CN108764854A - Project control method, apparatus, electronic equipment and medium - Google Patents
Project control method, apparatus, electronic equipment and medium Download PDFInfo
- Publication number
- CN108764854A CN108764854A CN201810565003.8A CN201810565003A CN108764854A CN 108764854 A CN108764854 A CN 108764854A CN 201810565003 A CN201810565003 A CN 201810565003A CN 108764854 A CN108764854 A CN 108764854A
- Authority
- CN
- China
- Prior art keywords
- destination item
- data
- project
- item
- responsible
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 48
- 230000000295 complement effect Effects 0.000 claims description 12
- 238000012550 audit Methods 0.000 claims description 8
- 230000006870 function Effects 0.000 description 18
- 238000004590 computer program Methods 0.000 description 13
- 238000007726 management method Methods 0.000 description 7
- 238000004458 analytical method Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 6
- 230000008569 process Effects 0.000 description 5
- 230000010365 information processing Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/18—Legal services
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Tourism & Hospitality (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Primary Health Care (AREA)
- Technology Law (AREA)
- General Health & Medical Sciences (AREA)
- Data Mining & Analysis (AREA)
- Health & Medical Sciences (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
A kind of project control method, apparatus of present invention offer, electronic equipment and medium.The project control method includes:Bulleted list is obtained, at least one project is stored in the bulleted list;The destination item with specified label is obtained from the bulleted list;Obtain the daily paper data of the destination item;The cost data of the destination item is determined according to the daily paper data of the destination item;Obtain the data of being responsible for a task until it is completed of the destination item;When the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when, obtain the execution data of the destination item;According to the contract dataset for data of being responsible for a task until it is completed described in the determination of the execution data of the destination item.The present invention can judge the reasonability of destination item, and further analyze the destination item according to the execution data of the destination item, to targetedly be handled.
Description
Technical field
The present invention relates to a kind of technical field of data processing more particularly to project control method, apparatus, electronic equipment and Jie
Matter.
Background technology
In prior art, user is when carrying out the management and control and analysis of project operation, it is often necessary to which a large amount of manpowers are actively
Intervention, and can not automatically be carried out by electronic equipment, human cost is not only wasted, efficiency is relatively low, simultaneously as artificial place
The error rate higher of reason can not also ensure the accuracy of analysis, and it is even more impossible to the reasonability of automatic identification contract, to propose there is needle
To the handling suggestion of property.
Invention content
In view of the foregoing, it is necessary to a kind of project control method, apparatus, electronic equipment and medium are provided, can judge mesh
The reasonability of mark project, and the destination item is further analyzed according to the execution data of the destination item, to be had
Targetedly handle.
A kind of project control method, the method includes:
Bulleted list is obtained, at least one project is stored in the bulleted list;
The destination item with specified label is obtained from the bulleted list;
Obtain the daily paper data of the destination item;
The cost data of the destination item is determined according to the daily paper data of the destination item;
Obtain the data of being responsible for a task until it is completed of the destination item;
When the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when, obtain the destination item
Execution data;
According to the contract dataset for data of being responsible for a task until it is completed described in the determination of the execution data of the destination item.
According to the preferred embodiment of the present invention, obtaining the target item with specified label from the bulleted list currently,
The method further includes:
Project of being responsible for a task until it is completed is obtained from the bulleted list, and label is specified described in project configuration for described be responsible for a task until it is completed.
According to the preferred embodiment of the present invention, the daily paper data include the combination of following one or more:
The destination item day executor service charge, the daily consumption expense of hardware device of the destination item, institute
State the daily consumption expense of the software systems of destination item.
It is described to determine the destination item according to the daily paper data of the destination item according to the preferred embodiment of the present invention
Cost data includes:
Obtain current time;
Calculate the sum of all daily paper data until the current time;
At the beginning of obtaining the destination item;
At the beginning of according to the destination item and the current time determines the executed time of the destination item;
The day-rate cost number of the destination item is determined according to the sum of all daily paper data and the executed time
According to;
Obtain the pre-execution time of the destination item;
The cost data of the destination item is determined according to the day-rate cost data and the pre-execution time.
It is described true according to the sum of all daily paper data and the executed time according to the preferred embodiment of the present invention
The day-rate cost data of the destination item include calmly:
All daily paper data and with the executed time quotient is calculated, using the quotient as the target
The day-rate cost data of project.
It is described according to data of being responsible for a task until it is completed described in the determination of the execution data of the destination item according to the preferred embodiment of the present invention
Contract dataset includes:
The item attribute that all sub-projects of the destination item are obtained from the execution data of the destination item, when having
When the item attribute of any sub-project is client's new projects, determine described in data of being responsible for a task until it is completed it is unreasonable, and prompt designated person with
Client signs the complementary agreement of the destination item contract;Or
The execution efficiency that all sub-projects of the destination item are obtained from the execution data of the destination item, when having
When the execution efficiency of any sub-project is less than or equal to default execution efficiency, data of being responsible for a task until it is completed described in determination are reasonable, and prompt institute
The executor for stating destination item improves the execution efficiency of the destination item;Or
The human cost data that the destination item is obtained from the execution data of the destination item, when the target item
When purpose human cost data are more than or equal to default human cost data, data of being responsible for a task until it is completed described in determination are reasonable, and prompt institute
The executor for stating destination item redistributes manpower;Or
The impersonal force cost data that the destination item is obtained from the execution data of the destination item, when the target
When the impersonal force cost data of project is more than or equal to default impersonal force cost data, data of being responsible for a task until it is completed described in determination are reasonable, and
The executor of the destination item is prompted to be equipped with impersonal force resource again.
According to the preferred embodiment of the present invention, the conjunction for data of being responsible for a task until it is completed described in being determined according to the execution data of the destination item
After rationality, the method further includes:
It prompts the executor of the destination item to audit the daily paper data of the destination item, obtains auditing result;
Obtain the auditing result;
When the auditing result shows that the daily paper data of the destination item are wrong, the execution of the destination item is prompted
Person redefines the daily paper data of the destination item.
A kind of project control device, described device include:
Acquiring unit stores at least one project for obtaining bulleted list in the bulleted list;
The acquiring unit is additionally operable to obtain the destination item with specified label from the bulleted list;
The acquiring unit is additionally operable to obtain the daily paper data of the destination item;
Determination unit, the cost data for determining the destination item according to the daily paper data of the destination item;
The acquiring unit is additionally operable to obtain the data of being responsible for a task until it is completed of the destination item;
The acquiring unit is additionally operable to be more than the data of being responsible for a task until it is completed of the destination item when the cost data of the destination item
When, obtain the execution data of the destination item;
The determination unit is additionally operable to the contract number according to data of being responsible for a task until it is completed described in the determination of the execution data of the destination item
According to.
According to the preferred embodiment of the present invention, described device further includes:
Dispensing unit, for obtaining the target item with specified label from the bulleted list currently, from the item
Project of being responsible for a task until it is completed is obtained in mesh list, and label is specified described in project configuration for described be responsible for a task until it is completed.
According to the preferred embodiment of the present invention, the daily paper data include the combination of following one or more:
The destination item day executor service charge, the daily consumption expense of hardware device of the destination item, institute
State the daily consumption expense of the software systems of destination item.
According to the preferred embodiment of the present invention, the determination unit determines the mesh according to the daily paper data of the destination item
The cost data of mark project includes:
Obtain current time;
Calculate the sum of all daily paper data until the current time;
At the beginning of obtaining the destination item;
At the beginning of according to the destination item and the current time determines the executed time of the destination item;
The day-rate cost number of the destination item is determined according to the sum of all daily paper data and the executed time
According to;
Obtain the pre-execution time of the destination item;
The cost data of the destination item is determined according to the day-rate cost data and the pre-execution time.
It is described true according to the sum of all daily paper data and the executed time according to the preferred embodiment of the present invention
The day-rate cost data of the destination item include calmly:
All daily paper data and with the executed time quotient is calculated, using the quotient as the target
The day-rate cost data of project.
According to the preferred embodiment of the present invention, the determination unit determines the packet according to the execution data of the destination item
The contract dataset of dry data includes:
The item attribute that all sub-projects of the destination item are obtained from the execution data of the destination item, when having
When the item attribute of any sub-project is client's new projects, determine described in data of being responsible for a task until it is completed it is unreasonable, and prompt designated person with
Client signs the complementary agreement of the destination item contract;Or
The execution efficiency that all sub-projects of the destination item are obtained from the execution data of the destination item, when having
When the execution efficiency of any sub-project is less than or equal to default execution efficiency, data of being responsible for a task until it is completed described in determination are reasonable, and prompt institute
The executor for stating destination item improves the execution efficiency of the destination item;Or
The human cost data that the destination item is obtained from the execution data of the destination item, when the target item
When purpose human cost data are more than or equal to default human cost data, data of being responsible for a task until it is completed described in determination are reasonable, and prompt institute
The executor for stating destination item redistributes manpower;Or
The impersonal force cost data that the destination item is obtained from the execution data of the destination item, when the target
When the impersonal force cost data of project is more than or equal to default impersonal force cost data, data of being responsible for a task until it is completed described in determination are reasonable, and
The executor of the destination item is prompted to be equipped with impersonal force resource again.
According to the preferred embodiment of the present invention, described device further includes:
Prompt unit, after the reasonability of data of being responsible for a task until it is completed described in being determined according to the execution data of the destination item,
It prompts the executor of the destination item to audit the daily paper data of the destination item, obtains auditing result;
The acquiring unit is additionally operable to obtain the auditing result;
The prompt unit is additionally operable to, when the auditing result shows that the daily paper data of the destination item are wrong, carry
Show that the executor of the destination item redefines the daily paper data of the destination item.
A kind of electronic equipment, the electronic equipment include:
Memory stores at least one instruction;And
Processor executes the instruction stored in the memory to realize the project control method.
A kind of computer readable storage medium is stored at least one instruction, institute in the computer readable storage medium
At least one instruction is stated to be executed to realize the project control method by the processor in electronic equipment.
As can be seen from the above technical solutions, the present invention by the daily paper data of the destination item, data of being responsible for a task until it is completed and is held
Row data determine the contract dataset of the destination item, so as to reduce the process artificially participated in, improve accuracy rate, and more intelligence
Energyization, the present invention can also be further analyzed the destination item according to the execution data, to reasonability problem
It is targetedly handled, and provides handling suggestion.
Description of the drawings
Fig. 1 is the flow chart of the preferred embodiment of project control method of the present invention.
Fig. 2 is the functional block diagram of the preferred embodiment of project control device of the present invention.
Fig. 3 is the structural schematic diagram of the electronic equipment for the preferred embodiment that the present invention realizes project control method.
Main element symbol description
Electronic equipment | 1 |
Memory | 12 |
Processor | 13 |
Project control device | 11 |
Acquiring unit | 110 |
Determination unit | 111 |
Dispensing unit | 112 |
Prompt unit | 113 |
Specific implementation mode
To make the objectives, technical solutions, and advantages of the present invention clearer, right in the following with reference to the drawings and specific embodiments
The present invention is described in detail.
As shown in Figure 1, being the flow chart of the preferred embodiment of project control method of the present invention.According to different requirements, should
The sequence of step can change in flow chart, and certain steps can be omitted.
The project control method is applied in one or more electronic equipment, and the electronic equipment is that one kind can be by
According to the instruction for being previously set or storing, numerical computations are carried out automatically and/or the equipment of information processing, hardware include but not limited to
Microprocessor, application-specific integrated circuit (Application Specific Integrated Circuit, ASIC), programmable gate
Array (Field-Programmable Gate Array, FPGA), digital processing unit (Digital Signal
Processor, DSP), embedded device etc..
The electronic equipment can be the electronic product that any type can carry out human-computer interaction with user, for example, personal meter
Calculation machine, tablet computer, smart mobile phone, personal digital assistant (Personal Digital Assistant, PDA), game machine, friendship
Mutual formula Web TV (Internet Protocol Television, IPTV), intellectual Wearable etc..
The electronic equipment can also include the network equipment and/or user equipment.Wherein, the network equipment includes, but
It is not limited to single network server, the server group of multiple network servers composition or is based on cloud computing (Cloud
Computing the cloud being made of a large amount of hosts or network server).
Network residing for the electronic equipment include but not limited to internet, wide area network, Metropolitan Area Network (MAN), LAN, it is virtual specially
With network (Virtual Private Network, VPN) etc..
S10, the electronic equipment obtain bulleted list, at least one project are stored in the bulleted list.
In at least one embodiment of the present invention, the electronic equipment safeguards a bulleted list, the bulleted list
In store at least one project.
Specifically, the bulleted list includes all items of an enterprise, a group or a department.
Further, the bulleted list can preserve in the local database, can also be stored in and be set with the electronics
In the standby external data base communicated, the present invention is not limited.
It is understood that when the bulleted list preserves in the local database, the electronic equipment can be saved
Acquisition speed, and when the bulleted list is stored in the external data base communicated with the electronic equipment, Ke Yijie
The memory of the about described electronic equipment.
S11, the electronic equipment obtain the destination item with specified label from the bulleted list.
Preferably, the target item with specified label is obtained from the bulleted list in the electronic equipment currently, institute
The method of stating further includes:
The electronic equipment obtains project of being responsible for a task until it is completed from the bulleted list, and mark is specified described in project configuration for described be responsible for a task until it is completed
Note.
By the above embodiment, the project of being responsible for a task until it is completed in the bulleted list can be determined as described by the electronic equipment
Destination item.
In at least one embodiment of the present invention, the specified label is for distinguishing project and other of being responsible for a task until it is completed
Mesh, therefore, the present invention are not limited the form of the specified label.Such as:The form of the specified label may include,
But it is not limited to:Designated character is added before project name (such as:BG the label of designated color), is carried out (such as to project name:It is red
Font) etc..
S12, the electronic equipment obtain the daily paper data of the destination item.
Preferably, the daily paper data include, but are not limited to the combination of following one or more:
The destination item day executor service charge, the daily consumption expense of hardware device of the destination item, institute
State the daily consumption expense etc. of the software systems of destination item.
Such as:The daily paper data of destination item A can be 1,000,000 etc..
Certainly, in other embodiments, according to different project demands, the daily paper data can also include other shapes
Formula, the present invention are not limited.
S13, the electronic equipment determine the cost data of the destination item according to the daily paper data of the destination item.
Preferably, the electronic equipment determines the cost number of the destination item according to the daily paper data of the destination item
According to including:
The electronic equipment obtains current time, calculates the sum of all daily paper data until the current time, institute
State at the beginning of electronic equipment obtains the destination item, and according to the destination item at the beginning of and it is described current when
Between determine executed time of the destination item, the electronic equipment according to the sums of all daily paper data and it is described
The execution time determines the day-rate cost data of the destination item, when the electronic equipment obtains the pre-execution of the destination item
Between, and determine according to the day-rate cost data and the pre-execution time cost data of the destination item.
