WO2024007614A1 - Construction control method for partition type concrete diaphragm wall anchorage foundation - Google Patents

Construction control method for partition type concrete diaphragm wall anchorage foundation Download PDF

Info

Publication number
WO2024007614A1
WO2024007614A1 PCT/CN2023/081102 CN2023081102W WO2024007614A1 WO 2024007614 A1 WO2024007614 A1 WO 2024007614A1 CN 2023081102 W CN2023081102 W CN 2023081102W WO 2024007614 A1 WO2024007614 A1 WO 2024007614A1
Authority
WO
WIPO (PCT)
Prior art keywords
mud
construction
depth
phase
wall
Prior art date
Application number
PCT/CN2023/081102
Other languages
French (fr)
Chinese (zh)
Inventor
杨钊
陈培帅
饶为胜
姬付全
刘朋飞
李德杰
马超
王新龙
贺祖浩
朱俊涛
邱敏
赵旭
肖靖
李嘉成
曾旭涛
李雪松
杨睿
石章入
张瑞元
Original Assignee
中交第二航务工程局有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中交第二航务工程局有限公司 filed Critical 中交第二航务工程局有限公司
Publication of WO2024007614A1 publication Critical patent/WO2024007614A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/30Foundations made with permanent use of sheet pile bulkheads, walls of planks, or sheet piling boxes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Definitions

  • the invention relates to the field of construction of compartment-type ground connecting wall anchor foundations. More specifically, the present invention relates to a construction control method for a bay-type floor-to-wall anchorage foundation.
  • anchor foundation types include underground diaphragm walls, caissons, tunnel anchors, etc.
  • underground diaphragm walls and caissons are widely used in areas with deep overburden.
  • conventional underground diaphragm wall anchorage foundations are less economical when the bearing layer is too deep, and caisson foundations are only suitable for sand layers.
  • a compartment-type continuous wall anchorage foundation is proposed to overcome the shortcomings of conventional underground diaphragm wall anchorage foundations and caisson foundations.
  • the compartment-type ground connection wall anchorage foundation is different from the conventional underground diaphragm wall anchorage foundation and caisson foundation. It has unique engineering features such as row-type steel mesh joints for ground connection walls and large-depth foundation reinforcement. If according to the traditional The construction technology, construction speed and project quality could not meet the requirements. In order to speed up the construction speed of anchorage foundation and improve the construction quality, it is necessary to propose a construction control method suitable for compartment-type ground wall anchorage foundation. For this reason, the construction control method of the compartment-type ground wall anchorage foundation of this application is proposed, which simultaneously meets the requirements of construction speed and project quality.
  • One object of the present invention is to provide a construction control method for a compartment-type ground connecting wall anchorage foundation.
  • the compartment-type ground connecting wall anchorage foundation has the advantages of both a ground connection wall anchorage foundation and a caisson anchorage foundation.
  • the ground strata It has good adaptability and the construction control method of the present invention can improve the construction quality of the anchorage foundation and speed up the construction speed.
  • a construction control method for compartment-type ground wall anchorage foundation including:
  • Step 1 Design the basic structure of the compartment-type ground connection wall anchorage, and set the intersection points of the compartment-type ground connection walls as the first-phase trough sections, and the second-phase trough sections are set at non-compartment-type ground connection walls. at the intersection;
  • Step 2 Splice the processed first-phase steel box joint segments into a whole at the construction site to form a first-phase steel box joint, and the longitudinal deviation of the first-phase steel box joint after splicing is less than 5mm;
  • Step 3 The first phase of trough construction
  • Step 4 Install the first-phase steel box joints in the first-phase trough
  • Step 5 Visually pour the steel box concrete in the first phase of the trough to complete the construction of the first phase of the trough section;
  • Step 6 After the construction of the first phase trough section is completed, the second phase steel cage will be processed according to the design drawings, and then the second phase trough construction will be carried out, the second phase steel cage will be installed, and concrete will be poured to complete the second phase trough section construction;
  • Step 7 After the construction of the above-mentioned ground connecting wall is completed, carry out the foundation reinforcement construction of the partition type ground connecting wall;
  • Step 8 After the foundation reinforcement construction is completed, the excavation of the foundation pit inside the compartment-type ground connection wall is carried out, and then the underwater bottom seal, bottom plate, core filling body, and roof are constructed from bottom to top in the foundation pit to complete the compartment. Construction of ground-to-ground wall anchorage foundation.
  • the designed basic structure of compartment-type ground-to-wall anchorage includes:
  • the partition-type connecting wall includes an outer connecting wall and an inner dividing connecting wall.
  • the inner dividing connecting wall divides the enclosed area surrounded by the outer connecting wall into several small compartments;
  • Foundation reinforcement which includes ultra-high-pressure jet grouting pile reinforcement in the closed area surrounded by the outer ground connection wall;
  • the internal structure includes an underwater bottom seal, a bottom plate, a core-filling body, and a top plate arranged in sequence from the bottom at least.
  • the method for measuring the longitudinal deviation of the first-phase steel box joints spliced into a whole in step two is:
  • first-phase steel box joint Place the first-phase steel box joint flat on a tire frame whose flatness meets the design requirements, and arrange three light beams on the central axis of the upper surface of the first-phase steel box joint. Learn from prisms, which are evenly arranged at the upper, middle and lower points along the length of the first-phase steel box joint;
  • a total station is arranged outside the joint of the steel box in the first phase to collect the geodetic coordinates of three optical prisms (x 1 , y 1 , z 1 ), (x 2 , y 2 , z 2 ), (x 3 , y 3 , z 3 ), and calculate the deviations of the first-phase steel box joints in the x and z directions respectively:
  • n x (max(x 1 ,x 2 ,x 3 ) ⁇ min(x 1 ,x 2 ,x 3 ));
  • n z (max(z 1 ,z 2 ,z 3 ) ⁇ min(z 1 , z 2 ,z 3 ));
  • the trench holes are filled with bentonite mud, and the mud performance is automatically adjusted through the mud intelligent control system.
  • the mud intelligent control system includes a mud performance parameter detection device and a circulating mud pool. , a new slurry tank, a new slurry expansion tank and a pulping station.
  • the mud performance parameter detection device is used to detect the specific gravity, PH value, viscosity and sand content rate parameters of the mud in the circulating mud tank.
  • the circulating mud tank, new slurry tank, The new slurry expansion tank and the pulping station are connected in sequence.
  • a second pump is provided in the new slurry tank, which is used to pump the mud in the new slurry tank to the circulating mud tank.
  • a first pump is provided in the new slurry expansion tank.
  • the specific control method of the mud intelligent control system is:
  • the second pump is started to pump the new slurry in the new slurry pool to the circulation Mud pool, until the specific gravity of the mud in the circulating mud pool is less than 1.2, the pH value is less than 11, the viscosity is less than 35s, and the sand content is less than 4%, the second pump is turned off and the volume V 1 pumped into the circulating mud pool from the new mud pool is recorded;
  • the pulping station is started at the same time, and new pulp is mixed according to the preset new pulp ratio.
  • the mixing volume is V 1 and is transported to the new pulp expansion tank for expansion. After expansion for 24 hours, the first pulp is opened.
  • the pump pumps the fully expanded new slurry to the new slurry pool, thus completing the intelligent control of mud performance in one cycle.
  • the troughing detection equipment is used to detect the verticality of the troughing every 20m or 4h.
  • the troughing detection equipment includes an industrial control host, an electric winch, and a detection probe. , a pair of steel wire ropes and cables, the electric hoist is arranged at the center of the slot of the tank section to be tested, the detection probe is connected to the electric hoist through a pair of steel wire ropes on both sides and the cable in the middle and is located in the tank section to be tested Inside, the electric winch is also connected to the industrial control host through a cable. The drum on the electric winch is wound around a pair of steel wire ropes and cables.
  • the drum of the electric winch is driven by an AC motor to rotate forward and reverse.
  • a depth sensor is also provided, which is used to obtain the depth of the detection probe.
  • the detection probe includes an anti-twist connector, a sealing cylinder, a gyroscope, a fixed long rod, four measuring arms and a fixed disc.
  • An anti-twist connector is located at the top of the sealing cylinder, and a pair of steel wire ropes are symmetrically connected to the anti-twist connector.
  • the gyroscope is installed inside the sealing cylinder and is used to measure the azimuth angle of the detection probe.
  • the cable is connected to the gyroscope after passing through the center of the anti-twist connector, the fixed long rod is connected to the bottom center of the sealing cylinder, and four measuring arms are arranged in an orthogonal relationship at the bottom of the sealing cylinder, so
  • the top of the measuring arm is hinged with the sealing cylinder and is set by a pressure spring to rotate only along the plane formed by the vertical axis of the measuring arm and the fixed long rod.
  • An inclination sensor is provided on the top of the measuring arm for measuring the opening of the measuring arm.
  • the center of the fixed disk has a through hole through which the fixed long rod passes, and a ring of blocking rings is provided on the top surface of the fixed disk, which is used to limit the lower ends of the four measuring arms within it, and the
  • the industrial control host is used to control the action of the electric winch, read the data obtained by the depth sensor, gyroscope and inclination sensor and calculate the display results.
  • the method for the groove detection equipment to detect the verticality of the groove is:
  • step S6 Determine whether the measuring arm is open based on the data obtained by the inclination sensor, if so, proceed to the next step, otherwise jump to step S5;
  • the industrial control host calculates the groove width, length and verticality based on the read depth, probe azimuth angle and measuring arm opening angle information, and draws the groove wall depth-groove width curve and groove wall depth-groove length curve , depth-trough verticality curve and trough verticality; the specific method for calculating the trough width, length and verticality is as follows:
  • the depth of the measuring point is corrected as follows:
  • the rectangular center coordinates are the slot wall center coordinates. Connect the left edge depths of the slot wall centers to form a slot oblique curve, which is aligned with the axis in the width and length directions of the slot section.
  • the deviation angle is the corresponding verticality;
  • step S9 Determine whether the detection probe reaches the notch of the detection groove section according to the depth h j . If h j ⁇ 0, proceed to the next step, otherwise continue to step S6;
  • the concrete pouring visualization in step five specifically includes two parts: real-time monitoring of underwater concrete liquid level and real-time monitoring of conduit installation length;
  • the specific real-time monitoring of underwater concrete liquid level is as follows: when making the steel box joints of the first phase and the steel cage of the second phase, a temperature optical fiber with a resolution of 0.2m is installed in advance. When the concrete is poured, the temperature optical fiber is monitored through the temperature optical fiber demodulation equipment. Temperature changes, according to changes in temperature, reflect the concrete liquid level;
  • Real-time monitoring of the installation length of the conduit is as follows: installing a chip containing conduit length information on each section of conduit, and installing an electromagnetic induction device on the conduit frame. When each section of conduit is removed, the electromagnetic induction device automatically counts and reduces the total length of the conduit. Divide the length of the removed conduit into the length of the remaining conduit.
  • the foundation pit excavation control method in step eight is:
  • a crane covering the inner compartment is arranged at the intersection of the inner dividing ground connecting wall, and a belt-type horizontal conveyor is arranged on the top of the inner dividing connecting wall to transport the earth excavated from the inner compartment to the outside of the foundation pit;
  • Compartments are excavated in layers.
  • the excavation elevation of each compartment is automatically collected through sonar detection technology and transmitted to the control system.
  • the excavation depth of each layer is 2m.
  • the control system issues an alert;
  • Strain gauges are arranged in advance on the steel cage of the ground connection wall, and the stress value is obtained in real time through the control system.
  • the control system issues a Alarm, stop excavation of the compartment with deeper mud surface, and excavate adjacent compartments with shallower mud surface until the height difference of mud surface in all adjacent compartments is less than 0.3m, continue to excavate the next layer until all compartments are completed
  • the allowable stress threshold is the allowable tensile stress of poured concrete.
  • This application proposes a new construction method for the designed special compartment-type ground wall anchorage foundation structure, which can improve the construction quality of the anchorage foundation and speed up the construction speed.
  • the compartment-type ground connecting wall anchorage foundation of this application has the advantages of both ground connecting wall anchorage foundation and caisson anchorage foundation. It has good stratum adaptability and overcomes the shortcomings of conventional underground diaphragm wall anchorage foundation and caisson shaft foundation. , to meet the construction needs of super-large suspension bridges.
  • this application uses highly adaptable troughing detection equipment to detect the verticality of the trough every 20m or 4h to achieve "diligently measure and correct" and ensure high-precision troughing.
  • This equipment detects The accuracy is not affected by the properties of the mud. There is no need to clean holes and replace slurry in advance. There is no detection blind area.
  • the verticality of the slot can be automatically calculated and an alarm will be issued based on the set threshold.
  • the three-dimensional hole shape of the slot can be generated in real time.
  • this application uses the height of the underwater concrete liquid level and the installation length of the conduit to visualize the pouring, reflecting the progress of the underwater concrete pouring and the buried depth of the conduit in real time to ensure that the conduit is not pulled out of the concrete and remains 2
  • the burial depth of ⁇ 4m controls the quality of underwater concrete pouring and avoids underwater concrete pouring accidents caused by excessively deep buried pipes or misoperation of pulling out the pipes.
  • This application uses intelligent construction control methods for foundation pit earth excavation to achieve rapid excavation of compartment-type ground-to-wall dry excavation and balanced soil extraction from each compartment during underwater excavation to achieve efficient and safe construction.
  • Figure 1 is a schematic plan view of the compartment-type ground wall anchorage foundation of the present invention
  • Figure 2 is an A-A cross-sectional view of the compartment-type ground wall anchorage foundation in Figure 1 of the present invention
  • Figure 3 is a schematic diagram of the longitudinal deviation measurement method of the first-phase steel box joint of the present invention.
  • Figure 4 is a schematic structural diagram of the mud intelligent control system of the present invention.
  • Figure 5 is a schematic plan view of the floor connecting wall of the present invention.
  • Figure 6 is a schematic structural diagram of the groove detection equipment of the present invention.
  • Figure 7 is a schematic structural diagram of the detection probe of the groove detection equipment of the present invention.
  • Figure 8 is a flow chart of the detection process and program control of the groove detection equipment of the present invention.
  • Figure 9 is a top view of the position of the measuring arm during the detection process of the groove detection equipment of the present invention.
  • Figure 10 is a front view of the position of the measuring arm during the detection process of the groove detection equipment of the present invention.
  • Figure 11 is a schematic diagram of the three-dimensional shape of the groove wall detected by the groove detection equipment of the present invention.
  • Figure 12 is a control flow chart for foundation pit excavation according to the present invention.
  • the present invention provides a construction control method for a compartment-type ground wall anchorage foundation, including:
  • Step 1 Design the basic structure of the bay-type ground connecting wall anchorage, as shown in Figure 1 and Figure 2, and set the intersection points of the bay-type ground connecting walls as the first phase trough section 16 and the second phase trough section 17 They are all installed at the non-intersection points of the partition wall, as shown in Figure 5;
