CN104141480A - Slug sand-adding process for fracturing - Google Patents
Slug sand-adding process for fracturing Download PDFInfo
- Publication number
- CN104141480A CN104141480A CN201310523172.2A CN201310523172A CN104141480A CN 104141480 A CN104141480 A CN 104141480A CN 201310523172 A CN201310523172 A CN 201310523172A CN 104141480 A CN104141480 A CN 104141480A
- Authority
- CN
- China
- Prior art keywords
- sand
- slug
- add
- cycle
- ratio
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention relates to a slug sand-adding process for fracturing and belongs to the technical field of fracturing engineering for petroleum exploration and development. According to the process, the sand ratio is increased in the later period of a sand-adding phase of each slug sand-adding cycle of shale gas fracturing construction to form a high-sand-ratio phase, and the sand ratio in the phase is identical with that of the next sand-adding cycle. Through observation of the pressure change after the high-sand-ratio phase enters a stratum, subsequent construction is guided, and a fracturing construction task is finished.
Description
Technical field:
The present invention relates to a kind of pressure break slug and add sand process, belong to petroleum exploration and development fracturing engineering technical field.
Background technology:
Add in sand construction in petroleum exploration and development shale gas pressure break, usually adopt slug formula to add sand technique, be i.e., after the certain prepad fluid of pumping, add the sand stage and an insulating liquid stage of closelying follow is that a slug adds the sand cycle by one, multicycle, alternately to constructing the later stage, starts to add continuously sand to construction and finishes.Each cycle sand is than keeping a fixed value, a rear more last cycle sand of cycle is than high, this sand mode that adds is because a rear cycle sand is than improving suddenly, after easily causing the sand in this cycle to enter stratum, cause that construction pump pressure raises extremely, cause to add sand and stop in advance, or cause construction sand plug to cause constructing unsuccessfully.
Summary of the invention:
The object of the invention is to solve pressure anomaly in shale gas slug sand fracturing process raises, cause adding sand construction premature termination or failed defect, provide a kind of and slow down the pressure break slug that Fracturing Pressure abnormal ascending, raising pressure break add sand coincidence rate and add sand process.
The technical scheme of this process is as follows:
The present invention includes following steps:
1, pump into prepad fluid according to design;
2, pump into first slug and add the sand cycle.Start to add sand according to design sand ratio, within this cycle, add the front 80-90% of sand stage liquid measure, sand is than keeping a definite value, in the time adding sand liquid measure later stage 10-20%, carry high sand ratio, the sand ratio after raising is identical with the sand ratio in the second slug cycle of design, add after sand liquid measure when pumping into the period 1, stop sand, pump into the first slug by design and add the isolation liquid measure in the sand cycle, complete the first slug and add the construction of sand cycle.
3, pump into second slug and add the sand cycle.Start to add sand according to design sand ratio, within this cycle, add the front 80-90% of sand stage liquid measure, sand is than keeping a definite value, in the time adding surplus 20-10% of sand liquid measure later stage, carry high sand ratio, the sand ratio after raising is identical with the sand ratio in the 3rd slug cycle of design, add second round after sand liquid measure when pumping into, stop sand, pump into the second slug by design and add the isolation liquid measure in the sand cycle, complete the second slug and add the construction of sand cycle.
4, repeat above-mentioned 2,3 and pump into program, complete successively the follow-up each section of slug of this well and add the sand cycle.
5, complete and pump into each slug and add sand week after date, according to designing requirement, complete and add continuously sand pump and enter program, and replaced whole pressing crack construction task.
The present invention adds and adds the sand stage in the sand cycle at each slug of shale gas pressing crack construction, adding sand later stage increasing sand proportion, form a high sand ratio stage, this stage sand than the sand that adds the sand cycle with the next one than identical, enter pressure changing behind stratum by observing this high sand ratio stage, if pressure is without obvious fluctuation, pressing crack construction can normally carry out; The fluctuation if pressure obviously rises, can judge that current stratum is unfavorable for that follow-up high sand ratio adds sand construction, there is sand plug risk, but because this high sand ratio stage liquid measure increasing is few, the time is short, in the time causing pressure oscillation, in pit shaft, insulating liquid completes replacement substantially, can not cause and adds sand construction premature termination or construct unsuccessfully.
Detailed description of the invention:
Below in conjunction with embodiment, the present invention is further described in detail.
It is as follows that certain a bite shale gas well pressure break adds sand program:
In above-mentioned adding in sand program, each slug adds the sand cycle and adds the last 10-20% of sand stage liquid measure, increase a high sand ratio stage, this stage sand than the sand that adds the sand cycle with the next one than identical, enter pressure changing behind stratum by observing this high sand ratio stage, if pressure is without obvious fluctuation, pressing crack construction can normally carry out; The fluctuation if pressure obviously rises, can judge that current stratum is unfavorable for that follow-up high sand ratio adds sand construction, has sand plug risk, can reduce the sand ratio in follow-up each cycle, has continued construction.
