WO2019151880A1 - The method of installation of steel power line poles - Google Patents
The method of installation of steel power line poles Download PDFInfo
- Publication number
- WO2019151880A1 WO2019151880A1 PCT/PL2018/000128 PL2018000128W WO2019151880A1 WO 2019151880 A1 WO2019151880 A1 WO 2019151880A1 PL 2018000128 W PL2018000128 W PL 2018000128W WO 2019151880 A1 WO2019151880 A1 WO 2019151880A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- pole
- frame
- steel
- elements
- assembly
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
- E04H12/345—Arrangements for tilting up whole structures or sections thereof
Definitions
- the subject of the invention is the method of installation of steel poles of power lines, which shortens the time of their installation and reduces the costs of installation.
- the positioning of the pole itself which is a time-consuming operation, can be carried out without the use of a crane, which significantly reduces the cost of erecting the poles.
- a ⁇ prefabricated reinforced concrete pole which contains a ground part and a foot for positioning and fixing on the ground is known from the patent description PL21 1814, with an intermediate part between the ground part of the pole and the foot, whose lower end is fixed to the foot fixed to the ground, and the other end is fixed in the ground part of the pole.
- the ground part of the pole has at least one groove, situated in one of its walls, intended for the attachment of wall panels or other flat elements.
- Patent application P.377800 indicates the assembly method as an articulated connection between the lower part of the steel element and the foundation element, where the connection is made in the horizontal position of the steel element and then lifted by means of a rigid rod connected to the jib by means of a traction device.
- the kit for vertical setting of steelwork elements such as the pole and the chimney consists of a spatial jib, mounted on a steel element, a rigid rod connected to the corner of the jib and the tractor as a traction device.
- the purpose of the invention is to provide a solution concerning the method of assembly of the steel power line poles, which will provide the shortening of the time of assembly of power line poles, eliminate heavy assembly cranes, and thus enable the reduction of the cost of assembly of the power line poles.
- the method of assembling the pole according to the invention consists in joining the steel power pole at the level of 0.00 on the assembly supports in the horizontal position, then assembling the multifunctional auxiliary structure on the pole foundations, assembling the rotary frame, reinforcing the pole with the auxiliary structures and assembling the actuators with the rigging system and then raising the pole in six phases using the hydraulic actuators to the target position.
- the advantage of the invention is the elimination of the heavy equipment used so far, as well as the construction of special access roads, even if it is not possible to get to the site with the deliveries of pole elements, it is possible to reload the supplies and transport them with a tractor and trailer to the place of assembly.
- -/- The object of the invention is shown in the examples of the execution in the drawing in which fig. 1 shows the first phase of the assembly of the steel pole, fig. 2 shows the second phase of the pole assembly from the level 0.00 to 30° , fig. 3 shows the third phase of the pole assembly from an angle of 30° to 45°, fig. 4 shows the fourth phase of the assembly from an angle of 45° to 60°, fig.
- FIG. 5 shows the fifth phase of the assembly from an angle of 60° to 85° and fig. 6 shows the sixth phase of the assembly from an angle of 85° to 90° using a set of bolted fixing and stabilizing structures with the pole foundation.
- -/- In the example design, the E33P straight-line pole model was used for assembly, which is marked with the number 9 in the figure. -/-
- Fig. 1 shows a method which consists in horizontal integration of a complete steel pole 9 on three assembly supports 4. -/-
- Fig. 2 shows the raising of the pole from the level of 0.00 ⁇ o the angle of 30° using hydraulic actuators 7 and multifunctional auxiliary structures 2 two sets, fixed to the foundation feet 1 , and the rotating frame 3 fixed in the lower part to the auxiliary structure 2, while to the upper part of fhe rotating frame 3 the rigging system 8 is fixed, used to raise the pole 9 using the rope fixing elements on the upper level of the pole 5, and rope fixing elements on the lower level of fhe pole 6.
- the rotary frame 3 is fixed in the lower part to the auxiliary structure 2, the auxiliary structures 2 are fixed to the foundation feet 1 of pole 9 which are fixed in fhe aboveground par ⁇ of the pole, and to the upper part of fhe rotary frame 3 fhe rigging system 8 is fixed, used for raising the pole 9. -/-
- the elements of fhe assembly support 2 are screw systems for lowering the pole in the last phase of vertical alignment - transition from phase 5 ⁇ o phase 6.
- hydraulic actuators 7 used for lifting pole 9 are attached.
- Another assembly variant assumes the use of a frame built in fhe form of a ladder made of metal profiles with a square cross-section, which is equipped with two vertical rotating elements mounted on supports resting on reinforced elements of fhe frame.
- a load-bearing rope is fixed, connecting the frame with the mounted pole.
- the frame has a number of mounting holes for assembly of rotating elements, adjusting the lifting height.
- the load-bearing frame and vertical rotating elements are additionally connected with elements in the upper part of the frame, which at fhe same time serve as an additional bracket for the mounted pole.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Method of assembly of steel poles of power lines wherein in the first phase of assembly the steel power pole (9) is joined at the level of 0.00 on assembly supports (4) in the horizontal position, then multifunctional auxiliary structures (2) are mounted on the pole foundations, a rotary frame (3) is mounted, the pole is reinforced with auxiliary structures (5,6) with a rigging system (8), and with hydraulic actuators (7).
Description
The method of installation of steel power line poles.
The subject of the invention is the method of installation of steel poles of power lines, which shortens the time of their installation and reduces the costs of installation. The positioning of the pole itself, which is a time-consuming operation, can be carried out without the use of a crane, which significantly reduces the cost of erecting the poles. -/-
Reinforced concrete lighting pole reinforced with longitudinal and circular steel rods, with central two-diameter hole technologically converging upwards is known from patent description PL197355, consisting of upper pole with cross-section in the shape of a circle or polygon with a thickening at the bottom ended with a plane below which a central truncated cone or a correct truncated pyramid is made, converging to the bottom, with an apex angle of 0° ~ 0 56°, and at its smaller diameter a steel flat bar with a central hole perpendicular to the axis is concreted and from the lower, foundation part made with a central two-diameter hole converging to the top, ending from the top with a central hole converging downwards in the shape of a central truncated cone or a correct truncated pyramid with an apex angle corresponding to the apex angle of the cone in the lower part of the pole, and at its smaller diameter, in the central hole in the steel flat bar concreted perpendicular to the axis with a central hole, a nut is fixed axially with a vertical hole cooperating with a screw penetrating the flat bars from the top. -/-
In turn, a· prefabricated reinforced concrete pole, which contains a ground part and a foot for positioning and fixing on the ground is known from the patent description PL21 1814, with an intermediate part between the ground part of the pole and the foot, whose lower end is fixed to the foot fixed to the ground, and the other end is fixed in the ground part of the pole. The ground part of the pole has at least one groove, situated in one of its walls, intended for the attachment of wall panels or other flat elements. -/-
Patent application P.377800 indicates the assembly method as an articulated connection between the lower part of the steel element and the foundation element,
where the connection is made in the horizontal position of the steel element and then lifted by means of a rigid rod connected to the jib by means of a traction device. The kit for vertical setting of steelwork elements such as the pole and the chimney consists of a spatial jib, mounted on a steel element, a rigid rod connected to the corner of the jib and the tractor as a traction device. -/-
The purpose of the invention is to provide a solution concerning the method of assembly of the steel power line poles, which will provide the shortening of the time of assembly of power line poles, eliminate heavy assembly cranes, and thus enable the reduction of the cost of assembly of the power line poles. -/-
The method of assembling the pole according to the invention consists in joining the steel power pole at the level of 0.00 on the assembly supports in the horizontal position, then assembling the multifunctional auxiliary structure on the pole foundations, assembling the rotary frame, reinforcing the pole with the auxiliary structures and assembling the actuators with the rigging system and then raising the pole in six phases using the hydraulic actuators to the target position. Once the components of the steel power pole have been delivered to the erection site, the ancillary structures for the erection of the pole have been delivered to the erection site, the assembly supports have been positioned and the complete pole has been joined horizontally, using a forklift truck and scaffolding or assembly lifts, in several phases using hydraulic actuators, the integrated pole is lifted. -/-
The advantage of the invention is the elimination of the heavy equipment used so far, as well as the construction of special access roads, even if it is not possible to get to the site with the deliveries of pole elements, it is possible to reload the supplies and transport them with a tractor and trailer to the place of assembly. -/- The object of the invention is shown in the examples of the execution in the drawing in which fig. 1 shows the first phase of the assembly of the steel pole, fig. 2 shows the second phase of the pole assembly from the level 0.00 to 30° , fig. 3 shows the third phase of the pole assembly from an angle of 30° to 45°, fig. 4 shows the fourth phase of the assembly from an angle of 45° to 60°, fig. 5 shows the fifth phase of the assembly from an angle of 60° to 85° and fig. 6 shows the sixth phase of the assembly from an angle of 85° to 90° using a set of bolted fixing and stabilizing structures with the pole foundation. -/-
In the example design, the E33P straight-line pole model was used for assembly, which is marked with the number 9 in the figure. -/-
Fig. 1 shows a method which consists in horizontal integration of a complete steel pole 9 on three assembly supports 4. -/-
Fig. 2 shows the raising of the pole from the level of 0.00†o the angle of 30° using hydraulic actuators 7 and multifunctional auxiliary structures 2 two sets, fixed to the foundation feet 1 , and the rotating frame 3 fixed in the lower part to the auxiliary structure 2, while to the upper part of fhe rotating frame 3 the rigging system 8 is fixed, used to raise the pole 9 using the rope fixing elements on the upper level of the pole 5, and rope fixing elements on the lower level of fhe pole 6. -/-
The process of lifting the steel pole 9 is shown in fig. 2, fig. 3, fig. 4, fig. 5 and fig. 6, showing the subsequent phases of lifting Phase 2, Phase 3, Phase 4, Phase 5 and Phase 6. -/-
The rotary frame 3 is fixed in the lower part to the auxiliary structure 2, the auxiliary structures 2 are fixed to the foundation feet 1 of pole 9 which are fixed in fhe aboveground par† of the pole, and to the upper part of fhe rotary frame 3 fhe rigging system 8 is fixed, used for raising the pole 9. -/-
The elements of fhe assembly support 2 are screw systems for lowering the pole in the last phase of vertical alignment - transition from phase 5†o phase 6. -/- To the second set of auxiliary structure 2 hydraulic actuators 7 used for lifting pole 9 are attached. Another assembly variant assumes the use of a frame built in fhe form of a ladder made of metal profiles with a square cross-section, which is equipped with two vertical rotating elements mounted on supports resting on reinforced elements of fhe frame. To fhe lower par† of fhe frame and upper rotating elements a load-bearing rope is fixed, connecting the frame with the mounted pole. The frame has a number of mounting holes for assembly of rotating elements, adjusting the lifting height. The load-bearing frame and vertical rotating elements are additionally connected with elements in the upper part of the frame, which at fhe same time serve as an additional bracket for the mounted pole. -/-
Claims
1.The method of assembly of the steel power line poles, where the power pole contains the ground part the foot for positioning and fixing on the ground and the integrated part of the pole, characterised in that the steel pole (9) is integrated at the level of 0.00 on the mounting supports (4) in a horizontal position, then on the foundations (1 ) of the pole auxiliary structures (2) are mounted, the rotary frame (3) is mounted, the pole is reinforced with auxiliary structures (5,6) with a rigging system (8) and hydraulic actuators (7) are mounted and the pole (9) is lifted in six phases using the hydraulic actuators (7) to the target position or a frame is used, constructed in the form of a ladder of metal profiles with a square cross-section, equipped with two vertical rotating elements mounted on supports resting on its reinforced elements. -/-
2. Method according to claim 1 , characterised in that the complete steel power pole (9) is assembled in a horizontal position on three mounting supports (4). -/-
3. Method according to claim 1 , characterised in that a multifunctional auxiliary structure (2) to which a rotating frame (3) is mounted in the lower part is used during lifting, and to the lower part of the frame and upper rotating elements a load- bearing rope is fixed, connecting the frame (3) with the mounted pole, where the frame has a number of mounting holes intended for the assembly of rotating elements, being the lifting height adjustment, where the frame (3) and vertical rotating elements are additionally connected with elements in the upper part of the frame, which also serve as an additional bracket for the assembled pole. -/-
4. Method according to claim 1 , characterised in that a rotating frame (3) is used for the steel pole (9) lifting operation so that a rigging system (8) is fixed to its upper part for lifting the pole (9) using elements of the auxiliary structures (5) at the upper level of the pole, and mounting elements of the auxiliary structures (6) at the lower level of the pole. -/-
5. Method according to claim 1 , characterised in that hydraulic actuators (7) are used for lifting the steel pole (9). -/-
6. Method according to claim 1 , characterised in that in the sixth phase of the assembly, the steel power pole (9) is lifted from the angle of 85° to the angle of 90° with the use of a set of screw fixing and stabilizing structures (2) with the foundation ( 1 ) of the pole. -/-
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PLP.424503 | 2018-02-03 | ||
PL424503A PL424503A1 (en) | 2018-02-03 | 2018-02-03 | Method for assembling of electrical supply line steel towers |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2019151880A1 true WO2019151880A1 (en) | 2019-08-08 |
Family
ID=65352070
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/PL2018/000128 WO2019151880A1 (en) | 2018-02-03 | 2018-12-23 | The method of installation of steel power line poles |
Country Status (2)
Country | Link |
---|---|
PL (1) | PL424503A1 (en) |
WO (1) | WO2019151880A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113445812A (en) * | 2021-05-24 | 2021-09-28 | 邵小东 | Agricultural thing networking communication base station construction equipment |
CN115162823A (en) * | 2022-07-29 | 2022-10-11 | 中交路桥建设有限公司 | Method for assembling steeple steel member |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4027441A (en) * | 1975-10-02 | 1977-06-07 | Grigory Vasilievich Pitelyaev | Arrangement for erecting and dismounting an elongate object having one end articulated to a foundation |
PL211814A1 (en) | 1978-12-14 | 1980-06-16 | Os Bad Rozwojowy Armatury Prze | |
PL377800A1 (en) | 2005-10-24 | 2007-04-30 | Instytut Warzywnictwa im. Emila Chroboczka | Method for putting steel structure elements such as column or chimney stack in vertical position as well as a set for putting steel structure elements such as column or chimney stack in vertical position |
PL197355B1 (en) | 2001-06-04 | 2008-03-31 | Bielinski Artur | Reinforced concrete lamp post |
US20110016804A1 (en) * | 2009-07-22 | 2011-01-27 | Lonnie Howard | Ultra-light, re-usable, extended-height meteorological tower apparatus and method |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3715852A (en) * | 1970-12-08 | 1973-02-13 | Mitsubishi Heavy Ind Ltd | Method of erecting tower-like structure |
PL283593A1 (en) * | 1990-01-31 | 1991-08-12 | Jozef Lukaszewicz | Steel chimney and method of assembling it |
ES2304319B1 (en) * | 2007-03-29 | 2009-07-21 | GAMESA INNOVATION & TECHNOLOGY, S.L. | A TOWER OF CELOSIA AND A METHOD OF ERECTION OF AN AEROGENERATOR WITH A TOWER OF CELOSIA. |
GB0821775D0 (en) * | 2008-11-28 | 2009-01-07 | Rawlings Matthew J H | An apparatus and method for erecting wind turbines |
US8171614B2 (en) * | 2010-12-28 | 2012-05-08 | General Electric Company | Systems and method of assembling a tower section |
WO2013083802A2 (en) * | 2011-12-07 | 2013-06-13 | Dong Energy Wind Power A/S | Support structure for wind turbine and method of mounting such support structure |
-
2018
- 2018-02-03 PL PL424503A patent/PL424503A1/en unknown
- 2018-12-23 WO PCT/PL2018/000128 patent/WO2019151880A1/en active Application Filing
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4027441A (en) * | 1975-10-02 | 1977-06-07 | Grigory Vasilievich Pitelyaev | Arrangement for erecting and dismounting an elongate object having one end articulated to a foundation |
PL211814A1 (en) | 1978-12-14 | 1980-06-16 | Os Bad Rozwojowy Armatury Prze | |
PL197355B1 (en) | 2001-06-04 | 2008-03-31 | Bielinski Artur | Reinforced concrete lamp post |
PL377800A1 (en) | 2005-10-24 | 2007-04-30 | Instytut Warzywnictwa im. Emila Chroboczka | Method for putting steel structure elements such as column or chimney stack in vertical position as well as a set for putting steel structure elements such as column or chimney stack in vertical position |
US20110016804A1 (en) * | 2009-07-22 | 2011-01-27 | Lonnie Howard | Ultra-light, re-usable, extended-height meteorological tower apparatus and method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113445812A (en) * | 2021-05-24 | 2021-09-28 | 邵小东 | Agricultural thing networking communication base station construction equipment |
CN115162823A (en) * | 2022-07-29 | 2022-10-11 | 中交路桥建设有限公司 | Method for assembling steeple steel member |
CN115162823B (en) * | 2022-07-29 | 2024-02-23 | 中交路桥建设有限公司 | Assembling method of pinnacle steel member |
Also Published As
Publication number | Publication date |
---|---|
PL424503A1 (en) | 2019-08-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5629316B2 (en) | Telescopic tower assembly and method | |
US8297025B2 (en) | Method of building a hybrid tower for a wind generator | |
CN110230393B (en) | Large concrete tank dome climbing high formwork support system and installation method | |
EP2479430A1 (en) | Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower | |
CA2823814C (en) | Mounting assembly and method to erect in sections an annular tower for wind or heliostatic power generators in an energy farm | |
US20170167129A1 (en) | Method and apparatus for raising a structure | |
CN104099934A (en) | Supporting structure of large foundation pit | |
CN106930401A (en) | A kind of assembled industrialization steel structure house | |
CN110552507A (en) | Well is from automatic cloth system of concrete that climbs | |
WO2019151880A1 (en) | The method of installation of steel power line poles | |
JP6831714B2 (en) | Tower crane foundation and tower crane | |
CN205636516U (en) | Convertible template system of hollow concrete leaning tower | |
CN205369229U (en) | But walking hoisting frame suitable for manual hole digging pile steel reinforcement cage is laid | |
US20200284026A1 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
JP2018044318A (en) | Construction method of silo roof section, and silo roof structure | |
CN111847272A (en) | Supporting method of tower crane for reconstruction of existing building | |
US4782634A (en) | Building construction | |
CN216787874U (en) | Large-scale ring type truss hoisting structure in large-span high altitude | |
US11761196B2 (en) | Building system and method thereof | |
JP2579715B2 (en) | External tower crane | |
JP2018096163A (en) | Method of constructing building | |
CN210067523U (en) | Umbrella-type ground storehouse roof reinforcing apparatus that backs to | |
CN214996126U (en) | Lattice column direction control structure | |
CN217439509U (en) | Operating platform for high-rise hollow structure internal mold construction | |
RU103822U1 (en) | BIG SPAN BUILDING |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 18845421 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 18845421 Country of ref document: EP Kind code of ref document: A1 |