WO2023027137A1 - 電力制御装置、電力制御システムおよび電力制御方法 - Google Patents

電力制御装置、電力制御システムおよび電力制御方法 Download PDF

Info

Publication number
WO2023027137A1
WO2023027137A1 PCT/JP2022/031975 JP2022031975W WO2023027137A1 WO 2023027137 A1 WO2023027137 A1 WO 2023027137A1 JP 2022031975 W JP2022031975 W JP 2022031975W WO 2023027137 A1 WO2023027137 A1 WO 2023027137A1
Authority
WO
WIPO (PCT)
Prior art keywords
power
self
unit
network
load
Prior art date
Application number
PCT/JP2022/031975
Other languages
English (en)
French (fr)
Inventor
正俊 熊谷
浩人 佐々木
俊祐 松永
洋二 池田
Original Assignee
株式会社日立産機システム
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立産機システム filed Critical 株式会社日立産機システム
Publication of WO2023027137A1 publication Critical patent/WO2023027137A1/ja

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers

Definitions

  • the present invention relates to a power control device, a power control system, and a power control method for a power network that includes a power conversion circuit that converts a plurality of DC power sources into AC power.
  • GFL grid-forming inverter
  • GFI Grid-Forming Inverter
  • the GFL operates as a current source that follows the voltage waveform of the power system at the interconnection point, and controls the current based on the output set values of active power and reactive power.
  • the current is controlled to maximize the active power based on the voltage-current characteristic curve of the solar cell.
  • GFI operates as a voltage source that controls the frequency and amplitude of the voltage.
  • the voltage phase of the GFI lags behind that of the AC power system, thereby reducing the active power output.
  • the reactive power output decreases when the GFI lowers the amplitude of the voltage waveform relative to the voltage at the tie point.
  • the voltage frequency is lowered in proportion to the magnitude of the active power output by the GFI, and the voltage amplitude is lowered in proportion to the magnitude of the reactive power.
  • This method of sharing output by voltage frequency difference or voltage amplitude difference between power sources is called droop control.
  • As the number of synchronous generators is expected to decrease, it is expected to be a means to improve the stability of the power system.
  • droop control In droop control, the relationship between active power and frequency and the relationship between reactive power and amplitude are called droop characteristics.
  • the control characteristics change depending on For setting the droop characteristic, a method of changing the output sharing by correcting the gain (for example, Patent Document 1) and a method of changing the output sharing by correcting the offset (for example, Patent Document 2) are disclosed.
  • the present invention provides a power control device that avoids overloading the entire power network and does not increase the risk even if a partial failure or overload of the power network including a plurality of DC power sources occurs.
  • a control system and power control method are provided.
  • a DC power supply a power conversion unit that converts the output of the DC power supply to AC, and power from the power conversion unit to each load
  • a switching unit that cuts off supply a voltage measurement unit that measures the voltage value output from the power conversion unit, and a current measurement unit that measures the current value output from the power conversion unit on the same power system
  • a power control device that executes power control of an independent power network provided at each of the self-end receiving point and the other-end receiving point of the the overload determination result, the number of times the switching unit has been interrupted at the other end power receiving point detected from the amount of change in the voltage value or the current value, and information on the order of interrupting the switching unit that has been stored in advance.
  • a load shedding control unit that determines whether to shut off the opening/closing unit at the self-end power receiving point based on the load shedding control unit.
  • overload determination based on droop characteristics when converting from direct current to alternating current, and load shedding based on sudden change detection of voltage waveform or current waveform. Even if a partial failure or overload of the power grid occurs, the overload of the entire power grid is avoided and the risk is not increased by the determination and the predetermined order of interruption.
  • FIG. 1 is a configuration diagram of a power control system 100 configured from a plurality of power networks in this embodiment;
  • FIG. It is a functional block diagram in the power network A in this embodiment.
  • 2 is a hardware configuration diagram of a power control device according to the embodiment;
  • FIG. 4 is a characteristic diagram for explaining a droop control method by a droop control unit 112 and an overload determination method of an own end and the other end by an overload determination unit 115;
  • FIG. FIG. 4 is a characteristic diagram for explaining a first example of a load shedding detection method by the other-end shedding detection unit 118;
  • FIG. 9 is a characteristic diagram for explaining a second example of a load shedding detection method by the other-end shedding detection unit 118; 6 is a flowchart for explaining a load shedding determination method by a load shedding control unit 116; 3 is a diagram showing a blocking order table 204 stored in a blocking order storage unit 117; FIG. 4 is a flowchart showing a procedure for creating the shutdown order table 204 executed by the power management server 202; 4 is a diagram showing changes in voltage frequency when load shedding is executed in the power control system 100.
  • FIG. 1 shows a configuration diagram of a power control system 100 configured from a plurality of power networks in this embodiment.
  • a power system 101 is provided with a plurality of power receiving points 106a, 106b, and 106c, and each power receiving point is provided with power networks A, B, and C, respectively.
  • DC power supplied from DC power sources 102a, 102b, 102c is converted into AC power by power converters 104a, 104b, 104c, and loads 103a, 103b, 103c are supplied via switches 105a, 105b, 105c.
  • 1 shows the circuit configuration supplied to the .
  • These power systems 101 are connected by power lines indicated by thick lines in FIG.
  • DC power sources 102a, 102b, and 102c are, for example, solar power generation, storage batteries, EV chargers, and the like. Although it is used as a power supply, there is an operation state in which active power is consumed in the charging state of a storage battery or EV.
  • the power converters 104a, 104b, and 104c have a function of converting direct current to alternating current, and increase or decrease active power based on the frequency command value, as described later.
  • an electric circuit called an inverter including a coil, a capacitor, etc. is used, but it is not limited in this embodiment.
  • the power controllers 109a, 109b, 109c can communicate with the respective power converters 104a, 104b, 104c and the switches 105a, 105b, 105c, and perform power conversion for the respective power converters 104a, 104b, 104c.
  • the power supply to each load is cut off by transmitting the frequency of the hour as a command value and opening the respective switches 105a, 105b, and 105c based on the load cutoff determination described later.
  • the grid switch 201 is means for switching connections between the power grids A, B, and C shown in FIG. 1 and other power grids.
  • the power grid 101 shown in FIG. It becomes a micro grid), and it becomes necessary to match the supply and demand balance within it. Also, by receiving the closing signal, it supplies power to or receives power from the external power network.
  • the circuit operation in an independent power network will be mainly described with the system switch 201 in an open state.
  • the power management server 202 collects the power consumption measurement values of the loads 103a, 103b, and 103c by appropriate means such as the network 203 and operation input means (not shown), updates the power consumption information in the interruption order table described later,
  • the blocking order table is updated and managed as needed.
  • a facility manager may be able to edit information in a cutoff order table, which will be described later, using a user interface.
  • FIG. 2A is a functional block diagram within power network A in this embodiment.
  • the component within the power network A is expressed as "own end", and the component connected to other than the power network A is expressed as "other end”.
  • the other end corresponds to components in the two power grids B and C, but may be configured to form more power grids.
  • FIG. 2A a power receiving point 106a is provided as in FIG. Fig. 3 shows a detailed block diagram to supply;
  • a voltage measuring instrument 107a and a current measuring instrument 108a are provided in the middle of the power line connecting the DC power supply 102a to the power receiving point 106a via the power conversion device 104a, and the voltage effective value and current effective value of the output converted to alternating current are measured. Measure each.
  • the inside of the dotted line indicates the functional block of the power control device 109a.
  • the power control device 109a includes an output calculation unit 110, a control characteristic setting unit 111, a droop control unit 112, a second end characteristic storage unit 113, a second end output estimation unit 114, an overload It includes functional blocks of a determination unit 115 , a load shedding control unit 116 , a shedding order storage unit 117 , a second-end shedding detection unit 118 , and a load shedding counting unit 119 .
  • the function and operation of each functional block provided in the power control device 109a will be sequentially described below, but the power control devices 109b and 109c at the other end can also perform similar functions and operations.
  • the output calculation unit 110 calculates the self-end active power W1 of the AC power output from the power conversion device 104a from the measured values of the voltage measuring device 107a and the current measuring device 108a. Specifically, the active power is calculated by multiplying the measured voltage effective value and current effective value. The calculated self-end active power W1 is transmitted to overload determination section 115 .
  • the control characteristic setting unit 111 stores the self-end droop characteristic 301 and performs droop control operation.
  • the droop characteristic is described by the gain (the slope of the linear function) and the offset (the intercept of the linear function) as an active power-frequency relational expression, and details of the droop characteristic will be described later with reference to FIG.
  • the self-end droop characteristic in the control characteristic setting unit 111 may be provided with a self-diagnostic mode, and may be obtained and created offline when the power control device 109a is shipped from the factory or during maintenance.
  • the droop control unit 112 obtains the voltage frequency from the self-end active power W1 calculated by the output calculation unit 110 and the self-end droop characteristic 301 stored in the control characteristic setting unit 111, and outputs the frequency command value F to send. At the same time, the specified frequency value F is also sent to the other end output estimation unit 114 .
  • the droop control method executed by the droop control unit 112 will be described later in detail with reference to FIG.
  • the other end characteristic storage unit 113 stores the other end droop characteristics 302 of the power converters 104b and 104c installed in the other power networks B and C, respectively.
  • the other end droop characteristic 302 is represented by one characteristic, but is created and stored by the number of power converters installed in other power networks.
  • control characteristic setting unit 111 stores the own end droop characteristic 301
  • the other end characteristic storage unit 113 stores the droop characteristic 302 of the other end.
  • These self-end droop characteristics 301 and other-end droop characteristics 302 are obtained when the power control device 109a communicates with the power management server 202 via the network 203 at specific timings, such as when each power network is installed or restarted, or controls the power. It may be obtained through communication with the devices 109b and 109c, or may be input and set via a user interface on the power control device 109a. Also, it may be possible to read and write to a portable storage medium such as a flash memory.
  • the other end output estimation unit 114 estimates the other end active power W2 based on the frequency command value F transmitted from the droop control unit 112 and the other end droop characteristic 302 transmitted from the other end characteristic storage unit 113 .
  • a method of estimating the other-end active power W2 by the other-end output estimator 114 will be described later with reference to FIG. 3 together with the droop control method.
  • the overload determination unit 115 Based on the self-end active power W1 calculated by the output calculation unit 110 and the other-end active power W2 estimated by the other-end output estimation unit 114, the overload determination unit 115 performs power conversion on each of the self-end and the other end. Determine device overload conditions. If it is determined that the self-end is overloaded, the self-end overload determination signal S1 is transmitted to the load shedding control unit 116, and if the other end is determined to be overloaded, the other-end overload determination signal S2 is used for load shedding control. 116.
  • the overload determination method by the overload determination unit 115 will be described later with reference to FIG. 3 together with the droop control method.
  • the other-end cutoff detection unit 118 stores in advance a threshold indicating a sudden change in the measured value of the voltage measuring device 107a or the current measuring device 108a that deviates from the steady state, and compares the measured value with the threshold to Detects load shedding of switch 105b or 105c in the end power network.
  • the other end disconnection detection signal T is transmitted to the load disconnection counting unit 119 .
  • a method for detecting the blocking of the other end by the blocking detection unit 118 will be described later with reference to FIGS.
  • the load shedding counting unit 119 receives the other-end shedding detection signal T transmitted from the other-end shedding detection unit 118, counts and stores the number of shedding times S3.
  • the overload determination unit 115 determines that the self end or the other end is overloaded, the counted number of times S3 of cutoff is transmitted to the load cutoff control unit 116 .
  • the load shedding control unit 116 acquires the self-end overload determination signal S1 and the other-end overload determination signal S2 transmitted from the overload determination unit 115, the number of times of shedding S3 transmitted from the load shedding counting unit 119, and externally. Based on the cutoff order table 204, it is determined whether or not the load can be cut off. As a result of judging whether or not to cut off, when it is determined that the cut is to be executed, an open signal is transmitted to the switch 105a to cut off the power supply to the load. A load shedding determination method by the load shedding control unit 116 will be described later with reference to FIG.
  • the cutoff order storage unit 117 has a function of storing the cutoff order table 204 of the loads in each power network connected to the power system 101.
  • the power management server 202 on the network or another power control device 109b. , 109c, the cutoff order table 204 is acquired at a specific timing such as when each power network is installed or restarted, and then stored.
  • the information in the cutoff order table 204 may be stored and set by inputting the information in the cutoff order table 204 through a user interface. Also, it may be possible to read and write to a portable storage medium such as a flash memory.
  • FIG. 2B is a hardware configuration diagram of the power control device in this embodiment.
  • the power control device 109a includes a CPU (Central Processing Unit) 501, a memory 502 for temporarily storing data necessary for the CPU 501 to execute processing, a hard disk having a capacity to store a large amount of data, and a portable storage.
  • a storage unit 503 such as a medium, a communication unit 504 for communicating with other devices, an input/output device 505 such as a keyboard and a display for inputting/outputting data, and a communication bus 506 connecting these devices. It is a computer with a CPU (Central Processing Unit) 501, a memory 502 for temporarily storing data necessary for the CPU 501 to execute processing, a hard disk having a capacity to store a large amount of data, and a portable storage.
  • a storage unit 503 such as a medium
  • a communication unit 504 for communicating with other devices
  • an input/output device 505 such as a keyboard and a display for inputting/outputting
  • the CPU 501 reads from the storage unit 503 the power control program 109p including each functional block shown in FIG.
  • the functional block shown in FIG. 2A is virtually constructed, and the droop control method, overload determination method, and load shedding determination method described later are executed. do.
  • FIG. 3 is a characteristic diagram for explaining the droop control method by droop control section 112 and the overload determination method of the own end and the other end by overload determination section 115 .
  • the horizontal axis represents active power (in units of pu values), and the vertical axis represents the frequency of the output voltage (in units of pu values).
  • the pu value indicates a relative value with respect to the rated value of the power conversion device, and if it exceeds 1.0, it indicates that the output is outside the rating, indicating that the power conversion device is in an overloaded state.
  • a solid line 301 is the droop characteristic of the own end stored in the control characteristic setting section 111 .
  • the self-end droop characteristic 301 has an offset (operating point 303 in FIG. 3) that becomes the upper limit frequency ⁇ _u when the active power is 0, and a gain (slope of a straight line) including operating points 304 and 306.
  • a dotted line 302 is the droop characteristic of the power electronics device 109 b and the power electronics device 109 c stored in the other end characteristics storage unit 113 .
  • the other end droop characteristic 302 has an offset (operating point 303 in FIG. 3) that becomes the upper limit frequency ⁇ _u when the active power is 0, and a gain (slope of a straight line) including operating points 305 and 307. .
  • the overload determination method will be specifically described with reference to Operation Example 1 and Operation Example 2.
  • the output calculation unit 110 calculates the active power from the measured voltage value and the current value and the self-end active power is calculated as 0.5
  • the droop control unit 112 sets the active power value to 0.5. Send to
  • Droop control unit 112 that has received active power value 0.5 determines voltage frequency ⁇ _l from operating point 304 on self-end droop characteristic 301 in FIG. 0.5 is transmitted to the overload judgment unit 115 as the active power W1 of the own end.
  • the other-end output estimating unit 114 determines that the self-end and the other end are tuned to the voltage frequency ⁇ _l from the transmitted voltage frequency ⁇ _l and the other-end droop characteristic 302 stored in the other-end characteristic storage unit 113, and Based on the operating point 305 on the droop characteristic 302 , the other end active power W ⁇ b>2 is estimated to be 1.0 and transmitted to the overload determination section 115 .
  • the overload determination unit 115 receives signals of 0.5 of the self-end active power W1 and 1.0 of the other-end active power W2, and determines both the self-end overload determination signal S1 and the other-end overload determination signal S2 as No. (not overloaded), and transmits both overload determination signals to the load shedding control unit 116 .
  • the self-end active power 0.75 is drooped. It is transmitted to the control unit 112 .
  • the droop control unit 112 that has received the self-end active power of 0.75 determines the voltage frequency ⁇ _m from the operating point 306 on the self-end droop characteristic 301 of FIG. Along with transmitting it as the command value F, 0.75 is transmitted to the overload determination unit 115 as the self-end active power W1.
  • the other-end output estimator 114 determines that the self-end and the other end are tuned to the voltage frequency ⁇ _m based on the transmitted voltage frequency ⁇ _m and the other-end droop characteristic 302 stored in the other-end characteristic storage unit 113 . Based on the operating point 307 on the droop characteristic 302 , the other end active power W ⁇ b>2 is estimated to be 1.5 and transmitted to the overload determination section 115 .
  • the overload determination unit 115 receives signals of 0.75 of the self-end active power W1 and 1.5 of the other-end active power W2, and sets the self-end overload determination signal S1 to No (not overloaded).
  • Overload determination signal S2 is determined to be Yes (overload), and both overload determination signals are transmitted to load shedding control section 116 .
  • the own end droop control and the own end and the other end overload determination are executed.
  • the power conversion device 104a to which the frequency command value F is transmitted drives the output frequency based on the frequency command value F when converting from direct current to alternating current.
  • driving as shown in FIG. 1, in a plurality of power networks connected to the same power system 101, when a difference occurs in voltage frequency, power is supplied from a high-frequency power conversion device and a low-frequency power conversion device is used. A phenomenon occurs in which power is received by the device, and finally the frequency is tuned to drive stably. For example, when tuning at frequency ⁇ _l, self-sustaining control is performed so that the active power of the own end and the other end operates at a sharing ratio of 0.5:1.0.
  • FIG. 4 is a characteristic diagram for explaining a first example of the load shedding detection method by the other-end shedding detection unit 118.
  • FIG. The horizontal axis indicates the elapsed time, and the vertical axis indicates the voltage effective value measured by the voltage measuring device 107a.
  • Fig. 4 shows the voltage change when load rejection occurs at the other end at time t_s on the horizontal axis.
  • the switch 105b or 105c at the other end is cut off, the current sharply decreases by the amount of the cut off load, and a sharp voltage change 401 is measured by the inductance of the power line in the power system 101.
  • FIG. Since such a voltage change reaches several times to several tens of times the voltage in the steady state, for example, the amount of voltage change that deviates from the steady state is stored as a threshold value, and is obtained from the voltage measurement value by the voltage measuring device 107a.
  • the stored voltage change amount is compared with the stored threshold value, and if the voltage change amount exceeds the threshold value, the other end cutoff detection unit 118 determines that the load of the other end is cut off, and outputs the other end cutoff detection signal T to the load. It is transmitted to the interruption counting unit 119 .
  • FIG. 5 is a characteristic diagram for explaining a second example of the load shedding detection method by the other-end shedding detection unit 118 .
  • the horizontal axis indicates the elapsed time, and the vertical axis indicates the current effective value measured by the current measuring device 108a.
  • FIG. 5 shows the current change when the load cutoff of the other end occurs at time t_s on the horizontal axis.
  • a discontinuous decrease 402 in the output current is measured by the amount of the interrupted load.
  • a current change amount that deviates from the steady state is stored as a threshold, and the current change amount per unit time obtained from the current measurement value by the current measuring device 107a is compared with the stored threshold.
  • the other end cutoff detection unit 118 determines that the other end load has been cut off, and transmits the other end cutoff detection signal T to the load cutoff counting unit 119 .
  • the other end cutoff detection unit 118 can detect load cutoff of the other end from a sudden change in the voltage or current measured at the own end, as shown in FIG. 4 or FIG. It is also possible to use both the detection method based on the voltage change in the first example and the detection method based on the current change in the second example.
  • FIG. 6 is a flowchart for explaining a load shedding determination method by the load shedding control unit 116 .
  • the processing of this flow chart is periodically executed, for example, in a cycle of one second.
  • step S101 the number of interrupts S3 stored in the load interrupt counter 119 is reset (step S101). After that, by counting the number of times of interruption S3, the arrival of the interruption order of the own end is detected.
  • the load is shed at the self-end.
  • the number of times of interruption is 1, if the interruption order of the self-end is second, the load is shed at the self-end.
  • the own-end cutoff order the number of cutoff times S3+1, it means that the own-end cutoff order has not yet arrived.
  • it is judged to be timed out it indicates that there is a possibility that the load shedding of the other end, which has reached the cutoff order, has not been executed due to a failure of the switch of the other end. It is determined that load shedding at the other end has been executed. Therefore, if the blocking of the other end is detected or timed out in step S105, 1 is added to the number of times of blocking S3 (step S106).
  • step S107 After that, with load shedding executed at the other end, self-sustaining control is continued until the power control system 100 reaches an equilibrium state (step S107). After the balanced state is reached, it is determined that the number of times of interruption S3 ⁇ last interruption order ⁇ 1 (step S108). If the number of interrupts S3 ⁇ last interrupt order ⁇ 1 is established, the number of power converters supplying power to the load is two, and the effect of the load interrupt determination becomes low, so the power control in this embodiment is terminated. Moreover, when not materialized, it returns to step S102.
  • step S108 may be arbitrarily set by the facility manager. For example, the load shedding determination may be continued until only one power conversion device is supplied to the load. After the end of the power control, each device in the power control system 100 is restarted, reset, etc. are performed, and the power control system 100 is restarted.
  • load shedding determination method in steps S101 to S108 in FIG. 6 above has been described as being executed in the power control device 109a, by executing similar power control in other power control devices, Alternatively, load shedding at the other end is performed from time to time.
  • the electric power is determined by the overload generation determination method at the own end and the other end described in FIG. 3 and the load shedding detection method at the other end described in FIGS. Since it can be implemented without depending on communication between the control device and other power control devices, or between the power control device and an external device such as a power management server, multiple appropriate operation between power grids.
  • FIG. 7 is a diagram showing the blocking order table 204 stored in the blocking order storage unit 117. As shown in FIG. Although FIG. 7 is a table showing the order of interruption of seven power receiving points in order to facilitate the explanation of how to assign the order of interruption, the number of power receiving points is not limited to seven.
  • the shutdown order table 204 shown in FIG. 7 is composed of load names in the first column from the left, importance in the second column, power consumption in the third column, and shutdown order in the fourth column.
  • the importance listed in the second column is set such that the higher the importance, the higher the number, and the lower the importance, the lower the number. For example, in an area that constitutes an independent power grid (microgrid), the importance of disaster prevention equipment and communication equipment is set high, and the importance of air conditioning equipment and lighting equipment is set low.
  • the degree of importance is set to two levels for the sake of simplicity of explanation, but the degree of importance may be set to three or more levels.
  • the power consumption in the third column is the measured value of power consumption periodically collected from each load by the power management server 202 .
  • the facility manager may input through a user interface.
  • the shutdown order in the 4th column is ranked from 1st to 6th by sorting in order of low importance and high power consumption.
  • a predetermined threshold it is excluded from the shutdown target. For example, since the power consumption of the night light falls below the threshold value of 10 kW, it is set so as not to be assigned a cutoff order.
  • loads with high power consumption have a greater power saving effect when shutting down, so the shutting down order is set higher within the same importance. This is because it takes a certain amount of time for the load shedding to be executed and the droop control to reach a steady state.
  • the cutoff priority of the load with high power consumption is set high. The reason why load shedding below the threshold value is not assigned a shedding order is that load shedding does not contribute to the elimination of overload, as described above.
  • FIG. 8 is a flowchart showing a procedure for creating the shutdown order table 204 executed by the power management server 202.
  • Steps S201 to S203 show the flow of sorting the loads in descending order of importance and then sorting the loads in descending order of power consumption.
  • step S204 the collected power consumption values are compared with a predetermined power consumption threshold value, and in steps S205 and S206, the load exceeding the threshold value is sequentially assigned a cutoff order.
  • step S207 it is determined whether or not the assigned cutoff order is the last. If it is the last, it is determined that the cutoff order has been assigned to all the loads to be allocated, and the cutoff order table 204 is stored in step S208. If not, the process returns to step S204.
  • the power management server 202 periodically performs the processing shown in FIG. 8 and distributes the shutdown order table 204 to each power control device. Distribution of the cutoff order table 204 does not require immediacy such as the overload determination described in FIG. 3 and the load cutoff determination described in FIGS. Even if it is assumed that it is performed at a predetermined cycle, it does not reduce the effect of the power control method in this embodiment.
  • FIG. 9 is a diagram showing changes in voltage frequency when load shedding is executed in power control system 100.
  • the horizontal axis indicates the passage of time, and the vertical axis indicates the voltage frequency output from droop control section 112 .
  • time t_0a from the steady state, one of the power converters fails, and the active power output of the self-end increases accordingly.
  • the droop control unit 112 reduces the voltage frequency according to the droop characteristics described with reference to FIG.
  • the active power sharing rate of a plurality of power converters is determined by the phase difference between the respective output voltages, and the phase difference is the integrated value of the frequency.
  • time t_0a-t_0b is the time required to reach a steady state, and the steady state is reached at time t_0b.
  • the power control device with the first load shedding order executes load shedding.
  • the droop control unit 112 increases the voltage frequency because the active power of the self-end decreases accordingly.
  • load shedding is carried out at time t_2a and time t_3a until the overload is eliminated in all the power converters.
  • An overload of a power converter can occur, for example, in a microgrid that operates independently from an external power system, when some of a plurality of power converters fail.
  • overload determination by the droop characteristics of the own end and the other end, detection of the other end by the voltage measuring device and the current measuring device of the own end, and the number of times of interruption of the detected other end interruption detection By determining whether or not load shedding can be executed at the own end based on a predetermined shedding order, even if a partial failure or overload occurs in a power network including a plurality of DC power supplies, overloading of the entire power network can be prevented. It is effective in providing a power control device, a power control system, and a power control method that avoid loads and do not increase risks.
  • the power conversion device 104a and the switch 105a are not directly controlled via the communication line of the network 203, but at the time of installation of the power generation equipment, maintenance, etc., at predetermined intervals. Since the network 203 is used to receive control parameters such as droop characteristics and a cutoff order table only at times, high-speed responsiveness, such as on the order of milliseconds, is not essential.
  • the power system 101 may also include power receiving points such as a load only or a power supply only.
  • the operating point of the droop characteristic changes due to the existence of power receiving points of only the load and only the power supply. do not have.
  • the switch and the load are described as a set, there may be a plurality of these. For example, when there are different loads such as lighting and air conditioning, and a switch is provided for each of them, load shedding by the load shedding control unit 116 is performed individually. It does not limit the degree of freedom in terms of such circuit configuration.
  • DESCRIPTION OF SYMBOLS 100 Power control system 101... Power system 102a, 102b, 102c... DC power supply 103a, 103b, 103c... Load 104a, 104b, 104c... Power converter 105a, 105b, 105c... Switch 106a, 106b, 106c... Power receiving point 109a , 109b, 109c... Power control device 201... System switch 202... Power management server 203... Network 204... Interruption order table 110... Output calculation unit 111... Control characteristic setting unit 112... Droop control unit 113...

Abstract

直流電源と、電力変換部と、各負荷への電力供給を遮断する開閉部と、電力変換部からの出力を計測する電圧計測部および電流計測部と、を同一の電力系統上の自端電力網内および少なくとも1つの他端電力網内のそれぞれに備えられた、複数の電力網の電力制御を実行する電力制御装置であって、電力変換部の特性情報と、開閉部の遮断順位情報を記憶する記憶部と、有効電力と特性情報に基づいて過負荷が判定された際に、電圧値または電流値に基づいて検知された他端電力網における開閉部の遮断回数と、遮断順位情報と、に基づいて、自端電力網における開閉部の遮断を判断する負荷遮断制御部と、を備えた構成を有する。

Description

電力制御装置、電力制御システムおよび電力制御方法
 本発明は、複数の直流電源から交流に変換する電力変換回路を含む電力網の電力制御装置、電力制御システムおよび電力制御方法に関する。
 太陽光発電や蓄電池などの直流電源を交流の電力系統に連系する電力変換装置として、従来から用いられてきたグリッドフォローイングインバータ(Grid-Following Inverter、以下、GFL)に代わり、グリッドフォーミングインバータ(Grid-Forming Inverter、以下、GFI)への注目が高まっている。
 GFLは連系点における電力系統の電圧波形に追従する電流源として動作し、有効電力および無効電力の出力設定値に基づいて電流を制御する。あるいは、最大電力点追従(Maximum Power Point Tracker)と呼ばれる太陽光発電の出力制御においては、太陽電池の電圧-電流特性カーブに基づいて、有効電力を最大化するように電流を制御する。
 一方、GFIは電圧の周波数と振幅を制御する電圧源として動作する。たとえばGFIが電圧波形の周波数を下げると、交流の電力系統に対してGFIの電圧位相が遅れることで、有効電力の出力が減少する。また、GFIを系統に接続する電力ケーブルが誘導性であることから、GFIが電圧波形の振幅を連系点の電圧に対して下げると、無効電力の出力が減少する。このとき、GFIが出力する有効電力の大きさに比例して電圧周波数を下げるように、また、無効電力の大きさに比例して電圧振幅を下げるように制御することで、GFIは電力系統に接続された他のGFIや同期発電機との間で、自律的に出力の大きさを調整する作用を示す。このような電源間の電圧周波数差、または電圧振幅差によって出力を分担する方法はドループ制御と呼ばれ、今後、電力変換装置を介して接続された再生可能エネルギー(以下、再エネ)のさらなる増加と同期発電機の減少が予想されるなか、電力系統の安定性を向上する手段として期待されている。
 ドループ制御において、有効電力-周波数の関係、および無効電力-振幅の関係をドループ特性と呼び、ゲイン(上記2変数の一次関数で表されるドループ特性の傾き)とオフセット(同ドループ特性の切片)によって制御特性が変化する。ドループ特性の設定としては、ゲインを補正することで出力分担を変える方法(たとえば特許文献1)や、オフセットを補正することで出力分担を変える方法(たとえば特許文献2)が開示されている。
国際公開第2019/220763号 特開2016-119820号公報
 特許文献1、2のようなドループ制御方法では、たとえば蓄電池の充電量に応じて、GFIの有効電力の出力分担を変えることが出来る。しかしながら、この制御は、あくまでGFIの平常動作を前提としたものであり、複数のGFIのうち一部が故障した場合に、残存するGFIで過負荷が生じうるという課題があり、一部の故障が複数の発電機からなる電力網に影響してしまうという課題があった。
 本発明は、上記課題を解決するために、複数の直流電源を含む電力網の一部故障または過負荷が発生しても、電力網全体の過負荷を回避し、リスクを増大させない電力制御装置、電力制御システムおよび電力制御方法を提供する。
 上記課題を解決するための、本願発明の電力制御装置の一例を挙げるならば、直流電源と、前記直流電源の出力を交流に変換する電力変換部と、前記電力変換部から各負荷への電力供給を遮断する開閉部と、前記電力変換部から出力される電圧値を計測する電圧計測部と、前記電力変換部から出力される電流値を計測する電流計測部と、を同一の電力系統上の自端受電点および他端受電点のそれぞれに備えられた、独立した電力網の電力制御を実行する電力制御装置であって、前記電圧値と前記電流値から算定された有効電力に基づいて判定された過負荷判定結果と、前記電圧値、または前記電流値の変化量から検知された前記他端受電点における開閉部の遮断回数と、予め格納された前記開閉部の遮断順位情報と、に基づいて、前記自端受電点における開閉部の遮断を判断する負荷遮断制御部と、を備えた構成を有する。
 本発明に記載される電力制御装置、電力制御システムおよび電力制御方法によれば、直流から交流に変換する際のドループ特性による過負荷判定と、電圧波形や電流波形の急激な変化検出による負荷遮断判定と、予め定められた遮断順位により、電力網の一部故障または過負荷が発生しても、電力網全体の過負荷を回避し、リスクを増大させない。
本実施形態における複数の電力網から構成される電力制御システム100の構成図である。 本実施形態における電力網A内の機能ブロック図である。 本実施形態における電力制御装置のハードウェア構成図である。 ドループ制御部112によるドループ制御方法と、過負荷判定部115による自端および他端の過負荷判定方法を説明する特性図である。 他端遮断検知部118による負荷遮断検知方法の第1例を説明する特性図である。 他端遮断検知部118による負荷遮断検知方法の第2例を説明する特性図である。 負荷遮断制御部116による負荷遮断判定方法を説明するフローチャートである。 遮断順位記憶部117に記憶される遮断順位テーブル204を示す図である。 電力管理サーバ202によって実行される遮断順位テーブル204の作成手順を示すフローチャートである。 電力制御システム100内で負荷遮断を実行した際の電圧周波数の変化を示す図である。
 図1は、本実施形態における複数の電力網から構成される電力制御システム100の構成図を示している。
 電力制御システム100は、電力系統101に複数の受電点106a,106b,106cが設けられ、各受電点にそれぞれ電力網A、B、Cが設けられる。各電力網内には、直流電源102a,102b,102cから供給された直流電力を電力変換装置104a,104b,104cで交流に変換し、開閉器105a,105b,105cを介して負荷103a,103b,103cに供給される回路構成を示している。これらの電力系統101は、図1中の太線で示す電力線で接続されている。直流電源102a,102b,102cは、例えば太陽光発電、蓄電池、EV充電器などである。電源としているが、蓄電池やEVの充電状態においては、有効電力を消費する運転状態もある。
 電力変換装置104a,104b,104cは、直流を交流に変換する機能を有し、後述するように、周波数指令値に基づいて、有効電力を増減させる。直流から交流への変換回路に関しては、コイル、コンデンサ等を含む、インバーターと言われる電気回路が用いられるが、本実施形態においては限定するものではない。
 電力制御装置109a,109b,109cは、それぞれの電力変換装置104a,104b,104cと、開閉器105a,105b,105cと通信可能であり、それぞれの電力変換装置104a,104b,104cに対して電力変換時の周波数を指令値として送信すると共に、後述する負荷遮断判定に基づいて、それぞれの開閉器105a,105b,105cを開くことにより、それぞれの負荷への電力供給を遮断する。
 系統開閉器201は、図1に示す電力網A、B、Cと、他の電力網との接続を切り替える手段であり、開信号を受信することにより図1に示す電力系統101は、独立した電力網(マイクログリッド)となり、その内部で需給バランスを合わせる必要が生じる。また、閉信号を受信することにより外部の電力網に対して電力の供給、または外部の電力網から電力の受入を行う。本実施形態においては、主に系統開閉器201が開状態で、独立した電力網における回路動作を説明する。
 電力管理サーバ202は、ネットワーク203や操作入力手段(不図示)等適宜の手段により負荷103a,103b,103cの消費電力計測値を収集し、後述する遮断順位テーブル内の消費電力情報を更新し、遮断順位テーブルを随時更新して管理する。更に、設備管理者が、ユーザーインターフェースを用いて、後述する遮断順位テーブル内の情報を編集可能としてもよい。
 図2Aは、本実施形態における電力網A内の機能ブロック図である。図2Aにおいては、電力網A内の構成要素を「自端」と表現し、電力網A以外に接続される構成要素を「他端」と表現する。本実施形態では、他端は、2つの電力網B,C内の構成要素に相当するが、更に多くの電力網を形成した構成でもよい。
 図2Aは、図1と同様に、受電点106aが設けられ、受電点106aに直流電源102aから供給された直流出力を電力変換装置104aで交流に変換し、開閉器105aを介して負荷103aに供給する詳細構成図を示している。
 更に、直流電源102aから電力変換装置104aを経て受電点106aに接続される電力線の途中に電圧計測器107a、電流計測器108aを設け、交流に変換された出力の電圧実効値、電流実効値をそれぞれ計測する。
 図2Aにおいて、点線内が電力制御装置109aの機能ブロックを示しており、電力制御装置109aは、電力変換装置104aと同一の筐体に内蔵された計算機に実装する構成と、別筐体に内蔵された計算機に実装する構成があり、いずれかに限定するものではない。
 図2Aに示すように、電力制御装置109aは、出力算定部110と、制御特性設定部111と、ドループ制御部112と、他端特性記憶部113と、他端出力推定部114と、過負荷判定部115と、負荷遮断制御部116と、遮断順位記憶部117と、他端遮断検知部118と、負荷遮断計数部119と、の各機能ブロックを備えている。以下に、電力制御装置109a内に備えられた各機能ブロックの機能と動作を順次説明するが、他端の電力制御装置109b、109cにおいても同様の機能と動作を可能とする。
 出力算定部110は、電圧計測器107aと電流計測器108aの計測値から、電力変換装置104aから出力される交流電力の自端有効電力W1を算定する。具体的には、計測された電圧実効値と電流実効値を乗算することで有効電力が算定される。算定された自端有効電力W1は、過負荷判定部115に送信される。
 制御特性設定部111は、自端ドループ特性301を格納しており、ドループ制御動作を行う。ここで、ドループ特性は、有効電力-周波数の関係式としてゲイン(一次関数の傾き)とオフセット(一次関数の切片)によって記述されるものであり、図3において、ドループ特性の詳細を後述する。制御特性設定部111における自端ドループ特性は、自己診断モードを設け、電力制御装置109aの工場出荷時やメンテナンス時にオフラインで取得・作成されてもよい。
 ドループ制御部112は、出力算定部110で算定された自端有効電力W1と、制御特性設定部111に格納される自端ドループ特性301から電圧周波数を求め、電力変換装置104aに周波数指令値Fを送信する。同時に、周波数指定値Fは、他端出力推定部114にも送信される。ドループ制御部112が実行するドループ制御方法に関しては、図3において詳細を後述する。
 他端特性記憶部113は、他の電力網B、C内に設置される電力変換装置104b、104cに関するそれぞれの他端ドループ特性302を格納する。後述するドループ制御方法に関する説明では、他端ドループ特性302は、1特性で表現しているが、他の電力網内に設置される電力変換部の数だけ作成され、格納される。
 すなわち、制御特性設定部111は、自端ドループ特性301を格納し、他端特性記憶部113は、他端のドループ特性302を格納する。これら自端ドループ特性301および他端ドループ特性302は、電力制御装置109aが、各電力網の設置時、再始動時等特定のタイミングでネットワーク203を介して電力管理サーバ202との通信、もしくは電力制御装置109b、109cとの通信により取得してもよく、電力制御装置109a上のユーザーインターフェースを介して入力設定されてもよい。また、フラッシュメモリ等可搬性記憶媒体に対して読み書き可能としてもよい。
 他端出力推定部114は、ドループ制御部112から送信された周波数指令値Fと、他端特性記憶部113から送信された他端ドループ特性302に基づいて、他端有効電力W2を推定する。他端出力推定部114による他端有効電力W2の推定方法は、ドループ制御方法と共に、図3において後述する。
 過負荷判定部115は、出力算定部110で算定された自端有効電力W1と、他端出力推定部114で推定された他端有効電力W2に基づいて、自端と他端それぞれの電力変換装置の過負荷状態を判定する。自端において過負荷と判定された場合、自端過負荷判定信号S1を負荷遮断制御部116に送信し、他端において過負荷と判定された場合、他端過負荷判定信号S2を負荷遮断制御部116に送信する。過負荷判定部115による過負荷判定方法は、ドループ制御方法と共に、図3において後述する。
 他端遮断検知部118は、電圧計測器107a、または電流計測器108aの計測値の定常状態から逸脱する急激な変化を示す閾値を予め記憶しておき、計測値と閾値を比較することにより他端電力網内の開閉器105b、または105cの負荷遮断を検知する。他端電力網内の開閉器の遮断が検知された場合、他端遮断検知信号Tを負荷遮断計数部119に送信する。他端遮断検知部118による他端遮断検知方法は、図4、5において後述する。
 負荷遮断計数部119は、他端遮断検知部118から送信された他端遮断検知信号Tを受信し、遮断回数S3を計数して格納する。過負荷判定部115により、自端、または他端の過負荷が判定された場合、計数された遮断回数S3を負荷遮断制御部116に送信する。
 負荷遮断制御部116は、過負荷判定部115から送信された自端過負荷判定信号S1および他端過負荷判定信号S2と、負荷遮断計数部119から送信された遮断回数S3と、外部から取得した遮断順位テーブル204に基づいて、負荷遮断実行の可否を判断する。遮断可否を判断した結果、遮断実行と判定した場合、開閉器105aに開信号を送信し、負荷への電力供給を遮断する。負荷遮断制御部116による負荷遮断判定方法は、図6において後述する。
 遮断順位記憶部117は、電力系統101内に接続される各電力網内の負荷の遮断順位テーブル204を格納する機能を有し、例えば、ネットワーク上の電力管理サーバ202、もしくは他の電力制御装置109b、109cとの通信によって、各電力網の設置時、再始動時等特定のタイミングで遮断順位テーブル204を取得した後、格納する。または、ユーザーインターフェースにより遮断順位テーブル204内の情報を入力することにより格納・設定可能としてもよい。また、フラッシュメモリ等可搬性記憶媒体に対して読み書き可能としてもよい。
 次に、図2Bは、本実施形態における電力制御装置のハードウェア構成図である。電力制御装置109aは、CPU(Central Processing Unit)501と、CPU501が処理を実行するために必要なデータを一次記憶するためのメモリ502と、大量のデータを記憶する容量を持つハードディスク、可搬性記憶媒体等の記憶部503と、他装置と通信を行なうための通信部504と、キーボード、ディスプレイなどの入出力を行なうための入出力装置505と、これらの各装置を接続する通信バス506とを備えたコンピュータである。
 CPU501は、記憶部503から図2Aに示した各機能ブロックを含む電力制御プログラム109pと、自端ドループ特性301、他端ドループ特性302、遮断順位テーブル204、遮断回数S3といった制御情報を読み出し、メモリ502上において電力制御プログラム109p内の各プログラム110p~119pを動作させることにより、図2Aに示す機能ブロックを仮想的に構築し、後述するドループ制御方法、過負荷判定方法、負荷遮断判定方法を実行する。
 次に、ドループ制御方法と過負荷判定方法について詳細を述べる。図3は、ドループ制御部112によるドループ制御方法と、過負荷判定部115による自端および他端の過負荷判定方法を説明する特性図である。横軸は有効電力(pu値による単位表記)、縦軸は出力電圧の周波数(pu値による単位表記)である。なお、pu値は、電力変換装置の定格値に対する相対値を示しており、1.0を超えると定格外の出力であることを示し、電力変換装置が過負荷状態であることを示す。
 実線301は、制御特性設定部111に格納される自端のドループ特性である。自端ドループ特性301は、有効電力が0の場合に、上限周波数ω_uとなるオフセット(図3中の運転点303)と、運転点304、306を含むゲイン(直線の傾き)を有している。また、点線302は、他端特性記憶部113に格納される電力変換装置109b、および電力変換装置109cのドループ特性である。他端ドループ特性302は、有効電力が0の場合に、上限周波数ω_uとなるオフセット(図3中の運転点303)と、運転点305、307を含むゲイン(直線の傾き)を有している。
 過負荷判定方法に関して、動作例1と動作例2を挙げて具体的に説明する。動作例1として、出力算定部110が計測された電圧値、電流値から有効電力を算定した結果、自端有効電力0.5と算定された場合、有効電力値0.5をドループ制御部112に送信する。
 有効電力値0.5を受信したドループ制御部112は、図3の自端ドループ特性301上の運転点304から電圧周波数ω_lを決定し、電力変換装置104aおよび他端出力推定部114に周波数指令値Fとして送信すると共に、過負荷判定部115に自端有効電力W1として0.5を送信する。
 他端出力推定部114は、送信された電圧周波数ω_lと、他端特性記憶部113に記憶された他端ドループ特性302から、自端と他端で電圧周波数ω_lに同調すると判断し、他端ドループ特性302上の運転点305から、他端有効電力W2として1.0と推定し過負荷判定部115に送信する。
 過負荷判定部115は、自端有効電力W1の0.5と他端有効電力W2の1.0の信号を受信し、自端過負荷判定信号S1、他端過負荷判定信号S2を共にNo(過負荷ではない)と判定し、両方の過負荷判定信号を負荷遮断制御部116に送信する。
 一方、動作例2として、出力算定部110が計測された電圧値、電流値から有効電力を算定した結果、自端有効電力0.75と算定された場合、自端有効電力0.75をドループ制御部112に送信する。自端有効電力0.75を受信したドループ制御部112は、図3の自端ドループ特性301上の運転点306から電圧周波数ω_mを決定し、電力変換装置104aおよび他端出力推定部114に周波数指令値Fとして送信すると共に、過負荷判定部115に自端有効電力W1として0.75を送信する。
 他端出力推定部114は、送信された電圧周波数ω_mと、他端特性記憶部113に記憶された他端ドループ特性302から、自端と他端で電圧周波数ω_mに同調すると判断し、他端ドループ特性302上の運転点307から、他端有効電力W2として1.5と推定し過負荷判定部115に送信する。
 過負荷判定部115は、自端有効電力W1の0.75と、他端有効電力W2の1.5の信号を受け、自端過負荷判定信号S1をNo(過負荷ではない)、他端過負荷判定信号S2をYes(過負荷)と判定し、両方の過負荷判定信号を負荷遮断制御部116に送信する。以上のような処理過程で、自端のドループ制御と、自端および他端の過負荷判定を実行する。
 なお、いずれの動作例においても、周波数指令値Fを送信された電力変換装置104aは、直流から交流に変換する際の出力周波数を周波数指令値Fに基づいて駆動する。駆動した結果、図1に示すように、同一の電力系統101に接続される複数の電力網においては、電圧周波数に差が発生した場合、高い周波数の電力変換装置から給電し、低い周波数の電力変換装置に受電する現象が発生し、最終的に周波数が同調して安定駆動する。例えば、周波数ω_lで同調する場合、自端と他端の有効電力が0.5:1.0となる分担率で動作するように、自立制御が実行される。
 図4は、他端遮断検知部118による負荷遮断検知方法の第1例を説明する特性図である。横軸は経過時間、縦軸は電圧計測器107aで計測される電圧実効値を示している。
 図4は、横軸の時間t_sで、他端の負荷遮断が発生した場合の電圧変化を示している。他端の開閉器105b,または105cが遮断されると、遮断された負荷の分だけ電流が急減し、電力系統101内の電力線のインダクタンスによって急峻な電圧変化401が計測される。このような電圧変化は、定常状態の電圧の数倍~数十倍に達するため、例えば、定常状態を逸脱する電圧変化量を閾値として格納しておき、電圧計測器107aによる電圧計測値から求められた電圧変化量と、格納された閾値を比較して電圧変化量が閾値を超えた場合、他端遮断検知部118は、他端の負荷遮断と判定し、他端遮断検知信号Tを負荷遮断計数部119に送信する。
 また、図5は、他端遮断検知部118による負荷遮断検知方法の第2例を説明する特性図である。横軸は経過時間、縦軸は電流計測器108aで計測される電流実効値を示している。
 図5は、横軸の時間t_sで、他端の負荷遮断が発生した場合の電流変化を示している。他端の開閉器105b,または105cが遮断されると、遮断された負荷の分だけ出力電流の不連続減少402が計測される。このような電流変化は、定常状態を逸脱する電流変化量を閾値として格納しておき、電流計測器107aによる電流計測値から求められた単位時間あたりの電流変化量と、格納された閾値を比較して電流変化量が閾値を超えた場合、他端遮断検知部118は、他端の負荷遮断と判定し、他端遮断検知信号Tを負荷遮断計数部119に送信する。
 他端遮断検知部118は、図4、または図5に示されるように、自端で計測される電圧あるいは電流の急激な変化から、他端の負荷遮断を検知可能とする。また、第1例の電圧変化による検知方法と、第2例の電流変化による検知方法を併用して用いることも可能である。
 次に、本実施形態における負荷遮断判定方法を説明する。図6は、負荷遮断制御部116による負荷遮断判定方法を説明するフローチャートである。本フローチャートの処理は、たとえば1秒周期などで定期的に実行する。
 図6において、負荷遮断計数部119に格納されている遮断回数S3をリセットする(ステップS101)。この後、遮断回数S3の計数により、自端の遮断順位の到来を検出する。次に、過負荷判定部115により自端、または他端の過負荷が判定された場合に図6のフローが開始される。自端過負荷判定信号S1、または他端過負荷判定信号S2から過負荷を判定する(ステップS102)。自端、または他端の過負荷が発生した場合、自端遮断順位=遮断回数S3+1の成立を判定する(ステップS103)。ステップS103において自端遮断順位=遮断回数S3+1が成立した場合(Yes)、自端の開閉器105aを遮断して(ステップS104)、電力制御装置109aは自端の負荷遮断判定を終了する。
 具体的には、初期状態で遮断回数リセットにより0であり、自端の遮断順位が1位であれば、自端で負荷遮断を実行する。または、遮断回数が1となっている場合、自端の遮断順位が2位であれば、自端で負荷遮断を実行する。
 ステップS103において自端遮断順位=遮断回数S3+1が成立しない場合、もしくはタイムアウトと判定された場合(No)、ステップS105に進む。この場合、ステップS103で自端遮断順位=遮断回数S3+1が成立しない場合は、自端遮断順位がまだ到来していないことを示している。また、タイムアウトと判定された場合は、他端の開閉器の故障等により遮断順位が到来している他端の負荷遮断が実行されていない可能性が有ることを示しており、リスク回避のため他端負荷遮断が実行されたものと判断する。従って、ステップS105において他端遮断検知またはタイムアウトの場合、遮断回数S3を1加算する(ステップS106)。
 その後、他端で負荷遮断が実行された状態で、電力制御システム100が平衡状態になるまで自立制御を継続し、平衡状態になる(ステップS107)。平衡状態になった後、遮断回数S3<最後位遮断順位-1を判定する(ステップS108)。遮断回数S3<最後位遮断順位-1が成立した場合、負荷に電力供給している電力変換装置が2台となり、負荷遮断判定の効果が低くなるため本実施形態における電力制御を終了する。また、成立しない場合、ステップS102に戻る。
 なお、ステップS108における電力制御の終了判定については、設備管理者が任意に設定可能としてもよい。例えば、負荷に供給する電力変換装置が1台になるまで負荷遮断判定を継続してもよい。電力制御終了後、電力制御システム100内の各機器の再起動、再設定等を行い、電力制御システム100を再始動する。
 以上の図6のステップS101~S108における負荷遮断判定方法は、電力制御装置109aにおいて実行されるものとして述べたが、他の電力制御装置においても同様の電力制御を実行することにより、自端、または他端の負荷遮断が随時実施される。
 なお、図6におけるステップS101~S108の実行に関しては、図3で説明した自端および他端における過負荷発生判定方法、および図4、図5で説明した他端における負荷遮断検知方法によって、電力制御装置と他の電力制御装置、または電力制御装置と電力管理サーバ等外部装置との通信に依存せずに実施可能であることから、それぞれの電力変換装置の過負荷状態に応じて迅速に複数の電力網間の適切な運用が可能となる。
 次に、負荷遮断順位に関して詳細に説明する。図7は、遮断順位記憶部117に格納される遮断順位テーブル204を示す図である。図7は、遮断順位の付け方を説明しやすくするため7受電点の遮断順位を示すテーブルとしているが、7受電点に限定されるものではない。図7に示す遮断順位テーブル204は、左列から第1列に負荷の名称、第2列に重要度、第3列に消費電力、第4列に遮断順位から構成される。
 第2列に記載された重要度は重要度が高いほど数字を大きく、重要度が低いほど数字を小さく設定されている。例えば、独立した電力網(マイクログリッド)を構成する地域内において、防災設備や通信設備の重要度は高く、空調設備や照明設備の重要度は低く設定される。図7では、説明を簡略化するため重要度を2段階としているが、重要度は3段階以上に設定しても良い。
 第3列の消費電力は、電力管理サーバ202が各負荷から定期的に収集する消費電力の実測値である。また、設備管理者がユーザーインターフェースにより入力してもよい。
 第4列の遮断順位は、重要度が低く、かつ消費電力が高い順にソートすることにより、1位~6位まで順位付けしている。また、負荷の消費電力が所定の閾値を下回る場合には、遮断対象外とする。例えば、常夜灯は、消費電力が閾値10kWを下回るため、遮断順位を割り当てていない設定としている。
 図7においては、消費電力の高い負荷の方が、遮断実行時の節電効果が大きいため、同じ重要度の中で遮断順位を高く設定している。なぜなら、負荷遮断を実行し、ドループ制御が定常状態となるにはある程度の時間を要する。消費電力の小さな負荷の遮断を繰り返した場合、負荷遮断が過負荷解消に寄与しないばかりか、段階的な負荷遮断による過負荷解消に要する時間が、電力変換装置の設計上定められた値を上回る場合がある。従って、消費電力の高い負荷の遮断順位を高く設定している。閾値以下の負荷に遮断順位を割り当てない理由は、上述と同様に、負荷遮断が過負荷解消に寄与しないためである。
 次に、遮断順位テーブルの作成方法を説明する。図8は、電力管理サーバ202によって実行される遮断順位テーブル204の作成手順を示すフローチャートである。ステップS201~S203は、重要度が低い順に各負荷をソートした後、消費電力の高い順に各負荷をソートするフローを示している。更に、ステップS204において、収集した消費電力値を予め定められた消費電力の閾値と比較し、ステップS205、S206において閾値以上の負荷に順次遮断順位を割り当てる。ステップS207において割り当てられた遮断順位が最後位かどうかを判断する。最後位であれば、割り当てるべきすべての負荷に遮断順位を割り当てたと判断し、ステップS208において遮断順位テーブル204を格納する。最後位でなければ、ステップS204に戻る。
 電力管理サーバ202は、図8のような処理を定期的で実施して、各電力制御装置に遮断順位テーブル204を配信する。この遮断順位テーブル204の配信は、図3で説明した過負荷判定、図4、図5で説明した負荷遮断判定のような即時性を必要としないため、LAN、WAN等様々なネットワークを介して所定の周期で実施することを想定しても、本実施形態における電力制御方法の効果を低減させるものではない。
 次に、本実施形態における電力制御を実行した場合の動作状態を説明する。図9は、電力制御システム100内で負荷遮断を実行した際の電圧周波数の変化を示す図である。横軸は時刻の経過、縦軸はドループ制御部112が出力する電圧周波数を示す。
 定常状態から時刻t_0aで複数の電力変換装置のうち1つが故障し、その分、自端の有効電力出力が増加する。このとき、図3で説明したドループ特性に従って、ドループ制御部112は電圧周波数を低下させる。複数の電力変換装置による有効電力の分担率は、それぞれの出力電圧の位相差によって定まり、位相差は周波数の積分値であるため、ドループ制御による分担率は瞬時には定常状態とならない。図9において、時間t_0a-t_0bが定常状態になるまでに要する時間であり、時間t_0bで定常状態となる。
 次に、時刻t_1aにおいて、負荷遮断順位1位の電力制御装置が負荷遮断を実行する。その分、自端の有効電力が減少するため、ドループ制御部112は電圧周波数を上昇させる。ここでも分担率が定常状態になるまで、時間t_1a-t_1bを要する。以下、同様にして、すべての電力変換装置で過負荷が解消されるまで、時刻t_2a、時刻t_3aでもそれぞれ負荷遮断が実施される。電力変換装置の過負荷は、たとえば外部の電力系統から自立して運用されているマイクログリッドにおいて、複数の電力変換装置のうち一部が故障した場合に生じうる。
 以上述べたように、自端、および他端のドループ特性による過負荷判定と、自端の電圧計測器と電流計測器による他端遮断検知と、検知された他端遮断検知の遮断回数と、予め定められた遮断順位と、に基づいて、自端における負荷遮断の実行可否を判定することにより、複数の直流電源を含む電力網の一部故障または過負荷が発生しても、電力網全体の過負荷を回避し、リスクを増大させない電力制御装置、電力制御システムおよび電力制御方法を提供するという効果を奏する。
 更に、本実施形態における電力制御方法においては、ネットワーク203の通信回線を介して直接に電力変換装置104aや開閉器105aを制御するわけではなく、発電設備の設置時、メンテナンス時等の所定周期の時のみ、制御パラメータであるドループ特性や遮断順位テーブルを受信するためにネットワーク203を活用するため、たとえばミリ秒オーダーといった高速な応答性は必須ではない。
 なお、本実施形態においては、直流電源と負荷がセットになった受電点のみを記載したが、電力系統101には、負荷のみ、電源のみといった受電点も存在しうる。この場合、負荷のみ、電源のみの受電点の存在によってドループ特性の運転点が変化することとなるが、本実施形態における電力制御方法は、有用なものであり、上述した効果が低減するものではない。また、開閉器および負荷をセットで記載しているが、これらは複数の場合もある。例えば、負荷に照明や空調などの区別があり、それぞれに開閉器が設けられている場合は、負荷遮断制御部116による負荷遮断は個別に実施される。このような回路構成上の自由度を制限するものではない。
 100…電力制御システム
 101…電力系統
 102a,102b,102c…直流電源
 103a,103b,103c…負荷
 104a,104b,104c…電力変換装置
 105a,105b,105c…開閉器
 106a,106b,106c…受電点
 109a,109b,109c…電力制御装置
 201…系統開閉器
 202…電力管理サーバ
 203…ネットワーク
 204…遮断順位テーブル
 110…出力算定部
 111…制御特性設定部
 112…ドループ制御部
 113…他端特性記憶部
 114…他端出力推定部
 115…過負荷判定部
 116…負荷遮断制御部
 117…遮断順位記憶部
 118…他端遮断検知部
 119…負荷遮断計数部
 109p…電力制御プログラム
 110p…出力算定プログラム
 111p…制御特性設定プログラム
 112p…ドループ制御プログラム
 113p…他端特性記憶プログラム
 114p…他端出力推定プログラム
 115p…過負荷判定プログラム
 116p…負荷遮断制御プログラム
 117p…遮断順位記憶プログラム
 118p…他端遮断検知プログラム
 119p…負荷遮断計数プログラム
 301…自端ドループ特性
 302…他端ドループ特性
 303…ドループ特性オフセット(切片)
 304…動作例1の自端ドループ特性の運転点
 305…動作例1の他端ドループ特性の運転点
 306…動作例2の自端ドループ特性の運転点
 307…動作例2の他端ドループ特性の運転点
 401…他端遮断発生時の電圧変化
 402…他端遮断発生時の電流変化
 501…CPU
 502…メモリ
 503…記憶部
 504…通信部
 505…入出力装置
 506…通信バス
 A、B、C…電力網
 W1…自端有効電力
 W2…他端有効電力
 S1…自端過負荷判定信号
 S2…他端過負荷判定信号
 S3…遮断回数
 T…他端遮断検知信号

Claims (12)

  1.  直流電源と、
     前記直流電源の出力を交流に変換する電力変換部と、
     前記電力変換部から各負荷への電力供給を遮断する開閉部と、
     前記電力変換部から出力される電圧値を計測する電圧計測部と、
     前記電力変換部から出力される電流値を計測する電流計測部と、が同一の電力系統上の自端電力網内および少なくとも1つの他端電力網内のそれぞれに備えられた、複数の電力網の電力制御を実行する電力制御装置であって、
     前記自端電力網内の電力変換部の自端特性情報と、前記他端電力網内の電力変換部の他端特性情報と、前記複数の電力網内の各開閉部の遮断順位を示す遮断順位情報と、を記憶する記憶部と、
     前記自端電力網内で計測された電圧値と電流値に基づいて前記他端電力網内の開閉部の遮断を検知する他端遮断検知部と、
     前記自端電力網内で計測された電圧値と電流値から算定された有効電力と前記自端特性情報および前記他端特性情報に基づいて過負荷が判定された際に、前記他端遮断検知部によって検知された回数を累計した遮断回数と、前記遮断順位情報と、に基づいて、前記自端電力網内の開閉部の遮断を判断する負荷遮断制御部と、を備えたことを特徴とする電力制御装置。
  2.  前記他端遮断検知部は、前記複数の電力網が定常的な稼働状態から逸脱する電圧閾値を記憶し、
     前記電圧値の変化量が、前記電圧閾値を超えた場合に前記他端電力網内の開閉部の遮断と検知することを特徴とする請求項1に記載の電力制御装置。
  3.  前記他端遮断検知部は、前記複数の電力網が定常的な稼働状態から逸脱する電流閾値を記憶し、
     前記電流値の変化量が、前記電流閾値を超えた場合に前記他端電力網内の開閉部の遮断と検知することを特徴とする請求項1に記載の電力制御装置。
  4.  前記自端特性情報、前記他端特性情報および前記遮断順位情報は、ユーザーインターフェースにより任意に編集可能であることを特徴とする請求項1に記載の電力制御装置。
  5.  前記自端特性情報、前記他端特性情報および前記遮断順位情報は、可搬性記憶媒体に対して読み書き可能であることを特徴とする請求項1に記載の電力制御装置。
  6.  前記電力制御装置と同一ネットワーク上に電力管理サーバを更に備え、
     前記遮断順位情報は、前記電力管理サーバから取得されることを特徴とする請求項1に記載の電力制御装置。
  7.  前記自端特性情報は、前記電力管理サーバから取得されることを特徴とする請求項6に記載の電力制御装置。
  8.  前記他端特性情報は、前記電力管理サーバから取得されることを特徴とする請求項6に記載の電力制御装置。
  9.  請求項1に記載の前記同一の電力系統上に系統開閉装置を更に備え、
     前記系統開閉装置は、前記複数の電力網における自立電力制御、または前記複数の電力網の外部との電力受給制御のいずれかに切り替えることを特徴とする電力制御システム。
  10.  直流電源と、
     前記直流電源の出力を交流に変換する電力変換部と、
     前記電力変換部から各負荷への電力供給を遮断する開閉部と、
     前記電力変換部から出力される電圧値を計測する電圧計測部と、
     前記電力変換部から出力される電流値を計測する電流計測部と、が同一の電力系統上の自端電力網内および少なくとも1つの他端電力網内のそれぞれに備えられた、複数の電力網の電力制御を実行する電力制御方法であって、
     前記自端電力網内で計測された電圧値および電流値から有効電力を算定する出力算定ステップと、
     前記自端電力網内の電力変換部の自端特性情報と、前記他端電力網における電力変換部の他端特性情報と、前記複数の電力網内の各開閉部の遮断順位を示す遮断順位情報と、を記憶する第1の記憶ステップと、
     前記自端電力網内で計測された電圧値および電流値に基づいて前記他端電力網内の開閉部の遮断を検知する他端遮断検知ステップと、
     前記有効電力、前記自端特性情報および前記他端特性情報に基づいて過負荷が判定された際に、前記他端遮断検知ステップで検知された回数を累計した遮断回数と、前記遮断順位情報と、に基づいて、前記自端電力網における開閉部の遮断を判断する負荷遮断制御ステップと、を実行することを特徴とする電力制御方法。
  11.  前記遮断順位情報は、前記負荷の重要度情報、消費電力情報をそれぞれ収集し、前記重要度情報および前記消費電力情報の大小関係に基づいて遮断順位を決定されることを特徴とする請求項10に記載の電力制御方法。
  12.  前記開閉部の遮断効果が低い負荷を判定する消費電力閾値を記憶する第2の記憶ステップを更に備え、
     前記遮断順位情報は、前記負荷の消費電力情報が前記消費電力閾値以下の場合、遮断順位を割り当てないことを特徴とする請求項10に記載の電力制御方法。
PCT/JP2022/031975 2021-08-26 2022-08-25 電力制御装置、電力制御システムおよび電力制御方法 WO2023027137A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2021-138436 2021-08-26
JP2021138436A JP2023032357A (ja) 2021-08-26 2021-08-26 電力制御装置、電力制御システムおよび電力制御方法

Publications (1)

Publication Number Publication Date
WO2023027137A1 true WO2023027137A1 (ja) 2023-03-02

Family

ID=85322904

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2022/031975 WO2023027137A1 (ja) 2021-08-26 2022-08-25 電力制御装置、電力制御システムおよび電力制御方法

Country Status (2)

Country Link
JP (1) JP2023032357A (ja)
WO (1) WO2023027137A1 (ja)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7422951B1 (ja) 2023-01-31 2024-01-26 三菱電機株式会社 蓄電池制御システム、蓄電池の制御方法、蓄電池の制御プログラム、および統合コントローラ

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140097683A1 (en) * 2012-10-08 2014-04-10 Eaton Corporation Generator dispatching or load shedding control method and system for microgrid applications
JP2019030199A (ja) * 2017-08-03 2019-02-21 パナソニックIpマネジメント株式会社 電力変換装置、電力変換システム

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140097683A1 (en) * 2012-10-08 2014-04-10 Eaton Corporation Generator dispatching or load shedding control method and system for microgrid applications
JP2019030199A (ja) * 2017-08-03 2019-02-21 パナソニックIpマネジメント株式会社 電力変換装置、電力変換システム

Also Published As

Publication number Publication date
JP2023032357A (ja) 2023-03-09

Similar Documents

Publication Publication Date Title
JP4776475B2 (ja) 電力系統連系システム
US9671807B2 (en) Power grid stabilization system and power grid stabilization method
KR101827158B1 (ko) 마이크로그리드용 에너지 저장 장치에 대한 운영 장치 및 방법
WO2011129054A1 (ja) 電力管理システム、電力管理方法および区間コントローラ
US20120283888A1 (en) Seamless Transition Method and Apparatus for Micro-grid Connect/Disconnect from Grid
EP0959552A2 (en) Device for operating inverters and power supply system
AU2013101461A4 (en) Grid stability control system and method
EP2490312A1 (en) Solar generation method and system
CN115473223A (zh) 混合电力系统中的负载管理
TWI774142B (zh) 交流負荷供電系統和方法
CN108155663B (zh) 控制配电微电网的方法
KR101566296B1 (ko) 전력계통에서의 주파수 제어 시스템
KR20180121079A (ko) 계층형 전력 제어 시스템
RU2568013C2 (ru) Система выработки энергии и способ ее эксплуатации
WO2023027137A1 (ja) 電力制御装置、電力制御システムおよび電力制御方法
WO2020105359A1 (ja) 直流給配電システム
JP2001069668A (ja) 電力管理装置
CN107681649B (zh) 一种控制直流微电网母线电压稳定的方法
KR102324325B1 (ko) 에너지저장시스템 계층형 관리시스템
US10574056B1 (en) Communication enabled fast-acting imbalance reserve
CN115102187A (zh) 孤岛微电网管理系统及其能量管理方法
US20220302703A1 (en) Methods and systems for power management in a microgrid
EP3876377A1 (en) Energy consumption system
RU2726943C1 (ru) Способ снижения расхода топлива дизель-генераторными установками в гибридной электростанции с возобновляемыми источниками энергии
KR101936293B1 (ko) 에너지 저장 시스템

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22861425

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE