CN107404416A - A kind of visualizing monitor method of power information acquisition system - Google Patents
A kind of visualizing monitor method of power information acquisition system Download PDFInfo
- Publication number
- CN107404416A CN107404416A CN201710518649.6A CN201710518649A CN107404416A CN 107404416 A CN107404416 A CN 107404416A CN 201710518649 A CN201710518649 A CN 201710518649A CN 107404416 A CN107404416 A CN 107404416A
- Authority
- CN
- China
- Prior art keywords
- terminal
- power information
- acquisition terminal
- collection
- acquisition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L43/00—Arrangements for monitoring or testing data switching networks
- H04L43/04—Processing captured monitoring data, e.g. for logfile generation
- H04L43/045—Processing captured monitoring data, e.g. for logfile generation for graphical visualisation of monitoring data
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/29—Geographical information databases
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/06—Management of faults, events, alarms or notifications
- H04L41/0631—Management of faults, events, alarms or notifications using root cause analysis; using analysis of correlation between notifications, alarms or events based on decision criteria, e.g. hierarchy, tree or time analysis
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/12—Discovery or management of network topologies
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L43/00—Arrangements for monitoring or testing data switching networks
- H04L43/08—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters
- H04L43/0805—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability
- H04L43/0811—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability by checking connectivity
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L43/00—Arrangements for monitoring or testing data switching networks
- H04L43/08—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters
- H04L43/0805—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability
- H04L43/0817—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability by checking functioning
Landscapes
- Engineering & Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Data Mining & Analysis (AREA)
- Environmental & Geological Engineering (AREA)
- Databases & Information Systems (AREA)
- Theoretical Computer Science (AREA)
- Remote Sensing (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Telephonic Communication Services (AREA)
Abstract
The present invention is for acquisition terminal operating condition monitoring difficult problem in power information collection, it is proposed that a kind of visible detection method based on GIS.In power information collection, in order to ensure that the data of on-site terminal storage can gather in time, power information acquisition system needs timely to understand the operating condition of acquisition terminal, is needed for the acquisition terminal to break down in very first time timely processing.Spatial geography data of the invention based on GIS, with reference to special change transformer of the battalion with insertion collection in worksite, the public physical coordinates data for becoming transformer, acquisition terminal physical location is intuitively shown on map, the running status of real-time monitoring collection terminal and geographic area can be carried out is collected on map.This method can be applied to electricity consumption collection information system, can timely grasp the running status of collection in worksite terminal, supplement and perfect technological means of the power information acquisition system in monitoring site operation terminal.
Description
Technical field
The invention belongs to acquisition terminal FLT field, especially a kind of visualization of power information acquisition system
Monitoring method.
Background technology
Power information acquisition system is to realize information-based marketing management, automation, the necessary condition of modernization, seeks electric power
The technical support of pin and Demand-side modern management is achieved.Ensure the normal operation of power information acquisition system, be to comply with
The needs of social situations, it is the important bar for ensureing the sales service automatic business processings such as electric energy metrical, remote automatic meter reading, pre-payment
Part, it is the important means for lifting Electric Power Service in High.And in recent years, power information acquisition system obtains wide as power grid enterprises
The important support carrier of big power consumer electricity consumption data, has obtained large-scale application in the whole nation.As power information is adopted
The telecommunication of the more and more extensive application of collecting system, power information acquisition system and acquisition terminal is also faced with increasingly severeer
Challenge.Because there is communication module power supply is unstable, terminal and communication module electromagnetic interference are excessive, module power down and generation
Phenomena such as communication can not be recovered during failure, it is frequently upper offline to result in terminal, has a strong impact on the online rate of power information acquisition system,
So as to directly affect power information acquisition system normal use.The present invention is namely based on being adopted to power information for such a phenomenon proposition
The acquisition terminal monitoring method of collecting system.
The content of the invention
It is an object of the invention in place of overcome the deficiencies in the prior art, there is provided a kind of power information acquisition system it is visual
Change monitoring method, improve metering automation terminal fault locating accuracy,
The present invention solves its technical problem and takes following technical scheme to realize:
A kind of visualizing monitor method of power information acquisition system, it is characterised in that:Order performs following steps:
Step is (1):Taiwan area meter reading topological diagram is constructed, is layered and acquisition terminal is monitored;
Need to by the communication modes between acquisition terminal and main website on network topological diagram it is complete it is detailed show, clear and definite
After communication modes between acquisition terminal and main website, it is monitored respectively in Internet and operation layer, Internet is in main website front end processor
TCP is established between acquisition terminal to be connected;Operation layer makes acquisition terminal at regular intervals as main website reports heartbeat data;
Step is (2):Communication failure is diagnosed, by network tool, the acquisition terminal to break down diagnosed simultaneously
Record;
Step is (3):GIS platform is built, realizes that acquisition terminal visualizing monitor is analyzed;By building GIS platform, will gather
The geography information sampling input of terminal, inputs GIS platform, using battalion with the special of insertion collection in worksite by the failure cause being diagnosed to be
Become transformer, the public physical coordinates data for becoming transformer, visual displaying is carried out in GIS platform.
Moreover, (1) middle heartbeat data reported at intervals of 30 minutes step.
Moreover, step (2) described in network tool include, use ping instruments monitoring acquisition terminal network connection feelings
Condition;And the network routed path using tracert instruments monitoring acquisition terminal.
Moreover, step (3) in be diagnosed to be failure cause input GIS platform be to utilize Webservice application programs, will seek
Pin system carries out data with power information acquisition system and docked, by the acquisition terminal archive information importing telecommunications in marketing system
Acquisition system is ceased, forms terminal file.
The advantages and positive effects of the present invention are:
1st, on map real-time monitoring collection terminal running status, the record odd-numbered day is per station terminal operating mode online rate;Not
Under same map scale, the presence of real-time acquisition terminal carries out geographic area and collected, and shows the end in regional extent
End is online, not online, frequent upper offline ratio;By the daily statistics gatherer success rate to each terminal, system, which filters out, adopts
Collection archives, parameter such as issue at the distracter, analyze the high physical location central point of collection success rate, find strong because of movable signal
It is weak, cause the stability of terminal operating.
2nd, the present invention is had been further upgraded using power utilization information collection system, had in terms of lifting by displaying:Can and
When grasp in-site installation terminal running status, the timely processing within the very first time;Effectively solve due to regional signal
Power, cause the stability of terminal operating mode, supplement and improve technology of the power information acquisition system in monitoring site operation terminal
Means;Acquisition system operation maintenance personnel has found the shape of the terminal operating in institute compass of competency by directly perceived, visual mode
State.
Brief description of the drawings
Fig. 1 is the acquisition terminal monitoring method fundamental diagram of power information acquisition system of the present invention;
Fig. 2 is that topological diagram is transformed in the taiwan area meter reading of Tianjin of embodiment of the present invention Utilities Electric Co.;
Fig. 3 is that visual acquisition terminal monitors map schematic diagram.
Embodiment
Below in conjunction with the accompanying drawings and the invention will be further described by specific embodiment, and following examples are descriptive
, it is not limited, it is impossible to which protection scope of the present invention is limited with this.
A kind of visualizing monitor method of power information acquisition system, order perform following steps:
Step 1:Taiwan area meter reading topological diagram is constructed, is layered and acquisition terminal is monitored;
Need to by the communication modes between acquisition terminal and main website on network topological diagram it is complete it is detailed show, if net
Network topological diagram has mistake, then Internet routing node can be caused to lack, monitoring failure.It is logical between clear and definite acquisition terminal and main website
After news mode, it is monitored respectively in Internet and operation layer, Internet establishes TCP companies between main website front end processor and acquisition terminal
Connect.Operation layer makes acquisition terminal at regular intervals as main website reports heartbeat data, be spaced 30 minutes it is optimal.
Such as:Tianjin Utilities Electric Co. taiwan area meter reading topological diagram is built first, specifies the communication modes between acquisition terminal and main website.
By site inspection and topographical analysis, acquisition terminal is communicated and is monitored respectively with operation layer in Internet.In Internet
In monitoring, TCP is established with acquisition terminal by main website front end processor and is connected.If connection can be established, main website and collection are proved
Inter-terminal communication is normal.In operation layer monitoring, periodic monitoring is carried out to the power information acquisition terminal of scene operation, uses telecommunications
Breath acquisition terminal periodically carries out heartbeat data and reported and submitted, and terminal of often having reports heartbeat data, power information collection main website for every 30 minutes
These heartbeat datas are received, are stored in database, judge the running situation of power information acquisition terminal on this basis, if
Online.
Step 2:Communication failure is diagnosed;
By network tool, the acquisition terminal to break down is diagnosed and recorded.
By ping instruments, the network connection situation of acquisition terminal is monitored;
By tracert instruments, the network routed path of acquisition terminal is monitored;
By taking the acquisition terminal of certain taiwan area as an example, by ping and tracert network tools, it can be found that the acquisition terminal with
Communicated between power information acquisition system normal.If there is communication failure, the routing node of failure can be on tracert route road
Shown in the diagnosis of footpath.Using ping and tracert network tools, we can effectively be diagnosed to be the route to break down
Node and failure cause
Step 3:GIS platform is built, realizes that acquisition terminal visualizing monitor is analyzed
By building GIS platform, the geography information of acquisition terminal is sampled into input, the failure cause being diagnosed to be is inputted
GIS platform, using special change transformer of the battalion with insertion collection in worksite, the public physical coordinates data for becoming transformer, enter in GIS platform
The visual displaying of row.