  • Step 2 Transport the 9-meter first-phase steel box joint 9 sections processed in the factory to the construction site, and splice them into a whole at the construction site to form the first-phase steel box joint 9, and the first-phase steel box joint after the splicing is completed 9. Longitudinal deviation less than 5mm is qualified;
  • Step 3 The first phase of troughing construction; when the frequency of the amplitude of the guide wall opening wire rope 21 exceeding 5cm per unit time is not greater than 0.2 or the deflection angle of the milling bucket is not greater than 0.05° or the plane coordinate offset of the milling bucket is not greater than 7.5cm, The groove formation is qualified and the first phase of groove formation is completed;
  • Step 4 Install the first-phase steel box joint 9 in the first-phase trough; when the first-phase steel box joint 9 enters the trough, use the intelligent guide frame to guide and level the first-phase steel box joint 9 to ensure that the first-phase steel box joint 9 9 Installation verticality.
  • the intelligent guide frame has an automatic leveling function, which can eliminate the impact of the height difference of the guide wall on the verticality of the installation of the first-phase steel box joint 9;
  • Step 5 Visually pour the steel box concrete in the first phase of the trough to complete the construction of the first phase of trough section 16;
  • Step 6 After the construction of the first phase trough section 16 is completed, the second phase steel cage will be processed according to the design drawings, and then the second phase trough construction, installation of the second phase steel cage, and concrete pouring will be carried out to complete the second phase trough section 17 construction;
  • Step 7 After the construction of the above-mentioned ground connection wall is completed, the foundation reinforcement construction of the compartment-type ground connection wall is carried out; the foundation reinforcement construction technology is ultra-high pressure rotary spraying process, and before the official construction, pilot hole construction is required.
  • pilot hole construction When constructing the pilot hole, control the verticality of the pilot hole at the bottom of the drill pipe so that the verticality of the pilot hole is not greater than 1/500.
  • Step 8 After the foundation reinforcement construction is completed, the excavation of the foundation pit inside the compartment-type ground connecting wall is carried out. During the excavation of the foundation pit, an intelligent deburring robot is used to chisel the wall surface, and then the process is carried out from bottom to top in the foundation pit. During the construction of underwater bottom seal 4, bottom plate 5, core filling 6, and roof 7, a large-volume concrete temperature control system was used to control the condensate water system based on temperature sensor monitoring data to ensure that bottom plate 5, core filling 6, and roof 7 There will be no temperature cracks, and the construction of the compartment-type ground-to-wall anchorage foundation will be completed.
  • the shaded part is the first-stage tank section 16
  • the white part between the shaded parts is the second-stage tank section 17 .
  • the first-phase trench section 16 is constructed first. After the construction of the first-phase trench sections 16 adjacent to a certain second-phase trench section 17 is completed, the second-phase trench between the completed first-phase trench sections 16 can be constructed. Paragraph 17.
  • the trench is dug first, and after the trenching is completed, the steel box joint 9 of the first phase is placed into the dug trench section; during the construction of the trench section 17 of the second phase, the trench is dug first, and after the trenching is completed , place the second-stage steel cage into the dug trench section, and then pour concrete to complete the construction of the entire partition-type ground connection wall.
  • the designed compartment-type ground-to-wall anchorage infrastructure includes:
  • a compartment-type connecting wall includes an outer connecting wall 1 and an inner dividing connecting wall 2.
  • the inner dividing connecting wall 2 divides the closed area surrounded by the outer connecting wall 1 into several small compartments;
  • Foundation reinforcement 3 which includes ultra-high pressure jet grouting pile reinforcement in the closed area surrounded by the outer ground wall 1;
  • the internal structure includes an underwater bottom seal 4, a bottom plate 5, a core filling body 6, and a top plate 7 arranged in sequence at least from the bottom.
  • the longitudinal deviation measurement method of the first-phase steel box joint 9 that is spliced into a whole in the second step is:
  • first-phase steel box joint 9 Place the first-phase steel box joint 9 flatly on a tire frame whose flatness meets the design requirements, and arrange three sections on the central axis of the upper surface of the first-phase steel box joint 9
  • An optical prism 8 is evenly arranged at the upper, middle and lower points along the length direction of the primary steel box joint 9;
  • n x (max(x 1 ,x 2 ,x 3 ) ⁇ min(x 1 ,x 2 ,x 3 ));
  • n z (max(z 1 ,z 2 ,z 3 ) ⁇ min(z 1 , z 2 ,z 3 ));
  • the mud intelligent control system It includes a mud performance parameter detection device 11, a circulating mud tank 12, a new slurry tank 13, a new slurry expansion tank 14 and a pulping station 15.
  • the mud performance parameter detection device 11 is used to detect the specific gravity and PH of the mud in the circulating mud tank 12. value, viscosity, and sand content rate parameters.
  • the circulating mud tank 12, the new slurry tank 13, the new slurry expansion tank 14, and the pulping station 15 are connected in sequence.
  • the new slurry tank 13 is provided with a second pump, which is used to pump the new slurry.
  • the mud in the slurry tank 13 is pumped to the circulating mud tank 12.
  • the new slurry expansion tank 14 is provided with a first pump, which is used to pump the mud in the new slurry expansion tank 14 to the new slurry tank 13.
  • the circulating mud The mud in the pool 12 is filled into the slot hole;
  • the specific control method of the mud intelligent control system is:
  • the second pump is started to pump the new slurry in the new mud pool 13 Pump to the circulating mud pool 12 until the specific gravity of the mud in the circulating mud pool 12 is less than 1.2, the PH value is less than 11, the viscosity is less than 35s, and the sand content is less than 4%, then turn off the second pump and record the circulating mud pumped into the new mud pool 13 Volume V 1 of pool 12;
  • the pulping station 15 When the second pump is started, the pulping station 15 is started at the same time, and new pulp is mixed according to the preset new pulp ratio.
  • the mixing volume is V 1 and is transported to the new pulp expansion tank 14 for expansion. After expansion for 24 hours, open
  • the first pump pumps the fully expanded new slurry to the new slurry tank 13, which completes the intelligent control of mud performance in one cycle.
  • the trench holes are filled with bentonite mud, and the mud performance is automatically adjusted through the mud intelligent control system.
  • the mud intelligent control system and method automatically compares the performance parameters of the mud in the tank with the performance parameters required by the specification, automatically calculates the amount of additives that need to be added, and realizes intelligent adjustment of the mud performance through the automatic feeding module to ensure that the tank is completed with high-quality mud. quality.
  • the above-mentioned automation process is that the mud intelligent control system is equipped with a controller. After automatically acquiring data and comparing it, it automatically controls the actions of each equipment. This is a conventional control technology method and will not be described again here.
  • the troughing detection equipment is used to detect the verticality of the troughing every 20m or 4h.
  • the trough detection equipment includes an industrial control host 18, an electric winch 19, a detection probe 20, a pair of wire ropes 21 and cables 22.
  • the electric winch 19 is arranged at the center of the slot of the trough section 23 to be tested, and the detection probe 20 passes through both sides.
  • a pair of steel wire ropes 21 and the middle cable 22 are connected to the electric winch 19 and are located in the tank section 23 to be tested.
  • the electric winch 19 is also connected to the industrial control host 18 through the cable 22.
  • the winder on the electric winch 19 The drums are respectively wound around a pair of wire ropes 21 and cables 22.
  • the drum of the electric hoist 19 is driven by an AC motor to rotate forward and reverse.
  • a depth sensor is also provided in the electric hoist 19, which is used to obtain the location of the detection probe 20.
  • the detection probe 20 includes an anti-twist connector 24, a sealing cylinder 25, a gyroscope 26, a fixed long rod 27, four measuring arms 28 and a fixed disk 29.
  • the anti-twist connector 24 is located in the dense On the top of the sealing cylinder 25, a pair of steel wire ropes 21 are symmetrically connected to the anti-twist connector 24.
  • the gyroscope 26 is disposed inside the sealing cylinder 25 for measuring the azimuth angle of the detection probe 20.
  • the cable 22 After passing through the center of the anti-twist connector 24, it is connected to the gyroscope 26.
  • the fixed long rod 27 is connected to the bottom center of the sealing cylinder 25.
  • Four measuring arms 28 are arranged in an orthogonal relationship on the sealing cylinder. At the bottom of the sealing cylinder 25, the top of the measuring arm 28 is hinged with the sealing cylinder 25 and is set by a pressure spring to rotate only along the plane formed by the vertical axis of the measuring arm 28 and the fixed long rod 27.
  • the top of the measuring arm 28 is provided with The inclination sensor 30 is used to measure the opening angle of the measuring arm 28.
  • the center of the fixed disk 29 has a through hole through which the fixed long rod 27 passes.
  • the industrial control host 18 is used to control the action of the electric winch 19, read the data acquired by the depth sensor, the gyroscope 26 and the inclination sensor 30 and calculate the display results.
  • the verticality of the trough is detected every 20m or 4 hours using highly adaptable troughing detection equipment to achieve "diligently measure and correct" and ensure high-precision troughing.
  • This system The detection accuracy is not affected by the properties of the mud, and there is no need to clean the hole in advance. There is no detection blind area during slurry replacement. It can automatically calculate the verticality of the slot and issue an alarm based on the set threshold. It can generate a three-dimensional hole shape of the slot in real time.
  • the four measuring arms 28 are rectangularly distributed around the fixed long rod 27 with the fixed long rod 27 as the center.
  • the four measuring arms 28 are limited by the fixed disc 29 as shown in Figure 7.
  • the four measuring arms 28 open outwards under the action of the pressure spring, as shown in Figure 10.
  • the steel wire rope 21 is an anti-twist steel wire rope 21, and the drum of the electric winch 19 is driven by an AC motor to rotate forward and reverse, and is used to lower or lift the detection probe 20.
  • the anti-twist connector 24 is located at the top of the sealing cylinder 25 to connect the steel wire rope 21 and the probe cable 22 to the detection probe 20 while preventing the detection probe 20 from being greatly twisted.
  • the method for detecting the verticality of the groove by the groove detection equipment is:
  • step S6 Determine whether the measuring arm 28 is open based on the data obtained by the inclination sensor 30, if so, proceed to the next step, otherwise jump to step S5;
  • the industrial control host computer 18 calculates the groove width, length and verticality based on the read depth, probe azimuth angle, and measuring arm 28 opening angle information, and draws the groove wall depth-groove width curve, groove wall depth-groove formation Length curve, depth-trough verticality curve and trough verticality; the specific method for calculating the trough width, length and verticality is as follows:
  • the half-slot width detected by the measuring arms 281 and 283 is calculated through traditional geometric methods:
  • the four measuring points are all measured by the detection probe 20 at the same depth position, due to possible differences in the opening angles of the four measuring arms 28, the actual depths of the measuring points may not be consistent and cannot be obtained by simply adding the half-slot widths.
  • For the slot width calculate the depth corresponding to the bottom of the measuring arm 28 through the depth corresponding to the top of the measuring arm 28. The depth of the measuring point should be corrected according to the following formula:
  • the rectangular center coordinates are the slot wall center coordinates. Connect the left edge depths of the slot wall centers to form a slot oblique curve, which is aligned with the axis in the width and length directions of the slot section.
  • the deviation angle is the corresponding verticality;
  • step S9 Determine whether the detection probe 20 reaches the notch of the detection groove section according to the depth h j . If h j ⁇ 0, proceed to the next step, otherwise continue to step S6;
  • the detection accuracy of the gyroscope 26 used in this application is 0.5°
  • the detection accuracy of the inclination sensor 30 is 0.07°
  • the depth sensor accuracy is 0.2%, which makes the overall detection accuracy of the entire trough detection equipment higher and becomes more complete.
  • the inspection operation of the groove inspection equipment is fast and convenient.
  • the inspection equipment is small in weight, easy to move, and the equipment is simple to operate.
  • the time to complete the inspection of a single groove section is less than 10 minutes.
  • the four measuring arms 28 can be supported on the four sides of the groove section respectively, and the groove can be completed in one go. Detection of width, length and verticality improves detection efficiency.
  • the visualization of concrete pouring in step five specifically includes two parts: real-time monitoring of underwater concrete liquid level and real-time monitoring of conduit installation length;
  • the specific real-time monitoring of underwater concrete liquid level is as follows: when making the first-phase steel box joint 9 and the second-phase steel cage, temperature optical fibers with a resolution of 0.2m are installed in advance. During concrete pouring, the temperature optical fibers are monitored through temperature optical fiber demodulation equipment. The temperature change reflects the height of the concrete liquid level according to the temperature change; the principle used is that when concrete is poured, hydration heat will be released, resulting in a temperature difference with the ambient temperature. The part of the temperature optical fiber buried in the concrete and the part in the environment, There is a temperature difference to judge the interface between concrete and the environment;
  • Real-time monitoring of the installation length of the conduit is as follows: installing a chip containing conduit length information on each section of conduit, and installing an electromagnetic induction device on the conduit frame. When each section of conduit is removed, the electromagnetic induction device automatically counts and reduces the total length of the conduit. Divide the length of the removed conduit into the length of the remaining conduit.
  • the concrete pouring elevation can be measured in real time using sensors installed in advance at the first-stage steel box joint 9 or inside the second-stage steel cage.
  • an intelligent conduit that can automatically record the length of the conduit
  • visual pouring can be achieved.
  • the progress of the underwater concrete pouring and the burial depth of the conduit can be reflected in real time, ensuring that the conduit is not pulled out of the concrete and maintains a burial depth of 2 to 4m, thereby controlling the quality of underwater concrete pouring. Avoid underwater concrete pouring accidents caused by burying pipes too deep or pulling out pipes by mistake.
  • the foundation pit excavation control method in step eight is:
  • Compartments are excavated in layers.
  • the excavation elevation of each compartment is automatically collected through sonar detection technology and transmitted to the control system.
  • the excavation depth of each layer is 2m.
  • the control system issues an alert;
  • Strain gauges are arranged in advance on the steel cage of the ground connection wall, that is, the stress and strain monitoring sensors are used as data acquisition hardware.
  • the stress value is obtained in real time through the control system.
  • the allowable stress which is the design value
  • the excavation of the next layer continues.
  • the control system issues an alarm, and measures must be taken immediately to reduce the excavation elevation difference between adjacent compartments, stop excavation of compartments with deeper mud surfaces, and excavate compartments with shallower mud surfaces.
  • the allowable stress threshold is the allowable tensile stress of poured concrete, which is generally 0.5Mpa. .
  • the traditional ground-to-ground wall foundation pit adopts horizontal soil collection in the pit, and the excavation of the foundation pit can be completed by vertical excavation of the pit edge; while the foundation of large caissons generally adopts underwater mud suction operation.
  • the compartment type ground wall anchorage foundation in the present invention has the characteristics of the above two structures at the same time.
  • the excavation processes of the above two structures are not suitable. Therefore, a belt conveyor horizontal excavation process is proposed to realize the inner compartment Earth excavation.
  • the advantage of this process is that compared with large-tonnage tower crane excavation, the excavation speed is fast and the cost is low.
  • the multi-compartment balanced soil acquisition technology and the stress and deformation monitoring system of the inner dividing ground connecting wall are used to achieve safe and efficient construction of foundation pit excavation.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Abstract

Disclosed in the present invention is a construction control method for a partition type concrete diaphragm wall anchorage foundation. The construction control method comprises: step 1, designing a partition type concrete diaphragm wall anchorage foundation structure; step 2, splicing first-stage steel box joints; step 3, constructing first-stage grooves; step 4, mounting the first-stage steel box joints; step 5, visually casting steel box concrete in the first-stage grooves; step 6, constructing second-stage grooves, mounting a second-stage reinforcing cage, and casting concrete to complete second-stage groove section construction; step 7, reinforcing a foundation for the partition type concrete diaphragm wall; and step 8, excavating a foundation pit inside the partition type concrete diaphragm wall, and sequentially carrying out underwater bottom sealing, base plate, core filling body and top plate construction in the foundation pit from bottom to top to complete the construction of the partition type concrete diaphragm wall anchorage foundation. The partition type concrete diaphragm wall anchorage foundation of the present invention has the advantages of both the concrete diaphragm wall anchorage foundation and an open caisson anchorage foundation, and has excellent adaptability to the formation, and the construction control method of the present invention can improve the construction quality of the anchorage foundation and accelerate construction.

Description

隔仓式地连墙锚碇基础的施工控制方法Construction control method of compartment-type floor-to-ground wall anchorage foundation 技术领域Technical field
本发明涉及隔仓式地连墙锚碇基础建造领域。更具体地说,本发明涉及隔仓式地连墙锚碇基础的施工控制方法。The invention relates to the field of construction of compartment-type ground connecting wall anchor foundations. More specifically, the present invention relates to a construction control method for a bay-type floor-to-wall anchorage foundation.
背景技术Background technique
随着悬索桥的跨度、荷载日益增大,对应锚碇基础的规模也越来越大。常用的锚碇基础型式包括地下连续墙、沉井、隧道锚等,其中,地下连续墙和沉井在深厚覆盖层区域应用广泛。但常规地下连续墙锚碇基础在持力层埋深过大时,经济性较差,沉井基础仅在砂层有较好的适用性。为了满足超大型悬索桥的建设需求,提出一种隔仓式地连墙锚碇基础,克服常规地下连续墙锚碇基础和沉井基础的缺点。As the span and load of suspension bridges increase, the scale of the corresponding anchor foundations also increases. Commonly used anchor foundation types include underground diaphragm walls, caissons, tunnel anchors, etc. Among them, underground diaphragm walls and caissons are widely used in areas with deep overburden. However, conventional underground diaphragm wall anchorage foundations are less economical when the bearing layer is too deep, and caisson foundations are only suitable for sand layers. In order to meet the construction needs of super-large suspension bridges, a compartment-type continuous wall anchorage foundation is proposed to overcome the shortcomings of conventional underground diaphragm wall anchorage foundations and caisson foundations.
隔仓式地连墙锚碇基础不同于常规的地下连续墙锚碇基础和沉井基础,具有排插式钢筋网片接头形式地连墙、大埋深地基加固等特有工程特点,若按照传统施工工艺施工,施工速度和工程质量均无法满足要求。为加快锚碇基础的施工速度和提高施工质量,需要提出适用于隔仓式地连墙锚碇基础的施工控制方法。为此,提出本申请的隔仓式地连墙锚碇基础的施工控制方法,同时满足施工速度和工程质量的要求。The compartment-type ground connection wall anchorage foundation is different from the conventional underground diaphragm wall anchorage foundation and caisson foundation. It has unique engineering features such as row-type steel mesh joints for ground connection walls and large-depth foundation reinforcement. If according to the traditional The construction technology, construction speed and project quality could not meet the requirements. In order to speed up the construction speed of anchorage foundation and improve the construction quality, it is necessary to propose a construction control method suitable for compartment-type ground wall anchorage foundation. For this reason, the construction control method of the compartment-type ground wall anchorage foundation of this application is proposed, which simultaneously meets the requirements of construction speed and project quality.
发明内容Contents of the invention
本发明的一个目的是提供一种隔仓式地连墙锚碇基础的施工控制方法,隔仓式地连墙锚碇基础同时具备地连墙锚碇基础和沉井锚碇基础的优点,地层适应性好,本发明的施工控制方法可以提高锚碇基础的施工质量、加快施工速度。One object of the present invention is to provide a construction control method for a compartment-type ground connecting wall anchorage foundation. The compartment-type ground connecting wall anchorage foundation has the advantages of both a ground connection wall anchorage foundation and a caisson anchorage foundation. The ground strata It has good adaptability and the construction control method of the present invention can improve the construction quality of the anchorage foundation and speed up the construction speed.
为了实现根据本发明的这些目的和其它优点,提供了一种隔仓式地连墙锚碇基础的施工控制方法,包括:In order to achieve these objects and other advantages according to the present invention, a construction control method for compartment-type ground wall anchorage foundation is provided, including:
步骤一、设计隔仓式地连墙锚碇基础结构,并将隔仓式地连墙的交叉点处均设置为一期槽段,二期槽段均设置于隔仓式地连墙的非交叉点处;Step 1: Design the basic structure of the compartment-type ground connection wall anchorage, and set the intersection points of the compartment-type ground connection walls as the first-phase trough sections, and the second-phase trough sections are set at non-compartment-type ground connection walls. at the intersection;
步骤二、将加工好的一期钢箱接头节段在施工现场拼接为整体形成一期钢箱接头,且拼接完成后的一期钢箱接头纵向偏差小于5mm;Step 2: Splice the processed first-phase steel box joint segments into a whole at the construction site to form a first-phase steel box joint, and the longitudinal deviation of the first-phase steel box joint after splicing is less than 5mm;
步骤三、一期成槽施工;Step 3: The first phase of trough construction;
步骤四、在一期成槽内安装一期钢箱接头;Step 4: Install the first-phase steel box joints in the first-phase trough;
步骤五、可视化浇筑一期成槽内的钢箱混凝土,完成一期槽段施工;Step 5: Visually pour the steel box concrete in the first phase of the trough to complete the construction of the first phase of the trough section;
步骤六、一期槽段施工完成后,根据设计图纸加工二期钢筋笼,然后进行二期成槽施工、安装二期钢筋笼、浇筑混凝土,完成二期槽段施工;Step 6: After the construction of the first phase trough section is completed, the second phase steel cage will be processed according to the design drawings, and then the second phase trough construction will be carried out, the second phase steel cage will be installed, and concrete will be poured to complete the second phase trough section construction;
步骤七、上述地连墙施工完成后,进行隔仓式地连墙的地基加固施工;Step 7: After the construction of the above-mentioned ground connecting wall is completed, carry out the foundation reinforcement construction of the partition type ground connecting wall;
步骤八、地基加固施工完成后,进行隔仓式地连墙内部基坑的开挖施工,然后在基坑内从下至上依次进行水下封底、底板、填芯体、顶板的施工,完成隔仓式地连墙锚碇基础的施工。Step 8. After the foundation reinforcement construction is completed, the excavation of the foundation pit inside the compartment-type ground connection wall is carried out, and then the underwater bottom seal, bottom plate, core filling body, and roof are constructed from bottom to top in the foundation pit to complete the compartment. Construction of ground-to-ground wall anchorage foundation.
优选的是,设计的隔仓式地连墙锚碇基础结构包括:Preferably, the designed basic structure of compartment-type ground-to-wall anchorage includes:
隔仓式地连墙,其包括外侧地连墙和内侧分隔地连墙,内侧分隔地连墙将外侧地连墙所围成的封闭区域分隔为若干个小隔仓;The partition-type connecting wall includes an outer connecting wall and an inner dividing connecting wall. The inner dividing connecting wall divides the enclosed area surrounded by the outer connecting wall into several small compartments;
地基加固体,其包括外侧地连墙所围成的封闭区域内的超高压旋喷桩加固体;Foundation reinforcement, which includes ultra-high-pressure jet grouting pile reinforcement in the closed area surrounded by the outer ground connection wall;
内部结构,其包括从下至少依次设置的水下封底、底板、填芯体、顶板。The internal structure includes an underwater bottom seal, a bottom plate, a core-filling body, and a top plate arranged in sequence from the bottom at least.
优选的是,所述步骤二中拼接为整体的一期钢箱接头的纵向偏差测量方法为:Preferably, the method for measuring the longitudinal deviation of the first-phase steel box joints spliced into a whole in step two is:
将一期钢箱接头平放在平整度满足设计要求的胎架上,并在一期钢箱接头上表面中轴线上布置三个光 学棱镜,其沿一期钢箱接头长度方向均匀布置在上、中、下三点;Place the first-phase steel box joint flat on a tire frame whose flatness meets the design requirements, and arrange three light beams on the central axis of the upper surface of the first-phase steel box joint. Learn from prisms, which are evenly arranged at the upper, middle and lower points along the length of the first-phase steel box joint;
在一期钢箱接头外侧布置一台全站仪,采集三个光学棱镜的大地坐标(x1、y1、z1)、(x2、y2、z2)、(x3、y3、z3),并分别计算一期钢箱接头在x和z方向上的偏差:A total station is arranged outside the joint of the steel box in the first phase to collect the geodetic coordinates of three optical prisms (x 1 , y 1 , z 1 ), (x 2 , y 2 , z 2 ), (x 3 , y 3 , z 3 ), and calculate the deviations of the first-phase steel box joints in the x and z directions respectively:
nx=(max(x1,x2,x3)‐min(x1,x2,x3));nz=(max(z1,z2,z3)‐min(z1,z2,z3));n x =(max(x 1 ,x 2 ,x 3 )‐min(x 1 ,x 2 ,x 3 ));n z =(max(z 1 ,z 2 ,z 3 )‐min(z 1 , z 2 ,z 3 ));
当max(nx,nz)<5mm时,纵向偏差合格,进行下一步施工,反之纵向偏差不合格,重新拼接一期钢箱接头。When max (n x , n z ) <5mm, the longitudinal deviation is qualified and the next step of construction is carried out. Otherwise, the longitudinal deviation is unqualified and the first-phase steel box joints are re-spliced.
优选的是,所述步骤三中一期成槽施工时,槽孔内充满膨润土泥浆,泥浆性能通过泥浆智能控制系统进行自动调整,所述泥浆智能控制系统包括泥浆性能参数检测装置、循环泥浆池、新浆池、新浆膨化池和制浆站,所述泥浆性能参数检测装置用于检测循环泥浆池中泥浆的比重、PH值、粘度、含砂率参数,循环泥浆池、新浆池、新浆膨化池和制浆站依次连通,所述新浆池中设置有第二泵,其用于将新浆池中的泥浆泵至循环泥浆池,所述新浆膨化池中设置有第一泵,其用于将新浆膨化池中的泥浆泵至新浆池,所述循环泥浆池中的泥浆充入至槽孔内;Preferably, during the first phase of trenching construction in step three, the trench holes are filled with bentonite mud, and the mud performance is automatically adjusted through the mud intelligent control system. The mud intelligent control system includes a mud performance parameter detection device and a circulating mud pool. , a new slurry tank, a new slurry expansion tank and a pulping station. The mud performance parameter detection device is used to detect the specific gravity, PH value, viscosity and sand content rate parameters of the mud in the circulating mud tank. The circulating mud tank, new slurry tank, The new slurry expansion tank and the pulping station are connected in sequence. A second pump is provided in the new slurry tank, which is used to pump the mud in the new slurry tank to the circulating mud tank. A first pump is provided in the new slurry expansion tank. A pump for pumping the mud in the new slurry expansion tank to the new slurry tank, and filling the mud in the circulating mud tank into the slot hole;
所述泥浆智能控制系统的具体控制方法为:The specific control method of the mud intelligent control system is:
当泥浆性能参数检测装置检测到循环泥浆池中泥浆比重大于1.2或PH值大于11或粘度大于35s或含砂率大于4%时,启动第二泵,将新浆池中的新浆抽至循环泥浆池,直至循环泥浆池中泥浆比重小于1.2、PH值小于11、粘度小于35s、含砂率小于4%时,关闭第二泵,记录由新浆池泵入循环泥浆池的体积V1When the mud performance parameter detection device detects that the specific gravity of the mud in the circulating mud pool is greater than 1.2 or the PH value is greater than 11 or the viscosity is greater than 35s or the sand content is greater than 4%, the second pump is started to pump the new slurry in the new slurry pool to the circulation Mud pool, until the specific gravity of the mud in the circulating mud pool is less than 1.2, the pH value is less than 11, the viscosity is less than 35s, and the sand content is less than 4%, the second pump is turned off and the volume V 1 pumped into the circulating mud pool from the new mud pool is recorded;
第二泵启动时,同时启动制浆站,按预先设定的新浆配比拌制新浆,拌制体积为V1,并输送至新浆膨化池膨化,待膨化24h后,打开第一泵,将充分膨化的新浆抽至新浆池,即完成一次循环泥浆性能智能控制。When the second pump is started, the pulping station is started at the same time, and new pulp is mixed according to the preset new pulp ratio. The mixing volume is V 1 and is transported to the new pulp expansion tank for expansion. After expansion for 24 hours, the first pulp is opened. The pump pumps the fully expanded new slurry to the new slurry pool, thus completing the intelligent control of mud performance in one cycle.
优选的是,所述步骤三中一期成槽施工时,每间隔20m或4h利用成槽检测装备对成槽垂直度进行一次检测,所述成槽检测装备包括工控主机、电动卷扬机、检测探头、一对钢丝绳和电缆,所述电动卷扬机设置于待测槽段的槽口中心,所述检测探头通过两侧的一对钢丝绳和中间的电缆连接至所述电动卷扬机上并位于待测槽段内,所述电动卷扬机也通过电缆连接至工控主机,所述电动卷扬机上的卷筒分别缠绕一对钢丝绳和电缆,所述电动卷扬机的卷筒通过交流电机驱动正反转,所述电动卷扬机内还设置有深度传感器,其用于获取所述检测探头所处的深度,所述检测探头包括防扭连接件、密封筒、陀螺仪、固定长杆、四根测臂和固定圆盘,所述防扭连接件位于所述密封筒的顶部,一对钢丝绳对称连接于所述防扭连接件上,所述陀螺仪设置于所述密封筒的内部,用于测量检测探头的方位角,所述电缆穿过所述防扭连接件中心后连接至所述陀螺仪,所述固定长杆连接至所述密封筒的底部中心,四根测臂呈正交关系设置于所述密封筒底部,所述测臂顶端与所述密封筒铰接且通过压力弹簧设置为仅沿测臂与固定长杆的竖向轴线组成的平面内转动,所述测臂顶端设置倾角传感器,用于测量测臂张开角度,所述固定圆盘中心具有所述固定长杆穿过的通孔,所述固定圆盘顶面设置有一圈挡环,其用于将四根测臂的下端限位于其内,所述工控主机用于控制电动卷扬机动作,读取深度传感器、陀螺仪以及倾角传感器获取的数据并计算显示结果。Preferably, during the first phase of troughing construction in step three, the troughing detection equipment is used to detect the verticality of the troughing every 20m or 4h. The troughing detection equipment includes an industrial control host, an electric winch, and a detection probe. , a pair of steel wire ropes and cables, the electric hoist is arranged at the center of the slot of the tank section to be tested, the detection probe is connected to the electric hoist through a pair of steel wire ropes on both sides and the cable in the middle and is located in the tank section to be tested Inside, the electric winch is also connected to the industrial control host through a cable. The drum on the electric winch is wound around a pair of steel wire ropes and cables. The drum of the electric winch is driven by an AC motor to rotate forward and reverse. Inside the electric winch A depth sensor is also provided, which is used to obtain the depth of the detection probe. The detection probe includes an anti-twist connector, a sealing cylinder, a gyroscope, a fixed long rod, four measuring arms and a fixed disc. An anti-twist connector is located at the top of the sealing cylinder, and a pair of steel wire ropes are symmetrically connected to the anti-twist connector. The gyroscope is installed inside the sealing cylinder and is used to measure the azimuth angle of the detection probe. The cable is connected to the gyroscope after passing through the center of the anti-twist connector, the fixed long rod is connected to the bottom center of the sealing cylinder, and four measuring arms are arranged in an orthogonal relationship at the bottom of the sealing cylinder, so The top of the measuring arm is hinged with the sealing cylinder and is set by a pressure spring to rotate only along the plane formed by the vertical axis of the measuring arm and the fixed long rod. An inclination sensor is provided on the top of the measuring arm for measuring the opening of the measuring arm. Angle, the center of the fixed disk has a through hole through which the fixed long rod passes, and a ring of blocking rings is provided on the top surface of the fixed disk, which is used to limit the lower ends of the four measuring arms within it, and the The industrial control host is used to control the action of the electric winch, read the data obtained by the depth sensor, gyroscope and inclination sensor and calculate the display results.
优选的是,所述成槽检测装备对成槽垂直度进行检测的方法为:Preferably, the method for the groove detection equipment to detect the verticality of the groove is:
S1:在待测槽口安装成槽检测装备,使其为初始状态,四根测臂通过固定圆盘限位为竖直状态,检测探头陀螺仪数据归零;S1: Install the groove detection equipment at the notch to be tested, and make it the initial state. The four measuring arms are limited by the fixed disk to the vertical state, and the detection probe gyroscope data is reset to zero;
S2:通过电动卷扬机将检测探头放入待测槽段内,根据电动卷扬机内的深度传感器读取检测探头所处的深度位置,确定槽深H;S2: Put the detection probe into the groove section to be tested through the electric winch, read the depth position of the detection probe according to the depth sensor in the electric winch, and determine the groove depth H;
S3:人工通过探头电缆和钢丝绳的松紧判断检测探头是否到达槽底,是则进入下一步骤,否则跳到S2;S3: Manually judge whether the detection probe reaches the bottom of the tank through the tightness of the probe cable and steel wire rope. If so, go to the next step, otherwise jump to S2;
S4:设置检测探头提升深度间隔为L,则检测过程中数据组数N=H/L;S4: Set the detection probe lifting depth interval to L, then the number of data sets during the detection process N = H/L;
S5:快速提拉钢丝绳和电缆,利用泥浆阻力使固定圆盘向下脱开,四根测臂在压力弹簧的作用下向外张开,分别抵在待测槽段槽壁的四个侧面; S5: Quickly pull up the wire rope and cable, and use the mud resistance to release the fixed disc downwards. The four measuring arms open outwards under the action of the pressure spring and respectively press against the four sides of the tank wall of the tank section to be tested;
S6:通过倾角传感器获取的数据判断测臂是否张开,是则进入下一步骤,否则跳到步骤S5;S6: Determine whether the measuring arm is open based on the data obtained by the inclination sensor, if so, proceed to the next step, otherwise jump to step S5;
S7:通过电动卷扬机根据设定的深度间隔L缓慢提升检测探头,读取并储存深度传感器、陀螺仪和倾角传感器测得的深度hj、探头方位角cosαj和四根测臂的张开角其中,j=1,2,3,…N,i=1,2,3,4;S7: Use the electric winch to slowly lift the detection probe according to the set depth interval L, read and store the depth h j measured by the depth sensor, gyroscope and inclination sensor, the probe azimuth angle cosα j and the opening angle of the four measuring arms. Among them, j=1,2,3,...N, i=1,2,3,4;
S8:工控主机根据读取的深度、探头方位角、测臂张开角信息,计算出成槽宽度、长度和垂直度,并绘制出槽壁深度‐成槽宽度曲线、槽壁深度‐成槽长度曲线,深度‐成槽垂直度曲线以及成槽垂直度;计算成槽宽度、长度和垂直度具体方法如下:S8: The industrial control host calculates the groove width, length and verticality based on the read depth, probe azimuth angle and measuring arm opening angle information, and draws the groove wall depth-groove width curve and groove wall depth-groove length curve , depth-trough verticality curve and trough verticality; the specific method for calculating the trough width, length and verticality is as follows:
以相对的一对测臂1和测臂3为例,计算出测臂1和测臂3所检测出的半槽宽:

Taking the opposite pair of measuring arm 1 and measuring arm 3 as an example, calculate the half-slot width detected by measuring arm 1 and measuring arm 3:

测点深度按下式进行修正:

The depth of the measuring point is corrected as follows:

通过线性插值计算出每一个标准深度hj下所检测出的半槽宽B1和B2,相加得到成槽宽度B;Calculate the detected half-groove widths B 1 and B 2 at each standard depth h j through linear interpolation, and add them to obtain the groove width B;
按照上述方法计算测臂2和测臂4所检测出的半槽长;Calculate the half-groove length detected by measuring arm 2 and measuring arm 4 according to the above method;
根据每一个标准深度下所检测出的半槽宽以及半槽长,生成该深度对应的一个矩形截面,利用非均匀有理样条方法将这些矩形截面在深度上连接起来,形成槽壁三维形态;Based on the half-groove width and half-groove length detected at each standard depth, a rectangular section corresponding to that depth is generated, and the non-uniform rational spline method is used to connect these rectangular sections in depth to form a three-dimensional shape of the groove wall;
根据每一个标准深度下的矩形截面确定矩形中心坐标,矩形中心坐标就是槽壁中心坐标,将槽壁中心左边沿深度连接起来形成槽孔孔斜曲线,其与轴线在槽段宽度、长度方向的偏差角度即为对应的垂直度;Determine the rectangular center coordinates based on the rectangular cross-section at each standard depth. The rectangular center coordinates are the slot wall center coordinates. Connect the left edge depths of the slot wall centers to form a slot oblique curve, which is aligned with the axis in the width and length directions of the slot section. The deviation angle is the corresponding verticality;
S9:根据深度hj判断检测探头是否到达检测槽段的槽口,如果hj<0,则进入下一步骤,否则继续步骤S6;S9: Determine whether the detection probe reaches the notch of the detection groove section according to the depth h j . If h j <0, proceed to the next step, otherwise continue to step S6;
S10:停止提升检测探头,检测完成。S10: Stop lifting the detection probe and the detection is completed.
优选的是,所述步骤五中混凝土浇筑可视化具体包括水下混凝土液面实时监测和导管安装长度实时监测两部分;Preferably, the concrete pouring visualization in step five specifically includes two parts: real-time monitoring of underwater concrete liquid level and real-time monitoring of conduit installation length;
水下混凝土液面实时监测具体为:在一期钢箱接头及二期钢筋笼制作时,提前安装分辨率为0.2m的温度光纤,在混凝土浇筑时,通过温度光纤解调设备监测温度光纤的温度变化,根据温度的变化,反映混凝土液面高度;The specific real-time monitoring of underwater concrete liquid level is as follows: when making the steel box joints of the first phase and the steel cage of the second phase, a temperature optical fiber with a resolution of 0.2m is installed in advance. When the concrete is poured, the temperature optical fiber is monitored through the temperature optical fiber demodulation equipment. Temperature changes, according to changes in temperature, reflect the concrete liquid level;
导管安装长度实时监测具体为:在每一节导管上安装一个包含导管长度信息的芯片,在导管架上安装电磁感应装置,每拆除一节导管时,电磁感应装置自动计数,将导管总长度减去被拆除的导管长度,即可得到剩余导管的长度。Real-time monitoring of the installation length of the conduit is as follows: installing a chip containing conduit length information on each section of conduit, and installing an electromagnetic induction device on the conduit frame. When each section of conduit is removed, the electromagnetic induction device automatically counts and reduces the total length of the conduit. Divide the length of the removed conduit into the length of the remaining conduit.
优选的是,所述步骤八中基坑开挖控制方法为:Preferably, the foundation pit excavation control method in step eight is:
在内侧分隔地连墙的交叉点处布置覆盖内侧隔仓的克令吊,在内侧分隔地连墙顶部布置皮带式水平运输机,将内侧隔仓开挖的土方运至基坑外侧; A crane covering the inner compartment is arranged at the intersection of the inner dividing ground connecting wall, and a belt-type horizontal conveyor is arranged on the top of the inner dividing connecting wall to transport the earth excavated from the inner compartment to the outside of the foundation pit;
隔仓分层开挖,通过声呐探测技术对各隔仓开挖标高进行自动采集,并传输给控制系统,每层开挖深度为2m,当相邻隔仓开挖标高差超过2m时,控制系统发出警报;Compartments are excavated in layers. The excavation elevation of each compartment is automatically collected through sonar detection technology and transmitted to the control system. The excavation depth of each layer is 2m. When the difference in excavation elevation between adjacent compartments exceeds 2m, the control system The system issues an alert;
在地连墙钢筋笼上提前布置应变计,通过控制系统实时获取应力值,当地连墙内应力小于容许应力时,继续开挖下一层,当地连墙内应力超过容许应力时,控制系统发出警报,停止开挖泥面较深的隔仓,开挖泥面较浅的相邻隔仓,直至所有相邻隔仓泥面高差小于0.3m,继续开挖下一层,直至完成所有隔仓的开挖,容许应力阈值为浇筑混凝土容许抗拉应力。Strain gauges are arranged in advance on the steel cage of the ground connection wall, and the stress value is obtained in real time through the control system. When the stress in the ground connection wall is less than the allowable stress, the excavation of the next layer continues. When the stress in the ground connection wall exceeds the allowable stress, the control system issues a Alarm, stop excavation of the compartment with deeper mud surface, and excavate adjacent compartments with shallower mud surface until the height difference of mud surface in all adjacent compartments is less than 0.3m, continue to excavate the next layer until all compartments are completed For the excavation of the warehouse, the allowable stress threshold is the allowable tensile stress of poured concrete.
本发明至少包括以下有益效果:The present invention at least includes the following beneficial effects:
1、本申请针对设计的特殊隔仓式地连墙锚碇基础结构提出一种新的施工方法,可以提高锚碇基础的施工质量、加快施工速度。1. This application proposes a new construction method for the designed special compartment-type ground wall anchorage foundation structure, which can improve the construction quality of the anchorage foundation and speed up the construction speed.
2、本申请的隔仓式地连墙锚碇基础同时具备地连墙锚碇基础和沉井锚碇基础的优点,地层适应性好,克服常规地下连续墙锚碇基础和沉井基础的缺点,满足超大型悬索桥的建设施工需求。2. The compartment-type ground connecting wall anchorage foundation of this application has the advantages of both ground connecting wall anchorage foundation and caisson anchorage foundation. It has good stratum adaptability and overcomes the shortcomings of conventional underground diaphragm wall anchorage foundation and caisson shaft foundation. , to meet the construction needs of super-large suspension bridges.
3、本申请在成槽施工过程中,槽内的泥浆性能通过泥浆智能控制系统进行自动调整,以高质量泥浆保证成槽质量。3. During the trough construction process of this application, the performance of the mud in the trough is automatically adjusted through the mud intelligent control system to ensure the quality of the trough with high-quality mud.
4、本申请在成槽过程中,每间隔20m或4h利用高适应性成槽检测装备对成槽垂直度进行一次检测,以实现“勤测勤纠”,保证高精度成槽,该设备检测精度不受泥浆性质影响,无需提前进行清孔换浆,没有检测盲区,可自动计算成槽垂直度并根据设定阈值进行报警,可实时生成槽孔三维孔形。4. During the troughing process, this application uses highly adaptable troughing detection equipment to detect the verticality of the trough every 20m or 4h to achieve "diligently measure and correct" and ensure high-precision troughing. This equipment detects The accuracy is not affected by the properties of the mud. There is no need to clean holes and replace slurry in advance. There is no detection blind area. The verticality of the slot can be automatically calculated and an alarm will be issued based on the set threshold. The three-dimensional hole shape of the slot can be generated in real time.
5、本申请在成槽混凝土浇筑过程中,通过水下混凝土液面高度、导管安装长度,可视化浇筑,实时反映水下混凝土的浇筑进度以及导管埋深,确保导管不被拔离混凝土并保持2~4m的埋深,控制水下混凝土浇筑质量,避免埋管过深或误操作拔出导管导致的水下混凝土浇筑事故。5. During the trough concrete pouring process, this application uses the height of the underwater concrete liquid level and the installation length of the conduit to visualize the pouring, reflecting the progress of the underwater concrete pouring and the buried depth of the conduit in real time to ensure that the conduit is not pulled out of the concrete and remains 2 The burial depth of ~4m controls the quality of underwater concrete pouring and avoids underwater concrete pouring accidents caused by excessively deep buried pipes or misoperation of pulling out the pipes.
6、本申请利用基坑土方开挖智能化施工控制方法,实现隔仓式地连墙干开挖快速出土、水下开挖各隔仓均衡取土,实现高效安全施工。6. This application uses intelligent construction control methods for foundation pit earth excavation to achieve rapid excavation of compartment-type ground-to-wall dry excavation and balanced soil extraction from each compartment during underwater excavation to achieve efficient and safe construction.
本发明的其它优点、目标和特征将部分通过下面的说明体现,部分还将通过对本发明的研究和实践而为本领域的技术人员所理解。Other advantages, objects, and features of the present invention will be apparent in part from the description below, and in part will be understood by those skilled in the art through study and practice of the present invention.
附图说明Description of the drawings
图1为本发明隔仓式地连墙锚碇基础的平面示意图;Figure 1 is a schematic plan view of the compartment-type ground wall anchorage foundation of the present invention;
图2为本发明图1中隔仓式地连墙锚碇基础的A‐A剖面图;Figure 2 is an A-A cross-sectional view of the compartment-type ground wall anchorage foundation in Figure 1 of the present invention;
图3为本发明一期钢箱接头纵向偏差测量方法示意图;Figure 3 is a schematic diagram of the longitudinal deviation measurement method of the first-phase steel box joint of the present invention;
图4为本发明泥浆智能控制系统的结构示意图;Figure 4 is a schematic structural diagram of the mud intelligent control system of the present invention;
图5为本发明地连墙的平面结构示意图;Figure 5 is a schematic plan view of the floor connecting wall of the present invention;
图6为本发明成槽检测装备的结构示意图;Figure 6 is a schematic structural diagram of the groove detection equipment of the present invention;
图7为本发明成槽检测装备的检测探头的结构示意图;Figure 7 is a schematic structural diagram of the detection probe of the groove detection equipment of the present invention;
图8为本发明成槽检测装备检测过程及程序控制的流程图;Figure 8 is a flow chart of the detection process and program control of the groove detection equipment of the present invention;
图9为本发明成槽检测装备检测过程中测臂位置俯视图;Figure 9 is a top view of the position of the measuring arm during the detection process of the groove detection equipment of the present invention;
图10为本发明成槽检测装备检测过程中测臂位置主视图;Figure 10 is a front view of the position of the measuring arm during the detection process of the groove detection equipment of the present invention;
图11为本发明成槽检测装备检测的槽壁三维形态示意图;Figure 11 is a schematic diagram of the three-dimensional shape of the groove wall detected by the groove detection equipment of the present invention;
图12为本发明基坑开挖控制流程图。Figure 12 is a control flow chart for foundation pit excavation according to the present invention.
附图标记说明:1、外侧地连墙,2、内侧分隔地连墙,3、地基加固体,4、水下封底,5、底板,6、填芯,7、顶板,8、光学棱镜,9、一期钢箱接头,10、全站仪,11、泥浆性能参数检测装置,12、循环泥浆池,13、新浆池,14、新浆膨化池,15、制浆站,16、一期槽段,17、二期槽段,18、工控主机,19、电动卷扬机,20、检测探头,21、钢丝绳,22、电缆,23、待测槽段,24、防扭连接件,25、密封筒,26、 陀螺仪,27、固定长杆,28、测臂,29、固定圆盘,30、倾角传感器。Explanation of reference signs: 1. External connecting wall, 2. Internal dividing connecting wall, 3. Foundation reinforcement, 4. Underwater back seal, 5. Bottom plate, 6. Core filling, 7. Top plate, 8. Optical prism, 9. Phase I steel box joint, 10. Total station, 11. Mud performance parameter detection device, 12. Circulating mud tank, 13. New slurry tank, 14. New slurry expansion tank, 15. Pulp making station, 16. 1 Phase trough section, 17. Phase 2 trough section, 18. Industrial control host, 19. Electric winch, 20. Detection probe, 21. Wire rope, 22. Cable, 23. Tank section to be tested, 24. Anti-twist connector, 25. Sealing cylinder, 26, Gyroscope, 27. Fixed long rod, 28. Measuring arm, 29. Fixed disk, 30. Inclination sensor.
具体实施方式Detailed ways
下面结合附图对本发明做进一步的详细说明,以令本领域技术人员参照说明书文字能够据以实施。The present invention will be further described in detail below with reference to the accompanying drawings, so that those skilled in the art can implement it with reference to the text of the description.
需要说明的是,下述实施方案中所述实验方法,如无特殊说明,均为常规方法,所述试剂和材料,如无特殊说明,均可从商业途径获得;在本发明的描述中,术语“横向”、“纵向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,并不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It should be noted that the experimental methods described in the following embodiments, unless otherwise specified, are all conventional methods, and the reagents and materials, unless otherwise specified, can be obtained from commercial sources; in the description of the present invention, The terms "horizontal", "vertical", "top", "bottom", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", The orientations or positional relationships indicated by "inner", "outer", etc. are based on the orientations or positional relationships shown in the drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have Specific orientations, construction and operation in specific orientations and therefore are not to be construed as limitations of the invention.
如图1至12所示,本发明提供一种隔仓式地连墙锚碇基础的施工控制方法,包括:As shown in Figures 1 to 12, the present invention provides a construction control method for a compartment-type ground wall anchorage foundation, including:
步骤一、设计隔仓式地连墙锚碇基础结构,如图1和图2所示,并将隔仓式地连墙的交叉点处均设置为一期槽段16,二期槽段17均设置于隔仓式地连墙的非交叉点处,如图5所示;Step 1: Design the basic structure of the bay-type ground connecting wall anchorage, as shown in Figure 1 and Figure 2, and set the intersection points of the bay-type ground connecting walls as the first phase trough section 16 and the second phase trough section 17 They are all installed at the non-intersection points of the partition wall, as shown in Figure 5;
步骤二、将在工厂加工好的9m一节的一期钢箱接头9节段运送至施工现场,在施工现场拼接为整体形成一期钢箱接头9,且拼接完成后的一期钢箱接头9纵向偏差小于5mm为合格;Step 2: Transport the 9-meter first-phase steel box joint 9 sections processed in the factory to the construction site, and splice them into a whole at the construction site to form the first-phase steel box joint 9, and the first-phase steel box joint after the splicing is completed 9. Longitudinal deviation less than 5mm is qualified;
步骤三、一期成槽施工;当单位时间内导墙口钢丝绳21振幅超过5cm的频率不大于0.2时或铣斗偏转角不大于0.05°时或铣斗平面坐标偏移不大于7.5cm时,成槽合格,完成一期槽成槽;Step 3: The first phase of troughing construction; when the frequency of the amplitude of the guide wall opening wire rope 21 exceeding 5cm per unit time is not greater than 0.2 or the deflection angle of the milling bucket is not greater than 0.05° or the plane coordinate offset of the milling bucket is not greater than 7.5cm, The groove formation is qualified and the first phase of groove formation is completed;
步骤四、在一期成槽内安装一期钢箱接头9;一期钢箱接头9入槽时,利用智能导向架对一期钢箱接头9进行导向、调平,确保一期钢箱接头9安装垂直度。智能导向架具备自动调平功能,可消除导墙高差对一期钢箱接头9安装垂直度的影响;Step 4: Install the first-phase steel box joint 9 in the first-phase trough; when the first-phase steel box joint 9 enters the trough, use the intelligent guide frame to guide and level the first-phase steel box joint 9 to ensure that the first-phase steel box joint 9 9 Installation verticality. The intelligent guide frame has an automatic leveling function, which can eliminate the impact of the height difference of the guide wall on the verticality of the installation of the first-phase steel box joint 9;
步骤五、可视化浇筑一期成槽内的钢箱混凝土,完成一期槽段16施工;Step 5: Visually pour the steel box concrete in the first phase of the trough to complete the construction of the first phase of trough section 16;
步骤六、一期槽段16施工完成后,根据设计图纸加工二期钢筋笼,然后进行二期成槽施工、安装二期钢筋笼、浇筑混凝土,完成二期槽段17施工;Step 6: After the construction of the first phase trough section 16 is completed, the second phase steel cage will be processed according to the design drawings, and then the second phase trough construction, installation of the second phase steel cage, and concrete pouring will be carried out to complete the second phase trough section 17 construction;
步骤七、上述地连墙施工完成后,进行隔仓式地连墙的地基加固施工;地基加固施工工艺为超高压旋喷工艺,正式施工前,需进行引孔施工。引孔施工时,在钻杆底部进行引孔垂直度控制,使得引孔垂直度不大于1/500。Step 7: After the construction of the above-mentioned ground connection wall is completed, the foundation reinforcement construction of the compartment-type ground connection wall is carried out; the foundation reinforcement construction technology is ultra-high pressure rotary spraying process, and before the official construction, pilot hole construction is required. When constructing the pilot hole, control the verticality of the pilot hole at the bottom of the drill pipe so that the verticality of the pilot hole is not greater than 1/500.
步骤八、地基加固施工完成后,进行隔仓式地连墙内部基坑的开挖施工,基坑开挖过程中,墙面凿毛采用智能凿毛机器人,然后在基坑内从下至上依次进行水下封底4、底板5、填芯6体、顶板7的施工,施工时,采用大体积混凝土温度控制系统,根据温度传感器监测数据控制冷凝水系统,确保底板5、填芯6体、顶板7不出现温度裂缝,完成隔仓式地连墙锚碇基础的施工。Step 8. After the foundation reinforcement construction is completed, the excavation of the foundation pit inside the compartment-type ground connecting wall is carried out. During the excavation of the foundation pit, an intelligent deburring robot is used to chisel the wall surface, and then the process is carried out from bottom to top in the foundation pit. During the construction of underwater bottom seal 4, bottom plate 5, core filling 6, and roof 7, a large-volume concrete temperature control system was used to control the condensate water system based on temperature sensor monitoring data to ensure that bottom plate 5, core filling 6, and roof 7 There will be no temperature cracks, and the construction of the compartment-type ground-to-wall anchorage foundation will be completed.
在上述技术方案中,如图5所示,阴影部分为一期槽段16,阴影部分之间的白色部分为二期槽段17。施工时,先施工一期槽段16,待与某二期槽段17相邻的一期槽段16均施工完成后,方可施工已施工完成的一期槽段16之间的二期槽段17。一期槽段16施工时,先挖槽,挖槽完成后,将一期钢箱接头9放入已挖好的槽段中;二期槽段17施工时,先挖槽,挖槽完成后,将二期钢筋笼放入已挖好的槽段中,再浇筑混凝土,完成整个隔仓式地连墙的施工。In the above technical solution, as shown in FIG. 5 , the shaded part is the first-stage tank section 16 , and the white part between the shaded parts is the second-stage tank section 17 . During construction, the first-phase trench section 16 is constructed first. After the construction of the first-phase trench sections 16 adjacent to a certain second-phase trench section 17 is completed, the second-phase trench between the completed first-phase trench sections 16 can be constructed. Paragraph 17. During the construction of the trench section 16 of the first phase, the trench is dug first, and after the trenching is completed, the steel box joint 9 of the first phase is placed into the dug trench section; during the construction of the trench section 17 of the second phase, the trench is dug first, and after the trenching is completed , place the second-stage steel cage into the dug trench section, and then pour concrete to complete the construction of the entire partition-type ground connection wall.
在另一种技术方案中,如图1和图2所示,设计的隔仓式地连墙锚碇基础结构包括:In another technical solution, as shown in Figures 1 and 2, the designed compartment-type ground-to-wall anchorage infrastructure includes:
隔仓式地连墙,其包括外侧地连墙1和内侧分隔地连墙2,内侧分隔地连墙2将外侧地连墙1所围成的封闭区域分隔为若干个小隔仓;A compartment-type connecting wall includes an outer connecting wall 1 and an inner dividing connecting wall 2. The inner dividing connecting wall 2 divides the closed area surrounded by the outer connecting wall 1 into several small compartments;
地基加固体3,其包括外侧地连墙1所围成的封闭区域内的超高压旋喷桩加固体;Foundation reinforcement 3, which includes ultra-high pressure jet grouting pile reinforcement in the closed area surrounded by the outer ground wall 1;
内部结构,其包括从下至少依次设置的水下封底4、底板5、填芯6体、顶板7。The internal structure includes an underwater bottom seal 4, a bottom plate 5, a core filling body 6, and a top plate 7 arranged in sequence at least from the bottom.
在另一种技术方案中,如图3所示,所述步骤二中拼接为整体的一期钢箱接头9的纵向偏差测量方法为:In another technical solution, as shown in Figure 3, the longitudinal deviation measurement method of the first-phase steel box joint 9 that is spliced into a whole in the second step is:
将一期钢箱接头9平放在平整度满足设计要求的胎架上,并在一期钢箱接头9上表面中轴线上布置三 个光学棱镜8,其沿一期钢箱接头9长度方向均匀布置在上、中、下三点;Place the first-phase steel box joint 9 flatly on a tire frame whose flatness meets the design requirements, and arrange three sections on the central axis of the upper surface of the first-phase steel box joint 9 An optical prism 8 is evenly arranged at the upper, middle and lower points along the length direction of the primary steel box joint 9;
在一期钢箱接头9外侧附近布置一台全站仪10,采集三个光学棱镜8的大地坐标(x1、y1、z1)、(x2、y2、z2)、(x3、y3、z3),并分别计算一期钢箱接头9在x和z方向上的偏差:Arrange a total station 10 near the outside of the first-phase steel box joint 9 to collect the geodetic coordinates (x 1 , y 1 , z 1 ), (x 2 , y 2 , z 2 ), (x 3 , y 3 , z 3 ), and calculate the deviations of the first-phase steel box joint 9 in the x and z directions respectively:
nx=(max(x1,x2,x3)‐min(x1,x2,x3));nz=(max(z1,z2,z3)‐min(z1,z2,z3));n x =(max(x 1 ,x 2 ,x 3 )‐min(x 1 ,x 2 ,x 3 ));n z =(max(z 1 ,z 2 ,z 3 )‐min(z 1 , z 2 ,z 3 ));
当max(nx,nz)<5mm时,纵向偏差方为合格,进行下一步施工,反之纵向偏差不合格,重新拼接一期钢箱接头9。When max (n x , n z )<5mm, the longitudinal deviation is qualified and the next step of construction is carried out. Otherwise, the longitudinal deviation is unqualified and the first phase steel box joint 9 is re-spliced.
在另一种技术方案中,如图4所示,所述步骤三中一期成槽施工时,槽孔内充满膨润土泥浆,泥浆性能通过泥浆智能控制系统进行自动调整,所述泥浆智能控制系统包括泥浆性能参数检测装置11、循环泥浆池12、新浆池13、新浆膨化池14和制浆站15,所述泥浆性能参数检测装置11用于检测循环泥浆池12中泥浆的比重、PH值、粘度、含砂率参数,循环泥浆池12、新浆池13、新浆膨化池14和制浆站15依次连通,所述新浆池13中设置有第二泵,其用于将新浆池13中的泥浆泵至循环泥浆池12,所述新浆膨化池14中设置有第一泵,其用于将新浆膨化池14中的泥浆泵至新浆池13,所述循环泥浆池12中的泥浆充入至槽孔内;In another technical solution, as shown in Figure 4, during the first phase of trench construction in step three, the trench holes are filled with bentonite mud, and the mud performance is automatically adjusted through the mud intelligent control system. The mud intelligent control system It includes a mud performance parameter detection device 11, a circulating mud tank 12, a new slurry tank 13, a new slurry expansion tank 14 and a pulping station 15. The mud performance parameter detection device 11 is used to detect the specific gravity and PH of the mud in the circulating mud tank 12. value, viscosity, and sand content rate parameters. The circulating mud tank 12, the new slurry tank 13, the new slurry expansion tank 14, and the pulping station 15 are connected in sequence. The new slurry tank 13 is provided with a second pump, which is used to pump the new slurry. The mud in the slurry tank 13 is pumped to the circulating mud tank 12. The new slurry expansion tank 14 is provided with a first pump, which is used to pump the mud in the new slurry expansion tank 14 to the new slurry tank 13. The circulating mud The mud in the pool 12 is filled into the slot hole;
所述泥浆智能控制系统的具体控制方法为:The specific control method of the mud intelligent control system is:
当泥浆性能参数检测装置11检测到循环泥浆池12中泥浆比重大于1.2或PH值大于11或粘度大于35s或含砂率大于4%时,启动第二泵,将新浆池13中的新浆抽至循环泥浆池12,直至循环泥浆池12中泥浆比重小于1.2、PH值小于11、粘度小于35s、含砂率小于4%时,关闭第二泵,记录由新浆池13泵入循环泥浆池12的体积V1When the mud performance parameter detection device 11 detects that the specific gravity of the mud in the circulating mud pool 12 is greater than 1.2 or the PH value is greater than 11 or the viscosity is greater than 35 seconds or the sand content is greater than 4%, the second pump is started to pump the new slurry in the new mud pool 13 Pump to the circulating mud pool 12 until the specific gravity of the mud in the circulating mud pool 12 is less than 1.2, the PH value is less than 11, the viscosity is less than 35s, and the sand content is less than 4%, then turn off the second pump and record the circulating mud pumped into the new mud pool 13 Volume V 1 of pool 12;
第二泵启动时,同时启动制浆站15,按预先设定的新浆配比拌制新浆,拌制体积为V1,并输送至新浆膨化池14膨化,待膨化24h后,打开第一泵,将充分膨化的新浆抽至新浆池13,即完成一次循环泥浆性能智能控制。When the second pump is started, the pulping station 15 is started at the same time, and new pulp is mixed according to the preset new pulp ratio. The mixing volume is V 1 and is transported to the new pulp expansion tank 14 for expansion. After expansion for 24 hours, open The first pump pumps the fully expanded new slurry to the new slurry tank 13, which completes the intelligent control of mud performance in one cycle.
在上述技术方案中,二期成槽施工时,槽孔内充满膨润土泥浆,泥浆性能也通过泥浆智能控制系统进行自动调整。泥浆智能控制系统及方法将成槽泥浆的性能参数与规范要求的性能参数自动对比,自动计算需要添加的掺加剂的数量,通过自动投料模块,实现泥浆性能智能调整,以高质量泥浆保证成槽质量。上述自动化过程是泥浆智能控制系统搭载控制器,自动获取数据并进行对比之后,自动控制各设备的动作,此为常规控制技术手段,在此不再赘述。In the above technical solution, during the second phase of trench construction, the trench holes are filled with bentonite mud, and the mud performance is automatically adjusted through the mud intelligent control system. The mud intelligent control system and method automatically compares the performance parameters of the mud in the tank with the performance parameters required by the specification, automatically calculates the amount of additives that need to be added, and realizes intelligent adjustment of the mud performance through the automatic feeding module to ensure that the tank is completed with high-quality mud. quality. The above-mentioned automation process is that the mud intelligent control system is equipped with a controller. After automatically acquiring data and comparing it, it automatically controls the actions of each equipment. This is a conventional control technology method and will not be described again here.
在另一种技术方案中,如图6和图7所示,所述步骤三中一期成槽施工时,每间隔20m或4h利用成槽检测装备对成槽垂直度进行一次检测,所述成槽检测装备包括工控主机18、电动卷扬机19、检测探头20、一对钢丝绳21和电缆22,所述电动卷扬机19设置于待测槽段23的槽口中心,所述检测探头20通过两侧的一对钢丝绳21和中间的电缆22连接至所述电动卷扬机19上并位于待测槽段23内,所述电动卷扬机19也通过电缆22连接至工控主机18,所述电动卷扬机19上的卷筒分别缠绕一对钢丝绳21和电缆22,所述电动卷扬机19的卷筒通过交流电机驱动正反转,所述电动卷扬机19内还设置有深度传感器,其用于获取所述检测探头20所处的深度,所述检测探头20包括防扭连接件24、密封筒25、陀螺仪26、固定长杆27、四根测臂28和固定圆盘29,所述防扭连接件24位于所述密封筒25的顶部,一对钢丝绳21对称连接于所述防扭连接件24上,所述陀螺仪26设置于所述密封筒25的内部,用于测量检测探头20的方位角,所述电缆22穿过所述防扭连接件24中心后连接至所述陀螺仪26,所述固定长杆27连接至所述密封筒25的底部中心,四根测臂28呈正交关系设置于所述密封筒25底部,所述测臂28顶端与所述密封筒25铰接且通过压力弹簧设置为仅沿测臂28与固定长杆27的竖向轴线组成的平面内转动,所述测臂28顶端设置倾角传感器30,用于测量测臂28张开角度,所述固定圆盘29中心具有所述固定长杆27穿过的通孔,所述固定圆盘29顶面设置有一圈挡环,其用于将四根测臂28的下端限位于其内,所述工控主机18用于控制电动卷扬机19动作,读取深度传感器、陀螺仪26以及倾角传感器30获取的数据并计算显示结果。In another technical solution, as shown in Figures 6 and 7, during the first phase of troughing construction in step three, the troughing detection equipment is used to detect the verticality of the troughing every 20m or 4h. The trough detection equipment includes an industrial control host 18, an electric winch 19, a detection probe 20, a pair of wire ropes 21 and cables 22. The electric winch 19 is arranged at the center of the slot of the trough section 23 to be tested, and the detection probe 20 passes through both sides. A pair of steel wire ropes 21 and the middle cable 22 are connected to the electric winch 19 and are located in the tank section 23 to be tested. The electric winch 19 is also connected to the industrial control host 18 through the cable 22. The winder on the electric winch 19 The drums are respectively wound around a pair of wire ropes 21 and cables 22. The drum of the electric hoist 19 is driven by an AC motor to rotate forward and reverse. A depth sensor is also provided in the electric hoist 19, which is used to obtain the location of the detection probe 20. The detection probe 20 includes an anti-twist connector 24, a sealing cylinder 25, a gyroscope 26, a fixed long rod 27, four measuring arms 28 and a fixed disk 29. The anti-twist connector 24 is located in the dense On the top of the sealing cylinder 25, a pair of steel wire ropes 21 are symmetrically connected to the anti-twist connector 24. The gyroscope 26 is disposed inside the sealing cylinder 25 for measuring the azimuth angle of the detection probe 20. The cable 22 After passing through the center of the anti-twist connector 24, it is connected to the gyroscope 26. The fixed long rod 27 is connected to the bottom center of the sealing cylinder 25. Four measuring arms 28 are arranged in an orthogonal relationship on the sealing cylinder. At the bottom of the sealing cylinder 25, the top of the measuring arm 28 is hinged with the sealing cylinder 25 and is set by a pressure spring to rotate only along the plane formed by the vertical axis of the measuring arm 28 and the fixed long rod 27. The top of the measuring arm 28 is provided with The inclination sensor 30 is used to measure the opening angle of the measuring arm 28. The center of the fixed disk 29 has a through hole through which the fixed long rod 27 passes. With the lower ends of the four measuring arms 28 limited therein, the industrial control host 18 is used to control the action of the electric winch 19, read the data acquired by the depth sensor, the gyroscope 26 and the inclination sensor 30 and calculate the display results.
在上述技术方案中,成槽过程中,每间隔20m或4h利用高适应性成槽检测装备对成槽垂直度进行一次检测,以实现“勤测勤纠”,保证高精度成槽,该系统检测精度不受泥浆性质影响,无需提前进行清孔 换浆,没有检测盲区,可自动计算成槽垂直度并根据设定阈值进行报警,可实时生成槽孔三维孔形。当然二期成槽过程中也采用相同的装备及方法进行检测。四根测臂28以固定长杆27为中心呈矩形分布于固定长杆27外周,四根测臂28初始状态时如图7所示被固定圆盘29限位,当固定圆盘29拆除后,四根测臂28在压力弹簧的作用下向外张开呈如图10所示的状态。钢丝绳21为防扭转钢丝绳21,电动卷扬机19的卷筒通过交流电机驱动正反转,用于将检测探头20下放或提升。防扭连接件24位于密封筒25顶部,将钢丝绳21和探头电缆22与检测探头20连接,同时防止检测探头20发生较大的扭转。In the above technical solution, during the troughing process, the verticality of the trough is detected every 20m or 4 hours using highly adaptable troughing detection equipment to achieve "diligently measure and correct" and ensure high-precision troughing. This system The detection accuracy is not affected by the properties of the mud, and there is no need to clean the hole in advance. There is no detection blind area during slurry replacement. It can automatically calculate the verticality of the slot and issue an alarm based on the set threshold. It can generate a three-dimensional hole shape of the slot in real time. Of course, the same equipment and methods are also used for testing during the second phase of trough formation. The four measuring arms 28 are rectangularly distributed around the fixed long rod 27 with the fixed long rod 27 as the center. In the initial state, the four measuring arms 28 are limited by the fixed disc 29 as shown in Figure 7. When the fixed disc 29 is removed, , the four measuring arms 28 open outwards under the action of the pressure spring, as shown in Figure 10. The steel wire rope 21 is an anti-twist steel wire rope 21, and the drum of the electric winch 19 is driven by an AC motor to rotate forward and reverse, and is used to lower or lift the detection probe 20. The anti-twist connector 24 is located at the top of the sealing cylinder 25 to connect the steel wire rope 21 and the probe cable 22 to the detection probe 20 while preventing the detection probe 20 from being greatly twisted.
在另一种技术方案中,如图8至11所示,所述成槽检测装备对成槽垂直度进行检测的方法为:In another technical solution, as shown in Figures 8 to 11, the method for detecting the verticality of the groove by the groove detection equipment is:
S1:在待测槽口安装成槽检测装备,使其为初始状态,四根测臂28通过固定圆盘29限位为竖直状态,检测探头20陀螺仪26数据归零;S1: Install the groove detection equipment at the notch to be tested, so that it is in the initial state, the four measuring arms 28 are limited to the vertical state by the fixed disk 29, and the data of the detection probe 20 and the gyroscope 26 are reset to zero;
S2:通过电动卷扬机19将检测探头20放入待测槽段23内,根据电动卷扬机19内的深度传感器读取检测探头20所处的深度位置,确定槽深H;S2: Put the detection probe 20 into the groove section 23 to be tested through the electric winch 19, read the depth position of the detection probe 20 according to the depth sensor in the electric winch 19, and determine the groove depth H;
S3:人工通过探头电缆22和钢丝绳21的松紧判断检测探头20是否到达槽底,是则进入下一步骤,否则跳到S2;S3: Manually judge whether the detection probe 20 reaches the bottom of the tank through the tightness of the probe cable 22 and the steel wire rope 21, if so, proceed to the next step, otherwise jump to S2;
S4:设置检测探头20提升深度间隔为L,则检测过程中数据组数N=H/L;S4: Set the lifting depth interval of the detection probe 20 to L, then the number of data groups during the detection process is N=H/L;
S5:快速提拉钢丝绳21和电缆22,利用泥浆阻力使固定圆盘29向下脱开,四根测臂28在压力弹簧的作用下向外张开,分别抵在待测槽段23槽壁的四个侧面;S5: Quickly lift the wire rope 21 and cable 22, and use the mud resistance to disengage the fixed disk 29 downwards. The four measuring arms 28 open outwards under the action of the pressure spring and respectively press against the wall of the tank section 23 to be measured. the four sides;
S6:通过倾角传感器30获取的数据判断测臂28是否张开,是则进入下一步骤,否则跳到步骤S5;S6: Determine whether the measuring arm 28 is open based on the data obtained by the inclination sensor 30, if so, proceed to the next step, otherwise jump to step S5;
S7:通过电动卷扬机19根据设定的深度间隔L缓慢提升检测探头20,读取并储存深度传感器、陀螺仪26和倾角传感器30测得的深度hj、探头方位角cosαj和四根测臂28的张开角其中,j=1,2,3,…N,i=1,2,3,4;S7: Use the electric winch 19 to slowly lift the detection probe 20 according to the set depth interval L, read and store the depth h j , the probe azimuth angle cos α j and the four measuring arms measured by the depth sensor, gyroscope 26 and inclination sensor 30 Opening angle of 28 Among them, j=1,2,3,...N, i=1,2,3,4;
S8:工控主机18根据读取的深度、探头方位角、测臂28张开角信息,计算出成槽宽度、长度和垂直度,并绘制出槽壁深度‐成槽宽度曲线、槽壁深度‐成槽长度曲线,深度‐成槽垂直度曲线以及成槽垂直度;计算成槽宽度、长度和垂直度具体方法如下:S8: The industrial control host computer 18 calculates the groove width, length and verticality based on the read depth, probe azimuth angle, and measuring arm 28 opening angle information, and draws the groove wall depth-groove width curve, groove wall depth-groove formation Length curve, depth-trough verticality curve and trough verticality; the specific method for calculating the trough width, length and verticality is as follows:
以相对的一对测臂281和测臂283为例,如图9和图10所示,通过传统的几何方法计算出测臂281和测臂283所检测出的半槽宽:

