WO2023007916A1 - 生産計画装置、生産計画システムおよび生産計画方法 - Google Patents

生産計画装置、生産計画システムおよび生産計画方法 Download PDF

Info

Publication number
WO2023007916A1
WO2023007916A1 PCT/JP2022/020837 JP2022020837W WO2023007916A1 WO 2023007916 A1 WO2023007916 A1 WO 2023007916A1 JP 2022020837 W JP2022020837 W JP 2022020837W WO 2023007916 A1 WO2023007916 A1 WO 2023007916A1
Authority
WO
WIPO (PCT)
Prior art keywords
production
plan
plans
work
planning
Prior art date
Application number
PCT/JP2022/020837
Other languages
English (en)
French (fr)
Inventor
隆宏 中野
洋一 野中
大輔 堤
Original Assignee
株式会社日立製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立製作所 filed Critical 株式会社日立製作所
Priority to DE112022002742.8T priority Critical patent/DE112022002742T5/de
Priority to US18/570,855 priority patent/US20240281733A1/en
Publication of WO2023007916A1 publication Critical patent/WO2023007916A1/ja

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32252Scheduling production, machining, job shop
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32283Machine scheduling, several machines, several jobs
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Definitions

  • the present invention relates to a production planning device, a production planning system, and a production planning method.
  • the present invention claims priority of Japanese patent application number 2021-125953 filed on July 30, 2021, and for designated countries where incorporation by reference of documents is permitted, the content described in the application is incorporated into this application by reference.
  • Patent document 1 relates to a manufacturing system, and states, "When a replanning instruction is given from a server in response to a determination that a replanning execution condition has been established, the production control measure replans the production plan using a production simulator. Then, the re-planned production plan is assigned to each production facility in the factory, thereby making it possible to maintain the optimum condition without affecting subsequent production plans even if schedule delays occur. ” is stated.
  • Patent Document 1 discloses a technique for re-planning a production plan using a production simulator when a problem occurs.
  • the production system of this document only the production plan is re-planned, and the process plan and the work plan are not re-planned. That is, in the production system of Patent Document 1, the problem is dealt with only by re-planning the production plan without re-planning the process plan or work plan, so the scope of response is limited, resulting in a delay in the production plan. problems may occur.
  • the present invention has been made in view of the above problems, and aims to flexibly respond to production fluctuations by updating process plans, work plans, and production plans in a short period of time.
  • a production planning apparatus that solves the above problems is a process plan relating to a production process of a product, a process plan generation unit that generates a plurality of process plans including alternative process plans; a work plan generation unit that generates a work plan corresponding to the process plan; a production plan generation unit that generates a production plan using the plurality of process plans and the work plan; and a production planning re-planning unit that re-plans a production plan using the process plan and the work plan.
  • process plans, work plans, and production plans can be updated in a short period of time in response to production fluctuation events, and it is possible to flexibly respond to production fluctuations.
  • FIG. 10 is a flow diagram showing an example of a process for calculating the number of alternative steps;
  • FIG. 4 is a diagram showing an example of a work partial order graph; It is the figure which showed an example of the hardware constitutions of the 1st production planning apparatus.
  • FIG. 1 is a diagram showing an example of a schematic configuration of a production planning system 1000 according to this embodiment.
  • the production planning system 1000 has a first production planning device 100 and a second production planning device 200 .
  • the first production planning device 100 and the second production planning device 200 communicate with each other via a network N such as a public network such as the Internet, a LAN (Local Area Network), or a WAN (Wide Area Network). connected as possible.
  • a network N such as a public network such as the Internet, a LAN (Local Area Network), or a WAN (Wide Area Network). connected as possible.
  • the first production planning device 100 and the second production planning device 200 are used to transmit, via the network N, instructions for executing processing to these devices and information used for processing of each device. It is also communicably connected to the external device 300 .
  • the first production planning device 100 is a device that draws up a production plan for products manufactured on a factory production line.
  • the first production planning device 100 is implemented by, for example, a server device placed in a cloud environment.
  • the second production planning device 200 is a device that uses the production plan acquired from the first production planning device 100 to issue product manufacturing instructions to each piece of equipment that constitutes the production line of the factory.
  • the second production planning device 200 is implemented by a server placed in an edge environment such as a factory.
  • the first production planning device 100 generates in advance a plurality of process plans including alternative process plans and work plans corresponding to each process plan in order to flexibly respond to the occurrence of production fluctuation events. to formulate a production plan. Also, the first production planning device 100 transmits to the second production planning device 200 a production plan, a plurality of process plans including alternative process plans, and work plans corresponding to each process plan.
  • the second production planning device 200 analyzes whether or not a production fluctuation event has occurred according to the production line status of the factory, and when it determines to re-plan the production plan, the first production planning device 100 A plurality of acquired process plans and work plans corresponding to them are used to redesign a production plan, and based on the redesigned production plan, a manufacturing instruction is issued to each piece of equipment.
  • the first production planning device 100 has a processing unit 110, a storage unit 120, an input unit 130, an output unit 140, and a communication unit 150.
  • the processing unit 110 is a functional unit that executes various processes performed by the first production planning device 100. Specifically, the processing unit 110 has a process evaluation unit 111, a process evaluation graph generation unit 112, a process plan generation unit 113, a work plan generation unit 114, and a production plan generation unit 115. .
  • the process evaluation unit 111 is a functional unit that evaluates the work process of the components that make up the target product. Specifically, the process evaluation unit 111 calculates an evaluation index (process evaluation index) of dimensional variation and work time variation of components (including components similar to components). In addition, the process evaluation unit 111 calculates the operation rate of equipment used in processes that handle component parts (including parts similar to component parts).
  • the process evaluation graph generation unit 112 uses a graph showing the work partial order relationship of the product (hereinafter sometimes referred to as "work partial order graph") to generate an alternative process number reference value based on an evaluation index such as dimensional variation. calculate. In addition, the process evaluation graph generation unit 112 generates a process evaluation graph in which the alternative process number reference value is assigned to the node indicating the corresponding component part or process.
  • the process plan generation unit 113 is a functional unit that generates a process plan. Specifically, the process plan generation unit 113 calculates the number of alternative processes for the corresponding process based on the reference value for the number of alternative processes. In addition, the process plan generation unit 113 generates a process plan (including an alternative process plan) using a set of each process and equipment to which the number of facilities corresponding to the number of alternative processes is allocated.
  • the work plan generation unit 114 is a functional unit that generates work plans corresponding to each process plan.
  • the production plan generation unit 115 is a functional unit that generates a production plan using process plans and work plans.
  • the storage unit 120 is a functional unit that stores various information. Specifically, the storage unit 120 has production performance information 121, product CAD (Computer-Aided Design) information 122, part shape information 123, product amount information 124, and factory layout information 125. there is
  • FIG. 2 is a diagram showing an example of the actual production information 121.
  • the production performance information 121 is information about past production performance.
  • the product ID 121a of the actual production information 121 is information for identifying the product.
  • the part ID 121b is information for identifying the part.
  • the process ID 121c is information for identifying a process.
  • the production resource ID 121d is information for identifying production resources.
  • the date and time 121e is information indicating the execution date and time of a predetermined process, such as assembling the part of the corresponding part ID 121b, in the production of the product identified by the associated product ID 121a.
  • the starting time 121f is information indicating the starting time of the process identified by the associated process ID 121c.
  • the end time 121g is information indicating the end time of the process.
  • the production performance information 121 is updated by registering information on the target.
  • FIG. 3 is a diagram showing an example of the product CAD information 122.
  • Product CAD information 122 includes information including component work sequence relationships and other attribute information.
  • FIG. 4 is a diagram showing an example of the component shape information 123.
  • the part shape information 123 is information about the shape of the components that make up the product.
  • the component ID 123a of the component shape information 123 is information for identifying the component.
  • the part name 123b is information indicating the name of the part.
  • the shape characteristic 123c is information indicating the shape characteristics of a part such as a cylinder, rectangle, or cylinder.
  • Width 123d, length 123e, diameter 123f and weight 123g are information indicating the width, length, diameter and weight of the part, respectively.
  • FIG. 5 is a diagram showing an example of the product volume information 124.
  • the product amount information 124 is information on the amount of products or parts to be produced.
  • the product ID 124a of the product amount information 124 is information for identifying the product.
  • the monthly production amount 124b is information indicating the production amount of the target product or component parts in a predetermined target period.
  • FIG. 6 is a diagram showing an example of the factory layout information 125.
  • the factory layout information 125 is information indicating the positions of areas (cells) and conveyors in the factory for arranging equipment.
  • Each information in the storage unit 120 may not be stored in the storage unit 120 in advance, and may be acquired from the external device 300 when the processing in the first production planning device 100 is executed.
  • the input unit 130 is a functional unit that receives instructions and information input from the operator via the input device provided in the first production planning apparatus 100 .
  • the input unit 130 also receives instructions and input of information from the second production planning device 200 or the external device 300 via the communication unit 150 .
  • the output unit 140 is a functional unit that generates display information and displays the display information on the display devices (displays) provided in the first production planning device 100 or the second production planning device 200 and the external device 300 .
  • the communication unit 150 is a functional unit that performs information communication with the second production planning device 200 or the external device 300.
  • the second production planning device 200 has a processing unit 210, a storage unit 220, an input unit 230, an output unit 240, and a communication unit 250.
  • the processing unit 210 is a functional unit that executes various processes performed by the second production planning device 200. Specifically, the processing unit 210 has a manufacturing instruction unit 211 , a production plan update timing determination unit 212 , a production line analysis unit 213 , and a production plan re-planning unit 214 .
  • the manufacturing instruction unit 211 is a functional unit that transmits manufacturing instructions to each piece of equipment in the factory. Specifically, the manufacturing instruction unit 211 instructs each facility in the factory via the communication unit 250 to operate in accordance with the work plan corresponding to the production plan generated by the first production planning device 100. By outputting (manufacturing instructions), the product is produced.
  • the production plan update timing determination unit 212 is a functional unit that determines the update timing of the production plan. Specifically, the production plan update timing determination unit 212 determines whether or not the timing for reviewing the configuration of the production line or the timing for drafting the production plan has arrived. In addition, the information regarding these periods should just be stored in the memory
  • the production line analysis unit 213 is a functional unit that analyzes the status of the production line. Specifically, the production line analysis unit 213 acquires and analyzes information indicating the status of the production line from each equipment in the factory connected via the communication unit 250 .
  • the production plan re-planning unit 214 is a functional unit that re-plans the production plan. Specifically, the production plan re-drafting unit 214 re-drafts the production plan using the process plan acquired from the first production planning device 100 and the work plans corresponding to each process plan.
  • the storage unit 220 is a functional unit that stores various information. Specifically, the storage unit 220 has a process plan 221 including an alternative process plan acquired from the first production planning device 100, a work plan 222, a production plan 223, and production performance information 224. there is
  • FIG. 7 is a diagram showing an example of the process plan 221.
  • the process plan 221 information regarding the manufacturing process of the product is registered.
  • the product ID 221a of the process plan is information for identifying the target product.
  • the process ID 221b is information for identifying a process.
  • the production resource ID 221c is information for identifying production resources.
  • FIG. 8 is a diagram showing an example of the work plan 222.
  • the work plan 222 information indicating work contents to be performed in each process is registered.
  • the work ID 222 a of the work plan 222 is information for identifying work, and is information associated with each process ID 221 b of the process plan 221 .
  • the work plan ID 222b is information for identifying a work plan, and an ID indicating the contents of the work plan (for example, assembly work, etc.) is registered.
  • the work time 222c is information indicating the work time required for the facility (production resource) assigned to the process identified by the work ID 222a to execute the work content identified by the work plan ID 222b.
  • the work plan ID 222b is stored in the storage unit 120 in association with a robot program for realizing the work content to be performed in each process.
  • This robot program is generated according to each process plan based on known technology using predetermined information (not shown) regarding the placement of robots in the cell.
  • the robot program is generated by the work plan generation unit 114 using, for example, information about the arrangement pattern of cells in the factory (for example, information having predetermined parameter values such as the position, posture, and movement speed of the robot). be done.
  • the work content corresponding to the work plan ID 222b is registered in predetermined information (not shown) stored in the storage unit 120 in advance.
  • FIG. 9 is a diagram showing an example of the production plan 223.
  • the product ID 223a of the production plan is information for identifying the product.
  • the part ID 223b is information for identifying the part.
  • the process ID 223c is information for identifying a process.
  • the production resource ID 223d is information for identifying production resources.
  • the date and time 223e is information indicating the execution date and time of a predetermined process, such as assembling the part of the corresponding part ID 223b, in the production of the product identified by the associated product ID 223a.
  • the scheduled start time 223f is information indicating the scheduled start time of the process identified by the associated process ID 223c.
  • the scheduled end time 223g is information indicating the scheduled end time of the process.
  • the actual production information 224 in the storage unit 220 is common information with the actual production information 121 stored in the storage unit 120 of the first production planning device 100, and is produced according to the production plan. updated sequentially.
  • the communication section 250 is a functional section that performs information communication with the first production planning device 100 or the external device 300 .
  • FIG. 10 is a flowchart showing an example of production planning processing.
  • the first production planning device 100 executes the processing of steps S010 to S050
  • the second production planning device 200 executes the processing of steps S060 to S100.
  • the production planning process is started when a process execution instruction is received from the user via the input unit 130 of the first production planning apparatus 100, for example.
  • the first production planning device 100 acquires various information (step S010). Specifically, the process evaluation unit 111 acquires production performance information 121 , product CAD information 122 , part shape information 123 , product amount information 124 , and factory layout information 125 from the storage unit 120 .
  • the process evaluation unit 111 calculates an evaluation index for each process based on past production results (step S020).
  • FIG. 11 is a flow diagram showing an example of process evaluation processing corresponding to step S020.
  • the process evaluation unit 111 When such processing is started, the process evaluation unit 111 repeatedly executes the processing of steps S021 to S024 below for all components of all products (loop processing 1-1 to 1-2, loop processing 2-1 ⁇ 2-2).
  • the process evaluation unit 111 identifies each component of the target product and the corresponding process based on past production results. Specifically, the process evaluation unit 111 uses the actual production information 121 to identify each component of the target product and the corresponding process ID.
  • the process evaluation unit 111 identifies similar parts similar to each component part of the product and the corresponding process ID. Specifically, the process evaluation unit 111 converts the target product into a triangular mesh using the product CAD information 122 and the part shape information 123, and based on the connection relationship between the meshes and the shape characteristics and sizes of the component parts, Divide a product into its component parts. In addition, the process evaluation unit 111 identifies part IDs of parts having the same or similar shape characteristics and sizes from the part shape information 123, and identifies process IDs associated with the part IDs from the production performance information 121. .
  • the process evaluation unit 111 calculates an evaluation index for dimensional variation of each component based on past production results (step S022). Specifically, the process evaluation unit 111 uses predetermined information (not shown) in which, for example, the component ID and the dimension of the component are registered in association with the dimension of the specified component at the time of past production. to identify. In addition, the process evaluation unit 111 obtains the standard deviation of the dimensional variation, and calculates the standard deviation of the dimensional variation and the constants UTL (upper limit of tolerance of dimensional variation) and LTL (lower limit of tolerance of dimensional variation). , the evaluation index Cp of the dimensional variation of each component is calculated by the following formula (1). ⁇ indicates the standard deviation of the dimensional variation.
  • the process evaluation unit 111 calculates an evaluation index for variation in working time for each component from past production results (step S023). Specifically, the process evaluation unit 111 calculates the work time during the past production of the component based on the difference between the start time and the end time of the actual production information 121 . In addition, the process evaluation unit 111 obtains the standard deviation of the work time variation, and the standard deviation of the work time variation, USL (the upper limit of the tolerance of the work time variation) and LSL (the lower limit of the tolerance of the work time variation), which are constants. value), the evaluation index Tp of the working time variation of each component is calculated by the following equation (3). Note that ⁇ indicates the standard deviation of the work time variation.
  • the process evaluation unit 111 calculates the operation rate of the facility assigned to the process handling each component from past production results (step S024). Specifically, the process evaluation unit 111 identifies records in the production performance information 121 in which the part IDs and process IDs of the component parts are associated, and determines each process based on the difference between the start time and end time of the record. Calculate the operating rate of the allocated equipment.
  • process evaluation unit 111 terminates this flow after completing the process of step S024.
  • the first production planning device 100 calculates the number of alternative processes for each process based on the evaluation index (step S030).
  • FIG. 12 is a flow chart showing an example of the alternative process number calculation process corresponding to step S030.
  • the process evaluation graph generation unit 112 When such processing is started, the process evaluation graph generation unit 112 repeatedly executes the processing of steps S031 to S033 below for all products (loop processing 3-1 to 3-2).
  • step S031 the process evaluation graph generation unit 112 uses the product CAD information 122 to generate a work partial order graph.
  • FIG. 13 is a diagram showing an example of a work partial order graph.
  • the work partial order graph is composed of nodes A1 to A5 indicating product component parts and arcs indicating assembly relationships, ie, partial order relationships between the nodes.
  • a node can also be defined to indicate the process of handling each component. Therefore, hereinafter, a component and a process corresponding to the component may be synonymous.
  • the process evaluation graph generation unit 112 generates a process evaluation graph (step S032). Specifically, the process evaluation graph generation unit 112 calculates arc attribute values for three attributes: "sum of evaluation indices for dimensional variation”, “sum of evaluation indices for work time variation”, and “sum of equipment operating rates”. Calculate In addition, the process evaluation graph generation unit 112 clusters arcs whose attribute values are equal to or greater than a predetermined reference value for each attribute.
  • the process evaluation graph generation unit 112 calculates the attribute value of arcs for the "sum of evaluation indices of dimensional variation" among the attributes, and clusters the arcs with the attribute value equal to or greater than the reference value. Specifically, the process evaluation graph generation unit 112 assigns an evaluation index of dimensional variation of the corresponding component to each node of the generated work partial order graph. In addition, the process evaluation graph generator 112 calculates the sum of the evaluation indices assigned to the nodes at both ends, that is, the sum of the evaluation indices of the dimensional variations in the components at both ends, as the attribute value of the arc between the two nodes.
  • the process evaluation graph generation unit 112 compares the calculated attribute value of arcs with a predetermined reference value, and clusters arcs equal to or greater than the reference value.
  • the node at both ends of the clustered arc, the process (component part) that has a large degree of dimensional variation and is likely to cause problems, and the process related to that process, which affects when a problem occurs are associated by the clustered arcs.
  • the process evaluation graph generation unit 112 also clusters the arcs with respect to the attributes of "sum of evaluation indexes of work time variation" and "sum of facility operation rates” by a similar method.
  • process evaluation graph generation unit 112 generates a process evaluation graph by calculating the sum of the values aggregated for each attribute and assigning it to each corresponding node as an alternative process number reference value.
  • process evaluation graph generation unit 112 may generate the process evaluation graph using at least one attribute among the attributes of the three arcs, and it is not essential to use all three attributes.
  • step S033 the process plan generation unit 113 repeatedly executes the processing of step S033 below for all component parts of the product (loop processing 4-1 to 4-2).
  • step S033 the process plan generation unit 113 uses the process evaluation graph to calculate the number of alternative processes for the process corresponding to the node. Specifically, the process plan generation unit 113 calculates the number of alternative processes for each node according to the ratio of the reference value for the number of alternative processes for each node to the average value of CNi for all nodes. calculate.
  • the first production planning device 100 generates a plurality of process plans and corresponding work plans (step S040).
  • the method of generating the process plan and work plan is not particularly limited, an example thereof is shown below.
  • the process plan generation unit 113 identifies component IDs of component parts corresponding to the process and parts similar thereto from the component shape information 123, and identifies production resources associated with these component IDs as production result information 121. Identify from
  • the process plan generation unit 113 sets the specified production resources as production resource candidates for the process, and selects the number of production resource candidates according to the total number of alternative processes and basic equipment calculated in step S030. Allocate to the process a production resource candidate that is available and has a shorter working time for the process.
  • the process plan generation unit 113 performs the same processing for all component parts in all target products, so that for each process corresponding to each component part, the number of production resources corresponding to the number of alternative processes is generated for each product. Generate multiple process plans with candidate allocation.
  • the process plan generation unit 113 generates a work plan in which the work ID associated with the process, the work plan ID indicating the work content, and the work time are associated with each other for each generated process plan.
  • the method of generating the work plan based on the process plan is not particularly limited, and any known technique may be used.
  • the process plan generation unit 113 generates a plurality of sets of processes and facilities in which the number of facilities (module groups) corresponding to the calculated total number of alternative processes and the number of basic facilities is assigned to the corresponding process. Generate.
  • the work plan generation unit 114 estimates the work time based on the layout of the equipment (module group) within the cell in the factory layout, the operation rule, and the like.
  • the process plan generation unit 113 identifies a predetermined number of sets of processes and equipment that reduce the work time in the cell, and generates a plurality of process plans in consideration of the work order of all component parts in all products. .
  • the generated process plan includes the equipment configuration of the production line indicated by the equipment types and the number of equipment used in the production line.
  • the work plan generation unit 114 generates a work plan in which each process included in the process plan is associated with the work time of the equipment in the cell for each generated process plan.
  • the process plan generation unit 113 extracts the number of facilities (module group candidates) corresponding to the total number of the number of alternative processes and the number of basic facilities for each process.
  • the work plan generation unit 114 calculates the work time in consideration of the arrangement and orientation of each module group candidate in the cell and the operation rule.
  • the process plan generation unit 113 identifies a predetermined number of module group candidates and layout plans that reduce the work time in the cell in units of module group candidates.
  • the process plan generation unit 113 generates a plurality of process plans in which the identified module group candidates are assigned to corresponding processes.
  • the work plan generation unit 114 generates a work plan in which a work ID corresponding to each process included in the generated process plan is associated with the work time of the module group used for the process.
  • if necessary information for example, component attribute information, module group specification information, module specification information, module operation pattern information, layout information, etc.
  • necessary information for example, component attribute information, module group specification information, module specification information, module operation pattern information, layout information, etc.
  • the production plan generation unit 115 generates a production plan using a plurality of process plans and work plans, and at the same time optimizes the configuration of the production line (step S050). Specifically, the production plan generation unit 115 uses the generated process plan 221 and work plan 222, the product amount information 124, the factory layout information 125, etc., for all components of all products, to calculate the production throughput is maximized and the cell configuration change cost is below the reference value, generating an optimized production plan using a meta-heuristic method such as MIP (Mixed Integer Programming) Solver or GA (Genetic Algorithm), Allocate cells to each process and calculate the number of cells. Note that the cell configuration change cost may be stored in the storage unit 120 in advance.
  • MIP Mated Integer Programming
  • GA Genetic Algorithm
  • the production plan generating unit 115 performs the processing of step S050, the generated production plan 223 and a plurality of process plans (in this case, a plurality of process plans not related to the generated production plan) (including alternative process plans) 221 and work plans 222 corresponding to each process plan 221 are sent to the second production planning device 200 .
  • the second production planning device 200 executes product production based on the acquired production plan 223 (step S060).
  • the manufacturing instruction unit 211 uses the work plan 222 corresponding to the production plan 223 via the communication unit 250 to issue manufacturing instructions to each piece of equipment in the factory, thereby executing the production of the product. do.
  • the manufacturing instruction unit 211 uses the robot program linked to the work plan 222 corresponding to the production plan 223 to update the operation program of each piece of equipment in the factory. ensure that products are manufactured in accordance with
  • the production plan update timing determination unit 212 determines whether or not the timing for reviewing the configuration of the production line or the timing for drafting the production plan has arrived (step S070).
  • step S070 the production plan update timing determination unit 212 returns the process to step S010. In this case, the production plan update timing determination unit 212 transmits an instruction request regarding drafting of the production plan to the first production planning device 100 via the communication unit 250 . On the other hand, if it is determined that none of the times has been reached (No in step S070), the production plan update timing determination unit 212 shifts the process to step S080.
  • step S080 the production line analysis unit 213 analyzes whether or not a production fluctuation event has occurred based on the actual production results. Specifically, the production line analysis unit 213 compares the production performance information 121, which is updated as the product is manufactured, with the production plan 223, and determines whether the production of the product is behind the production plan 223. Analyze whether or not The production line analysis unit 213 also analyzes whether or not error information indicating a failure is output from each piece of equipment via the communication unit 250 .
  • the production line analysis unit 213 determines whether or not to re-plan the production plan (step S090). Specifically, when the production line analysis unit 213 re-formulates the production plan when there is a delay of a predetermined threshold or more in the production result with respect to the production plan 223 or when error information is output from the equipment. judge.
  • step S090 the production line analysis unit 213 returns the process to step S060.
  • step S100 the production line analysis unit 213 shifts the process to step S100.
  • step S100 the production plan re-planning unit 214 uses the plurality of process plans 221 acquired from the first production planning device 100 and the work plans 222 corresponding to each process plan 221 to re-plan the production plan. (re-drafting).
  • the production plan re-planning unit 214 uses a plurality of process plans 221, corresponding work plans 222, and the production volume information 124, etc., to maximize production throughput, minimize delivery delays, etc.
  • KPI Key Performance Indicator
  • re-planning of the optimized production plan by a meta-heuristic method such as MIP (Mixed Integer Programming) Solver or GA (Genetic Algorithm), and , assign cells to each process.
  • the production planning re-drafting unit 214 returns the process to step S060.
  • the manufacturing instruction unit 211 issues manufacturing instructions to each piece of equipment based on a robot program linked to the revised production plan and the corresponding work plan.
  • process plans, work plans, and production plans can be updated in a short time in response to production fluctuation events, and it is possible to flexibly respond to production fluctuations.
  • the first production planning device generates in advance a plurality of process plans including alternative process plans and work plans corresponding to each process plan, and when a production fluctuation event occurs in a factory, If this occurs, a production plan that optimizes a predetermined KPI related to productivity such as production throughput is re-planned using these multiple process plans and work plans, and each facility is redesigned based on the corresponding work plan production instructions for Therefore, according to the production planning system, it is possible to update the production plan without requiring manual labor, and it is possible to realize flexible production in response to production fluctuations.
  • the process evaluation index is used to quantitatively evaluate the dimensional variation of the component parts and the work time variation, and the processes and processes that are likely to cause problems (for example, work delays and rework) can be evaluated. More alternative processes (equipment allocations) can be created for sensitive processes.
  • the first production planning device it is possible to quantitatively evaluate the equipment utilization rate and create more alternative processes (equipment allocation) for processes that use equipment with a high utilization rate.
  • equipment utilization rate As a result, a process that uses equipment with a relatively low operating rate can be created as an alternative process, so even if a problem occurs in equipment with a high operating rate, it is possible to suppress the occurrence of work delays.
  • multiple process plans including alternative process plans, work plans (including robot programs), and production plans are generated by the first production planning device placed in the cloud environment.
  • a second production planning device placed in an edge environment such as a factory re-formulates the production plan using the alternative process plan and the corresponding work plan. Therefore, even if a problem occurs in the cloud environment and the first production planning device cannot be used, production fluctuations can be handled by the second production planning device in the edge environment, making it possible to continue manufacturing products. .
  • a plurality of second production planning devices 200 may be provided, and the first production planning device 100 transmits a plurality of process plans 221 to the plurality of second production planning devices 200 and corresponding work plans. 222 and the production plan 223 may be generated at the same time.
  • the second production planning device 200 may have each information in the processing section and the storage section provided in the first production planning device 100. .
  • the second production planning device 200 in the edge environment instead of the first production planning device 100, the second production planning device 200 in the edge environment generates a plurality of process plans 221, work plans 222 and production plans 223, and creates such production plans 223 and work plans 222. It suffices that products are produced by giving manufacturing instructions to each facility using the system.
  • the first production planning device 100 may have each information in the processing section and the storage section provided in the second production planning device 200. .
  • the first production planning device 100 in the cloud environment is connected to each facility via the communication unit 150, and the production of the product based on the production plan 223 and the work plan 222.
  • the first production planning device 100 uses a plurality of process plans 221 and work plans 222 to re-formulate a production plan in response to the occurrence of a production fluctuation event.
  • a production planning system includes a first production planning device 100 according to the second modified example and a second production planning device 200 according to the first modified example. They may coexist. That is, a plurality of process plans 221 and a work plan 222 are used to generate a production plan 223, and when a production fluctuation event occurs, a substitute process plan 221 and a corresponding work plan 222 are used to generate the production plan 223.
  • a production planning apparatus having the same configuration capable of re-planning may coexist in the cloud environment and the edge environment.
  • the process plan, the work plan and the production plan can be updated in a short time in response to the production fluctuation event, and the production fluctuation can be flexibly dealt with. can be done.
  • FIG. 14 is a diagram showing an example of the hardware configuration of the first production planning device 100.
  • the first production planning device 100 includes an input device 410, a display device 420, a processing device 430, a main storage device 440, an auxiliary storage device 450, a communication device 460, and electrically connecting them. and a bus 470 interconnecting to the .
  • the input device 410 is an input device such as a touch panel, keyboard, or mouse.
  • the display device 420 is a display device such as a liquid crystal display or an organic display.
  • the processing device 430 is, for example, a CPU (Central Processing Unit).
  • the main memory device 440 is a memory device such as RAM (Random Access Memory) or ROM (Read Only Memory).
  • the auxiliary storage device 450 is a non-volatile storage device such as a so-called hard disk drive, SSD (Solid State Drive), or flash memory that can store digital information.
  • SSD Solid State Drive
  • flash memory that can store digital information.
  • the communication device 460 is a wired communication device that performs wired communication via a network N cable, or a wireless communication device that performs wireless communication via an antenna.
  • the processing unit 110 of the first production planning device 100 is implemented by a program that causes the processing device 430 to perform processing.
  • This program is stored in the main storage device 440 or the auxiliary storage device 450 , loaded onto the main storage device 440 upon execution of the program, and executed by the processing device 430 .
  • the input unit 130 is implemented by the input device 410 .
  • the output unit 140 is realized by the display device 420 .
  • Storage unit 120 is implemented by main storage device 440, auxiliary storage device 450, or a combination thereof.
  • the communication unit 150 is implemented by the communication device 460 .
  • Hardware for realizing each of the processing unit 210, the input unit 230, the output unit 240, the storage unit 220 and the communication unit 250 of the second production planning device 200 is the same as that of the first production planning device 100. be.
  • part or all of the configurations, functions, processing units, processing means, etc. of the first production planning device 100 and the second production planning device 200 may be implemented as hardware by designing, for example, an integrated circuit. It can also be realized with clothing.
  • the above configurations and functions may be realized by software by a processor interpreting and executing a program for realizing each function.
  • Information such as programs, tables, and files that implement each function can be stored in storage devices such as memories, hard disks, and SSDs, or recording media such as IC cards, SD cards, and DVDs.
  • the present invention is not limited to the above-described embodiments and modifications, and includes various modifications within the scope of the same technical idea.
  • the above-described embodiments have been described in detail in order to explain the present invention in an easy-to-understand manner, and are not necessarily limited to those having all the described configurations.
  • it is possible to replace part of the configuration of one embodiment with the configuration of another embodiment and it is also possible to add the configuration of another embodiment to the configuration of one embodiment.
  • control lines and information lines indicate those that are considered necessary for the explanation, and not all the control lines and information lines are necessarily indicated on the product. In reality, it can be considered that almost all configurations are interconnected.
  • DESCRIPTION OF SYMBOLS 1000 ... Production planning system, 100... First production planning apparatus, 110... Processing part, 111... Process evaluation part, 112... Process evaluation graph generation part, 113... Process plan Generation unit 114 Work plan generation unit 115 Production plan generation unit 120 Storage unit 121 Actual production information 122 Product CAD information 123 Parts shape information, 124... production amount information, 125... factory layout information, 130... input section, 140... output section, 150... communication section, 200...
  • second production planning device 210...Processing unit 211...Manufacturing instruction unit 212...Production plan update timing determination unit 213...Production line analysis unit 214...Production plan re-planning unit 220...Storage Section 221 Process plan 222 Work plan 223 Production plan 224 Actual production information 230 Input unit 240 Output unit 250 Communication Part 300 External Device 410 Input Device 420 Display Device 430 Processing Device 440 Main Storage Device 450 Auxiliary Storage Device 460 Communication device, 470... bus, N... network

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Strategic Management (AREA)
  • Quality & Reliability (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Theoretical Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

生産変動事象に対して工程計画、作業計画および生産計画を短時間で更新し、生産変動にフレキシブルに対応することができる。 製品の生産工程に関する工程計画であって、代替の工程計画を含む複数の工程計画を生成する工程計画生成部と、各々の前記工程計画に対応する作業計画を生成する作業計画生成部と、複数の前記工程計画と、前記作業計画と、を用いて生産計画を生成する生産計画生成部と、生産変動事象の発生時に複数の前記工程計画および前記作業計画を用いて生産計画を再立案する生産計画再立案部と、を備える。

Description

生産計画装置、生産計画システムおよび生産計画方法
 本発明は、生産計画装置、生産計画システムおよび生産計画方法に関する。本発明は2021年7月30日に出願された日本国特許の出願番号2021-125953の優先権を主張し、文献の参照による織り込みが認められる指定国については、その出願に記載された内容は参照により本出願に織り込まれる。
 特許文献1は、製造システムに関し、「生産統括措置は、サーバから再計画の実施条件が成立したことの判断に応じて再計画が指示された場合は、生産シミュレータを用いて生産計画を再計画し、再計画した生産計画を工場の各生産設備に割当てる。これにより、計画遅れを生じた場合であっても以後の生産計画に影響を与えることなく最適な状態に保つことが可能となる。」と記載されている。
特開2020-98541号公報
 工場において、生産性の分析に基づく品種切替や設備故障などの生産変動事象が発生した場合、問題解決のための対策を立案し、この対策に基づいて工程計画、作業計画および生産計画を更新する必要がある。
 一方で、このような対策の立案や生産計画などの更新は、工場の生産性の稼働データに基づいて工場の生産管理者や生産技術者による人手作業が必要となるため、対策等の立案期間中は生産性が阻害され、生産変動に対してフレキシブルに対応することが困難になる、という課題がある。
 なお、特許文献1には、問題が生じた際に生産シミュレータを用いて生産計画を再計画する技術が開示されている。しかしながら、同文献の生産システムでは、生産計画のみを再計画し、工程計画や作業計画の再計画が行われない。すなわち、特許文献1の生産システムでは、問題に対して工程計画や作業計画を再計画せずに生産計画の再計画のみで対応するため、対応範囲が限定的となり、結果的に生産計画の遅延などの問題が生じる可能性がある。
 本発明は、上記課題に鑑みてなされたものであり、生産変動事象に対して工程計画、作業計画および生産計画を短時間で更新し、生産変動にフレキシブルに対応することを目的とする。
 本願は、上記課題の少なくとも一部を解決する手段を複数含んでいるが、その例を挙げるならば、以下のとおりである。上記の課題を解決する本発明の一態様に係る生産計画装置は、製品の生産工程に関する工程計画であって、代替の工程計画を含む複数の工程計画を生成する工程計画生成部と、各々の前記工程計画に対応する作業計画を生成する作業計画生成部と、複数の前記工程計画と、前記作業計画と、を用いて生産計画を生成する生産計画生成部と、生産変動事象の発生時に複数の前記工程計画および前記作業計画を用いて生産計画を再立案する生産計画再立案部と、を備える。
 本発明によれば、生産変動事象に対して工程計画、作業計画および生産計画を短時間で更新し、生産変動にフレキシブルに対応することができる。
本実施形態に係る生産計画システムの概略構成の一例を示した図である。 生産実績情報の一例を示した図である。 製品CAD情報の一例を示した図である。 部品形状情報の一例を示した図である。 生産物量情報の一例を示した図である。 工場レイアウト情報の一例を示した図である。 工程計画の一例を示した図である。 作業計画の一例を示した図である。 生産計画の一例を示した図である。 生産計画処理の一例を示したフロー図である。 工程評価処理の一例を示したフロー図である。 代替工程数算出処理の一例を示したフロー図である。 作業半順序グラフの一例を示した図である。 第一の生産計画装置のハードウェア構成の一例を示した図である。
 以下、本発明の実施形態について図面を用いて説明する。
 図1は、本実施形態に係る生産計画システム1000の概略構成の一例を示した図である。図示するように、生産計画システム1000は、第一の生産計画装置100と、第二の生産計画装置200と、を有している。また、第一の生産計画装置100と、第二の生産計画装置200とは、例えばインターネット等の公衆網やLAN(Local Area Network)あるいはWAN(Wide Area Network)などのネットワークNを介して相互通信可能に接続されている。
 また、第一の生産計画装置100および第二の生産計画装置200は、ネットワークNを介して、これらの装置に対する処理の実行指示や各装置の処理に用いられる情報を送信するために使用される外部装置300にも通信可能に接続されている。
 第一の生産計画装置100は、工場の生産ラインで製造される製品の生産計画を立案する装置である。第一の生産計画装置100は、例えばクラウド環境に置かれたサーバ装置により実現される。また、第二の生産計画装置200は、第一の生産計画装置100から取得した生産計画を用いて、工場の生産ラインを構成する各設備に対して製品の製造指示を行う装置である。第二の生産計画装置200は、例えば工場などのエッジ環境に置かれたサーバ装置により実現される。
 第一の生産計画装置100は、生産変動事象の発生にフレキシブルに対応するため、予め代替工程計画を含む複数の工程計画と、各々の工程計画に対応する作業計画と、を生成し、これらを用いて生産計画を立案する。また、第一の生産計画装置100は、生産計画と、代替工程計画を含む複数の工程計画と、各工程計画に対応する作業計画と、を第二の生産計画装置200に送信する。
 第二の生産計画装置200は、工場の生産ライン状況に応じて生産変動事象が発生したか否かを分析し、生産計画の再立案を行うと判定した場合、第一の生産計画装置100から取得した複数の工程計画と、それらに対応する作業計画と、を用いて生産計画の再立案を行い、再立案した生産計画に基づいて各設備に対して製造指示を行う。
 以下、第一の生産計画装置100および第二の生産計画装置200の各機能構成の一例について説明する。
 図1に示すように、第一の生産計画装置100は、処理部110と、記憶部120と、入力部130と、出力部140と、通信部150と、を有している。
 処理部110は、第一の生産計画装置100で行われる様々な処理を実行する機能部である。具体的には、処理部110は、工程評価部111と、工程評価グラフ生成部112と、工程計画生成部113と、作業計画生成部114と、生産計画生成部115と、を有している。
 工程評価部111は、対象製品を構成する構成部品の作業工程を評価する機能部である。具体的には、工程評価部111は、構成部品(構成部品の類似部品を含む)の寸法ばらつきや作業時間ばらつきの評価指数(工程評価指数)を算出する。また、工程評価部111は、構成部品(構成部品の類似部品を含む)を扱う工程で使用される設備の稼働率を算出する。
 工程評価グラフ生成部112は、製品の作業半順序関係を示すグラフ(以下では、「作業半順序グラフ」という場合がある)を用いて、寸法ばらつき等の評価指数に基づく代替工程数基準値を算出する。また、工程評価グラフ生成部112は、代替工程数基準値を対応する構成部品あるいは工程を示すノードに対して付与した工程評価グラフを生成する。
 工程計画生成部113は、工程計画を生成する機能部である。具体的には、工程計画生成部113は、代替工程数基準値に基づき、対応する工程の代替工程数を算出する。また、工程計画生成部113は、代替工程数に応じた数の設備を割り付けた各工程と設備との組を用いて工程計画(代替工程計画を含む)を生成する。
 作業計画生成部114は、工程計画の各々に対応する作業計画を生成する機能部である。
 生産計画生成部115は、工程計画および作業計画を用いて生産計画を生成する機能部である。
 記憶部120は、様々な情報を記憶する機能部である。具体的には、記憶部120は、生産実績情報121と、製品CAD(Computer-Aided Design)情報122と、部品形状情報123と、生産物量情報124と、工場レイアウト情報125と、を有している。
 図2は、生産実績情報121の一例を示した図である。生産実績情報121は、過去の生産実績に関する情報である。なお、生産実績情報121の製品ID121aは、製品を識別するための情報である。部品ID121bは、部品を識別するための情報である。工程ID121cは、工程を識別するための情報である。生産リソースID121dは、生産リソースを識別するための情報である。日時121eは、対応付けられている製品ID121aにより識別される製品の生産において、例えば対応する部品ID121bの部品を組み付け等する所定工程の実施日時を示す情報である。着手時間121fは、対応付けられている工程ID121cにより識別される工程の着手時間を示す情報である。終了時間121gは、かかる工程の終了時間を示す情報である。
 このような生産実績情報121は、製品ID121aおよび部品ID121bで特定される対象について工程ID121cで特定される工程が終了すると、かかる対象に関する情報が登録されて更新される。
 図3は、製品CAD情報122の一例を示した図である。製品CAD情報122には、構成部品の作業半順序関係およびその他の属性情報を含む情報が含まれている。
 図4は、部品形状情報123の一例を示した図である。部品形状情報123は、製品を構成する構成部品の形状に関する情報である。なお、部品形状情報123の部品ID123aは、部品を識別するための情報である。部品名123bは、部品の名称を示す情報である。形状特性123cは、例えば円筒や矩形あるいは円柱などの部品の形状的特徴を示す情報である。幅123d、長さ123e、径123fおよび重量123gは各々、部品の幅、長さ、径および重量を示す情報である。
 図5は、生産物量情報124の一例を示した図である。生産物量情報124は、生産される製品あるいは部品の物量に関する情報である。なお、生産物量情報124の製品ID124aは、製品を識別するための情報である。また、月別生産物量124bは、所定の対象期間における対象製品あるいは構成部品の生産量を示す情報である。
 図6は、工場レイアウト情報125の一例を示した図である。工場レイアウト情報125は、設備を配置するための工場内におけるエリア(セル)やコンベアなどの位置を示す情報である。
 なお、記憶部120内の各情報は、予め記憶部120に格納されていなくとも良く、第一の生産計画装置100における処理の実行時に外部装置300から取得されても良い。
 図1に戻って説明する。入力部130は、第一の生産計画装置100が備える入力装置を介して、オペレータからの指示や情報の入力を受け付ける機能部である。また、入力部130は、通信部150を介して第二の生産計画装置200または外部装置300からの指示や情報の入力を受け付ける。
 出力部140は、表示情報を生成し、第一の生産計画装置100あるいは第二の生産計画装置200および外部装置300が備える表示装置(ディスプレイ)に表示情報を表示する機能部である。
 通信部150は、第二の生産計画装置200または外部装置300との間で情報通信を行う機能部である。
 以上、第一の生産計画装置100の機能構成の一例について説明した。
 また、図1に示すように、第二の生産計画装置200は、処理部210と、記憶部220と、入力部230と、出力部240と、通信部250と、を有している。
 処理部210は、第二の生産計画装置200で行われる様々な処理を実行する機能部である。具体的には、処理部210は、製造指示部211と、生産計画更新時期判定部212と、生産ライン分析部213と、生産計画再立案部214と、を有している。
 製造指示部211は、工場内の各設備に製造指示を送信する機能部である。具体的には、製造指示部211は、通信部250を介して、工場内の各設備に対して、第一の生産計画装置100で生成された生産計画に対応する作業計画に従った動作指示(製造指示)を出力することで、製品の生産を実行する。
 生産計画更新時期判定部212は、生産計画の更新時期について判定する機能部である。具体的には、生産計画更新時期判定部212は、生産ラインの構成の見直し時期または生産計画の立案時期に到達したか否かを判定する。なお、これらの時期に関する情報は予め記憶部220に格納されていれば良い。
 生産ライン分析部213は、生産ラインの状況を分析する機能部である。具体的には、生産ライン分析部213は、通信部250を介して接続されている工場内の各設備から生産ラインの状況を示す情報を取得および分析する。
 生産計画再立案部214は、生産計画を再立案する機能部である。具体的には、生産計画再立案部214は、第一の生産計画装置100から取得した工程計画と、各々の工程計画に対応する作業計画と、を用いて生産計画を再立案する。
 記憶部220は、様々な情報を記憶する機能部である。具体的には、記憶部220は、第一の生産計画装置100から取得した代替工程計画を含む工程計画221と、作業計画222と、生産計画223と、生産実績情報224と、を有している。
 図7は、工程計画221の一例を示した図である。工程計画221には、製品の製造工程に関する情報が登録されている。なお、工程計画の製品ID221aは、対象製品の識別するための情報である。工程ID221bは、工程の識別するための情報である。生産リソースID221cは、生産リソースを識別するための情報である。
 図8は、作業計画222の一例を示した図である。作業計画222には、各工程で実施される作業内容を示す情報が登録されている。なお、作業計画222の作業ID222aは、作業を識別するための情報であって、工程計画221の各工程ID221bに紐づく情報である。作業計画ID222bは、作業計画を識別するための情報であって、作業計画の内容(例えば、組付け作業など)を示すIDが登録されている。作業時間222cは、作業ID222aで特定される工程に割り付けられた設備(生産リソース)が作業計画ID222bで特定される作業内容を実行する際の作業時間を示す情報である。
 なお、作業計画ID222bには、各工程で実施される作業内容を実現するためのロボットプログラムが紐付けられて記憶部120に格納されているものとする。このロボットプログラムは、セル内におけるロボットの配置等に関する所定情報(図示せず)を用いて公知技術に基づき各工程計画に応じて生成される。具体的には、ロボットプログラムは、例えば工場内におけるセルの配置パターンに関する情報(例えば、ロボットの位置や姿勢、動作速度など所定のパラメータ値を有する情報)を用いて、作業計画生成部114により生成される。また、作業計画ID222bに対応する作業内容は、予め記憶部120に格納されている所定情報(図示せず)に登録されているものとする。
 図9は、生産計画223の一例を示した図である。生産計画223には、製品の生産計画に関する情報が登録されている。なお、生産計画の製品ID223aは、製品を識別するための情報である。部品ID223bは、部品を識別するための情報である。工程ID223cは、工程を識別するための情報である。生産リソースID223dは、生産リソースを識別するための情報である。日時223eは、対応付けられている製品ID223aにより識別される製品の生産において、例えば対応する部品ID223bの部品を組み付け等する所定工程の実施日時を示す情報である。着手予定時間223fは、対応付けられている工程ID223cにより識別される工程の着手予定の時間を示す情報である。終了予定時間223gは、かかる工程の終了予定の時間を示す情報である。
 なお、記憶部220内の生産実績情報224は、第一の生産計画装置100の記憶部120に格納されている生産実績情報121と共通の情報であって、生産計画に基づく製品の製造に伴って逐次更新される。
 また、入力部230および出力部240は、第一の生産計画装置100と同様のため、詳細な説明は省略する。
 通信部250は、第一の生産計画装置100または外部装置300との間で情報通信を行う機能部である。
 以上、第二の生産計画装置200の機能構成の一例について説明した。
 [動作の説明]
 図10は、生産計画処理の一例を示したフロー図である。後述するように、生産計画処理は、第一の生産計画装置100によりステップS010~ステップS050の処理が実行され、第二の生産計画装置200によりステップS060~ステップS100の処理が実行される。なお、生産計画処理は、例えば第一の生産計画装置100における入力部130を介して処理の実行指示をユーザから受け付けると開始される。
 処理が開始されると、第一の生産計画装置100は、各種情報を取得する(ステップS010)。具体的には、工程評価部111は、生産実績情報121と、製品CAD情報122と、部品形状情報123と、生産物量情報124と、工場レイアウト情報125と、を記憶部120から取得する。
 次に、工程評価部111は、過去の生産実績に基づき各工程の評価指数を算出する(ステップS020)。
 図11は、ステップS020に対応する工程評価処理の一例を示したフロー図である。かかる処理が開始されると、工程評価部111は、以下のステップS021~ステップS024の処理を全製品の全構成部品について繰り返し実行する(ループ処理1-1~1-2、ループ処理2-1~2-2)。
 ステップS021では、工程評価部111は、過去の生産実績に基づき、対象製品の各構成部品および対応する工程を特定する。具体的には、工程評価部111は、生産実績情報121を用いて、対象製品の各構成部品と、対応する工程IDと、を特定する。
 なお、工程評価部111は、対象製品の生産実績が生産実績情報121に含まれていない場合、当該製品の各構成部品に類似する類似部品および対応する工程IDを特定する。具体的には、工程評価部111は、製品CAD情報122および部品形状情報123を用いて対象製品を3角メッシュ化し、メッシュ間の連結関係と、構成部品の形状特性およびサイズと、に基づいて製品をその構成部品に分割する。また、工程評価部111は、かかる形状特性およびサイズが同一または類似の部品の部品IDを部品形状情報123から特定し、かかる部品IDに対応付けられている工程IDを生産実績情報121から特定する。
 なお、このような処理は、例えば特願2020-144537に記載の工程ラベリング処理と同様の方法が用いられれば良い。
 次に、工程評価部111は、過去の生産実績に基づき、各構成部品の寸法ばらつきの評価指数を算出する(ステップS022)。具体的には、工程評価部111は、特定した構成部品の過去生産時における寸法を、例えば構成部品の部品IDと寸法とが対応付けられて登録されている所定情報(図示せず)を用いて特定する。また、工程評価部111は、かかる寸法のばらつきの標準偏差を求め、当該寸法ばらつきの標準偏差と、定数であるUTL(寸法ばらつきの公差上限値)およびLTL(寸法ばらつきの公差下限値)とを用いて、以下の式(1)により各構成部品の寸法ばらつきの評価指数Cpを算出する。なお、σは寸法ばらつきの標準偏差を示す。
Figure JPOXMLDOC01-appb-M000001
 なお、工程評価部111は、前述の所定情報を用いて寸法ばらつきの平均値を求め、以下の式(2)により各構成部品の寸法ばらつきの評価指数Cpkを算出しても良い。なお、T=(UTL-LTL)/2であり、μは寸法ばらつきの平均値を示す。
Figure JPOXMLDOC01-appb-M000002
 次に、工程評価部111は、過去の生産実績から各構成部品の作業時間のばらつきの評価指数を算出する(ステップS023)。具体的には、工程評価部111は、構成部品の過去生産時における作業時間を、生産実績情報121の着手時間および終了時間の差分に基づき算出する。また、工程評価部111は、かかる作業時間のばらつきの標準偏差を求め、当該作業時間ばらつきの標準偏差と、定数であるUSL(作業時間ばらつきの公差上限値)およびLSL(作業時間ばらつきの公差下限値)とを用いて、以下の式(3)により各構成部品の作業時間ばらつきの評価指数Tpを算出する。なお、σは作業時間ばらつきの標準偏差を示す。
Figure JPOXMLDOC01-appb-M000003
 なお、工程評価部111は、生産実績情報121を用いて作業時間ばらつきの平均値を求め、以下の式(4)により各構成部品の作業時間ばらつきの評価指数Tpkを算出しても良い。なお、S=(USL-LSL)/2であり、εは作業時間ばらつきの平均値を示す。
Figure JPOXMLDOC01-appb-M000004
 次に、工程評価部111は、過去の生産実績から各構成部品を取り扱う工程に割り付けられた設備の稼働率を算出する(ステップS024)。具体的には、工程評価部111は、構成部品の部品IDおよび工程IDが対応付けられている生産実績情報121のレコードを特定し、かかるレコードの着手時間および終了時間の差分に基づき各工程に割り付けられた設備の稼働率を算出する。
 また、工程評価部111は、ステップS024の処理を終えると、本フローを終了する。
 図10に戻って説明する。次に、第一の生産計画装置100は、評価指数に基づき各工程の代替工程数を算出する(ステップS030)。
 図12は、ステップS030に対応する代替工程数算出処理の一例を示したフロー図である。かかる処理が開始されると、工程評価グラフ生成部112は、以下のステップS031~ステップS033の処理を全製品について繰り返し実行する(ループ処理3-1~3-2)。
 ステップS031では、工程評価グラフ生成部112は、製品CAD情報122を用いて、作業半順序グラフを生成する。
 図13は、作業半順序グラフの一例を示した図である。図示するように、作業半順序グラフは、製品の構成部品を示すノードA1~A5と、各ノード間の組付け関係すなわち半順序関係を示すアークと、から構成されている。なお、ノードは、各構成部品を取り扱う工程を示すものとして定義することも可能である。そのため、以下では、構成部品と、かかる構成部品に対応する工程とを同義として説明する場合がある。
 次に、工程評価グラフ生成部112は、工程評価グラフを生成する(ステップS032)。具体的には、工程評価グラフ生成部112は、「寸法ばらつきの評価指数の和」、「作業時間ばらつきの評価指数の和」および「設備稼働率の和」という3つの属性についてアークの属性値を算出する。また、工程評価グラフ生成部112は、属性ごとに、属性値が所定の基準値以上となるアークをクラスタリングする。
 まず、工程評価グラフ生成部112は、属性のうち「寸法ばらつきの評価指数の和」について、アークの属性値を算出し、属性値が基準値以上のアークをクラスタリングする。具体的には、工程評価グラフ生成部112は、生成した作業半順序グラフの各ノードに、対応する構成部品の寸法ばらつきの評価指数を割り当てる。また、工程評価グラフ生成部112は、両端のノードに割り当てられた評価指数の和すなわち両端の構成部品における寸法ばらつきの評価指数の和を両ノード間のアークの属性値として算出する。
 また、工程評価グラフ生成部112は、算出したアークの属性値と所定の基準値とを比較し、かかる基準値以上のアークをクラスタリングする。これにより、クラスタリングされたアークの両端のノードであって、寸法ばらつきの度合いが大きく、問題が生じ易い工程(構成部品)と、その工程に関連する工程であって、問題が生じた際に影響を受け易い工程と、がクラスタリングされたアークにより関連付けられる。
 また、工程評価グラフ生成部112は、同様の方法により、「作業時間ばらつきの評価指数の和」および「設備稼働率の和」の属性についてもアークをクラスタリングする。
 また、工程評価グラフ生成部112は、ノードiについて、接続されているアークの中でクラスタリングされたアークの数CNiをアークの属性ごとに集計する。具体的には、工程評価グラフ生成部112は、アークの属性ごとに、クラスタリングされたアークに接続されているノードに対してCNiを加算する。例えば、属性「寸法ばらつきの評価指数の和」の場合であって、アークxおよびアークyがクラスタリングされている場合、ノードA3のCNiはアークx=1と、アークy=1と、を加算した「2」となる。また、例えば、属性が「作業時間ばらつきの評価指数の和」の場合であって、アークxおよびアークzがクラスタリングされている場合、ノード3のCNiはアークx=1と、アークz=1と、を加算した「2」となる。また、属性「設備稼働率の和」の場合であって、アークx、アークyおよびアークzがクラスタリングされている場合、ノード3のCNiはアークx=1と、アークy=1と、アークz=1と、を加算した「3」となる。
 また、工程評価グラフ生成部112は、属性ごとに集計した値の合計を算出し、それを代替工程数基準値として対応する各ノードに付与することで工程評価グラフを生成する。
 なお、工程評価グラフ生成部112は、3つのアークの属性のうち、少なくとも1つ以上の属性を用いて工程評価グラフを生成すれば良く、3つの属性の全てを用いることは必須ではない。
 次に、工程計画生成部113は、以下のステップS033の処理を製品の全構成部品について繰り返し実行する(ループ処理4-1~4-2)。
 ステップS033では、工程計画生成部113は、工程評価グラフを用いて、ノードに対応する工程の代替工程数を算出する。具体的には、工程計画生成部113は、全ノードのCNiの平均値に対する個々のノードの代替工程数基準値の大きさの割合いに応じて、ノードごとに対応する工程の代替工程数を算出する。
 なお、工程計画生成部113は、全ノードのCNiの平均値未満の代替工程数基準値が付与されているノードについは代替工程数を「1」とする。この場合、かかるノードに対応する工程には、設備が1つ割り付けられることになり(各工程は基本設備数=1であるため)、代替工程として他の設備は割り付けられない。
 また、工程計画生成部113は、例えば全ノードのCNiの平均値以上の代替工程数基準値が付与されているノードについては、かかる基準値の大きさの割合に応じて代替工程数=「2」~「n」を算出する。この場合、かかるノードに対応する工程には、基本設備数=1と、算出された代替工程数と、を合計した数の設備が割り付けられることになる。
 また、工程計画生成部113は、全製品の全構成部品について、各工程の代替工程数を算出すると、本フローを終了する。
 図10に戻って説明する。次に、第一の生産計画装置100は、複数の工程計画および対応する作業計画を生成する(ステップS040)。なお、工程計画および作業計画の生成方法は特に限定されないが、以下にその一例を示す。
 まず、工程計画生成部113は、工程に対応する構成部品およびこれに類似する部品の部品IDを部品形状情報123から特定し、これらの部品IDが対応付けられている生産リソースを生産実績情報121から特定する。
 また、工程計画生成部113は、特定した複数の生産リソースをかかる工程の生産リソースの候補とし、ステップS030で算出された代替工程数と基本設備数の合計数に応じた数の生産リソース候補であって、かつ、工程の作業時間がより小さくなる生産リソース候補を工程に割り付ける。
 また、工程計画生成部113は、全対象製品における全構成部品について同様の処理を行うことで、製品ごとに、各構成部品に対応する各工程に対して代替工程数に応じた数の生産リソース候補を割り付けた複数通りの工程計画を生成する。
 なお、このような工程計画の生成方法は、例えば特願2020-144537号に記載の技術が用いられれば良い。
 また、工程計画生成部113は、生成された工程計画ごとに、工程に紐づく作業IDと、作業内容を示す作業計画IDと、作業時間とを対応付けた作業計画を生成する。なお、工程計画に基づく作業計画の生成方法は特に限定されるものではなく、公知の技術が用いられれば良い。
 また、工程計画の生成方法に係る他の一例としては、例えば特願2020-030479号に記載の技術が用いられても良い。具体的には、工程計画生成部113は、算出された代替工程数と基本設備数の合計数に応じた数の設備(モジュールグループ)を対応する工程に割り付けた工程および設備の組を複数通り生成する。また、作業計画生成部114は、かかる設備(モジュールグループ)の工場レイアウトにおけるセル内での配置や動作ルール等に基づく作業時間を見積もる。また、工程計画生成部113は、セル内での作業時間がより小さくなる所定数の工程および設備の組を特定し、全製品における全構成部品の作業順序を考慮した複数の工程計画を生成する。なお、工程に対して設備を割り付けると、これに伴い各工程における必要な設備台数が決定される。そのため、生成される工程計画には、生産ラインで使用される設備種類とその台数とにより示される生産ラインの設備構成が含まれている。また、作業計画生成部114は、生成された工程計画ごとに、工程計画に含まれる各工程にセル内での設備の作業時間を対応付けた作業計画を生成する。
 より具体的には、工程計画生成部113は、各工程ごとに、代替工程数と基本設備数の合計数に応じた数の設備(モジュールグループ候補)を抽出する。また、作業計画生成部114は、セル内における各モジュールグループ候補の配置や向きおよび動作ルールを考慮した作業時間を算出する。また、工程計画生成部113は、モジュールグループ候補単位でのセル内における作業時間がより小さくなる所定数のモジュールグループ候補と配置案を特定する。また、工程計画生成部113は、特定したモジュールグループ候補を対応する各工程に割り付けた複数通りの工程計画を生成する。また、作業計画生成部114は、生成された工程計画に含まれる各工程に対し、対応する作業IDと、かかる工程に用いられるモジュールグループの作業時間とを対応付けた作業計画を生成する。
 なお、かかる方法により工程計画を生成する場合、必要情報(例えば、部品属性情報、モジュールグループ仕様情報、モジュール仕様情報、モジュール動作パターン情報およびレイアウト情報など)は予め記憶部120に格納されていれば良く、あるいは、通信部150を介して外部装置300から取得されても良い。
 次に、生産計画生成部115は、複数の工程計画と作業計画とを用いて生産計画を生成し、同時に生産ラインの構成を最適化する(ステップS050)。具体的には、生産計画生成部115は、全製品の全構成部品について、生成された工程計画221および作業計画222と、生産物量情報124や工場レイアウト情報125等と、を用いて、生産スループットが最大化され、かつ、セル構成の変更コストが基準値以下となるように、MIP(Mixed Integer Programming) SolverあるいはGA(Genetic Algorithm)等のメタヒューリスティック法により、最適化された生産計画の生成、各工程へのセルの割り付け、および、セルの台数の算出を行う。なお、セル構成の変更コストは、予め記憶部120に格納されていれば良い。
 また、生産計画生成部115は、ステップS050の処理を行うと、通信部150を介して、生成された生産計画223と、複数の工程計画(この場合、生成された生産計画に関連しない複数の代替工程計画を含む)221と、各工程計画221に対応する作業計画222と、を第二の生産計画装置200に送信する。
 次に、第二の生産計画装置200は、取得した生産計画223に基づき製品の生産を実行する(ステップS060)。具体的には、製造指示部211は、通信部250を介して、生産計画223に対応する作業計画222を用いて工場内の各設備に対して製造指示を行うことで、製品の生産を実行する。より具体的には、製造指示部211は、生産計画223に対応する作業計画222に紐付けられているロボットプログラムを用いて工場内の各設備の動作プログラムを更新することで、生産計画223に従った製品の製造が行われるようにする。
 次に、生産計画更新時期判定部212は、生産ラインの構成の見直し時期または生産計画の立案時期に到達したか否かを判定する(ステップS070)。
 そして、いずれかの時期に到達したと判定した場合(ステップS070でYes)、生産計画更新時期判定部212は、処理をステップS010に戻す。この場合、生産計画更新時期判定部212は、通信部250を介して、生産計画の立案に関する指示要求を第一の生産計画装置100に送信する。一方で、いずれの時期にも到達していないと判定した場合(ステップS070でNo)、生産計画更新時期判定部212は、処理をステップS080に移行する。
 ステップS080では、生産ライン分析部213は、生産実績に基づき生産変動事象が発生しているか否かを分析する。具体的には、生産ライン分析部213は、製品の製造に伴って逐次更新される生産実績情報121と生産計画223とを比較し、生産計画223に対して製品の製造に遅れが生じているか否か等を分析する。また、生産ライン分析部213は、通信部250を介して、各設備から故障を示すエラー情報が出力されているか否かを分析する。
 次に、生産ライン分析部213は、生産計画を再立案するか否かを判定する(ステップS090)。具体的には、生産ライン分析部213は、生産計画223に対して生産実績に所定の閾値以上の遅れが生じている場合や設備からエラー情報が出力されている場合に生産計画を再立案すると判定する。
 そして、生産計画を再立案しないと判定した場合(ステップS090でNo)、生産ライン分析部213は、処理をステップS060に戻す。一方で、生産計画を再立案すると判定した場合(ステップS090でYes)、生産ライン分析部213は、処理をステップS100に移行する。
 ステップS100では、生産計画再立案部214は、第一の生産計画装置100から取得した複数の工程計画221と、各々の工程計画221に対応する作業計画222と、を用いて生産計画の再計画(再立案)を行う。
 具体的には、生産計画再立案部214は、複数の工程計画221および対応する作業計画222と、生産物量情報124等と、を用いて、生産スループットの最大化や、納期遅延の最小化といった生産性に関する所定のKPI(Key Performance Indicator)が最大化されるように、MIP(Mixed Integer Programming) SolverあるいはGA(Genetic Algorithm)等のメタヒューリスティック法により、最適化された生産計画の再立案、および、各工程へのセルの割り付けを行う。
 また、生産計画再立案部214は、ステップS100の処理を行うと、処理をステップS060に戻す。この場合、製造指示部211は、再立案された生産計画および対応する作業計画に紐づくロボットプログラムに基づき、各設備に対して製造指示を行う。
 以上、本実施形態に係る生産計画処理について説明した。
 このような生産計画システムによれば、生産変動事象に対して工程計画、作業計画および生産計画を短時間で更新し、生産変動にフレキシブルに対応することができる。特に、生産計画システムでは、第一の生産計画装置において、予め代替工程計画を含む複数の工程計画と、各々の工程計画に対応する作業計画と、を生成しておき、工場において生産変動事象が発生した場合には、これら複数の工程計画と作業計画とを用いて、生産スループットなどの生産性に関する所定のKPIが最適化される生産計画が再立案され、対応する作業計画に基づいて各設備に対する製造指示が行われる。そのため、生産計画システムによれば、人手を要することなく生産計画を更新することが可能となり、生産変動に対してフレキシブルな生産を実現することができる。
 また、第一の生産計画装置によれば、工程評価指数を用いて、構成部品の寸法ばらつきや作業時間ばらつきを定量評価し、問題(例えば、作業遅れや作業のやり直し)が生じ易い工程やその影響を受け易い工程についてより多くの代替工程(設備の割り付け)を作成することができる。
 また、第一の生産計画装置によれば、設備稼働率を定量評価し、稼働率の高い設備を使っている工程についてより多くの代替工程(設備の割り付け)を作成することができる。これにより、相対的に低稼働率の設備を使う工程を代替工程として作成することができるため、稼働率の高い設備に不具合が生じた場合でも、作業遅延の発生を抑制することができる。
 また、生産計画システムによれば、代替工程計画を含む複数の工程計画、作業計画(ロボットプログラムを含む)および生産計画をクラウド環境に置かれた第一の生産計画装置で生成し、生産変動が生じた場合には、工場などのエッジ環境に置かれた第二の生産計画装置が代替工程計画や対応する作業計画を用いて生産計画を再立案する。そのため、クラウド環境に問題が生じ、第一の生産計画装置が使用できない状況下においてもエッジ環境にある第二の生産計画装置によって生産変動に対応でき、製品の製造を継続することが可能となる。
 なお、第二の生産計画装置200は複数あっても良く、第一の生産計画装置100は、複数の第二の生産計画装置200に対して送信する複数の工程計画221と、対応する作業計画222と、生産計画223と、を同時に生成しても良い。
 また、本発明の第一の変形例に係る生産計画システムは、第二の生産計画装置200が、第一の生産計画装置100が備える処理部および記憶部内の各情報を有していても良い。この場合、第一の生産計画装置100に代わり、エッジ環境における第二の生産計画装置200が複数の工程計画221、作業計画222および生産計画223を生成し、かかる生産計画223および作業計画222を用いて製造指示を各設備に行うことで、製品の生産が行われれば良い。
 また、本発明の第二の変形例に係る生産計画システムは、第一の生産計画装置100が、第二の生産計画装置200が備える処理部および記憶部内の各情報を有していても良い。この場合、第二の生産計画装置200に代わり、クラウド環境における第一の生産計画装置100が通信部150を介して接続される各設備に対して、生産計画223および作業計画222に基づく製品の製造指示を行う。また、生産変動事象の発生に応じて、第一の生産計画装置100が複数の工程計画221および作業計画222を用いて生産計画を再立案する。
 また、本発明の第三の変形例に係る生産計画システムは、第二の変形例に係る第一の生産計画装置100と、第一の変形例に係る第二の生産計画装置200と、が併存していても良い。すなわち、複数の工程計画221と、作業計画222と、を用いて生産計画223を生成し、生産変動事象が発生した際に代替の工程計画221と対応する作業計画222とを用いて生産計画223を再立案することが可能な同一構成の生産計画装置がクラウド環境とエッジ環境とに併存する構成であっても良い。
 このような第二の生産計画装置または第一の生産計画装置の構成によっても、生産変動事象に対して工程計画、作業計画および生産計画を短時間で更新し、生産変動にフレキシブルに対応することができる。
 次に、第一の生産計画装置100のハードウェア構成の一例について説明する。なお、第二の生産計画装置200のハードウェア構成は、第一の生産計画装置100と同様のため、詳細な説明は省略する。
 図14は、第一の生産計画装置100のハードウェア構成の一例を示した図である。図示するように、第一の生産計画装置100は、入力装置410と、表示装置420と、処理装置430と、主記憶装置440と、補助記憶装置450と、通信装置460と、これらを電気的に相互接続するバス470と、を有している。
 入力装置410は、例えばタッチパネルやキーボードあるいはマウスなどの入力デバイスである。表示装置420は、液晶ディスプレイや有機ディスプレイなどの表示デバイスである。
 処理装置430は、例えばCPU(Central Processing Unit)である。主記憶装置440は、RAM(Random Access Memory)やROM(Read Only Memory)などのメモリ装置である。
 補助記憶装置450は、デジタル情報を記憶可能ないわゆるハードディスク(Hard Disk Drive)やSSD(Solid State Drive)あるいはフラッシュメモリなどの不揮発性記憶装置である。
 通信装置460は、ネットワークNケーブルを介して有線通信を行う有線の通信装置、またはアンテナを介して無線通信を行う無線通信装置である。
 以上、第一の生産計画装置100のハードウェア構成の一例について説明した。
 このような第一の生産計画装置100の処理部110は、処理装置430に処理を行わせるプログラムによって実現される。このプログラムは、主記憶装置440あるいは補助記憶装置450に記憶され、プログラムの実行にあたって主記憶装置440上にロードされ、処理装置430により実行される。
 また、入力部130は、入力装置410により実現される。また、出力部140は、表示装置420により実現される。また、記憶部120は、主記憶装置440または補助記憶装置450あるいはこれらの組合せにより実現される。また、通信部150は、通信装置460により実現される。
 なお、第二の生産計画装置200の処理部210、入力部230、出力部240、記憶部220および通信部250の各々を実現するハードウェアは、第一の生産計画装置100の場合と同様である。
 また、第一の生産計画装置100および第二の生産計画装置200の上記の各構成、機能、処理部および処理手段等は、それらの一部または全部を、例えば集積回路で設計する等によりハードウェアで実現しても良い。また、上記構成、機能は、プロセッサがそれぞれの機能を実現するプログラムを解釈し、実行することによりソフトウェアで実現しても良い。各機能を実現するプログラム、テーブル、ファイル等の情報は、メモリやハードディスク、SSD等の記憶装置またはICカード、SDカードおよびDVD等の記録媒体に置くことができる。
 また、本発明は上記した実施形態および変形例に限定されるものではなく、同一の技術的思想の範囲内において様々な変形例が含まれる。例えば、上記した実施例は本発明を分かりやすく説明するために詳細に説明したものであり、必ずしも説明した全ての構成を備えるものに限定されるものではない。また、ある実施例の構成の一部を他の実施例の構成に置き換えることが可能であり、また、ある実施例の構成に他の実施例の構成を加えることも可能である。また、各実施例の構成の一部について、他の構成の追加、削除、置換をすることが可能である。
 また、上記説明では、制御線や情報線は、説明上必要と考えられるものを示しており、製品上必ずしも全ての制御線や情報線を示しているとは限らない。実際には殆ど全ての構成が相互に接続されていると考えて良い。
1000・・・生産計画システム、100・・・第一の生産計画装置、110・・・処理部、111・・・工程評価部、112・・・工程評価グラフ生成部、113・・・工程計画生成部、114・・・作業計画生成部、115・・・生産計画生成部、120・・・記憶部、121・・・生産実績情報、122・・・製品CAD情報、123・・・部品形状情報、124・・・生産物量情報、125・・・工場レイアウト情報、130・・・入力部、140・・・出力部、150・・・通信部、200・・・第二の生産計画装置、210・・・処理部、211・・・製造指示部、212・・・生産計画更新時期判定部、213・・・生産ライン分析部、214・・・生産計画再立案部、220・・・記憶部、221・・・工程計画、222・・・作業計画、223・・・生産計画、224・・・生産実績情報、230・・・入力部、240・・・出力部、250・・・通信部、300・・・外部装置、410・・・入力装置、420・・・表示装置、430・・・処理装置、440・・・主記憶装置、450・・・補助記憶装置、460・・・通信装置、470・・・バス、N・・・ネットワーク

Claims (11)

  1.  製品の生産工程に関する工程計画であって、代替の工程計画を含む複数の工程計画を生成する工程計画生成部と、
     各々の前記工程計画に対応する作業計画を生成する作業計画生成部と、
     複数の前記工程計画と、前記作業計画と、を用いて生産計画を生成する生産計画生成部と、
     生産変動事象の発生時に複数の前記工程計画および前記作業計画を用いて生産計画を再立案する生産計画再立案部と、を備える
    ことを特徴とする生産計画装置。
  2.  請求項1に記載の生産計画装置であって、
     前記生産工程ごとに所定の工程評価指数を算出する工程評価部をさらに備え、
     前記工程計画生成部は、
     前記工程評価指数に基づき所定の属性について前記生産工程を評価し、当該評価に基づき前記生産工程に割り付ける設備候補数を算出し、前記生産工程と、前記設備候補数に応じた数の設備候補と、の組に基づき複数の前記工程計画を生成する
    ことを特徴とする生産計画装置。
  3.  請求項2に記載の生産計画装置であって、
     前記工程評価部は、
     前記生産工程に対応する構成部品の寸法ばらつきに関する前記工程評価指数を算出する
    ことを特徴とする生産計画装置。
  4.  請求項2に記載の生産計画装置であって、
     前記工程評価部は、
     前記生産工程における作業時間のばらつきに関する前記工程評価指数を算出する
    ことを特徴とする生産計画装置。
  5.  請求項2に記載の生産計画装置であって、
     前記工程評価部は、
     前記生産工程に割り付けられた設備の稼働率を算出し、
     前記工程計画生成部は、
     前記設備の稼働率に基づき所定の属性について前記生産工程を評価し、当該評価に基づき前記生産工程に割り付ける設備候補数を算出し、前記生産工程と、前記設備候補数に応じた数の前記設備候補と、の組に基づき複数の前記工程計画を生成する
    ことを特徴とする生産計画装置。
  6.  請求項1に記載の生産計画装置であって、
     前記生産計画および前記作業計画に基づき、所定設備に対して製造指示を出力する所定の装置に対し、複数の前記工程計画、前記作業計画および前記生産計画を送信する通信部をさらに備える
    ことを特徴とする生産計画装置。
  7.  請求項6に記載の生産計画装置であって、
     前記所定の装置は、
     生産変動事象の発生時に複数の前記工程計画および前記作業計画を用いて生産計画を再立案する生産計画再立案部を有する
    ことを特徴とする生産計画装置。
  8.  請求項7に記載の生産計画装置であって、
     前記所定の装置は、
     前記生産計画と、更新された生産実績と、を用いて生産ラインの状況を分析する生産ライン分析部を有し、
     前記生産計画再立案部は
     前記生産ライン分析部による分析結果に基づいて、生産計画の再立案の必要性を判定する
    ことを特徴とする生産計画装置。
  9.  請求項1に記載の生産計画装置であって、
     前記生産計画と、更新された生産実績と、を用いて生産ラインの状況を分析する生産ライン分析部をさらに備え、
     前記生産計画再立案部は
     前記生産ライン分析部による分析結果に基づいて、生産計画の再立案の必要性を判定する
    ことを特徴とする生産計画装置。
  10.  第一の生産計画装置と、第二の生産計画装置と、を有する生産計画システムであって、
     前記第一の生産計画装置は、
     製品の生産工程に関する工程計画であって、代替の工程計画を含む複数の工程計画を生成する工程計画生成部と、
     各々の前記工程計画に対応する作業計画を生成する作業計画生成部と、
     複数の前記工程計画と、前記作業計画と、を用いて生産計画を生成する生産計画生成部と、
     複数の前記工程計画と、前記作業計画と、前記生産計画と、を前記第二の生産計画装置に送信する通信部と、を備え、
     前記第二の生産計画装置は、
     前記第一の生産計画装置から取得した前記生産計画および前記作業計画を用いて製品の製造を行う
    ことを特徴とする生産計画システム。
  11.  生産計画装置が行う生産計画方法であって、
     前記生産計画装置は、
     製品の生産工程に関する工程計画であって、代替の工程計画を含む複数の工程計画を生成する工程計画生成ステップと、
     各々の前記工程計画に対応する作業計画を生成する作業計画生成ステップと、
     複数の前記工程計画と、前記作業計画と、を用いて生産計画を生成する生産計画生成ステップと、を行う
    ことを特徴とする生産計画方法。
PCT/JP2022/020837 2021-07-30 2022-05-19 生産計画装置、生産計画システムおよび生産計画方法 WO2023007916A1 (ja)

Priority Applications (2)

Application Number Priority Date Filing Date Title
DE112022002742.8T DE112022002742T5 (de) 2021-07-30 2022-05-19 Produktionsplanungsvorrichtung, produktionsplanungssystem und produktionsplanungsverfahren
US18/570,855 US20240281733A1 (en) 2021-07-30 2022-05-19 Production planning device, production planning system, and production planning method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2021125953A JP2023020541A (ja) 2021-07-30 2021-07-30 生産計画装置、生産計画システムおよび生産計画方法
JP2021-125953 2021-07-30

Publications (1)

Publication Number Publication Date
WO2023007916A1 true WO2023007916A1 (ja) 2023-02-02

Family

ID=85086473

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2022/020837 WO2023007916A1 (ja) 2021-07-30 2022-05-19 生産計画装置、生産計画システムおよび生産計画方法

Country Status (4)

Country Link
US (1) US20240281733A1 (ja)
JP (1) JP2023020541A (ja)
DE (1) DE112022002742T5 (ja)
WO (1) WO2023007916A1 (ja)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117495045A (zh) * 2023-11-28 2024-02-02 广州宇格水淼科技有限公司 一种信息化工厂的生产控制方法、系统、设备及存储介质

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04176545A (ja) * 1990-11-08 1992-06-24 Nec Corp 製造計画作成装置
JP2013186866A (ja) * 2012-03-12 2013-09-19 Hitachi Ltd 加工工程計画装置
JP2015176239A (ja) * 2014-03-13 2015-10-05 トヨタ自動車株式会社 作業計画作成システム
JP2019032819A (ja) * 2017-06-19 2019-02-28 ザ・ボーイング・カンパニーThe Boeing Company 製造偏差に応じた製造プランの動的修正
JP2020098541A (ja) * 2018-12-19 2020-06-25 株式会社デンソー 生産システム

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7159689B2 (ja) 2018-08-20 2022-10-25 富士通株式会社 決済装置、決済方法及びプログラム
JP7324015B2 (ja) 2019-03-05 2023-08-09 健 坪井 給与プリペイドシステム
JP7440286B2 (ja) 2020-02-04 2024-02-28 株式会社三井ハイテック 積層鉄心の製造方法及び積層鉄心の製造装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04176545A (ja) * 1990-11-08 1992-06-24 Nec Corp 製造計画作成装置
JP2013186866A (ja) * 2012-03-12 2013-09-19 Hitachi Ltd 加工工程計画装置
JP2015176239A (ja) * 2014-03-13 2015-10-05 トヨタ自動車株式会社 作業計画作成システム
JP2019032819A (ja) * 2017-06-19 2019-02-28 ザ・ボーイング・カンパニーThe Boeing Company 製造偏差に応じた製造プランの動的修正
JP2020098541A (ja) * 2018-12-19 2020-06-25 株式会社デンソー 生産システム

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117495045A (zh) * 2023-11-28 2024-02-02 广州宇格水淼科技有限公司 一种信息化工厂的生产控制方法、系统、设备及存储介质

Also Published As

Publication number Publication date
US20240281733A1 (en) 2024-08-22
JP2023020541A (ja) 2023-02-09
DE112022002742T5 (de) 2024-04-11

Similar Documents

Publication Publication Date Title
US10754688B2 (en) Systems and methods of a production environment tool
Young et al. An artificial intelligence-based constraint network system for concurrent engineering
JP6758274B2 (ja) スキーマで表される必要条件を用いた自動プロセス制御ハードウェア工学
US20030236878A1 (en) Statistical method for estimating the performances of computer systems
CN109784686B (zh) 产品全生命周期管理系统及方法
WO2023007916A1 (ja) 生産計画装置、生産計画システムおよび生産計画方法
WO2022222834A1 (zh) 一种数据处理方法以及装置
JP6050980B2 (ja) 生産可能数計算装置、生産可能数計算プログラム及び記憶媒体
US11823108B1 (en) System for managing resources and scheduling, and related method and software
US9501607B1 (en) Composite views for IP blocks in ASIC designs
US20230185549A1 (en) Automatic Workflow Generation
JP2021170240A (ja) 工程編成の装置、その方法およびそのプログラム
CN108694493B (zh) 作业委托支援系统及其方法
CN114492051B (zh) 数字化车间动态重构方法、装置、设备和存储介质
US11995586B2 (en) Production planning system and production planning method
Mas et al. Concurrent conceptual design of aero-structure assembly lines
JP7039232B2 (ja) 技術情報共有システム及び技術情報共有方法
CN109871318B (zh) 一种基于软件运行网络的关键类识别方法
US20240281740A1 (en) Systems and methods for resource management and scheduling
US20230221706A1 (en) Factory Plan Device, Factory Plan System, and Factory Plan Method
Jacobs Performance quantification and simulation optimization of manufacturing flow lines
JP2018041262A (ja) コスト算出プログラム
US20140067747A1 (en) Object based method to evaluate rules
Bernstein et al. Securing, authenticating, and visualizing data-links for manufacturing enterprises
WO2021095136A1 (ja) ソフトウェア開発支援装置、ソフトウェア開発支援方法及びプログラム

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22848995

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 18570855

Country of ref document: US

WWE Wipo information: entry into national phase

Ref document number: 112022002742

Country of ref document: DE

122 Ep: pct application non-entry in european phase

Ref document number: 22848995

Country of ref document: EP

Kind code of ref document: A1