Using Webservice application programs, marketing system is subjected to data with power information acquisition system and docked, will be sought
Acquisition terminal archive information in pin system imports power information acquisition system, forms terminal file;
State net GIS platform is relied on, using the data-interface provided in GIS platform, by the archive information of acquisition terminal, online
State and fault type importer net GIS platform, form visual acquisition terminal monitoring map.Then, on monitoring map
Specific acquisition terminal is clicked on, can further check the archive information of terminal
In summary, by being monitored to collection in worksite terminal.When acquisition terminal breaks down, by ping
The network tools such as tracert, the failure that acquisition terminal occurs is diagnosed, and diagnostic data is uploaded to by data-interface
State's net GIS platform, using special change transformer of the battalion with insertion collection in worksite, the public physical coordinates data for becoming transformer, put down in GIS
Platform carries out visual displaying.Meanwhile by the data interaction of marketing system and power information acquisition system, obtain acquisition terminal
Archive information, provide more fully technical support for live O&M.
Although disclosing embodiments of the invention and accompanying drawing for the purpose of illustration, those skilled in the art can manage
Solution:Do not departing from the present invention and spirit and scope of the appended claims in, it is various replace, change and modifications all be it is possible,
Therefore, the scope of the present invention is not limited to embodiment and accompanying drawing disclosure of that.
Claims (4)
1. a kind of visualizing monitor method of power information acquisition system, it is characterised in that:Order performs following steps:
Step is (1):Taiwan area meter reading topological diagram is constructed, is layered and acquisition terminal is monitored;
Need to by the communication modes between acquisition terminal and main website on network topological diagram it is complete it is detailed show, clearly gathering
After communication modes between terminal and main website, it is monitored respectively in Internet and operation layer, Internet is in main website front end processor with adopting
Collection terminal room establishes TCP connections;Operation layer makes acquisition terminal at regular intervals as main website reports heartbeat data;
Step is (2):Communication failure is diagnosed, by network tool, the acquisition terminal to break down is diagnosed and remembered
Record;
Step is (3):GIS platform is built, realizes that acquisition terminal visualizing monitor is analyzed;By building GIS platform, by acquisition terminal
Geography information sampling input, by the failure cause being diagnosed to be input GIS platform, utilize battalion with insertion collection in worksite special change become
Depressor, the public physical coordinates data for becoming transformer, visual displaying is carried out in GIS platform.
2. the visualizing monitor method of power information acquisition system according to claim 1, it is characterised in that:Step (1) in
Heartbeat data was reported at intervals of 30 minutes.
3. the visualizing monitor method of power information acquisition system according to claim 1, it is characterised in that:Step (2) in
Described network tool includes, and the network connection situation of acquisition terminal is monitored using ping instruments;And use tracert instruments
Monitor the network routed path of acquisition terminal.
4. the visualizing monitor method of power information acquisition system according to claim 1, it is characterised in that:Step (3) in
The failure cause input GIS platform being diagnosed to be is to utilize Web service application programs, and marketing system and power information are gathered
System carries out data docking, and the acquisition terminal archive information in marketing system is imported into power information acquisition system, forms terminal
Archives.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710518649.6A CN107404416A (en) | 2017-06-30 | 2017-06-30 | A kind of visualizing monitor method of power information acquisition system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710518649.6A CN107404416A (en) | 2017-06-30 | 2017-06-30 | A kind of visualizing monitor method of power information acquisition system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107404416A true CN107404416A (en) | 2017-11-28 |
Family
ID=60404597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710518649.6A Pending CN107404416A (en) | 2017-06-30 | 2017-06-30 | A kind of visualizing monitor method of power information acquisition system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107404416A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108241100A (en) * | 2017-12-28 | 2018-07-03 | 黄振强 | A kind of processing method and processing device of data |
CN109905290A (en) * | 2019-02-21 | 2019-06-18 | 国网山东省电力公司临沂供电公司 | A kind of strange land is for class's automatic warning system and method |
CN113629871A (en) * | 2021-08-12 | 2021-11-09 | 广西电网有限责任公司 | Wave recording master station optimized operation method applying source end wave recording information filtering |
CN116647443A (en) * | 2023-06-28 | 2023-08-25 | 广东昆仑信息科技有限公司 | Method and system for rapidly positioning network fault equipment in steel plant |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120306620A1 (en) * | 2011-05-31 | 2012-12-06 | General Electric Company | Systems and methods for alert visualization |
CN104077641A (en) * | 2013-03-28 | 2014-10-01 | 国家电网公司 | Power grid operation and emergency command method and power commanding system |
CN203951479U (en) * | 2014-06-25 | 2014-11-19 | 国网吉林省电力有限公司信息通信公司 | The power information acquisition terminal that possesses communication network signals collecting and GPS location |
CN104320311A (en) * | 2014-11-20 | 2015-01-28 | 国电南京自动化股份有限公司 | Heartbeat detection method of SCADA distribution type platform |
CN104360208A (en) * | 2014-12-05 | 2015-02-18 | 国家电网公司 | Acquisition failure analyzing and processing method of electricity utilization information acquisition operating and maintaining system |
CN206115680U (en) * | 2016-10-28 | 2017-04-19 | 国网河南省电力公司电力科学研究院 | Use electric information collection device |
-
2017
- 2017-06-30 CN CN201710518649.6A patent/CN107404416A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120306620A1 (en) * | 2011-05-31 | 2012-12-06 | General Electric Company | Systems and methods for alert visualization |
CN104077641A (en) * | 2013-03-28 | 2014-10-01 | 国家电网公司 | Power grid operation and emergency command method and power commanding system |
CN203951479U (en) * | 2014-06-25 | 2014-11-19 | 国网吉林省电力有限公司信息通信公司 | The power information acquisition terminal that possesses communication network signals collecting and GPS location |
CN104320311A (en) * | 2014-11-20 | 2015-01-28 | 国电南京自动化股份有限公司 | Heartbeat detection method of SCADA distribution type platform |
CN104360208A (en) * | 2014-12-05 | 2015-02-18 | 国家电网公司 | Acquisition failure analyzing and processing method of electricity utilization information acquisition operating and maintaining system |
CN206115680U (en) * | 2016-10-28 | 2017-04-19 | 国网河南省电力公司电力科学研究院 | Use electric information collection device |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108241100A (en) * | 2017-12-28 | 2018-07-03 | 黄振强 | A kind of processing method and processing device of data |
CN109905290A (en) * | 2019-02-21 | 2019-06-18 | 国网山东省电力公司临沂供电公司 | A kind of strange land is for class's automatic warning system and method |
CN113629871A (en) * | 2021-08-12 | 2021-11-09 | 广西电网有限责任公司 | Wave recording master station optimized operation method applying source end wave recording information filtering |
CN113629871B (en) * | 2021-08-12 | 2023-10-24 | 广西电网有限责任公司 | Optimized operation method of wave recording master station by using source end wave recording information filtering |
CN116647443A (en) * | 2023-06-28 | 2023-08-25 | 广东昆仑信息科技有限公司 | Method and system for rapidly positioning network fault equipment in steel plant |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8769085B2 (en) | Systems and methods for analyzing the health of networks and identifying points of interest in networks | |
CN105915398B (en) | Rural power grid fault based rapid detection and power restoration system and concentrator detection method thereof | |
CN107404416A (en) | A kind of visualizing monitor method of power information acquisition system | |
CN110658415B (en) | Low-voltage distribution line fault detection method and system | |
CN106532935B (en) | For carrying out the method and its system of secondary system of intelligent substation fault diagnosis | |
CN102231171A (en) | Calculation, comparison, analysis and loss reduction method for statistical line loss and theoretical line loss | |
CN107680194A (en) | A kind of information system for power enterprise automates cruising inspection system | |
US11063998B2 (en) | System and method for energy management information system reliability assurance | |
CN103632524A (en) | Multi-platform energy consumption monitoring system with various access ways | |
CN103605326A (en) | Real-time on-line energy monitoring and management system and energy management and optimization method | |
CN109584103A (en) | A kind of electric network fault fast reaction and educated decisions support system | |
CN103383769A (en) | Grid fault hidden danger management analytical method and system | |
CN106530653B (en) | Power information acquisition method | |
CN102338835B (en) | Power quality dynamic monitoring system | |
CN109581115B (en) | Power distribution network low-voltage diagnosis system and diagnosis method | |
CN204945365U (en) | Gate energy meter supervising device | |
CN103780660A (en) | GPU cluster monitoring system and method for issuing monitoring alarm | |
CN103545805A (en) | Modeling-based railway power supply arm monitoring method | |
CN111062825A (en) | Low-voltage fault diagnosis and rapid power restoration method based on mobile App | |
Zhou et al. | Research and Implementation of Distribution Network Operating Analysis Platform Based on Multi-source Heterogeneous Data | |
CN206115680U (en) | Use electric information collection device | |
CN208314554U (en) | A kind of substation monitoring system based on LabView and unmanned plane | |
CN103336213A (en) | In-situ diagnostic method and device used for on-line monitoring of transformer substation | |
CN203101929U (en) | Compressed air remote management system | |
CN103855800A (en) | Power network device state monitoring and diagnostic system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171128 |