Such as:For destination item A, it is the 3rd day that the electronic equipment, which gets current time, and the electronic equipment is simultaneously
The daily paper data that the daily paper data that the daily paper data for getting the 1st day are the 1,000,000, the 2nd day are the 500,000, the 3rd day are 600,000, described
Electronic equipment calculate all daily paper data until the current time the 3rd day and be 1,00+,50+,60=,210 ten thousand, it is described
It is the 1st day that electronic equipment, which is got at the beginning of the destination item A, and according to current time the 3rd day, the electronic equipment was true
The executed time of the fixed destination item A is 3 days, the electronic equipment according to all daily paper data and 2,100,000 and
The day-rate cost data of the 3 days executed time determination destination item A are 700,000, and the electronic equipment obtains the target
The pre-execution time of project A is 10 days, then the electronic equipment is according to the day-rate cost data 700,000 and the pre-execution time
10 days, determine that the cost data of the destination item is 7,000,000.
Preferably, the electronic equipment is according to described in the sum of all daily paper data and executed time determination
The day-rate cost data of destination item include:
The electronic equipment calculates all daily paper data and with the executed time quotient, with the quotient
Day-rate cost data as the destination item.
Such as:The electronic equipment get all daily paper data of the destination item A and be 2,100,000, and obtain
To the destination item A the executed time be 3 days, the electronic equipment calculate all daily paper data and 2,100,000 and
The quotient of the 3 days executed time is 700,000, then the electronic equipment determines that the day-rate cost data of the destination item A are 70
Ten thousand.
By the above embodiment, the electronic equipment can estimate the cost data of the destination item, side
Toilet states electronic equipment and carries out subsequent analyzing processing according to the cost data.
S14, the electronic equipment obtain the data of being responsible for a task until it is completed of the destination item.
Specifically, the data of being responsible for a task until it is completed of the destination item include the valence of being responsible for a task until it is completed of the destination item.In the destination item
When signing a contract, whether the determination destination item is the project of being responsible for a task until it is completed by contract parties, when the destination item is the project of being responsible for a task until it is completed
When, contract parties will negotiate the valence of being responsible for a task until it is completed of the determining destination item.After the valence of being responsible for a task until it is completed of the destination item is determined, in institute
, will be using the valence of being responsible for a task until it is completed as full payment in the implementation procedure for stating destination item, and no longer collect other fees.
Therefore, the determination of the data of being responsible for a task until it is completed of the destination item is the important component in contract, by directly affecting
State the profit and loss situation of destination item.
S15, when the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when, the electronic equipment
Obtain the execution data of the destination item.
Specifically, the execution data of the destination item include, but are not limited to the combination of following one or more:
The subitem mesh number of the destination item, the item attribute of the sub-project of the destination item, the destination item
The impersonal force cost data etc. of execution efficiency, the human cost data of the destination item, the destination item.
Specifically, the item attribute of the sub-project of the destination item includes, but are not limited to following one or more
Combination:Client's new projects, original project, the new projects etc. of original demand.
The execution efficiency of the destination item refers to the workload completed in the unit interval.Specifically, the electronic equipment
Obtain the destination item is completed subitem mesh number, and obtains the executed time of the destination item, and according to it is described
It completes subitem mesh number and the executed time determines the execution efficiency of the destination item.
The human cost data of the destination item include, but are not limited to the combination of following one or more:O&M people
Member's cost data, developer's cost data, tester's cost data etc..Specifically, the electronic equipment obtains the mesh
All executors of mark project, and the monthly pay data of all executors are obtained, the electronic equipment obtains the target item
The purpose executed time, and determine the destination item according to the monthly pay data of the executed time and all executors
Human cost data.
The impersonal force cost data of the destination item includes, but are not limited to the combination of following one or more:Software
System cost data, hardware system cost data etc..Specifically, the electronic equipment obtains all applications of the destination item
System, and the unit price and quantity of all application systems are obtained, and it is true according to the unit price and quantity of all application systems
The impersonal force cost data of the fixed destination item.
It is understood that the electronic equipment is after obtaining the execution data of the destination item, you can according to institute
The execution data for stating destination item are analyzed, with the contract dataset of the determination destination item, and according to the execution data
Carry out analysis and early warning.Concrete mode will be explained hereinafter.
S16, the electronic equipment according to the execution data of the destination item determine described in be responsible for a task until it is completed the contract datasets of data.
In at least one embodiment of the present invention, the electronic equipment is in the execution data for getting the destination item
Afterwards, by the analysis for executing data, you can whether the contract dataset for data of being responsible for a task until it is completed described in judgement is reasonable.It below will be to this
Deterministic process is described in detail.
Preferably, the electronic equipment according to the execution data of the destination item determine described in be responsible for a task until it is completed the contract numbers of data
According to including, but are not limited to any one following situation:
(1) electronic equipment obtains all sub-projects of the destination item from the execution data of the destination item
Item attribute, when the item attribute for having any sub-project is client's new projects, the electronic equipment determine described in be responsible for a task until it is completed
Data are unreasonable, and designated person is prompted to sign the complementary agreement of the destination item contract with client.
Such as:The electronic equipment obtains all subitems of the destination item from the execution data of the destination item
After purpose item attribute, determine that there are one the item attribute of sub-project B be client's new projects, since the sub-project B is not
Original demand of the destination item, but client causes, that is to say, that the sub-project B is to be not present in contract signing
, therefore, the electronic equipment can determine that the data of being responsible for a task until it is completed are unreasonable, and designated person is prompted to sign the mesh with client
Mark the complementary agreement of Project contract.
In addition, in the complementary agreement, user can individually charge to the sub-project B, in order to avoid cause damages.
By the above embodiment, the electronic equipment can not only analyze the conjunction of the contract dataset of the destination item
Rationality can also be carried out complementary agreement for ancillary cost caused by client, be impacted, be given with the whole implementation of exempt from customs examination project
Company brings loss.
(2) electronic equipment obtains all sub-projects of the destination item from the execution data of the destination item
Execution efficiency, when the execution efficiency for having any sub-project is less than or equal to default execution efficiency, the electronic equipment is true
The data of being responsible for a task until it is completed are reasonable, and the executor of the destination item is prompted to improve the execution efficiency of the destination item.
Such as:The electronic equipment obtains all subitems of the destination item from the execution data of the destination item
After purpose execution efficiency, determine that there are one the execution efficiencys of sub-project C to be less than or equal to default execution efficiency (such as:60%),
Since the execution efficiency of the sub-project C is too low, the electronic equipment can determine that the data of being responsible for a task until it is completed are reasonable,
But the efficiency of inner working is too low, the executor of destination item described in the electronic device prompts improves the destination item
Execution efficiency.
In the present embodiment, the electronic equipment obtains the work number of packages of all sub-projects, and obtains described all
The executed time of sub-project, and according to the work number of packages of all sub-projects and the executed time of all sub-projects
Determine the execution efficiency of all sub-projects.
Wherein, the default execution efficiency can be configured by the electronic equipment, can also be received by the electronic equipment
The setting of user configures, and the present invention is not limited.
By the above embodiment, the electronic equipment can not only analyze the conjunction of the contract dataset of the destination item
Rationality can also be directed to the too low reason of inner working efficiency, and the executor of the destination item is prompted to improve the target item
Purpose execution efficiency plays internal operational staff certain warning function.
(3) electronic equipment obtains the human cost number of the destination item from the execution data of the destination item
According to when the human cost data of the destination item are more than or equal to default human cost data, the electronic equipment is true
The fixed data of being responsible for a task until it is completed are reasonable, and the executor of the destination item is prompted to redistribute manpower.