Claims (2)
1. pressure break slug adds a sand process, it is characterized in that, adds the later stage in sand cycle at each slug, increases a high sand ratio stage, this stage sand than the sand that adds the sand cycle with next slug than identical.
2. a kind of pressure break slug according to claim 1 adds sand process, it is characterized in that, comprises the following steps:
(1) pump into prepad fluid according to design;
(2) pump into first slug and add the sand cycle.Start to add sand according to design sand ratio, within this cycle, add the front 80-90% of sand stage liquid measure, sand is than keeping a definite value, in the time adding surplus 20-10% of sand liquid measure later stage, carry high sand ratio, the sand ratio after raising is identical with the sand ratio in the second slug cycle of design, add after sand liquid measure when pumping into the period 1, stop sand, pump into the first slug by design and add the isolation liquid measure in the sand cycle, complete the first slug and add the construction of sand cycle;
(3) pump into second slug and add the sand cycle.Start to add sand according to design sand ratio, within this cycle, add the front 80-90% of sand stage liquid measure, sand is than keeping a definite value, in the time adding surplus 20-10% of sand liquid measure later stage, carry high sand ratio, the sand ratio after raising is identical with the sand ratio in the 3rd slug cycle of design, add second round after sand liquid measure when pumping into, stop sand, pump into the second slug by design and add the isolation liquid measure in the sand cycle, complete the second slug and add the construction of sand cycle;
(4) repeat above-mentioned (2), (3) pump into program, complete successively the follow-up each section of slug of this well and add the sand cycle;
(5) complete and pump into each slug and add sand week after date, according to designing requirement, complete and add continuously sand pump and enter program, and replaced whole pressing crack construction task.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310523172.2A CN104141480B (en) | 2013-10-29 | 2013-10-29 | A kind of pressure break slug adds sand process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310523172.2A CN104141480B (en) | 2013-10-29 | 2013-10-29 | A kind of pressure break slug adds sand process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104141480A true CN104141480A (en) | 2014-11-12 |
CN104141480B CN104141480B (en) | 2018-07-06 |
Family
ID=51850792
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310523172.2A Active CN104141480B (en) | 2013-10-29 | 2013-10-29 | A kind of pressure break slug adds sand process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104141480B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106593394A (en) * | 2017-01-23 | 2017-04-26 | 重庆矿产资源开发有限公司 | Shale gas fracturing stepping sand-adding method |
CN106761644A (en) * | 2016-12-27 | 2017-05-31 | 中国石油化工股份有限公司江汉油田分公司石油工程技术研究院 | The processing method that control pressure rises extremely in a kind of shale fracturing process |
CN107023285A (en) * | 2017-05-16 | 2017-08-08 | 华美孚泰油气增产技术服务有限责任公司 | A kind of shale gas reservoir hydraulic fracturing adds sand technique |
CN108222910A (en) * | 2018-01-22 | 2018-06-29 | 成都西油联合石油天然气工程技术有限公司 | A kind of fixed displacement slug formula fracturing technology |
CN111335862A (en) * | 2020-04-26 | 2020-06-26 | 中国石油天然气集团有限公司 | Variable viscosity sand fracturing method |
CN112240191A (en) * | 2019-07-19 | 2021-01-19 | 中国石油化工股份有限公司 | Shale gas fracturing sand adding method |
CN114592842A (en) * | 2020-12-04 | 2022-06-07 | 中国石油天然气股份有限公司 | Continental facies shale oil reservoir fracturing sand adding method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6863128B2 (en) * | 2001-10-24 | 2005-03-08 | Schlumberger Technology Corporation | Method of predicting friction pressure drop of proppant-laden slurries using surface pressure data |
US20090209438A1 (en) * | 2008-02-04 | 2009-08-20 | Sanjel Corporation | Low residue fluid fracturing system and method of use |
CN102562022A (en) * | 2012-03-02 | 2012-07-11 | 陕西延长石油(集团)有限责任公司研究院 | Process technology suitable for deep coal bed gas fracturing |
CN103244094A (en) * | 2013-05-16 | 2013-08-14 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | Carbonate rock multi-slug injection type fracturing method |
CN103306661A (en) * | 2012-11-29 | 2013-09-18 | 中国石油化工股份有限公司 | Method for controlling fracturing of multiple fractures of oil and gas field with natural micro-fracture-developed reservoir stratum |
-
2013
- 2013-10-29 CN CN201310523172.2A patent/CN104141480B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6863128B2 (en) * | 2001-10-24 | 2005-03-08 | Schlumberger Technology Corporation | Method of predicting friction pressure drop of proppant-laden slurries using surface pressure data |
US20090209438A1 (en) * | 2008-02-04 | 2009-08-20 | Sanjel Corporation | Low residue fluid fracturing system and method of use |
CN102562022A (en) * | 2012-03-02 | 2012-07-11 | 陕西延长石油(集团)有限责任公司研究院 | Process technology suitable for deep coal bed gas fracturing |
CN103306661A (en) * | 2012-11-29 | 2013-09-18 | 中国石油化工股份有限公司 | Method for controlling fracturing of multiple fractures of oil and gas field with natural micro-fracture-developed reservoir stratum |
CN103244094A (en) * | 2013-05-16 | 2013-08-14 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | Carbonate rock multi-slug injection type fracturing method |
Non-Patent Citations (1)
Title |
---|
蒋廷学: "《页岩油气水平井压裂裂缝复杂性指数研究及应用展望》", 《石油钻探技术》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106761644A (en) * | 2016-12-27 | 2017-05-31 | 中国石油化工股份有限公司江汉油田分公司石油工程技术研究院 | The processing method that control pressure rises extremely in a kind of shale fracturing process |
CN106593394A (en) * | 2017-01-23 | 2017-04-26 | 重庆矿产资源开发有限公司 | Shale gas fracturing stepping sand-adding method |
CN107023285A (en) * | 2017-05-16 | 2017-08-08 | 华美孚泰油气增产技术服务有限责任公司 | A kind of shale gas reservoir hydraulic fracturing adds sand technique |
CN108222910A (en) * | 2018-01-22 | 2018-06-29 | 成都西油联合石油天然气工程技术有限公司 | A kind of fixed displacement slug formula fracturing technology |
CN112240191A (en) * | 2019-07-19 | 2021-01-19 | 中国石油化工股份有限公司 | Shale gas fracturing sand adding method |
CN111335862A (en) * | 2020-04-26 | 2020-06-26 | 中国石油天然气集团有限公司 | Variable viscosity sand fracturing method |
CN114592842A (en) * | 2020-12-04 | 2022-06-07 | 中国石油天然气股份有限公司 | Continental facies shale oil reservoir fracturing sand adding method |
Also Published As
Publication number | Publication date |
---|---|
CN104141480B (en) | 2018-07-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104141480A (en) | Slug sand-adding process for fracturing | |
CN105626006B (en) | Low-permeability oil deposit CO2Drive technical limit well space and determine method | |
CN106097120B (en) | A kind of water-drive pool natural water encroachment, water filling and exploitation equilibrium state determination method | |
CN107989592B (en) | Staged fracturing method for horizontal well | |
CN110984943B (en) | Limit clustering perforation fracturing method for long horizontal well of compact reservoir | |
MX365203B (en) | A method of increasing efficiency in a hydraulic fracturing operation. | |
WO2015048021A3 (en) | Method of optimizing conductivity in a hydraulic fracturing operation | |
MX2016015616A (en) | Applications of ultra-low viscosity fluids to stimulate ultra-tight hydrocarbon-bearing formations. | |
CA2831500C (en) | System and method for improved propped fracture geometry for high permeability reservoirs | |
CN103498663B (en) | A kind of sucker rod pump hoisting system pumping technological parameter defining method and device | |
MY174671A (en) | Method for producing crude oil using surfactants based on c16c18 containing alkyl-propoxy surfactants | |
CN109783765B (en) | Energy analysis method for fracture-cavity type oil reservoir interference well testing | |
CN104832156A (en) | Method for predicting yield of gas well | |
CN109209332B (en) | Acid slickwater composite fracturing method for shale gas horizontal well | |
CN109826590B (en) | Water plugging and fracturing method for high-water-content old well in low-permeability oil and gas field | |
CN103678927B (en) | The method determining Casing In Thermal Recovery Wells overall strain | |
CN111058824B (en) | Temporary plugging and shunting acidification method for strong heterogeneous sandstone reservoir through sieve tube | |
MY175346A (en) | Methods for acidizing a subterranean formation using a stabilized microemulsion carrier fluid | |
MX2012004023A (en) | Method for tertiary oil production using surfactant mixtures. | |
CN104389566A (en) | Method for judging gas fleeing time | |
RU2474676C1 (en) | Multiformation oil deposit development method | |
RU2494246C1 (en) | Treatment method of bore-hole zone | |
CN104632173A (en) | Fracture-network fracturing layer selection method for non-natural fracture tight reservoir | |
CN112727426B (en) | Real-time decision-making method for deep shale gas fracturing process | |
CN104989349A (en) | Constant-volume gas-injection well gas injection quantity design method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |