WO2023028818A1 - Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor - Google Patents

Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor Download PDF

Info

Publication number
WO2023028818A1
WO2023028818A1 PCT/CN2021/115589 CN2021115589W WO2023028818A1 WO 2023028818 A1 WO2023028818 A1 WO 2023028818A1 CN 2021115589 W CN2021115589 W CN 2021115589W WO 2023028818 A1 WO2023028818 A1 WO 2023028818A1
Authority
WO
WIPO (PCT)
Prior art keywords
corridor
horizontal
several
construction
rise building
Prior art date
Application number
PCT/CN2021/115589
Other languages
French (fr)
Chinese (zh)
Inventor
胡松涛
贺宏波
王杰
徐俊
郭乐
Original Assignee
中铁上海工程局集团第三工程有限公司
中铁上海工程局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁上海工程局集团第三工程有限公司, 中铁上海工程局集团有限公司 filed Critical 中铁上海工程局集团第三工程有限公司
Priority to PCT/CN2021/115589 priority Critical patent/WO2023028818A1/en
Priority to DE212021000476.8U priority patent/DE212021000476U1/en
Publication of WO2023028818A1 publication Critical patent/WO2023028818A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3247Storey high safety barrier hung from the facade and sliding up from level to level as work progresses

Definitions

  • the invention relates to the technical field of high-rise building construction, in particular to an external hanger for the construction of a high-rise building structure reflecting a poured aerial corridor and a construction method thereof.
  • the cantilevered scaffolding system is mostly used for the outer frame system at the corridor, using I-beam six layers and one overhang (cantilever steel pipe fasteners shall not exceed 25 meters in height according to relevant regulations).
  • high-rise buildings need to use a large number of steel pipe fasteners.
  • the construction requires a lot of labor, the construction is difficult, the construction period is long, and the safety risk of the construction is high.
  • Air corridors in high-rise buildings are mostly found between two taller buildings (main buildings), and their structures are cast-in-place reinforced concrete structures. During construction, formwork needs to be laid and concrete poured, and scaffolding needs to be erected for construction. However, when the air corridor (mainly the beam supporting its main body) adopts a pure reinforced concrete structure, because it cannot bear external forces before solidification, it is even necessary to rely on the reinforcement cage on other structures to ensure its accurate position during construction, and it is necessary to set up support. Formwork and scaffolding; and when the ground height of the aerial corridor is high, the erected formwork and scaffolding are easy to lose stability, and relevant regulations do not allow this, the cost is high, and disassembly is difficult, and there is a greater safety risk .
  • the object of the present invention is to provide an external hanger for the construction of high-rise building structure reflecting the pouring corridor in the sky and its construction method, so as to realize safe, reliable and convenient construction of the cast-in-place reinforced concrete structure of the sky corridor of the high-rise building structure.
  • a high-rise building structure embodies an external hanger for the construction of an aerial corridor, comprising:
  • each horizontal support beam cantilever horizontally on both sides of the cured cast-in-place concrete corridor on the current floor, and are fixed by locking parts pre-buried above the cast-in-place concrete corridor. fixed;
  • the main body of the external hanger includes a two-layer protective structure, wherein the bottom protective structure is fixed to the horizontal support beam, including the bottom walkway slab and several vertical support rods located on both sides of the bottom walkway slab, and the upper protective structure includes the upper walkway slab and several vertical protective rods located outside the upper walkway slab, the vertical support rods are used to support the upper walkway slab, the height of the upper walkway slab is the same as the height of the upper corridor to be constructed adapt.
  • the bottom protection structure also includes two bottom horizontal horizontal bars parallel to each other and along the extension direction of the corridor, and several bottom horizontal vertical bars connecting the two bottom horizontal bars.
  • the bottom walkway board is laid on On several bottom horizontal longitudinal bars, several vertical support bars are arranged on two bottom horizontal cross bars;
  • the upper protective structure also includes two upper horizontal bars parallel to each other and along the extending direction of the corridor, several upper horizontal longitudinal bars connecting the two upper horizontal bars, and the upper layer walkway boards are laid on several upper layer On the horizontal longitudinal bar, several vertical protective bars are arranged on the outer upper level horizontal bar;
  • Each upper level horizontal bar connects several vertical support bars on one side of the bottom walkway slab.
  • the vertical support rods on both sides of the bottom walkway slab are oppositely arranged, and a transverse tie rod is connected between the two oppositely arranged vertical support rods.
  • a diagonal tie rod is connected between the transverse tie rod and the upper protective structure.
  • the inner vertical support rods in the bottom protection structure are arranged oppositely, and a horizontal tie rod is connected between the two oppositely arranged vertical support rods.
  • the inner sides of the bottom walkway slab and the upper walkway slab are provided with flaps.
  • the locking member is a U-shaped pipe clamp, including a U-shaped sleeve, two bolts and a steel pressure plate, and the two free ends of the U-shaped sleeve are provided with internal threads that cooperate with the bolts.
  • There are two through holes on the steel pressure plate the bottom of the U-shaped sleeve is pre-buried in concrete, the horizontal support beam is placed between the two free ends of the U-shaped sleeve, and the bolts pass through
  • the through hole of the steel pressing plate is threadedly connected with the free end of the U-shaped sleeve, and the steel pressing plate is used for pressing and fastening the horizontal support beam.
  • the main body of the external hanger is fixedly connected to the end of the horizontal support beam;
  • step S3 use a tower crane to lift the main body of the external hanger layer by layer.
  • the present invention cantilever and fix the horizontal support beam on the cured corridor, and the two ends of the horizontal support beam respectively support two external hanger main bodies, that is, the external hanger main bodies are installed on both sides of the corridor, and the external hanger main body includes two layers.
  • the height of the bottom protective structure is adapted to the height of the corridor on the current floor
  • the height of the upper walkway slab of the upper protective structure is adapted to the height of the upper corridor to be constructed, so the upper protective structure is suitable for the corridor on the first floor to be constructed for construction. Since the horizontal support beam is fixed above the corridor, there is no need to reserve an I-shaped steel hole in the outer wall, which reduces the engineering volume of the outer wall blocking the hole and the construction difficulty of the outer wall waterproof. With the layer-by-layer construction of the corridor, the main body of the outer hanger It can also be lifted layer by layer. The entire external rack is only the height of the two-story corridor, which has good stability and low safety risks.
  • Fig. 1 is the front view of the external hanger for the construction of the high-rise building structure embodied in the sky corridor provided by an embodiment of the present invention
  • Fig. 2 is a schematic structural view of the main body of the external hanger provided by an embodiment of the present invention
  • Fig. 3 is a schematic diagram of installing an external pylon provided by an embodiment of the present invention.
  • Fig. 4 is a schematic diagram of an external hanger during corridor construction provided by an embodiment of the present invention.
  • Fig. 5 is a front view of a gallery U-shaped pipe clip provided by an embodiment of the present invention.
  • Fig. 6 is a schematic diagram of a pre-embedded U-shaped pipe clamp provided by an embodiment of the present invention.
  • Fig. 7 is a schematic diagram of installing a horizontal support beam provided by an embodiment of the present invention.
  • a high-rise building structure provided by an embodiment of the present invention embodies an external hanger for the construction of a corridor in the air, including: several horizontal support beams 100, and the two ends of each horizontal support beam 100 are horizontal Cantilevered on both sides of the cured cast-in-place concrete corridor on the current floor, fixed by the locking parts 200 pre-buried above the cast-in-place concrete corridor; several external hanger bodies 300 located on both sides of the corridor, Each of the hanger main bodies 300 is fixedly connected to ends of several horizontal support beams 100 .
  • the horizontal support beam 100 can be made of I-beam.
  • the main body 300 of the external hanger is a two-layer protective structure, wherein the bottom protective structure 310 is fixed to the horizontal support beam 100, including the bottom walkway plate 311 and several vertical support rods located on both sides of the bottom walkway plate 312, the upper protective structure 320 includes an upper walkway slab 321 and a number of vertical protective bars 322 located outside the upper walkway slab 321, the vertical support bars 312 are used to support the upper walkway slab 321, the upper walkway slab
  • the height of 321 adapts to the height of the upper corridor to be constructed.
  • the external hanger structure provided in this embodiment is to hang and fix the horizontal support beam 100 on the cured corridor, and the two ends of the horizontal support beam 100 respectively support two external hanger main bodies 300, that is, the external hangers are installed on both sides of the corridor.
  • the frame main body 300 and the external hanger main body include two layers, wherein the height of the bottom protective structure 310 is adapted to the height of the corridor on the current floor, and the height of the upper walkway plate 321 of the upper protective structure 320 is adapted to the height of the upper corridor to be constructed. Therefore, the upper protective structure 320 is suitable for construction of the upper corridor to be constructed.
  • the horizontal support beam 100 is fixed above the corridor, there is no need to reserve an I-shaped steel hole in the outer wall, which reduces the engineering volume of the outer wall plugging the hole and the construction difficulty of the outer wall waterproof.
  • the external hanger The main body 300 can also be lifted layer by layer, and the entire external hanger is only the height of a two-story corridor, which has good stability and low safety risks.
  • Hanging lugs can be reserved on the main body 300 of the external hanger, and the hanging points can be set on the top of the main body 300 of the external hanger. There are no less than two hanging points, and the lifting lugs are custom-made connecting steel plates. Hanging points can also be arranged on the frameworks on both sides of the external hanger main body 300, in order to maintain the overall balance of the frame body, the hanging points should be no less than 4 points, symmetrically and evenly arranged.
  • the bottom protection structure 310 also includes two bottom horizontal bars 313 parallel to each other and along the extension direction of the corridor, and several bottom horizontal bars 314 connecting the two bottom horizontal bars 313.
  • the bottom walkway slab 311 is laid on several bottom horizontal longitudinal bars 314, and several vertical support bars 312 are arranged on two bottom horizontal bars 313;
  • the upper protective structure 320 also includes two The upper horizontal bar 323 in the extension direction of the corridor, several upper horizontal longitudinal bars 324 connecting the two upper horizontal bar 323, the upper floor walkway board 321 is laid on several upper horizontal longitudinal bars 324, several vertical
  • the protective rod 322 is arranged on the upper horizontal bar 323 on the outside; the upper horizontal bar 323 on the inner side connects several vertical support bars 312 inside the bottom walkway plate 311, and the upper horizontal bar 323 on the outer side connects the bottom layer
  • Several vertical support rods 312 on the inner side of the corridor slab 311, the inner side and the outer side here are relative to the corridor, the side of the bottom corridor 311 close to the corridor is the inner side, and the side
  • the bottom walkway plate 311 and the upper walkway plate 321 can be patterned steel plates for anti-slip when people walk.
  • the rods such as the longitudinal bar 314, the upper horizontal bar 323, and the upper horizontal bar 324 can be square tubes, and the specific size can be set according to the actual situation, such as 60 square tubes, 50 square tubes, etc.
  • the vertical support rods 312 on both sides of the bottom walkway plate 311 are arranged oppositely, and a transverse tie rod 315 can be arranged between the two oppositely arranged vertical support rods 312, and the transverse tie rod The two ends of 315 are respectively connected to two vertical support rods 312.
  • a diagonal stay rod 316 may be arranged between the transverse stay rod 315 and the upper protective structure 320, and one end of the diagonal stay rod 316 is connected to the transverse stay rod 315. The other end can be connected to the upper horizontal longitudinal bar 324 of the upper protective structure 320 . Therefore, the stability of the external hanger main body 300 can be enhanced through the arrangement.
  • the vertical support rods 312 located on the inside of the bottom protection structure 310 are arranged oppositely, and a horizontal Tie rod 317.
  • the overall stability of the external hanger main bodies 300 on both sides opposite to each other can be enhanced by arranging the horizontal tie rods 317.
  • several vertical support rods 312 on the outer side may be connected to the bottom horizontal protection rod 318 , and several vertical protection rods 322 may be connected to the upper horizontal protection rod 325 .
  • the protection of the pylon can be improved.
  • protective measures can be provided outside the facade of the external hanger, and several vertical support rods 312 located on the outside are connected to the bottom protective mesh 319, and several vertical protective rods 322 are connected to the upper protective mesh 326.
  • the inner sides of the bottom walkway slab and the upper walkway slab are provided with flaps A, which are used to provide protection for workers during construction.
  • 2-5 horizontal support beams 100 can be used as a group, and the two ends of a group of horizontal support beams 100 are used to support two external hanger main bodies 300 arranged oppositely, forming a hanger together
  • two hangers can be set to connect the unit body in sequence.
  • the locking member 200 can be a U-shaped pipe clamp, as shown in Figures 5a to 5c, including a U-shaped sleeve 210, two bolts 220 and a steel pressure plate 230, the U-shaped sleeve 210
  • the two free ends are provided with internal threads that cooperate with the bolts
  • the steel plate 230 is provided with two through holes
  • the bottom of the U-shaped sleeve 210 is pre-embedded in concrete
  • the horizontal support beam 100 is placed between the two free ends of the U-shaped sleeve 210
  • the bolt 220 passes through the through hole of the steel pressing plate 230 and is threadedly connected with the free end of the U-shaped sleeve 210
  • the steel pressing plate 230 uses Fasten the horizontal support beam 100 by pressing.
  • the U-shaped sleeve 210 is welded integrally with the main girder reinforcement of the corridor to form a joint weld. After the solidified strength of the concrete of the corridor after cast-in-place is greater than 75%, install the horizontal support beam 100 between the two free ends of the U-shaped sleeve 210 and lock it with the bolt 220 and the steel plate 230 .
  • the present invention also provides a construction method for the above-mentioned high-rise building structure embodying the construction of the external hanger for pouring the aerial corridor construction, comprising the following steps:
  • the locking piece is a U-shaped pipe clip as shown in FIG. 5
  • the corridor after the pre-embedded locking piece is shown in FIG. 6 .
  • the horizontal support beams are installed, and the corridor after the installation of the horizontal support beams is shown in FIG. 7 .
  • the main body of the external hanger is fixedly connected to the end of the horizontal support beam;
  • step S3 use a tower crane to lift the main body of the external hanger layer by layer.
  • the corridor after construction is shown in Figure 4.
  • the present invention pre-embeds the locking parts in advance during the cast-in-place corridor, installs the horizontal support beam cantilevered, and installs the main body of the external hanger.
  • the construction of the cast-in-place reinforced concrete structure of the air corridor of the building structure provides a safe, reliable and convenient construction method for the external hanger.
  • connection In the description of the present invention, unless otherwise clearly specified and limited, the terms “installation”, “connection”, “connection” and “fixation” should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection , or integrated; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
  • a first feature being “on” or “under” a second feature may include direct contact between the first and second features, and may also include the first and second features Not in direct contact but through another characteristic contact between them.
  • “above”, “above” and “above” the first feature on the second feature include that the first feature is directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature.
  • “Below”, “beneath” and “under” the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.

Abstract

Disclosed in the present invention are an outer hanger for cast-in-place air corridor construction of a high-rise building structure and a construction method therefor. The outer hanger comprises: several horizontal support beams, the two ends of each horizontal support beam being horizontally suspended on the two sides of a current layer-cured cast-in-place concrete corridor, and being fixed by means of locking members pre-buried above the corridor; and several outer hanger bodies located on the two sides of the corridor, and fixedly connected to the ends of the several horizontal support beams. Each outer hanger body comprises two layers of protection structures; a bottom-layer protection structure is fixed to the horizontal support beams, and comprises a bottom-layer walkway plate and several vertical support rods located on the two sides of the bottom-layer walkway plate; an upper-layer protection structure comprises an upper-layer walkway plate and several vertical protection rods located on the outer side of the upper-layer walkway plate; the vertical support rods are used for supporting the upper-layer walkway plate; and the height of the upper walkway plate is matched with the height of a higher-layer corridor to be constructed. By using the outer hanger provided by the present invention, the construction of a cast-in-situ reinforced concrete structure of the air corridor of the high-rise building structure can be performed more safely, reliably and conveniently.

Description

高层建筑结构体现浇空中连廊施工用外挂架及其施工方法High-rise building structure embodies the external hanger and its construction method for the construction of poured aerial corridors 技术领域technical field
本发明涉及高层建筑施工技术领域,特别涉及一种高层建筑结构体现浇空中连廊施工用外挂架及其施工方法。The invention relates to the technical field of high-rise building construction, in particular to an external hanger for the construction of a high-rise building structure reflecting a poured aerial corridor and a construction method thereof.
背景技术Background technique
目前对于连廊处的外架体系多采用悬挑脚手架体系,使用工字钢六层一悬挑(悬挑钢管扣件根据有关规定不得大于25米高)。然而,高层建筑需要使用大量的钢管扣件,施工所需劳动力多、施工难度大、搭拆工期长、施工的安全风险大,需要在外墙预留大量工字钢洞,增加了外墙堵洞的工程量和外墙防水的施工难度。At present, the cantilevered scaffolding system is mostly used for the outer frame system at the corridor, using I-beam six layers and one overhang (cantilever steel pipe fasteners shall not exceed 25 meters in height according to relevant regulations). However, high-rise buildings need to use a large number of steel pipe fasteners. The construction requires a lot of labor, the construction is difficult, the construction period is long, and the safety risk of the construction is high. It is necessary to reserve a large number of I-shaped steel holes in the outer wall, which increases the number of blocked holes in the outer wall. The amount of engineering and the construction difficulty of exterior wall waterproofing.
高层建筑空中连廊多见于两座较高建筑物(主建筑物)之间,其结构则为现浇钢筋砼结构,施工时需要铺设模板浇捣混凝土,而且需要为施工搭设脚手架,但是,当空中连廊(主要是支撑其主体的梁)采用纯钢筋混凝土结构时,因其凝固前不能承受外力,施工时甚至需要将钢筋笼依赖于其它结构上以保证其准确的位置,而且需要设置支模架和脚手架;而当空中连廊地面高度较高时,搭设的支模架和脚手架容易失稳,有关规定也不允许这样做,成本较高,且拆卸难度大,存在较大的安全风险。Air corridors in high-rise buildings are mostly found between two taller buildings (main buildings), and their structures are cast-in-place reinforced concrete structures. During construction, formwork needs to be laid and concrete poured, and scaffolding needs to be erected for construction. However, when When the air corridor (mainly the beam supporting its main body) adopts a pure reinforced concrete structure, because it cannot bear external forces before solidification, it is even necessary to rely on the reinforcement cage on other structures to ensure its accurate position during construction, and it is necessary to set up support. Formwork and scaffolding; and when the ground height of the aerial corridor is high, the erected formwork and scaffolding are easy to lose stability, and relevant regulations do not allow this, the cost is high, and disassembly is difficult, and there is a greater safety risk .
发明的公开disclosure of invention
本发明的目的是提供一种高层建筑结构体现浇空中连廊施工用外挂架及其施工方法,实现安全、可靠、便捷的进行高层建筑结构体空中连廊现浇钢筋砼结构施工。The object of the present invention is to provide an external hanger for the construction of high-rise building structure reflecting the pouring corridor in the sky and its construction method, so as to realize safe, reliable and convenient construction of the cast-in-place reinforced concrete structure of the sky corridor of the high-rise building structure.
为了实现以上目的,本发明通过以下技术方案实现:In order to achieve the above object, the present invention is achieved through the following technical solutions:
一种高层建筑结构体现浇空中连廊施工用外挂架,包括:A high-rise building structure embodies an external hanger for the construction of an aerial corridor, comprising:
若干水平支撑梁,每一所述水平支撑梁的两端水平悬挑于当前层已固化 的现浇混凝土连廊的两侧,通过预埋在所述现浇混凝土连廊上方的锁紧件进行固定;A number of horizontal support beams, the two ends of each horizontal support beam cantilever horizontally on both sides of the cured cast-in-place concrete corridor on the current floor, and are fixed by locking parts pre-buried above the cast-in-place concrete corridor. fixed;
若干个位于连廊两侧的外挂架主体,每一所述外挂架主体与若干所述水平支撑梁的端部固定连接;Several external hanger bodies located on both sides of the corridor, each of which is fixedly connected to the ends of several horizontal support beams;
所述外挂架主体包括两层防护结构,其中,底层防护结构与所述水平支撑梁固定,包括底层走道板和位于所述底层走道板两侧的若干竖直支撑杆,上层防护结构包括上层走道板和位于所述上层走道板外侧的若干竖直防护杆,所述竖直支撑杆用于支撑所述上层走道板,所述上层走道板的高度与待施工的高一层连廊的高度相适应。The main body of the external hanger includes a two-layer protective structure, wherein the bottom protective structure is fixed to the horizontal support beam, including the bottom walkway slab and several vertical support rods located on both sides of the bottom walkway slab, and the upper protective structure includes the upper walkway slab and several vertical protective rods located outside the upper walkway slab, the vertical support rods are used to support the upper walkway slab, the height of the upper walkway slab is the same as the height of the upper corridor to be constructed adapt.
进一步的,所述底层防护结构还包括两个互相平行且沿所述连廊延伸方向的底层水平横杆、连接两个底层水平横杆的若干个底层水平纵杆,所述底层走道板铺设于若干个底层水平纵杆上,若干竖直支撑杆设置于两个底层水平横杆上;Further, the bottom protection structure also includes two bottom horizontal horizontal bars parallel to each other and along the extension direction of the corridor, and several bottom horizontal vertical bars connecting the two bottom horizontal bars. The bottom walkway board is laid on On several bottom horizontal longitudinal bars, several vertical support bars are arranged on two bottom horizontal cross bars;
所述上层防护结构还包括两个互相平行且沿所述连廊延伸方向的上层水平横杆、连接两个上层水平横杆的若干个上层水平纵杆,所述上层走道板铺设于若干个上层水平纵杆上,若干竖直防护杆设置于外侧的上层水平横杆上;The upper protective structure also includes two upper horizontal bars parallel to each other and along the extending direction of the corridor, several upper horizontal longitudinal bars connecting the two upper horizontal bars, and the upper layer walkway boards are laid on several upper layer On the horizontal longitudinal bar, several vertical protective bars are arranged on the outer upper level horizontal bar;
每个上层水平横杆连接所述底层走道板一侧的若干竖直支撑杆。Each upper level horizontal bar connects several vertical support bars on one side of the bottom walkway slab.
进一步的,位于外侧的若干竖直支撑杆连接有底层水平防护杆,若干竖直防护杆连接有上层水平防护杆。Further, several vertical support rods located on the outside are connected to the bottom horizontal protection rods, and several vertical protection rods are connected to the upper horizontal protection rods.
进一步的,位于外侧的若干竖直支撑杆连接底层防护网片,若干竖直防护杆连接上层防护网片。Further, several vertical support rods located on the outside are connected to the bottom protection mesh, and several vertical protection rods are connected to the upper protection mesh.
进一步的,所述底层防护结构中,所述底层走道板两侧的竖直支撑杆相对设置,相对设置的两个竖直支撑杆之间连接有横向拉杆。Further, in the bottom protection structure, the vertical support rods on both sides of the bottom walkway slab are oppositely arranged, and a transverse tie rod is connected between the two oppositely arranged vertical support rods.
进一步的,所述横向拉杆与所述上层防护结构之间连接有斜拉杆。Further, a diagonal tie rod is connected between the transverse tie rod and the upper protective structure.
进一步的,在连廊两侧的两个外挂架主体中,所述底层防护结构中位于内侧的竖直支撑杆相对设置,相对设置的两个竖直支撑杆之间连接有水平拉杆。Further, in the two hanger main bodies on both sides of the corridor, the inner vertical support rods in the bottom protection structure are arranged oppositely, and a horizontal tie rod is connected between the two oppositely arranged vertical support rods.
进一步的,所述底层走道板和所述上层走道板的内侧设有翻板。Further, the inner sides of the bottom walkway slab and the upper walkway slab are provided with flaps.
进一步的,所述锁紧件为U型管卡,包括U型套筒、两个螺栓和钢压板,所述U型套筒的两个自由端设有与所述螺栓配合的内螺纹,所述钢压板上设 有两个通孔,所述U型套筒的底部预埋在混凝土中,所述水平支撑梁置于所述U型套筒的两个自由端之间,所述螺栓穿过所述钢压板的通孔与所述U型套筒的自由端螺纹连接,所述钢压板用于压制紧固所述水平支撑梁。Further, the locking member is a U-shaped pipe clamp, including a U-shaped sleeve, two bolts and a steel pressure plate, and the two free ends of the U-shaped sleeve are provided with internal threads that cooperate with the bolts. There are two through holes on the steel pressure plate, the bottom of the U-shaped sleeve is pre-buried in concrete, the horizontal support beam is placed between the two free ends of the U-shaped sleeve, and the bolts pass through The through hole of the steel pressing plate is threadedly connected with the free end of the U-shaped sleeve, and the steel pressing plate is used for pressing and fastening the horizontal support beam.
一种如上文所述的高层建筑结构体现浇空中连廊施工用外挂架的施工方法,包括以下步骤:A kind of construction method of the external hanger used for the construction of the high-rise building structure embodied in the sky corridor as described above, comprising the following steps:
S1、在连廊的现浇混凝土中预埋锁紧件;S1. Pre-embed the locking parts in the cast-in-place concrete of the corridor;
S2、待混凝土固化到一定程度后,将若干水平支撑梁纵向放置于连廊上并使其两端水平悬挑于连廊的两侧,采用所述锁紧件对水平支撑梁进行固定;S2. After the concrete is solidified to a certain extent, place several horizontal support beams longitudinally on the corridor and make both ends of the horizontal cantilever on both sides of the corridor, and use the locking parts to fix the horizontal support beams;
S3、在连廊的两侧,将外挂架主体与水平支撑梁的端部进行固定连接;S3. On both sides of the corridor, the main body of the external hanger is fixedly connected to the end of the horizontal support beam;
在所述外挂架主体的上层走道板上对高一层连廊进行现浇施工,并重复步骤S1~S3,在步骤S3中采用塔吊逐层提升所述外挂架主体。Perform cast-in-place construction on the upper floor corridor on the upper walkway slab of the main body of the external hanger, and repeat steps S1 to S3. In step S3, use a tower crane to lift the main body of the external hanger layer by layer.
本发明至少具有以下优点之一:The present invention has at least one of the following advantages:
本发明通过在已固化的连廊上悬挑固定水平支撑梁,水平支撑梁的两端分别支撑两个外挂架主体,即在连廊的两侧安装外挂架主体,外挂架主体包括两层,其中底层防护结构的高度与当前层连廊的高度相适应,上层防护结构的上层走道板高度与待施工的上层连廊的高度相适应,故上层防护结构适用于对待施工的高一层连廊进行施工。由于水平支撑梁固定于连廊上方,不需要在外墙预留工字钢洞,降低了外墙堵洞的工程量和外墙防水的施工难度,随着连廊的逐层施工,外挂架主体也可逐层提升,整个外挂架只有两层连廊的高度,稳定性好,安全风险低。The present invention cantilever and fix the horizontal support beam on the cured corridor, and the two ends of the horizontal support beam respectively support two external hanger main bodies, that is, the external hanger main bodies are installed on both sides of the corridor, and the external hanger main body includes two layers. Among them, the height of the bottom protective structure is adapted to the height of the corridor on the current floor, and the height of the upper walkway slab of the upper protective structure is adapted to the height of the upper corridor to be constructed, so the upper protective structure is suitable for the corridor on the first floor to be constructed for construction. Since the horizontal support beam is fixed above the corridor, there is no need to reserve an I-shaped steel hole in the outer wall, which reduces the engineering volume of the outer wall blocking the hole and the construction difficulty of the outer wall waterproof. With the layer-by-layer construction of the corridor, the main body of the outer hanger It can also be lifted layer by layer. The entire external rack is only the height of the two-story corridor, which has good stability and low safety risks.
附图的简要说明Brief description of the drawings
图1为本发明一实施例提供的高层建筑结构体现浇空中连廊施工用外挂架的主视图;Fig. 1 is the front view of the external hanger for the construction of the high-rise building structure embodied in the sky corridor provided by an embodiment of the present invention;
图2为本发明一实施例提供的外挂架主体的结构示意图;Fig. 2 is a schematic structural view of the main body of the external hanger provided by an embodiment of the present invention;
图3为本发明一实施例提供的安装外挂架的示意图;Fig. 3 is a schematic diagram of installing an external pylon provided by an embodiment of the present invention;
图4为本发明一实施例提供的连廊施工时外挂架的示意图;Fig. 4 is a schematic diagram of an external hanger during corridor construction provided by an embodiment of the present invention;
图5为本发明一实施例提供的廊U型管卡的主视图;Fig. 5 is a front view of a gallery U-shaped pipe clip provided by an embodiment of the present invention;
图6为本发明一实施例提供的预埋U型管卡的示意图;Fig. 6 is a schematic diagram of a pre-embedded U-shaped pipe clamp provided by an embodiment of the present invention;
图7为本发明一实施例提供的安装水平支撑梁的示意图。Fig. 7 is a schematic diagram of installing a horizontal support beam provided by an embodiment of the present invention.
实现本发明的最佳方式BEST MODE FOR CARRYING OUT THE INVENTION
以下结合附图和具体实施方式对本发明提出的一种单叶片吊具传动装置及单叶片吊具作进一步详细说明。根据下面说明,本发明的优点和特征将更清楚。需要说明的是,附图采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本发明实施方式的目的。为了使本发明的目的、特征和优点能够更加明显易懂,请参阅附图。须知,本说明书所附图式所绘示的结构、比例、大小等,均仅用以配合说明书所揭示的内容,以供熟悉此技术的人士了解与阅读,并非用以限定本发明实施的限定条件,故不具技术上的实质意义,任何结构的修饰、比例关系的改变或大小的调整,在不影响本发明所能产生的功效及所能达成的目的下,均应仍落在本发明所揭示的技术内容能涵盖的范围内。A single-blade spreader transmission device and a single-blade spreader proposed by the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. The advantages and features of the present invention will become clearer from the following description. It should be noted that the drawings are in a very simplified form and all use imprecise scales, which are only used to facilitate and clearly assist the purpose of illustrating the embodiments of the present invention. In order to make the objects, features and advantages of the present invention more comprehensible, please refer to the accompanying drawings. It should be noted that the structures, proportions, sizes, etc. shown in the drawings attached to this specification are only used to match the content disclosed in the specification, for those who are familiar with this technology to understand and read, and are not used to limit the implementation of the present invention. condition, so it has no technical substantive meaning, and any modification of structure, change of proportional relationship or adjustment of size shall still fall within the scope of the present invention without affecting the effect and purpose of the present invention. within the scope covered by the disclosed technical content.
请参考图1~7,本发明一实施例提供的一种高层建筑结构体现浇空中连廊施工用外挂架,包括:若干水平支撑梁100,每一所述水平支撑梁100的两端水平悬挑于当前层已固化的现浇混凝土连廊的两侧,通过预埋在所述现浇混凝土连廊上方的锁紧件200进行固定;若干个位于连廊两侧的外挂架主体300,每一所述外挂架主体300与若干所述水平支撑梁100的端部固定连接。所述水平支撑梁100可以采用工字钢。Please refer to Figures 1 to 7, a high-rise building structure provided by an embodiment of the present invention embodies an external hanger for the construction of a corridor in the air, including: several horizontal support beams 100, and the two ends of each horizontal support beam 100 are horizontal Cantilevered on both sides of the cured cast-in-place concrete corridor on the current floor, fixed by the locking parts 200 pre-buried above the cast-in-place concrete corridor; several external hanger bodies 300 located on both sides of the corridor, Each of the hanger main bodies 300 is fixedly connected to ends of several horizontal support beams 100 . The horizontal support beam 100 can be made of I-beam.
具体的,所述外挂架主体300为两层防护结构,其中,底层防护结构310与所述水平支撑梁100固定,包括底层走道板311和位于所述底层走道板两侧的若干竖直支撑杆312,上层防护结构320包括上层走道板321和位于所述上层走道板321外侧的若干竖直防护杆322,所述竖直支撑杆312用于支撑所述上层走道板321,所述上层走道板321的高度与待施工的上层连廊的高度相适应。Specifically, the main body 300 of the external hanger is a two-layer protective structure, wherein the bottom protective structure 310 is fixed to the horizontal support beam 100, including the bottom walkway plate 311 and several vertical support rods located on both sides of the bottom walkway plate 312, the upper protective structure 320 includes an upper walkway slab 321 and a number of vertical protective bars 322 located outside the upper walkway slab 321, the vertical support bars 312 are used to support the upper walkway slab 321, the upper walkway slab The height of 321 adapts to the height of the upper corridor to be constructed.
本实施例提供的外挂架结构,通过在已固化的连廊上悬挑固定水平支撑梁100,水平支撑梁100的两端分别支撑两个外挂架主体300,即在连廊的两侧安装外挂架主体300,外挂架主体包括两层,其中底层防护结构310的高度与当前层连廊的高度相适应,上层防护结构320的上层走道板321高度与待施工的上层连廊的高度相适应,故上层防护结构320适用于对待施工的上层连廊进行施工。由于水平支撑梁100固定于连廊上方,不需要在外墙预留 工字钢洞,降低了外墙堵洞的工程量和外墙防水的施工难度,随着连廊的逐层施工,外挂架主体300也可逐层提升,整个外挂架只有两层连廊的高度,稳定性好,安全风险低。The external hanger structure provided in this embodiment is to hang and fix the horizontal support beam 100 on the cured corridor, and the two ends of the horizontal support beam 100 respectively support two external hanger main bodies 300, that is, the external hangers are installed on both sides of the corridor. The frame main body 300 and the external hanger main body include two layers, wherein the height of the bottom protective structure 310 is adapted to the height of the corridor on the current floor, and the height of the upper walkway plate 321 of the upper protective structure 320 is adapted to the height of the upper corridor to be constructed. Therefore, the upper protective structure 320 is suitable for construction of the upper corridor to be constructed. Since the horizontal support beam 100 is fixed above the corridor, there is no need to reserve an I-shaped steel hole in the outer wall, which reduces the engineering volume of the outer wall plugging the hole and the construction difficulty of the outer wall waterproof. With the layer-by-layer construction of the corridor, the external hanger The main body 300 can also be lifted layer by layer, and the entire external hanger is only the height of a two-story corridor, which has good stability and low safety risks.
所述外挂架主体300上可预留吊耳,吊点可设置于外挂架主体300顶部,吊点不少于2处,吊耳为定制连接钢板。吊点也可设于外挂架主体300两侧骨架上,为保持架体整体平衡,吊点不少于4点,对称均匀布置。Hanging lugs can be reserved on the main body 300 of the external hanger, and the hanging points can be set on the top of the main body 300 of the external hanger. There are no less than two hanging points, and the lifting lugs are custom-made connecting steel plates. Hanging points can also be arranged on the frameworks on both sides of the external hanger main body 300, in order to maintain the overall balance of the frame body, the hanging points should be no less than 4 points, symmetrically and evenly arranged.
本实施例中,所述底层防护结构310还包括两个互相平行且沿所述连廊延伸方向的底层水平横杆313、连接两个底层水平横杆313的若干个底层水平纵杆314,所述底层走道板311铺设于若干个底层水平纵杆314上,若干竖直支撑杆312设置于两个底层水平横杆313上;类似的,所述上层防护结构320还包括两个互相平行且沿所述连廊延伸方向的上层水平横杆323、连接两个上层水平横杆323的若干个上层水平纵杆324,所述上层走道板321铺设于若干个上层水平纵杆324上,若干竖直防护杆322设置于外侧的上层水平横杆323上;位于内侧的上层水平横杆323连接所述底层走道板311内侧的若干竖直支撑杆312,位于外侧的上层水平横杆323连接所述底层走道板311内侧的若干竖直支撑杆312,此处的内侧和外侧是相对于连廊而言的,所述底层走道板311靠近连廊的一侧为内侧,远离连廊的一侧为外侧。在实际应用中,所述底层走道板311和上层走道板321可以为花纹钢板,用于人行走时防滑,所述竖直支撑杆312、竖直防护杆322、底层水平横杆313、底层水平纵杆314、上层水平横杆323、上层水平纵杆324等杆件可以为方管,具体尺寸可以根据实际情况进行设置,例如为60方管、50方管等。In this embodiment, the bottom protection structure 310 also includes two bottom horizontal bars 313 parallel to each other and along the extension direction of the corridor, and several bottom horizontal bars 314 connecting the two bottom horizontal bars 313. The bottom walkway slab 311 is laid on several bottom horizontal longitudinal bars 314, and several vertical support bars 312 are arranged on two bottom horizontal bars 313; similarly, the upper protective structure 320 also includes two The upper horizontal bar 323 in the extension direction of the corridor, several upper horizontal longitudinal bars 324 connecting the two upper horizontal bar 323, the upper floor walkway board 321 is laid on several upper horizontal longitudinal bars 324, several vertical The protective rod 322 is arranged on the upper horizontal bar 323 on the outside; the upper horizontal bar 323 on the inner side connects several vertical support bars 312 inside the bottom walkway plate 311, and the upper horizontal bar 323 on the outer side connects the bottom layer Several vertical support rods 312 on the inner side of the corridor slab 311, the inner side and the outer side here are relative to the corridor, the side of the bottom corridor 311 close to the corridor is the inner side, and the side far away from the corridor is the outer side . In practical applications, the bottom walkway plate 311 and the upper walkway plate 321 can be patterned steel plates for anti-slip when people walk. The rods such as the longitudinal bar 314, the upper horizontal bar 323, and the upper horizontal bar 324 can be square tubes, and the specific size can be set according to the actual situation, such as 60 square tubes, 50 square tubes, etc.
进一步的,所述底层防护结构310中,所述底层走道板311两侧的竖直支撑杆312相对设置,相对设置的两个竖直支撑杆312之间可以设置横向拉杆315,所述横向拉杆315的两端分别连接两个竖直支撑杆312,此外,所述横向拉杆315与所述上层防护结构320之间可以设置斜拉杆316,所述斜拉杆316的一端连接所述横向拉杆315,另一端可以连接所述上层防护结构320的上层水平纵杆324。由此,通过设置说可加强外挂架主体300的稳定性。Further, in the bottom protection structure 310, the vertical support rods 312 on both sides of the bottom walkway plate 311 are arranged oppositely, and a transverse tie rod 315 can be arranged between the two oppositely arranged vertical support rods 312, and the transverse tie rod The two ends of 315 are respectively connected to two vertical support rods 312. In addition, a diagonal stay rod 316 may be arranged between the transverse stay rod 315 and the upper protective structure 320, and one end of the diagonal stay rod 316 is connected to the transverse stay rod 315. The other end can be connected to the upper horizontal longitudinal bar 324 of the upper protective structure 320 . Therefore, the stability of the external hanger main body 300 can be enhanced through the arrangement.
进一步的,在连廊两侧的两个外挂架主体30中,所述底层防护结构310中位于内侧的竖直支撑杆312相对设置,相对设置的两个竖直支撑杆312之间连接有水平拉杆317。由此,通过设置所述水平拉杆317可加强相对设置 的两侧外挂架主体300整体的稳定性。Further, in the two external hanger main bodies 30 on both sides of the corridor, the vertical support rods 312 located on the inside of the bottom protection structure 310 are arranged oppositely, and a horizontal Tie rod 317. Thus, the overall stability of the external hanger main bodies 300 on both sides opposite to each other can be enhanced by arranging the horizontal tie rods 317.
本实施例中,可以使位于外侧的若干竖直支撑杆312连接底层水平防护杆318,若干竖直防护杆322连接上层水平防护杆325。由此,可提高外挂架的防护性。进一步的,可在外挂架立面外设置防护措施,在位于外侧的若干竖直支撑杆312连接底层防护网片319,若干竖直防护杆322连接上层防护网片326。In this embodiment, several vertical support rods 312 on the outer side may be connected to the bottom horizontal protection rod 318 , and several vertical protection rods 322 may be connected to the upper horizontal protection rod 325 . Thus, the protection of the pylon can be improved. Further, protective measures can be provided outside the facade of the external hanger, and several vertical support rods 312 located on the outside are connected to the bottom protective mesh 319, and several vertical protective rods 322 are connected to the upper protective mesh 326.
进一步的,所述底层走道板和所述上层走道板的内侧设有翻板A,用于在施工时为工人提供防护。Further, the inner sides of the bottom walkway slab and the upper walkway slab are provided with flaps A, which are used to provide protection for workers during construction.
一般的,为便于拆卸和提升,可将2-5个水平支撑梁100作为一组,一组水平支撑梁100的两端用于支撑相对设置的两个外挂架主体300,共同组成一个挂架单元体,当连廊较长时,可设置多个挂架单元体依次连接。Generally, in order to facilitate disassembly and lifting, 2-5 horizontal support beams 100 can be used as a group, and the two ends of a group of horizontal support beams 100 are used to support two external hanger main bodies 300 arranged oppositely, forming a hanger together For the unit body, when the corridor is long, multiple hangers can be set to connect the unit body in sequence.
本实施例中,所述锁紧件200可以为U型管卡,如图5a~5c所示,包括U型套筒210、两个螺栓220和钢压板230,所述U型套筒210的两个自由端设有与所述螺栓配合的内螺纹,所述钢压板230上设有两个通孔,所述U型套筒210的底部预埋在混凝土中,所述水平支撑梁100置于所述U型套筒210的两个自由端之间,所述螺栓220穿过所述钢压板230的通孔与所述U型套筒210的自由端螺纹连接,所述钢压板230用于压制紧固所述水平支撑梁100。优选的,所述U型套筒210与连廊主梁钢筋焊接成一体且形成交合焊接。待现浇后的连廊混凝土固化强度大于75%后,将水平支撑梁100安装在U型套筒210的两个自由端之间,并采用螺栓220和钢压板230锁紧。In this embodiment, the locking member 200 can be a U-shaped pipe clamp, as shown in Figures 5a to 5c, including a U-shaped sleeve 210, two bolts 220 and a steel pressure plate 230, the U-shaped sleeve 210 The two free ends are provided with internal threads that cooperate with the bolts, the steel plate 230 is provided with two through holes, the bottom of the U-shaped sleeve 210 is pre-embedded in concrete, and the horizontal support beam 100 is placed Between the two free ends of the U-shaped sleeve 210, the bolt 220 passes through the through hole of the steel pressing plate 230 and is threadedly connected with the free end of the U-shaped sleeve 210, and the steel pressing plate 230 uses Fasten the horizontal support beam 100 by pressing. Preferably, the U-shaped sleeve 210 is welded integrally with the main girder reinforcement of the corridor to form a joint weld. After the solidified strength of the concrete of the corridor after cast-in-place is greater than 75%, install the horizontal support beam 100 between the two free ends of the U-shaped sleeve 210 and lock it with the bolt 220 and the steel plate 230 .
本发明还提供了上述高层建筑结构体现浇空中连廊施工用外挂架的施工方法,包括以下步骤:The present invention also provides a construction method for the above-mentioned high-rise building structure embodying the construction of the external hanger for pouring the aerial corridor construction, comprising the following steps:
S1、在连廊的现浇混凝土中预埋锁紧件;S1. Pre-embed the locking parts in the cast-in-place concrete of the corridor;
优选的,锁紧件为如图5所示的U型管卡,预埋锁紧件后的连廊如图6所示。Preferably, the locking piece is a U-shaped pipe clip as shown in FIG. 5 , and the corridor after the pre-embedded locking piece is shown in FIG. 6 .
S2、待混凝土固化到一定程度后,将若干水平支撑梁纵向放置于连廊上并使其两端水平悬挑于连廊的两侧,采用所述锁紧件对水平支撑梁进行固定;S2. After the concrete is solidified to a certain extent, place several horizontal support beams longitudinally on the corridor and make both ends of the horizontal cantilever on both sides of the corridor, and use the locking parts to fix the horizontal support beams;
优选的,待混凝土固化强度大于75%后,安装水平支撑梁,安装水平支撑梁后的连廊如图7所示。Preferably, after the curing strength of the concrete is greater than 75%, the horizontal support beams are installed, and the corridor after the installation of the horizontal support beams is shown in FIG. 7 .
S3、在连廊的两侧,将外挂架主体与水平支撑梁的端部进行固定连接;S3. On both sides of the corridor, the main body of the external hanger is fixedly connected to the end of the horizontal support beam;
安装外挂架主体后的连廊如图3所示。The corridor after installing the main body of the external hanger is shown in Figure 3.
在所述外挂架主体的上层走道板上对高一层连廊进行现浇施工,并重复步骤S1~S3,在步骤S3中采用塔吊逐层提升所述外挂架主体。施工后的连廊如图4所示。Perform cast-in-place construction on the upper floor corridor on the upper walkway slab of the main body of the external hanger, and repeat steps S1 to S3. In step S3, use a tower crane to lift the main body of the external hanger layer by layer. The corridor after construction is shown in Figure 4.
综上所述,本发明通过在现浇连廊时提前预埋锁紧件,悬挑安装水平支撑梁,并安装外挂架主体,在多层连廊施工过程中层层提升外挂架主体,为高层建筑结构体空中连廊现浇钢筋砼结构施工提供了一种安全、可靠、便捷的外挂架施工方法。In summary, the present invention pre-embeds the locking parts in advance during the cast-in-place corridor, installs the horizontal support beam cantilevered, and installs the main body of the external hanger. The construction of the cast-in-place reinforced concrete structure of the air corridor of the building structure provides a safe, reliable and convenient construction method for the external hanger.
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is a relationship between these entities or operations. There is no such actual relationship or order between them. Furthermore, the term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus comprising a set of elements includes not only those elements, but also includes elements not expressly listed. other elements of or also include elements inherent in such a process, method, article, or device. Without further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article or apparatus comprising said element.
在本发明的描述中,需要理解的是,术语“中心”、“高度”、“厚度”、“上”、“下”、“竖直”、“水平”、“顶”、“底”、“内”、“外”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。In describing the present invention, it is to be understood that the terms "center", "height", "thickness", "upper", "lower", "vertical", "horizontal", "top", "bottom", The orientations or positional relationships indicated by "inner", "outer", "axial", "radial", and "circumferential" are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying Describes, but does not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and operate in a specific orientation, and therefore should not be construed as limiting the invention. In the description of the present invention, unless otherwise specified, "plurality" means two or more.
在本发明的描述中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, unless otherwise clearly specified and limited, the terms "installation", "connection", "connection" and "fixation" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection , or integrated; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
在本发明中,除非另有明确的规定和限定,第一特征在第二特征之“上”或之“下”可以包括第一和第二特征直接接触,也可以包括第一和第二特征不是直接接触而是通过它们之间的另外的特征接触。而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。In the present invention, unless otherwise clearly specified and limited, a first feature being "on" or "under" a second feature may include direct contact between the first and second features, and may also include the first and second features Not in direct contact but through another characteristic contact between them. Moreover, "above", "above" and "above" the first feature on the second feature include that the first feature is directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature. "Below", "beneath" and "under" the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.
尽管本发明的内容已经通过上述优选实施例作了详细介绍,但应当认识到上述的描述不应被认为是对本发明的限制。在本领域技术人员阅读了上述内容后,对于本发明的多种修改和替代都将是显而易见的。因此,本发明的保护范围应由所附的权利要求来限定。Although the content of the present invention has been described in detail through the above preferred embodiments, it should be understood that the above description should not be considered as limiting the present invention. Various modifications and alterations to the present invention will become apparent to those skilled in the art upon reading the above disclosure. Therefore, the protection scope of the present invention should be defined by the appended claims.

Claims (10)

  1. 一种高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,包括:A high-rise building structure embodies an external hanger for the construction of an aerial corridor, which is characterized in that it includes:
    若干水平支撑梁,每一所述水平支撑梁的两端水平悬挑于当前层已固化的现浇混凝土连廊的两侧,通过预埋在所述现浇混凝土连廊上方的锁紧件进行固定;A number of horizontal support beams, the two ends of each horizontal support beam cantilever horizontally on both sides of the cured cast-in-place concrete corridor on the current floor, and are fixed by locking parts pre-buried above the cast-in-place concrete corridor. fixed;
    若干个位于连廊两侧的外挂架主体,每一所述外挂架主体与若干所述水平支撑梁的端部固定连接;Several external hanger bodies located on both sides of the corridor, each of which is fixedly connected to the ends of several horizontal support beams;
    所述外挂架主体包括两层防护结构,其中,底层防护结构与所述水平支撑梁固定,包括底层走道板和位于所述底层走道板两侧的若干竖直支撑杆,上层防护结构包括上层走道板和位于所述上层走道板外侧的若干竖直防护杆,所述竖直支撑杆用于支撑所述上层走道板,所述上层走道板的高度与待施工的高一层连廊的高度相适应。The main body of the external hanger includes a two-layer protective structure, wherein the bottom protective structure is fixed to the horizontal support beam, including the bottom walkway slab and several vertical support rods located on both sides of the bottom walkway slab, and the upper protective structure includes the upper walkway slab and several vertical protective rods located outside the upper walkway slab, the vertical support rods are used to support the upper walkway slab, the height of the upper walkway slab is the same as the height of the upper corridor to be constructed adapt.
  2. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,所述底层防护结构还包括两个互相平行且沿所述连廊延伸方向的底层水平横杆、连接两个底层水平横杆的若干个底层水平纵杆,所述底层走道板铺设于若干个底层水平纵杆上,若干竖直支撑杆设置于两个底层水平横杆上;The high-rise building structure as claimed in claim 1 is characterized in that, the bottom protective structure also includes two bottom horizontal bars parallel to each other and along the extension direction of the corridor, Several bottom horizontal longitudinal bars connecting the two bottom horizontal bars, the bottom walkway plate is laid on several bottom horizontal longitudinal bars, and several vertical support bars are arranged on the two bottom horizontal bars;
    所述上层防护结构还包括两个互相平行且沿所述连廊延伸方向的上层水平横杆、连接两个上层水平横杆的若干个上层水平纵杆,所述上层走道板铺设于若干个上层水平纵杆上,若干竖直防护杆设置于外侧的上层水平横杆上;The upper protective structure also includes two upper horizontal bars parallel to each other and along the extending direction of the corridor, several upper horizontal longitudinal bars connecting the two upper horizontal bars, and the upper layer walkway boards are laid on several upper layer On the horizontal longitudinal bar, several vertical protective bars are arranged on the outer upper level horizontal bar;
    每个上层水平横杆连接所述底层走道板一侧的若干竖直支撑杆。Each upper level horizontal bar connects several vertical support bars on one side of the bottom walkway slab.
  3. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,位于外侧的若干竖直支撑杆连接有底层水平防护杆,若干竖直防护杆连接有上层水平防护杆。The high-rise building structure as claimed in claim 1 is characterized in that the external hangers for the construction of pouring corridors in the sky are characterized in that, some vertical support rods located on the outside are connected with bottom level protection rods, and some vertical protection rods are connected with upper level protection rods. pole.
  4. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,位于外侧的若干竖直支撑杆连接底层防护网片,若干竖直防护杆连接上层防护网片。The high-rise building structure according to claim 1 is characterized in that a plurality of vertical support rods located on the outside are connected to the bottom protection mesh, and a plurality of vertical protection rods are connected to the upper protection mesh.
  5. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其 特征在于,所述底层防护结构中,所述底层走道板两侧的竖直支撑杆相对设置,相对设置的两个竖直支撑杆之间连接有横向拉杆。The high-rise building structure according to claim 1 is characterized in that, in the bottom protection structure, the vertical support rods on both sides of the bottom walkway plate are relatively arranged, and the oppositely arranged A transverse tie rod is connected between the two vertical support rods.
  6. 如权利要求5所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,所述横向拉杆与所述上层防护结构之间连接有斜拉杆。The high-rise building structure according to claim 5 is characterized in that a diagonal tie rod is connected between the horizontal tie rod and the upper protective structure.
  7. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,在连廊两侧的两个外挂架主体中,所述底层防护结构中位于内侧的竖直支撑杆相对设置,相对设置的两个竖直支撑杆之间连接有水平拉杆。The high-rise building structure as claimed in claim 1 embodying the external hanger for pouring the construction of the corridor in the air, characterized in that, in the two external hanger main bodies on both sides of the corridor, the vertical support located on the inner side of the bottom protection structure The rods are arranged oppositely, and a horizontal tie rod is connected between the two vertical support rods arranged oppositely.
  8. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,所述底层走道板和所述上层走道板的内侧设有翻板。The high-rise building structure according to claim 1 is characterized in that, the inside of the bottom walkway slab and the upper walkway slab are provided with flaps.
  9. 如权利要求1所述的高层建筑结构体现浇空中连廊施工用外挂架,其特征在于,所述锁紧件为U型管卡,包括U型套筒、两个螺栓和钢压板,所述U型套筒的两个自由端设有与所述螺栓配合的内螺纹,所述钢压板上设有两个通孔,所述U型套筒的底部预埋在混凝土中,所述水平支撑梁置于所述U型套筒的两个自由端之间,所述螺栓穿过所述钢压板的通孔与所述U型套筒的自由端螺纹连接,所述钢压板用于压制紧固所述水平支撑梁。The high-rise building structure as claimed in claim 1 is characterized in that the external hanger for pouring aerial corridor construction is characterized in that the locking member is a U-shaped pipe clamp, including a U-shaped sleeve, two bolts and a steel plate. The two free ends of the U-shaped sleeve are provided with internal threads that cooperate with the bolts, and the steel pressure plate is provided with two through holes. The bottom of the U-shaped sleeve is pre-embedded in concrete, and the horizontal The support beam is placed between the two free ends of the U-shaped sleeve, and the bolts pass through the through holes of the steel platen and are screwed to the free ends of the U-shaped sleeve, and the steel platen is used for pressing Fasten the horizontal support beams.
  10. 一种如权利要求1-9任一项所述的高层建筑结构体现浇空中连廊施工用外挂架的施工方法,其特征在于,包括以下步骤:A construction method for an external hanger for the construction of a high-rise building structure embodied in a poured aerial corridor as claimed in any one of claims 1-9, characterized in that it comprises the following steps:
    S1、在连廊的现浇混凝土中预埋锁紧件;S1. Pre-embed the locking parts in the cast-in-place concrete of the corridor;
    S2、待混凝土固化到一定程度后,将若干水平支撑梁纵向放置于连廊上并使其两端水平悬挑于连廊的两侧,采用所述锁紧件对水平支撑梁进行固定;S2. After the concrete is solidified to a certain extent, place several horizontal support beams longitudinally on the corridor and make both ends of the horizontal cantilever on both sides of the corridor, and use the locking parts to fix the horizontal support beams;
    S3、在连廊的两侧,将外挂架主体与水平支撑梁的端部进行固定连接;S3. On both sides of the corridor, the main body of the external hanger is fixedly connected to the end of the horizontal support beam;
    在所述外挂架主体的上层走道板上对高一层连廊进行现浇施工,并重复步骤S1~S3,在步骤S3中采用塔吊逐层提升所述外挂架主体。Perform cast-in-place construction on the upper floor corridor on the upper walkway slab of the main body of the external hanger, and repeat steps S1 to S3. In step S3, use a tower crane to lift the main body of the external hanger layer by layer.
PCT/CN2021/115589 2021-08-31 2021-08-31 Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor WO2023028818A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
PCT/CN2021/115589 WO2023028818A1 (en) 2021-08-31 2021-08-31 Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor
DE212021000476.8U DE212021000476U1 (en) 2021-08-31 2021-08-31 External suspension frame for building an in-situ cast air corridor of a high-rise structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2021/115589 WO2023028818A1 (en) 2021-08-31 2021-08-31 Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor

Publications (1)

Publication Number Publication Date
WO2023028818A1 true WO2023028818A1 (en) 2023-03-09

Family

ID=85410677

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/115589 WO2023028818A1 (en) 2021-08-31 2021-08-31 Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor

Country Status (2)

Country Link
DE (1) DE212021000476U1 (en)
WO (1) WO2023028818A1 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU1871002A (en) * 2001-02-28 2002-08-29 Statewide Roofing Guttering/fascia installation platform
US7735606B1 (en) * 2006-08-14 2010-06-15 Norton William L Scaffold support platform
CN207348430U (en) * 2017-09-24 2018-05-11 中铁四局集团建筑工程有限公司 High-building intelligent elevating safety operating platform
CN211473320U (en) * 2019-08-31 2020-09-11 上海二十冶建设有限公司 Tool type external hanging rack for corridor
CN211899567U (en) * 2020-04-01 2020-11-10 河南五建建设集团有限公司 Novel assembled building corridor external hanging rack
CN113638587A (en) * 2021-08-06 2021-11-12 安徽居升建筑科技有限公司 Outer hanging protective scaffold suitable for cast-in-place vestibule construction of assembled
CN216196475U (en) * 2021-08-06 2022-04-05 安徽居升建筑科技有限公司 Outer hanging protective scaffold suitable for cast-in-place vestibule construction of assembled

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU1871002A (en) * 2001-02-28 2002-08-29 Statewide Roofing Guttering/fascia installation platform
US7735606B1 (en) * 2006-08-14 2010-06-15 Norton William L Scaffold support platform
CN207348430U (en) * 2017-09-24 2018-05-11 中铁四局集团建筑工程有限公司 High-building intelligent elevating safety operating platform
CN211473320U (en) * 2019-08-31 2020-09-11 上海二十冶建设有限公司 Tool type external hanging rack for corridor
CN211899567U (en) * 2020-04-01 2020-11-10 河南五建建设集团有限公司 Novel assembled building corridor external hanging rack
CN113638587A (en) * 2021-08-06 2021-11-12 安徽居升建筑科技有限公司 Outer hanging protective scaffold suitable for cast-in-place vestibule construction of assembled
CN216196475U (en) * 2021-08-06 2022-04-05 安徽居升建筑科技有限公司 Outer hanging protective scaffold suitable for cast-in-place vestibule construction of assembled

Also Published As

Publication number Publication date
DE212021000476U1 (en) 2023-08-09

Similar Documents

Publication Publication Date Title
CN101435276B (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
CN103635643B (en) The construction method of nigh-level synthesis steel bar concrete cylindrical shell
WO2016129826A1 (en) Safety-enhanced pc truss wall structure, and underground-structure construction method using same
WO2023240812A1 (en) Overall construction platform structure and method for adding core tube wall body in air
CN103147582A (en) Overhead cantilever formwork construction method
CN101503908B (en) Construction method for spacing suspension cable structural template support platform
CN113513160A (en) Construction method of basement high and large formwork support system
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
WO2023028818A1 (en) Outer hanger for cast-in-place air corridor construction of high-rise building structure and construction method therefor
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN104831928B (en) High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method
CN203547125U (en) Column type overall steel platform hydraulic creeping formwork
CN109989590A (en) For the auxiliary fixing device of roof overlength steel girder erection and the hanging method of girder steel
CN210976550U (en) Adjustable fastening tool type externally-hung protection frame system
CN212743447U (en) Reinforced structure that building structure is firm anti collapsing
CN210369895U (en) Indoor super-high and large template Bailey beam supporting system for building
CN111593874A (en) Supporting system for overweight overhung suspended member of super high-rise residential conversion layer and construction method
CN111764623A (en) Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method
CN217379735U (en) Wall connecting device suitable for large-span high frame
CN219887503U (en) Construction device for cantilever floor slab of high-rise roof
CN216276830U (en) Super high-rise core tube formwork lowering construction device
CN216865908U (en) Staircase operation protection platform
CN213204915U (en) Overweight overhanging suspended component supporting system of super high-rise residential conversion layer
CN216339062U (en) Auxiliary assembly for mounting bridge diaphragm beam template
CN219100689U (en) Attachment structure suitable for super high floor attached lifting scaffold

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21955389

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 212021000476

Country of ref document: DE