Such as:The electronic equipment obtains the human cost of the destination item from the execution data of the destination item
After data, determine that there are one the human cost data of sub-project C to be more than or equal to default human cost data (such as:100 ten thousand),
Since the human cost data of the sub-project C are excessively high, the electronic equipment can determine that the data of being responsible for a task until it is completed are reasonable
, but the human cost of inner working does not have management and control good, the executor of destination item described in the electronic device prompts is again
Distribute manpower.
Wherein, the default human cost data can be configured, this hair before signing a contract by the designated person
It is bright not to be limited.
By the above embodiment, the electronic equipment can not only analyze the conjunction of the contract dataset of the destination item
Rationality can also be directed to the human cost management and control problem of inner working, the executor of the destination item is prompted to redistribute people
Power plays internal executive condition certain warning function.
(4) electronic equipment obtains the impersonal force cost of the destination item from the execution data of the destination item
Data, when the impersonal force cost data of the destination item is more than or equal to default impersonal force cost data, the electronics
Data of being responsible for a task until it is completed described in equipment determination are reasonable, and the executor of the destination item is prompted to be equipped with impersonal force resource again.
Such as:The electronic equipment obtained from the execution data of the destination item impersonal force of the destination item at
After notebook data, determine that there are one the impersonal force cost data of sub-project C to be more than or equal to default impersonal force cost data (such as:
100 ten thousand), since the impersonal force cost data of the sub-project C is excessively high, the electronic equipment can determine described be responsible for a task until it is completed
Data are reasonable, but the impersonal force cost of inner working does not have that management and control is good, destination item described in the electronic device prompts
Executor be equipped with impersonal force resource again.
Wherein, the default impersonal force cost data can be configured before signing a contract by the designated person, this
Invention is not limited.
By the above embodiment, the electronic equipment can not only analyze the conjunction of the contract dataset of the destination item
Rationality can also be directed to the impersonal force cost control problem of inner working, the executor of the destination item is prompted to be equipped with again
Impersonal force resource plays internal executive condition certain warning function.
Preferably, in the electronic equipment according to the reasonable of data of being responsible for a task until it is completed described in the determination of the execution data of the destination item
After property, the method further includes:
The executor of destination item described in the electronic device prompts audits the daily paper data of the destination item, is examined
Core is as a result, the electronic equipment obtains the auditing result, when the auditing result shows the daily paper data of the destination item
When wrong, the executor of destination item described in the electronic device prompts redefines the daily paper data of the destination item.
By the above embodiment, the mode of artificial participation audit is it is possible to prevente effectively from since data upload mistake to judgement
As a result influence, keeps judging result more accurate caused by.
In conclusion the present invention is by the daily paper data of the destination item, data of being responsible for a task until it is completed and executes described in data determination
The contract dataset of destination item improves accuracy rate, and more intelligent, the present invention is also so as to reduce the process artificially participated in
The destination item can be further analyzed according to the execution data, to be carried out targetedly to reasonability problem
Processing, and provide handling suggestion.
As shown in Fig. 2, being the functional block diagram of the preferred embodiment of project control device of the present invention.The project control dress
It includes acquiring unit 110, determination unit 111, dispensing unit 112 and prompt unit 113 to set 11.The so-called module of the present invention/mono-
Member refers to that one kind can be performed by processor 13, and can complete the series of computation machine program segment of fixed function, is deposited
Storage is in memory 12.In the present embodiment, it will be described in detail in subsequent embodiment about the function of each module/unit.
Acquiring unit 110 obtains bulleted list, and at least one project is stored in the bulleted list.
In at least one embodiment of the present invention, the electronic equipment safeguards a bulleted list, the bulleted list
In store at least one project.
Specifically, the bulleted list includes all items of an enterprise, a group or a department.
Further, the bulleted list can preserve in the local database, can also be stored in and be set with the electronics
In the standby external data base communicated, the present invention is not limited.
It is understood that when the bulleted list preserves in the local database, the electronic equipment can be saved
Acquisition speed, and when the bulleted list is stored in the external data base communicated with the electronic equipment, Ke Yijie
The memory of the about described electronic equipment.
The acquiring unit 110 obtains the destination item with specified label from the bulleted list.
Preferably, the target item with specified label is obtained from the bulleted list in the acquiring unit 110 currently,
The method further includes:
The acquiring unit 110 obtains project of being responsible for a task until it is completed from the bulleted list, and the project of being responsible for a task until it is completed is matched described in dispensing unit 112
Set the specified label.
By the above embodiment, the project of being responsible for a task until it is completed in the bulleted list can be determined as described by the electronic equipment
Destination item.
In at least one embodiment of the present invention, the specified label is for distinguishing project and other of being responsible for a task until it is completed
Mesh, therefore, the present invention are not limited the form of the specified label.Such as:The form of the specified label may include,
But it is not limited to:Designated character is added before project name (such as:BG the label of designated color), is carried out (such as to project name:It is red
Font) etc..
The acquiring unit 110 obtains the daily paper data of the destination item.
Preferably, the daily paper data include, but are not limited to the combination of following one or more:
The destination item day executor service charge, the daily consumption expense of hardware device of the destination item, institute
State the daily consumption expense etc. of the software systems of destination item.
Such as:The daily paper data of destination item A can be 1,000,000 etc..
Certainly, in other embodiments, according to different project demands, the daily paper data can also include other shapes
Formula, the present invention are not limited.
Determination unit 111 determines the cost data of the destination item according to the daily paper data of the destination item.
Preferably, the determination unit 111 according to the daily paper data of the destination item determine the destination item at
Notebook data includes:
The determination unit 111 obtains current time, calculates the sum of all daily paper data until the current time,
At the beginning of the determination unit 111 obtains the destination item, and according to the destination item at the beginning of and it is described
Current time determines the executed time of the destination item, the determination unit 111 according to the sums of all daily paper data,
And the executed time determines that the day-rate cost data of the destination item, the determination unit 111 obtain the destination item
The pre-execution time, and determine according to the day-rate cost data and the pre-execution time cost data of the destination item.
Such as:For destination item A, it is the 3rd day that the electronic equipment, which gets current time, the determination unit 111
The daily paper data that the daily paper data that the daily paper data for getting the 1st day simultaneously are the 1,000,000, the 2nd day are the 500,000, the 3rd day are 600,000,
The determination unit 111 calculate all daily paper data until the current time the 3rd day and be 100+50+60=210
Ten thousand, it is the 1st day that the determination unit 111, which is got at the beginning of the destination item A, described according to current time the 3rd day
Determination unit 111 determines that the executed time of the destination item A is 3 days, and the determination unit 111 is according to all daily paper
Data and the 2100000 and 3 days executed time determination destination item A day-rate cost data are 700,000, the determination
The pre-execution time that unit 111 obtains the destination item A is 10 days, then the determination unit 111 is according to the day-rate cost number
According to 700,000 and the 10 days pre-execution time, determine that the cost data of the destination item is 7,000,000.
Preferably, the determination unit 111 determines institute according to the sum and the executed time of all daily paper data
The day-rate cost data for stating destination item include:
The determination unit 111 calculates all daily paper data and with the executed time quotient, with described
Day-rate cost data of the quotient as the destination item.
Such as:The determination unit 111 get all daily paper data of the destination item A and be 2,100,000, and obtain
Get the destination item A the executed time be 3 days, the determination unit 111 calculate all daily paper data and 210
Ten thousand with the quotient of the 3 days executed time be 700,000, then the determination unit 111 determines the day-rate cost of the destination item A
Data are 700,000.
By the above embodiment, the determination unit 111 can estimate the cost data of the destination item,
The electronic equipment is facilitated to carry out subsequent analyzing processing according to the cost data.
The acquiring unit 110 obtains the data of being responsible for a task until it is completed of the destination item.
Specifically, the data of being responsible for a task until it is completed of the destination item include the valence of being responsible for a task until it is completed of the destination item.In the destination item
When signing a contract, whether the determination destination item is the project of being responsible for a task until it is completed by contract parties, when the destination item is the project of being responsible for a task until it is completed
When, contract parties will negotiate the valence of being responsible for a task until it is completed of the determining destination item.After the valence of being responsible for a task until it is completed of the destination item is determined, in institute
, will be using the valence of being responsible for a task until it is completed as full payment in the implementation procedure for stating destination item, and no longer collect other fees.
Therefore, the determination of the data of being responsible for a task until it is completed of the destination item is the important component in contract, by directly affecting
State the profit and loss situation of destination item.
When the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when, the acquiring unit 110
Obtain the execution data of the destination item.
Specifically, the execution data of the destination item include, but are not limited to the combination of following one or more:
The subitem mesh number of the destination item, the item attribute of the sub-project of the destination item, the destination item
The impersonal force cost data etc. of execution efficiency, the human cost data of the destination item, the destination item.
Specifically, the item attribute of the sub-project of the destination item includes, but are not limited to following one or more
Combination:Client's new projects, original project, the new projects etc. of original demand.
The execution efficiency of the destination item refers to the workload completed in the unit interval.Specifically, the acquiring unit
Subitem mesh number is completed in the 110 acquisition destination items, and obtains the executed time of the destination item, and according to described
Subitem mesh number is completed and the executed time determines the execution efficiency of the destination item.
The human cost data of the destination item include, but are not limited to the combination of following one or more:O&M people
Member's cost data, developer's cost data, tester's cost data etc..Specifically, the acquiring unit 110 obtains described
All executors of destination item, and the monthly pay data of all executors are obtained, the acquiring unit 110 obtains the mesh
The executed time of mark project, and determine the target according to the monthly pay data of the executed time and all executors
The human cost data of project.
The impersonal force cost data of the destination item includes, but are not limited to the combination of following one or more:Software
System cost data, hardware system cost data etc..Specifically, the acquiring unit 110 obtains all of the destination item
Application system, and the unit price and quantity of all application systems are obtained, and according to the unit price and number of all application systems
Amount determines the impersonal force cost data of the destination item.
It is understood that the acquiring unit 110 is after obtaining the execution data of the destination item, you can according to
The execution data of the destination item are analyzed, with the contract dataset of the determination destination item, and according to the execution number
According to progress analysis and early warning.Concrete mode will be explained hereinafter.
The determination unit 111 according to the execution data of the destination item determine described in be responsible for a task until it is completed the contract datasets of data.
In at least one embodiment of the present invention, the acquiring unit 110 is in the execution for getting the destination item
After data, the determination unit 111 passes through to the analysis for executing data, you can the contract dataset for data of being responsible for a task until it is completed described in judgement
Whether rationally.This deterministic process will be described in detail below.
Preferably, the determination unit 111 according to the execution data of the destination item determine described in be responsible for a task until it is completed the conjunctions of data
Include, but are not limited to any one following situation with data:
(1) determination unit 111 obtains all sons of the destination item from the execution data of the destination item
The item attribute of project, when the item attribute for having any sub-project is client's new projects, the determination unit 111 determines institute
It states that data of being responsible for a task until it is completed are unreasonable, and designated person is prompted to sign the complementary agreement of the destination item contract with client.
Such as:The determination unit 111 obtains all of the destination item from the execution data of the destination item
After the item attribute of sub-project, determine that there are one the item attribute of sub-project B be client's new projects, due to the sub-project B
Original demand of the not described destination item, client cause, that is to say, that the sub-project B is not in contract signing
Existing, therefore, the determination unit 111 can determine that the data of being responsible for a task until it is completed are unreasonable, and designated person is prompted to be signed with client
Order the complementary agreement of the destination item contract.
In addition, in the complementary agreement, user can individually charge to the sub-project B, in order to avoid cause damages.
By the above embodiment, the determination unit 111 can not only analyze the contract dataset of the destination item
Reasonability, can also for caused by client ancillary cost carry out complementary agreement, shadow is caused with the whole implementation of exempt from customs examination project
It rings, loss is brought to company.
(2) determination unit 111 obtains all sons of the destination item from the execution data of the destination item
The execution efficiency of project, it is described determining single when the execution efficiency for having any sub-project is less than or equal to default execution efficiency
Member 111 determine described in data of being responsible for a task until it is completed it is reasonable, and prompt what the executor of the destination item improved the destination item to execute effect
Rate.
Such as:The determination unit 111 obtains all of the destination item from the execution data of the destination item
After the execution efficiency of sub-project, determine that there are one the execution efficiencys of sub-project C to be less than or equal to default execution efficiency (such as:
60%), since the execution efficiency of the sub-project C is too low, the determination unit 111 can determine the data of being responsible for a task until it is completed
It is reasonable, but the efficiency of inner working is too low, the determination unit 111 prompts the executor of the destination item to improve institute
State the execution efficiency of destination item.
In the present embodiment, the determination unit 111 obtains the work number of packages of all sub-projects, and obtains the institute
There is the executed time of sub-project, and when according to the executed of the work number of packages of all sub-projects and all sub-projects
Between determine the execution efficiencys of all sub-projects.
Wherein, the default execution efficiency can be configured by the electronic equipment, can also be received by the electronic equipment
The setting of user configures, and the present invention is not limited.
By the above embodiment, the determination unit 111 can not only analyze the contract dataset of the destination item
Reasonability, the too low reason of inner working efficiency can also be directed to, the executor of the destination item be prompted to improve the mesh
The execution efficiency of mark project plays internal operational staff certain warning function.
(3) determination unit 111 obtained from the execution data of the destination item manpower of the destination item at
Notebook data, it is described determining single when the human cost data of the destination item are more than or equal to default human cost data
Data of being responsible for a task until it is completed described in 111 determination of member are reasonable, and the executor of the destination item is prompted to redistribute manpower.
Such as:The determination unit 111 obtains the manpower of the destination item from the execution data of the destination item
After cost data, determine that there are one the human cost data of sub-project C to be more than or equal to default human cost data (such as:100
Ten thousand), since the human cost data of the sub-project C are excessively high, the determination unit 111 can determine the number of being responsible for a task until it is completed
According to being reasonable, but the human cost of inner working does not have management and control good, and the determination unit 111 prompts the destination item
Executor redistributes manpower.
Wherein, the default human cost data can be configured, this hair before signing a contract by the designated person
It is bright not to be limited.
By the above embodiment, the determination unit 111 can not only analyze the contract dataset of the destination item
Reasonability, can also be directed to inner working human cost management and control problem, prompt the executor of the destination item to divide again
With manpower, certain warning function is played for internal executive condition.
(4) determination unit 111 obtains the impersonal force of the destination item from the execution data of the destination item
Cost data, it is described when the impersonal force cost data of the destination item is more than or equal to default impersonal force cost data
Data of being responsible for a task until it is completed described in the determination of determination unit 111 are reasonable, and the executor of the destination item is prompted to be equipped with impersonal force resource again.
Such as:The determination unit 111 obtains the inhuman of the destination item from the execution data of the destination item
After power cost data, determine that there are one the impersonal force cost data of sub-project C to be more than or equal to default impersonal force cost data
(such as:100 ten thousand), since the impersonal force cost data of the sub-project C is excessively high, the determination unit 111 can determine institute
Data of being responsible for a task until it is completed are stated to be reasonable, but the impersonal force cost of inner working does not have that management and control is good, the determination unit 111 prompts described
The executor of destination item is equipped with impersonal force resource again.
Wherein, the default impersonal force cost data can be configured before signing a contract by the designated person, this
Invention is not limited.
By the above embodiment, the determination unit 111 can not only analyze the contract dataset of the destination item
Reasonability, can also be directed to inner working impersonal force cost control problem, prompt the executor of the destination item again
It is equipped with impersonal force resource, certain warning function is played for internal executive condition.
Preferably, in the determination unit 111 according to data of being responsible for a task until it is completed described in the determination of the execution data of the destination item
After reasonability, the method further includes:
Prompt unit 113 prompts the executor of the destination item to audit the daily paper data of the destination item, is examined
Core is as a result, the acquiring unit 110 obtains the auditing result, when the auditing result shows the day count off of the destination item
According to it is wrong when, the prompt unit 113 prompts the executor of the destination item to redefine the day count off of the destination item
According to.
By the above embodiment, the mode of artificial participation audit is it is possible to prevente effectively from since data upload mistake to judgement
As a result influence, keeps judging result more accurate caused by.
In conclusion the present invention is by the daily paper data of the destination item, data of being responsible for a task until it is completed and executes described in data determination
The contract dataset of destination item improves accuracy rate, and more intelligent, the present invention is also so as to reduce the process artificially participated in
The destination item can be further analyzed according to the execution data, to be carried out targetedly to reasonability problem
Processing, and provide handling suggestion.
As shown in figure 3, being the structural schematic diagram of the electronic equipment for the preferred embodiment that the present invention realizes project control method.
The electronic equipment 1 be it is a kind of can according to the instruction for being previously set or storing, it is automatic carry out numerical computations and/or
The equipment of information processing, hardware include but not limited to microprocessor, application-specific integrated circuit (Application Specific
Integrated Circuit, ASIC), programmable gate array (Field-Programmable Gate Array, FPGA), number
Word processing device (Digital Signal Processor, DSP), embedded device etc..
The electronic equipment 1 can also be but not limited to any type can with user by keyboard, mouse, remote controler, touch
The modes such as template or voice-operated device carry out the electronic product of human-computer interaction, for example, personal computer, tablet computer, smart mobile phone,
Personal digital assistant (Personal Digital Assistant, PDA), game machine, Interactive Internet TV (Internet
Protocol Television, IPTV), intellectual Wearable etc..
The electronic equipment 1 can also be that the calculating such as desktop PC, notebook, palm PC and cloud server are set
It is standby.
Network residing for the electronic equipment 1 include but not limited to internet, wide area network, Metropolitan Area Network (MAN), LAN, it is virtual specially
With network (Virtual Private Network, VPN) etc..
In one embodiment of the invention, the electronic equipment 1 includes, but are not limited to memory 12, processor 13,
And it is stored in the computer program that can be run in the memory 12 and on the processor 13, such as project control journey
Sequence.
It will be understood by those skilled in the art that the schematic diagram is only the example of electronic equipment 1, not structure paired electrons
The restriction of equipment 1 may include either combining certain components or different components, example than illustrating more or fewer components
Such as electronic equipment 1 can also include input-output equipment, network access equipment, bus.
Alleged processor 13 can be central processing unit (Central Processing Unit, CPU), can also be
Other general processors, digital signal processor (Digital Signal Processor, DSP), application-specific integrated circuit
(Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field-
Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic,
Discrete hardware components etc..General processor can be microprocessor or the processor can also be any conventional processor
Deng the processor 13 is arithmetic core and the control centre of the electronic equipment 1, entire using various interfaces and connection
The various pieces of electronic equipment 1, and execute the operating system of the electronic equipment 1 and types of applications program, the program of installation
Code etc..
The processor 13 executes the operating system of the electronic equipment 1 and the types of applications program of installation.The place
Reason device 13 executes the application program to realize the step in above-mentioned each project control embodiment of the method, such as shown in FIG. 1
Step S10, S11, S12, S13, S14, S15, S16.
Alternatively, the processor 13 realizes each module in above-mentioned each device embodiment/mono- when executing the computer program
The function of member, such as:Bulleted list is obtained, at least one project is stored in the bulleted list;It is obtained from the bulleted list
Take the destination item with specified label;Obtain the daily paper data of the destination item;According to the day count off of the destination item
According to the cost data of the determination destination item;Obtain the data of being responsible for a task until it is completed of the destination item;When the cost of the destination item
Data be more than the destination item be responsible for a task until it is completed data when, obtain the execution data of the destination item;According to the destination item
Execution data determine described in be responsible for a task until it is completed the contract datasets of data.
Illustratively, the computer program can be divided into one or more module/units, one or more
A module/unit is stored in the memory 12, and is executed by the processor 13, to complete the present invention.It is one
Or multiple module/units can be the series of computation machine program instruction section that can complete specific function, the instruction segment is for retouching
State implementation procedure of the computer program in the electronic equipment 1.It is obtained for example, the computer program can be divided into
Take unit 110, determination unit 111, dispensing unit 112 and prompt unit 113.
The memory 12 can be used for storing the computer program and/or module, the processor 13 by operation or
The computer program and/or module being stored in the memory 12 are executed, and calls the data being stored in memory 12,
Realize the various functions of the electronic equipment 1.The memory 12 can include mainly storing program area and storage data field,
In, storing program area can storage program area, application program (such as sound-playing function, image needed at least one function
Playing function etc.) etc.;Storage data field can be stored uses created data (such as audio data, phone directory according to mobile phone
Deng) etc..In addition, memory 12 may include high-speed random access memory, can also include nonvolatile memory, such as firmly
Disk, memory, plug-in type hard disk, intelligent memory card (Smart Media Card, SMC), secure digital (Secure Digital,
SD) block, flash card (Flash Card), at least one disk memory, flush memory device or other volatile solid-states
Part.
The memory 12 can be the external memory and/or internal storage of electronic equipment 1.Further, described
Memory 12 can be the circuit with store function for not having in integrated circuit physical form, such as RAM (Random-Access
Memory, random access memory), FIFO (First In First Out) etc..Alternatively, the memory 12 can also be
Memory with physical form, such as memory bar, TF card (Trans-flash Card).
If the integrated module/unit of the electronic equipment 1 is realized in the form of SFU software functional unit and as independent
Product is sold or in use, can be stored in a computer read/write memory medium.Based on this understanding, the present invention is real
All or part of flow in existing above-described embodiment method, can also instruct relevant hardware come complete by computer program
At the computer program can be stored in a computer readable storage medium, which is being executed by processor
When, it can be achieved that the step of above-mentioned each embodiment of the method.
Wherein, the computer program includes computer program code, and the computer program code can be source code
Form, object identification code form, executable file or certain intermediate forms etc..The computer-readable medium may include:It can
Carry any entity or device, recording medium, USB flash disk, mobile hard disk, magnetic disc, CD, computer of the computer program code
Memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access
Memory), electric carrier signal, telecommunication signal and software distribution medium etc..It should be noted that the computer-readable medium
Including content can carry out increase and decrease appropriate according to legislation in jurisdiction and the requirement of patent practice, such as in certain departments
Method administrative area, according to legislation and patent practice, computer-readable medium does not include electric carrier signal and telecommunication signal.
In conjunction with Fig. 1, the memory 12 in the electronic equipment 1 stores multiple instruction to realize a kind of project control side
Method, the processor 13 can perform the multiple instruction to realize:Bulleted list is obtained, is stored at least in the bulleted list
One project;The destination item with specified label is obtained from the bulleted list;Obtain the day count off of the destination item
According to;The cost data of the destination item is determined according to the daily paper data of the destination item;Obtain the packet of the destination item
Dry data;When the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when, obtain the destination item
Execution data;According to the contract dataset for data of being responsible for a task until it is completed described in the determination of the execution data of the destination item.
