連の工事が終了す
ると、工事区間1を道路に沿って移動させる。
In the second excavation step, the trench 7 is dug by the excavator 6 and the excavated earth and sand is discharged by the dump truck 5.
In the three steps of piping and welding, crane trucks 8 sequentially lay, for example, 6 m or 12 m long pipes in grooves 7, and weld
Weld the pipe joints with the welding equipment installed in. In the four steps of inspection and backfilling, the welding portion is inspected by an inspection device mounted on the inspection vehicle 10, and the groove 7 is backfilled by a backfilling machine (not shown) to perform paving. When the above series of works is completed, the work section 1 is moved along the road.

【0005】この1回の工事で実施する工事区間1の工
事区間長は長くなるほど、機械の使用効率や作業効率が
高くなり、工事の施工効率が向上すると考えられる。し
かし、工事区間1は道路交通に対して障害となるため、
交通量によっては渋滞が発生するので、長い工事区間1
を確保できない場合がある。長い工事区間1を設置する
と、著しい交通渋滞が発生し、周辺環境や運転者に与え
る影響を悪化するだけでなく、経済的にも大きな損失を
まねく危険がある。
[0005] It is considered that the longer the construction section length of the construction section 1 to be carried out in this one construction is, the higher the use efficiency and the working efficiency of the machine are, and the construction efficiency of the construction is improved. However, construction section 1 is an obstacle to road traffic,
Long construction section 1 due to traffic congestion depending on traffic volume
May not be secured. When the long construction section 1 is installed, a significant traffic congestion occurs, which not only worsens the influence on the surrounding environment and the driver, but also causes a great economical loss.

【0006】警察等の道路使用許可者は、工事業者から
道路占用工事に対する道路使用許可申請が出されると、
工事を実施しない状態での道路工事が実施される工事区
間の周辺の交通量が一定規準以下で、かつ道路工事を実
施したときに、著しい交通渋滞が発生しないと判定した
場合のみ工事許可を与える。
[0006] The police or other road use permitters, when a construction contractor applies for a road use permit for road occupation work,
A construction permit is granted only when the traffic volume around the construction section where road construction is carried out without construction is below a certain standard, and when it is determined that no significant traffic congestion occurs when carrying out road construction .

【0007】したがって、工事業者は、予め工事を実施
する工事区間の周辺の交通量の調査を実施して、交通量
が一定基準以下であることを確認した後、申請を実施し
ている。
[0007] Accordingly, the construction contractor conducts an application before carrying out a survey of the traffic volume around the construction section where the construction is to be performed and confirms that the traffic volume is below a certain standard.

【0008】図10は工事業者が実施する道路使用許可
申請処理の流れ図である。ガス会社や水道局の工事発注
者から配管の敷設位置(敷設地図)、埋設深さ、管の種
類や径等の基本仕様を指定した工事を受注する(S
1)。次に、受領した基本仕様を満たすための工事の施
工計画の立案を行う(S2)。この施工計画には、各工
事区間長や工事時間等が含まれる。次に、前述した工事
を実施しようとする区間の交通量の調査を行う(S
3)。
FIG. 10 is a flowchart of a road use permission application process carried out by a contractor. Receive orders from the gas company or the Water Works Bureau for work that specifies the basic specifications such as the pipe laying position (laying map), burial depth, pipe type and diameter (S
1). Next, a construction plan for the construction to satisfy the received basic specifications is made (S2). This construction plan includes the length of each construction section, construction time, and the like. Next, the traffic volume in the section where the above-mentioned construction is to be performed is investigated (S
3).

【0009】交通量が一定基準以下であれば、施工計画
に基づいて、道路使用許可申請書類を作成し(S4)、
道路使用許可者に交通量調査結果を添えて、道路使用許
可申請を実施する(S5)。道路使用許可者から申請許
可が下ると(S6)、施工計画に基づいて実際の工事を
実施する(S7)。そして、工事完了を工事発注者に報
告する。なお、申請が却下されると(S6)、S2へ戻
り、施工計画をやり直す。
If the traffic volume is below a certain standard, a road use permission application document is prepared based on the construction plan (S4),
A road use permit application is carried out with the traffic use result attached to the road use permitter (S5). When application permission is obtained from a road use permitter (S6), actual construction is performed based on the construction plan (S7). Then, the construction completion is reported to the construction orderer. When the application is rejected (S6), the process returns to S2, and the construction plan is redone.

【0010】[0010]

【発明が解決しようとする課題】しかしながら、図10
に示す手順で工事を実施する道路占用工事の施工方法に
おいてもまだ改良すべき次のような課題があった。
However, FIG.
The following problems still need to be improved in the construction method of the road occupation construction in which the construction is performed according to the procedure described in (1).

【0011】道路使用許可者は、工事業者から提出され
た交通量調査結果を基に、最大交通量のときに、申請さ
れた長さの工事区間の設置により渋滞が発生するか否か
を判定するか、あるいはどの程度の渋滞が発生するかを
評価して、道路使用を許可するか否かを判定している。
[0011] Based on the traffic volume survey results submitted by the contractor, the road use permitr determines whether or not a congestion will occur due to installation of a construction section of the requested length at the time of maximum traffic volume. Or how much congestion will occur, to determine whether to permit use of the road.

【0012】しかしながら、道路使用許可者には状況に
応じて定量的に渋滞の程度を評価する手段がないので、
過去に行われた道路工事の際の実績や経験を勘案して判
定している。そのため、渋滞の発生するおそれの少ない
短い工事区間で工事を実施することがほとんどであり、
過去に実績のない長い工事区間の道路使用申請がなされ
ても判定することができないので、許可される可能性は
きわめて低い。
[0012] However, since there is no means for the road permitter to quantitatively evaluate the degree of congestion according to the situation,
Judgments are made by taking into account the results and experience of road construction performed in the past. For this reason, construction is often carried out in short construction sections where traffic jams are less likely to occur.
Since it cannot be determined even if a road use application for a long construction section with no track record in the past is made, the possibility of permission is extremely low.

【0013】また、実績や経験に基づく判定のため、必
ずしも現状の交通状況に対応しているわけではない。過
去に渋滞を起こさずに工事を実施した場所において、同
様な工事をした場合でも、僅かな状況の変化により渋滞
を引き起こす可能性もある。
[0013] Further, since the judgment is based on the actual results and experiences, the judgment does not always correspond to the current traffic situation. Even if similar construction is performed at a place where construction was performed without causing traffic congestion in the past, there is a possibility that a slight change in the situation may cause traffic congestion.

【0014】また、同じ交通量でも大型車が多い場合と
小型車が多い場合では渋滞の程度が異なるにもかかわら
ず、従来は、大型車・小型車等の車両種類を考慮して評
価していない。
In addition, although the degree of congestion differs between a large number of large vehicles and a large number of small vehicles even with the same traffic volume, evaluation has not been made in consideration of vehicle types such as large vehicles and small vehicles.

【0015】本発明はこのような事情に鑑みてなされた
ものであり、実際に測定された交通量を用いた工事区間
周辺の交通シミュレーションを行うことにより、実際に
道路工事を実施している状態の渋滞発生の有無及び渋滞
の程度を推定でき、工事に起因する障害を最小限に抑制
し、かつ工事を効率的に実施できる交通規制を伴う道路
占用工事における施工方法、施工計画方法、施工計画支
援方法、申請支援方法、及び施工計画を行うコンピュー
タ読取可能なプログラムを記録した記録媒体を提供する
ことを目的とする。
[0015] The present invention has been made in view of such circumstances, and a traffic simulation around a construction section using an actually measured traffic volume is performed, so that road construction is actually performed. Method, construction planning method, and construction plan for road occupation with traffic regulation that can estimate the occurrence of traffic congestion and the degree of traffic congestion, minimize obstacles caused by construction, and efficiently carry out construction An object of the present invention is to provide a recording medium recording a computer-readable program for performing a support method, an application support method, and a construction plan.

【0016】[0016]

【課題を解決するための手段】本発明は、予め定められ
た基本仕様に従って道路に対する工事を実施する道路占
用工事の施工方法に適用される。そして、上記課題を解
消するために、本発明においては、道路工事を実施しな
い状態で測定された交通量と道路工事が実施される工事
区間の周辺における交通条件と道路工事の実施条件とに
基づいて、道路工事が実施された場合の工事区間におけ
る交通状況の予測を含む交通シミュレーションを行う交
通シミュレーション工程と、交通シミュレーション結果
において交通渋滞情報が判定基準を充足するとき、当該
工事の実施条件及び基本仕様に基づいて施工計画を作成
する施工計画作成工程と、この作成された施工計画に基
づいて道路工事を実施する施工工程とを備えている。
SUMMARY OF THE INVENTION The present invention is applied to a road occupation construction method for performing a road construction in accordance with a predetermined basic specification. In order to solve the above-mentioned problem, in the present invention, based on the traffic volume measured in a state where the road construction is not performed, the traffic conditions around the construction section where the road construction is performed, and the execution conditions of the road construction. A traffic simulation process for performing a traffic simulation including a prediction of traffic conditions in a construction section when road construction is carried out; and, when traffic congestion information satisfies a judgment criterion in a traffic simulation result, the condition for implementing the construction and the basic It includes a construction plan creation step of creating a construction plan based on the specifications, and a construction step of performing road construction based on the created construction plan.

【0017】このように構成された道路占用工事の施工
方法においては、道路工事が実施された場合の工事区間
における交通状況の予測を含む交通シミュレーションが
実施され、この交通シミュレーション結果において交通
渋滞情報が判定基準を充足するときに施工計画が作成さ
れる。したがって、この施工計画を実際に施工している
過程で、予想しない大規模な交通渋滞が発生する可能性
は低い。
In the construction method of the road occupation construction constructed as described above, a traffic simulation including a prediction of a traffic condition in a construction section when the road construction is carried out is carried out. A construction plan is created when the criteria are satisfied. Therefore, it is unlikely that unexpected large-scale traffic congestion will occur during the actual execution of this construction plan.

【0018】また、別の発明は、上述した発明の道路占
用工事の施工方法にける周辺における交通条件は工事区
間を含む道路の道路形状、周囲の信号位置及び当該信号
の信号周期とを含む。さらに、工事の実施条件は工事占
有長さ及び道路使用時間情報を含む。
In another aspect of the present invention, the traffic conditions in the periphery in the road occupation construction method according to the above invention include a road shape of a road including a construction section, a surrounding signal position, and a signal period of the signal. Further, the execution condition of the construction includes the construction occupation length and the road use time information.

【0019】また、別の発明は、上述した発明の道路占
用工事の施工方法において、交通シミュレーション結果
における交通渋滞情報は、通過時間、遅れ時間、待ち時
間、待ち台数、又は渋滞長さのうちいずれか1以上を含
むようにしている。
According to another invention, in the road occupancy construction method according to the invention described above, the traffic congestion information in the traffic simulation result includes any one of a transit time, a delay time, a waiting time, the number of waiting units, and a congestion length. Or more than one.

【0020】また、別の発明は、上述した発明の道路占
用工事の施工方法に対して、さらに、施工計画作成工程
にて作成された施工計画を含む道路使用許可申請を当該
道路の使用許可者へ提出する申請工程を付加している。
[0020] In another aspect of the present invention, in addition to the road occupation construction method of the invention described above, a road use permission application including a construction plan created in a construction plan creation step is further applied to the road use permitter. An application process to submit to is added.

【0021】さらに、別の発明は、上述した発明の道路
占用工事の施工方法において、道路使用許可申請は、交
通シミュレーション結果の交通渋滞情報も含む。さら
に、別の発明は、上述した発明の道路占用工事の施工方
法において、申請工程は、道路使用許可申請を通信ネッ
トワークを介して道路の使用許可者へ提出するようにし
ている。
According to another aspect of the invention, in the road occupation construction method of the invention described above, the road use permission application includes traffic congestion information as a result of a traffic simulation. Further, in another invention, in the construction method of the road occupation construction according to the invention described above, the application step submits a road use permission application to a road use permitter via a communication network.

【0022】また、別の発明は、上述した発明の道路占
用工事の施工方法に対して、さらに、施工計画作成工程
にて作成された施工計画に基づいて基本仕様に対する工
事見積を作成する見積工程を付加している、また、別の
発明は、上述した発明の道路占用工事の施工方法に対し
て、さらに、周辺の交通条件と工事の実施条件とのうち
少なくとも一方の条件を変更しつつ、交通シミュレーシ
ョン工程及び施工計画作成工程を繰返し実行し、施工工
程で実施される施工計画を最適化する施工計画最適化工
程を付加している。このように構成された道路占用工事
の施工方法においては、交通渋滞情報が判定基準を充足
する限りにおいて、最も効率的に施工できる施工計画が
得られる。
According to another aspect of the present invention, there is provided a road occupancy construction method according to the above-described invention, further comprising: an estimating step of creating a construction estimate for basic specifications based on the construction plan created in the construction plan creating step. In addition, another invention is a construction method of the road occupation work of the invention described above, further, while changing at least one of the surrounding traffic conditions and the implementation conditions of the construction, The traffic simulation process and the construction plan creation process are repeatedly executed, and a construction plan optimization process for optimizing the construction plan performed in the construction process is added. In the construction method of the road occupation construction thus configured, a construction plan that can be most efficiently constructed is obtained as long as the traffic congestion information satisfies the determination criteria.

【0023】さらに、別の発明は、上述した発明の道路
占用工事の施工方法において、計画最適化工程は、基本
仕様を実現させるに要する工事全体の施工期間が最小と
なるように、及び又は、施工コストが最小となるよう
に、施工工程で実施される施工計画を最適化する。
Further, another invention is the road occupancy construction method of the invention described above, wherein the plan optimizing step is performed so that the construction period of the entire construction required to realize the basic specification is minimized, and / or Optimize the construction plan implemented in the construction process so that the construction cost is minimized.

【0024】また、本発明は、予め定められた基本仕様
に従って道路に対する工事を実施する道路占用工事の施
工計画方法である。そして、道路工事を実施しない状態
で測定された交通量と道路工事が実施される工事区間の
周辺における交通条件と道路工事の実施条件とに基づい
て、道路工事が実施された場合の工事区間における交通
状況の予測を含む交通シミュレーションを行う交通シミ
ュレーション工程と、交通シミュレーション結果におい
て交通渋滞情報が判定基準を充足するとき、当該工事の
実施条件及び基本仕様に基づいて施工計画を作成する施
工計画作成工程とを備えている。
[0024] The present invention is also a construction planning method for a road occupation construction for performing construction on a road in accordance with a predetermined basic specification. Then, based on the traffic volume measured without road construction and the traffic conditions around the construction section where the road construction is carried out, and the conditions for the road construction, A traffic simulation process for performing a traffic simulation including prediction of traffic conditions, and a construction plan creation process for creating a construction plan based on the execution conditions and basic specifications of the construction when traffic congestion information satisfies a determination criterion in the traffic simulation results. And

【0025】このような構成の道路占用工事の施工計画
方法においても、交通シミュレーションを行うことによ
って先の発明における施工方法とほぼ同様の作用効果を
奏することができる。
Also in the construction planning method for the road occupation construction having such a configuration, by performing the traffic simulation, it is possible to obtain substantially the same operation and effect as the construction method in the above invention.

【0026】さらに、別の発明は、上述した発明の道路
占用工事の施工計画方法に加えて、上述した見積工程を
加えている。さらに、別の発明は、上述した発明の道路
占用工事の施工計画方法に加えて、上述した施工計画最
適化工程を付加している。
Further, another invention adds the above-mentioned estimation step in addition to the construction planning method for road occupation work of the invention described above. Further, another invention adds the above-described construction plan optimizing step to the construction planning method of the road occupation construction of the invention described above.

【0027】また、本発明は、予め定められた基本仕様
に従って道路に対する工事を実施する道路占用工事の施
工計画支援方法である。そして、支援要求元から基本仕
様を受付ける基本仕様受付工程と、道路工事を実施しな
い状態で測定された交通量と道路工事が実施される工事
区間の周辺における交通条件と道路工事の実施条件とに
基づいて、道路工事が実施された場合の工事区間におけ
る交通状況の予測を含む交通シミュレーションを行う交
通シミュレーション工程と、交通シミュレーション結果
において交通渋滞情報が判定基準を充足するとき、当該
工事の実施条件及び基本仕様に基づいて施工計画を作成
する施工計画作成工程と、この施工計画作成工程で作成
された施工計画を支援要求元へ引渡す施工計画引渡工程
とを備えている。
Further, the present invention is a construction plan support method for a road occupying construction, which carries out construction on a road in accordance with predetermined basic specifications. Then, the basic specification receiving process of receiving the basic specification from the support request source, the traffic volume measured without road construction, the traffic conditions around the construction section where the road construction is performed, and the road construction implementation conditions A traffic simulation step of performing a traffic simulation including a prediction of traffic conditions in a construction section when road construction is performed, and, when traffic congestion information satisfies a determination criterion in a traffic simulation result, execution conditions of the construction and The method includes a construction plan creation process for creating a construction plan based on the basic specifications, and a construction plan delivery process for delivering the construction plan created in the construction plan creation process to a support request source.

【0028】このように構成された道路占用工事の施工
計画支援方法においては、工事を実際に実行する工事業
者(支援要求元)と、交通シミュレーションを行い施工
計画を作成するする工事計画作成支援業者とが異なる。
そして、工事計画作成支援業者が工事業者(支援要求
元)がら基本仕様を受けて交通シミュレーションを行い
施工計画を作成し、工事業者(支援要求元)へ引き渡
す。
In the construction plan support method for road occupation construction constructed as described above, a construction company (support request source) that actually executes the construction and a construction plan creation support company that creates a construction plan by performing a traffic simulation. Is different.
The construction plan creation support company receives the basic specifications from the construction company (support request source), performs a traffic simulation, creates a construction plan, and hands over the construction plan (support request source).

【0029】さらに、別の発明は、上述した発明の道路
占用工事の施工計画支援方法において、基本仕様受付工
程は通信ネットワークを介して基本仕様を受付け、施工
計画引渡工程は通信ネットワークを介して施工計画を引
渡す。
Another aspect of the present invention is the method for supporting a construction plan for a road occupation construction according to the above invention, wherein the basic specification receiving step receives the basic specification via a communication network, and the construction plan delivery step executes the construction plan via the communication network. Deliver the plan.

【0030】また、本発明は、予め定められた基本仕様
に従って道路に対する工事を実施する道路占用工事の申
請支援方法である。そして、支援要求元から基本仕様を
受付ける基本仕様受付工程と、道路工事を実施しない状
態で測定された交通量と道路工事が実施される工事区間
の周辺における交通条件と道路工事の実施条件とに基づ
いて、道路工事が実施された場合の工事区間における交
通状況の予測を含む交通シミュレーションを行う交通シ
ミュレーション工程と、交通シミュレーション結果にお
いて交通渋滞情報が判定基準を充足するとき、当該工事
の実施条件及び基本仕様に基づいて施工計画を作成する
施工計画作成工程と、この施工計画作成工程にて作成さ
れた施工計画を含む道路使用許可申請を、支援要求元に
代って、当該道路の使用許可者へ提出する申請工程とを
備えている。
Further, the present invention is a method for supporting an application for a road occupation construction, which implements a construction for a road in accordance with a predetermined basic specification. Then, the basic specification receiving process of receiving the basic specification from the support request source, the traffic volume measured without road construction, the traffic conditions around the construction section where the road construction is performed, and the road construction implementation conditions A traffic simulation step of performing a traffic simulation including a prediction of traffic conditions in a construction section when road construction is performed, and, when traffic congestion information satisfies a determination criterion in a traffic simulation result, execution conditions of the construction and A construction plan creation process that creates a construction plan based on the basic specifications and a road use permission application that includes the construction plan created in this construction plan creation process And an application process for submission to

【0031】このように構成された道路占用工事の申請
支援方法においては、工事計画作成支援業者は、作成さ
れた施工計画を含む道路使用許可申請を、工事業者(支
援要求元)に代って、当該道路の使用許可者へ提出す支
援までを行う。したがって、工事業者である支援要求元
に対するサービスをより一層向上できる。
In the road occupation application application support method configured as described above, the construction plan preparation support contractor submits a road use permission application including the prepared construction plan on behalf of the construction contractor (support request source). And support for submitting to the road licensor. Therefore, the service to the support requester who is a construction contractor can be further improved.

【0032】さらに、別の発明は、上述した発明の道路
占用工事の申請支援方法における申請工程は、記支援要
求元に対して施工計画申請の許可を得た後、当該道路の
使用許可者への道路使用許可申請を行うようにしてい
る。
In another aspect of the invention, the application process in the application support method for road occupation construction of the invention described above includes, after obtaining permission for the execution plan application from the support requester, to the person who has authorized use of the road. To apply for permission to use the road.

【0033】さらに、別の発明は、上述した発明の道路
占用工事の申請支援方法における基本仕様受付工程は通
信ネットワークを介して基本仕様を受付ける。また、申
請工程は通信ネットワークを介して支援要求元に対して
施工計画申請の許可を得る。
Further, in another invention, the basic specification receiving step in the application support method for road occupation construction according to the above invention receives the basic specification via a communication network. In the application process, the permission of the construction request is obtained from the support requester via the communication network.

【0034】さらに、別の発明は、上述した発明の道路
占用工事の申請支援方法における申請工程は、道路使用
許可申請を通信ネットワークを介して道路の使用許可者
へ提出する。
According to another aspect of the invention, in the application supporting method for road occupation construction in the above-described invention, the application step submits a road use permission application to a road use permitter via a communication network.

【0035】また、本発明は、予め定められた基本仕様
に従って道路に対する工事を実施する道路占用工事の施
工計画を行うコンピュータ読取可能なプログラムを記録
した記録媒体である。そして、プログラムは、コンピュ
ータに対して、道路工事を実施しない状態で測定された
交通量と道路工事が実施される工事区間の周辺における
交通条件と道路工事の実施条件とに基づいて、道路工事
が実施された場合の工事区間における交通状況の予測を
含む交通シミュレーションを行なわせ、交通シミュレー
ション結果において交通渋滞情報が判定基準を充足する
とき、当該工事の実施条件及び基本仕様に基づいて施工
計画を作成させる。
Further, the present invention is a recording medium which records a computer-readable program for performing a construction plan of a road occupation construction for performing a construction on a road according to a predetermined basic specification. Then, based on the traffic volume measured without road construction and the traffic conditions around the construction section where the road construction is to be performed and the road construction implementation conditions, the program notifies the computer of the road construction. A traffic simulation including a prediction of the traffic situation in the construction section in the case of implementation is performed, and when the traffic congestion information satisfies the criteria in the traffic simulation result, a construction plan is created based on the implementation conditions and basic specifications of the construction. Let it.

【0036】また、別の発明は、上述した発明のプログ
ラムを記録した記録媒体に対して、さらに、コンピュー
タに対して、工事見積を作成させる。また、別の発明
は、上述した発明のプログラムを記録した記録媒体に対
して、さらに、コンピュータに対して、作成される施工
計画を最適化させる。
According to another aspect of the present invention, a construction estimate is created for a recording medium on which the program of the above-described invention is recorded and for a computer. Further, another invention optimizes a construction plan created for a recording medium on which the program of the above-described invention is recorded and further for a computer.

【0037】[0037]

【発明の実施の形態】以下、本発明の各実施形態を図面
を用いて説明する。 (第1実施形態)図1は、本発明の道路占用工事の施工
計画方法、施工計画方法、施工計画支援方法、申請支援
方法が適用される第1実施形態システムの概略構成を示
すブロック図である。
Embodiments of the present invention will be described below with reference to the drawings. (First Embodiment) FIG. 1 is a block diagram showing a schematic configuration of a first embodiment system to which a construction planning method, a construction planning method, a construction planning support method, and an application support method of a road occupation construction of the present invention are applied. is there.

【0038】この第1実施形態システムにおいては、ガ
ス会社や水道局等の工事発注者21、警察等の道路使用
許可者22、工事業者(支援要求元)23、工事計画作
成支援業者24が存在する。
In the first embodiment system, there are a work orderer 21 such as a gas company or a water bureau, a road use permitter 22 such as a police, a construction company (support request source) 23, and a construction plan creation support company 24. I do.

【0039】工事発注者21は、基本仕様作成部25
で、例えば配管工事の場合、配管の敷設位置(敷設地
図)、埋設深さ、管の種類や径等の基本仕様を作成す
る。この作成した基本仕様を工事の発注依頼と共に工事
業者23へ例えばインターネット等の通信ネットワーク
を介して送信する。なお、書面で手渡す場合もある。
The construction orderer 21 has a basic specification creating unit 25.
For example, in the case of piping work, basic specifications such as a pipe laying position (laying map), a burying depth, a pipe type and a diameter, and the like are created. The created basic specifications are transmitted to the construction company 23 via a communication network such as the Internet, together with a construction order request. It may be handed in writing.

【0040】道路使用許可者22は、工事業者23から
例えばインターネット等の通信ネットワークを介して送
信された道路使用許可申請に対して、申請判定部26で
可否判定を行い、申請許可の場合は、申請許可を工事業
者23へ応答し、申請不許可の場合は、申請不許可を工
事業者23へ応答する。なお、道路使用許可申請及び申
請判定結果を書面で手渡す場合もある。
The road use permitter 22 determines whether or not the road use permission application transmitted from the construction company 23 through a communication network such as the Internet is determined by the application determination unit 26. An application permission is returned to the construction contractor 23, and in the case of application rejection, an application non-permission is returned to the construction contractor 23. In some cases, the application for permission to use the road and the result of the application decision may be handed in writing.

【0041】工事業者23は、工事発注者21から基本
仕様を工事の発注依頼と共に受領すると、工事計画発注
部27が、工事計画作成支援業者24へ基本仕様と共に
工事計画作成依頼を、例えばインターネット等の通信ネ
ットワークを介して送信する。また、工事計画作成支援
業者24から、道路使用許可申請情報を受領すると、道
路使用許可申請部28が道路使用許可者22に対して、
道路使用許可申請を送信する。なお、これらの情報送受
を書面で手渡す場合もある。
When the construction company 23 receives the basic specifications from the construction orderer 21 together with a construction order request, the construction plan ordering section 27 sends a construction plan creation request to the construction plan creation support company 24 together with the basic specifications, for example, via the Internet or the like. Over the communication network. Also, when receiving the road use permission application information from the construction plan creation support company 24, the road use permission application unit 28
Send the road use permission application. In some cases, such information transmission / reception may be handed in writing.

【0042】さらに、工事業者23の施工部29は、道
路使用許可者22から道路使用許可を受領すると、工事
計画作成支援業者24から受領した施工計画に従って工
事を実施する。具体的には、具体的な工事指示を出力す
る。
Further, when the construction section 29 of the construction company 23 receives the road use permission from the road use permitter 22, the construction section 29 carries out the construction according to the construction plan received from the construction plan preparation support company 24. Specifically, a specific construction instruction is output.

【0043】工事計画作成支援業者24内には、例え
ば、コンピュータ等の情報処理装置で構成された、交通
シミュレーション部30、施工計画作成部31、見積作
成部32、申請情報作成部33等が設けられている。
In the construction plan creation support company 24, for example, a traffic simulation unit 30, a construction plan creation unit 31, an estimate creation unit 32, an application information creation unit 33, and the like, which are constituted by information processing devices such as computers, are provided. Have been.

【0044】なお、工事計画作成支援業者24が工事業
者23に代わって、道路使用許可者22に対して、直
接、道路使用許可申請を提出可能なように、代理申請部
34が設けられてている。
A proxy application unit 34 is provided so that the construction plan preparation support company 24 can directly submit a road use permission application to the road use permitter 22 on behalf of the construction company 23. I have.

【0045】図2は、交通シミュレーション部30の概
略構成を示すブロック図である。この交通シミュレーシ
ョン部30は、条件入力部35と演算処理部36とで構
成されている。条件入力部35には、実測交通量データ
ベース37から実測の交通量38が入力される。また、
地図データベース39から交通条件40が入力される。
さらに、前述した基本仕様41を参考にしてオペレータ
が設定した工事条件としての工事区間長42及び道路使
用時間情報43が入力される。なお、道路使用時間情報
43とは、施工に必要な工事区間を道路上に設置してい
る時間に関する情報である。
FIG. 2 is a block diagram showing a schematic configuration of the traffic simulation unit 30. The traffic simulation unit 30 includes a condition input unit 35 and an arithmetic processing unit 36. The measured traffic volume 38 from the measured traffic volume database 37 is input to the condition input unit 35. Also,
Traffic conditions 40 are input from the map database 39.
Further, a construction section length 42 and road use time information 43 as construction conditions set by the operator with reference to the basic specification 41 described above are input. The road use time information 43 is information relating to the time during which a construction section required for construction is installed on the road.

【0046】図3は、地図データベース39から読出し
た工事区間44を含む道路の道路形状、周囲の信号交差
点45、当該信号の信号周期等を含む交通条件を示す図
である、実測の交通量38とは、工事区間44が設定さ
れ、一方通行の工事用信号機47が設置されて、交通規
制が実施される以前に、この地図上の各道路を走行中の
各車両46の車種と位置と走行方向と速度との情報を含
む。この実測の交通量38は、例えば、地図上の各位置
に設置された車両センサで検出される。
FIG. 3 is a diagram showing the traffic shape including the road shape of the road including the construction section 44 read from the map database 39, the surrounding signal intersection 45, the signal cycle of the signal, and the like. Means that the construction section 44 is set, a one-way construction traffic light 47 is installed, and before the traffic regulation is enforced, the type, position, and traveling of each vehicle 46 traveling on each road on this map. Includes direction and speed information. The actually measured traffic volume 38 is detected, for example, by vehicle sensors installed at various positions on the map.

【0047】演算処理部36は、工事区間長42、道路
使用時間情報43に基づいて工事区間44が設定され交
通規制が実施された状態における交通量38で入力され
た各車両46の速度変化を算出する(R1)。次に、地
図上における各位置における車両46の平均速度を算出
する(R2)。この平均速度から地図上における各位置
における交通渋滞を算出する(R3)。
The arithmetic processing unit 36 calculates the speed change of each vehicle 46 input by the traffic volume 38 in the state where the construction section 44 is set based on the construction section length 42 and the road use time information 43 and the traffic regulation is performed. Calculate (R1). Next, the average speed of the vehicle 46 at each position on the map is calculated (R2). The traffic congestion at each position on the map is calculated from the average speed (R3).

【0048】交通シミュレーション部30は、このよう
な手順で算出した、工事区間44が設置された交通規制
を実施した場合に予測される交通渋滞情報57を出力す
る。
The traffic simulation unit 30 outputs the traffic congestion information 57 calculated according to such a procedure and predicted when traffic regulation in which the construction section 44 is installed is performed.

【0049】なお、上述した交通シミュレーション部3
0における交通シミュレーションの詳細動作は、発明者
等が特開平10―307983号公報に報告済みであ
る。
The traffic simulation unit 3 described above
The detailed operation of the traffic simulation at 0 is reported by the inventors in Japanese Patent Application Laid-Open No. Hei 10-307983.

【0050】図4は、施工計画作成部31の概略構成を
示すブロック図である。この実施形態で作成される施工
計画は、基本的に、図9で示した工事区間1と同様に、
図5に示すように、掘削2と、配管・溶接3と、検査・
埋め戻し4の3作業工程からなる作業帯と導流帯とから
なる工事区間44を、道路に沿って移動させていくこと
によって、基本仕様41が規定する工事が完了する。こ
こで、工事区間44を構成する掘削2と、配管・溶接3
と、検査・埋め戻し4の各工程の作業長さを合計した作
業帯長さと、導流帯との合計が該当工事区間44の工事
区間長42となる。
FIG. 4 is a block diagram showing a schematic configuration of the construction plan creating section 31. The construction plan created in this embodiment is basically similar to the construction section 1 shown in FIG.
As shown in FIG. 5, excavation 2, piping and welding 3, inspection and
By moving along the road the construction section 44 consisting of the work zone consisting of the three work steps of backfill 4 and the diversion zone, the construction specified by the basic specifications 41 is completed. Here, the excavation 2 constituting the construction section 44 and the piping / welding 3
The total of the work zone length obtained by adding the work lengths of the respective steps of the inspection and backfilling 4 and the diversion zone is the construction section length 42 of the construction section 44.

【0051】図4において、施工計画作成部31は、基
本仕様41全体の工事を計画する全体計画部49と、こ
の全体計画部49内に設けられ各工事区間44内の工事
を計画する個別計画部50と、この個別計画部50内に
設けられ、掘削2、配管・溶接3、検査・埋め戻し4の
各作業工程の工事を計画する工程別施工計画部51とで
構成されている。
In FIG. 4, a construction plan creating section 31 includes a general planning section 49 for planning the construction of the entire basic specification 41 and an individual planning section provided in the general planning section 49 for planning the construction in each construction section 44. A part 50 and a step-by-step construction planning part 51 which is provided in the individual planning part 50 and plans the construction of the respective work processes of excavation 2, piping / welding 3, and inspection / backfill 4.

【0052】この施工計画作成部31は、交通シミュレ
ーション部30から出力された交通渋滞情報57が判定
部48において、判定基準を充足する場合に起動する。
The construction plan creation section 31 is activated when the traffic congestion information 57 output from the traffic simulation section 30 satisfies the judgment criteria in the judgment section 48.

【0053】判定部48において、交通状態情報57に
含まれる通過時間、遅れ時間、待ち時間、待ち台数、及
び渋滞長さ等の渋滞の程度を表す情報(交通渋滞情報)
が、場所、交通状況及び実績データを勘案して予め設定
した判定基準を充足するか否かを判定する。
In the determination unit 48, information (traffic congestion information) indicating the degree of congestion such as the transit time, the delay time, the waiting time, the number of waiting units, and the congestion length included in the traffic state information 57.
Determines whether or not a predetermined criterion is satisfied in consideration of the place, the traffic situation, and the result data.

【0054】本実施形態では、上記渋滞の程度を表す情
報のうち、1部又は全部を用いて判定を行う。また、交
通渋滞情報の種別は、上記した通過時間等に限らず、他
の種類の情報を用いてもよい。判定は、交通渋滞情報と
判定基準との照合をコンピュータなどを用いて自動的に
行う。また、人が照合して行うこともある。
In the present embodiment, the determination is made using one or all of the information indicating the degree of the congestion. Further, the type of traffic congestion information is not limited to the above-described transit time and the like, and other types of information may be used. The judgment is made by automatically comparing the traffic congestion information with the judgment standard using a computer or the like. In some cases, the verification is performed by a person.

【0055】この施工計画作成部31が起動されると、
交通シミュレーション部30における条件入力部35に
現在時点で設定されている工事区間44、工事区間長4
2、道路使用時間情報43と、基本仕様41とを取り込
んで、工程別施工計画部51を起動する。
When the construction plan creating section 31 is started,
Construction section 44 and construction section length 4 currently set in the condition input section 35 of the traffic simulation section 30
2. The road use time information 43 and the basic specifications 41 are fetched, and the process-specific construction planning unit 51 is started.

【0056】工程別施工計画部51において、各工程作
業長さの設定部52において、前述した1つの工事区間
44の工事区間長42内における掘削2、配管・溶接
3、検査・埋め戻し4の各作業工程の作業長を決定す
る。そして、建設機械・車両の能力計画部53で、各作
業工程に必要な建設機械・車両の能力を決定する。ま
た、作業人員計画部54にて、各作業工程に必要な作業
人員、作業時間を決定する。
In the step-by-step construction planning section 51, the setting section 52 of each step work length sets the excavation 2, pipe / weld 3, and inspection / backfill 4 in the construction section length 42 of one construction section 44 described above. Determine the operation length of each operation process. Then, the capacity planning section 53 of the construction machine / vehicle determines the capacity of the construction machine / vehicle necessary for each work process. Further, the work staff planning unit 54 determines the work staff and work time required for each work process.

【0057】しかるのち、個別計画部50における建設
機械・車両・人員の配置計画部55にて、1つの工事区
間44の工事を実施するのに必要な建設機械・車両の種
類、台数、作業人員、作業時間等からなる個別計画を作
成する。そして、個別計画部50は作成した1つの工事
区間44に対する個別計画書58を出力する。
Thereafter, in the individual planning section 50, the type, number, and number of construction machines / vehicles required to carry out the construction of one construction section 44 are arranged by the placement planning section 55 of construction machines / vehicles / personnel. Create an individual plan consisting of work hours and so on. Then, the individual planning unit 50 outputs the created individual plan document 58 for one construction section 44.

【0058】個別計画部50で1つの工事区間44に対
する個別計画の作成が終了すると、全体計画部49にお
ける施工パターンの全体計画部56が起動して、基本仕
様41における未計画の部分が残っていれば、再度、個
別計画部50を起動して、次の工事区間44に対する個
別計画の作成を開始する。なお、次の工事区間44の交
通条件が前の工事区間44の交通条件に対してほぼ同一
と見なせる場合は、前回の交通シミュレーション結果を
そのまま採用する。
When the individual planning unit 50 completes the preparation of the individual plan for one construction section 44, the overall planning unit 56 of the construction pattern in the overall planning unit 49 starts, and the unplanned part in the basic specification 41 remains. Then, the individual planning unit 50 is started again, and the creation of the individual plan for the next construction section 44 is started. If the traffic conditions in the next construction section 44 can be considered to be substantially the same as the traffic conditions in the previous construction section 44, the previous traffic simulation result is used as it is.

【0059】施工パターンの全体計画部56は、基本仕
様41が指定した全部の配管に対する全工事区間44の
設定、各工事区間44における各個別計画の作成が終了
すると、基本仕様41に対する施工計画の作成を終了さ
せる。
When the setting of all construction sections 44 for all the pipes designated by the basic specifications 41 and the creation of each individual plan in each construction section 44 are completed, the overall planning section 56 of the construction pattern Finish the creation.

【0060】このようにして、作成された全体工事に対
する施工計画が最適か否かを評価部59で評価し、改良
の余地がある場合は、交通シミュレーション部30にお
ける条件入力部35に対する工事区間長42や道路使用
時間情報43等の工事の実施条件、又は、隣接交差点4
5の信号機の信号周期等の交通条件40を変更して交通
シミュレーションを再度実行する。そして、再度、施工
計画作成部31を起動して施工計画の最適化を図ること
が可能である。
The evaluation section 59 evaluates whether or not the construction plan for the entire construction created in this way is optimal. If there is room for improvement, the construction section length to the condition input section 35 in the traffic simulation section 30 is evaluated. 42 or road use time information 43, etc., or the intersection 4
The traffic simulation such as the signal period of the traffic light 5 is changed and the traffic simulation is executed again. Then, the construction plan creation unit 31 can be activated again to optimize the construction plan.

【0061】この場合、評価部59は、作成された施工
計画を実施した場合における交通渋滞の程度、全体の工
事期間、全体の工事費用がバランス良く最小になる施工
計画を最適の施工計画と判断し、施工計画書60を出力
する。
In this case, the evaluation unit 59 determines the construction plan that minimizes the degree of traffic congestion, the entire construction period, and the total construction cost in a well-balanced manner when the created construction plan is implemented, as the optimal construction plan. Then, the construction plan 60 is output.

【0062】例えば、交通シミュレーション部30にお
ける条件入力部35に設定する道路使用時間情報43等
の工事の実施条件としては、図6に示す(a)〜(g)
の7種類の実施条件がある。
For example, the construction execution conditions such as the road use time information 43 set in the condition input unit 35 in the traffic simulation unit 30 are shown in FIGS. 6A to 6G.
There are seven types of implementation conditions.

【0063】道路使用時間情報とは、施工に必要な工事
区間を道路上に設置している時間に関する情報である。
例えば(a)の実施条件においては、図3に示す地図に
おいて、一方の信号交差点45から他方の信号交差点4
5までの道路区間全体において昼夜を通した常設の工事
区間とし、この場合の道路使用時間は24時間である。
The road use time information is information on the time during which a construction section required for construction is installed on the road.
For example, under the implementation condition of (a), in the map shown in FIG.
The entire road section up to 5 is a permanent construction section throughout the day and night, and the road usage time in this case is 24 hours.

【0064】また、(b)の実施条件においては、各信
号交差点近傍は交通渋滞が発生する可能性が高いため、
昼間の工事区間とし、この部分の道路使用時間は午前9
時から午後5までの8時間である。残りの部分は常設の
工事区間なので、道路使用時間は24時間である。
In the condition (b), traffic congestion is likely to occur near each signalized intersection.
It is a daytime construction section, and the road usage time in this part is 9 am
8 hours from time to 5 pm. Since the remaining part is a permanent construction section, the road usage time is 24 hours.

【0065】さらに、最後の(g)の実施条件において
は、一方の信号交差点45から他方の信号交差点45ま
での道路区間全体を夜間だけの工事区間とし、この場合
の道路使用時間は通常午後8時から翌日午前6までの1
0時間である。
Further, in the last implementation condition (g), the entire road section from one signalized intersection 45 to the other signalized intersection 45 is a construction section only at night, and the road use time in this case is usually 8 pm 1 from time to 6 am the next day
0 hours.

【0066】このような信号交差点間の道路区間全体に
おける常設、昼間、及び夜間の工事区間の配置も道路使
用時間情報に含まれる。すなわち、図6(b)(c)
(d)(f)のように複数種類の工事形態(常設、昼
間、夜間)が合わされる場合には、道路使用時間情報は
複数の道路使用時間と上記工事形態の情報を有すること
になる。
The arrangement of the permanent, daytime and nighttime construction sections in the entire road section between signalized intersections is also included in the road use time information. That is, FIGS. 6B and 6C
When a plurality of types of construction forms (permanent, daytime, nighttime) are combined as in (d) and (f), the road use time information has a plurality of road use times and information on the construction form.

【0067】すなわち、交通規制を必要とする一般的な
埋設管敷設工事では、前述したように掘削2、配管溶接
3、検査埋戻し4の3つ作業工程からなる。それぞれの
作業工程の作業帯長さを長く設定することにより、工事
進捗率を上げることが可能である。また、作業帯長さを
長く設定することにより、大型建設機械の導入が可能と
なるために施工の効率化が図れる。
That is, a general buried pipe laying work that requires traffic regulation includes three working steps of excavation 2, pipe welding 3, and inspection backfill 4 as described above. By setting the length of the work zone of each work process to be long, it is possible to increase the construction progress rate. In addition, by setting the length of the work zone long, it becomes possible to introduce a large-sized construction machine, so that the efficiency of construction can be improved.

【0068】しかし、交通量の多い場所においては、図
6(g)に示すように、夜間工事となる場合があるが、
夜間工事は施工能率の低下や騒音等の問題が大きく、そ
の対策を含め高コストな施工となる.。一般的な道路交
通は朝夕に交通量の多い時間帯が集中している。そこ
で、交通シミュレーションを用いて工事開始時刻及び工
事終了時刻を設定することにより、交通量の多い時間帯
を避け、交通量の多い場所においても昼間の工事が可能
となる。
However, in places with heavy traffic, nighttime work may be required as shown in FIG.
Nighttime construction is a major problem, such as reduced construction efficiency and noise. General road traffic is concentrated in the morning and evening when traffic is heavy. Therefore, by setting a construction start time and a construction end time using a traffic simulation, daytime construction is possible even in a place with a large traffic volume, avoiding a time zone with a large traffic volume.

【0069】1日単位で完全に埋戻す即日復旧工事で
は、各工程の施工能力を十分に発揮するためにはある程
度の長さの工事区間長42が必要となる。そこで、交通
量の少ない時間帯には長めの工事区間長42を設置し、
交通量の増加する時間帯では施工をしないか、あるいは
可能な限り工事区間長42を縮小することにより、渋滞
の発生を最小限に.抑制しつつ、効率的な施工が可能と
なる。
In the same-day restoration work in which land is completely backfilled in one-day units, a work section length 42 of a certain length is required in order to sufficiently exercise the construction capacity of each process. Therefore, a longer construction section length 42 is set up during times of light traffic,
Efficient construction is possible while minimizing the occurrence of congestion by not performing construction or reducing the construction section length 42 as much as possible during times of increased traffic.

【0070】さらに、1日24時間を通して交通渋滞を
引き起こす交通量に至らない場所においては、図6
(a)に示すように、常設の工事区間による施工方法を
採用することにより、掘削2、埋戻し4工程を大幅に縮
小でき、建設機械の移動の手間も省くことができるた
め、大幅な施工効率の向上を図れる。
Further, in a place where traffic volume causing traffic congestion does not reach throughout 24 hours a day,
As shown in (a), by adopting the construction method based on the permanent construction section, the excavation 2 and backfill 4 processes can be greatly reduced, and the labor for moving the construction equipment can be reduced, so that the construction is greatly performed. The efficiency can be improved.

【0071】さらに、夜間工事、昼間工事、常設工事等
の施工方法の選択には、前述のとおり交通量が重要な基
準になる。一般的に夜間工事から昼間工事、さらに常設
工事となるにつれ施工効率の向上が見込まれる。
Furthermore, traffic volume is an important criterion for selecting construction methods such as night work, daytime work, permanent work and the like, as described above. In general, improvement in construction efficiency is expected as night work becomes day work and then permanent work.

【0072】表1に、工事区間長と、夜間工事、昼間工
事、常設工事の各施工時間における配管進捗率(1日当
たりの敷設延長)を示す。当然、常設工事でかつ工事区
間長が長い方が配管進捗率は高い。
Table 1 shows the construction section lengths and the pipe progress rate (lengthening of laying per day) at each construction time of night work, daytime work and permanent work. Naturally, the progress rate of piping is higher for permanent works and longer work sections.

【0073】[0073]

【表1】 [Table 1]

【0074】信号交差点45に近接する場所において
は、単に交通量だけでなく信号周期や工事区間以外の道
路の交通量、さらに交差点において左折又は右折する車
両の割合により、混雑の度合いが変わる。このため、信
号交差点45に近接する場所において工事を実施する場
合には、交差点の影響がない場所に比べ、工事時間帯の
選択や工事区間長さに対し条件が厳しくなる場合が一般
的である。
At a place close to the signalized intersection 45, the degree of congestion varies depending not only on the traffic volume, but also on the signal period, the traffic volume on roads other than the construction section, and the ratio of vehicles turning left or right at the intersection. For this reason, when the construction is performed in a place close to the signalized intersection 45, the conditions for selection of construction time zone and construction section length are generally stricter than in a place where there is no influence of the intersection. .

【0075】そして、図4の施工計画作成部31におけ
る評価部59で最適と判断された施工計画を施工計画書
60として出力する。
Then, the construction plan determined to be optimal by the evaluation unit 59 in the construction plan creation unit 31 of FIG.

【0076】図7は、工事業者23及び工事計画作成支
援業者24が実施する処理全体を示す流れ図である。
FIG. 7 is a flowchart showing the entire processing performed by the construction company 23 and the construction plan creation support company 24.

【0077】工事業者23が工事発注者21から基本仕
様41を指定した工事の引き合いを受けると(Q1)、
この基本仕様41を付して工事計画作成支援業者24へ
施工計画の作成依頼を送出する。工事計画作成支援業者
24においては、この基本仕様41に対する概略の施工
計画を、前述した交通シミュレーション部30及び施工
計画作成部31を用いて作成する(Q2、Q3、Q
4)。
When the construction contractor 23 receives an inquiry for the construction designating the basic specification 41 from the construction orderer 21 (Q1),
A request for creating a construction plan is sent to the construction plan creation support company 24 with the basic specification 41 attached. The construction plan creation support company 24 creates a rough construction plan for the basic specification 41 using the traffic simulation unit 30 and the construction plan creation unit 31 described above (Q2, Q3, Q
4).

【0078】次に、見積作成部32にて、概略の施工計
画に対する工事費用の見積を算出して見積書を作成し
て、工事業者23へ送信する(Q5)。工事業者23は
その見積書を確認して、この工事を正式に受注し(Q
6)、工事計画作成支援業者24へ詳細な施工計画の作
成依頼を送付する(Q7)。
Next, the estimate creating section 32 calculates an estimate of the construction cost for the rough construction plan, creates an estimate, and sends it to the construction company 23 (Q5). The contractor 23 confirms the estimate and receives an order for this construction (Q
6), a request for creating a detailed construction plan is sent to the construction plan creation support company 24 (Q7).

【0079】工事計画作成支援業者24においては、先
の基本仕様41に対する詳細な施工計画を、前述した交
通シミュレーション部30及び施工計画作成部31を用
いて作成する(Q8、Q9)。
The construction plan creation support company 24 creates a detailed construction plan for the basic specification 41 using the traffic simulation unit 30 and the construction plan creation unit 31 (Q8, Q9).

【0080】基本仕様(Q2)では、交通シミュレーシ
ョンと計画シミュレーションにより個別の工事区間に対
して最適な計画を作成するのに必要な周辺状況などの情
報がない場合が多く、詳細な検討はできない。但し、最
小限の情報や仮定に基づいて交通シミュレーション及び
計画シミュレーション(Q3)を行うことにより、概算
施工計画(Q4)段階で施工期間の短縮あるいは施工費
用の低減を考慮した計画の作成が可能であり、見積(Q
5)に反映できる。
In the basic specification (Q2), there are many cases where there is no information such as the surrounding conditions necessary for creating an optimal plan for each construction section by the traffic simulation and the plan simulation, and a detailed study cannot be made. However, by performing traffic simulation and planning simulation (Q3) based on the minimum information and assumptions, it is possible to create a plan in consideration of shortening the construction period or reducing construction costs at the approximate construction plan (Q4) stage. Yes, estimate (Q
5) can be reflected.

【0081】また、詳細設計(Q7)を実施する段階で
は、工事区間の周辺状況なども明らかになり、必要な情
報については調査も可能になるため、交通シミュレーシ
ョンと計画シミュレーション(Q8)を繰り返し実施す
ることにより、施工計画の最適化を図れる。なお、本明
細書では、この交通シミュレーションと計画シミュレー
ションを繰り返し実施すること自体も施工計画最適化と
称する。
At the stage of the detailed design (Q7), the surrounding conditions of the construction section are clarified, and necessary information can be investigated. Therefore, the traffic simulation and the planning simulation (Q8) are repeatedly performed. By doing so, the construction plan can be optimized. In the present specification, the repeated execution of the traffic simulation and the plan simulation itself is also referred to as construction plan optimization.

【0082】基本仕様41に対する詳細な施工計画が得
られると、申請情報作成部32にて、この施工計画と交
通シミュレーション結果の交通渋滞の情報を付した道路
使用許可申請情報を作成して(Q10)、工事業者23
へ送信する。工事業者23の道路使用許可申請部28が
起動して道路使用許可者22へ道路使用許可申請を行う
(Q11)。
When a detailed construction plan for the basic specifications 41 is obtained, the application information creating unit 32 creates road use permission application information to which information of the construction plan and traffic congestion as a result of the traffic simulation is added (Q10). ), Contractor 23
Send to The road use permission application unit 28 of the construction company 23 is activated to apply for a road use permission to the road use permitter 22 (Q11).

【0083】なお、工事計画作成支援者24が、工事業
者23に代って道路使用許可者22に対して、道路使用
許可申請を行う場合は、道路使用許可申請情報を作成し
て工事業者23へ送信して、工事業者23から申請許可
の通知を受領した後、代理申請部34が道路使用許可者
22に対して、道路使用許可申請を行う。
When the construction plan preparation supporter 24 makes a road use permission application to the road use permitter 22 on behalf of the construction company 23, the road use permission application information is created and the construction company 23 After receiving the notification of the application permission from the construction contractor 23, the proxy application unit 34 makes a road use permission application to the road use permitter 22.

【0084】工事業者23において、道路使用許可者2
2から申請に対する許可が下りると(Q12)、施工部
29が起動して、工事を施工する。具体的には、施工計
画に基づいて細かい作業指示を出力する(Q13)。な
お、申請不許可の場合は、道路使用許可申請部28が再
度、交通シミュレーション部30及び施工計画作成部3
1を用いて施工計画を作成する。工事が完了すると、完
了報告を工事発注者21へ送出する(Q14)。
In the construction company 23, the road use permitter 2
When permission for the application is obtained from 2 (Q12), the construction unit 29 is activated to carry out construction. Specifically, a detailed work instruction is output based on the construction plan (Q13). If the application is not permitted, the road use permission application unit 28 again executes the traffic simulation unit 30 and the construction plan creation unit 3
The construction plan is created using 1. When the construction is completed, a completion report is sent to the construction orderer 21 (Q14).

【0085】このように構成された道路占用工事におけ
る施工方法、施工計画方法、施工計画支援方法、申請支
援方法においては、ガス会社や水道局等の道路工事の発
注者21が基本仕様41を指定して道路工事を工事業者
23に発注すると、工事業者23は工事計画作成支援業
者24へ基本仕様41を指定して道路工事の施工計画の
作成依頼を送出する。
In the construction method, construction planning method, construction plan support method, and application support method in the road private construction constructed as described above, the orderer 21 of the road construction, such as a gas company or the water bureau, specifies the basic specification 41. When the road construction is ordered from the construction contractor 23, the construction contractor 23 sends a request for creating a construction plan for the road construction to the construction plan preparation support contractor 24 by designating the basic specifications 41.

【0086】工事計画作成支援業者24の交通シミュレ
ーション部30が、測定された工事区間44が設定され
る前の交通量38と、現場周辺の交通条件40と、工事
区間長42や道路使用時間情報43の工事の実施条件と
を用いて、工事区間44が設定された状態の現場周辺の
交通シミュレーションを実施して、工事区間44が設定
されたことに起因する交通渋滞情報57を求める。
The traffic simulation unit 30 of the construction plan creation support company 24 calculates the traffic volume 38 before the measured construction section 44 is set, the traffic conditions 40 around the site, the construction section length 42 and the road use time information. The traffic simulation around the site where the construction section 44 is set is performed by using the execution conditions of the construction section 43 and the traffic congestion information 57 resulting from the setting of the construction section 44 is obtained.

【0087】そして、この交通渋滞情報57が判定基準
を充足する場合に、施工計画作成部31で該当工事に対
する施工計画を作成して工事業者23へ送る。工事業者
23は、この施工計画と、交通渋滞情報が判定基準を充
足すことを示す交通シミュレーション結果とを、道路使
用許可申請として、道路使用許可者22へ提出する。
When the traffic congestion information 57 satisfies the judgment criteria, the construction plan creation section 31 creates a construction plan for the construction and sends it to the construction contractor 23. The contractor 23 submits the construction plan and a traffic simulation result indicating that the traffic congestion information satisfies the determination criteria to the road use permitter 22 as a road use permission application.

【0088】道路使用許可者22は、交通規制を伴う工
事区間44が設定された場合における交通渋滞の発生の
有無、発生の程度を定量的に推測できるので、渋滞によ
る社会的影響と経済的影響とを勘案して、道路使用許可
申請に対する許可・不許可の判断を正確にできる。その
結果、渋滞を最小にすることができ、あるいは、施工期
間を最小にできるので、道路工事による社会的影響と経
済的影響とを小さくできる。
The road use permitter 22 can quantitatively estimate whether or not traffic congestion has occurred and the extent of the traffic congestion when the construction section 44 with traffic regulation is set. In consideration of the above, it is possible to accurately determine whether to permit or reject a road use permit application. As a result, traffic congestion can be minimized or the construction period can be minimized, so that the social and economic impacts of road construction can be reduced.

【0089】例えば、従来の実績よりも長い工事区間を
設定しても、渋滞の程度がそれほど悪くならないと予測
された場合には、その長い工事区間を設定して、施工期
間を短くすることで、かえって、社会的、経済的影響を
小さくできる。
For example, if it is predicted that the degree of congestion will not be so bad even if a construction section longer than the conventional construction section is set, the longer construction section is set and the construction period is shortened. On the contrary, the social and economic impact can be reduced.

【0090】工事業者23は、施工効率の高い長い工事
区間長さで道路工事を施工することに対して道路使用許
可されるので、施工期間及び施工コストを低減すること
ができる。
The construction company 23 is permitted to use the road for constructing a road with a long construction section length having a high construction efficiency, so that the construction period and the construction cost can be reduced.

【0091】また、工事業者23にとっても、工事区間
44が設定された状態の現場周辺の交通シミュレーショ
ンが正確に実施できるので、図6(a)〜(g)に示す
ように、工事区間44の工事区間長42や道路使用時間
情報43の実施条件を細かく設定して、極力渋滞が発生
しないように調整することが可能である。
Further, since the construction contractor 23 can accurately perform the traffic simulation around the site where the construction section 44 is set, as shown in FIGS. It is possible to finely set the execution conditions of the construction section length 42 and the road use time information 43 so as to adjust the traffic congestion as little as possible.

【0092】(第2実施形態)図8は本発明の道路占用
工事の施工方法、施工計画方法が適用される第2実施形
態システムの概略構成を示すブロック図である。図1に
示す第1実施形態システムと同一部分には同一符号が付
してある。したがって、重複する部分の詳細説明は省略
する。
(Second Embodiment) FIG. 8 is a block diagram showing a schematic configuration of a second embodiment system to which a construction method and a construction planning method of a road occupation construction according to the present invention are applied. The same parts as those in the first embodiment shown in FIG. 1 are denoted by the same reference numerals. Therefore, the detailed description of the overlapping part will be omitted.

【0093】この第2実施形態システムにおいては、ガ
ス会社や水道局等の工事発注者21、警察等の道路使用
許可者22、工事業者23が存在する。しかし、この第
2実施形態システムにおいては、図1に示した第1実施
形態システムにおける工事計画作成支援業者24は存在
しない。すなわち、第1実施形態システムにおける工事
計画作成支援業者24が実行していた施工計画作成機能
を含む全ての機能は工事業者24が自己内で実施する。
In the system of the second embodiment, there are a work orderer 21 such as a gas company or a waterworks bureau, a road use permitter 22 such as a police, and a construction company 23. However, in the second embodiment system, there is no construction plan creation support company 24 in the first embodiment system shown in FIG. That is, all functions including the construction plan creation function executed by the construction plan creation support company 24 in the first embodiment system are performed by the construction company 24 within itself.

【0094】すなわち、工事業者24内には、交通シミ
ュレーション部30、施工計画作成部31、見積作成部
32、申請情報作成部32、道路使用許可申請部28、
施工部29等が設けられている。
That is, in the construction company 24, the traffic simulation unit 30, the construction plan creation unit 31, the estimate creation unit 32, the application information creation unit 32, the road use permission application unit 28,
A construction section 29 and the like are provided.

【0095】このように構成された第2実施形態システ
ムにおいて、工事業者24は、基本仕様を指定した工事
を受注すると、施工計画の作成依頼を外部に発注するこ
となく、自己内に設置された交通シミュレーション部3
0、施工計画作成部31で施工計画を作成して、道路使
用許可申請情報を作成して、道路使用許可申請部28で
道路使用許可者22に対して、道路使用許可申請を実施
する。そして、道路使用許可がおりると、施工部29で
該当工事が施工される。
In the system according to the second embodiment configured as described above, when a contractor 24 receives an order for a work in which the basic specifications are designated, the contractor 24 is installed in the self without requesting a construction plan creation request from the outside. Traffic simulation part 3
0. A construction plan is created by the construction plan creation unit 31, road use permission application information is created, and a road use permission application is performed by the road use permission application unit 28 to the road use permitter 22. Then, when the road use permission is given, the construction unit 29 performs the corresponding construction.

【0096】このように構成された第2実施形態システ
ムにおいても、交通シミュレーション部30及び施工計
画作成部31を用いて施工計画を作成するので、第1実
施形態システムとほぼ同様の作用効果を奏することがで
きる。
In the system of the second embodiment configured as described above, the construction plan is created by using the traffic simulation unit 30 and the construction plan creation unit 31, so that substantially the same operation and effect as in the system of the first embodiment can be obtained. be able to.

【0097】なお、上述した各実施形態システムにおい
て記載した手法は、コンピュータに実行させることので
きるプログラムとして、例えば磁気ディスク(フロッピ
ー(登録商標)ディスク、ハードディスク等)、光ディ
スク(CD−ROM、DVD等)、半導体メモリなどの
記録媒体に書込んで工事業者23や工事計画作成支援業
者24に適用したり、通信媒体により伝送して各種装置
に適用することも可能である。本装置を実現するコンピ
ュータは、記録媒体に記録されたプログラムを読込み、
プログラムによって動作が制御されることにより、上述
した処理を実行する。
Note that the method described in each of the above-described embodiment systems is, for example, a magnetic disk (floppy (registered trademark) disk, hard disk, etc.), an optical disk (CD-ROM, DVD, etc.) as a program that can be executed by a computer. ), It is also possible to write the data on a recording medium such as a semiconductor memory and apply it to the construction company 23 or the construction plan creation support company 24, or transmit the data via a communication medium and apply it to various devices. A computer that realizes the present apparatus reads a program recorded on a recording medium,
The above-described processing is executed by controlling the operation by the program.

【0098】[0098]

【発明の効果】以上説明したように、本発明の道路占用
工事における施工方法、施工計画方法、施工計画支援方
法、申請支援方法、及び施工計画を行うコンピュータ読
取可能なプログラムを記録した記録媒体においては、実
際に測定された交通量を用いた工事区間周辺の交通シミ
ュレーションを行なっている。したがって、実際に道路
工事を実施している状態の渋滞発生の有無及び渋滞の程
度を推定でき、工事に起因する障害を最小限に抑制し、
かつ工事を効率的に実施できる。
As described above, the construction method, construction plan method, construction plan support method, application support method, and computer readable program for performing the construction plan in the road occupation construction work of the present invention are described above. Performs a traffic simulation around the construction section using the actually measured traffic volume. Therefore, it is possible to estimate the occurrence of traffic congestion and the degree of traffic congestion in the state where road construction is actually being carried out, minimizing obstacles caused by construction,
And construction can be carried out efficiently.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の道路占用工事の施工方法及び計画方法
が適用される第1実施形態システムの概略構成を示すブ
ロック図
FIG. 1 is a block diagram showing a schematic configuration of a system according to a first embodiment to which a construction method and a planning method of a road occupation construction according to the present invention are applied;

【図2】同第1実施形態システムに組込まれた交通シミ
ュレーション部の概略構成を示すブロック図
FIG. 2 is a block diagram showing a schematic configuration of a traffic simulation unit incorporated in the system of the first embodiment;

【図3】工事区間周辺の地図Fig. 3 Map around the construction section

【図4】同第1実施形態システムに組込まれた施工計画
作成部の概略構成を示すブロック図
FIG. 4 is a block diagram showing a schematic configuration of a construction plan creation unit incorporated in the system of the first embodiment;

【図5】工事区間と各作業工程を示す図FIG. 5 is a diagram showing a construction section and each work process.

【図6】各工事区間と施工時間との関係を示す図FIG. 6 is a diagram showing a relationship between each construction section and construction time.

【図7】同第1実施形態システム全体の処理動作を示す
流れ図
FIG. 7 is a flowchart showing the processing operation of the entire system of the first embodiment;

【図8】本発明の道路占用工事の施工方法及び計画方法
が適用される第2実施形態システムの概略構成を示すブ
ロック図
FIG. 8 is a block diagram showing a schematic configuration of a second embodiment system to which a construction method and a planning method for road occupation work of the present invention are applied.

【図9】一般的な工事区間の見取り図Fig. 9 Floor plan of a general construction section

【図10】従来の工事業者が実施する道路使用申請処理
手順を示す流れ図
FIG. 10 is a flowchart showing a procedure for processing a road use application performed by a conventional construction company.

【符号の説明】[Explanation of symbols]

21…工事発注者 22…道路使用許可者 23…工事業者 24…工事計画作成支援業者 25…基本仕様作成部 26…申請判定部 27…工事計画発注部 28…道路使用許可申請部 29…施工部 30…交通シミュレーション部 31…施工計画作成部 32…見積作成部 33…申請情報作成部 34…代理申請部 35…条件入力部 36…演算処理部 38…交通量 40…交通条件 41…基本仕様 42…工事区間長 43…道路使用時間情報 44…工事区間 45…信号機交差点 46…車両 21 ... Constructor 22 ... Road use permit 23 ... Constructor 24 ... Construction plan creation support supplier 25 ... Basic specification creation section 26 ... Application determination section 27 ... Construction plan order section 28 ... Road use permission application section 29 ... Construction section DESCRIPTION OF SYMBOLS 30 ... Traffic simulation part 31 ... Construction plan creation part 32 ... Estimation creation part 33 ... Application information creation part 34 ... Proxy application part 35 ... Condition input part 36 ... Operation processing part 38 ... Traffic volume 40 ... Traffic condition 41 ... Basic specifications 42 ... Construction section length 43 ... Road use time information 44 ... Construction section 45 ... Signal intersection 46 ... Vehicle

Claims (21)

【特許請求の範囲】[Claims] 【請求項1】 予め定められた基本仕様に従って道路に
対する工事を実施する道路占用工事の施工方法におい
て、 道路工事を実施しない状態で測定された交通量と前記道
路工事が実施される工事区間の周辺における交通条件と
前記道路工事の実施条件とに基づいて、前記道路工事が
実施された場合の前記工事区間における交通状況の予測
を含む交通シミュレーションを行う交通シミュレーショ
ン工程と、 前記交通シミュレーション結果において交通渋滞情報が
判定規準を充足するとき、当該工事の実施条件及び前記
基本仕様に基づいて施工計画を作成する施工計画作成工
程と、 この作成された施工計画に基づいて道路工事を実施する
施工工程とを備えた道路占用工事の施工方法。
1. A road occupation construction method for constructing a road in accordance with a predetermined basic specification, comprising: a traffic volume measured in a state where the road construction is not performed; A traffic simulation step of performing a traffic simulation including prediction of a traffic situation in the construction section when the road construction is performed, based on the traffic conditions in the road construction and the execution conditions of the road construction. When the information satisfies the judgment criterion, a construction plan creation step of creating a construction plan based on the execution conditions of the construction and the basic specifications, and a construction step of performing a road construction based on the created construction plan Construction method of road private construction work equipped.
【請求項2】 前記周辺における交通条件は工事区間を
含む道路の道路形状、周囲の信号位置及び当該信号の信
号周期とを含み、 前記工事の実施条件は工事占有長さ及び道路使用時間情
報を含むことを特徴とする請求項1記載の道路占用工事
の施工方法。
2. The traffic condition in the surroundings includes a road shape of a road including a construction section, a surrounding signal position, and a signal cycle of the signal, and the execution condition of the construction includes construction occupation length and road use time information. The construction method for road occupation work according to claim 1, wherein the method includes:
【請求項3】 前記交通シミュレーション結果における
交通渋滞情報は、通過時間、遅れ時間、待ち時間、待ち
台数、又は渋滞長さのうちいずれか1以上を含むことを
特徴とする請求項1又は2記載の道路占用工事の施工方
法。
3. The traffic congestion information in the traffic simulation result includes at least one of a transit time, a delay time, a waiting time, a number of waiting units, and a congestion length. Construction method of road private use construction.
【請求項4】 前記施工計画作成工程にて作成された施
工計画を含む道路使用許可申請を当該道路の使用許可者
へ提出する申請工程を備えたことを特徴とする請求項1
から3のいずれか1項記載の道路占用工事の施工方法。
4. The method according to claim 1, further comprising an application step of submitting a road use permission application including the construction plan created in the construction plan creation step to a person permitted to use the road.
4. The construction method for road occupation construction according to any one of items 3 to 3.
【請求項5】 前記道路使用許可申請には、前記交通シ
ミュレーション結果の交通渋滞情報も含むことを特徴と
する請求項4記載の道路占用工事の施工方法。
5. The method according to claim 4, wherein the road use permission application also includes traffic congestion information obtained as a result of the traffic simulation.
【請求項6】 前記申請工程は、前記道路使用許可申請
を通信ネットワークを介して前記道路の使用許可者へ提
出することを特徴とする請求項4又は5記載の道路占用
工事の施工方法。
6. The road occupation construction method according to claim 4, wherein the application step submits the road use permission application to a road use permitter via a communication network.
【請求項7】 前記施工計画作成工程にて作成された施
工計画に基づいて前記基本仕様に対する工事見積を作成
する見積工程を備えたことを特徴とする請求項1から6
のいずれか1項記載の道路占用工事の施工方法。
7. The method according to claim 1, further comprising an estimation step of creating a construction estimate for the basic specifications based on the construction plan created in the construction plan creation step.
The construction method for road occupation work according to any one of the preceding claims.
【請求項8】 前記周辺の交通条件と前記工事の実施条
件とのうち少なくとも一方の条件を変更しつつ、前記シ
ミュレーション工程及び前記施工計画作成工程を繰返し
実行し、前記施工工程で実施される施工計画を最適化す
る施工計画最適化工程を備えたことを特徴とする請求項
1から7のいずれか1項記載の道路占用工事の施工方
法。
8. The construction performed in the construction step by repeatedly executing the simulation step and the construction plan creation step while changing at least one of the surrounding traffic conditions and the execution condition of the construction. Claims characterized by comprising a construction plan optimization process for optimizing the plan.
8. The construction method for road occupation work according to any one of 1 to 7.
【請求項9】 前記計画最適化工程は、前記基本仕様を
実現させるに要する工事全体の施工期間が最小となるよ
うに、及び又は、施工コストが最小となるように前記施
工工程で実施される施工計画を最適化することを特徴と
する請求項8記載の道路占用工事の施工方法。
9. The plan optimization step is performed in the construction step so that the construction period of the entire construction required to realize the basic specifications is minimized and / or the construction cost is minimized. 9. The construction method for road occupation work according to claim 8, wherein the construction plan is optimized.
【請求項10】 予め定められた基本仕様に従って道路
に対する工事を実施する道路占用工事の施工計画方法に
おいて、 道路工事を実施しない状態で測定された交通量と前記道
路工事が実施される工事区間の周辺における交通条件と
前記道路工事の実施条件とに基づいて、前記道路工事が
実施された場合の前記工事区間における交通状況の予測
を含む交通シミュレーションを行う交通シミュレーショ
ン工程と、 前記交通シミュレーション結果において交通渋滞情報が
判定基準を充足するとき、当該工事の実施条件及び前記
基本仕様に基づいて施工計画を作成する施工計画作成工
程とを備えた道路占用工事の施工計画方法。
10. A construction planning method for a road occupation construction in which construction is performed on a road in accordance with a predetermined basic specification, comprising: a traffic volume measured in a state where the road construction is not performed; A traffic simulation step of performing a traffic simulation including a prediction of a traffic condition in the construction section when the road construction is performed, based on the traffic conditions in the surroundings and the execution conditions of the road construction; A construction planning method for road private construction, comprising: a construction plan creation step of creating a construction plan based on the execution conditions of the construction and the basic specifications when the traffic congestion information satisfies a determination criterion.
【請求項11】 前記施工計画作成工程にて作成された
施工計画に基づいて前記基本仕様に対する工事見積を作
成する見積工程を備えたことを特徴とする請求項10記
載の道路占用工事の施工計画方法。
11. The construction plan for road occupation work according to claim 10, further comprising an estimation step of creating a construction estimate for the basic specification based on the construction plan created in the construction plan creation step. Method.
【請求項12】 前記周辺の交通条件と前記工事の実施
条件とのうち少なくとも一方の条件を変更しつつ、前記
シミュレーション工程及び前記施工計画作成工程を繰返
し実行し、作成される施工計画を最適化する施工計画最
適化工程を備えたことを特徴とする請求項10又は11
記載の道路占用工事の施工計画方法。
12. The simulation step and the execution plan creation step are repeatedly performed while changing at least one of the surrounding traffic conditions and the execution condition of the construction to optimize the execution plan to be created. 12. The construction plan optimizing step of:
The construction planning method for the road occupation work described.
【請求項13】 予め定められた基本仕様に従って道路
に対する工事を実施する道路占用工事の施工計画支援方
法において、 支援要求元から前記基本仕様を受付ける基本仕様受付工
程と、 道路工事を実施しない状態で測定された交通量と前記道
路工事が実施される工事区間の周辺における交通条件と
前記道路工事の実施条件とに基づいて、前記道路工事が
実施された場合の前記工事区間における交通状況の予測
を含む交通シミュレーションを行う交通シミュレーショ
ン工程と、 前記交通シミュレーション結果において交通渋滞情報が
判定基準を充足するとき、当該工事の実施条件及び前記
基本仕様に基づいて施工計画を作成する施工計画作成工
程と、 この施工計画作成工程で作成された施工計画を前記支援
要求元へ引渡す施工計画引渡工程とを備えた道路占用工
事の施工計画支援方法。
13. A method for supporting a construction plan of a road occupation construction for performing construction on a road in accordance with a predetermined basic specification, comprising: a basic specification receiving step of receiving the basic specification from a support request source; Based on the measured traffic volume and the traffic conditions around the construction section where the road construction is performed and the execution conditions of the road construction, predict the traffic condition in the construction section when the road construction is performed. A traffic simulation step of performing a traffic simulation including: when the traffic congestion information satisfies a determination criterion in the traffic simulation result, a construction plan creation step of creating a construction plan based on the execution conditions of the construction and the basic specification; The construction plan delivery process of delivering the construction plan created in the construction plan creation process to the support request source Construction planning support method of construction for the road occupied with a.
【請求項14】 前記基本仕様受付工程は通信ネットワ
ークを介して基本仕様を受付け、 前記施工計画引渡工程は通信ネットワークを介して施工
計画を引渡すことを特徴とする請求項13記載の道路占
用工事の施工計画支援方法。
14. The road occupation construction work according to claim 13, wherein the basic specification receiving step receives a basic specification via a communication network, and the construction plan delivery step delivers a construction plan via a communication network. Construction plan support method.
【請求項15】 予め定められた基本仕様に従って道路
に対する工事を実施する道路占用工事の申請支援方法に
おいて、 支援要求元から前記基本仕様を受付ける基本仕様受付工
程と、 道路工事を実施しない状態で測定された交通量と前記道
路工事が実施される工事区間の周辺における交通条件と
前記道路工事の実施条件とに基づいて、前記道路工事が
実施された場合の前記工事区間における交通状態の予測
を含む交通シミュレーションを行う交通シミュレーショ
ン工程と、 前記交通シミュレーション結果において交通渋滞情報が
判定基準を充当するとき、当該工事の実施条件及び前記
基本仕様に基づいて施工計画を作成する施工計画作成工
程と、 この施工計画作成工程にて作成された施工計画を含む道
路使用許可申請を、前記支援要求元に代って、当該道路
の使用許可者へ提出する申請工程とを備えた道路占用工
事の申請支援方法。
15. A method for supporting application for road occupation construction in which construction is performed on a road in accordance with a predetermined basic specification, comprising: a basic specification receiving step of receiving the basic specification from a support requester; and measuring without performing the road construction. Based on the performed traffic volume, the traffic conditions around the construction section where the road construction is performed, and the execution conditions of the road construction, prediction of the traffic condition in the construction section when the road construction is performed is included. A traffic simulation step of performing a traffic simulation, and, when the traffic congestion information satisfies a determination criterion in the traffic simulation result, a construction plan creation step of creating a construction plan based on the execution conditions of the construction and the basic specifications. The road use permission application including the construction plan created in the plan creation process , Application support method of construction for the road occupied with the application process to be submitted to use the authorized person of the road.
【請求項16】 前記申請工程は、前記支援要求元に対
して前記施工計画申請の許可を得た後、当該道路の使用
許可者への道路使用許可申請を行うことを特徴とする請
求項15記載の道路占用工事の申請支援方法。
16. The method according to claim 15, wherein in the application step, after obtaining permission for the construction plan application from the support request source, a road use permission application is made to a person who is permitted to use the road. Application support method for road private use construction as described.
【請求項17】 前記基本仕様受付工程は通信ネットワ
ークを介して基本仕様を受付け、 前記申請工程は通信ネットワークを介して前記支援要求
元に対して前記施工計画申請の許可を得ることを特徴と
する請求項16記載の道路占用工事の申請支援方法。
17. The basic specification receiving step receives a basic specification via a communication network, and the application step obtains permission of the construction plan application from the support request source via a communication network. The method for supporting application for road occupation construction according to claim 16.
【請求項18】 前記申請工程は、前記道路使用許可申
請を通信ネットワークを介して前記道路の使用許可者へ
提出することを特徴とする請求項15から17のいずれ
か1項記載の道路占用工事の申請支援方法。
18. The road occupation work according to claim 15, wherein the application step submits the road use permission application to a road use permitter via a communication network. Application support method.
【請求項19】 予め定められた基本仕様に従って道路
に対する工事を実施する道路占用工事の施工計画を行う
コンピュータ読取可能なプログラムを記録した記録媒体
において、 前記プログラムは、前記コンピュータに対して、 道路工事を実施しない状態で測定された交通量と前記道
路工事が実施される工事区間の周辺における交通条件と
前記道路工事の実施条件とに基づいて、前記道路工事が
実施された場合の前記工事区間における交通状況の予測
を含む交通シミュレーションを行なわせ、 前記交通シミュレーション結果において交通渋滞情報が
判定基準を充足するとき、当該工事の実施条件及び前記
基本仕様に基づいて施工計画を作成させることを特徴と
するプログラムを記録した記録媒体。
19. A recording medium recording a computer-readable program for performing a construction plan of a road occupation construction for performing a construction on a road in accordance with a predetermined basic specification, the program comprising: Based on the traffic volume measured in a state where the road construction is not performed and the traffic conditions around the construction section where the road construction is performed and the execution conditions of the road construction, in the construction section where the road construction is performed A traffic simulation including a prediction of a traffic situation is performed, and when the traffic congestion information satisfies a criterion in the traffic simulation result, a construction plan is created based on the execution conditions of the construction and the basic specification. A recording medium on which a program is recorded.
【請求項20】 前記コンピュータに対して、前記作成
された施工計画に基づいて前記基本仕様に対する工事見
積を作成させることを特徴とする請求項19記載のプロ
グラムを記録した記録媒体。
20. The recording medium according to claim 19, wherein said computer causes the computer to create a construction estimate for the basic specifications based on the created construction plan.
【請求項21】 前記コンピュータに対して、前記周辺
の交通条件と前記工事の実施条件とのうち少なくとも一
方の条件を変更しつつ、前記シミュレーション及び前記
施工計画作成を繰返し実行し、作成される施工計画を最
適化させることを特徴とする請求項19又は20記載の
プログラムを記録した記録媒体。
21. The computer executes the simulation and the construction plan creation repeatedly while changing at least one of the surrounding traffic conditions and the execution condition of the construction for the computer. 21. A recording medium recording the program according to claim 19, wherein the plan is optimized.
JP2000345245A 2000-11-13 2000-11-13 Method for executing and planning of construction work for road occupation Pending JP2002146761A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000345245A JP2002146761A (en) 2000-11-13 2000-11-13 Method for executing and planning of construction work for road occupation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000345245A JP2002146761A (en) 2000-11-13 2000-11-13 Method for executing and planning of construction work for road occupation

Publications (1)

Publication Number Publication Date
JP2002146761A true JP2002146761A (en) 2002-05-22

Family

ID=18819309

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000345245A Pending JP2002146761A (en) 2000-11-13 2000-11-13 Method for executing and planning of construction work for road occupation

Country Status (1)

Country Link
JP (1) JP2002146761A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009288155A (en) * 2008-05-30 2009-12-10 Aisin Aw Co Ltd Reporting zone determining system and program
CN104778832A (en) * 2015-04-24 2015-07-15 东南大学 Multimode city road cross section resource coordinated configuration method
CN110888358A (en) * 2019-11-25 2020-03-17 中国十九冶集团有限公司 Road construction detection system and method
JP2020166584A (en) * 2019-03-29 2020-10-08 トヨタ自動車株式会社 Image information collection system and vehicle
CN117592809A (en) * 2023-11-21 2024-02-23 广州市盾建建设有限公司 Municipal engineering construction scheme optimization method and system based on artificial intelligence

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009288155A (en) * 2008-05-30 2009-12-10 Aisin Aw Co Ltd Reporting zone determining system and program
CN104778832A (en) * 2015-04-24 2015-07-15 东南大学 Multimode city road cross section resource coordinated configuration method
JP2020166584A (en) * 2019-03-29 2020-10-08 トヨタ自動車株式会社 Image information collection system and vehicle
CN110888358A (en) * 2019-11-25 2020-03-17 中国十九冶集团有限公司 Road construction detection system and method
CN117592809A (en) * 2023-11-21 2024-02-23 广州市盾建建设有限公司 Municipal engineering construction scheme optimization method and system based on artificial intelligence
CN117592809B (en) * 2023-11-21 2024-05-10 广州市盾建建设有限公司 Municipal engineering construction scheme optimization method and system based on artificial intelligence

Similar Documents

Publication Publication Date Title
Chong et al. Comparative analysis on the adoption and use of BIM in road infrastructure projects
US9857191B2 (en) Context-based routing and access path selection
US9361793B2 (en) Systems and methods for distance and congestion-aware resource deployment
KR101994496B1 (en) Providing routes through information collection and retrieval
Lee et al. Computer simulation model: Construction analysis for pavement rehabilitation strategies
US10204388B2 (en) Method, system, and medium of construction project management
Lee et al. Utilizing noise mapping for environmental impact assessment in a downtown redevelopment area of Seoul, Korea
US20130035978A1 (en) Management of materials on a construction site
US20090198505A1 (en) Interactive path planning with dynamic costing
RU2589381C2 (en) Navigation system and method for pilot tracking of movement
US20130197960A1 (en) System for adaptive construction sequencing
CN101751615A (en) Method and system for managing raw materials on construction site
Sharma et al. Location-based planning and scheduling of highway construction projects in hilly terrain using GIS
JP2002146761A (en) Method for executing and planning of construction work for road occupation
CN105547313A (en) Vehicle navigation method and device
Lee et al. Minimizing total cost for urban freeway reconstruction with integrated construction/traffic analysis
Lee et al. Integrated design/construction/operations analysis for fast-track urban freeway reconstruction
JP2984262B1 (en) Underground line support system
Gowda et al. Development of a budget-prioritized pavement management system based on engineering criteria
Brady et al. Mitigating the disruption caused by utility street works
Karmakar et al. Automated route planning for construction site utilizing Building Information Modeling.
KR101959800B1 (en) Method for installation and repairing of pipe and apparatus for using the method
JP3526557B2 (en) Approach road information processing system
de Lima et al. Optimization of earthmoving operations planning: a novel approach considering interferences
JP4565494B2 (en) Design and management support system for buried pipe work and civil engineering work

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050405

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050802