WO2020091087A1 - 하프장전 방법을 이용한 암반발파 방법 - Google Patents

하프장전 방법을 이용한 암반발파 방법 Download PDF

Info

Publication number
WO2020091087A1
WO2020091087A1 PCT/KR2018/012887 KR2018012887W WO2020091087A1 WO 2020091087 A1 WO2020091087 A1 WO 2020091087A1 KR 2018012887 W KR2018012887 W KR 2018012887W WO 2020091087 A1 WO2020091087 A1 WO 2020091087A1
Authority
WO
WIPO (PCT)
Prior art keywords
blasting
hole
comparative example
time
excavation
Prior art date
Application number
PCT/KR2018/012887
Other languages
English (en)
French (fr)
Inventor
양형식
김정규
김승준
정승원
김남수
카칸발루치
Original Assignee
전남대학교산학협력단
(주)엔에스비 나우이엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 전남대학교산학협력단, (주)엔에스비 나우이엔씨 filed Critical 전남대학교산학협력단
Priority to PCT/KR2018/012887 priority Critical patent/WO2020091087A1/ko
Publication of WO2020091087A1 publication Critical patent/WO2020091087A1/ko

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/08Tamping methods; Methods for loading boreholes with explosives; Apparatus therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Definitions

  • the present invention relates to a method for rock blasting that increases construction speed by using half charge blasting and simplifies the working process to reduce construction costs.
  • FIG. 1 is a flowchart of a general blasting method
  • FIG. 2 is a conceptual diagram of a construction of a general blasting method.
  • the general blasting method includes a first step (S10) of drilling a blasting hole 11, a second step of charging the explosives 21 in the blasting hole 11 (S20), and a blasting hole ( It consists of a third step (S30) of blasting the explosives charged in the inside, and a fourth step (S40) of processing the generated force after blasting, and then repeatedly repeating the process of drilling a blast hole by a predetermined length again. Excavation is being carried out.
  • the method of increasing the excavation length in most one excavation is used, and the explosive capacity is increased to increase excavation efficiency.
  • the present invention is to solve the problems of the prior art, by increasing the construction speed by using half-loading to perform blasting by charging explosives within a loading length range of less than 1/2 of the blasting hole and simplifying the working process It is to provide a rock blasting method to reduce the.
  • the rock blasting method according to the present invention for achieving this object is produced after blasting after blasting a blast hole, charging an explosive within a load length range of 1/2 or less with respect to the entire length of the blast hole, and performing the first blasting. It is characterized in that it processes the burping force and re-explodes the explosives for the remaining length in the blasting hole to perform blasting two or more times.
  • the loading length of the explosive for the first blasting is longer than 1/3, and the blasting ball is a V-cut (V-cut) that has a slope in the left and right symmetrical to the cardiac ball with respect to the center line of the membrane surface. ) Perforation is made by the construction method.
  • Rock blasting method by blasting the blasting hole, charges the explosives within a loading length range of 1/2 or less with respect to the total length of the blasting hole, performs the primary blasting, and then processes the generated force after blasting.
  • the second blasting can be carried out to increase the construction speed and simplify the work process, thereby reducing air shortening and construction cost.
  • FIG. 3 is a flowchart of a rock blasting method according to an embodiment of the present invention.
  • FIG. 4 is a conceptual diagram of a rock blasting method according to an embodiment of the present invention.
  • FIG. 5 is a front view showing a perforation pattern for tunnel blasting
  • FIG. 6 and 7 are A-A cross-sectional pattern diagrams of FIG. 5, and a perforation pattern diagram according to the present embodiment in the present invention.
  • Figure 8 is a perforation pattern diagram according to the prior art
  • 11 to 13 is a graph of the results of the regression analysis for this example and the comparative example
  • CMS 3D laser scanner
  • FIG. 3 is a flowchart of a rock blasting method according to an embodiment of the present invention
  • FIG. 4 is a conceptual diagram of a construction of a rock blasting method according to an embodiment of the present invention.
  • the rock blasting method of this embodiment (a) blasting hole 111 step (S110), and (b) the total length of the blasting hole 111 (L) 1 / Step (S120) of charging the explosive (121) within a loading length range of 2 or less (S130), (C) blasting the charged explosive (121) in the blasting hole (111) (S130), (d) generated after blasting Step (S140) for processing the burr force, (e) reloading the explosive 131 for the remaining length (residual hole) of the blasting hole 111 (S210), and (f) reloading the explosive (131) ) (S220).
  • step (a) (S110) is a process of selecting a puncture location and drilling a blast hole 111, taking into account the purpose of blasting, explosives used, the nature of the rock, the condition of the free surface, etc. Determine the size. Meanwhile, a sealing process may be added when a leak occurs in the free surface.
  • step (B) step (S120) is a charge process, charges the explosives 121 within the range of L / 2 or less with respect to the total length (L) of the blasting hole 111.
  • the half loading length is L / 3 or more and L / 2 or less.
  • a well-known guider or holder may be used to insert the explosive into the correct position in the charge hole in the charge process, and may further include a color transfer process.
  • blasting can be made by dividing the total blasting hole length into three or more times in consideration of the rock grade and the like.
  • the blasting method using the harb loading of the present invention made in this way, it is possible to perform the drilling operations corresponding to 2 or 3 times at a time and perform the blasting operation according to the amount of explosives. Therefore, when performing the drilling operation of the general blasting method Since the time required for equipment movement and preparation time can be reduced, the working time can be shortened. For example, in the case of road tunnels, blasting is performed twice a day, but even if a small disruption occurs in the work process, blasting may not be performed twice, so in tunnel blasting excavation with a tunnel length of several kilometers. A half-loaded blasting technique, seen in the field where there is a risk of overtime, can be a solution.
  • excavation is usually performed twice a day in the morning (perforation-charge-blasting-burst treatment) and afternoon operation (perforation-charge-blasting-burst treatment).
  • first blasting is performed once a day, or the drilling time of the afternoon work is shortened (shortening the fabrication plant), resulting in a shorter excavation site and an increase in the blasting period.
  • the present invention is relatively safe from the risk of exceeding the daily work cycle by reducing the drilling time and simplifying the construction, and because of the good excavation efficiency due to the nature of the construction method, the overall construction period can be shortened to reduce the overall construction cost.
  • FIG. 5 is a front view showing a perforation pattern for tunnel blasting
  • FIGS. 6 and 7 are A-A cross-sectional pattern views of FIG. 5 and are perforation pattern diagrams according to the present embodiment during horizontal drilling.
  • FIG. 8 shows a perforation pattern diagram according to a conventional construction method for the A-A cross section of FIG. 5 for comparison.
  • the half-loading of the present invention was carried out in a general V-cut blasting method to experimentally confirm the possibility of an improved construction method by using a half-loading blasting system and an increase in vibration reduction effect and excavation efficiency compared to the same excavation amount.
  • test blasting was conducted by following the general loading method (comparative example) and half loading method (this example) in the V-cut blasting method at 00 Cement 00 mine in Jangseong-gun.
  • 9 is a perforation pattern diagram (front view and cross-sectional view) applied to the present embodiment for this test blasting
  • FIG. 10 is a perforation pattern diagram (front view and cross-section view) applied to a comparative example (general blasting) for this test blasting to be.
  • the total length of the blasting hole is 3.6 m and blasting is performed by charging the blasting hole of 1.8 m from the primary blasting (half blasting), and the blasting is performed by reloading the blasting hole of the remaining 1.8 m in the secondary blasting (residual blasting). It was done.
  • blasting was performed by setting the total length of the blasting hole to 1.8 m. In this example and the comparative example, the test was conducted by applying the same blasting conditions to each other except for the length of the blasting hole.
  • the comparative example means general blasting by a general V-cut charge
  • the half load means a charge at half of the entire length of the blast hole, and the residue charges at the remaining blast hole after the half blast.
  • primary blasting means blasting by half loading
  • secondary blasting means blasting by residual loading after primary blasting.
  • [Table 2] shows the regression analysis formula used, the maximum loading amount per delay is 11.25 kg / delay, and the separation distance is applied to the blasting location and the installation point of the instrument using the coordinates on the drawing (CAD), and the maximum particle size. Regression analysis was performed using the rate (PPV) and the maximum charge per delay. The regression analysis equations for the square root and the cubic root with 95% reliability were derived.
  • the analysis method changes the separation distance from the blasting point during excavation, performs a regression analysis to check the propagation characteristics of the blasting vibration, and performs a blasting operation (blaster operation) at the site, which is the minimum separation distance of 100m.
  • the expected vibration value (mm / sec) at the minimum separation distance 20m (directly below the blasting source, the thickness of the crown pillar 20m) where the excavation work is performed with the blasting source is compared with the comparative example (general method) and the vibration reduction rate of this embodiment. Each was compared.
  • [Table 2] shows the results of vibration prediction for each separation distance (m).
  • the comparative example general blasting
  • when working with 11.25kg of charge per foot used in the field according to the square root prediction formula at the point of 20m
  • a vibration value of 1.71 cm / sec is predicted at a point of 71.34 cm / sec and 100 m.
  • vibration values of 71.2 cm / sec at 20 m and 1.70 cm / sec at 100 m are predicted.
  • vibration values of 21.25 cm / sec at the 20 m point and 1.36 cm / sec at the 100 m point are predicted, and according to the trigonometric prediction equation, 11.9 cm at the 20 m point
  • the vibration value of 0.71 cm / sec is predicted at / sec and 100m.
  • the vibration value of 40.51 cm / sec at the 20 m point and 1.27 cm / sec at the 100 m point is predicted, and according to the trigeminal root prediction formula, 40.49 cm / at the 20 m point A vibration value of 1.27 cm / sec is predicted at the sec and 100 m points.
  • the square root and tristem root prediction formulas are applied, and when the vibration prediction values of the distances of 20 m and 100 m are both, vibration reduction is predicted by at least 20% or more.
  • a vibration reduction of at least 25% is expected.
  • the half-blasting of this example had a lower initial vibration value compared to the comparative example (normal blasting), and the residual hole blasting of this example was analyzed to have a higher vibration damping rate than the comparative example (normal blasting). .
  • 11 is a blasting regression graph for a comparative example, (a) is a square root regression graph, and (b) is a triple root regression graph.
  • 12 is a graph of a regression analysis for the present embodiment (half blasting; first round), (a) is a square root regression graph, and (b) is a quadriceps regression graph.
  • 13 is a regression analysis graph for the present embodiment (residual blasting; second round), (a) is a square root regression graph, and (b) is a trigonometric regression graph.
  • the refractive index (%) is calculated as (Guljinjang / Chun factory) ⁇ 100, and was judged as 'success' when the refractive index increased by about 10% compared to the comparative example.
  • the average excavation efficiency was measured to be 75.28%, and in the case of the half-load in this example, the average excavation efficiency was measured to be 85.50%. Since the method of measuring the length of the excavation has a limitation in measuring the residual length of the entire hole, the excavation length was inverted by the blasting excavation volume using a 3D scanner. The experiment was conducted in the same closet, and the experiment was performed by crossing the comparative example (general blasting) and this example (half loading). As a result, the half loading method of this example was 10.2% higher than that of the mill. It increased, and it was confirmed that the refractive index increased by at least 10.6% and at most 13.5% compared to the comparative example (normal blasting). Therefore, it can be expected that it is possible to shorten the working time and construction period of the long-lasting tunnel blasting construction.
  • V-cut (comparative example) 1.8 116.61 64 7 68 75 standard No. 2 V-cut (this example) 3.6 249.66 70 7 113 120 success No. 3 V-cut (this example) 3.6 249.66 70 7 116 121 success No. 4 V-cut (this example) 3.6 249.66 70 7 107 114 success No. 5 V-cut (comparative example) 1.8 116.61 64 7 65 72 standard No. 6 V-cut (this example) 3.6 249.66 70 7 112 119 success No. 7 V-cut (this example) 3.6 249.66 70 7 106 112 success
  • both the general method and the proposed method were calculated on the basis of the blasting pattern, and due to the nature of the method, in the case of the half-loading of the present embodiment, the comparative example (general blasting) was performed twice in advance, so that the comparative example was twice drilled (3.6m).
  • the puncture time was compared with the average puncture time of this example (3.6m).
  • the drilling time of the comparative example No. 1 + No. 5
  • the average drilling time of the present example No. 2, 3, 4, 6, 7) were compared.
  • the preparation time bit change, equipment movement, preparation for drilling work, etc.
  • the average value was applied equally to each method (420 seconds). Comparative Example Since the first marking operation was not performed, the marking operation time was excluded from the drilling operation time.
  • the punching time of the two comparative example methods took 147 minutes, and the half-loading punching time of this example was at least 112 minutes and a maximum of 121 minutes, with an average of about 117 minutes.
  • the marking time was compared with the comparative example, and the average number of working hours was calculated by adding 6 holes in this example, and the drilling time was expressed by the total drilling time including the preparation time for dot-board drilling.
  • the charging time is applied using an anpo loader in the field, and the average working time of each method is applied, and the blasting time is the average blasting preparation time excluding the ventilation time.
  • the average processing time of each method was applied when 15 25-ton dumps were operated at the test site.
  • the scaling time is processed by applying the average working time as in the case of the work after the next blasting (excluding the remaining processing time).
  • the average working time is a comparison of the average working time of the comparative example and the present embodiment (half + residual) for two times, and the result of analyzing a total of 12 blasting working hours is the excavation working time of the comparative example (2 times). An average of 447 minutes was measured, and the average excavation working time of this example (half + residue) was 398.2 minutes.
  • this embodiment it can be seen that the drilling cycle time of about 10.9% is shortened compared to the comparative example. Therefore, this embodiment is safe from the risk of exceeding the daily work cycle time compared to the comparative example, and it is possible to shorten the entire excavation construction period due to the increase in the excavation rate due to the method characteristics.
  • the blasting method using the half load of the present invention has the following features. 1) It can be applied to all blasting patterns such as vertical drilling, horizontal drilling, and inclined drilling. 2) Applicability is excellent at the site where security objects are around, and construction period is shortened and construction cost is reduced. 3) Applicable regardless of the type of explosive, such as powdered explosive, cartridge explosive, and bulk explosive. 4) Air-Deck effect expression, multi-stage charging method is possible. 5) It can be applied to various blasting methods such as open blasting, tunnel blasting, and vertical blasting.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Earth Drilling (AREA)

Abstract

본 발명은 하프장전 방법(half charge blasting)을 이용하여 시공속도를 증가시키고 작업공정을 단순화하여 공사비를 절감하는 암반발파를 위한 방법에 관한 것으로, 발파공을 천공하여 상기 발파공의 전체 길이에 대해 1/2 이하의 장전 길이 범위 내에서 폭약을 장약하고 1차 발파를 실시한 후에 발파후 생성된 버력을 처리하며, 상기 발파공 내의 잔여 길이에 대해 폭약을 재장전하여 2차 발파를 실시하는 것을 특징으로 한다.

Description

하프장전 방법을 이용한 암반발파 방법
본 발명은 하프장전 방법(half charge blasting)을 이용하여 시공속도를 증가시키고 작업공정을 단순화하여 공사비를 절감하는 암반발파를 위한 방법에 관한 것이다.
도 1은 일반적인 발파공법의 흐름도이며, 도 2는 일반적인 발파공법의 시공 개념도이다.
도 1 및 도 2를 참고하면, 일반적인 발파공법은 발파공(11)을 천공하는 제1단계(S10)와, 발파공(11) 내에 폭약(21)을 장약하는 제2단계(S20)와, 발파공(11) 내에 장약된 폭약을 발파하는 제3단계(S30)와, 발파후 생성된 버력을 처리하는 제4단계(S40)로 이루어지며, 이후 다시 일정 길이만큼 발파공을 천공하는 과정을 계속적으로 반복하여 굴착작업을 수행하고 있다.
일반적으로 발파방법을 이용하여 굴착시공 속도를 증가시키기 위하여 대부분 1회 굴착 시 굴진장을 증가시키는 방법을 사용하고 굴진효율을 높이기 위하여 폭약사용량을 늘리게 된다.
그러나 도심지나 보안건물이 위치한 곳에서는 진동 및 소음발생 증가로 인하여 이러한 방법의 발파굴착 공법의 적용이 어렵다.
또한, 진동을 저감하기 위한 다양한 발파굴착 방법 중 뇌관 기폭초시를 조절하여 지발당 장약량을 줄이는 방법과, 공당 장약량을 줄이는 방법이 있지만 폭약사용량 감소는 굴진장 감소로 결국 시공속도가 저하되는 문제점이 있다.
선대구경 천공방법이나 기계굴착의 경우 일반 발파공법에 비해 진동이 저감되지만 추가 장비가 필요하고 작업 효율성 및 시공성 저하로 결국 이는 공사비 증가로 귀결된다.
[선행기술문헌]
[특허문헌]
대한민국 등록특허공보 특0143712호(1998.04.10. 등록)
본 발명은 이러한 종래기술의 문제점을 해소하기 위한 것으로, 발파공의 1/2 이하의 장전 길이 범위 내에서 폭약을 장약하여 발파를 수행하는 하프장전을 이용하여 시공속도를 증가시키고 작업공정을 단순화하여 공사비를 절감하는 암반발파 방법을 제공하고자 하는 것이다.
이러한 목적을 달성하기 위한 본 발명에 따른 암반발파 방법은, 발파공을 천공하여 상기 발파공의 전체 길이에 대해 1/2 이하의 장전 길이 범위 내에서 폭약을 장약하고 1회차 발파를 실시한 후에 발파 후 생성된 버력을 처리하며, 상기 발파공 내의 잔여 길이에 대해 폭약을 재장전하여 2회차 이상 발파를 실시하는 것을 특징으로 한다.
바람직하게는, 1회차 발파를 위한 폭약의 장전 길이는 1/3 보다는 더 길며, 상기 발파공은 막장면의 중심선을 기준으로 심발공을 좌우에 대칭 형태로 경사를 갖게 되는 브이-커트(V-cut) 공법에 의해 천공이 이루어진다.
본 발명에 따른 암반발파 방법은, 발파공을 천공하여 상기 발파공의 전체 길이에 대해 1/2 이하의 장전 길이 범위 내에서 폭약을 장약하고 1차 발파를 실시한 후에 발파 후 생성된 버력을 처리하며, 상기 발파공 내의 잔여 길이에 대해 폭약을 재장전하여 2차 발파를 실시함으로써 시공속도를 높이고 작업공정을 단순화하여 공기 단축과 공사비를 절감할 수 있다.
도 1은 일반적인 발파공법의 흐름도,
도 2는 일반적인 발파공법의 시공 개념도,
도 3은 본 발명의 실시예에 따른 암반발파 방법의 흐름도,
도 4는 본 발명의 실시예에 따른 암반발파 방법의 시공 개념도,
도 5는 터널 발파용 천공 패턴을 보여주는 정면도,
도 6 및 도 7은 도 5의 A-A 단면 패턴도로서 본 발명에 본 실시예에 따른 천공 패턴도,
도 8은 종래기술에 따른 천공 패턴도,
도 9는 본 실시예에 따른 실험발파를 위한 천공 패턴도,
도 10은 비교예에 따른 실험발파를 위한 천공 패턴도,
도 11 내지 도 13은 본 실시예와 비교예에 대한 회귀분석 결과 그래프,
도 14는 3차원 레이저 스캐너(CMS)를 이용하여 공동기관에서 제안한 3차원 굴진장 평가과정을 간략히 보여주는 도면.
이하, 본 발명의 실시예를 첨부 도면을 참고하여 상세히 설명하면 다음과 같다.
도 3은 본 발명의 실시예에 따른 암반발파 방법의 흐름도이며, 도 4는 본 발명의 실시예에 따른 암반발파 방법의 시공 개념도이다.
도 3 및 도 4를 참고하면, 본 실시예의 암반발파 방법은, (a) 발파공(111)을 천공하는 단계(S110)와, (b) 발파공(111)의 전체 길이(L)에 대해 1/2 이하의 장전 길이 범위 내에서 폭약(121)을 장약하는 단계(S120)와, (c) 발파공(111) 내에 장약된 폭약(121)을 발파하는 단계(S130)와, (d) 발파후 생성된 버력을 처리하는 단계(S140)와, (e) 발파공(111)의 잔여 길이(잔류공)에 대해 폭약(131)을 재장약하는 단계(S210)와, (f) 재장약된 폭약(131)을 발파하는 단계(S220)를 포함한다.
구체적으로, (a)단계(S110)는 천공 위치를 선정하고 발파공(111)을 천공하는 과정으로서, 발파 목적, 사용 폭약, 암반의 성질, 자유면의 상태 등을 고려하여 발파공의 위치, 깊이, 크기를 결정한다. 한편, 자유면에서 누수가 발생 시에 씰링(sealing) 과정이 추가될 수 있다.
(b)단계(S120)는 장약 과정으로서, 발파공(111)의 전체 길이(L)에 대해 L/2 이하의 범위 내에서 폭약(121)을 장약한다. 바람직하게는, 하프 장전 길이는 L/3 이상이고 L/2 이하이다. 한편, 장약 과정에서 폭약을 장약공 내의 정확한 위치에 삽입 위치시키기 위하여 주지의 가이더 또는 홀더가 사용될 수 있으며, 전색 과정을 더 포함할 수 있다.
다음으로, 발파 단계(S130)와, 1차 발파 이후에 발생된 버력을 처리하는 버력 처리 단계(S140)가 이루어지며, 이후 나머지 잔류공(111a)에 폭약(131)의 재장약 단계(S210)와 2차 발파 단계(S220)가 진행된다.
본 실시예에서는 전체 발파공을 2회로 나누어 발파가 이루어지는 것을 예시하여 설명하였으나, 암반등급 등을 고려하여 전체 발파공 길이에 대해 3회차 이상으로 나누어 발파가 이루어질 수 있음을 이해하여야 할 것이다.
이와 같이 이루어지는 본 발명의 하브 장전을 이용한 발파방법은 2, 3회에 해당되는 천공작업을 한 번에 작업하고 폭약 사용량에 맞춰서 발파 작업을 수행할 수 있으며, 따라서 일반 발파방법의 천공 작업을 진행할 경우 장비 이동과 준비시간에 소요되는 시간을 줄일 수 있기 때문에 작업시간을 단축할 수 있다. 예를 들어, 도로터널의 경우에 하루 2회 발파를 진행하는데 작업공정에 작은 차질이 발생하여도 2회 발파를 진행하지 못하는 경우가 발생되며, 따라서 터널 연장이 수 km에 달하는 터널 발파 굴착 작업에서 작업 사이클 타임 초과 위험이 있는 현장에서 본 하프장전 발파공법은 해결책이 될 수 있다.
즉, 터널 발파굴착 공사의 경우 보통 하루에 오전 작업(천공-장약-발파-버력 처리)과 오후 작업(천공-장약-발파-버력 처리)으로 2회 굴착이 진행된다. 이러한 작업 과정에서 중간에 공정이 잘못되거나 시간이 초과했을 때 하루에 1회 발파만 진행되거나 오후 작업의 천공시간이 짧아져서(천공장을 짧게 함) 결국 굴진장이 짧아지고 발파공사 기간이 증가한다.
반면에 본 발명은 상대적으로 천공시간을 줄이고 작업시공을 단순화하여 1일 작업 사이클 초과 위험으로부터 안전하며, 공법 특성상 굴진효율이 좋기 때문에 전체 공사기간이 단축되어 전체 공사비를 절감할 수 있다.
도 5는 터널 발파용 천공 패턴을 보여주는 정면도로서, 도 6 및 도 7은 도 5의 A-A 단면 패턴도로서 수평 천공 시에 본 실시예에 따른 천공 패턴도이다. 참고로, 비교를 위하여 도 8에서는 도 5의 A-A 단면에 대한 종래 시공방법에 따른 천공 패턴도를 보여주고 있다.
이하에서는 구체적인 실험예에 대하여 설명한다.
실험예
일반 V-cut 발파공법에 본 발명의 하프장전을 실시하여 동일굴착량 대비 진동저감 효과 및 굴진효율 증가와 하프장전 발파시스템을 활용하여 개선된 시공방법의 가능성을 실험적으로 확인하였다.
장성군 소재의 00시멘트 00광산에서 V-cut 발파공법에 일반장전 방법(비교예)과 하프장전 방법(본 실시예)을 따라서 시험발파를 진행하였다. 도 9는 본 시험발파을 위하여 본 실시예에 적용된 천공 패턴도(정면도 및 그 단면도)이며, 도 10은 본 시험발파를 위하여 비교예(일반 발파)에 적용된 천공 패턴도(정면도 및 그 단면도)이다.
본 실시예는 발파공의 전체 길이를 3.6m이고 1차 발파(하프발파)에서 1.8m의 발파공에 장약하여 발파가 이루어지며 2차 발파(잔류공 발파)에서 나머지 1.8m의 발파공에 재장약하여 발파가 이루어졌다. 한편, 비교예는 발파공의 전체 길이를 1.8m로 하여 발파가 이루어졌다. 본 실시예와 비교예는 각각 발파공의 길이를 제외하고 나머지 발파 조건은 동일하게 적용하여 시험이 이루어졌다. 이하 설명에서 비교예는 일반 V-cut 장약에 의한 일반발파를 의미하며, 본 실시예에서 하프장전은 발파공의 전체 길이에 대해 절반 부에 장약을 의미하고, 잔류는 하프 발파 후에 잔여 발파공에 장약하는 것을 의미한다. 또한, 이하 설명에서 1차 발파는 하프 장전에 의한 발파를 의미하고 2차 발파는 1차 발파 후에 잔류 장전에 의한 발파를 의미한다.
Figure PCTKR2018012887-appb-T000001
[표 2]는 사용된 회귀분석 식을 보여주고 있으며, 최대 지발당 장약량 11.25 kg/delay이고, 이격거리는 발파장소와 계측기 설치지점을 도면(CAD)상의 좌표를 이용하여 직선거리 적용하였으며, 최대 입자속도(PPV)와 최대지발당 장약량을 사용하여 회귀분석을 진행하였다. 95% 신뢰도의 자승근 및 삼승근 회귀분석 식 도출하였다.
계측기는 10대(SV-1 2대, 미니메이트, 플러스 8대)가 사용되어 동일한 위치에 고정하여 설치하였으며, 이격거리 100m ~ 237m, 터널 내부에 설치하여 지오센서만 설정하였다. 지반의 상태에 따라 진동 전파특성이 달라지기 때문에 지반에 대한 측정 오차를 최소화하기 위하여 동일 위치에 동일한 진동 계측기를 설치하여 측정하였다. 진동 데이터는 최소 설정값 미만으로 측정된 데이터는 노이즈로 판단하여 분석에서 제외하였다. 각 공법은 비교예(일반발파) 2회, 본 실시예에서 하프 발파 2회와 잔류발파 2회를 실시하여 총 6회 발파를 실시하여 46개 진동 데이터를 획득하였다.
분석방법은 굴착이 진행되는 동안 발파 지점과의 이격거리가 변하고, 발파진동의 전파특성을 확인하기 위하여 회귀분석을 진행하고, 현장에서 발파작업(발파기 작동)을 진행하는 최소 이격거리인 100m 지점과, 발파원과 굴착작업이 진행되는 최소 이격거리 20m(발파원의 직 하부, 크라운 필라 두께 20m)에서의 예상 진동값(mm/sec)으로 비교예(일반공법)와 본 실시예의 진동 저감율을 각각 비교하였다.
구분 적용 공법 이격거리(m)별 진동(cm/sec) 예측치 판정
자승근 삼승근
20 m 100 m 20 m 100 m
No. 1 일반발파 71.34 cm/sec 1.71 cm/sec 71.2 cm/sec 1.70 cm/sec 기준
No. 2 제안발파 하프 21.25 cm/sec 1.36 cm/sec 11.9 cm/sec 0.71 cm/sec 성공
No. 3 잔류 40.51 cm/sec 1.27 cm/sec 40.49 cm/sec 1.27 cm/sec 성공
[표 2]는 이격 거리(m) 별 진동 예측치를 보여주는 결과이며, 비교예(일반발파)의 경우 현장에서 사용하고 있는 지발당 장약량 11.25kg를 사용하여 작업할 경우 자승근 예측식에 따르면 20m지점에서 71.34cm/sec, 100m 지점에서 1.71cm/sec의 진동값이 예측된다. 삼승근 예측식에 따르면 20m지점에서 71.2cm/sec, 100m지점에서 1.70cm/sec의 진동값이 예측된다.
본 실시예의 하프장전 발파의 경우 동일조건으로 자승근 예측식에 따르면, 20m 지점에서 21.25cm/sec, 100m 지점에서 1.36cm/sec,의 진동값이 예측되며, 삼승근 예측식에 의하면 20m지점에서 11.9cm/sec, 100m지점에서 0.71cm/sec의 진동값이 예측된다.
본 실시예의 잔류공 발파의 경우 동일조건으로 자승근 예측식에 의하면 20m 지점에서 40.51cm/sec, 100m 지점에서 1.27cm/sec의 진동값이 예측되며,, 삼승근 예측식에 의하면 20m지점에서 40.49cm/sec, 100m지점에서 1.27cm/sec의 진동값이 예측된다.
분석결과 비교예(일반발파)에 비해 본 실시예의 하프장전 발파의 경우 자승근 및 삼승근 예측식을 적용하고, 20m와 100m 이격거리의 진동 예측값은 모두 했을 때 모두 최소 20%이상 진동감소가 예측된다. 또한 동일조건으로 비교예(일반발파)와 본 실시예의 잔류발파를 비교했을 때 최소 25%이상 진동감소가 예상된다.
진동예측식을 분석한 결과 본 실시예의 하프발파는 비교예(일반발파)와 비교하여 초기 진동값이 낮았고, 본 실시예의 잔류공 발파는 비교예(일반발파)에 비하여 진동 감쇠율이 높은 것으로 분석되었다.
[표 2]에서 비교예와 대비하여 진동 저감율이 10% 이상인 경우에 '성공'으로 판정하였다.
도 11은 비교예에 대한 발파 회귀분석 그래프로서, (a)는 자승근 회귀분석 그래프이며, (b)는 삼승근 회귀분석 그래프이다. 도 12는 본 실시예(하프발파; 1회차)에 대한 회귀분석 그래프로서, (a)는 자승근 회귀분석 그래프이며, (b)는 삼승근 회귀분석 그래프이다. 도 13은 본 실시예(잔류 발파; 2회차)에 대한 회귀분석 그래프로서, (a)는 자승근 회귀분석 그래프이며, (b)는 삼승근 회귀분석 그래프이다.
다음으로, 3차원 레이저 스캐너(CMS)를 이용하여 공동기관에서 제안한 3차원 굴진장 평가방법(도 14 참고)에 따라서 발파 후에 굴진효율을 분석한 결과 다음의 [표 3]의 굴질율 결과를 얻었다. 굴질율(%)은 (굴진장/천공장)×100으로 계산되며, 비교예와 대비하여 약 10%의 굴진율 증가 시에 '성공'으로 판정하였다.
구분 적용 공법 장약 방법 천공장(m) 굴진장(m) 굴진율(%) 비고 판정
No. 1 V-cut 일반 장전 1.8 1.34 74.44 비교예 기준
No. 2 하프 장전 3.6 1.12 84.17 본 실시예(하프장전) 성공
No. 3 잔류공 장전 1.91
No. 4 하프 장전 3.6 1.19 85.83
No. 5 잔류공 장전 1.90
No. 6 하프 장전 3.6 1.22 86.11
No. 7 잔류공 장전 1.88
No. 8 일반 장전 1.8 1.37 76.11 비교예 기준
No. 9 하프 장전 3.6 1.17 85.00 본 실시예(하프장전) 성공
No. 10 잔류공 장전 1.87
No. 11 하프 장전 3.6 1.25 86.39
No. 12 잔류공 장전 1.86
2회의 비교예(일반 발파) 실험결과 평균 굴진효율이 75.28%가 측정되었고, 본 실시예의 하프장전의 경우 평균 굴진효율이 85.50%로 측정되었다. 굴진장 측정방법은 전체공의 잔류길이를 측정하는데 한계가 있기 때문에 3D스캐너를 활용하여 발파 굴착 부피로 굴진장을 역산하였다. 동일 막장에서 실험을 진행하였고, 비교예(일반발파)와 본 실시예(하프장전)를 교차하여 실험을 진행한 결과, 본 실시예의 하프장전 방법을 적용한 경우가 천공장 대비 평균 10.2% 굴진율이 증가하였고, 비교예(일반발파) 대비 최소 10.6%, 최대 13.5%의 굴진율이 증가함을 확인하였다. 따라서 연장이 긴 터널발파 공사의 작업시간 및 공사기간 단축이 가능함을 예상할 수 있다.
다음의 [표 4]는 본 실시예와 비교예에 대한 천공 작업시간을 측정한 결과를 보여주고 있다. 1Boom 디젤 점보 천공작업을 진행하고, 7회 모두 동일한 천공 작업자가 진행하였다. 비교예와 대비하여 천공 작업시간이 20%의 단축 시 '성공'으로 판정하였다.
구분 적용 천공장(m) 연 천공장(m) 총 천공수(공) 작업준비시간(min) 천공시간(min) 총 천공시간(min) 판정
No. 1 V-cut(비교예) 1.8 116.61 64 7 68 75 기준
No. 2 V-cut(본 실시예) 3.6 249.66 70 7 113 120 성공
No. 3 V-cut(본 실시예) 3.6 249.66 70 7 116 121 성공
No. 4 V-cut(본 실시예) 3.6 249.66 70 7 107 114 성공
No. 5 V-cut(비교예) 1.8 116.61 64 7 65 72 기준
No. 6 V-cut(본 실시예) 3.6 249.66 70 7 112 119 성공
No. 7 V-cut(본 실시예) 3.6 249.66 70 7 106 112 성공
일반공법과 제안공법 모두 발파 패턴도를 기준으로 산출하였으며, 공법 특성상 본 실시예의 하프장전의 경우 비교예(일반발파) 2회 천공작업 분량을 미리 작업하기 때문에 비교예 2회 천공(3.6m)의 천공시간과, 본 실시예의 평균 천공(3.6m) 시간을 비교하였다. 비교예의 천공작업시간 (제1번 + 제5번), 본 실시예의 평균 천공작업시간 (제2, 3, 4, 6, 7번)을 비교하였다. 작업 준비 시간(비트교환, 장비이동, 천공작업 준비 등)은 평균값을 각 공법에 동일하게 적용하였다(420초). 비교예 제1번의 마킹작업을 진행하지 않아 천공작업시간에서 마킹작업시간은 제외하였다.
총 7회의 천공시간을 측정한 결과 2회의 비교예 공법의 천공시간은 147분이 소요되었고, 본 실시예의 하프장전 천공시간은 최소 112분, 최대 121분으로 평균 약 117분으로 측정되었다.
비교예 2회의 천공시간에 비해 본 실시예(하프장전)가 약 25% 단축됨을 확인하였다.
디젤점보를 사용하여 작업을 진행하였기 때문에 유압디젤장비를 사용할 경우 수압펌프 연결 작업 등 작업준비 시간이 증가하기 때문에 유압디젤장비를 사용하는 현장의 경우 제안공법의 천공 작업 시간단축이 더 클 것으로 예상된다.
다음의 [표 5]는 본 실시예와 비교예에 대한 굴착 사이클 시간(Cycle-time)을 측정한 결과를 보여주고 있다. 2회의 비교예와 대비하여 작업 사이클 시간이 10% 이상 단축하는 경우에 '성공'으로 판정하였다.
작업시간(min) 판정
마킹 천공 장약 발파 버력처리 스케일링 평균
No. 1 비교예(일반발파) 30 75 32 5 60 23 225 447 기준
No. 2 비교예(일반발파) 72 222
No. 3 본실시예 하프 32 120 38 51 269 398.2 성공
잔류 - - 32 72 132
No. 4 본실시예 하프 32 121 38 51 270 성공
잔류 - - 32 72 132
No. 5 본실시예 하프 32 114 38 51 263 성공
잔류 - - 32 72 132
No. 6 본실시예 하프 32 119 38 51 268 성공
잔류 - - 32 72 132
No. 7 본실시예 하프 32 112 38 51 261 성공
잔류 - - 32 72 132
마킹 시간은 비교예와 대비하여 본 실시예의 천공수 6공가 추가되어 평균 작업시간을 산출하여 적용하였으며, 천공 시간은 점보드릴 작업 준비시간을 포함한 총 천공시간을 표시하였다. 장약 시간은 현장에서 안포 장전기를 사용하여 장약하여 각 공법의 평균 작업시간을 적용하며, 발파 시간은 환기 시간을 제외한 평균 발파 준비시간이다. 버력처리 시간은 시험 현장에서 25톤 덤프 15대 가동 시에 각 공법의 평균 작업 시간을 적용한 것이다. 스케일링 시간은 잔버력 처리 시간을 제외하여 (다음 발파 후 작업 때 같이 평균 작업 시간을 적용하여 처리한 것이다.
평균 작업시간은 2회에 대한 비교예와 본 실시예(하프+잔류)의 평균 작업 시간을 비교한 것이며, 총 12회의 발파굴착 작업 시간을 분석한 결과 비교예(2회)의 굴착 작업 시간은 평균 447분이 측정되었고, 본 실시예(하프+잔류)의 굴착 작업시간은 평균 398.2분이 측정되었다.
본 실시예는 비교예와 대비하여 약 10.9%의 굴착 사이클 시간이 단축됨을 확인할 수 있다. 따라서 본 실시예는 비교예와 대비하여 1일 작업 사이클 시간의 초과 위험으로부터 안전하고, 공법 특성상 굴진율 증가로 인한 전체 굴착 공사 기간 단축이 가능하다.
이러한 본 발명의 하프장전을 이용한 발파방법은 다음과 같은 특징이 있다. 1) 수직 천공, 수평 천공, 경사 천공 등의 모든 발파 패턴에 적용이 가능하다. 2) 주변에 보안 물건이 존재하는 현장에 적용성이 우수하고 공사기간 단축 및 공사비가 절감된다. 3) 분상폭약, 카트리지 폭약, 벌크형 폭약 등과 같이 폭약의 종류에 상관없이 적용이 가능하다. 4) Air-Deck 효과발현, 다단장약 방법이 가능하다. 5) 노천 발파, 터널 발파, 수직구 등과 같이 다양한 발파공법에 적용이 가능한다.
이상에서 설명한 본 발명은 전술한 실시예 및 첨부된 도면에 의해 한정되는 것이 아니고, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 여러 가지 치환, 변형 및 변경이 가능함은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 명백할 것이다.
[부호의 설명]
111 : 발파공 121, 131 : 폭약

Claims (3)

  1. 발파공을 천공하여 상기 발파공의 전체 길이에 대해 1/2 이하의 장전 길이 범위 내에서 폭약을 장약하고 1회차 발파를 실시한 후에 발파후 생성된 버력을 처리하며, 상기 발파공 내의 잔여 길이에 대해 폭약을 재장전하여 2회차 이상 발파를 실시하는 것을 특징으로 하는 암반발파 방법.
  2. 제1항에 있어서, 1회차 발파를 위한 폭약의 장전 길이는 1/3 보다는 더 긴 것을 특징으로 하는 암반발파 방법.
  3. 제1항에 있어서, 상기 발파공은 막장면의 중심선을 기준으로 심발공을 좌우에 대칭 형태로 경사를 갖게 되는 브이-커트(V-cut) 공법에 의해 천공이 이루어지는 것을 특징으로 하는 암반발파 방법.
PCT/KR2018/012887 2018-10-29 2018-10-29 하프장전 방법을 이용한 암반발파 방법 WO2020091087A1 (ko)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/KR2018/012887 WO2020091087A1 (ko) 2018-10-29 2018-10-29 하프장전 방법을 이용한 암반발파 방법

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/KR2018/012887 WO2020091087A1 (ko) 2018-10-29 2018-10-29 하프장전 방법을 이용한 암반발파 방법

Publications (1)

Publication Number Publication Date
WO2020091087A1 true WO2020091087A1 (ko) 2020-05-07

Family

ID=70462392

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2018/012887 WO2020091087A1 (ko) 2018-10-29 2018-10-29 하프장전 방법을 이용한 암반발파 방법

Country Status (1)

Country Link
WO (1) WO2020091087A1 (ko)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20210372758A1 (en) * 2019-12-10 2021-12-02 Hanwha Corporation Device and method for providing converted blasting pattern coordinate
CN114001608A (zh) * 2021-10-20 2022-02-01 中铁三局集团第二工程有限公司 无仰拱隧道中心水沟爆破开挖方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020074766A (ko) * 2001-03-21 2002-10-04 이동윤 V-분할 확심 발파 공법 (M-Cut공법)
KR20020082501A (ko) * 2001-03-20 2002-10-31 티앤알비 주식회사 천공간격, 장약량 및 발파순서를 조절한 암파쇄벤치발파방법
KR20030009743A (ko) * 2001-07-23 2003-02-05 이동윤 2자유면 발파에서의 다단 분할 Double Bench 발파 공법
KR101093772B1 (ko) * 2011-08-11 2011-12-19 에스에이치블래스텍 주식회사 수평방향 연주식 발파공법
US9482507B2 (en) * 2009-09-29 2016-11-01 Orica Explosives Technology Pty Ltd Method of underground rock blasting

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020082501A (ko) * 2001-03-20 2002-10-31 티앤알비 주식회사 천공간격, 장약량 및 발파순서를 조절한 암파쇄벤치발파방법
KR20020074766A (ko) * 2001-03-21 2002-10-04 이동윤 V-분할 확심 발파 공법 (M-Cut공법)
KR20030009743A (ko) * 2001-07-23 2003-02-05 이동윤 2자유면 발파에서의 다단 분할 Double Bench 발파 공법
US9482507B2 (en) * 2009-09-29 2016-11-01 Orica Explosives Technology Pty Ltd Method of underground rock blasting
KR101093772B1 (ko) * 2011-08-11 2011-12-19 에스에이치블래스텍 주식회사 수평방향 연주식 발파공법

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20210372758A1 (en) * 2019-12-10 2021-12-02 Hanwha Corporation Device and method for providing converted blasting pattern coordinate
CN114001608A (zh) * 2021-10-20 2022-02-01 中铁三局集团第二工程有限公司 无仰拱隧道中心水沟爆破开挖方法

Similar Documents

Publication Publication Date Title
WO2020091087A1 (ko) 하프장전 방법을 이용한 암반발파 방법
CN108286920A (zh) 一种隧道爆破和开挖的实施方法
CN107289828B (zh) 一种露天矿爆破效果评价方法
CN112922606B (zh) 一种适用iii、iv级围岩大断面铁路隧道全电脑三臂凿岩台车全断面光面爆破施工方法
CN106524844A (zh) 一种盾构隧道沿线孤石勘查和爆破处理的施工方法
CN104089551B (zh) 老闸定向倾斜倒塌爆破拆除施工方法
CN110514080B (zh) 一种隧道礃子面爆破方法
CN110206547B (zh) 适应于深部地层及高应力区域竖井掘进与支护的方法
CN102305580A (zh) 一种应用数码雷管实现全断面光面爆破施工方法
CN112343602B (zh) 一种上下层重叠隧道施工方法
RU2399763C1 (ru) Способ разработки маломощных крутопадающих месторождений скального типа
CN112432566A (zh) 一种大断面隧道全断面快速开挖方法
CN116839440A (zh) 定向爆破装药设计与效果评价方法及系统
CN103075939A (zh) 一种硐室盲炮处理的方法
Morozov Creation of rock mass monitoring deformations systems on rock burst hazardous mineral deposits
KR20200049922A (ko) 하프장전 방법을 이용한 암반발파 방법
CN111664760B (zh) 一种微台阶全断面施工精准爆破方法
CN114322686A (zh) 一种暗挖隧道安全爆破的起爆网路架构及控制方法
CN210570272U (zh) 一种降低地表震动的电梯井待爆破区域的结构
SU1634784A1 (ru) Способ локализации горных выработок
SU1532705A1 (ru) Способ разработки месторождений полезных ископаемых
Cai et al. Comparative study of rock support system design practice for large-scale underground excavations
KR100403385B1 (ko) 여굴 생성 방지를 위한 터널 굴착방법
SU785493A1 (ru) Способ разработки мощных рудных залежей
RU2383741C1 (ru) Способ дегазации угольных пластов

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18938395

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18938395

Country of ref document: EP

Kind code of ref document: A1