According to the preferred embodiment of the present invention, the processor 13 also executes multiple instruction and includes:
Project of being responsible for a task until it is completed is obtained from the bulleted list, and label is specified described in project configuration for described be responsible for a task until it is completed.
According to the preferred embodiment of the present invention, the daily paper data include the combination of following one or more:
The destination item day executor service charge, the daily consumption expense of hardware device of the destination item, institute
State the daily consumption expense of the software systems of destination item.
According to the preferred embodiment of the present invention, the processor 13 also executes multiple instruction and includes:
Obtain current time;
Calculate the sum of all daily paper data until the current time;
At the beginning of obtaining the destination item;
At the beginning of according to the destination item and the current time determines the executed time of the destination item;
The day-rate cost number of the destination item is determined according to the sum of all daily paper data and the executed time
According to;
Obtain the pre-execution time of the destination item;
The cost data of the destination item is determined according to the day-rate cost data and the pre-execution time.
According to the preferred embodiment of the present invention, the processor 13 also executes multiple instruction and includes:
All daily paper data and with the executed time quotient is calculated, using the quotient as the target
The day-rate cost data of project.
According to the preferred embodiment of the present invention, the processor 13 also executes multiple instruction and includes:
The item attribute that all sub-projects of the destination item are obtained from the execution data of the destination item, when having
When the item attribute of any sub-project is client's new projects, determine described in data of being responsible for a task until it is completed it is unreasonable, and prompt designated person with
Client signs the complementary agreement of the destination item contract;Or
The execution efficiency that all sub-projects of the destination item are obtained from the execution data of the destination item, when having
When the execution efficiency of any sub-project is less than or equal to default execution efficiency, data of being responsible for a task until it is completed described in determination are reasonable, and prompt institute
The executor for stating destination item improves the execution efficiency of the destination item;Or
The human cost data that the destination item is obtained from the execution data of the destination item, when the target item
When purpose human cost data are more than or equal to default human cost data, data of being responsible for a task until it is completed described in determination are reasonable, and prompt institute
The executor for stating destination item redistributes manpower;Or
The impersonal force cost data that the destination item is obtained from the execution data of the destination item, when the target
When the impersonal force cost data of project is more than or equal to default impersonal force cost data, data of being responsible for a task until it is completed described in determination are reasonable, and
The executor of the destination item is prompted to be equipped with impersonal force resource again.
According to the preferred embodiment of the present invention, the processor 13 also executes multiple instruction and includes:
It prompts the executor of the destination item to audit the daily paper data of the destination item, obtains auditing result;
Obtain the auditing result;
When the auditing result shows that the daily paper data of the destination item are wrong, the execution of the destination item is prompted
Person redefines the daily paper data of the destination item.
Specifically, the processor 13 can refer to the concrete methods of realizing of above-metioned instruction related in Fig. 1 corresponding embodiments
The description of step, this will not be repeated here.
In several embodiments provided by the present invention, it should be understood that disclosed system, device and method can be with
It realizes by another way.For example, the apparatus embodiments described above are merely exemplary, for example, the module
It divides, only a kind of division of logic function, formula that in actual implementation, there may be another division manner.
The module illustrated as separating component may or may not be physically separated, aobvious as module
The component shown may or may not be physical unit, you can be located at a place, or may be distributed over multiple
In network element.Some or all of module therein can be selected according to the actual needs to realize the mesh of this embodiment scheme
's.
In addition, each function module in each embodiment of the present invention can be integrated in a processing unit, it can also
It is that each unit physically exists alone, it can also be during two or more units be integrated in one unit.Above-mentioned integrated list
The form that hardware had both may be used in member is realized, can also be realized in the form of hardware adds software function module.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie
In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.
Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this
The range of invention is indicated by the appended claims rather than the foregoing description, it is intended that by falling in the equivalent requirements of the claims
All changes in meaning and scope include within the present invention.Any attached associated diagram label in claim should not be considered as limit
The involved claim of system.
Furthermore, it is to be understood that one word of " comprising " is not excluded for other units or step, odd number is not excluded for plural number.In system claims
The multiple units or device of statement can also be realized by a unit or device by software or hardware.Second equal words are used
It indicates title, and does not represent any particular order.
Finally it should be noted that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although reference
Preferred embodiment describes the invention in detail, it will be understood by those of ordinary skill in the art that, it can be to the present invention's
Technical solution is modified or equivalent replacement, without departing from the spirit of the technical scheme of the invention and range.
Claims (10)
1. a kind of project control method, which is characterized in that the method includes:
Bulleted list is obtained, at least one project is stored in the bulleted list;
The destination item with specified label is obtained from the bulleted list;
Obtain the daily paper data of the destination item;
The cost data of the destination item is determined according to the daily paper data of the destination item;
Obtain the data of being responsible for a task until it is completed of the destination item;
When the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when, obtain holding for the destination item
Row data;
According to the contract dataset for data of being responsible for a task until it is completed described in the determination of the execution data of the destination item.
2. project control method as described in claim 1, which is characterized in that obtained with specified from the bulleted list
The target item of label is currently, the method further includes:
Project of being responsible for a task until it is completed is obtained from the bulleted list, and label is specified described in project configuration for described be responsible for a task until it is completed.
3. project control method as described in claim 1, which is characterized in that the daily paper data include following a kind of or more
The combination of kind:
The destination item day executor service charge, the daily consumption expense of hardware device of the destination item, the mesh
The daily consumption expense of the software systems of mark project.
4. project control method as described in claim 1, which is characterized in that the daily paper data according to the destination item
Determine that the cost data of the destination item includes:
Obtain current time;
Calculate the sum of all daily paper data until the current time;
At the beginning of obtaining the destination item;
At the beginning of according to the destination item and the current time determines the executed time of the destination item;
The day-rate cost data of the destination item are determined according to the sum of all daily paper data and the executed time;
Obtain the pre-execution time of the destination item;
The cost data of the destination item is determined according to the day-rate cost data and the pre-execution time.
5. project control method as claimed in claim 4, which is characterized in that the sum according to all daily paper data,
And the executed time determines that the day-rate cost data of the destination item include:
All daily paper data and with the executed time quotient is calculated, using the quotient as the destination item
Day-rate cost data.
6. project control method as described in claim 1, which is characterized in that the execution data according to the destination item
The contract dataset for data of being responsible for a task until it is completed described in determination includes:
The item attribute of all sub-projects of the destination item is obtained from the execution data of the destination item, it is any when having
When the item attribute of sub-project is client's new projects, data of being responsible for a task until it is completed described in determination are unreasonable, and prompt designated person and client
Sign the complementary agreement of the destination item contract;Or
The execution efficiency of all sub-projects of the destination item is obtained from the execution data of the destination item, it is any when having
When the execution efficiency of sub-project is less than or equal to default execution efficiency, data of being responsible for a task until it is completed described in determination are reasonable, and prompt the mesh
The executor of mark project improves the execution efficiency of the destination item;Or
The human cost data that the destination item is obtained from the execution data of the destination item, when the destination item
When human cost data are more than or equal to default human cost data, data of being responsible for a task until it is completed described in determination are reasonable, and prompt the mesh
The executor of mark project redistributes manpower;Or
The impersonal force cost data that the destination item is obtained from the execution data of the destination item, when the destination item
Impersonal force cost data when being more than or equal to default impersonal force cost data, determine described in data of being responsible for a task until it is completed it is reasonable, and prompt
The executor of the destination item is equipped with impersonal force resource again.
7. project control method as described in claim 1, which is characterized in that true according to the execution data of the destination item
It is responsible for a task until it is completed after the reasonability of data described in fixed, the method further includes:
It prompts the executor of the destination item to audit the daily paper data of the destination item, obtains auditing result;
Obtain the auditing result;
When the auditing result shows that the daily paper data of the destination item are wrong, executor's weight of the destination item is prompted
Newly determine the daily paper data of the destination item.
8. a kind of project control device, which is characterized in that described device includes:
Acquiring unit stores at least one project for obtaining bulleted list in the bulleted list;
The acquiring unit is additionally operable to obtain the destination item with specified label from the bulleted list;
The acquiring unit is additionally operable to obtain the daily paper data of the destination item;
Determination unit, the cost data for determining the destination item according to the daily paper data of the destination item;
The acquiring unit is additionally operable to obtain the data of being responsible for a task until it is completed of the destination item;
The acquiring unit, be additionally operable to when the cost data of the destination item be more than the destination item be responsible for a task until it is completed data when,
Obtain the execution data of the destination item;
The determination unit is additionally operable to the contract dataset according to data of being responsible for a task until it is completed described in the determination of the execution data of the destination item.
9. a kind of electronic equipment, which is characterized in that the electronic equipment includes:
Memory stores at least one instruction;And
Processor executes the instruction stored in the memory to realize project as claimed in any of claims 1 to 7 in one of claims
Control method.
10. a kind of computer readable storage medium, it is characterised in that:At least one is stored in the computer readable storage medium
A instruction, at least one instruction are executed by the processor in electronic equipment to realize such as any one of claim 1 to 7
The project control method.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810565003.8A CN108764854B (en) | 2018-06-04 | 2018-06-04 | Project control method, project control device, electronic equipment and medium |
PCT/CN2018/099291 WO2019232916A1 (en) | 2018-06-04 | 2018-08-08 | Project control method and apparatus, and electronic device and medium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810565003.8A CN108764854B (en) | 2018-06-04 | 2018-06-04 | Project control method, project control device, electronic equipment and medium |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108764854A true CN108764854A (en) | 2018-11-06 |
CN108764854B CN108764854B (en) | 2023-04-07 |
Family
ID=64002564
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810565003.8A Active CN108764854B (en) | 2018-06-04 | 2018-06-04 | Project control method, project control device, electronic equipment and medium |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN108764854B (en) |
WO (1) | WO2019232916A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110414915A (en) * | 2019-06-18 | 2019-11-05 | 平安科技(深圳)有限公司 | Project processing method, device, electronic equipment and storage medium |
CN117726304A (en) * | 2024-02-05 | 2024-03-19 | 天津航远信息技术有限公司 | Project progress prediction and project resource allocation recommendation method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103136636A (en) * | 2013-03-15 | 2013-06-05 | 中广核工程有限公司 | Nuclear power project progress measuring method and system |
CN104112174A (en) * | 2013-04-17 | 2014-10-22 | 中广核工程有限公司 | Project regulating and controlling method and system of nuclear power plant |
CN107423917A (en) * | 2017-08-15 | 2017-12-01 | 安徽婧文科技有限公司 | Construction project cost auditing system based on big data |
CN107451745A (en) * | 2017-08-02 | 2017-12-08 | 合肥哲诚项目管理有限公司 | A kind of foundation key element of architectural engineering base number of a tender preparation method and the preparation method |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003168002A (en) * | 2001-09-18 | 2003-06-13 | Nec Corp | Method and system for contracting insurance, portable terminal and insurance contract program |
CN101593332A (en) * | 2008-05-28 | 2009-12-02 | 北京邮电大学 | A kind of electronic contract management system and its implementation |
CN103765463A (en) * | 2011-03-16 | 2014-04-30 | 格里迪克斯公司 | Method and system for efficiently processing large volumes of complex small value financial transactions |
CN102609405A (en) * | 2012-02-15 | 2012-07-25 | 合一网络技术(北京)有限公司 | Method for generating dynamic contract text and system |
CN106127082B (en) * | 2016-06-13 | 2019-03-15 | 点击律(上海)网络科技有限公司 | A kind of online contract generation method and system |
-
2018
- 2018-06-04 CN CN201810565003.8A patent/CN108764854B/en active Active
- 2018-08-08 WO PCT/CN2018/099291 patent/WO2019232916A1/en active Application Filing
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103136636A (en) * | 2013-03-15 | 2013-06-05 | 中广核工程有限公司 | Nuclear power project progress measuring method and system |
CN104112174A (en) * | 2013-04-17 | 2014-10-22 | 中广核工程有限公司 | Project regulating and controlling method and system of nuclear power plant |
CN107451745A (en) * | 2017-08-02 | 2017-12-08 | 合肥哲诚项目管理有限公司 | A kind of foundation key element of architectural engineering base number of a tender preparation method and the preparation method |
CN107423917A (en) * | 2017-08-15 | 2017-12-01 | 安徽婧文科技有限公司 | Construction project cost auditing system based on big data |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110414915A (en) * | 2019-06-18 | 2019-11-05 | 平安科技(深圳)有限公司 | Project processing method, device, electronic equipment and storage medium |
CN117726304A (en) * | 2024-02-05 | 2024-03-19 | 天津航远信息技术有限公司 | Project progress prediction and project resource allocation recommendation method |
CN117726304B (en) * | 2024-02-05 | 2024-05-17 | 天津航远信息技术有限公司 | Project progress prediction and project resource allocation recommendation method |
Also Published As
Publication number | Publication date |
---|---|
WO2019232916A1 (en) | 2019-12-12 |
CN108764854B (en) | 2023-04-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10051082B2 (en) | Cost determination to provide software as a service | |
US20150324229A1 (en) | Propagation of task progress through the use of coalesced time intervals | |
US10158725B2 (en) | Differentiated service identification in a networked computing environment | |
WO2010050926A1 (en) | Workforce planning | |
CN111563703B (en) | Project management system, project management method, computer device, and computer-readable storage medium | |
CN107491907A (en) | Cost for Electric Power Engineering control and analysis and system | |
CN108734561A (en) | Electronic device, order data processing method and computer readable storage medium | |
CN109376873A (en) | O&M method, apparatus, electronic equipment and computer readable storage medium | |
US20090012854A1 (en) | Flexible, dynamic design to allow for fixed and percentage discount pricing at configurable option levels | |
CN108764854A (en) | Project control method, apparatus, electronic equipment and medium | |
US20040225583A1 (en) | Architecture and application return-on-investment metrics | |
CN115578138A (en) | Marketing method, marketing device, marketing medium and computing equipment | |
CN107330709A (en) | Determine the method and device of destination object | |
CN111126929A (en) | Intelligent contracting device and method | |
CN112181376B (en) | Code resource management method, device, electronic equipment and medium | |
US20170270482A1 (en) | Enterprise performance management system and method | |
Natschläger et al. | Optimizing resource utilization by combining activities across process instances | |
US20140207504A1 (en) | System and method of calculating task efforts and applying the results for resource planning | |
CN110796381A (en) | Method and device for processing evaluation indexes of modeling data, terminal equipment and medium | |
CN115775137A (en) | Logic table generation method, logic table generation device, and readable storage medium | |
CN114625975A (en) | Knowledge graph-based customer behavior analysis system | |
CN113743791A (en) | Business evaluation method and device for business work order, electronic equipment and medium | |
CN108846582A (en) | Health degree data determination method, electronic equipment and computer readable storage medium | |
JP2004252710A (en) | Cost profit management system, method and program | |
US20140114719A1 (en) | Allocating Service Consumers into Compatible Resource Pools |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |