WO2022033503A1 - Construction method for dismantling concrete supports of prefabricated subway station - Google Patents
Construction method for dismantling concrete supports of prefabricated subway station Download PDFInfo
- Publication number
- WO2022033503A1 WO2022033503A1 PCT/CN2021/111987 CN2021111987W WO2022033503A1 WO 2022033503 A1 WO2022033503 A1 WO 2022033503A1 CN 2021111987 W CN2021111987 W CN 2021111987W WO 2022033503 A1 WO2022033503 A1 WO 2022033503A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- supports
- concrete
- support
- blocks
- dismantling
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 70
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 84
- 239000010959 steel Substances 0.000 claims abstract description 84
- 238000000034 method Methods 0.000 claims abstract description 34
- 239000003337 fertilizer Substances 0.000 claims abstract description 11
- 238000011065 in-situ storage Methods 0.000 claims 1
- 230000001141 propulsive effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 14
- 238000005266 casting Methods 0.000 description 2
- 239000004927 clay Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 229910000976 Electrical steel Inorganic materials 0.000 description 1
- 102100039855 Histone H1.2 Human genes 0.000 description 1
- 102100027368 Histone H1.3 Human genes 0.000 description 1
- 101001035375 Homo sapiens Histone H1.2 Proteins 0.000 description 1
- 101001009450 Homo sapiens Histone H1.3 Proteins 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/04—Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2220/00—Temporary installations or constructions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
Definitions
- the invention relates to the technical field of station construction with a pile support system, in particular to a construction method for dismantling concrete supports of a prefabricated subway station.
- the pre-support of the foundation pit and the roadway is completed through the first excavation construction of the foundation pit and the roadway, and then the floor block hoisting, base grouting, fertilizer tank backfilling, side wall assembly, middle plate assembly and roof plate are carried out.
- the floor block hoisting, base grouting, fertilizer tank backfilling, side wall assembly, middle plate assembly and roof plate are carried out.
- Pre-support usually includes many concrete supports and steel structure supports, and the concrete supports are arranged at the top (first row) of the foundation pit or roadway, and the steel structure supports are arranged at the middle (second row) and bottom (third row) of the foundation pit or roadway.
- the concrete supports and steel structure supports are evenly arranged and grouped according to the distance according to one concrete support and multiple steel structure supports.
- Concrete support and steel structure support are set through pre-construction, providing great support force for foundation pit and roadway. Strict construction sequence and stress control are required during demolition. Only in this way can a safe and orderly dismantling be achieved, otherwise the uneven distribution of stress may lead to a roof fall accident or a hidden safety hazard.
- the existing dismantling methods are time-consuming, labor-intensive, and inefficient, resulting in a long construction period and low safety. This problem has always had a great impact on the construction of subway stations and has not been effectively solved.
- the present invention provides a construction method for dismantling concrete supports of a prefabricated subway station, aiming to start the construction from the end of the foundation pit and the roadway and carry out the construction on the roadway.
- the setting of , middle and bottom plates, and the dismantling of supports are carried out at the same time to provide a safe and reliable guarantee for the construction of the roadway.
- the dismantling method disclosed above is realized simultaneously in the process of advancing the construction of the foundation pit and the roadway, and the original concrete supports and steel supports can be gradually dismantled during the assembly of the floor blocks, side wall blocks, roof blocks, etc.
- the process is simple, the efficiency is higher, and it is safer and more reliable.
- each set of supports includes a concrete support at the top, a steel support at the middle and a steel support at the lower part. Both the middle steel support and the lower steel support include at least two in the depth direction.
- the advantage of this setting is that through the cooperation of one set of concrete supports and multiple sets of steel supports, the stress in the foundation pit and the roadway can be reasonably distributed, and the foundation pit and roadway can be reliably carried out. support, and can ensure sufficient construction space in the later stage.
- the bottom plate blocks need to be assembled and strengthened, but also the side wall blocks, the middle plate and the top plate.
- a number of side wall blocks, a number of middle panels and a number of top panels are tensioned and locked respectively.
- the side wall block needs to maintain a predetermined direction after tensioning and locking.
- the outer side of the side wall block is provided with an enclosure pile. After the side wall block is assembled, the side wall block and the enclosure pile are connected and fastened. .
- the fence piles or the fence purlins can be connected and fastened to the side wall blocks, and the specific fastening method can be tightened by a jack.
- the concrete supports are arranged at the heights of the foundation pit and the roadway, and need to be supported and maintained during the demolition, and then hoisted and transported after demolition. Specifically, the following feasible solutions are given: when the concrete support is removed, at least two corbels are arranged under the concrete support, and both ends of the concrete support are cut simultaneously, and the concrete support falls on the corbel after being cut.
- the corbel can be made of various materials or structures.
- the corbel is made of concrete, and a wire saw is used to cut the concrete support, and the corbel is There is a pre-embedded pipe on the top, and the wire saw passes through the pre-embedded pipe when cutting the concrete support.
- the specific construction operation methods are listed here: in the depth direction, the floor blocks are arranged in groups according to the number of rings, and the floor blocks are set in sequence, and then the floor blocks are hoisted ring by ring, tensioned and locked by ring, and 4 rings are assembled each time. Carry out a base grouting, and carry out a fertilizer tank backfill and an inverted arch backfill every 5 to 10 rings assembled.
- the construction of the bottom plate can be carried out synchronously.
- the following specific construction operation method in the depth direction, set the bottom plate in groups according to the number of rings, and set them in sequence.
- the floor block carry out the backfilling of the fertilizer tank and the construction of the cast-in-place layer of the middle plate superimposition every 10 to 20 rings.
- remove the fixed end of the section steel combination apply the reserved post-casting belt, and carry out the top plate. Backfill, restore the original ground.
- the present invention has the following beneficial effects:
- the construction method disclosed in the present invention provides temporary support during the assembling process, does not affect the assembling process, and can also remove part of the pre-supported components. Through the construction method disclosed in the present invention, it can be realized synchronously in the process of advancing the construction of the foundation pit and the roadway. For the removal of concrete supports, the original concrete supports and steel supports can be gradually removed when assembling the floor blocks, side wall blocks, roof blocks, etc. The removal process is simple, more efficient, and safer and more reliable.
- Fig. 1 is the schematic diagram of hoisting the first ring bottom plate block
- Fig. 2 is the schematic diagram of hoisting the second ring bottom plate block
- Figure 3 is a schematic diagram of longitudinal tensioning and locking of the bottom plate block
- Fig. 4 is the schematic diagram after the floor block construction is completed
- Fig. 5 is the schematic diagram of assembling the first ring side wall block, the middle block and the roof block;
- Fig. 6 is the schematic diagram of dismantling the first steel support
- Fig. 7 is the schematic diagram of assembling the second ring and the third ring side wall block, middle block and roof block;
- Figure 8 is a schematic diagram of adding a second temporary support at the steel support and removing the second steel support
- Fig. 9 is the schematic diagram of assembling the fourth ring and the fifth ring side wall block, middle block and roof block;
- Figure 10 is a schematic diagram of adding a third temporary support at the steel support and removing the third steel support
- Figure 11 is a schematic diagram of assembling the sixth ring and the seventh ring side wall block, middle block and roof block;
- Figure 12 is a schematic diagram of adding a fourth temporary support at the steel support and removing the fourth steel support
- Figure 13 is a schematic diagram of assembling the eighth ring and the ninth ring side wall block, middle block and roof block;
- Figure 14 is a schematic diagram of construction completion
- Fig. 15 is the structural representation of corbel
- 16 is a schematic cross-sectional view of the B-B section.
- the foundation pit and the roadway are sequentially composed of a cast-in-place section with a length of 42 m, an assembly section with a length of 148 m, and a cast-in-place section with a length of 28 m.
- the foundation pits and roadways are mainly located in plain fill, silty clay, cohesive soil gravel, strongly weathered tuff, moderately weathered tuff and slightly weathered tuff.
- the foundation pits and roadways are mainly located in silty clay and cohesive soil gravel. In the sand, the base is located in strongly and moderately weathered tuff, and the anti-floating water level elevation is 12m.
- the size of the cross-section of the concrete support to be removed is 1000mm ⁇ 800mm, the length is 22m, and the weight of the concrete support is about 44t.
- Demolition of concrete supports is carried out in foundation pits and roadways from construction to assembly.
- the present embodiment discloses a construction method for dismantling concrete supports of a prefabricated subway station. During the assembly construction process, the supports are gradually dismantled, including:
- S04 The bottom plate continues to be hoisted forward and ring by ring, and tensioned and locked by ring by ring. Base grouting is carried out once every 4 rings are assembled, and every 5 to 10 rings can be backfilled with fertilizer grooves on both sides of the bottom plate and inverted arch backfilling above the bottom plate. Complete the bottom plate assembly, grouting, backfilling and other processes.
- Concrete supports and steel supports are evenly arranged in the depth direction.
- the grouping of concrete supports and steel supports is set during construction.
- each The group support includes a concrete support at the top, a steel support at the middle and a steel support at the lower part, and both the middle steel support and the lower steel support include at least two in the depth direction.
- the advantage of this setting is that through the cooperation of one set of concrete supports and multiple sets of steel supports, the stress in the foundation pit and the roadway can be reasonably distributed, and the foundation pit and roadway can be reliably carried out. support, and can ensure sufficient construction space in the later stage.
- the first line is located at the end of the construction of the cast-in-place section, and the second line of concrete support meets it for 7.4m, followed by a concrete support evenly arranged every 8m; the steel support at the middle and bottom, the first One is set 3m away from the construction end of the cast-in-place section, and then a steel support is evenly set every 4m, and the middle steel support and the lower steel support are vertically aligned, and the second concrete support is aligned with the second steel support Bracing, the third concrete brace aligns with the fourth steel brace, the third concrete brace aligns with the sixth steel brace...and so on.
- the temporary support adopts steel support, which is arranged between two steel supports inside each group of supports, and the temporary support between the two steel supports is located in the middle position, and the distance between the nearest steel supports at the front and rear is 2m. And when temporary support is set, the distance between the first steel support closest to the construction position is 800mm from the side wall block, middle plate and roof plate, and the distance between the subsequent steel support and the side wall block, middle plate and roof plate is 1m.
- S11 Assemble the side wall, middle plate, and top plate of the sixth ring and the seventh ring in sequence, and tension and lock them one by one.
- the side wall of the middle plate height and the steel purlin of the retaining pile are tightened by a jack.
- the bottom plate blocks need to be assembled and strengthened, but also the side wall blocks, the middle plate and the top plate.
- the wall blocks, some middle blocks and some top blocks are respectively tensioned and locked.
- the specific tensioning and locking method can adopt the conventional method in the industry.
- the outer side of the side wall block is provided with an enclosure pile. After the side wall block is assembled, the side wall block and the enclosure pile are connected and fastened.
- the fence piles or the fence purlins can be connected and fastened to the side wall blocks, and the specific fastening method can be tightened by a jack.
- the concrete supports are arranged at the heights of the foundation pit and roadway, and need to be supported and maintained during dismantling, and then hoisted and transported after dismantling.
- the present embodiment adopts the following feasible solution: when the concrete support 2 is removed, at least two corbels 1 are arranged under the concrete support 2, and both ends of the concrete support 2 are cut at the same time. on leg 1.
- the corbel is made of concrete, and a wire saw is used to cut the concrete support.
- a pre-embedded pipe on the top, and the wire saw passes through the pre-embedded pipe when cutting the concrete support.
- the construction of the floor panels can be carried out simultaneously.
- the following specific construction operation methods are listed here: in the depth direction, set the floor panels in groups according to the number of rings, and then set the floor panels in sequence. , every 10 to 20 rings, carry out backfilling of the fertilizer tank and the construction of the cast-in-place layer of the middle plate.
- After the bottom plate is assembled remove the fixed end of the steel combination, and apply the reserved post-casting belt of 1m, and carry out the backfill above the top plate. , to restore the original ground.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Sustainable Development (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The present invention relates to the technical field of pile support system prefabricated station construction, and specifically relates to a construction method for dismantling concrete supports of a prefabricated subway station. The method comprises: hoisting several fixing bottom plate blocks in sequence, and tightening and locking the bottom plate blocks along the longitudinal depth direction; performing base grouting, fertilizer trough backfilling and inverted-arch backfilling; grouping according to several corresponding steel supports below first concrete supports, and dividing the concrete supports and the steel supports into a plurality of groups in the depth advancement direction; and splicing side wall blocks, middle plate blocks and top plate blocks in a group in succession according to the depth advancement direction, adding temporary supports in the construction advancement direction, and dismantling the steel supports and concrete supports in the group. By means of the disclosed construction method, the concrete supports may be dismantled simultaneously during the propulsive construction of the foundation pit and a roadway, and the original concrete supports and steel supports may be gradually dismantled when the bottom plate blocks, side wall blocks, top plate blocks and so on are spliced. The dismantling process is simple and more efficient, and is also safer and more reliable.
Description
本发明涉及桩撑体系车站施工技术领域,尤其涉及一种用于装配式地铁车站混凝土支撑拆除的施工方法。The invention relates to the technical field of station construction with a pile support system, in particular to a construction method for dismantling concrete supports of a prefabricated subway station.
装配式地铁车站施工过程中,通过基坑和巷道的先行掘进施工,完成基坑和巷道的预支护,后续进行底板块吊装、基地注浆、肥槽回填、侧墙拼装、中板拼装和顶板拼装等施工,在此还需要对预支护进行拆除,并进行长效支护的设置。During the construction of the prefabricated subway station, the pre-support of the foundation pit and the roadway is completed through the first excavation construction of the foundation pit and the roadway, and then the floor block hoisting, base grouting, fertilizer tank backfilling, side wall assembly, middle plate assembly and roof plate are carried out. For construction such as assembly, it is also necessary to dismantle the pre-support and set up the long-term support.
预支护通常包括诸多混凝土支撑和钢结构支撑,且混凝土支撑设置于基坑或巷道的顶部(第一排),钢结构支撑设置于基坑或巷道的中部(第二排)和底部(第三排)并位于混凝土支撑的下方,混凝土支撑和钢结构支撑均匀排布并按照距离按照一道混凝土支撑、多道钢结构支撑进行分组。混凝土支撑和钢结构支撑是通过前期施工设置的,为基坑和巷道提供极大的支护力,在拆除时需要进行严格的施工顺序和应力控制。从而才可实现安全有序的拆除,否则可能由于应力分配不均导致冒顶事故或埋下安全隐患。现有的拆除方式费时费力,效率低下,导致工期长,且安全性不高,该问题一直对地铁车站的施工造成极大的影响并且未得到有效解决。Pre-support usually includes many concrete supports and steel structure supports, and the concrete supports are arranged at the top (first row) of the foundation pit or roadway, and the steel structure supports are arranged at the middle (second row) and bottom (third row) of the foundation pit or roadway. The concrete supports and steel structure supports are evenly arranged and grouped according to the distance according to one concrete support and multiple steel structure supports. Concrete support and steel structure support are set through pre-construction, providing great support force for foundation pit and roadway. Strict construction sequence and stress control are required during demolition. Only in this way can a safe and orderly dismantling be achieved, otherwise the uneven distribution of stress may lead to a roof fall accident or a hidden safety hazard. The existing dismantling methods are time-consuming, labor-intensive, and inefficient, resulting in a long construction period and low safety. This problem has always had a great impact on the construction of subway stations and has not been effectively solved.
因此需要对其施工过程进行研究优化以得到更为合理的技术方案,解决现有技术中的不足。Therefore, it is necessary to study and optimize the construction process to obtain a more reasonable technical solution and solve the deficiencies in the existing technology.
发明内容SUMMARY OF THE INVENTION
为了克服上述内容中提到的现有技术存在的缺陷,本发明提供了一种用于装配式地铁车站混凝土支撑拆除的施工方法,旨在从基坑和巷道的端部开始施工并进行巷道上、中、底板的设置,同时进行支撑的拆除,为推进巷道的施工提供安全可靠的保障。In order to overcome the defects of the prior art mentioned in the above content, the present invention provides a construction method for dismantling concrete supports of a prefabricated subway station, aiming to start the construction from the end of the foundation pit and the roadway and carry out the construction on the roadway. The setting of , middle and bottom plates, and the dismantling of supports are carried out at the same time to provide a safe and reliable guarantee for the construction of the roadway.
为了实现上述目的,本发明具体采用的技术方案是:In order to achieve the above object, the technical scheme specifically adopted in the present invention is:
一种用于装配式地铁车站混凝土支撑拆除的施工方法,在拼装施工过程中逐步拆除支撑,包括:A construction method for dismantling concrete supports of a prefabricated subway station, the supports are gradually dismantled during the assembly construction process, including:
依次吊装若干固定底板块,将底板块在纵深方向上张拉锁紧;Hoist several fixed floor blocks in sequence, and tension and lock the floor blocks in the depth direction;
进行基底注浆、肥槽回填和仰拱回填;Carry out base grouting, fertilizer tank backfill and inverted arch backfill;
按照第一道混凝土支撑下方对应若干道钢支撑进行分组,将混凝土支撑和钢支撑在进深方向分成多组;在按照进深推进方向在组内依次拼装侧墙块、中板块和顶板块,在施工前进方向增设临时支撑并拆除组内的钢支撑和混凝土支撑。Group according to the corresponding steel supports below the first concrete support, and divide the concrete supports and steel supports into multiple groups in the depth direction; assemble the side wall blocks, middle blocks and roof blocks in sequence according to the depth advancing direction. Temporary supports were added in the forward direction and steel supports and concrete supports were removed within the group.
上述公开的拆除方法,是在进行基坑和巷道推进施工的过程中同步实现的,在进行底板块、侧墙块、顶板块等的拼装时可逐步拆除原先的混凝土支撑和钢支撑,拆除过程工艺简单,效率更高,也更安全可靠。The dismantling method disclosed above is realized simultaneously in the process of advancing the construction of the foundation pit and the roadway, and the original concrete supports and steel supports can be gradually dismantled during the assembly of the floor blocks, side wall blocks, roof blocks, etc. The process is simple, the efficiency is higher, and it is safer and more reliable.
进一步的,混凝土支撑和钢支撑在进深方向上是按规律均匀排布的,为方便拆卸,在施工时对混凝土支撑和钢支撑的分组进行设定,具体的,此处举出一种可行的方案:每组支撑包括位于顶部的混凝土支撑、位于中部的钢支撑和位于下部的钢支撑,中部钢支撑和下部钢支撑在进深方向上均至少包括两道。作为多种可行选择中的一种,这样设置的好处是,通过一组混凝土支撑与多组钢支撑的配合,可将基坑和巷道内的应力进行合理 分配,能够对基坑和巷道进行可靠的支撑,并能够保证后期足够的施工空间。Further, the concrete supports and steel supports are evenly arranged in the depth direction. In order to facilitate disassembly, the grouping of concrete supports and steel supports is set during construction. Specifically, a feasible method is listed here. Scheme: Each set of supports includes a concrete support at the top, a steel support at the middle and a steel support at the lower part. Both the middle steel support and the lower steel support include at least two in the depth direction. As one of many feasible options, the advantage of this setting is that through the cooperation of one set of concrete supports and multiple sets of steel supports, the stress in the foundation pit and the roadway can be reasonably distributed, and the foundation pit and roadway can be reliably carried out. support, and can ensure sufficient construction space in the later stage.
进一步的,为提高施工过程中的安全可靠性,此处举出一种具体可行的方案:在沿进深方向拼装侧墙块、中板块和顶板块之前,至少在下部钢支撑的多道支撑之间设置临时支撑,临时支撑设置后,拆除施工位置处的中部钢支撑和下部钢支撑,再进行侧墙块、中板块和顶板块的拼装,拼装进行至临时支撑处时,将临时支撑拆除。Further, in order to improve the safety and reliability in the construction process, here is a specific and feasible solution: before assembling the side wall blocks, the middle plate and the top plate along the depth direction, at least one of the multiple supports of the lower steel supports shall be installed. Temporary support is set between the two parts. After the temporary support is set, the middle steel support and the lower steel support at the construction site are removed, and then the side wall blocks, the middle board and the roof board are assembled. When the temporary support is reached, the temporary support is removed.
再进一步,为提高施工过程中的安全可靠性,此处举出额外一种具体可行的方案:在沿进深方向拼装侧墙块、中板块和顶板块之前,至少在混凝土支撑处设置临时支撑,临时支撑设置后,拆除施工位置处的混凝土支撑,再进行侧墙块、中板块和顶板块的拼装。Further, in order to improve the safety and reliability in the construction process, an additional specific and feasible solution is proposed here: before assembling the side wall blocks, the middle plate and the top plate along the depth direction, at least temporary supports are arranged at the concrete supports, After the temporary support is set, the concrete support at the construction site is removed, and then the side wall blocks, the middle block and the roof block are assembled.
进一步的,在施工过程中,不仅是底板块需要进行拼装加强,侧墙块、中板块和顶板块也需要拼装加强,具体的,依次拼装侧墙块、中板块和顶板块时,在进深方向上将若干侧墙块、若干中板块和若干顶板块分别张拉锁紧。Further, in the construction process, not only the bottom plate blocks need to be assembled and strengthened, but also the side wall blocks, the middle plate and the top plate. A number of side wall blocks, a number of middle panels and a number of top panels are tensioned and locked respectively.
进一步的,侧墙块出了张拉锁紧还需要保持预定走向,具体的,侧墙块的外侧设置有围护桩,拼装侧墙块后,将侧墙块与围护桩进行连接紧固。围护桩或围檩均能够对侧墙块进行连接紧固,具体紧固方式可通过千斤顶进行抵紧。Further, the side wall block needs to maintain a predetermined direction after tensioning and locking. Specifically, the outer side of the side wall block is provided with an enclosure pile. After the side wall block is assembled, the side wall block and the enclosure pile are connected and fastened. . The fence piles or the fence purlins can be connected and fastened to the side wall blocks, and the specific fastening method can be tightened by a jack.
进一步的,混凝土支撑设置在基坑和巷道的高处,在拆除时需要进行支撑维护,拆除后吊装转运。具体的,举出如下可行的方案:拆除混凝土支撑时,在混凝土支撑下方设置至少两个牛腿,并对混凝土支撑的两端同时进行切割,混凝土支撑切断后下落在牛腿上。Further, the concrete supports are arranged at the heights of the foundation pit and the roadway, and need to be supported and maintained during the demolition, and then hoisted and transported after demolition. Specifically, the following feasible solutions are given: when the concrete support is removed, at least two corbels are arranged under the concrete support, and both ends of the concrete support are cut simultaneously, and the concrete support falls on the corbel after being cut.
进一步的,牛腿可采用多种材质或结构,此处为了方便切割混凝土支撑,举出一种具体可行的方案:所述的牛腿采用混凝土制成,且采用绳锯 切割混凝土支撑,牛腿上设置有预埋管,绳锯切割混凝土支撑时从预埋管中通过。Further, the corbel can be made of various materials or structures. Here, in order to facilitate the cutting of the concrete support, a specific and feasible solution is given: the corbel is made of concrete, and a wire saw is used to cut the concrete support, and the corbel is There is a pre-embedded pipe on the top, and the wire saw passes through the pre-embedded pipe when cutting the concrete support.
进一步的,在吊装底板块时,此处举出具体的施工操作方式:在进深方向按照环数分组设置底板块,依次设置底板块后逐环吊装、逐环张拉锁紧,每拼装4环进行一次基地注浆,每拼装5~10环进行一次肥槽回填和仰拱回填。Further, when hoisting the floor blocks, the specific construction operation methods are listed here: in the depth direction, the floor blocks are arranged in groups according to the number of rings, and the floor blocks are set in sequence, and then the floor blocks are hoisted ring by ring, tensioned and locked by ring, and 4 rings are assembled each time. Carry out a base grouting, and carry out a fertilizer tank backfill and an inverted arch backfill every 5 to 10 rings assembled.
再进一步,在拼装侧墙版、中板块和顶板块过程中,可同步进行底板块的施工推进,此处举出如下具体的施工操作方式:在进深方向按照环数分组设置底板块,依次设置底板块后,每10~20环进行一次肥槽回填和中板叠合现浇层施工,在底板块拼装完成后,拆除型钢组合固定端,施作预留的后浇带,并进行顶板上方回填,恢复原地面。Further, in the process of assembling the side wall plate, the middle plate and the top plate, the construction of the bottom plate can be carried out synchronously. Here is the following specific construction operation method: in the depth direction, set the bottom plate in groups according to the number of rings, and set them in sequence. After the floor block, carry out the backfilling of the fertilizer tank and the construction of the cast-in-place layer of the middle plate superimposition every 10 to 20 rings. After the assembly of the floor block is completed, remove the fixed end of the section steel combination, apply the reserved post-casting belt, and carry out the top plate. Backfill, restore the original ground.
与现有技术相比,本发明具有的有益效果是:Compared with the prior art, the present invention has the following beneficial effects:
本发明公开的施工方法在进行拼装过程中提供临时支撑,不影响拼装工艺,还可拆除部分预支撑部件,通过该本发明公开的施工方法,在进行基坑和巷道推进施工的过程中同步实现混凝土支撑的拆除,在进行底板块、侧墙块、顶板块等的拼装时可逐步拆除原先的混凝土支撑和钢支撑,拆除过程工艺简单,效率更高,也更安全可靠。The construction method disclosed in the present invention provides temporary support during the assembling process, does not affect the assembling process, and can also remove part of the pre-supported components. Through the construction method disclosed in the present invention, it can be realized synchronously in the process of advancing the construction of the foundation pit and the roadway. For the removal of concrete supports, the original concrete supports and steel supports can be gradually removed when assembling the floor blocks, side wall blocks, roof blocks, etc. The removal process is simple, more efficient, and safer and more reliable.
为了更清楚地说明本发明实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅表示出了本发明的部分实施例,因此不应看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它相关的附图。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the following briefly introduces the accompanying drawings used in the embodiments. It should be understood that the following drawings only show some embodiments of the present invention, and therefore should not be It is regarded as a limitation of the scope. For those of ordinary skill in the art, other related drawings can also be obtained according to these drawings without any creative effort.
图1是吊装第一环底板块的示意图;Fig. 1 is the schematic diagram of hoisting the first ring bottom plate block;
图2是吊装第二环底板块的示意图;Fig. 2 is the schematic diagram of hoisting the second ring bottom plate block;
图3是对底板块进行纵向张拉锁紧的示意图;Figure 3 is a schematic diagram of longitudinal tensioning and locking of the bottom plate block;
图4是底板块施工完成后的示意图;Fig. 4 is the schematic diagram after the floor block construction is completed;
图5是拼装第一环侧墙块、中板块和顶板块的示意图;Fig. 5 is the schematic diagram of assembling the first ring side wall block, the middle block and the roof block;
图6是拆除第一道钢支撑的示意图;Fig. 6 is the schematic diagram of dismantling the first steel support;
图7是拼装第二环和第三环侧墙块、中板块和顶板块的示意图;Fig. 7 is the schematic diagram of assembling the second ring and the third ring side wall block, middle block and roof block;
图8是在钢支撑处增设第二道临时支撑并拆除第二道钢支撑的示意图;Figure 8 is a schematic diagram of adding a second temporary support at the steel support and removing the second steel support;
图9是拼装第四环和第五环侧墙块、中板块和顶板块的示意图;Fig. 9 is the schematic diagram of assembling the fourth ring and the fifth ring side wall block, middle block and roof block;
图10是在钢支撑处增设第三道临时支撑并拆除第三道钢支撑的示意图;Figure 10 is a schematic diagram of adding a third temporary support at the steel support and removing the third steel support;
图11是拼装第六环和第七环侧墙块、中板块和顶板块的示意图;Figure 11 is a schematic diagram of assembling the sixth ring and the seventh ring side wall block, middle block and roof block;
图12是钢支撑处增设第四道临时支撑并拆除第四道钢支撑的示意图;Figure 12 is a schematic diagram of adding a fourth temporary support at the steel support and removing the fourth steel support;
图13是拼装第八环和第九环侧墙块、中板块和顶板块的示意图;Figure 13 is a schematic diagram of assembling the eighth ring and the ninth ring side wall block, middle block and roof block;
图14是施工完成示意图;Figure 14 is a schematic diagram of construction completion;
图15是牛腿的结构示意图;Fig. 15 is the structural representation of corbel;
图16是B-B截面的剖面示意图。16 is a schematic cross-sectional view of the B-B section.
附图中的标号所对应的含义为:1、牛腿;2、混凝土支撑。The corresponding meanings of the symbols in the accompanying drawings are: 1. Corbel; 2. Concrete support.
下面结合附图及具体实施例对本发明做进一步阐释。The present invention will be further explained below with reference to the accompanying drawings and specific embodiments.
在此需要说明的是,对于这些实施例方式的说明用于帮助理解本发明,但并不构成对本发明的限定。本文公开的特定结构和功能细节仅用于描述 本发明的示例实施例。然而,可用很多备选的形式来体现本发明,并且不应当理解为本发明限制在本文阐述的实施例中。It should be noted here that the descriptions of these embodiments are used to help the understanding of the present invention, but do not constitute a limitation of the present invention. Specific structural and functional details disclosed herein are merely illustrative of example embodiments of the present invention. The present invention, however, may be embodied in many alternative forms and should not be construed as limited to the embodiments set forth herein.
实施例Example
本实施例应用于装配式地铁车站,在本实施例中,基坑和巷道依次由42m长现浇段、148m长装配段和28m长现浇段组成。基坑和巷道所在地质主要有素填土、粉质黏土、含黏性土砾砂、强风化凝灰岩、中风化凝灰岩和微风化凝灰岩,基坑和巷道主要位于粉质黏土和含黏性土砾砂中,基地位于强、中风化凝灰岩,抗浮水位标高为12m。This embodiment is applied to a prefabricated subway station. In this embodiment, the foundation pit and the roadway are sequentially composed of a cast-in-place section with a length of 42 m, an assembly section with a length of 148 m, and a cast-in-place section with a length of 28 m. The foundation pits and roadways are mainly located in plain fill, silty clay, cohesive soil gravel, strongly weathered tuff, moderately weathered tuff and slightly weathered tuff. The foundation pits and roadways are mainly located in silty clay and cohesive soil gravel. In the sand, the base is located in strongly and moderately weathered tuff, and the anti-floating water level elevation is 12m.
需要拆除的混凝土支撑横截面尺寸为1000mm×800mm,长度22m,混凝土支撑重量约44t。在修建至拼装阶段的基坑和巷道内进行混凝土支撑的拆除。The size of the cross-section of the concrete support to be removed is 1000mm×800mm, the length is 22m, and the weight of the concrete support is about 44t. Demolition of concrete supports is carried out in foundation pits and roadways from construction to assembly.
具体的,本实施例公开了一种用于装配式地铁车站混凝土支撑拆除的施工方法,在拼装施工过程中逐步拆除支撑,包括:Specifically, the present embodiment discloses a construction method for dismantling concrete supports of a prefabricated subway station. During the assembly construction process, the supports are gradually dismantled, including:
依次吊装若干固定底板块,将底板块在纵深方向上张拉锁紧;Hoist several fixed floor blocks in sequence, and tension and lock the floor blocks in the depth direction;
进行基底注浆、肥槽回填和仰拱回填;Carry out base grouting, fertilizer tank backfill and inverted arch backfill;
按照第一道混凝土支撑下方对应两道钢支撑进行分组,将混凝土支撑和钢支撑在进深方向分成多组;在按照进深推进方向在组内依次拼装侧墙块、中板块和顶板块,在施工前进方向增设临时支撑并拆除组内的钢支撑和混凝土支撑。Group according to the corresponding two steel supports below the first concrete support, and divide the concrete support and steel support into multiple groups in the depth direction; assemble the side wall block, middle plate and top plate in sequence according to the depth advancing direction. Temporary supports were added in the forward direction and steel supports and concrete supports were removed within the group.
如图1~图4所示,具体可按照如下步骤操作:As shown in Figure 1 to Figure 4, the specific steps can be as follows:
S01:吊装第一环底板块A1,与首环固定型钢支架沿纵向张拉锁紧。S01: Hoist the first ring bottom plate block A1, and tension and lock it longitudinally with the first ring fixed section steel bracket.
S02:第二步:吊装第二环底板块A2。S02: The second step: hoist the second ring base plate block A2.
S03:向A1方向移动A2块,将A2块与A1块通过纵向接力式钢棒进 行纵向张拉锁紧。S03: Move the A2 block to the A1 direction, and longitudinally tension and lock the A2 block and the A1 block through the longitudinal relay steel rod.
S04:底板块继续向前逐环吊装、逐环张拉锁紧。每拼装4环进行一次基底注浆,每拼装5~10环可进行一次底板两侧肥槽回填及底板上方仰拱回填,底板拼装与基底注浆、肥槽及仰拱回填可流水作业。完成底板块拼装及注浆、回填等工序。S04: The bottom plate continues to be hoisted forward and ring by ring, and tensioned and locked by ring by ring. Base grouting is carried out once every 4 rings are assembled, and every 5 to 10 rings can be backfilled with fertilizer grooves on both sides of the bottom plate and inverted arch backfilling above the bottom plate. Complete the bottom plate assembly, grouting, backfilling and other processes.
混凝土支撑和钢支撑在进深方向上是按规律均匀排布的,为方便拆卸,在施工时对混凝土支撑和钢支撑的分组进行设定,具体的,此处举出一种可行的方案:每组支撑包括位于顶部的混凝土支撑、位于中部的钢支撑和位于下部的钢支撑,中部钢支撑和下部钢支撑在进深方向上均至少包括两道。作为多种可行选择中的一种,这样设置的好处是,通过一组混凝土支撑与多组钢支撑的配合,可将基坑和巷道内的应力进行合理分配,能够对基坑和巷道进行可靠的支撑,并能够保证后期足够的施工空间。Concrete supports and steel supports are evenly arranged in the depth direction. In order to facilitate disassembly, the grouping of concrete supports and steel supports is set during construction. Specifically, here is a feasible solution: each The group support includes a concrete support at the top, a steel support at the middle and a steel support at the lower part, and both the middle steel support and the lower steel support include at least two in the depth direction. As one of many feasible options, the advantage of this setting is that through the cooperation of one set of concrete supports and multiple sets of steel supports, the stress in the foundation pit and the roadway can be reasonably distributed, and the foundation pit and roadway can be reliably carried out. support, and can ensure sufficient construction space in the later stage.
位于顶部的混凝土支撑,其第一道位于现浇段的施工结束位置处,第二道混凝土支撑与其相聚7.4m,后续每隔8m均匀设置有一道混凝土支撑;位于中部和底部的钢支撑,第一道均设置在距离现浇段施工结束位置3m处,后续每隔4m均匀设置一道钢支撑,且中部钢支撑和下部钢支撑在竖直方向上对齐,第二道混凝土支撑对齐第二道钢支撑,第三道混凝土支撑对齐第四道钢支撑,第三道混凝土支撑对齐第六道钢支撑……以此类推。For the concrete support located at the top, the first line is located at the end of the construction of the cast-in-place section, and the second line of concrete support meets it for 7.4m, followed by a concrete support evenly arranged every 8m; the steel support at the middle and bottom, the first One is set 3m away from the construction end of the cast-in-place section, and then a steel support is evenly set every 4m, and the middle steel support and the lower steel support are vertically aligned, and the second concrete support is aligned with the second steel support Bracing, the third concrete brace aligns with the fourth steel brace, the third concrete brace aligns with the sixth steel brace...and so on.
为提高施工过程中的安全可靠性,此处举出一种具体可行的方案:在沿进深方向拼装侧墙块、中板块和顶板块之前,至少在下部钢支撑的多道支撑之间设置临时支撑,临时支撑设置后,拆除施工位置处的中部钢支撑和下部钢支撑,再进行侧墙块、中板块和顶板块的拼装,拼装进行至临时支撑处时,将临时支撑拆除。In order to improve the safety and reliability in the construction process, here is a specific and feasible solution: before assembling the side wall blocks, the middle plate and the top plate along the depth direction, at least temporarily set up temporary support between the multiple supports of the lower steel support. Support, after the temporary support is set, remove the middle steel support and the lower steel support at the construction site, and then assemble the side wall, middle and top panels. When the assembly reaches the temporary support, remove the temporary support.
临时支撑采用钢支撑,其设置在每组支撑件内部的两道钢支撑之间,且两道钢支撑之间的临时支撑位于中间位置处,其距离前后最近的钢支撑 均为2m。并且设置临时支撑时,第一道最靠近施工位置的钢支撑距离侧墙块、中板块和顶板块的距离为800mm,后续钢支撑距离侧墙块、中板块和顶板块的距离为1m。The temporary support adopts steel support, which is arranged between two steel supports inside each group of supports, and the temporary support between the two steel supports is located in the middle position, and the distance between the nearest steel supports at the front and rear is 2m. And when temporary support is set, the distance between the first steel support closest to the construction position is 800mm from the side wall block, middle plate and roof plate, and the distance between the subsequent steel support and the side wall block, middle plate and roof plate is 1m.
为提高施工过程中的安全可靠性,此处举出额外一种具体可行的方案:在沿进深方向拼装侧墙块、中板块和顶板块之前,至少在混凝土支撑处设置临时支撑,临时支撑设置后,拆除施工位置处的混凝土支撑,再进行侧墙块、中板块和顶板块的拼装。在施工时,临时支撑设置的位置从混凝土支撑往施工位置推进1.6m,相邻两个临时支撑支架的距离为8m。In order to improve the safety and reliability in the construction process, an additional specific and feasible solution is proposed here: before assembling the side wall blocks, the middle plate and the top plate along the depth direction, at least temporary supports shall be provided at the concrete supports, and temporary supports shall be provided. After that, remove the concrete support at the construction site, and then assemble the side wall, middle and top panels. During construction, the position of the temporary support is pushed 1.6m from the concrete support to the construction position, and the distance between two adjacent temporary support brackets is 8m.
如图5~图14所示,具体按照如下步骤操作:As shown in Figure 5 to Figure 14, the specific steps are as follows:
S05:依次拼装第一环侧墙块B1、中板块、顶板块C1,并分别与首环固定型钢支架沿纵向张拉锁紧。中板高度的侧墙块与围护桩钢围檩之间通过千斤顶顶紧,在拆除中板高度支撑前增加临时支撑。S05: Assemble the first ring side wall block B1, the middle block, and the top block C1 in sequence, and tension and lock them longitudinally with the fixed section steel bracket of the first ring respectively. The side wall blocks at the height of the middle slab and the steel purlins of the retaining piles are tightened by jacks, and temporary support is added before the support at the height of the middle slab is removed.
S06:拆除第二排第一道钢支撑G2-1、第三排第一道钢支撑G3-1,创造第2环、第3环构件吊装空间。S06: Remove the first steel support G2-1 in the second row and the first steel support G3-1 in the third row to create a hoisting space for the second and third rings.
S07:依次拼装第二环、第三环的侧墙、中板、顶板,逐环逐块张拉锁紧。中板高度的侧墙与围护桩钢围檩之间通过千斤顶顶紧。S07: Assemble the second ring and the side wall, middle plate and top plate of the third ring in sequence, and tension and lock them one by one. The side wall of the middle plate height and the steel purlin of the retaining pile are tightened by a jack.
S08:在第三环顶板块C3上方增设一道钢支撑HC1,施加预应力后,拆除第一排第二道混凝土支撑H1-2;然后依次拆除第二排第二道钢支撑G2-2、第三排第二道钢支撑G3-2。S08: Add a steel support HC1 above the third ring roof plate C3, after applying prestress, remove the first row of the second concrete support H1-2; then remove the second row of the second steel support G2-2, Three rows of second steel support G3-2.
S09:依次拼装第四环、第五环的侧墙、中板、顶板,逐环逐块张拉锁紧。中板高度的侧墙与围护桩钢围檩之间通过千斤顶顶紧。S09: Assemble the side wall, middle plate, and top plate of the fourth ring and the fifth ring in sequence, and tension and lock the rings one by one. The side wall of the middle plate height and the steel purlin of the retaining pile are tightened by a jack.
S10:依次拆除第二排第三道钢支撑G2-3、第三排第三道钢支撑G3-3。S10: Remove the third steel support G2-3 in the second row and the third steel support G3-3 in the third row in sequence.
S11:依次拼装第六环、第七环的侧墙、中板、顶板,逐环逐块张拉锁紧。中板高度的侧墙与围护桩钢围檩之间通过千斤顶顶紧。S11: Assemble the side wall, middle plate, and top plate of the sixth ring and the seventh ring in sequence, and tension and lock them one by one. The side wall of the middle plate height and the steel purlin of the retaining pile are tightened by a jack.
S12:在第七环顶板块C7上方增设一道钢支撑HC2,施加预应力后,拆除第一排第三道混凝土支撑H1-3;然后依次拆除第二排第三道钢支撑G2-3、第三排第三道钢支撑G3-3。S12: Add a steel support HC2 above the top plate C7 of the seventh ring. After applying prestress, remove the first row of the third concrete support H1-3; then remove the second row of the third steel support G2-3, The third row of three steel supports G3-3.
S13:依次拼装第八环、第九环的侧墙、中板、顶板,逐环逐块张拉锁紧。中板高度的侧墙与围护桩钢围檩之间通过千斤顶顶紧。后续拼装工艺即重复上述步骤。S13: Assemble the side walls, the middle plate and the top plate of the eighth ring and the ninth ring in sequence, and tension and lock the rings one by one. The side wall of the middle plate height and the steel purlin of the retaining pile are tightened by a jack. The subsequent assembly process repeats the above steps.
施工过程中,不仅是底板块需要进行拼装加强,侧墙块、中板块和顶板块也需要拼装加强,具体的,依次拼装侧墙块、中板块和顶板块时,在进深方向上将若干侧墙块、若干中板块和若干顶板块分别张拉锁紧。具体张拉锁紧的方式采用行业内的常规方式即可。During the construction process, not only the bottom plate blocks need to be assembled and strengthened, but also the side wall blocks, the middle plate and the top plate. The wall blocks, some middle blocks and some top blocks are respectively tensioned and locked. The specific tensioning and locking method can adopt the conventional method in the industry.
侧墙块出了张拉锁紧还需要保持预定走向,具体的,侧墙块的外侧设置有围护桩,拼装侧墙块后,将侧墙块与围护桩进行连接紧固。围护桩或围檩均能够对侧墙块进行连接紧固,具体紧固方式可通过千斤顶进行抵紧。After the side wall block is tensioned and locked, it needs to maintain a predetermined direction. Specifically, the outer side of the side wall block is provided with an enclosure pile. After the side wall block is assembled, the side wall block and the enclosure pile are connected and fastened. The fence piles or the fence purlins can be connected and fastened to the side wall blocks, and the specific fastening method can be tightened by a jack.
如图15、图16所示,混凝土支撑设置在基坑和巷道的高处,在拆除时需要进行支撑维护,拆除后吊装转运。具体的,本实施例采用如下可行的方案:拆除混凝土支撑2时,在混凝土支撑2下方设置至少两个牛腿1,并对混凝土支撑2的两端同时进行切割,混凝土支撑切断后下落在牛腿1上。As shown in Figure 15 and Figure 16, the concrete supports are arranged at the heights of the foundation pit and roadway, and need to be supported and maintained during dismantling, and then hoisted and transported after dismantling. Specifically, the present embodiment adopts the following feasible solution: when the concrete support 2 is removed, at least two corbels 1 are arranged under the concrete support 2, and both ends of the concrete support 2 are cut at the same time. on leg 1.
牛腿可采用多种材质或结构,此处为了方便切割混凝土支撑,本实施例举出一种具体可行的方案:所述的牛腿采用混凝土制成,且采用绳锯切割混凝土支撑,牛腿上设置有预埋管,绳锯切割混凝土支撑时从预埋管中通过。A variety of materials or structures can be used for the corbel. Here, in order to facilitate the cutting of concrete support, this embodiment presents a specific and feasible solution: the corbel is made of concrete, and a wire saw is used to cut the concrete support. There is a pre-embedded pipe on the top, and the wire saw passes through the pre-embedded pipe when cutting the concrete support.
在吊装底板块时,此处举出具体的施工操作方式:在进深方向按照环数分组设置底板块,依次设置底板块后逐环吊装、逐环张拉锁紧,每拼装4环进行一次基地注浆,每拼装5~10环进行一次肥槽回填和仰拱回填。When hoisting the floor blocks, the specific construction operation methods are listed here: in the depth direction, set the floor blocks in groups according to the number of rings, set the floor blocks in sequence, hoist them one by one, tension and lock them one by one, and make a base for every 4 rings assembled. Grouting, every 5 to 10 rings are assembled to carry out backfilling of the fertilizer tank and backfilling of the inverted arch.
在拼装侧墙版、中板块和顶板块过程中,可同步进行底板块的施工推进,此处举出如下具体的施工操作方式:在进深方向按照环数分组设置底板块,依次设置底板块后,每10~20环进行一次肥槽回填和中板叠合现浇层施工,在底板块拼装完成后,拆除型钢组合固定端,施作预留的后浇带为1m,并进行顶板上方回填,恢复原地面。In the process of assembling the side wall panels, middle panels and top panels, the construction of the floor panels can be carried out simultaneously. The following specific construction operation methods are listed here: in the depth direction, set the floor panels in groups according to the number of rings, and then set the floor panels in sequence. , every 10 to 20 rings, carry out backfilling of the fertilizer tank and the construction of the cast-in-place layer of the middle plate. After the bottom plate is assembled, remove the fixed end of the steel combination, and apply the reserved post-casting belt of 1m, and carry out the backfill above the top plate. , to restore the original ground.
以上即为本发明列举的实施方式,但本发明不局限于上述可选的实施方式,本领域技术人员可根据上述方式相互任意组合得到其他多种实施方式,任何人在本发明的启示下都可得出其他各种形式的实施方式。上述具体实施方式不应理解成对本发明的保护范围的限制,本发明的保护范围应当以权利要求书中界定的为准,并且说明书可以用于解释权利要求书。The above are the listed embodiments of the present invention, but the present invention is not limited to the above-mentioned optional embodiments. Those skilled in the art can arbitrarily combine the above-mentioned methods to obtain other various embodiments. Various other forms of implementation can be derived. The above specific embodiments should not be construed as limiting the protection scope of the present invention, which should be defined in the claims, and the description can be used to interpret the claims.
Claims (10)
- 一种用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于,在拼装施工过程中逐步拆除支撑,包括:A construction method for dismantling concrete supports of prefabricated subway stations, characterized in that the supports are gradually dismantled during the assembly construction process, including:依次吊装若干固定底板块,将底板块在纵深方向上张拉锁紧;Hoist several fixed floor blocks in sequence, and tension and lock the floor blocks in the depth direction;进行基底注浆、肥槽回填和仰拱回填;Carry out base grouting, fertilizer tank backfill and inverted arch backfill;按照第一道混凝土支撑下方对应若干道钢支撑进行分组,将混凝土支撑和钢支撑在进深方向分成多组;在按照进深推进方向在组内依次拼装侧墙块、中板块和顶板块,在施工前进方向增设临时支撑并拆除组内的钢支撑和混凝土支撑。Group according to the corresponding steel supports below the first concrete support, and divide the concrete supports and steel supports into multiple groups in the depth direction; assemble the side wall blocks, middle blocks and roof blocks in sequence according to the depth advancing direction. Temporary supports were added in the forward direction and steel supports and concrete supports were removed within the group.
- 根据权利要求1所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 1, is characterized in that:每组支撑包括位于顶部的混凝土支撑、位于中部的钢支撑和位于下部的钢支撑,中部钢支撑和下部钢支撑在进深方向上均至少包括两道。Each set of supports includes a concrete support at the top, a steel support at the middle and a steel support at the lower part, and each of the middle steel support and the lower steel support includes at least two in the depth direction.
- 根据权利要求2所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 2, is characterized in that:在沿进深方向拼装侧墙块、中板块和顶板块之前,至少在下部钢支撑的多道支撑之间设置临时支撑,临时支撑设置后,拆除施工位置处的中部钢支撑和下部钢支撑,再进行侧墙块、中板块和顶板块的拼装,拼装进行至临时支撑处时,将临时支撑拆除。Before assembling the side wall block, middle block and roof block along the depth direction, set up temporary supports at least between the multiple supports of the lower steel supports. Assemble the side wall, middle and top panels. When the assembly reaches the temporary support, remove the temporary support.
- 根据权利要求2所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 2, is characterized in that:在沿进深方向拼装侧墙块、中板块和顶板块之前,至少在混凝土支撑处设置临时支撑,临时支撑设置后,拆除施工位置处的混凝土支撑,再进 行侧墙块、中板块和顶板块的拼装。Before assembling the side wall, middle and top panels along the depth direction, set up temporary supports at least at the concrete supports. assembled.
- 根据权利要求1所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 1, is characterized in that:依次拼装侧墙块、中板块和顶板块时,在进深方向上将若干侧墙块、若干中板块和若干顶板块分别张拉锁紧。When assembling the side wall blocks, the middle block and the top block in sequence, tension and lock several side wall blocks, some middle blocks and some top blocks respectively in the depth direction.
- 根据权利要求1或5所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a fabricated subway station according to claim 1 or 5, characterized in that:侧墙块的外侧设置有围护桩,拼装侧墙块后,将侧墙块与围护桩进行连接紧固。The outer side of the side wall block is provided with an enclosure pile, and after the side wall block is assembled, the side wall block and the enclosure pile are connected and fastened.
- 根据权利要求1所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 1, is characterized in that:拆除混凝土支撑时,在混凝土支撑下方设置至少两个牛腿,并对混凝土支撑的两端同时进行切割,混凝土支撑切断后下落在牛腿上。When dismantling the concrete support, at least two corbels are arranged under the concrete support, and both ends of the concrete support are cut at the same time, and the concrete support falls on the corbel after being cut.
- 根据权利要求7所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 7, characterized in that:所述的牛腿采用混凝土制成,且采用绳锯切割混凝土支撑,牛腿上设置有预埋管,绳锯切割混凝土支撑时从预埋管中通过。The corbel is made of concrete, and a wire saw is used to cut the concrete support. The corbel is provided with a pre-buried pipe, and the wire saw passes through the pre-buried pipe when cutting the concrete support.
- 根据权利要求1所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 1, is characterized in that:在进深方向按照环数分组设置底板块,依次设置底板块后逐环吊装、逐环张拉锁紧,每拼装4环进行一次基地注浆,每拼装5~10环进行一次肥槽回填和仰拱回填。In the depth direction, set the floor blocks in groups according to the number of rings, set the floor blocks in sequence, and then hoist them one by one, stretch and lock them one by one, and perform base grouting once every 4 rings assembled, and once every 5 to 10 rings are assembled. Arch backfill.
- 根据权利要求1所述的用于装配式地铁车站混凝土支撑拆除的施工方法,其特征在于:The construction method for dismantling the concrete support of a prefabricated subway station according to claim 1, is characterized in that:在进深方向按照环数分组设置底板块,依次设置底板块后,每10~20环进行一次肥槽回填和中板叠合现浇层施工,在底板块拼装完成后,拆除型钢组合固定端,施作预留的后浇带,并进行顶板上方回填,恢复原地面。In the depth direction, set the floor blocks in groups according to the number of rings. After the floor blocks are set in sequence, the backfilling of the fertilizer tank and the construction of the cast-in-situ layer of the middle plate are carried out every 10 to 20 rings. Apply the reserved post-pouring belt, and backfill the top of the roof to restore the original ground.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010800793.0A CN111926858A (en) | 2020-08-11 | 2020-08-11 | Construction method for dismantling concrete support of assembled subway station |
CN202010800793.0 | 2020-08-11 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2022033503A1 true WO2022033503A1 (en) | 2022-02-17 |
Family
ID=73310262
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2021/111987 WO2022033503A1 (en) | 2020-08-11 | 2021-08-11 | Construction method for dismantling concrete supports of prefabricated subway station |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN111926858A (en) |
WO (1) | WO2022033503A1 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114908794A (en) * | 2022-04-12 | 2022-08-16 | 中铁二院工程集团有限责任公司 | Assembly type construction method of subway station |
CN115110575A (en) * | 2022-06-13 | 2022-09-27 | 中电建南方建设投资有限公司 | Assembling method for assembly type station component |
CN115142431A (en) * | 2022-06-23 | 2022-10-04 | 中国建筑第八工程局有限公司 | Construction method for removing inner supports of foundation pits at two sides with zero distance from operating subway |
CN115506371A (en) * | 2022-10-28 | 2022-12-23 | 中建一局集团建设发展有限公司 | Construction method for dismantling ultrahigh inner support of deep foundation pit |
CN115627780A (en) * | 2022-12-23 | 2023-01-20 | 中国建筑第六工程局有限公司 | Foundation pit supporting structure and construction method thereof |
CN115853570A (en) * | 2023-02-24 | 2023-03-28 | 中建六局(天津)绿色建筑科技有限公司 | Prefabricated rail top air duct assembly type structure based on foamed ceramics and construction method |
CN116950129A (en) * | 2023-09-19 | 2023-10-27 | 北京建工土木工程有限公司 | Construction method for connecting subway station main body with auxiliary structure and post-pouring belt |
CN118187993A (en) * | 2024-04-16 | 2024-06-14 | 中铁建华南建设(广州)高科技产业有限公司 | Construction method of assembled rail top air duct |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111926858A (en) * | 2020-08-11 | 2020-11-13 | 中铁八局集团昆明铁路建设有限公司 | Construction method for dismantling concrete support of assembled subway station |
CN113062354A (en) * | 2021-03-26 | 2021-07-02 | 北京城建设计发展集团股份有限公司 | Assembly method for prefabricated subway station of open-cut pile support system |
CN113216257A (en) * | 2021-06-01 | 2021-08-06 | 中铁四局集团有限公司 | Full hoisting construction method for assembled subway station in pile anchor enclosing structure system |
CN113668601B (en) * | 2021-07-22 | 2023-04-14 | 中铁八局集团昆明铁路建设有限公司 | Subway station assembly section construction method for open cut foundation pit steel support supporting system |
CN115125995B (en) * | 2022-06-13 | 2024-05-10 | 中电建南方建设投资有限公司 | Construction method for entrance and exit ring frames of assembled station |
CN115288149B (en) * | 2022-06-28 | 2024-04-16 | 北京城建设计发展集团股份有限公司 | Auxiliary ring frame under assembled support system and construction method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11152761A (en) * | 1997-11-19 | 1999-06-08 | Kajima Corp | Underground structure and construction method thereof |
WO2013147652A2 (en) * | 2012-03-30 | 2013-10-03 | Общество с ограниченной ответственностью "Инженерное бюро Юркевича" | Metro station and method for constructing same |
CN105926669B (en) * | 2016-04-29 | 2018-04-20 | 广州地铁设计研究院有限公司 | A kind of Construction Method of Metro Station |
CN107130629B (en) * | 2017-05-03 | 2019-05-17 | 中铁十六局集团地铁工程有限公司 | A kind of assembled station construction method using anchor cable and bracing members building enclosure |
CN106703828B (en) * | 2017-01-22 | 2019-06-21 | 济南轨道交通集团有限公司 | The construction method of subway station is built using prefabricated assembled lining cutting combination PBA |
CN111926858A (en) * | 2020-08-11 | 2020-11-13 | 中铁八局集团昆明铁路建设有限公司 | Construction method for dismantling concrete support of assembled subway station |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755701A (en) * | 2018-06-21 | 2018-11-06 | 腾达建设集团股份有限公司 | The construction method of the support construction of deep basal pit |
RU2717324C1 (en) * | 2019-07-29 | 2020-03-20 | Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" | Upper transverse abutment of approach tunnel to operating metro station, constructed without interruption of operation of station with middle and side tunnels |
-
2020
- 2020-08-11 CN CN202010800793.0A patent/CN111926858A/en active Pending
-
2021
- 2021-08-11 WO PCT/CN2021/111987 patent/WO2022033503A1/en active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11152761A (en) * | 1997-11-19 | 1999-06-08 | Kajima Corp | Underground structure and construction method thereof |
WO2013147652A2 (en) * | 2012-03-30 | 2013-10-03 | Общество с ограниченной ответственностью "Инженерное бюро Юркевича" | Metro station and method for constructing same |
CN105926669B (en) * | 2016-04-29 | 2018-04-20 | 广州地铁设计研究院有限公司 | A kind of Construction Method of Metro Station |
CN106703828B (en) * | 2017-01-22 | 2019-06-21 | 济南轨道交通集团有限公司 | The construction method of subway station is built using prefabricated assembled lining cutting combination PBA |
CN107130629B (en) * | 2017-05-03 | 2019-05-17 | 中铁十六局集团地铁工程有限公司 | A kind of assembled station construction method using anchor cable and bracing members building enclosure |
CN111926858A (en) * | 2020-08-11 | 2020-11-13 | 中铁八局集团昆明铁路建设有限公司 | Construction method for dismantling concrete support of assembled subway station |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114908794A (en) * | 2022-04-12 | 2022-08-16 | 中铁二院工程集团有限责任公司 | Assembly type construction method of subway station |
CN114908794B (en) * | 2022-04-12 | 2023-05-16 | 中铁二院工程集团有限责任公司 | Assembled building method of subway station |
CN115110575A (en) * | 2022-06-13 | 2022-09-27 | 中电建南方建设投资有限公司 | Assembling method for assembly type station component |
CN115142431A (en) * | 2022-06-23 | 2022-10-04 | 中国建筑第八工程局有限公司 | Construction method for removing inner supports of foundation pits at two sides with zero distance from operating subway |
CN115142431B (en) * | 2022-06-23 | 2024-03-12 | 中国建筑第八工程局有限公司 | Construction method for dismantling supports in foundation pits on two sides at zero distance from operation subway |
CN115506371A (en) * | 2022-10-28 | 2022-12-23 | 中建一局集团建设发展有限公司 | Construction method for dismantling ultrahigh inner support of deep foundation pit |
CN115627780A (en) * | 2022-12-23 | 2023-01-20 | 中国建筑第六工程局有限公司 | Foundation pit supporting structure and construction method thereof |
CN115853570A (en) * | 2023-02-24 | 2023-03-28 | 中建六局(天津)绿色建筑科技有限公司 | Prefabricated rail top air duct assembly type structure based on foamed ceramics and construction method |
CN116950129A (en) * | 2023-09-19 | 2023-10-27 | 北京建工土木工程有限公司 | Construction method for connecting subway station main body with auxiliary structure and post-pouring belt |
CN116950129B (en) * | 2023-09-19 | 2024-01-19 | 北京建工土木工程有限公司 | Construction method for connecting subway station main body with auxiliary structure and post-pouring belt |
CN118187993A (en) * | 2024-04-16 | 2024-06-14 | 中铁建华南建设(广州)高科技产业有限公司 | Construction method of assembled rail top air duct |
Also Published As
Publication number | Publication date |
---|---|
CN111926858A (en) | 2020-11-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2022033503A1 (en) | Construction method for dismantling concrete supports of prefabricated subway station | |
CN109162296B (en) | Single-side formwork supporting system and construction method for pouring outer wall by utilizing same | |
CN110159298B (en) | Subway underground excavation station primary support buckling arch construction method | |
CN106522236B (en) | The structure and construction method of pattern foundation pit supporting structure | |
CN110863841A (en) | Two-lining three-step construction method for large-span shallow-buried underground excavation tunnel | |
CN110106892B (en) | Construction method for large-span breaking of underground diaphragm wall | |
CN108612110A (en) | A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting | |
CN109139049B (en) | Construction method for secondary lining buckling arch of underground excavation station of subway | |
CN112681332A (en) | Construction method for supporting system by using steel sheet piles in complex environment | |
CN110777802A (en) | Deep foundation pit high-low span supporting structure and construction method thereof | |
EP1021640B1 (en) | Arched support structure | |
CN116289491A (en) | String beam formula foundation ditch steel landing stage | |
CN113417300B (en) | Slope support system and construction method thereof | |
CN212506301U (en) | Support system in combination assembled forever | |
CN114526083A (en) | Mine method tunnel segment shield large longitudinal slope air-pushing and translation transition construction method | |
CN106013783A (en) | Formwork support and erecting method thereof | |
CN112030995B (en) | Construction method for quickly taking out of ground for supporting and disassembling in advance for main building of super high-rise building | |
CN111778990A (en) | Permanent-temporary combined assembly type inner support system and construction method | |
CN110159312B (en) | Method for repairing straight wall circular arch tunnel lining | |
CN217328763U (en) | Counter-force support system for pipe jacking construction | |
CN112459787A (en) | Construction method of large-section large-gradient tunnel | |
CN107299596B (en) | Concrete support trestle plate lower supporting beam template system and construction method thereof | |
JP7225356B2 (en) | Press bars and struts for open shield construction | |
KR20040031451A (en) | Prestressed scaffolding method | |
CN113417664A (en) | Tunnel construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 21855554 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 21855554 Country of ref document: EP Kind code of ref document: A1 |