Taking the opposite pair of measuring arms 281 and 283 as an example, as shown in Figures 9 and 10, the half-slot width detected by the measuring arms 281 and 283 is calculated through traditional geometric methods:

虽然四个测点都是检测探头20在同一深度位置测得,但由于四根测臂28张开的角度可能存在差异,测点的实际深度可能并不一致,不能简单将半槽宽相加得到槽宽,通过测臂28顶端对应的深度来计算测臂28底部对应的深度,应对测点深度按下式进行修正:

Although the four measuring points are all measured by the detection probe 20 at the same depth position, due to possible differences in the opening angles of the four measuring arms 28, the actual depths of the measuring points may not be consistent and cannot be obtained by simply adding the half-slot widths. For the slot width, calculate the depth corresponding to the bottom of the measuring arm 28 through the depth corresponding to the top of the measuring arm 28. The depth of the measuring point should be corrected according to the following formula:

通过线性插值计算出每一个标准深度hj下所检测出的半槽宽B1和B2,相加得到成槽宽度B;例如根据4m和6m处对应的槽宽来通过线性插值,计算出5m这个位置的半槽宽,提高检测效率;Calculate the detected half-groove widths B 1 and B 2 at each standard depth h j through linear interpolation, and add them together to obtain the groove width B; for example, based on the corresponding groove widths at 4m and 6m, calculate through linear interpolation The half-trough width at this position of 5m improves detection efficiency;
按照上述方法计算测臂282和测臂284所检测出的半槽长;Calculate the half-groove length detected by the measuring arm 282 and the measuring arm 284 according to the above method;
根据每一个标准深度下所检测出的半槽宽以及半槽长,生成该深度对应的一个矩形截面,利用非均匀 有理样条方法将这些矩形截面在深度上连接起来,形成槽壁三维形态,如图11所示;Based on the half-groove width and half-groove length detected at each standard depth, a rectangular cross-section corresponding to the depth is generated, using non-uniform The rational spline method connects these rectangular sections in depth to form a three-dimensional shape of the groove wall, as shown in Figure 11;
根据每一个标准深度下的矩形截面确定矩形中心坐标,矩形中心坐标就是槽壁中心坐标,将槽壁中心左边沿深度连接起来形成槽孔孔斜曲线,其与轴线在槽段宽度、长度方向的偏差角度即为对应的垂直度;Determine the rectangular center coordinates based on the rectangular cross-section at each standard depth. The rectangular center coordinates are the slot wall center coordinates. Connect the left edge depths of the slot wall centers to form a slot oblique curve, which is aligned with the axis in the width and length directions of the slot section. The deviation angle is the corresponding verticality;
S9:根据深度hj判断检测探头20是否到达检测槽段的槽口,如果hj<0,则进入下一步骤,否则继续步骤S6;S9: Determine whether the detection probe 20 reaches the notch of the detection groove section according to the depth h j . If h j <0, proceed to the next step, otherwise continue to step S6;
S10:停止提升检测探头20,检测完成。S10: Stop lifting the detection probe 20, and the detection is completed.
在上述技术方案中,本申请采用的陀螺仪26检测精度为0.5°,倾角传感器30检测精度为0.07°,深度传感器精度为0.2%,使得整个成槽检测装备的整体检测精度较高,并且成槽检测装备检测操作快捷方便,检测装备重量较小,移动方便,设备操作简单,完成单幅槽段检测时间<10min,四根测臂28可以分别支撑在槽段的四个侧面,一次完成槽宽度、长度和垂直度的检测,提高检测效率。In the above technical solution, the detection accuracy of the gyroscope 26 used in this application is 0.5°, the detection accuracy of the inclination sensor 30 is 0.07°, and the depth sensor accuracy is 0.2%, which makes the overall detection accuracy of the entire trough detection equipment higher and becomes more complete. The inspection operation of the groove inspection equipment is fast and convenient. The inspection equipment is small in weight, easy to move, and the equipment is simple to operate. The time to complete the inspection of a single groove section is less than 10 minutes. The four measuring arms 28 can be supported on the four sides of the groove section respectively, and the groove can be completed in one go. Detection of width, length and verticality improves detection efficiency.
在另一种技术方案中,所述步骤五中混凝土浇筑可视化具体包括水下混凝土液面实时监测和导管安装长度实时监测两部分;In another technical solution, the visualization of concrete pouring in step five specifically includes two parts: real-time monitoring of underwater concrete liquid level and real-time monitoring of conduit installation length;
水下混凝土液面实时监测具体为:在一期钢箱接头9及二期钢筋笼制作时,提前安装分辨率为0.2m的温度光纤,在混凝土浇筑时,通过温度光纤解调设备监测温度光纤的温度变化,根据温度的变化,反映混凝土液面高度;利用的原理是,混凝土浇筑时会释放水化热,与环境温度产生温差,温度光纤埋在混凝土里面的部分与在环境中的部分,存在温度差异,以此实现对混凝土与环境分界面的判断;The specific real-time monitoring of underwater concrete liquid level is as follows: when making the first-phase steel box joint 9 and the second-phase steel cage, temperature optical fibers with a resolution of 0.2m are installed in advance. During concrete pouring, the temperature optical fibers are monitored through temperature optical fiber demodulation equipment. The temperature change reflects the height of the concrete liquid level according to the temperature change; the principle used is that when concrete is poured, hydration heat will be released, resulting in a temperature difference with the ambient temperature. The part of the temperature optical fiber buried in the concrete and the part in the environment, There is a temperature difference to judge the interface between concrete and the environment;
导管安装长度实时监测具体为:在每一节导管上安装一个包含导管长度信息的芯片,在导管架上安装电磁感应装置,每拆除一节导管时,电磁感应装置自动计数,将导管总长度减去被拆除的导管长度,即可得到剩余导管的长度。Real-time monitoring of the installation length of the conduit is as follows: installing a chip containing conduit length information on each section of conduit, and installing an electromagnetic induction device on the conduit frame. When each section of conduit is removed, the electromagnetic induction device automatically counts and reduces the total length of the conduit. Divide the length of the removed conduit into the length of the remaining conduit.
在上述技术方案中,利用提前安装在一期钢箱接头9或二期钢筋笼内部的传感器,可以实时测量混凝土浇筑标高,结合可自动记录导管长度的智能导管,实现可视化浇筑。根据水下混凝土液面高度、导管安装长度,即可实时反映水下混凝土的浇筑进度以及导管埋深,确保导管不被拔离混凝土并保持2~4m的埋深,控制水下混凝土浇筑质量,避免埋管过深或误操作拔出导管导致的水下混凝土浇筑事故。In the above technical solution, the concrete pouring elevation can be measured in real time using sensors installed in advance at the first-stage steel box joint 9 or inside the second-stage steel cage. Combined with an intelligent conduit that can automatically record the length of the conduit, visual pouring can be achieved. According to the height of the underwater concrete liquid level and the installation length of the conduit, the progress of the underwater concrete pouring and the burial depth of the conduit can be reflected in real time, ensuring that the conduit is not pulled out of the concrete and maintains a burial depth of 2 to 4m, thereby controlling the quality of underwater concrete pouring. Avoid underwater concrete pouring accidents caused by burying pipes too deep or pulling out pipes by mistake.
在另一种技术方案中,如图12所示,所述步骤八中基坑开挖控制方法为:In another technical solution, as shown in Figure 12, the foundation pit excavation control method in step eight is:
在内侧分隔地连墙2的交叉点处布置覆盖内侧隔仓的克令吊,在内侧分隔地连墙2顶部布置皮带式水平运输机,将内侧隔仓开挖的土方运至基坑外侧;Arrange a crane covering the inner compartment at the intersection of the inner partition wall 2, and arrange a belt-type horizontal transporter on the top of the inner partition wall 2 to transport the earth excavated from the inner compartment to the outside of the foundation pit;
隔仓分层开挖,通过声呐探测技术对各隔仓开挖标高进行自动采集,并传输给控制系统,每层开挖深度为2m,当相邻隔仓开挖标高差超过2m时,控制系统发出警报;Compartments are excavated in layers. The excavation elevation of each compartment is automatically collected through sonar detection technology and transmitted to the control system. The excavation depth of each layer is 2m. When the difference in excavation elevation between adjacent compartments exceeds 2m, the control system The system issues an alert;
在地连墙钢筋笼上提前布置应变计,即应力、应变监测传感器作为数据采集硬件,通过控制系统实时获取应力值,当地连墙内应力小于容许应力即设计值时,继续开挖下一层,当地连墙内应力超过容许应力时,控制系统发出警报,需立即采取减小相邻隔仓开挖标高差的措施,停止开挖泥面较深的隔仓,开挖泥面较浅的相邻隔仓,直至所有相邻隔仓泥面高差小于0.3m,继续开挖下一层,直至完成所有隔仓的开挖,容许应力阈值为浇筑混凝土容许抗拉应力,一般取0.5Mpa。Strain gauges are arranged in advance on the steel cage of the ground connection wall, that is, the stress and strain monitoring sensors are used as data acquisition hardware. The stress value is obtained in real time through the control system. When the stress in the ground connection wall is less than the allowable stress, which is the design value, the excavation of the next layer continues. , when the stress in the local connecting wall exceeds the allowable stress, the control system issues an alarm, and measures must be taken immediately to reduce the excavation elevation difference between adjacent compartments, stop excavation of compartments with deeper mud surfaces, and excavate compartments with shallower mud surfaces. For adjacent compartments, until the height difference between the mud surfaces of all adjacent compartments is less than 0.3m, continue to excavate the next layer until the excavation of all compartments is completed. The allowable stress threshold is the allowable tensile stress of poured concrete, which is generally 0.5Mpa. .
在上述技术方案中,传统地连墙基坑采用坑内水平集土,坑边垂直出土即可完成基坑开挖作业;而大型沉井基础一般采用水下吸泥作业。但本发明中的隔仓式地连墙锚碇基础,同时具备上述两种结构的特点,上述两种结构的开挖工艺均不适用,因此,提出皮带式运输机水平出土工艺,实现内侧隔仓土方开挖。该工艺的优点是,相比于大吨位塔吊出土,出土速度快、造价低。同时采用多隔仓均衡取土技术、内侧分隔地连墙2应力、变形监测系统实现基坑开挖的安全高效施工。 In the above technical solution, the traditional ground-to-ground wall foundation pit adopts horizontal soil collection in the pit, and the excavation of the foundation pit can be completed by vertical excavation of the pit edge; while the foundation of large caissons generally adopts underwater mud suction operation. However, the compartment type ground wall anchorage foundation in the present invention has the characteristics of the above two structures at the same time. The excavation processes of the above two structures are not suitable. Therefore, a belt conveyor horizontal excavation process is proposed to realize the inner compartment Earth excavation. The advantage of this process is that compared with large-tonnage tower crane excavation, the excavation speed is fast and the cost is low. At the same time, the multi-compartment balanced soil acquisition technology and the stress and deformation monitoring system of the inner dividing ground connecting wall are used to achieve safe and efficient construction of foundation pit excavation.
尽管本发明的实施方案已公开如上,但其并不仅仅限于说明书和实施方式中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节和这里示出与描述的图例。 Although the embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the description and embodiments. They can be applied to various fields suitable for the present invention. For those familiar with the art, they can easily Additional modifications may be made, and the invention is therefore not limited to the specific details and illustrations shown and described herein without departing from the general concept defined by the claims and equivalent scope.

Claims (8)

  1. 隔仓式地连墙锚碇基础的施工控制方法,其特征在于,包括:The construction control method of the compartment-type ground wall anchorage foundation is characterized by including:
    步骤一、设计隔仓式地连墙锚碇基础结构,并将隔仓式地连墙的交叉点处均设置为一期槽段,二期槽段均设置于隔仓式地连墙的非交叉点处;Step 1: Design the basic structure of the compartment-type ground connection wall anchorage, and set the intersection points of the compartment-type ground connection walls as the first-phase trough sections, and the second-phase trough sections are set at non-compartment-type ground connection walls. at the intersection;
    步骤二、将加工好的一期钢箱接头节段在施工现场拼接为整体形成一期钢箱接头,且拼接完成后的一期钢箱接头纵向偏差小于5mm;Step 2: Splice the processed first-phase steel box joint segments into a whole at the construction site to form a first-phase steel box joint, and the longitudinal deviation of the first-phase steel box joint after splicing is less than 5mm;
    步骤三、一期成槽施工;Step 3: The first phase of trough construction;
    步骤四、在一期成槽内安装一期钢箱接头;Step 4: Install the first-phase steel box joints in the first-phase trough;
    步骤五、可视化浇筑一期成槽内的钢箱混凝土,完成一期槽段施工;Step 5: Visually pour the steel box concrete in the first phase of the trough to complete the construction of the first phase of the trough section;
    步骤六、一期槽段施工完成后,根据设计图纸加工二期钢筋笼,然后进行二期成槽施工、安装二期钢筋笼、浇筑混凝土,完成二期槽段施工;Step 6: After the construction of the first phase trough section is completed, the second phase steel cage will be processed according to the design drawings, and then the second phase trough construction will be carried out, the second phase steel cage will be installed, and concrete will be poured to complete the second phase trough section construction;
    步骤七、上述地连墙施工完成后,进行隔仓式地连墙的地基加固施工;Step 7: After the construction of the above-mentioned ground connecting wall is completed, carry out the foundation reinforcement construction of the partition type ground connecting wall;
    步骤八、地基加固施工完成后,进行隔仓式地连墙内部基坑的开挖施工,然后在基坑内从下至上依次进行水下封底、底板、填芯体、顶板的施工,完成隔仓式地连墙锚碇基础的施工。Step 8. After the foundation reinforcement construction is completed, the excavation of the foundation pit inside the compartment-type ground connection wall is carried out, and then the underwater bottom seal, bottom plate, core filling body, and roof are constructed from bottom to top in the foundation pit to complete the compartment. Construction of ground-to-ground wall anchorage foundation.
  2. 如权利要求1所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,设计的隔仓式地连墙锚碇基础结构包括:The construction control method of compartment-type ground connection wall anchorage foundation according to claim 1, characterized in that the designed compartment-type ground connection wall anchorage foundation structure includes:
    隔仓式地连墙,其包括外侧地连墙和内侧分隔地连墙,内侧分隔地连墙将外侧地连墙所围成的封闭区域分隔为若干个小隔仓;The partition-type connecting wall includes an outer connecting wall and an inner dividing connecting wall. The inner dividing connecting wall divides the enclosed area surrounded by the outer connecting wall into several small compartments;
    地基加固体,其包括外侧地连墙所围成的封闭区域内的超高压旋喷桩加固体;Foundation reinforcement, which includes ultra-high-pressure jet grouting pile reinforcement in the closed area surrounded by the outer ground connection wall;
    内部结构,其包括从下至少依次设置的水下封底、底板、填芯体、顶板。The internal structure includes an underwater bottom seal, a bottom plate, a core-filling body, and a top plate arranged in sequence at least from the bottom.
  3. 如权利要求1所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,所述步骤二中拼接为整体的一期钢箱接头的纵向偏差测量方法为:The construction control method of compartment-type ground wall anchorage foundation according to claim 1, characterized in that the longitudinal deviation measurement method of the first-phase steel box joints spliced into a whole in step two is:
    将一期钢箱接头平放在平整度满足设计要求的胎架上,并在一期钢箱接头上表面中轴线上布置三个光学棱镜,其沿一期钢箱接头长度方向均匀布置在上、中、下三点;Place the first-stage steel box joint flat on a tire frame whose flatness meets the design requirements, and arrange three optical prisms on the central axis of the upper surface of the first-stage steel box joint, which are evenly arranged on the upper surface along the length direction of the first-stage steel box joint. , middle and lower three points;
    在一期钢箱接头外侧布置一台全站仪,采集三个光学棱镜的大地坐标(x1、y1、z1)、(x2、y2、z2)、(x3、y3、z3),并分别计算一期钢箱接头在x和z方向上的偏差:
    nx=(max(x1,x2,x3)‐min(x1,x2,x3));nz=(max(z1,z2,z3)‐min(z1,z2,z3));
    A total station is arranged outside the joint of the steel box in the first phase to collect the geodetic coordinates of three optical prisms (x 1 , y 1 , z 1 ), (x 2 , y 2 , z 2 ), (x 3 , y 3 , z 3 ), and calculate the deviations of the first-phase steel box joints in the x and z directions respectively:
    n x =(max(x 1 ,x 2 ,x 3 )‐min(x 1 ,x 2 ,x 3 ));n z =(max(z 1 ,z 2 ,z 3 )‐min(z 1 , z 2 ,z 3 ));
    当max(nx,nz)<5mm时,纵向偏差合格,进行下一步施工,反之纵向偏差不合格,重新拼接一期钢箱接头。When max (n x , n z ) <5mm, the longitudinal deviation is qualified and the next step of construction is carried out. Otherwise, the longitudinal deviation is unqualified and the first-phase steel box joints are re-spliced.
  4. 如权利要求1所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,所述步骤三中一期成槽施工时,槽孔内充满膨润土泥浆,泥浆性能通过泥浆智能控制系统进行自动调整,所述泥浆智能控制系统包括泥浆性能参数检测装置、循环泥浆池、新浆池、新浆膨化池和制浆站,所述泥浆性能参数检测装置用于检测循环泥浆池中泥浆的比重、PH值、粘度、含砂率参数,循环泥浆池、新浆池、新浆膨化池和制浆站依次连通,所述新浆池中设置有第二泵,其用于将新浆池中的泥浆泵至循环泥浆池,所述新浆膨化池中设置有第一泵,其用于将新浆膨化池中的泥浆泵至新浆池,所述循环泥浆池中的泥浆充入至槽孔内;The construction control method of compartment type ground wall anchorage foundation according to claim 1, characterized in that, during the first-stage trough construction in step three, the slot holes are filled with bentonite mud, and the mud performance is intelligently controlled by the mud. The system automatically adjusts. The mud intelligent control system includes a mud performance parameter detection device, a circulating mud pool, a new mud pool, a new mud expansion tank and a pulping station. The mud performance parameter detection device is used to detect mud in the circulating mud pool. Specific gravity, pH value, viscosity, and sand content parameters, the circulating mud tank, the new slurry tank, the new slurry expansion tank and the pulping station are connected in sequence, and a second pump is provided in the new slurry tank, which is used to pump the new slurry The mud in the pool is pumped to the circulating mud pool. The new mud expansion pool is provided with a first pump, which is used to pump the mud in the new mud expansion pool to the new mud pool. The mud in the circulating mud pool is filled into into the slot;
    所述泥浆智能控制系统的具体控制方法为:The specific control method of the mud intelligent control system is:
    当泥浆性能参数检测装置检测到循环泥浆池中泥浆比重大于1.2或PH值大于11或粘度大于35s或含砂率大于4%时,启动第二泵,将新浆池中的新浆抽至循环泥浆池,直至循 环泥浆池中泥浆比重小于1.2、PH值小于11、粘度小于35s、含砂率小于4%时,关闭第二泵,记录由新浆池泵入循环泥浆池的体积V1When the mud performance parameter detection device detects that the specific gravity of the mud in the circulating mud pool is greater than 1.2 or the PH value is greater than 11 or the viscosity is greater than 35s or the sand content is greater than 4%, the second pump is started to pump the new slurry in the new slurry pool to the circulation Mud pool until circulating When the specific gravity of the mud in the ring mud pool is less than 1.2, the pH value is less than 11, the viscosity is less than 35s, and the sand content is less than 4%, turn off the second pump and record the volume V 1 pumped into the circulating mud pool from the new mud pool;
    第二泵启动时,同时启动制浆站,按预先设定的新浆配比拌制新浆,拌制体积为V1,并输送至新浆膨化池膨化,待膨化24h后,打开第一泵,将充分膨化的新浆抽至新浆池,即完成一次循环泥浆性能智能控制。When the second pump is started, the pulping station is started at the same time, and new pulp is mixed according to the preset new pulp ratio. The mixing volume is V 1 and is transported to the new pulp expansion tank for expansion. After expansion for 24 hours, the first pulp is opened. The pump pumps the fully expanded new slurry to the new slurry pool, thus completing the intelligent control of mud performance in one cycle.
  5. 如权利要求1所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,所述步骤三中一期成槽施工时,每间隔20m或4h利用成槽检测装备对成槽垂直度进行一次检测,所述成槽检测装备包括工控主机、电动卷扬机、检测探头、一对钢丝绳和电缆,所述电动卷扬机设置于待测槽段的槽口中心,所述检测探头通过两侧的一对钢丝绳和中间的电缆连接至所述电动卷扬机上并位于待测槽段内,所述电动卷扬机也通过电缆连接至工控主机,所述电动卷扬机上的卷筒分别缠绕一对钢丝绳和电缆,所述电动卷扬机的卷筒通过交流电机驱动正反转,所述电动卷扬机内还设置有深度传感器,其用于获取所述检测探头所处的深度,所述检测探头包括防扭连接件、密封筒、陀螺仪、固定长杆、四根测臂和固定圆盘,所述防扭连接件位于所述密封筒的顶部,一对钢丝绳对称连接于所述防扭连接件上,所述陀螺仪设置于所述密封筒的内部,用于测量检测探头的方位角,所述电缆穿过所述防扭连接件中心后连接至所述陀螺仪,所述固定长杆连接至所述密封筒的底部中心,四根测臂呈正交关系设置于所述密封筒底部,所述测臂顶端与所述密封筒铰接且通过压力弹簧设置为仅沿测臂与固定长杆的竖向轴线组成的平面内转动,所述测臂顶端设置倾角传感器,用于测量测臂张开角度,所述固定圆盘中心具有所述固定长杆穿过的通孔,所述固定圆盘顶面设置有一圈挡环,其用于将四根测臂的下端限位于其内,所述工控主机用于控制电动卷扬机动作,读取深度传感器、陀螺仪以及倾角传感器获取的数据并计算显示结果。The construction control method of compartment type ground wall anchorage foundation according to claim 1, characterized in that, during the first phase of troughing construction in step three, the troughing detection equipment is used to check the troughing every 20m or 4h. The verticality is tested once. The trough detection equipment includes an industrial control host, an electric winch, a detection probe, a pair of wire ropes and cables. The electric winch is set at the center of the slot of the trough section to be tested. The detection probe passes through both sides. A pair of steel wire ropes and a middle cable are connected to the electric winch and are located in the tank section to be tested. The electric winch is also connected to the industrial control host through cables. The drums on the electric winch are respectively wound around a pair of steel wire ropes and cables. , the drum of the electric winch is driven by an AC motor to rotate forward and reverse. The electric winch is also provided with a depth sensor, which is used to obtain the depth of the detection probe. The detection probe includes an anti-twist connector, A sealing cylinder, a gyroscope, a fixed long rod, four measuring arms and a fixed disk. The anti-twist connector is located at the top of the sealing cylinder. A pair of steel wire ropes are symmetrically connected to the anti-twist connector. The gyro The instrument is arranged inside the sealing cylinder and is used to measure the azimuth angle of the detection probe. The cable passes through the center of the anti-twist connector and is connected to the gyroscope. The fixed long rod is connected to the sealing cylinder. At the center of the bottom, four measuring arms are arranged in an orthogonal relationship at the bottom of the sealing cylinder. The top end of the measuring arm is hinged with the sealing cylinder and is arranged through a pressure spring to only consist of the vertical axis of the measuring arm and the fixed long rod. Rotate in the plane, the top of the measuring arm is equipped with an inclination sensor for measuring the opening angle of the measuring arm, the center of the fixed disk has a through hole through which the fixed long rod passes, and the top surface of the fixed disk is provided with a The ring is used to limit the lower ends of the four measuring arms within it. The industrial control host is used to control the action of the electric winch, read the data obtained by the depth sensor, gyroscope and inclination sensor and calculate and display the results.
  6. 如权利要求5所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,所述成槽检测装备对成槽垂直度进行检测的方法为:The construction control method of compartment-type ground wall anchorage foundation according to claim 5, characterized in that the method for detecting the verticality of the trough by the trough detection equipment is:
    S1:在待测槽口安装成槽检测装备,使其为初始状态,四根测臂通过固定圆盘限位为竖直状态,检测探头陀螺仪数据归零;S1: Install the groove detection equipment at the notch to be tested, and make it the initial state. The four measuring arms are limited by the fixed disk to the vertical state, and the detection probe gyroscope data is reset to zero;
    S2:通过电动卷扬机将检测探头放入待测槽段内,根据电动卷扬机内的深度传感器读取检测探头所处的深度位置,确定槽深H;S2: Put the detection probe into the groove section to be tested through the electric winch, read the depth position of the detection probe according to the depth sensor in the electric winch, and determine the groove depth H;
    S3:人工通过探头电缆和钢丝绳的松紧判断检测探头是否到达槽底,是则进入下一步骤,否则跳到S2;S3: Manually judge whether the detection probe reaches the bottom of the tank through the tightness of the probe cable and steel wire rope. If so, go to the next step, otherwise jump to S2;
    S4:设置检测探头提升深度间隔为L,则检测过程中数据组数N=H/L;S4: Set the detection probe lifting depth interval to L, then the number of data sets during the detection process N = H/L;
    S5:快速提拉钢丝绳和电缆,利用泥浆阻力使固定圆盘向下脱开,四根测臂在压力弹簧的作用下向外张开,分别抵在待测槽段槽壁的四个侧面;S5: Quickly pull up the wire rope and cable, and use the mud resistance to release the fixed disc downwards. The four measuring arms open outwards under the action of the pressure spring and respectively press against the four sides of the tank wall of the tank section to be tested;
    S6:通过倾角传感器获取的数据判断测臂是否张开,是则进入下一步骤,否则跳到步骤S5;S6: Determine whether the measuring arm is open based on the data obtained by the inclination sensor, if so, proceed to the next step, otherwise jump to step S5;
    S7:通过电动卷扬机根据设定的深度间隔L缓慢提升检测探头,读取并储存深度传感器、陀螺仪和倾角传感器测得的深度hj、探头方位角cosαj和四根测臂的张开角其中,j=1,2,3,…N,i=1,2,3,4;S7: Use the electric winch to slowly lift the detection probe according to the set depth interval L, read and store the depth h j measured by the depth sensor, gyroscope and inclination sensor, the probe azimuth angle cosα j and the opening angle of the four measuring arms. Among them, j=1,2,3,...N, i=1,2,3,4;
    S8:工控主机根据读取的深度、探头方位角、测臂张开角信息,计算出成槽宽度、长度和垂直度,并绘制出槽壁深度‐成槽宽度曲线、槽壁深度‐成槽长度曲线,深度‐成槽垂直度曲线以及成槽垂直度;计算成槽宽度、长度和垂直度具体方法如下: S8: The industrial control host calculates the groove width, length and verticality based on the read depth, probe azimuth angle and measuring arm opening angle information, and draws the groove wall depth-groove width curve and groove wall depth-groove length curve , depth-trough verticality curve and trough verticality; the specific method for calculating the trough width, length and verticality is as follows:
    以相对的一对测臂1和测臂3为例,计算出测臂1和测臂3所检测出的半槽宽:

    Taking the opposite pair of measuring arm 1 and measuring arm 3 as an example, calculate the half-slot width detected by measuring arm 1 and measuring arm 3:

    测点深度按下式进行修正:

    The depth of the measuring point is corrected as follows:

    通过线性插值计算出每一个标准深度hj下所检测出的半槽宽B1和B2,相加得到成槽宽度B;Calculate the detected half-groove widths B 1 and B 2 at each standard depth h j through linear interpolation, and add them to obtain the groove width B;
    按照上述方法计算测臂2和测臂4所检测出的半槽长;Calculate the half-groove length detected by measuring arm 2 and measuring arm 4 according to the above method;
    根据每一个标准深度下所检测出的半槽宽以及半槽长,生成该深度对应的一个矩形截面,利用非均匀有理样条方法将这些矩形截面在深度上连接起来,形成槽壁三维形态;Based on the half-groove width and half-groove length detected at each standard depth, a rectangular section corresponding to that depth is generated, and the non-uniform rational spline method is used to connect these rectangular sections in depth to form a three-dimensional shape of the groove wall;
    根据每一个标准深度下的矩形截面确定矩形中心坐标,矩形中心坐标就是槽壁中心坐标,将槽壁中心左边沿深度连接起来形成槽孔孔斜曲线,其与轴线在槽段宽度、长度方向的偏差角度即为对应的垂直度;Determine the rectangular center coordinates based on the rectangular cross-section at each standard depth. The rectangular center coordinates are the slot wall center coordinates. Connect the left edge depths of the slot wall centers to form a slot oblique curve, which is aligned with the axis in the width and length directions of the slot section. The deviation angle is the corresponding verticality;
    S9:根据深度hj判断检测探头是否到达检测槽段的槽口,如果hj<0,则进入下一步骤,否则继续步骤S6;S9: Determine whether the detection probe reaches the notch of the detection groove section according to the depth h j . If h j <0, proceed to the next step, otherwise continue to step S6;
    S10:停止提升检测探头,检测完成。S10: Stop lifting the detection probe and the detection is completed.
  7. 如权利要求1所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,所述步骤五中混凝土浇筑可视化具体包括水下混凝土液面实时监测和导管安装长度实时监测两部分;The construction control method of compartment type ground wall anchorage foundation according to claim 1, characterized in that the concrete pouring visualization in step five specifically includes two parts: real-time monitoring of underwater concrete liquid level and real-time monitoring of conduit installation length. ;
    水下混凝土液面实时监测具体为:在一期钢箱接头及二期钢筋笼制作时,提前安装分辨率为0.2m的温度光纤,在混凝土浇筑时,通过温度光纤解调设备监测温度光纤的温度变化,根据温度的变化,反映混凝土液面高度;The specific real-time monitoring of underwater concrete liquid level is as follows: when making the steel box joints of the first phase and the steel cage of the second phase, a temperature optical fiber with a resolution of 0.2m is installed in advance. When the concrete is poured, the temperature optical fiber is monitored through the temperature optical fiber demodulation equipment. Temperature changes, according to changes in temperature, reflect the concrete liquid level;
    导管安装长度实时监测具体为:在每一节导管上安装一个包含导管长度信息的芯片,在导管架上安装电磁感应装置,每拆除一节导管时,电磁感应装置自动计数,将导管总长度减去被拆除的导管长度,即可得到剩余导管的长度。Real-time monitoring of the installation length of the conduit is as follows: installing a chip containing conduit length information on each section of conduit, and installing an electromagnetic induction device on the conduit frame. When each section of conduit is removed, the electromagnetic induction device automatically counts and reduces the total length of the conduit. Divide the length of the removed conduit into the length of the remaining conduit.
  8. 如权利要求2所述的隔仓式地连墙锚碇基础的施工控制方法,其特征在于,所述步骤八中基坑开挖控制方法为:The construction control method of compartment type ground wall anchorage foundation according to claim 2, characterized in that the foundation pit excavation control method in step eight is:
    在内侧分隔地连墙的交叉点处布置覆盖内侧隔仓的克令吊,在内侧分隔地连墙顶部布置皮带式水平运输机,将内侧隔仓开挖的土方运至基坑外侧;A crane covering the inner compartment is arranged at the intersection of the inner dividing ground connecting wall, and a belt-type horizontal conveyor is arranged on the top of the inner dividing connecting wall to transport the earth excavated from the inner compartment to the outside of the foundation pit;
    隔仓分层开挖,通过声呐探测技术对各隔仓开挖标高进行自动采集,并传输给控制系 统,每层开挖深度为2m,当相邻隔仓开挖标高差超过2m时,控制系统发出警报;The compartments are excavated in layers. The excavation elevation of each compartment is automatically collected through sonar detection technology and transmitted to the control system. The excavation depth of each layer is 2m. When the difference in elevation between adjacent compartments exceeds 2m, the control system will issue an alarm;
    在地连墙钢筋笼上提前布置应变计,通过控制系统实时获取应力值,当地连墙内应力小于容许应力时,继续开挖下一层,当地连墙内应力超过容许应力时,控制系统发出警报,停止开挖泥面较深的隔仓,开挖泥面较浅的相邻隔仓,直至所有相邻隔仓泥面高差小于0.3m,继续开挖下一层,直至完成所有隔仓的开挖,容许应力阈值为浇筑混凝土容许抗拉应力。 Strain gauges are arranged in advance on the steel cage of the ground connection wall, and the stress value is obtained in real time through the control system. When the stress in the ground connection wall is less than the allowable stress, the excavation of the next layer continues. When the stress in the ground connection wall exceeds the allowable stress, the control system issues a Alarm, stop excavation of the compartment with deeper mud surface, and excavate adjacent compartments with shallower mud surface until the height difference of mud surface in all adjacent compartments is less than 0.3m, continue to excavate the next layer until all compartments are completed For the excavation of the warehouse, the allowable stress threshold is the allowable tensile stress of poured concrete.
PCT/CN2023/081102 2022-07-08 2023-03-13 Construction control method for partition type concrete diaphragm wall anchorage foundation WO2024007614A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210800468.3 2022-07-08
CN202210800468.3A CN115198783B (en) 2022-07-08 2022-07-08 Construction control method of compartment type ground continuous wall anchorage foundation

Publications (1)

Publication Number Publication Date
WO2024007614A1 true WO2024007614A1 (en) 2024-01-11

Family

ID=83579850

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2023/081102 WO2024007614A1 (en) 2022-07-08 2023-03-13 Construction control method for partition type concrete diaphragm wall anchorage foundation

Country Status (2)

Country Link
CN (1) CN115198783B (en)
WO (1) WO2024007614A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117911419A (en) * 2024-03-20 2024-04-19 东北大学 Method and device for detecting steel rotation angle enhancement of medium plate, medium and equipment

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115198783B (en) * 2022-07-08 2023-09-08 中交第二航务工程局有限公司 Construction control method of compartment type ground continuous wall anchorage foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102748008A (en) * 2012-07-18 2012-10-24 武汉岩海工程技术有限公司 Detecting device capable of realizing drill hole three-dimensional imaging and method thereof
CN110409421A (en) * 2019-08-05 2019-11-05 广西路桥工程集团有限公司 Ultra-deep stake ground-connecting-wall construction system
CN111206577A (en) * 2020-01-15 2020-05-29 保利长大工程有限公司 Construction method of steel guide wall foundation of sea area deepwater anchorage foundation
CN113006113A (en) * 2021-03-04 2021-06-22 浙江大学 Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation
CN115198783A (en) * 2022-07-08 2022-10-18 中交第二航务工程局有限公司 Construction control method of partition chamber type diaphragm wall anchorage foundation

Family Cites Families (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH614484A5 (en) * 1977-07-05 1979-11-30 Comar Reg Trust Metal formwork element for the formation of vertical joints during the construction of cast walls
JPH0781482B2 (en) * 1991-07-18 1995-08-30 鹿島建設株式会社 Method and device for measuring the wall shape of a continuous underground wall
NL9201345A (en) * 1992-07-24 1994-02-16 Verstraeten Beheersmij Bv A method for arranging deep partition walls in the soil, as well as an excavating device for use in this method.
JPH06212650A (en) * 1993-01-20 1994-08-02 Ohbayashi Corp Underground continuous wall and construction thereof
JPH0820943A (en) * 1994-07-08 1996-01-23 Mitsui Constr Co Ltd Construction method of under ground wall
JP4037004B2 (en) * 1999-03-08 2008-01-23 株式会社奥村組 Construction method of underground structure
WO2007130667A2 (en) * 2006-05-05 2007-11-15 Henderson Allan P Post-tension pile anchor foundation and method therefor
JP2008280828A (en) * 2007-04-12 2008-11-20 Kinji Takeuchi Soil improvement body, foundation structure of building comprising mat foundation, and construction method of soil improvement mat foundation
ITTO20110909A1 (en) * 2011-10-13 2013-04-14 Soilmec Spa TREATMENT PLANT FOR PUNCHING SLUDGE.
CN103266618B (en) * 2013-05-22 2015-12-09 安徽省交通控股集团有限公司 The anchoring process of steel cofferdam and steel cofferdam structure
CN103510531B (en) * 2013-09-18 2016-06-15 中交公路长大桥建设国家工程研究中心有限公司 A kind of split type open caisson staking Compound Anchorage basis and construction method thereof
CN104131584B (en) * 2014-06-04 2016-03-16 杨燕军 With continuous wall trench underground quality detection device and the method thereof of electronic compass
CN106013086A (en) * 2016-06-23 2016-10-12 程华清 Construction method for processing underground continuous wall joint through boss type I-steel joint box
US10138616B2 (en) * 2016-08-12 2018-11-27 Wuhan Zhihe Geotechnical Engineering Co., Ltd. Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
JP6812233B2 (en) * 2016-12-21 2021-01-13 株式会社熊谷組 Pile hole inspection method and pile hole inspection equipment
CN109778837A (en) * 2019-03-20 2019-05-21 广东省源天工程有限公司 Cast-in-place ground-connecting-wall adjacent slot section I-shaped steel joint sand pocket device and its application method
CN111964636A (en) * 2019-05-20 2020-11-20 北京零偏科技有限责任公司 Method for detecting deformation of pipeline by using pipeline deformation detection device
CN110409422B (en) * 2019-08-05 2021-02-26 广西路桥工程集团有限公司 Diaphragm wall construction method and diaphragm wall construction system
CN111287353B (en) * 2020-02-14 2021-04-13 上海上安机械施工有限公司 Unit curtain wall hoisting process
CN111519637B (en) * 2020-04-10 2021-12-24 深圳市工勘基础工程有限公司 Grooving comprehensive construction method for pipeline underground diaphragm wall
CN112376599B (en) * 2020-11-16 2024-08-06 中交公路规划设计院有限公司 Double-layer double-square composite ground continuous wall anchorage foundation and construction method thereof
CN113718753B (en) * 2021-06-15 2023-04-28 中交二航局第三工程有限公司 Anchor underground continuous wall foundation assembled type intermediate wall and construction method
CN113671159A (en) * 2021-08-19 2021-11-19 黄河勘测规划设计研究院有限公司 Method for inspecting construction quality of impervious wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102748008A (en) * 2012-07-18 2012-10-24 武汉岩海工程技术有限公司 Detecting device capable of realizing drill hole three-dimensional imaging and method thereof
CN110409421A (en) * 2019-08-05 2019-11-05 广西路桥工程集团有限公司 Ultra-deep stake ground-connecting-wall construction system
CN111206577A (en) * 2020-01-15 2020-05-29 保利长大工程有限公司 Construction method of steel guide wall foundation of sea area deepwater anchorage foundation
CN113006113A (en) * 2021-03-04 2021-06-22 浙江大学 Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation
CN115198783A (en) * 2022-07-08 2022-10-18 中交第二航务工程局有限公司 Construction control method of partition chamber type diaphragm wall anchorage foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117911419A (en) * 2024-03-20 2024-04-19 东北大学 Method and device for detecting steel rotation angle enhancement of medium plate, medium and equipment

Also Published As

Publication number Publication date
CN115198783B (en) 2023-09-08
CN115198783A (en) 2022-10-18

Similar Documents

Publication Publication Date Title
WO2024007614A1 (en) Construction control method for partition type concrete diaphragm wall anchorage foundation
CN105239563B (en) A kind of supporting rotary drilling rig dry method pore-creating filling pile structure of grouting behind shaft or drift lining and construction method
CN105887813A (en) Large-diameter super-long pile construction method in karst area through full-casing pipe full rotating and rotary drilling
CN102691294B (en) Construction method of underground continuous wall
CN203846485U (en) Long pile percussion drill hole forming construction device
CN103924585B (en) The construction method of wind-powered electricity generation socketed pile
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN105672314B (en) A kind of semi-inverse method steel pipe post pile construction method
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
CN105696550B (en) A kind of three axes agitating pile construction method of additional reinforcement continuous wall trench underground
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN108149678A (en) A kind of loess retaining wall does the construction method of operation pore-creating filling pile
CN110258658B (en) Construction method for pre-judging and treating leakage of underground diaphragm wall
CN106836206A (en) Casing rotary digging bore forming method
CN102635113A (en) Construction method for hydraulic vibrating sinking pipe cast-in-place piles
CN208721064U (en) Real-time monitoring system across existing subway tunnel on a kind of city tunnel
CN104264663A (en) Hard cutting construction technology for secant piles
CN116289969A (en) Deep foundation pit support structure secant pile anti-seepage construction method based on sonar detection technology
CN205748469U (en) Many Information Field monitoring systems of a kind of reservoir landslide
CN115369860A (en) Construction method of super-long isolation pile close to subway
CN107100213A (en) Soil disturbance monitoring system and monitoring method of the bridge construction of pile groups to adjacent piles
CN111519624A (en) Pile foundation construction method
CN207943803U (en) Diaphram wall steel reinforcement cage lifting device under overpass
CN115726403A (en) Open caisson construction visual monitoring system and monitoring method based on Beidou and 5G
CN107675700A (en) The construction method of diaphram wall

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 23834398

Country of ref document: EP

Kind code of ref document: A1