WO2022089582A1 - 一种绷弦式半刚性基板框架的胶接装配工艺方法 - Google Patents

一种绷弦式半刚性基板框架的胶接装配工艺方法 Download PDF

Info

Publication number
WO2022089582A1
WO2022089582A1 PCT/CN2021/127429 CN2021127429W WO2022089582A1 WO 2022089582 A1 WO2022089582 A1 WO 2022089582A1 CN 2021127429 W CN2021127429 W CN 2021127429W WO 2022089582 A1 WO2022089582 A1 WO 2022089582A1
Authority
WO
WIPO (PCT)
Prior art keywords
tooling
joint
frame
symmetrical
restraint
Prior art date
Application number
PCT/CN2021/127429
Other languages
English (en)
French (fr)
Inventor
徐挺
郑建虎
陈维强
沈淑康
徐伟丽
张玉生
黎昱
崔林如
Original Assignee
北京卫星制造厂有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 北京卫星制造厂有限公司 filed Critical 北京卫星制造厂有限公司
Publication of WO2022089582A1 publication Critical patent/WO2022089582A1/zh

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B11/00Connecting constructional elements or machine parts by sticking or pressing them together, e.g. cold pressure welding
    • F16B11/006Connecting constructional elements or machine parts by sticking or pressing them together, e.g. cold pressure welding by gluing

Definitions

  • the invention belongs to the technical field of frame composite material structure manufacturing, and in particular relates to a method for gluing and assembling a string stretched semi-rigid base plate frame.
  • the stretched-string semi-rigid base plate is a brand-new structural form, which is mainly to meet the power supply ( ⁇ 25kw) requirements of the new generation of ultra-large-capacity geostationary orbit satellite platforms, the weight reduction requirements of solar wings and the high deployment stiffness requirements of solar wings.
  • the stretched semi-rigid base plate is mainly composed of a stretched semi-rigid base plate frame, a stretched string positioning bracket and a Kevlar fiber woven stretched string, which are all assembled into one by adhesive bonding.
  • the stretched string semi-rigid substrate frame structure uses a rectangular tube formed by a high-modulus carbon fiber/cyanate resin composite material to form the main frame, and then stretches a high-strength fiber rope with a certain tension value on the main frame to connect with the sun. Connection of battery slices.
  • high requirements are placed on the overall flatness of the stretched semi-rigid substrate frame; High precision, which puts forward high requirements for the hole position accuracy of several key interfaces of the stretched semi-rigid substrate frame, and puts forward high requirements for the stress-free assembly of various parts.
  • the external dimensions of the single-piece stretched semi-rigid substrate frame are about (4050 ⁇ 1) mm ⁇ (2500 ⁇ 1) mm ⁇ 32 mm.
  • the stretched-string semi-rigid substrate frame consists of more than 30 square tubes, more than 30 limit beams, 9 compression point joints, L-shaped frame joints, more than 20 embedded parts, more than 200 pieces of corner pieces and other parts glued and assembled composition.
  • the commonly used method of bonding the frame of the stretched semi-rigid substrate is: after all the main beams, frame beams, reinforcing beams, limit beams, compression joints, frame joints, corner boxes, corner pieces and other parts are all set together Placed on the glue-bonding assembly tool and assembled into a substrate frame assembly by a single glue-bonding assembly.
  • This method has the following disadvantages:
  • the technical solution of the present invention is to overcome the deficiencies of the prior art, and provide a method for gluing and assembling a stretched string semi-rigid substrate frame, aiming to solve the problem of glue existing in the existing method for gluing a stretched semi-rigid substrate frame.
  • There are problems such as compact construction period, poor assembly accuracy, and large assembly stress.
  • the present invention discloses a method for gluing and assembling a stretched-string semi-rigid substrate frame, including:
  • Glue the center frame Position the compression point joints, transverse beams and longitudinal beams by gluing the assembly tooling; Glue the transverse beams and longitudinal beams through the compression point joints to form the center frame; among them, the transverse beams and The longitudinal beams are provided with horizontal and vertical mounting holes;
  • Install reinforcement beams and limit beams Position the reinforcement beam joints by gluing and assembling the tooling; insert the reinforcement beams and limit beams into the center frame according to the assembly relationship between the reinforcement beams, limit beams and the center frame. Carry out trial assembly in the horizontal and vertical installation holes set on the transverse beam and the longitudinal beam; glue the reinforcing beam and the joint of the reinforcing beam, and preliminarily fix it;
  • Glue the external frame Position the end frame joints, hinge joints, frame joints, transverse frame main beams and longitudinal frame main beams by gluing assembly tooling; connect the transverse frame main beam and longitudinal frame main beam through the end frame joints, hinges Joints and frame joints are glued and assembled to form an external frame;
  • Glue the corner box and the corner piece According to the assembly relationship, glue the corner box and the corner piece to the corresponding positions of the transverse beam, longitudinal beam, reinforcement beam, limit beam, transverse frame main beam and longitudinal frame main beam to obtain the tension. Chorded semi-rigid baseplate frame.
  • the compression point joint is a thin-walled cavity structure; before the transverse beam and the longitudinal beam are glued and assembled through the compression point
  • the bonding area of the joint is reinforced with carbon cloth to ensure good assembly during the bonding process and stable bearing during use.
  • the gluing and assembling tooling includes: tooling body, main beam symmetrical restraint tooling, main beam frame symmetrical restraint tooling, compression point joint symmetrical restraint tooling, hinge joint Symmetrical restraint tooling and outer frame symmetrical restraint tooling;
  • the tooling body is a rectangular structure, including: side I, side II, side III and side IV;
  • Main beam symmetrical restraint tooling including: main beam symmetrical restraint tooling I, main beam symmetrical restraint tooling II, main beam symmetrical restraint tooling III, main beam symmetrical restraint tooling IV, main beam symmetrical restraint tooling V and the main beam symmetry constraint tooling VI; among them, the main beam symmetry constraint tooling I, the main beam symmetry constraint tooling II and the main beam symmetry constraint tooling III are located on the first horizontal line, and the first horizontal line is the main beam frame symmetry constraint tooling II and the main beam symmetry constraint tooling II.
  • connection line of the beam frame symmetry constraint tooling IV; the main beam symmetry constraint tooling IV, the main beam symmetry constraint tooling V and the main beam symmetry constraint tooling VI are located on the second horizontal line, and the second horizontal line is the main beam frame symmetry constraint tool I and the main beam
  • connection line of the frame symmetry constraint tool V; the main beam symmetry constraint tool I and the main beam symmetry constraint tool IV are located on the first vertical line, and the first vertical line is the hinge joint symmetry constraint tool IV and the hinge joint symmetry constraint tool X.
  • connection line; the main beam symmetry constraint tooling II and the main beam symmetry constraint tooling V are located on the second vertical line, and the second vertical line is the connection line between the main beam frame symmetry constraint tooling III and the main beam frame symmetry constraint tooling VI; Beam symmetry constraint tooling III and main beam symmetry constraint tooling VI are located on the third vertical line, and the third vertical line is the connection line between hinge joint symmetry constraint tooling V and hinge joint symmetry constraint tooling IX;
  • Main beam frame symmetry constraint tooling including: main beam frame symmetry constraint tooling I, main beam frame symmetry constraint tooling II, main beam frame symmetry constraint tooling III, main beam frame symmetry constraint tooling IV, main beam frame symmetry constraint tooling V and main beam frame symmetry constraint tooling Beam frame symmetry constraint tooling VI; among them, the main beam frame symmetry constraint tooling I and the main beam frame symmetry constraint tooling II are arranged on side I at intervals, and the main beam frame symmetry constraint tooling I is located at the hinge joint symmetry constraint tooling I and the hinge joint symmetry Between the constraint tooling II, the main beam frame symmetrical constraint tooling II is located between the hinge joint symmetrical constraint tooling II and the hinge joint symmetrical constraint tooling III; the main beam frame symmetrical constraint tooling III is set on the side II, located in the hinge joint symmetrical constraint tooling IV and the hinge joint symmetry constraint tooling V; the main beam frame symmetry constraint tooling
  • Symmetrical restraint tooling for pressing point joints including: symmetrical restraining tooling for pressing point joints I, symmetrical restraining tooling for pressing point joints II, symmetrical restraining tooling for pressing point joints III, pressing point joints uniformly distributed in the rectangular structure of the tooling body Symmetric constraint tooling IV, compression point joint symmetry constraint tooling V, compression point connector symmetry constraint tooling VI, compression point connector symmetry constraint tooling VII, compression point connector symmetry constraint tooling VIII and compression point connector symmetry constraint tooling IX;
  • the compression point joint symmetrical constraint tooling I, the compression point joint symmetrical constraint tooling II and the compression point joint symmetrical constraint tooling III are located on the third horizontal line, and the third horizontal line is the hinge joint symmetrical constraint tooling III and the hinged joint symmetrical constraint tooling
  • Symmetrical constraint tooling for hinge joints including: Symmetrical constraint tooling for hinged joint I, Symmetrical constraint tooling for hinged joint II, Symmetrical constraint tooling for hinged joint III, Symmetrical constraint tooling for hinged joint IV, Symmetrical constraint tooling for hinged joint V, Symmetrical constraint tooling for hinged joint VI, Symmetrical constraining tooling for hinge joint VII, symmetrical constraining tooling for hinged joint VIII, symmetrical constraining tooling for hinged joint IX, and symmetrical constraining tooling for hinged joint X; among them, symmetrical constraining tooling for hinged joint I, tooling for symmetrical constraining of hinged joint II and tooling for symmetrical constraining of hinged joint III The interval is set on side I; the hinge joint symmetry constraint tool IV and the hinge joint symmetry constraint tool V are set on the side II at intervals; the hinge joint symmetry constraint tool VI, hinge joint symmetry constraint tool VII and hinge joint joint
  • Outer frame symmetry constraint tooling including: outer frame symmetry constraint tooling I, outer frame symmetry constraint tooling II, outer frame symmetry constraint tooling III and outer frame symmetry constraint tooling IV; among them, outer frame symmetry constraint tooling I, outer frame symmetry constraint tooling II.
  • the outer frame symmetry constraint tooling III and the outer frame symmetry constraint tooling IV are respectively arranged at the four vertex positions of the rectangular structure of the tooling body.
  • Compression point connectors including: compression point connector I, compression point connector II, compression point connector III, compression point connector IV, compression point connector V, compression point connector VI, compression point connector VII, compression point connector Tight point joint VIII and pinch point joint IX;
  • Transverse beams including: transverse beam I, transverse beam II and transverse beam III;
  • Longitudinal beams including: longitudinal beam I, longitudinal beam II and longitudinal beam III.
  • the compression point joints, the transverse beams and the longitudinal beams are positioned by the gluing assembly tooling, including:
  • the compression point joint IX is placed in the order of compression point joint symmetry constraint tooling I, compression point joint symmetry constraint tooling II, compression point joint symmetry constraint tooling III, compression point joint symmetry constraint tooling IV, compression point joint symmetry Restriction tooling V, compression point joint symmetry constraint tooling VI, compression point connector symmetry constraint tooling VII, compression point connector symmetry constraint tooling VIII, and compression point connector symmetry constraint tooling IX, and fix them to complete the adjustment of each compression point the positioning of the joint;
  • the longitudinal beam III is positioned according to the compression point joint symmetrical constraint tooling III, the compression point joint symmetrical constraint tooling VI and the compression point joint symmetrical constraint tooling IX.
  • Strengthening beam joints including: strengthening beam joint I, strengthening beam joint II, strengthening beam joint III, strengthening beam joint IV, strengthening beam joint V and strengthening beam joint VI;
  • Reinforcing beams including: reinforcing beam I and reinforcing beam II;
  • the limit beam includes: limit beam I, limit beam II, limit beam III, limit beam IV, limit beam V and limit beam VI.
  • the joints of the reinforcing beams are positioned by gluing and assembling tooling; And the limit beam is inserted into the horizontal and vertical installation holes set on the transverse beam and the longitudinal beam in the center frame respectively, and the trial assembly is carried out, including:
  • Beam symmetrical restraint tooling III, main beam symmetrical restraint tooling IV, main beam symmetrical restraint tooling V and main beam symmetrical restraint tooling VI are installed and fixed to complete the positioning of each reinforcing beam joint;
  • End frame joints including: end frame joint I, end frame joint II, end frame joint III and end frame joint IV;
  • Hinge joints including: joint joint I, joint joint II, joint joint III, joint joint IV, joint joint V, joint joint VI, joint joint VII, joint joint VIII, joint joint IX and joint joint X;
  • Frame connectors including: frame connector I, frame connector II, frame connector III, frame connector IV, frame connector V and frame connector VI.
  • the end frame joints, hinge joints, frame joints, transverse frame main beams and longitudinal frame main beams are positioned by gluing and assembling tooling, including:
  • end frame joint I Place the end frame joint I, end frame joint II, end frame joint III and end frame joint IV on the outer frame symmetry constraint tooling I, outer frame symmetry constraint tooling II, outer frame symmetry constraint tooling III and outer frame symmetry constraint tooling IV, and fix it to complete the positioning of each end frame joint;
  • hinge joint I Place hinge joint I, hinge joint II, hinge joint III, hinge joint IV, hinge joint V, hinge joint VI, hinge joint VII, hinge joint VIII, hinge joint IX and hinge joint X in sequence on the hinge joint symmetry constraint tool I.
  • Symmetrical constraint tooling for hinged joint II Symmetrical constraint tooling for hinged joint III, Symmetrical constraint tooling for hinged joint IV, Symmetrical constraint tooling for hinged joint V, Symmetrical constraint tooling for hinged joint VI, Symmetrical constraint tooling for hinged joint VII, Symmetrical constraint tooling for hinged joint VIII ,
  • the hinge joint symmetrical restraint tooling IX and the hinge joint symmetrical restraint tooling X are fixed, and the positioning of each hinge joint is completed;
  • the transverse frame main beam includes: the transverse frame main beam I and the transverse frame main beam II; wherein, the transverse frame main beam I is respectively glued with the end frame joint I, the hinge joint X, the frame joint VI, the hinge joint IX and the end frame joint IV
  • the transverse frame main beam II is glued and assembled with the end frame joint II, hinge joint IV, frame joint III, hinge joint V and end frame joint III respectively;
  • the longitudinal frame main beam includes: longitudinal frame main beam I and longitudinal frame main beam II; wherein the longitudinal frame main beam I is respectively connected with end frame joint I, hinge joint I, frame joint I, hinge joint II, frame joint II, hinge joint Joint III and end frame joint II are glued and assembled; longitudinal frame main beam II is glued and assembled with end frame joint IV, hinge joint VIII, frame joint V, hinge joint VII, frame joint IV, hinge joint VI and end frame joint III. .
  • the present invention discloses an adhesive bonding and assembling process method for a stretched string semi-rigid substrate frame, which optimizes the assembly sequence and performs a four-step bonding process for installation, which solves the problem of the existing stretched string semi-rigid substrate frame glue
  • the bonding process method has the problems of compact bonding time period, poor assembly accuracy, and large assembly stress.
  • the present invention discloses a method for gluing and assembling a string-tensioned semi-rigid substrate frame.
  • the compression point joint is a thin-walled cavity structure.
  • the area is reinforced with carbon cloth to ensure good assembly during the bonding process and stable bearing during use.
  • the present invention discloses a method for gluing and assembling a string-tensioned semi-rigid substrate frame.
  • the key interface positions with high positioning accuracy such as multiple pressing point joints and hinge joints, are constrained by three-dimensional symmetry to ensure the frame structure.
  • all external forces of the entire frame system are self-balanced.
  • the entire frame system is pressurized to ensure stress-free gluing assembly, and the product does not produce additional lateral or longitudinal displacement, thus ensuring the hinge installation hole.
  • the positional accuracy requirements of the hole at the pressing point, and at the same time reduce the product combination processing process, improve the product development efficiency and reduce the development cost.
  • FIG. 1 is an assembly schematic diagram of a stretched string semi-rigid substrate frame in an embodiment of the present invention
  • FIG. 2 is a schematic structural diagram of an adhesive bonding assembly tool in an embodiment of the present invention
  • Fig. 3 is the assembly schematic diagram of a kind of center frame in the embodiment of the present invention.
  • Fig. 4 is the assembly schematic diagram of a kind of reinforcement beam in the embodiment of the present invention.
  • Fig. 5 is the assembly schematic diagram of a kind of limit beam in the embodiment of the present invention.
  • Fig. 6 is the assembly schematic diagram of a kind of external frame in the embodiment of the present invention.
  • FIG. 7 is a schematic structural diagram of a main beam symmetry restraint tooling in an embodiment of the present invention.
  • FIG. 8 is a schematic structural diagram of a main beam frame symmetry restraint tooling in an embodiment of the present invention.
  • FIG. 9 is a schematic structural diagram of a compression point joint symmetrical restraint tooling in an embodiment of the present invention.
  • FIG. 10 is a schematic structural diagram of a hinge joint symmetrical restraint tool in an embodiment of the present invention.
  • FIG. 11 is a schematic structural diagram of an outer frame symmetry restraint tooling in an embodiment of the present invention.
  • FIG. 12 is a schematic structural diagram of a fastening mechanism in an embodiment of the present invention.
  • the present invention discloses a method for gluing and assembling a string-tensioned semi-rigid substrate frame.
  • the method of wrapping carbon filaments is used to control the gluing gap of each assembly position.
  • the wet carbon filaments are evenly wound on each
  • the surface of the square tube of the glued joint ensures that the circumferential glued gap between the joint and the beam is uniform, reduces the generation of glueing stress, and improves the dimensional accuracy of the frame product.
  • the present invention solves the problems of compact gluing period, poor assembly precision, and large assembly stress in the existing semi-rigid substrate frame gluing and assembling process. All performance indicators of the product meet the design and use requirements, and have successfully undergone various mechanical and thermal tests and assessments, and successfully completed the assembly and mechanical performance tests of the whole wing and the whole star.
  • the present invention discloses a method for gluing and assembling a stretched semi-rigid substrate frame, which can be realized by gluing and assembling tooling.
  • the adhesive assembly tooling may include: tooling body 1, main beam symmetry constraint tooling, main beam frame symmetry constraint tooling, compression point joint symmetry constraint tooling, hinge joint symmetry constraint tooling and outer frame symmetry constraint tooling.
  • the tooling body 1 is a rectangular structure, which may specifically include: side I11, side II12, side III13 and side IV14.
  • the main beam symmetry constraint tooling may specifically include: main beam symmetry constraint tooling I21, main beam symmetry constraint tooling II22, main beam symmetry constraint tooling III23, main beam symmetry constraint tooling IV24, main beam symmetry constraint tooling IV24, and main beam symmetry constraint tooling evenly distributed in the rectangular structure of tooling body 1 Constraint tooling V25 and main beam symmetry constraint tooling VI26; among them, main beam symmetry constraint tooling I21, main beam symmetry constraint tooling II22 and main beam symmetry constraint tooling III23 are located on the first horizontal line, and the first horizontal line is the main beam frame symmetry constraint tooling II32
  • the connection line with the main beam frame symmetry constraint tooling IV34; the main beam symmetry constraint tooling IV24, the main beam symmetry constraint tooling V25 and the main beam symmetry constraint tooling VI26 are located on the second horizontal line, and the second horizontal line is the main beam frame symmetry constraint tooling I31 and The connection line of the
  • the main beam frame symmetry constraint tooling may specifically include: main beam frame symmetry constraint tooling I31, main beam frame symmetry constraint tooling II32, main beam frame symmetry constraint tooling III33, main beam frame symmetry constraint tooling IV34, main beam frame symmetry constraint tooling V35 and Main beam frame symmetry constraint tooling VI36; wherein, the main beam frame symmetry constraint tooling I31 and the main beam frame symmetry constraint tooling II32 are arranged on the side I11 at intervals, and the main beam frame symmetry constraint tooling I31 is located at the hinge joint symmetrical constraint tooling I51 and the hinge joint Between the symmetrical restraint tooling II52, the main beam frame symmetrical restraint tooling II32 is located between the hinge joint symmetrical restraint tooling II52 and the hinge joint symmetrical restraint tooling III53; the main beam frame symmetrical restraint tooling III33 is set on the side II12, located in the hinge joint symmetrical restraint tooling Between IV54
  • the compression point joint symmetry constraint tooling may specifically include: compression point connector symmetry constraint tooling I41, compression point connector symmetry constraint tooling II42, compression point connector symmetry constraint tooling III43, compression point connector symmetry constraint tooling III43, compression point connector symmetry constraint tooling evenly distributed in the rectangular structure of the tooling body 1 Point Joint Symmetrical Constraint Tooling IV44, Pressing Point Joint Symmetrical Constraining Tooling V45, Pressing Point Joint Symmetrical Constraint Tooling VI46, Pressing Point Joint Symmetrical Constraint Tooling VII47, Pressing Point Joint Symmetrical Constraint Tooling VIII48 and Pressing Point Joint Symmetrical Constraint Tooling IX49; Among them, the compression point joint symmetry constraint tooling I41, the compression point joint symmetry constraint tooling II42 and the compression point joint symmetry constraint tooling III43 are located on the third horizontal line, and the third horizontal line is the hinge joint symmetry constraint tooling III53 and the hinge joint symmetry The connection line of
  • the hinge joint symmetrical constraint tooling may specifically include: hinge joint symmetrical constraint tooling I51, hinged joint symmetrical constraint tooling II52, hinged joint symmetrical constraint tooling III53, hinged joint symmetrical constraint tooling IV54, hinged joint symmetrical constraint tooling V55, hinged joint symmetrical constraint tooling VI56 , hinge joint symmetry constraint tooling VII57, hinge joint symmetry constraint tooling VIII58, hinge joint symmetry constraint tooling IX59 and hinge joint symmetry constraint tooling X510; among them, hinge joint symmetry constraint tooling I51, hinge joint symmetry constraint tooling II52 and hinge joint symmetry constraint tooling III53 is set on the side I11 at intervals; the hinge joint symmetrical restraint tool IV54 and the hinge joint symmetrical restraint tooling V55 are set on the side II12 at intervals; the hinge joint symmetrical restraint tooling VI56, the hinge joint symmetrical restraint tooling VII57 and the hinge joint symmetric
  • the outer frame symmetry constraint tooling may specifically include: outer frame symmetry constraint tooling I61, outer frame symmetry constraint tooling II62, outer frame symmetry constraint tooling III63, and outer frame symmetry constraint tooling IV64; among them, outer frame symmetry constraint tooling I61, outer frame symmetry constraint tooling I61, outer frame symmetry constraint tooling The tooling II62, the outer frame symmetrical restraining tooling III63 and the outer frame symmetrical restraining tooling IV64 are respectively arranged at the four vertex positions of the rectangular structure of the tooling body 1.
  • the gluing assembly process method of the stretched-string semi-rigid substrate frame realized based on the above-mentioned gluing assembly tooling may specifically include the following steps:
  • Step 101 gluing the center frame 104 : positioning the compression point joints, the transverse beams and the longitudinal beams by gluing the assembly tool;
  • both the transverse beam and the longitudinal beam are provided with transverse and longitudinal mounting holes.
  • the compression point joint is a thin-walled cavity structure; before the transverse beam and the longitudinal beam are glued and assembled through the compression point joint, carbon cloth reinforcement is performed on the glued area of the compression point joint.
  • the compression point joints may specifically include: compression point joints I1011, compression point joints II1012, compression point joints III1013, compression point joints IV1014, compression point joints V1015, compression point joints VI1016 , Compression point connector VII1017, compression point connector VIII1018 and compression point connector IX1019.
  • the transverse beams may specifically include: transverse beams I 1021 , transverse beams II 1022 and transverse beams III 1023 .
  • the longitudinal beams may specifically include: longitudinal beams I 1031 , longitudinal beams II 1032 and longitudinal beams III 1033 .
  • the specific implementation process of the above step 101 may be as follows: the compression point connector I 1011, the compression point connector II 1012, the compression point connector III 1013, the compression point connector IV 1014, the compression point connector V 1015, the compression point connector VI 1016, The compression point joint VII1017, the compression point joint VIII1018 and the compression point joint IX1019 are placed in the order in order.
  • the compression point joint symmetrical restraint tooling I41, the compression point joint symmetrical restraint tooling II42 and the compression point joint symmetrical restraint tooling III43, the transverse beam III1023 is carried out.
  • the compression point joint symmetrical restraint tooling VI46 and the compression point joint symmetrical restraint tooling IX49 are used to locate the longitudinal beam III1033.
  • Step 102 install the reinforcement beam and the limit beam: position the reinforcement beam joints by gluing the assembly tool; according to the assembly relationship between the reinforcement beam, the limit beam and the center frame 104, respectively Insert into the horizontal and vertical mounting holes provided on the transverse beam and the longitudinal beam in the center frame 104 to conduct trial assembly; glue the reinforcing beam and the joint of the reinforcing beam, and preliminarily fix it.
  • the reinforcing beam joints may specifically include: reinforcing beam joint I1131, reinforcing beam joint II1132, reinforcing beam joint III1133, reinforcing beam joint IV1134, reinforcing beam joint V1135 and reinforcing beam Connector VI1136.
  • the reinforcement beams may specifically include: reinforcement beams I 1051 and reinforcement beams II 1052 .
  • the limit beam may specifically include: limit beam I 1061 , limit beam II 1062 , limit beam III 1063 , limit beam IV 1064 , limit beam V 1065 and limit beam VI 1066 .
  • the specific implementation process of the above step 102 may be as follows: the reinforcing beam joint I 1131, the reinforcing beam joint II 1132, the reinforcing beam joint III 1133, the reinforcing beam joint IV 1134, the reinforcing beam joint V 1135 and the reinforcing beam joint VI 1136 are sequentially placed on the main beam in sequence.
  • Symmetrical restraint tooling I21, main beam symmetrical restraint tooling II22, main beam symmetrical restraint tooling III23, main beam symmetrical restraint tooling IV24, main beam symmetrical restraint tooling V25 and main beam symmetrical restraint tooling VI26 fix them to complete the joints of each reinforcing beam positioning.
  • the reinforcing beam II 1052 is placed along the main beam symmetrical restraint tooling I21, the main beam symmetrical restraint tooling II22 and the main beam symmetrical restraint tooling III23, and passes through the transverse mounting holes provided on the transverse beam and the longitudinal beam in the center frame 104.
  • the reinforcing beam I1051 is placed along the main beam symmetrical restraint tooling IV24, the main beam symmetrical restraint tooling V25 and the main beam symmetrical restraint tooling VI26, and passes through the transverse mounting holes provided on the transverse beam and the longitudinal beam in the center frame 104.
  • the limit beam I 1061, the limit beam II 1062, the limit beam III 1063, the limit beam IV 1064, the limit beam V 1065 and the limit beam VI 1066 are arranged vertically in order from left to right, and pass through the horizontal beam in the center frame 104 and the longitudinal mounting holes provided on the longitudinal beams; wherein, the limit beam I1061 is located on the left side of the longitudinal beam I1031, the limit beam II1062 and the limit beam III1063 are located between the longitudinal beam I1031 and the longitudinal beam II1032, and the limit beam IV1064 and the limit beam
  • the beam V 1065 is located between the longitudinal beam II 1032 and the longitudinal beam III 1033, and the limit beam VI 1066 is located on the right side of the longitudinal beam III 1033.
  • Step 103 gluing the outer frame 112 .
  • end frame joints, hinge joints, frame joints, transverse frame main beams and longitudinal frame main beams are positioned by gluing and assembling tooling;
  • the hinge joints and frame joints are glued together to form the outer frame 112 .
  • the end frame joints may specifically include: end frame joints I 1071 , end frame joints II 1072 , end frame joints III 1073 and end frame joints IV 1074 .
  • the hinge joints may specifically include: hinge joints I1081, hinged joints II1082, hinged joints III1083, hinged joints IV1084, hinged joints V1085, hinged joints VI1086, hinged joints VII1087, hinged joints VIII1088, hinged joints IX1089 and hinged joints X10810.
  • the frame joints may specifically include: frame joints I 1091 , frame joints II 1092 , frame joints III 1093 , frame joints IV 1094 , frame joints V 1095 and frame joints VI 1096 .
  • the specific implementation process of the above step 103 may be as follows: place the end frame joint I 1071, the end frame joint II 1072, the end frame joint III 1073 and the end frame joint IV 1074 in sequence on the outer frame symmetry constraint tool I61 and the outer frame symmetry constraint tool II 62 , Outer frame symmetry constraint tooling III63 and outer frame symmetry constraint tooling IV64, and fix them to complete the positioning of each end frame joint.
  • Place hinge joint I1081, hinge joint II1082, hinge joint III1083, hinge joint IV1084, hinge joint V1085, hinge joint VI1086, hinge joint VII1087, hinged joint VIII1088, hinged joint IX1089 and hinged joint X10810 in sequence on the hinged joint symmetry constraint tooling. I51.
  • the hinge joint symmetrical restraint tool IX59 and the hinge joint symmetrical restraint tool X510 are fixed, and the positioning of each hinge joint is completed.
  • the transverse frame main beam may specifically include: transverse frame main beam I1101 and transverse frame main beam II 1102; wherein, transverse frame main beam I1101 is respectively connected with end frame joint I1071, hinge joint X10810, frame joint VI1096, hinge joint IX1089 and The end frame joint IV1074 is glued and assembled; the transverse frame main beam II1102 is glued and assembled with the end frame joint II1072, the hinge joint IV1084, the frame joint III1093, the hinge joint V1085 and the end frame joint III1073.
  • the longitudinal frame main beams may specifically include: longitudinal frame main beams I1201 and longitudinal frame main beams II1202; wherein the longitudinal frame main beams I1201 are respectively connected with end frame joints I1071, hinge joints I1081, frame joints I1091, hinge joints II1082, frame joints II1092, The hinge joint III1083 and the end frame joint II1072 are glued and assembled; the longitudinal frame main beam II1202 is glued with the end frame joint IV1074, the hinge joint VIII1088, the frame joint V1095, the hinge joint VII1087, the frame joint IV1094, the hinge joint VI1086 and the end frame joint III1073. assembly.
  • step 104 the corner box and the corner piece 114 are glued together.
  • all corner boxes and corner pieces 114 can be glued at the corresponding positions of the transverse beam, longitudinal beam, reinforcement beam, limit beam, transverse frame main beam and longitudinal frame main beam to obtain a stretched Chorded semi-rigid baseplate frame.
  • each main beam has the same symmetrical restraint tooling structure, including: three sets of fastening mechanisms 7 .
  • the three groups of fastening mechanisms 7 are arranged in a concave shape.
  • each compression point joint has the same symmetrical restraint tooling structure, including: four sets of fastening mechanisms 7 and a compression point positioning joint pin 8 .
  • each hinge joint has the same symmetrical restraint tooling structure, including: three sets of fastening mechanisms 7 and a hinge interface positioning joint pin 9 .
  • the three groups of fastening mechanisms 7 are arranged in a concave shape, and the hinge interface positioning joint pin 9 is arranged in the center of the concave region surrounded by the three groups of fastening mechanisms 7 .
  • FIG. 10 shows that the four groups of fastening mechanisms 7 are connected in sequence at the end, and the pressing point positioning joint pin 8 is arranged in the center of the rectangle surrounded by the four groups of fastening mechanisms 7 connected in sequence.
  • each hinge joint has the same symmetrical restraint tooling structure, including: three sets of fastening mechanisms 7 and a hinge interface positioning joint pin 9 .
  • the three groups of fastening mechanisms 7 are arranged in a concave shape, and the hinge interface positioning joint pin 9 is arranged in the center of the concave region surrounded by the three groups of fastening mechanisms 7 .
  • the structure of the symmetrical restraint tooling of each outer frame is the same, including: two sets of fastening mechanisms 7 .
  • the two groups of fastening mechanisms 7 are arranged in a ⁇ shape.
  • the combination method of the fastening mechanism adopted by each constraint tooling adopts three-dimensional symmetrical constraints on the key interface positions of high positioning accuracy such as multiple compression point joints and hinge joints to ensure that the string-type semi-rigid substrate frame is glued during the bonding process.
  • the fastening mechanism 7 may specifically include: a symmetrical constraining push rod 71 , a positioning seat bracket 72 and a fastener 73 .
  • the positioning seat bracket 72 is fixed on the tool body by the fastener 73 .
  • the symmetrical restraint push rod 71 is movably connected with the positioning seat bracket 72; when the product to be assembled is installed in place, the symmetrical restraint push rod 71 is pushed bidirectionally symmetrically to realize the tightening of the symmetrical restraint push rod 71 and the to-be-assembled product as well as the assembly product itself. Stress assembly.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种绷弦式半刚性基板框架的胶接装配工艺方法,包括:胶接中心框架(104);安装加强梁和限位梁,进行试装配;胶接外部框架(112);胶接角盒与角片(114),得到绷弦式半刚性基板框架。该方法解决了现有绷弦式半刚性基板框架胶接工艺方法存在的胶接工期紧凑、装配精度差、装配应力较大等问题。

Description

一种绷弦式半刚性基板框架的胶接装配工艺方法
本申请要求于2020年10月30日提交中国专利局、申请号为202011191862.9、申请名称为“一种绷弦式半刚性基板框架的胶接装配工艺方法”的中国专利申请的优先权,其全部内容通过引用结合在本申请中。
技术领域
本发明属于框架复合材料结构制造技术领域,尤其涉及一种绷弦式半刚性基板框架的胶接装配工艺方法。
背景技术
绷弦式半刚性基板是一个全新的结构形式,主要是为适应新一代超大容量静止轨道卫星平台的电源功率(≥25kw)需求、太阳翼减重需求和太阳翼高展开刚度需求。绷弦式半刚性基板主要由绷弦式半刚性基板框架、绷弦定位支架和Kevlar纤维编织绷弦组成,并且全部通过胶粘剂胶接装配成一体。绷弦式半刚性基板框架结构采用高模量碳纤维/氰酸酯树脂复合材料铺层成型的矩形管搭成主体框架,然后在主体框架上面绷一定张力值的高强度纤维绳,用于与太阳电池片的连接。为保证绷弦式半刚性基板的电池片在卫星发射阶段不与相邻基板的磕碰,对绷弦式半刚性基板框架整体平面度提出了高要求;为保证绷弦式半刚性基板收拢与展开精度,对绷弦式半刚性基板框架数个关键接口的孔位精度提出了高要求,对各零件胶接无应力装配提出了高要求。其中,单块绷弦式半刚性基板框架的外形尺寸约为(4050±1)mm×(2500±1)mm×32mm。绷弦式半刚性基板框架由30多根方管、30多件限位梁、9个压紧点接头、L型边框接头、20多件预埋件、200多件角片等零件胶接装配组成。
目前,常用的绷弦式半刚性基板框架胶接工艺方法是:将所有主梁、边框梁、加强梁、限位梁、压紧接头、边框接头、角盒、角片等零件全部齐套后放置于胶接装配工装上一次胶接装配成基板框架组件。该方法存在以下缺点:
1)由于零件种类数量均较多,胶接位置较多,受操作人员数量、胶接操作空间、胶粘剂适用期限制,较难实现快速同时一次胶接。
2)所有装配位置均须同步执行胶接固化加压过程,每个接口均存在各个方向的胶接装配关系,一次胶接无法保证加压均匀,易产生加压引起的横向位移,影响产品尺寸精度。
3)由于基板框架零件数量较多,各零件间装配关系复杂,多种装配关系耦合较多,一次胶接无法兼顾所有装配接口,易引起部分装配位置装配应力较大,导致产品使用过程中在 高低温环境下胶接不可靠。
发明内容
本发明的技术解决问题:克服现有技术的不足,提供一种绷弦式半刚性基板框架的胶接装配工艺方法,旨在解决现有绷弦式半刚性基板框架胶接工艺方法存在的胶接工期紧凑、装配精度差、装配应力较大等问题。
为了解决上述技术问题,本发明公开了一种绷弦式半刚性基板框架的胶接装配工艺方法,包括:
胶接中心框架:通过胶接装配工装,对压紧点接头、横向梁和纵向梁进行定位;将横向梁和纵向梁通过压紧点接头进行胶接装配,形成中心框架;其中,横向梁和纵向梁上均设置有横、纵向的安装孔;
安装加强梁和限位梁:通过胶接装配工装,对加强梁接头进行定位;根据加强梁、限位梁与中心框架之间的装配关系,将各加强梁和限位梁分别插入中心框架中横向梁和纵向梁上设置的横、纵向的安装孔内,进行试装配;将加强梁与加强梁接头胶接,初步固定;
胶接外部框架:通过胶接装配工装,对端框接头、铰链接头、边框接头、横向边框主梁和纵向边框主梁进行定位;将横向边框主梁和纵向边框主梁通过端框接头、铰链接头和边框接头进行胶接装配,形成外部框架;
胶接角盒与角片:根据装配关系,将角盒与角片胶接在横向梁、纵向梁、加强梁、限位梁、横向边框主梁和纵向边框主梁的相应位置处,得到绷弦式半刚性基板框架。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,压紧点接头为薄壁空腔结构;在将横向梁和纵向梁通过压紧点接头进行胶接装配之前,对压紧点接头的胶接区域进行碳布补强,保证胶接过程良好装配及使用过程中稳定承载。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,胶接装配工装,包括:工装本体、主梁对称约束工装、主梁边框对称约束工装、压紧点接头对称约束工装、铰链接头对称约束工装和外边框对称约束工装;
工装本体为一矩形结构,包括:边Ⅰ、边Ⅱ、边Ⅲ和边Ⅳ;
主梁对称约束工装,包括:均布在工装本体矩形结构内的主梁对称约束工装Ⅰ、主梁对称约束工装Ⅱ、主梁对称约束工装Ⅲ、主梁对称约束工装Ⅳ、主梁对称约束工装Ⅴ和主梁对称约束工装Ⅵ;其中,主梁对称约束工装Ⅰ、主梁对称约束工装Ⅱ和主梁对称约束工装Ⅲ位于第一水平线上,第一水平线为主梁边框对称约束工装Ⅱ和主梁边框对称约束工装Ⅳ的连线;主梁对称约束工装Ⅳ、主梁对称约束工装Ⅴ和主梁对称约束工装Ⅵ位于第二水平线上, 第二水平线为主梁边框对称约束工装Ⅰ和主梁边框对称约束工装Ⅴ的连线;主梁对称约束工装Ⅰ和主梁对称约束工装Ⅳ位于第一竖直线上,第一竖直线为铰链接头对称约束工装Ⅳ和铰链接头对称约束工装Ⅹ的连线;主梁对称约束工装Ⅱ和主梁对称约束工装Ⅴ位于第二竖直线上,第二竖直线为主梁边框对称约束工装Ⅲ和主梁边框对称约束工装Ⅵ的连线;主梁对称约束工装Ⅲ和主梁对称约束工装Ⅵ位于第三竖直线上,第三竖直线为铰链接头对称约束工装Ⅴ和铰链接头对称约束工装Ⅸ的连线;
主梁边框对称约束工装,包括:主梁边框对称约束工装Ⅰ、主梁边框对称约束工装Ⅱ、主梁边框对称约束工装Ⅲ、主梁边框对称约束工装Ⅳ、主梁边框对称约束工装Ⅴ和主梁边框对称约束工装Ⅵ;其中,主梁边框对称约束工装Ⅰ和主梁边框对称约束工装Ⅱ间隔设置在边Ⅰ上,且主梁边框对称约束工装Ⅰ位于铰链接头对称约束工装Ⅰ和铰链接头对称约束工装Ⅱ之间,主梁边框对称约束工装Ⅱ位于铰链接头对称约束工装Ⅱ和铰链接头对称约束工装Ⅲ之间;主梁边框对称约束工装Ⅲ设置在边Ⅱ上,位于铰链接头对称约束工装Ⅳ和铰链接头对称约束工装Ⅴ之间;主梁边框对称约束工装Ⅳ和主梁边框对称约束工装Ⅴ间隔设置在边Ⅲ上,且主梁边框对称约束工装Ⅳ位于铰链接头对称约束工装Ⅵ和铰链接头对称约束工装Ⅶ之间,主梁边框对称约束工装Ⅴ位于铰链接头对称约束工装Ⅶ和铰链接头对称约束工装Ⅷ之间;主梁边框对称约束工装Ⅵ设置在边Ⅳ上,位于铰链接头对称约束工装Ⅸ和铰链接头对称约束工装Ⅹ之间;
压紧点接头对称约束工装,包括:均布在工装本体矩形结构内的压紧点接头对称约束工装Ⅰ、压紧点接头对称约束工装Ⅱ、压紧点接头对称约束工装Ⅲ、压紧点接头对称约束工装Ⅳ、压紧点接头对称约束工装Ⅴ、压紧点接头对称约束工装Ⅵ、压紧点接头对称约束工装Ⅶ、压紧点接头对称约束工装Ⅷ和压紧点接头对称约束工装Ⅸ;其中,压紧点接头对称约束工装Ⅰ、压紧点接头对称约束工装Ⅱ和压紧点接头对称约束工装Ⅲ位于第三水平线上,第三水平线为铰链接头对称约束工装Ⅲ和铰链接头对称约束工装Ⅵ的连线;压紧点接头对称约束工装Ⅳ、压紧点接头对称约束工装Ⅴ和压紧点接头对称约束工装Ⅵ位于第四水平线上,第四水平线为铰链接头对称约束工装Ⅱ和铰链接头对称约束工装Ⅶ的连线;压紧点接头对称约束工装Ⅶ、压紧点接头对称约束工装Ⅷ和压紧点接头对称约束工装Ⅸ位于第五水平线上,第五水平线为铰链接头对称约束工装Ⅰ和铰链接头对称约束工装Ⅷ的连线;压紧点接头对称约束工装Ⅰ、压紧点接头对称约束工装Ⅳ和压紧点接头对称约束工装Ⅶ位于第一竖直线上;压紧点接头对称约束工装Ⅱ、压紧点接头对称约束工装Ⅴ和压紧点接头对称约束工装Ⅷ位于第二竖直线上;压紧点接头对称约束工装Ⅲ、压紧点接头对称约束工装Ⅵ和压紧点接头对称约束工装Ⅸ位于第三竖直线上;
铰链接头对称约束工装,包括:铰链接头对称约束工装Ⅰ、铰链接头对称约束工装Ⅱ、铰链接头对称约束工装Ⅲ、铰链接头对称约束工装Ⅳ、铰链接头对称约束工装Ⅴ、铰链接头对称约束工装Ⅵ、铰链接头对称约束工装Ⅶ、铰链接头对称约束工装Ⅷ、铰链接头对称约束工装Ⅸ和铰链接头对称约束工装Ⅹ;其中,铰链接头对称约束工装Ⅰ、铰链接头对称约束工装Ⅱ和铰链接头对称约束工装Ⅲ间隔设置在边Ⅰ上;铰链接头对称约束工装Ⅳ和铰链接头对称约束工装Ⅴ间隔设置在边Ⅱ上;铰链接头对称约束工装Ⅵ、铰链接头对称约束工装Ⅶ和铰链接头对称约束工装Ⅷ间隔设置在边Ⅲ上;铰链接头对称约束工装Ⅸ和铰链接头对称约束工装Ⅹ间隔设置在边Ⅳ上;
外边框对称约束工装,包括:外边框对称约束工装Ⅰ、外边框对称约束工装Ⅱ、外边框对称约束工装Ⅲ和外边框对称约束工装Ⅳ;其中,外边框对称约束工装Ⅰ、外边框对称约束工装Ⅱ、外边框对称约束工装Ⅲ和外边框对称约束工装Ⅳ分别设置在工装本体矩形结构的四个顶点位置处。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,
压紧点接头,包括:压紧点接头Ⅰ、压紧点接头Ⅱ、压紧点接头Ⅲ、压紧点接头Ⅳ、压紧点接头Ⅴ、压紧点接头Ⅵ、压紧点接头Ⅶ、压紧点接头Ⅷ和压紧点接头Ⅸ;
横向梁,包括:横向梁Ⅰ、横向梁Ⅱ和横向梁Ⅲ;
纵向梁,包括:纵向梁Ⅰ、纵向梁Ⅱ和纵向梁Ⅲ。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,通过胶接装配工装,对压紧点接头、横向梁和纵向梁进行定位,包括:
将压紧点接头Ⅰ、压紧点接头Ⅱ、压紧点接头Ⅲ、压紧点接头Ⅳ、压紧点接头Ⅴ、压紧点接头Ⅵ、压紧点接头Ⅶ、压紧点接头Ⅷ和压紧点接头Ⅸ按顺序依次放置在压紧点接头对称约束工装Ⅰ、压紧点接头对称约束工装Ⅱ、压紧点接头对称约束工装Ⅲ、压紧点接头对称约束工装Ⅳ、压紧点接头对称约束工装Ⅴ、压紧点接头对称约束工装Ⅵ、压紧点接头对称约束工装Ⅶ、压紧点接头对称约束工装Ⅷ和压紧点接头对称约束工装Ⅸ上,并固定,完成对各压紧点接头的定位;
根据压紧点接头对称约束工装Ⅰ、压紧点接头对称约束工装Ⅱ和压紧点接头对称约束工装Ⅲ,对横向梁Ⅲ进行定位;
根据压紧点接头对称约束工装Ⅳ、压紧点接头对称约束工装Ⅴ和压紧点接头对称约束工装Ⅵ,对横向梁Ⅱ进行定位;
根据压紧点接头对称约束工装Ⅶ、压紧点接头对称约束工装Ⅷ和压紧点接头对称约束工装Ⅸ,对横向梁Ⅰ进行定位;
根据压紧点接头对称约束工装Ⅰ、压紧点接头对称约束工装Ⅳ和压紧点接头对称约束工装Ⅶ,对纵向梁Ⅰ进行定位;
根据压紧点接头对称约束工装Ⅱ、压紧点接头对称约束工装Ⅴ和压紧点接头对称约束工装Ⅷ,对纵向梁Ⅱ进行定位;
根据压紧点接头对称约束工装Ⅲ、压紧点接头对称约束工装Ⅵ和压紧点接头对称约束工装Ⅸ,对纵向梁Ⅲ进行定位。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,
加强梁接头,包括:加强梁接头Ⅰ、加强梁接头Ⅱ、加强梁接头Ⅲ、加强梁接头Ⅳ、加强梁接头Ⅴ和加强梁接头Ⅵ;
加强梁,包括:加强梁Ⅰ和加强梁Ⅱ;
限位梁,包括:限位梁Ⅰ、限位梁Ⅱ、限位梁Ⅲ、限位梁Ⅳ、限位梁Ⅴ和限位梁Ⅵ。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,通过胶接装配工装,对加强梁接头进行定位;根据加强梁、限位梁与中心框架之间的装配关系,将各加强梁和限位梁分别插入中心框架中横向梁和纵向梁上设置的横、纵向的安装孔内,进行试装配,包括:
将加强梁接头Ⅰ、加强梁接头Ⅱ、加强梁接头Ⅲ、加强梁接头Ⅳ、加强梁接头Ⅴ和加强梁接头Ⅵ按顺序依次放置在主梁对称约束工装Ⅰ、主梁对称约束工装Ⅱ、主梁对称约束工装Ⅲ、主梁对称约束工装Ⅳ、主梁对称约束工装Ⅴ和主梁对称约束工装Ⅵ上,并固定,完成对各加强梁接头的定位;
将加强梁Ⅱ沿主梁对称约束工装Ⅰ、主梁对称约束工装Ⅱ和主梁对称约束工装Ⅲ进行放置,并穿过中心框架中横向梁和纵向梁上设置的横向安装孔;
将加强梁Ⅰ沿主梁对称约束工装Ⅳ、主梁对称约束工装Ⅴ和主梁对称约束工装Ⅵ进行放置,并穿过中心框架中横向梁和纵向梁上设置的横向安装孔;
将限位梁Ⅰ、限位梁Ⅱ、限位梁Ⅲ、限位梁Ⅳ、限位梁Ⅴ和限位梁Ⅵ按顺序从左至右依次竖直设置,并穿过中心框架中横向梁和纵向梁上设置的纵向安装孔;其中,限位梁Ⅰ位于纵向梁Ⅰ左侧,限位梁Ⅱ和限位梁Ⅲ位于纵向梁Ⅰ和纵向梁Ⅱ之间,限位梁Ⅳ和限位梁Ⅴ位于纵向梁Ⅱ和纵向梁Ⅲ之间,限位梁Ⅵ位于纵向梁Ⅲ右侧。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,
端框接头,包括:端框接头Ⅰ、端框接头Ⅱ、端框接头Ⅲ和端框接头Ⅳ;
铰链接头,包括:铰链接头Ⅰ、铰链接头Ⅱ、铰链接头Ⅲ、铰链接头Ⅳ、铰链接头Ⅴ、铰链接头Ⅵ、铰链接头Ⅶ、铰链接头Ⅷ、铰链接头Ⅸ和铰链接头Ⅹ;
边框接头,包括:边框接头Ⅰ、边框接头Ⅱ、边框接头Ⅲ、边框接头Ⅳ、边框接头Ⅴ和 边框接头Ⅵ。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,通过胶接装配工装,对端框接头、铰链接头、边框接头、横向边框主梁和纵向边框主梁进行定位,包括:
将端框接头Ⅰ、端框接头Ⅱ、端框接头Ⅲ和端框接头Ⅳ按顺序依次放置在外边框对称约束工装Ⅰ、外边框对称约束工装Ⅱ、外边框对称约束工装Ⅲ和外边框对称约束工装Ⅳ上,并固定,完成对各端框接头的定位;
将铰链接头Ⅰ、铰链接头Ⅱ、铰链接头Ⅲ、铰链接头Ⅳ、铰链接头Ⅴ、铰链接头Ⅵ、铰链接头Ⅶ、铰链接头Ⅷ、铰链接头Ⅸ和铰链接头Ⅹ按顺序依次放置在铰链接头对称约束工装Ⅰ、铰链接头对称约束工装Ⅱ、铰链接头对称约束工装Ⅲ、铰链接头对称约束工装Ⅳ、铰链接头对称约束工装Ⅴ、铰链接头对称约束工装Ⅵ、铰链接头对称约束工装Ⅶ、铰链接头对称约束工装Ⅷ、铰链接头对称约束工装Ⅸ和铰链接头对称约束工装Ⅹ上,并固定,完成对各铰链接头的定位;
将边框接头Ⅰ、边框接头Ⅱ、边框接头Ⅲ、边框接头Ⅳ、边框接头Ⅴ和边框接头Ⅵ按顺序依次放置在主梁边框对称约束工装Ⅰ、主梁边框对称约束工装Ⅱ、主梁边框对称约束工装Ⅲ、主梁边框对称约束工装Ⅳ、主梁边框对称约束工装Ⅴ和主梁边框对称约束工装Ⅵ上,并固定,完成对各边框接头的定位。
在上述绷弦式半刚性基板框架的胶接装配工艺方法中,
横向边框主梁,包括:横向边框主梁Ⅰ和横向边框主梁Ⅱ;其中,横向边框主梁Ⅰ分别与端框接头Ⅰ、铰链接头Ⅹ、边框接头Ⅵ、铰链接头Ⅸ和端框接头Ⅳ胶接装配;横向边框主梁Ⅱ分别与端框接头Ⅱ、铰链接头Ⅳ、边框接头Ⅲ、铰链接头Ⅴ和端框接头Ⅲ胶接装配;
纵向边框主梁,包括:纵向边框主梁Ⅰ和纵向边框主梁Ⅱ;其中,纵向边框主梁Ⅰ分别与端框接头Ⅰ、铰链接头Ⅰ、边框接头Ⅰ、铰链接头Ⅱ、边框接头Ⅱ、铰链接头Ⅲ和端框接头Ⅱ胶接装配;纵向边框主梁Ⅱ分别与端框接头Ⅳ、铰链接头Ⅷ、边框接头Ⅴ、铰链接头Ⅶ、边框接头Ⅳ、铰链接头Ⅵ和端框接头Ⅲ胶接装配。
本发明具有以下优点:
(1)本发明公开了一种绷弦式半刚性基板框架的胶接装配工艺方法,对装配顺序进行了优化,安装四步胶接工艺执行,解决了现有绷弦式半刚性基板框架胶接工艺方法存在的胶接工期紧凑、装配精度差、装配应力较大等问题。
(2)本发明公开了一种绷弦式半刚性基板框架的胶接装配工艺方法,压紧点接头为薄壁空腔结构,为保证压紧点力学性能,对压紧点接头的胶接区域进行碳布补强,以保证胶接过程良好装配及使用过程中稳定承载。
(3)本发明公开了一种绷弦式半刚性基板框架的胶接装配工艺方法,对多处压紧点接头及铰链接头等高定位精度关键接口位置采用三个维度对称约束,保证框架结构胶接过程中整个框架系统所有外力自身平衡,胶接加压固化过程中为整个框架系统内加压,保证无应力胶接装配,产品不产生额外的横向位移或纵向位移,从而保证铰链安装孔及压紧点处孔的位置精度要求,同时减少了产品组合加工工序,提高了产品的研制效率和降低了研制成本。
附图说明
图1是本发明实施例中一种绷弦式半刚性基板框架的装配示意图;
图2是本发明实施例中一种胶接装配工装的结构示意图;
图3是本发明实施例中一种中心框架的装配示意图;
图4是本发明实施例中一种加强梁的装配示意图;
图5是本发明实施例中一种限位梁的装配示意图;
图6是本发明实施例中一种外部框架的装配示意图;
图7是本发明实施例中一种主梁对称约束工装的结构示意图;
图8是本发明实施例中一种主梁边框对称约束工装的结构示意图;
图9是本发明实施例中一种压紧点接头对称约束工装的结构示意图;
图10是本发明实施例中一种铰链接头对称约束工装的结构示意图;
图11是本发明实施例中一种外边框对称约束工装的结构示意图;
图12是本发明实施例中一种紧固机构的结构示意图。
具体实施方式
为使本发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明公开的实施方式作进一步详细描述。
由于绷弦式半刚性基板中压紧点接头、铰链接头、边框接头、预埋件数量较多,各处尺寸位置精度要求高,且各尺寸互相联动,一处位置装配不准确将影响周围尺寸定位精度。针对以上特点,本发明公开了一种绷弦式半刚性基板框架的胶接装配工艺方法,采用缠碳丝法对各装配位置胶接间隙进行了控制,具体为将湿碳纤维丝均匀缠绕在各胶接接头的方管表面,保证接头与梁周向胶接间隙均匀一致,减小胶接应力的产生,提高框架产品尺寸精度。本发明解决了使用现有半刚性基板框架胶接装配工艺中胶接工期紧凑、装配精度差、存在较大装配应力等问题,使用该半刚性基板框架胶接装配工艺方法装配的半刚性基板框架产品各项性能指标符合设计及使用要求,并成功经历各项力学、热学试验考核,并顺利完成整翼与 整星的装配及力学性能试验。
如图1和图2,本发明公开了一种绷弦式半刚性基板框架的胶接装配工艺方法,该绷弦式半刚性基板框架的胶接装配工艺方法可以通过胶接装配工装来实现。
如图2,该胶接装配工装可以包括:工装本体1、主梁对称约束工装、主梁边框对称约束工装、压紧点接头对称约束工装、铰链接头对称约束工装和外边框对称约束工装。其中,工装本体1为一矩形结构,具体可以包括:边Ⅰ11、边Ⅱ12、边Ⅲ13和边Ⅳ14。主梁对称约束工装具体可以包括:均布在工装本体1矩形结构内的主梁对称约束工装Ⅰ21、主梁对称约束工装Ⅱ22、主梁对称约束工装Ⅲ23、主梁对称约束工装Ⅳ24、主梁对称约束工装Ⅴ25和主梁对称约束工装Ⅵ26;其中,主梁对称约束工装Ⅰ21、主梁对称约束工装Ⅱ22和主梁对称约束工装Ⅲ23位于第一水平线上,第一水平线为主梁边框对称约束工装Ⅱ32和主梁边框对称约束工装Ⅳ34的连线;主梁对称约束工装Ⅳ24、主梁对称约束工装Ⅴ25和主梁对称约束工装Ⅵ26位于第二水平线上,第二水平线为主梁边框对称约束工装Ⅰ31和主梁边框对称约束工装Ⅴ35的连线;主梁对称约束工装Ⅰ21和主梁对称约束工装Ⅳ24位于第一竖直线上,第一竖直线为铰链接头对称约束工装Ⅳ54和铰链接头对称约束工装Ⅹ的连线;主梁对称约束工装Ⅱ22和主梁对称约束工装Ⅴ25位于第二竖直线上,第二竖直线为主梁边框对称约束工装Ⅲ33和主梁边框对称约束工装Ⅵ36的连线;主梁对称约束工装Ⅲ23和主梁对称约束工装Ⅵ26位于第三竖直线上,第三竖直线为铰链接头对称约束工装Ⅴ55和铰链接头对称约束工装Ⅸ59的连线。主梁边框对称约束工装具体可以包括:主梁边框对称约束工装Ⅰ31、主梁边框对称约束工装Ⅱ32、主梁边框对称约束工装Ⅲ33、主梁边框对称约束工装Ⅳ34、主梁边框对称约束工装Ⅴ35和主梁边框对称约束工装Ⅵ36;其中,主梁边框对称约束工装Ⅰ31和主梁边框对称约束工装Ⅱ32间隔设置在边Ⅰ11上,且主梁边框对称约束工装Ⅰ31位于铰链接头对称约束工装Ⅰ51和铰链接头对称约束工装Ⅱ52之间,主梁边框对称约束工装Ⅱ32位于铰链接头对称约束工装Ⅱ52和铰链接头对称约束工装Ⅲ53之间;主梁边框对称约束工装Ⅲ33设置在边Ⅱ12上,位于铰链接头对称约束工装Ⅳ54和铰链接头对称约束工装Ⅴ55之间;主梁边框对称约束工装Ⅳ34和主梁边框对称约束工装Ⅴ35间隔设置在边Ⅲ13上,且主梁边框对称约束工装Ⅳ34位于铰链接头对称约束工装Ⅵ56和铰链接头对称约束工装Ⅶ57之间,主梁边框对称约束工装Ⅴ35位于铰链接头对称约束工装Ⅶ57和铰链接头对称约束工装Ⅷ58之间;主梁边框对称约束工装Ⅵ36设置在边Ⅳ14上,位于铰链接头对称约束工装Ⅸ59和铰链接头对称约束工装Ⅹ之间。压紧点接头对称约束工装具体可以包括:均布在工装本体1矩形结构内的压紧点接头对称约束工装Ⅰ41、压紧点接头对称约束工装Ⅱ42、压紧点接头对称约束工装Ⅲ43、压紧点接头对称约束工装Ⅳ44、压紧点接头对称约束工装Ⅴ45、压紧点接头对 称约束工装Ⅵ46、压紧点接头对称约束工装Ⅶ47、压紧点接头对称约束工装Ⅷ48和压紧点接头对称约束工装Ⅸ49;其中,压紧点接头对称约束工装Ⅰ41、压紧点接头对称约束工装Ⅱ42和压紧点接头对称约束工装Ⅲ43位于第三水平线上,第三水平线为铰链接头对称约束工装Ⅲ53和铰链接头对称约束工装Ⅵ56的连线;压紧点接头对称约束工装Ⅳ44、压紧点接头对称约束工装Ⅴ45和压紧点接头对称约束工装Ⅵ46位于第四水平线上,第四水平线为铰链接头对称约束工装Ⅱ52和铰链接头对称约束工装Ⅶ57的连线;压紧点接头对称约束工装Ⅶ47、压紧点接头对称约束工装Ⅷ48和压紧点接头对称约束工装Ⅸ49位于第五水平线上,第五水平线为铰链接头对称约束工装Ⅰ51和铰链接头对称约束工装Ⅷ58的连线;压紧点接头对称约束工装Ⅰ41、压紧点接头对称约束工装Ⅳ44和压紧点接头对称约束工装Ⅶ47位于第一竖直线上;压紧点接头对称约束工装Ⅱ42、压紧点接头对称约束工装Ⅴ45和压紧点接头对称约束工装Ⅷ48位于第二竖直线上;压紧点接头对称约束工装Ⅲ43、压紧点接头对称约束工装Ⅵ46和压紧点接头对称约束工装Ⅸ49位于第三竖直线上。铰链接头对称约束工装具体可以包括:铰链接头对称约束工装Ⅰ51、铰链接头对称约束工装Ⅱ52、铰链接头对称约束工装Ⅲ53、铰链接头对称约束工装Ⅳ54、铰链接头对称约束工装Ⅴ55、铰链接头对称约束工装Ⅵ56、铰链接头对称约束工装Ⅶ57、铰链接头对称约束工装Ⅷ58、铰链接头对称约束工装Ⅸ59和铰链接头对称约束工装Ⅹ510;其中,铰链接头对称约束工装Ⅰ51、铰链接头对称约束工装Ⅱ52和铰链接头对称约束工装Ⅲ53间隔设置在边Ⅰ11上;铰链接头对称约束工装Ⅳ54和铰链接头对称约束工装Ⅴ55间隔设置在边Ⅱ12上;铰链接头对称约束工装Ⅵ56、铰链接头对称约束工装Ⅶ57和铰链接头对称约束工装Ⅷ58间隔设置在边Ⅲ13上;铰链接头对称约束工装Ⅸ59和铰链接头对称约束工装Ⅹ间隔设置在边Ⅳ14上。外边框对称约束工装具体可以包括:外边框对称约束工装Ⅰ61、外边框对称约束工装Ⅱ62、外边框对称约束工装Ⅲ63和外边框对称约束工装Ⅳ64;其中,外边框对称约束工装Ⅰ61、外边框对称约束工装Ⅱ62、外边框对称约束工装Ⅲ63和外边框对称约束工装Ⅳ64分别设置在工装本体1矩形结构的四个顶点位置处。
基于上述胶接装配工装实现的绷弦式半刚性基板框架的胶接装配工艺方法具体可以包括如下步骤:
步骤101,胶接中心框架104:通过胶接装配工装,对压紧点接头、横向梁和纵向梁进行定位;将横向梁和纵向梁通过压紧点接头进行胶接装配,形成中心框架104。
在本实施例中,横向梁和纵向梁上均设置有横、纵向的安装孔。其中,压紧点接头为薄壁空腔结构;在将横向梁和纵向梁通过压紧点接头进行胶接装配之前,对压紧点接头的胶接区域进行碳布补强。
如图1和图3,压紧点接头具体可以包括:压紧点接头Ⅰ1011、压紧点接头Ⅱ1012、压紧点接头Ⅲ1013、压紧点接头Ⅳ1014、压紧点接头Ⅴ1015、压紧点接头Ⅵ1016、压紧点接头Ⅶ1017、压紧点接头Ⅷ1018和压紧点接头Ⅸ1019。横向梁具体可以包括:横向梁Ⅰ1021、横向梁Ⅱ1022和横向梁Ⅲ1023。纵向梁具体可以包括:纵向梁Ⅰ1031、纵向梁Ⅱ1032和纵向梁Ⅲ1033。
优选的,上述步骤101的具体实现过程可以如下:将压紧点接头Ⅰ1011、压紧点接头Ⅱ1012、压紧点接头Ⅲ1013、压紧点接头Ⅳ1014、压紧点接头Ⅴ1015、压紧点接头Ⅵ1016、压紧点接头Ⅶ1017、压紧点接头Ⅷ1018和压紧点接头Ⅸ1019按顺序依次放置在压紧点接头对称约束工装Ⅰ41、压紧点接头对称约束工装Ⅱ42、压紧点接头对称约束工装Ⅲ43、压紧点接头对称约束工装Ⅳ44、压紧点接头对称约束工装Ⅴ45、压紧点接头对称约束工装Ⅵ46、压紧点接头对称约束工装Ⅶ47、压紧点接头对称约束工装Ⅷ48和压紧点接头对称约束工装Ⅸ49上,并固定,完成对各压紧点接头的定位;根据压紧点接头对称约束工装Ⅰ41、压紧点接头对称约束工装Ⅱ42和压紧点接头对称约束工装Ⅲ43,对横向梁Ⅲ1023进行定位;根据压紧点接头对称约束工装Ⅳ44、压紧点接头对称约束工装Ⅴ45和压紧点接头对称约束工装Ⅵ46,对横向梁Ⅱ1022进行定位;根据压紧点接头对称约束工装Ⅶ47、压紧点接头对称约束工装Ⅷ48和压紧点接头对称约束工装Ⅸ49,对横向梁Ⅰ1021进行定位;根据压紧点接头对称约束工装Ⅰ41、压紧点接头对称约束工装Ⅳ44和压紧点接头对称约束工装Ⅶ47,对纵向梁Ⅰ1031进行定位;根据压紧点接头对称约束工装Ⅱ42、压紧点接头对称约束工装Ⅴ45和压紧点接头对称约束工装Ⅷ48,对纵向梁Ⅱ1032进行定位;根据压紧点接头对称约束工装Ⅲ43、压紧点接头对称约束工装Ⅵ46和压紧点接头对称约束工装Ⅸ49,对纵向梁Ⅲ1033进行定位。
步骤102,安装加强梁和限位梁:通过胶接装配工装,对加强梁接头进行定位;根据加强梁、限位梁与中心框架104之间的装配关系,将各加强梁和限位梁分别插入中心框架104中横向梁和纵向梁上设置的横、纵向的安装孔内,进行试装配;将加强梁与加强梁接头胶接,初步固定。
在本实施例中,如图1、图4和图5,加强梁接头具体可以包括:加强梁接头Ⅰ1131、加强梁接头Ⅱ1132、加强梁接头Ⅲ1133、加强梁接头Ⅳ1134、加强梁接头Ⅴ1135和加强梁接头Ⅵ1136。加强梁具体可以包括:加强梁Ⅰ1051和加强梁Ⅱ1052。限位梁具体可以包括:限位梁Ⅰ1061、限位梁Ⅱ1062、限位梁Ⅲ1063、限位梁Ⅳ1064、限位梁Ⅴ1065和限位梁Ⅵ1066。
优选的,上述步骤102的具体实现过程可以如下:将加强梁接头Ⅰ1131、加强梁接头Ⅱ1132、加强梁接头Ⅲ1133、加强梁接头Ⅳ1134、加强梁接头Ⅴ1135和加强梁接头Ⅵ1136按顺序依次放置在主梁对称约束工装Ⅰ21、主梁对称约束工装Ⅱ22、主梁对称约束工装Ⅲ23、 主梁对称约束工装Ⅳ24、主梁对称约束工装Ⅴ25和主梁对称约束工装Ⅵ26上,并固定,完成对各加强梁接头的定位。将加强梁Ⅱ1052沿主梁对称约束工装Ⅰ21、主梁对称约束工装Ⅱ22和主梁对称约束工装Ⅲ23进行放置,并穿过中心框架104中横向梁和纵向梁上设置的横向安装孔。将加强梁Ⅰ1051沿主梁对称约束工装Ⅳ24、主梁对称约束工装Ⅴ25和主梁对称约束工装Ⅵ26进行放置,并穿过中心框架104中横向梁和纵向梁上设置的横向安装孔。将限位梁Ⅰ1061、限位梁Ⅱ1062、限位梁Ⅲ1063、限位梁Ⅳ1064、限位梁Ⅴ1065和限位梁Ⅵ1066按顺序从左至右依次竖直设置,并穿过中心框架104中横向梁和纵向梁上设置的纵向安装孔;其中,限位梁Ⅰ1061位于纵向梁Ⅰ1031左侧,限位梁Ⅱ1062和限位梁Ⅲ1063位于纵向梁Ⅰ1031和纵向梁Ⅱ1032之间,限位梁Ⅳ1064和限位梁Ⅴ1065位于纵向梁Ⅱ1032和纵向梁Ⅲ1033之间,限位梁Ⅵ1066位于纵向梁Ⅲ1033右侧。
步骤103,胶接外部框架112。
在本实施例中,通过胶接装配工装,对端框接头、铰链接头、边框接头、横向边框主梁和纵向边框主梁进行定位;将横向边框主梁和纵向边框主梁通过端框接头、铰链接头和边框接头进行胶接装配,形成外部框架112。
如图1和图6,在本实施例中,端框接头具体可以包括:端框接头Ⅰ1071、端框接头Ⅱ1072、端框接头Ⅲ1073和端框接头Ⅳ1074。铰链接头具体可以包括:铰链接头Ⅰ1081、铰链接头Ⅱ1082、铰链接头Ⅲ1083、铰链接头Ⅳ1084、铰链接头Ⅴ1085、铰链接头Ⅵ1086、铰链接头Ⅶ1087、铰链接头Ⅷ1088、铰链接头Ⅸ1089和铰链接头Ⅹ10810。边框接头具体可以包括:边框接头Ⅰ1091、边框接头Ⅱ1092、边框接头Ⅲ1093、边框接头Ⅳ1094、边框接头Ⅴ1095和边框接头Ⅵ1096。
优选的,上述步骤103的具体实现过程可以如下:将端框接头Ⅰ1071、端框接头Ⅱ1072、端框接头Ⅲ1073和端框接头Ⅳ1074按顺序依次放置在外边框对称约束工装Ⅰ61、外边框对称约束工装Ⅱ62、外边框对称约束工装Ⅲ63和外边框对称约束工装Ⅳ64上,并固定,完成对各端框接头的定位。将铰链接头Ⅰ1081、铰链接头Ⅱ1082、铰链接头Ⅲ1083、铰链接头Ⅳ1084、铰链接头Ⅴ1085、铰链接头Ⅵ1086、铰链接头Ⅶ1087、铰链接头Ⅷ1088、铰链接头Ⅸ1089和铰链接头Ⅹ10810按顺序依次放置在铰链接头对称约束工装Ⅰ51、铰链接头对称约束工装Ⅱ52、铰链接头对称约束工装Ⅲ53、铰链接头对称约束工装Ⅳ54、铰链接头对称约束工装Ⅴ55、铰链接头对称约束工装Ⅵ56、铰链接头对称约束工装Ⅶ57、铰链接头对称约束工装Ⅷ58、铰链接头对称约束工装Ⅸ59和铰链接头对称约束工装Ⅹ510上,并固定,完成对各铰链接头的定位。将边框接头Ⅰ1091、边框接头Ⅱ1092、边框接头Ⅲ1093、边框接头Ⅳ1094、边框接头Ⅴ1095和边框接头Ⅵ1096按顺序依次放置在主梁边框对称约束工装Ⅰ31、主梁边 框对称约束工装Ⅱ32、主梁边框对称约束工装Ⅲ33、主梁边框对称约束工装Ⅳ34、主梁边框对称约束工装Ⅴ35和主梁边框对称约束工装Ⅵ36上,并固定,完成对各边框接头的定位。
进一步优选的,横向边框主梁具体可以包括:横向边框主梁Ⅰ1101和横向边框主梁Ⅱ1102;其中,横向边框主梁Ⅰ1101分别与端框接头Ⅰ1071、铰链接头Ⅹ10810、边框接头Ⅵ1096、铰链接头Ⅸ1089和端框接头Ⅳ1074胶接装配;横向边框主梁Ⅱ1102分别与端框接头Ⅱ1072、铰链接头Ⅳ1084、边框接头Ⅲ1093、铰链接头Ⅴ1085和端框接头Ⅲ1073胶接装配。纵向边框主梁具体可以包括:纵向边框主梁Ⅰ1201和纵向边框主梁Ⅱ1202;其中,纵向边框主梁Ⅰ1201分别与端框接头Ⅰ1071、铰链接头Ⅰ1081、边框接头Ⅰ1091、铰链接头Ⅱ1082、边框接头Ⅱ1092、铰链接头Ⅲ1083和端框接头Ⅱ1072胶接装配;纵向边框主梁Ⅱ1202分别与端框接头Ⅳ1074、铰链接头Ⅷ1088、边框接头Ⅴ1095、铰链接头Ⅶ1087、边框接头Ⅳ1094、铰链接头Ⅵ1086和端框接头Ⅲ1073胶接装配。
步骤104,胶接角盒与角片114。
在本实施例,可以根据装配关系,将所有角盒与角片114胶接在横向梁、纵向梁、加强梁、限位梁、横向边框主梁和纵向边框主梁的相应位置处,得到绷弦式半刚性基板框架。
其中,需要说明的是,对于胶接装配工装,如图7,各主梁对称约束工装结构相同,包括:两组紧固机构7。其中,两组紧固机构7平行设置。如图8,各主梁边框对称约束工装结构相同,包括:三组紧固机构7。其中,三组紧固机构7呈凹型设置。如图9,各压紧点接头对称约束工装结构相同,包括:四组紧固机构7和一压紧点定位接头销8。其中,四组紧固机构7收尾依次相连,压紧点定位接头销8设置在由四组紧固机构7收尾依次相连围成的矩形中心。如图10,各铰链接头对称约束工装结构相同,包括:三组紧固机构7和一铰链接口定位接头销9。其中,三组紧固机构7呈凹型设置,铰链接口定位接头销9设置在由三组紧固机构7围成的凹型区域中心。如图11,各外边框对称约束工装结构相同,包括:两组紧固机构7。其中,两组紧固机构7呈∟型设置。其中,各约束工装采用的紧固机构的组合方式,对多处压紧点接头及铰链接头等高定位精度关键接口位置采用三个维度对称约束,保证绷弦式半刚性基板框架胶接过程中整个框架系统所有外力自身平衡,胶接加压固化过程中为整个绷弦式半刚性基板框架系统内加压,保证无应力胶接装配,产品不产生额外的横向位移或纵向位移,从而保证铰链安装孔及压紧点处孔的位置精度要求,同时减少了产品组合加工工序,提高了产品的研制效率和降低了研制成本。
进一步的,如图12,紧固机构7具体可以包括:对称约束推杆71、定位座托72和紧固件73。其中,定位座托72通过紧固件73固定在工装本体上。对称约束推杆71与定位座托72活动连接;当待装配产品安装到位后,通过双向对称推动对称约束推杆71,实现对称约 束推杆71与待装配产品的紧固以及装配产品自身的无应力装配。
本发明虽然已以较佳实施例公开如上,但其并不是用来限定本发明,任何本领域技术人员在不脱离本发明的精神和范围内,都可以利用上述揭示的方法和技术内容对本发明技术方案做出可能的变动和修改,因此,凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化及修饰,均属于本发明技术方案的保护范围。
本发明说明书中未作详细描述的内容属于本领域专业技术人员的公知技术。

Claims (10)

  1. 一种绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,包括:胶接中心框架(104):通过胶接装配工装,对压紧点接头、横向梁和纵向梁进行定位;将横向梁和纵向梁通过压紧点接头进行胶接装配,形成中心框架(104);其中,横向梁和纵向梁上均设置有横、纵向的安装孔;
    安装加强梁和限位梁:通过胶接装配工装,对加强梁接头进行定位;根据加强梁、限位梁与中心框架(104)之间的装配关系,将各加强梁和限位梁分别插入中心框架(104)中横向梁和纵向梁上设置的横、纵向的安装孔内,进行试装配;将加强梁与加强梁接头胶接,初步固定;
    胶接外部框架(112):通过胶接装配工装,对端框接头、铰链接头、边框接头、横向边框主梁和纵向边框主梁进行定位;将横向边框主梁和纵向边框主梁通过端框接头、铰链接头和边框接头进行胶接装配,形成外部框架(112);
    胶接角盒与角片(114):根据装配关系,将角盒与角片(114)胶接在横向梁、纵向梁、加强梁、限位梁、横向边框主梁和纵向边框主梁的相应位置处,得到绷弦式半刚性基板框架。
  2. 根据权利要求1所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,压紧点接头为薄壁空腔结构;在将横向梁和纵向梁通过压紧点接头进行胶接装配之前,对压紧点接头的胶接区域进行碳布补强。
  3. 根据权利要求1所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,胶接装配工装,包括:工装本体(1)、主梁对称约束工装、主梁边框对称约束工装、压紧点接头对称约束工装、铰链接头对称约束工装和外边框对称约束工装;
    工装本体(1)为一矩形结构,包括:边Ⅰ(11)、边Ⅱ(12)、边Ⅲ(13)和边Ⅳ(14);
    主梁对称约束工装,包括:均布在工装本体(1)矩形结构内的主梁对称约束工装Ⅰ(21)、主梁对称约束工装Ⅱ(22)、主梁对称约束工装Ⅲ(23)、主梁对称约束工装Ⅳ(24)、主梁对称约束工装Ⅴ(25)和主梁对称约束工装Ⅵ(26);其中,主梁对称约束工装Ⅰ(21)、主梁对称约束工装Ⅱ(22)和主梁对称约束工装Ⅲ(23)位于第一水平线上,第一水平线为主梁边框对称约束工装Ⅱ(32)和主梁边框对称约束工装Ⅳ(34)的连线;主梁对称约束工装Ⅳ(24)、主梁对称约束工装Ⅴ(25)和主梁对称约束工装Ⅵ(26)位于第二水平线上,第二水平线为主梁边框对称约束工装Ⅰ(31)和主梁边框对称约束工装Ⅴ(35)的连线;主梁对称约束工装Ⅰ(21)和主梁对称约束工装Ⅳ(24)位于第一竖直线上,第一 竖直线为铰链接头对称约束工装Ⅳ(54)和铰链接头对称约束工装Ⅹ的连线;主梁对称约束工装Ⅱ(22)和主梁对称约束工装Ⅴ(25)位于第二竖直线上,第二竖直线为主梁边框对称约束工装Ⅲ(33)和主梁边框对称约束工装Ⅵ(36)的连线;主梁对称约束工装Ⅲ(23)和主梁对称约束工装Ⅵ(26)位于第三竖直线上,第三竖直线为铰链接头对称约束工装Ⅴ(55)和铰链接头对称约束工装Ⅸ(59)的连线;
    主梁边框对称约束工装,包括:主梁边框对称约束工装Ⅰ(31)、主梁边框对称约束工装Ⅱ(32)、主梁边框对称约束工装Ⅲ(33)、主梁边框对称约束工装Ⅳ(34)、主梁边框对称约束工装Ⅴ(35)和主梁边框对称约束工装Ⅵ(36);其中,主梁边框对称约束工装Ⅰ(31)和主梁边框对称约束工装Ⅱ(32)间隔设置在边Ⅰ(11)上,且主梁边框对称约束工装Ⅰ(31)位于铰链接头对称约束工装Ⅰ(51)和铰链接头对称约束工装Ⅱ(52)之间,主梁边框对称约束工装Ⅱ(32)位于铰链接头对称约束工装Ⅱ(52)和铰链接头对称约束工装Ⅲ(53)之间;主梁边框对称约束工装Ⅲ(33)设置在边Ⅱ(12)上,位于铰链接头对称约束工装Ⅳ(54)和铰链接头对称约束工装Ⅴ(55)之间;主梁边框对称约束工装Ⅳ(34)和主梁边框对称约束工装Ⅴ(35)间隔设置在边Ⅲ(13)上,且主梁边框对称约束工装Ⅳ(34)位于铰链接头对称约束工装Ⅵ(56)和铰链接头对称约束工装Ⅶ(57)之间,主梁边框对称约束工装Ⅴ(35)位于铰链接头对称约束工装Ⅶ(57)和铰链接头对称约束工装Ⅷ(58)之间;主梁边框对称约束工装Ⅵ(36)设置在边Ⅳ(14)上,位于铰链接头对称约束工装Ⅸ(59)和铰链接头对称约束工装Ⅹ之间;
    压紧点接头对称约束工装,包括:均布在工装本体(1)矩形结构内的压紧点接头对称约束工装Ⅰ(41)、压紧点接头对称约束工装Ⅱ(42)、压紧点接头对称约束工装Ⅲ(43)、压紧点接头对称约束工装Ⅳ(44)、压紧点接头对称约束工装Ⅴ(45)、压紧点接头对称约束工装Ⅵ(46)、压紧点接头对称约束工装Ⅶ(47)、压紧点接头对称约束工装Ⅷ(48)和压紧点接头对称约束工装Ⅸ(49);其中,压紧点接头对称约束工装Ⅰ(41)、压紧点接头对称约束工装Ⅱ(42)和压紧点接头对称约束工装Ⅲ(43)位于第三水平线上,第三水平线为铰链接头对称约束工装Ⅲ(53)和铰链接头对称约束工装Ⅵ(56)的连线;压紧点接头对称约束工装Ⅳ(44)、压紧点接头对称约束工装Ⅴ(45)和压紧点接头对称约束工装Ⅵ(46)位于第四水平线上,第四水平线为铰链接头对称约束工装Ⅱ(52)和铰链接头对称约束工装Ⅶ(57)的连线;压紧点接头对称约束工装Ⅶ(47)、压紧点接头对称约束工装Ⅷ(48)和压紧点接头对称约束工装Ⅸ(49)位于第五水平线上,第五水平线为铰链接头对称约束工装Ⅰ(51)和铰链接头对称约束工装Ⅷ(58)的连线;压紧点接头对称约束工装Ⅰ(41)、压紧点接头对称约束工装Ⅳ(44)和压紧点接头对称约束工装Ⅶ(47) 位于第一竖直线上;压紧点接头对称约束工装Ⅱ(42)、压紧点接头对称约束工装Ⅴ(45)和压紧点接头对称约束工装Ⅷ(48)位于第二竖直线上;压紧点接头对称约束工装Ⅲ(43)、压紧点接头对称约束工装Ⅵ(46)和压紧点接头对称约束工装Ⅸ(49)位于第三竖直线上;
    铰链接头对称约束工装,包括:铰链接头对称约束工装Ⅰ(51)、铰链接头对称约束工装Ⅱ(52)、铰链接头对称约束工装Ⅲ(53)、铰链接头对称约束工装Ⅳ(54)、铰链接头对称约束工装Ⅴ(55)、铰链接头对称约束工装Ⅵ(56)、铰链接头对称约束工装Ⅶ(57)、铰链接头对称约束工装Ⅷ(58)、铰链接头对称约束工装Ⅸ(59)和铰链接头对称约束工装Ⅹ(510);其中,铰链接头对称约束工装Ⅰ(51)、铰链接头对称约束工装Ⅱ(52)和铰链接头对称约束工装Ⅲ(53)间隔设置在边Ⅰ(11)上;铰链接头对称约束工装Ⅳ(54)和铰链接头对称约束工装Ⅴ(55)间隔设置在边Ⅱ(12)上;铰链接头对称约束工装Ⅵ(56)、铰链接头对称约束工装Ⅶ(57)和铰链接头对称约束工装Ⅷ(58)间隔设置在边Ⅲ(13)上;铰链接头对称约束工装Ⅸ(59)和铰链接头对称约束工装Ⅹ间隔设置在边Ⅳ(14)上;
    外边框对称约束工装,包括:外边框对称约束工装Ⅰ(61)、外边框对称约束工装Ⅱ(62)、外边框对称约束工装Ⅲ(63)和外边框对称约束工装Ⅳ(64);其中,外边框对称约束工装Ⅰ(61)、外边框对称约束工装Ⅱ(62)、外边框对称约束工装Ⅲ(63)和外边框对称约束工装Ⅳ(64)分别设置在工装本体(1)矩形结构的四个顶点位置处。
  4. 根据权利要求3所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,
    压紧点接头,包括:压紧点接头Ⅰ(1011)、压紧点接头Ⅱ(1012)、压紧点接头Ⅲ(1013)、压紧点接头Ⅳ(1014)、压紧点接头Ⅴ(1015)、压紧点接头Ⅵ(1016)、压紧点接头Ⅶ(1017)、压紧点接头Ⅷ(1018)和压紧点接头Ⅸ(1019);
    横向梁,包括:横向梁Ⅰ(1021)、横向梁Ⅱ(1022)和横向梁Ⅲ(1023);
    纵向梁,包括:纵向梁Ⅰ(1031)、纵向梁Ⅱ(1032)和纵向梁Ⅲ(1033)。
  5. 根据权利要求4所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,通过胶接装配工装,对压紧点接头、横向梁和纵向梁进行定位,包括:
    将压紧点接头Ⅰ(1011)、压紧点接头Ⅱ(1012)、压紧点接头Ⅲ(1013)、压紧点接头Ⅳ(1014)、压紧点接头Ⅴ(1015)、压紧点接头Ⅵ(1016)、压紧点接头Ⅶ(1017)、压紧点接头Ⅷ(1018)和压紧点接头Ⅸ(1019)按顺序依次放置在压紧点接头对称约束工装Ⅰ(41)、压紧点接头对称约束工装Ⅱ(42)、压紧点接头对称约束工装Ⅲ(43)、压紧点接头对称约束工装Ⅳ(44)、压紧点接头对称约束工装Ⅴ(45)、压紧点接头对称约束工装Ⅵ(46)、压紧点接头对称约束工装Ⅶ(47)、压紧点接头对称约束工装Ⅷ(48) 和压紧点接头对称约束工装Ⅸ(49)上,并固定,完成对各压紧点接头的定位;
    根据压紧点接头对称约束工装Ⅰ(41)、压紧点接头对称约束工装Ⅱ(42)和压紧点接头对称约束工装Ⅲ(43),对横向梁Ⅲ(1023)进行定位;
    根据压紧点接头对称约束工装Ⅳ(44)、压紧点接头对称约束工装Ⅴ(45)和压紧点接头对称约束工装Ⅵ(46),对横向梁Ⅱ(1022)进行定位;
    根据压紧点接头对称约束工装Ⅶ(47)、压紧点接头对称约束工装Ⅷ(48)和压紧点接头对称约束工装Ⅸ(49),对横向梁Ⅰ(1021)进行定位;
    根据压紧点接头对称约束工装Ⅰ(41)、压紧点接头对称约束工装Ⅳ(44)和压紧点接头对称约束工装Ⅶ(47),对纵向梁Ⅰ(1031)进行定位;
    根据压紧点接头对称约束工装Ⅱ(42)、压紧点接头对称约束工装Ⅴ(45)和压紧点接头对称约束工装Ⅷ(48),对纵向梁Ⅱ(1032)进行定位;
    根据压紧点接头对称约束工装Ⅲ(43)、压紧点接头对称约束工装Ⅵ(46)和压紧点接头对称约束工装Ⅸ(49),对纵向梁Ⅲ(1033)进行定位。
  6. 根据权利要求4所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,
    加强梁接头,包括:加强梁接头Ⅰ(1131)、加强梁接头Ⅱ(1132)、加强梁接头Ⅲ(1133)、加强梁接头Ⅳ(1134)、加强梁接头Ⅴ(1135)和加强梁接头Ⅵ(1136);
    加强梁,包括:加强梁Ⅰ(1051)和加强梁Ⅱ(1052);
    限位梁,包括:限位梁Ⅰ(1061)、限位梁Ⅱ(1062)、限位梁Ⅲ(1063)、限位梁Ⅳ(1064)、限位梁Ⅴ(1065)和限位梁Ⅵ(1066)。
  7. 根据权利要求6所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,通过胶接装配工装,对加强梁接头进行定位;根据加强梁、限位梁与中心框架(104)之间的装配关系,将各加强梁和限位梁分别插入中心框架(104)中横向梁和纵向梁上设置的横、纵向的安装孔内,进行试装配,包括:
    将加强梁接头Ⅰ(1131)、加强梁接头Ⅱ(1132)、加强梁接头Ⅲ(1133)、加强梁接头Ⅳ(1134)、加强梁接头Ⅴ(1135)和加强梁接头Ⅵ(1136)按顺序依次放置在主梁对称约束工装Ⅰ(21)、主梁对称约束工装Ⅱ(22)、主梁对称约束工装Ⅲ(23)、主梁对称约束工装Ⅳ(24)、主梁对称约束工装Ⅴ(25)和主梁对称约束工装Ⅵ(26)上,并固定,完成对各加强梁接头的定位;
    将加强梁Ⅱ(1052)沿主梁对称约束工装Ⅰ(21)、主梁对称约束工装Ⅱ(22)和主梁对称约束工装Ⅲ(23)进行放置,并穿过中心框架(104)中横向梁和纵向梁上设置的横向安装孔;
    将加强梁Ⅰ(1051)沿主梁对称约束工装Ⅳ(24)、主梁对称约束工装Ⅴ(25)和主梁对称约束工装Ⅵ(26)进行放置,并穿过中心框架(104)中横向梁和纵向梁上设置的横向安装孔;
    将限位梁Ⅰ(1061)、限位梁Ⅱ(1062)、限位梁Ⅲ(1063)、限位梁Ⅳ(1064)、限位梁Ⅴ(1065)和限位梁Ⅵ(1066)按顺序从左至右依次竖直设置,并穿过中心框架(104)中横向梁和纵向梁上设置的纵向安装孔;其中,限位梁Ⅰ(1061)位于纵向梁Ⅰ(1031)左侧,限位梁Ⅱ(1062)和限位梁Ⅲ(1063)位于纵向梁Ⅰ(1031)和纵向梁Ⅱ(1032)之间,限位梁Ⅳ(1064)和限位梁Ⅴ(1065)位于纵向梁Ⅱ(1032)和纵向梁Ⅲ(1033)之间,限位梁Ⅵ(1066)位于纵向梁Ⅲ(1033)右侧。
  8. 根据权利要求3所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,
    端框接头,包括:端框接头Ⅰ(1071)、端框接头Ⅱ(1072)、端框接头Ⅲ(1073)和端框接头Ⅳ(1074);
    铰链接头,包括:铰链接头Ⅰ(1081)、铰链接头Ⅱ(1082)、铰链接头Ⅲ(1083)、铰链接头Ⅳ(1084)、铰链接头Ⅴ(1085)、铰链接头Ⅵ(1086)、铰链接头Ⅶ(1087)、铰链接头Ⅷ(1088)、铰链接头Ⅸ(1089)和铰链接头Ⅹ(10810);
    边框接头,包括:边框接头Ⅰ(1091)、边框接头Ⅱ(1092)、边框接头Ⅲ(1093)、边框接头Ⅳ(1094)、边框接头Ⅴ(1095)和边框接头Ⅵ(1096)。
  9. 根据权利要求8所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,通过胶接装配工装,对端框接头、铰链接头、边框接头、横向边框主梁和纵向边框主梁进行定位,包括:
    将端框接头Ⅰ(1071)、端框接头Ⅱ(1072)、端框接头Ⅲ(1073)和端框接头Ⅳ(1074)按顺序依次放置在外边框对称约束工装Ⅰ(61)、外边框对称约束工装Ⅱ(62)、外边框对称约束工装Ⅲ(63)和外边框对称约束工装Ⅳ(64)上,并固定,完成对各端框接头的定位;
    将铰链接头Ⅰ(1081)、铰链接头Ⅱ(1082)、铰链接头Ⅲ(1083)、铰链接头Ⅳ(1084)、铰链接头Ⅴ(1085)、铰链接头Ⅵ(1086)、铰链接头Ⅶ(1087)、铰链接头Ⅷ(1088)、铰链接头Ⅸ(1089)和铰链接头Ⅹ(10810)按顺序依次放置在铰链接头对称约束工装Ⅰ(51)、铰链接头对称约束工装Ⅱ(52)、铰链接头对称约束工装Ⅲ(53)、铰链接头对称约束工装Ⅳ(54)、铰链接头对称约束工装Ⅴ(55)、铰链接头对称约束工装Ⅵ(56)、铰链接头对称约束工装Ⅶ(57)、铰链接头对称约束工装Ⅷ(58)、铰链接头对称约束工装Ⅸ(59)和铰链接头对称约束工装Ⅹ(510)上,并固定,完成对各铰链接头的定位;
    将边框接头Ⅰ(1091)、边框接头Ⅱ(1092)、边框接头Ⅲ(1093)、边框接头Ⅳ(1094)、边框接头Ⅴ(1095)和边框接头Ⅵ(1096)按顺序依次放置在主梁边框对称约束工装Ⅰ(31)、主梁边框对称约束工装Ⅱ(32)、主梁边框对称约束工装Ⅲ(33)、主梁边框对称约束工装Ⅳ(34)、主梁边框对称约束工装Ⅴ(35)和主梁边框对称约束工装Ⅵ(36)上,并固定,完成对各边框接头的定位。
  10. 根据权利要求8所述的绷弦式半刚性基板框架的胶接装配工艺方法,其特征在于,
    横向边框主梁,包括:横向边框主梁Ⅰ(1101)和横向边框主梁Ⅱ(1102);其中,横向边框主梁Ⅰ(1101)分别与端框接头Ⅰ(1071)、铰链接头Ⅹ(10810)、边框接头Ⅵ(1096)、铰链接头Ⅸ(1089)和端框接头Ⅳ(1074)胶接装配;横向边框主梁Ⅱ(1102)分别与端框接头Ⅱ(1072)、铰链接头Ⅳ(1084)、边框接头Ⅲ(1093)、铰链接头Ⅴ(1085)和端框接头Ⅲ(1073)胶接装配;
    纵向边框主梁,包括:纵向边框主梁Ⅰ(1201)和纵向边框主梁Ⅱ(1202);其中,纵向边框主梁Ⅰ(1201)分别与端框接头Ⅰ(1071)、铰链接头Ⅰ(1081)、边框接头Ⅰ(1091)、铰链接头Ⅱ(1082)、边框接头Ⅱ(1092)、铰链接头Ⅲ(1083)和端框接头Ⅱ(1072)胶接装配;纵向边框主梁Ⅱ(1202)分别与端框接头Ⅳ(1074)、铰链接头Ⅷ(1088)、边框接头Ⅴ(1095)、铰链接头Ⅶ(1087)、边框接头Ⅳ(1094)、铰链接头Ⅵ(1086)和端框接头Ⅲ(1073)胶接装配。
PCT/CN2021/127429 2020-10-30 2021-10-29 一种绷弦式半刚性基板框架的胶接装配工艺方法 WO2022089582A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202011191862.9 2020-10-30
CN202011191862.9A CN112343907B (zh) 2020-10-30 2020-10-30 一种绷弦式半刚性基板框架的胶接装配工艺方法

Publications (1)

Publication Number Publication Date
WO2022089582A1 true WO2022089582A1 (zh) 2022-05-05

Family

ID=74356288

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/127429 WO2022089582A1 (zh) 2020-10-30 2021-10-29 一种绷弦式半刚性基板框架的胶接装配工艺方法

Country Status (2)

Country Link
CN (1) CN112343907B (zh)
WO (1) WO2022089582A1 (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343907B (zh) * 2020-10-30 2022-07-29 北京卫星制造厂有限公司 一种绷弦式半刚性基板框架的胶接装配工艺方法
CN113548200B (zh) * 2021-07-07 2023-09-15 北京空间飞行器总体设计部 一种轻量化绷弦式太阳翼半刚性基板

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2749088A1 (fr) * 1996-05-21 1997-11-28 Logo Procede de montage d'une monture de lunettes sur un verre, et lunettes ainsi montees
CN102748563A (zh) * 2012-06-21 2012-10-24 上海卫星工程研究所 全复合材料全胶接框架结构装置
US20140113116A1 (en) * 2012-10-24 2014-04-24 Nokia Corporation Attaching Window Assembly Using Optical Welding
US20160253444A1 (en) * 2015-02-27 2016-09-01 Space Systems/Loral, Llc Truss structure optimization techniques
CN109263057A (zh) * 2018-09-26 2019-01-25 中国科学院长春光学精密机械与物理研究所 一种精密碳纤维桁架的粘接与装配方法
CN109774190A (zh) * 2019-01-17 2019-05-21 江苏恒神股份有限公司 一种碳纤维复合材料多通接头的制造方法
CN111098507A (zh) * 2019-12-31 2020-05-05 上海复合材料科技有限公司 卫星复合材料桁架原位胶接装配的方法
CN112343907A (zh) * 2020-10-30 2021-02-09 北京卫星制造厂有限公司 一种绷弦式半刚性基板框架的胶接装配工艺方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2749088A1 (fr) * 1996-05-21 1997-11-28 Logo Procede de montage d'une monture de lunettes sur un verre, et lunettes ainsi montees
CN102748563A (zh) * 2012-06-21 2012-10-24 上海卫星工程研究所 全复合材料全胶接框架结构装置
US20140113116A1 (en) * 2012-10-24 2014-04-24 Nokia Corporation Attaching Window Assembly Using Optical Welding
US20160253444A1 (en) * 2015-02-27 2016-09-01 Space Systems/Loral, Llc Truss structure optimization techniques
CN109263057A (zh) * 2018-09-26 2019-01-25 中国科学院长春光学精密机械与物理研究所 一种精密碳纤维桁架的粘接与装配方法
CN109774190A (zh) * 2019-01-17 2019-05-21 江苏恒神股份有限公司 一种碳纤维复合材料多通接头的制造方法
CN111098507A (zh) * 2019-12-31 2020-05-05 上海复合材料科技有限公司 卫星复合材料桁架原位胶接装配的方法
CN112343907A (zh) * 2020-10-30 2021-02-09 北京卫星制造厂有限公司 一种绷弦式半刚性基板框架的胶接装配工艺方法

Also Published As

Publication number Publication date
CN112343907A (zh) 2021-02-09
CN112343907B (zh) 2022-07-29

Similar Documents

Publication Publication Date Title
WO2022089582A1 (zh) 一种绷弦式半刚性基板框架的胶接装配工艺方法
US8128025B2 (en) Providing skins for aircraft fuselages
US10640221B2 (en) Wing airfoil stiffening for solar powered aircraft
CN110726541B (zh) 一种大涵道比航空发动机中介机匣强度试验装置
CN101146711A (zh) 组合碳-金属的不对称拼接的装置与方法
CN107848634A (zh) 卫星框架和制备卫星的方法
US4686322A (en) Solar panel
US20140000584A1 (en) Fixing system for connecting two components to each other and method for fixing a mirror element, in particular for a solar collector module, to a support frame using such fixing systems
US5411617A (en) Method for use in fabricating and/or testing a thin mirror
Gray et al. Support of large borosilicate honeycomb mirrors
CN1341536A (zh) 自旋稳定的薄膜反射镜及其在太空的应用
CN112389683B (zh) 一种太阳帆航天器薄膜预应力保持方法
CN106428640A (zh) 卫星太阳能帆板自动对日定向器
WO2014183612A1 (zh) 战斗机座舱透明件紧固结构及其紧固方法
CN113548200B (zh) 一种轻量化绷弦式太阳翼半刚性基板
CN101465390A (zh) 半刚性太阳电池阵基板成型工艺
CN109639218A (zh) 一种适用于双玻组件固定结构的施工方法
JPS6260301A (ja) アンテナ装置
CN116346013A (zh) 一种平面非对称复合展开式偏t字构型空间太阳电池阵
Olds et al. Composite structures for the Advanced X-ray Astrophysics Facility (AXAF) telescope
CN220419675U (zh) 一种用于空间引力波探测的望远镜系统
Vosteen Composite aircraft structures
CN114560070A (zh) 一种适用于中小型无人机的复合材料整体机翼及成型方法
Stumm et al. Graphite/epoxy material characteristics and design techniques for airborne instrument application
CHERRY Composites technology-Threshold to low cost aircraft structures

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21885308

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21885308

Country of ref document: EP

Kind code of ref document: A1