WO2019000750A1 - Method for installing propeller shaft bracket - Google Patents

Method for installing propeller shaft bracket Download PDF

Info

Publication number
WO2019000750A1
WO2019000750A1 PCT/CN2017/108826 CN2017108826W WO2019000750A1 WO 2019000750 A1 WO2019000750 A1 WO 2019000750A1 CN 2017108826 W CN2017108826 W CN 2017108826W WO 2019000750 A1 WO2019000750 A1 WO 2019000750A1
Authority
WO
WIPO (PCT)
Prior art keywords
frame
segment
shaft hole
welding
line
Prior art date
Application number
PCT/CN2017/108826
Other languages
French (fr)
Chinese (zh)
Inventor
熊飞
谭继良
姚杰
李伟
孙振财
Original Assignee
广船国际有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 广船国际有限公司 filed Critical 广船国际有限公司
Publication of WO2019000750A1 publication Critical patent/WO2019000750A1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Definitions

  • the invention relates to the technical field of ships, and in particular to a method for installing a truss frame.
  • the special type of ship with the truss shaft system is generally a long shaft system capable of spanning several large closed sections. In the installation process of the truss frame, the precision of the control shaft system is difficult.
  • the common installation method for the boring frame is to mount the shafting section in the docking stage, and then adjust according to the axis installation and the subsequent initial pulling line. Due to the large size and heavy weight of the single-piece boring frame, for example, the size of the single-piece boring frame is 2.4 ⁇ 7 ⁇ 8m (length ⁇ width ⁇ height) and the weight is 60t, which is equivalent to the specification of the medium-sized segment.
  • the positioning method of the boring frame is required to be carried out by using the hoist-assisted lifting positioning method. Therefore, the conventional boring frame mounting method has the following disadvantages: 1.
  • An object of the present invention is to provide a method for mounting a creel frame, which can reduce the safety of the creel Difficulty in loading and increasing the safety of the work.
  • Another object of the present invention is to provide a pylon mounting method capable of accurately controlling installation accuracy, shortening the docking cycle, and saving production costs.
  • a creel mounting method is provided that provides a boring frame on which the creel is mounted during the staged assembly phase and then hangs together with the segment to the dock for large closure assembly.
  • Step S10 the segmentation is performed
  • Step S20 positioning the pylon frame: setting a pole on the ground, and drawing a height inspection line on the pole, the height inspection line including a horizontal base line of the tire frame and a center line height of the shaft hole, the yoke frame Hanging to the segment and having the shaft hole between the corresponding poles, pulling the wire according to the central line height line of the shaft hole, one end of the wire and one of the shaft holes of the boring frame
  • the poles of the side are connected, the other end is connected to the pole on the other side through the shaft hole of the shank, and the position of the wire at the pole is adjusted to make the wire and the raft
  • the theoretical center line of the shaft hole of the yoke is coincident, and then the position of the yoke frame is adjusted such that the center line of the shaft hole of the yoke frame is offset from the wire set distance in the horizontal and vertical directions, and then the wire hammer is used. Adjusting a front and rear position of the yoke frame in a length direction of the
  • Step S30 the boring frame welding: welding the boring frame and the segment, and monitoring during the welding process, and re-adjusting if there is a deviation to ensure the accuracy of the welding.
  • the step S10 specifically includes:
  • Step S11 drawing, on the ground sample, the contoured contour line, the segment center line, the rib inspection line, and the benchmark position line of the segment according to the drawing;
  • Step S12 preparing a tire frame on the ground sample, and forming the segment on the tire frame;
  • Step S13 Draw a theoretical centerline of the shaft hole of the boring frame on the outer panel of the segment.
  • a step S21 is further disposed between the step S20 and the step S30: the locating frame is reinforced by the positioning member.
  • step S20 after adjusting the center line of the shaft hole, the center line of the shaft hole is offset upward in the vertical direction. -2mm, then offset 0-5mm away from the side in the horizontal direction, and then use the line hammer to adjust the front and rear position of the yoke in the length direction of the segment.
  • the yoke frame and the segment welding are preheated before welding and are performed after welding. Insulation, wherein the preheating temperature is from 120 ° C to 150 ° C.
  • the yoke frame is simultaneously welded symmetrically.
  • the welding sequence of the boring frame is: firstly, the ribs on the segment that are respectively abutted with the inner and outer arms Welding between the butt joints, welding the inner and outer arms of the creel and the gussets of the segmented ribs, and then the inner arms of the yoke The arms are welded to the corner joints of the segmented outer plates, and finally the butt joints between the bulk outer plates and the other outer plates are welded.
  • the precision monitoring of the boring frame welding process is performed, and the center line of the shaft hole and the theoretical center line of the shaft hole of the boring frame are welded.
  • the deviation before is ⁇ 1 mm
  • the deviation after welding is ⁇ 2 mm.
  • the deviation between the center of the front and rear end faces of the shaft hole and the position of the theoretical center before welding is ⁇ 2 mm
  • the position deviation after welding is ⁇ 3 mm.
  • Step S40 Before the segment leaves the frame, respectively, corresponding marks are marked on the segment and the cymbal frame for subsequent loading, and the corresponding markings include: dividing the points on the ground.
  • the segment center line is respectively led to the ⁇ position of the segment and the front and rear end faces of the shaft hole of the yoke frame, and the rib line is led to the front and rear end faces of the shaft hole and the rib line adjacent to the pole Leading to the outer surface of the shank, guiding the center line of the shaft hole to the front and rear end faces of the hub of the yoke.
  • the invention has the beneficial effects that the installation of the boring frame in the stage assembly stage can reduce the installation difficulty of the boring frame; the reverse manufacturing method is used in the installation process, the height of the construction is lowered, the work at height is avoided, and the construction is increased. Safety, in the installation process of the boring frame, the construction personnel can directly construct on the section, without the need to additionally carry the construction platform. Among them, the installation steps of segmentation, truss positioning, and boring frame welding can be used to accurately control the installation of the creel and improve the installation accuracy of the creel.
  • Figure 1 is a cross-sectional view showing the mounting of the creel bracket of the embodiment on the segment.
  • Figure 2 is a longitudinal cross-sectional view of the creel frame of the embodiment during installation (the wire is not shown).
  • Fig. 3 is a schematic transverse cross-sectional view showing the boring frame of the embodiment during installation.
  • Fig. 4 is a schematic view showing the drawing of the ground line of the embodiment.
  • a method for mounting a creel frame provides a creel 2 in which the yoke 2 is mounted at the stage of assembly. On the segment 1, and then together with the segment 1 to the dock to carry out a large collapse assembly.
  • the installation of the boring frame 2 in the stage assembly stage can reduce the installation difficulty of the boring frame 2, and is installed by reverse engineering during the installation process, that is, the segment 1 is flipped during the installation to keep the outer plate 12 away from the installation.
  • the deck On one side of the ground 9, the deck is located on the side close to the ground 9, which reduces the height of the construction and increases the safety of the construction.
  • the construction personnel can directly construct on the section 1 without Also equipped with a construction platform. It is installed by the reverse manufacturing method, and it is convenient to adjust the installation precision of the boring frame 2 during the installation process, and reduce the workload of pulling the wire.
  • the sling is hanged together with the section 1 to the dock for large-close assembly, and the darkening work of the boring boring frame 2 can be completed in the workshop, and the method can reduce the occupation of the dock. Time, shortening the dock cycle, improving the utilization of the dock, and making rational use of production resources.
  • the mounting method of the boring frame 2 comprises the following steps:
  • Step S10 the segment 1 is made
  • Step S20 positioning the boring frame 2: setting a benchmark 4 on the scale, and drawing a height inspection line on the benchmark 4, the height inspection line including the horizontal baseline 3 of the tire frame and the center height line of the shaft hole,
  • the shank 2 is hung to the segment 1 and has its axial hole 23 located between the corresponding poles 4, and the wire is drawn according to the central line height of the shaft hole, one end of the wire and the
  • the rod 4 of one side of the shaft hole 23 of the pylon 2 is connected, and the other end is connected to the rod 4 on the other side thereof through the shaft hole 23 of the creel 2 to adjust the wire Position on the pole 4 to make the steel wire and the shaft hole
  • the center line is coincident, and then the position of the yoke 2 is adjusted so that the center line of the shaft hole of the yoke 2 is offset from the wire set distance in the horizontal and vertical directions, and then the yoke 2 is adjusted by the wire hammer.
  • Step S30 the boring frame 2 is welded: the boring frame 2 is welded to the segment 1 and monitored during the welding process, and if there is a deviation, it is re-adjusted to ensure the accuracy of the welding.
  • the manufacturing accuracy of the boring frame 2 is checked and the machining allowance is confirmed, and the marks of the yoke 2 at the center of the front and rear end faces of the shaft hole 23 are inspected for subsequent scribing and welding.
  • the height of the inspection line can be determined as the installation height of the creel 2, and the pulling wire can assist the center line 24 of the shaft hole to coincide with the theoretical center line of the shaft hole.
  • step S30 Displaceing the wire set distance in the horizontal and vertical directions on the theoretical centerline of the shaft hole, fully taking into account the amount of welding shrinkage when the truss frame 2 and the segment 1 are welded, and providing space for welding deformation to ensure The accuracy of the actual installation of the boring frame 2 in the horizontal direction and the vertical direction is then adjusted by the wire hammer to adjust the longitudinal position of the creel 2 in the longitudinal direction of the segment 1 to achieve the length of the segment 1 Precision control.
  • step S30 the welding process is monitored, the welding deviation can be adjusted in time, the subsequent adjustment work is reduced, the welding accuracy is ensured, and the welding efficiency is improved.
  • the wire rod is pulled by a wire having a diameter of 0.6 mm.
  • a weight of 30 kg is applied to both ends of the wire to reduce the error of wire positioning.
  • the step S10 specifically includes: step S11, drawing a contour sample line 8 of the segment 1 according to the drawing, a segment 1 center line, a rib line 7 and a pole position line 41 according to the drawing. ;
  • Step S12 making a tire frame in the ground sample, and forming the segment 1 on the tire frame;
  • Step S13 the theoretical centerline of the shaft hole of the boring frame 2 is drawn on the outer panel 12 of the segment 1.
  • the benchmark 4 is set on the benchmark position line 41 drawn by the ground sample, and the benchmark 4 is fixed by the fixing member to ensure that the benchmark 4 is perpendicular to the horizontal plane, and the relative displacement of the benchmark 4 is ensured during the whole construction process, and is maintained well. The stability is avoided to affect the installation accuracy of the creel 2 .
  • the fixing member is a channel steel.
  • a step S21 is further provided between the step S20 and the step S30: the truss frame 2 is reinforced by the positioning member.
  • the yoke 2 is positioned by the positioning member to prevent the yoke 2 from being displaced during the welding process, ensuring the mounting accuracy of the yoke 2, and facilitating the welding of the yoke 2 to the segment 1.
  • the ⁇ is adjusted. After the shaft hole center line 24 of the yoke 2 overlaps with the wire 24, the shaft hole center line 24 is offset upward in the vertical direction by 0-2 mm, and then shifted in the horizontal direction away from the side of the ship. 0-5 mm, and then the line hammer is used to adjust the front and rear positions of the yoke 2 in the longitudinal direction of the segment 1.
  • the mounting accuracy of the yoke 2 can be controlled such that after the boring frame 2 and the segment 1 are welded, the axis of the yoke 2 coincides with the wire 24 within the error tolerance to fit the installation.
  • the shaft hole center line 24 is offset upward by 2 mm in the vertical direction and then offset by 5 mm in the horizontal direction away from the side of the ship.
  • the specific anti-deformation release amount that is, the axial hole center line 24 is offset upward in the vertical direction by the distance of the steel wire, and the shaft hole center line 24 is offset in the horizontal direction away from the side of the ship.
  • the distances are set according to the size of the inner arm 21 and the outer arm 22 of the boring frame 2, and are based on shipyard experience.
  • the boring frame 2 and the segment 1 are preheated before welding and are insulated after welding, wherein the preheating temperature is 120 ° C to 150 ° C.
  • Preheated The time depends on the specific construction conditions. Preheating can slow down the cooling after welding, avoid the overflow of diffused hydrogen in the metal, improve the crack resistance of the weld, reduce the welding stress, and effectively mention the quality of the weld. Insulation after welding can make the weld shrink evenly and prevent cracking at the weld.
  • the yoke frame 2 is simultaneously symmetrically welded to the left and right. Simultaneously welding the two trusses 2 to the left and right symmetry, which can simultaneously control the shape variables on the left and right sides of the split body, so that the left and right sides of the split body can be kept consistent, avoiding the difference of the order of welding on the left and right sides, so that the stern frame 2 is There is a difference between the left and right sides of the segment 1 which affects the balance of the segment 1 and improves the performance of the creel 2 .
  • the inner arm 21 and the outer arm 22 are welded to the segment 1 in a fully through-welded manner.
  • the use of full penetration welding avoids the occurrence of welds at the welds, satisfies the strength requirements of the boring frame 2 during use, and prolongs its service life.
  • the welding sequence of the creel 2 is: first, the butt joint between the ribs 11 on the segment 1 and the abutting ribs 11 of the inner arm 21 and the outer arm 22, respectively,
  • the inner arm 21 and the outer arm 22 of the yoke 2 are welded to the gusset 11 between the ribs 11 of the segment 1, and then the inner arm 21 and the outer arm 22 of the yoke 2 are The corner joints of the outer panel 12 of the segment 1 are welded, and finally the butt joint between the bulk outer panel and the other outer panels is welded.
  • the welding position of the yoke 2 is reserved on the segment 1.
  • the rib 11 which is not installed at the abutting position of the boring frame 2 of the segment 1 is welded to the rib 11 which is not welded to the segment 1 during the welding of the yoke 2
  • the inner arm 21 and the outer arm 22 are welded to the rib 11 while ensuring good welding between the ribs 1 which are in contact with the inner arm 21 and the outer arm 22.
  • the installation port is reserved at the position where the stern frame 1 is docked on the segment 1 to reserve space for the welding construction, which can reduce the welding difficulty and facilitate the welding of the yoke frame 2.
  • the damage to the outer panel 12 outside the welded area can be minimized, and the adjustment of the outer panel 12 during the convenient welding process is also facilitated.
  • the precision of the welding process of the boring frame 2 is monitored, so that the deviation between the center line 24 of the shaft hole and the theoretical center line of the shaft hole before welding is ⁇ 1 mm, after welding The deviation is ⁇ 2 mm, and the position of the front and rear end faces of the shaft hole 23 and the position of the theoretical center is ⁇ 2 mm before welding, and the positional deviation after welding is ⁇ 3 mm.
  • the step S30 is followed by the step S40: the segment 1 is separated from the frame before the segment 1
  • Corresponding markings are made on the yoke 2 for subsequent loading.
  • the corresponding markings include: the centerline of the segment 1 on the ground to the ⁇ position of the segment 1 and the pylon 2
  • the rib line is led to the front and rear end faces of the shaft hole 23 and the rib line near the pole 4 is led to the outer surface of the boring frame 2
  • the shaft hole center line 24 is It is led to the front and rear end faces of the shaft hole 23 of the creel.
  • the marks on each segment 1 are correspondingly closed, which reduces the workload of the large-close assembly and improves the production efficiency of the ship.
  • the installation of the boring frame is changed from the docking operation to the segmentation stage, and the aerial work is transferred to the ground, which not only saves the cost of the detaching frame, but also saves the construction of the scaffolding of the dock, and calculates the space area according to the length of 16m ⁇ 4m ⁇ 12m. , can save labor costs of about 61,440 yuan.

Abstract

A method for installing a propeller shaft bracket: providing a propeller shaft bracket (2); during a segment (1) assembly stage, installing the propeller shaft bracket (2) on a segment (1) and then hanging the same together with the segment (1) on a dock for large joining assembly. Using the present method for installing a propeller shaft bracket may reduce the difficulty of installation for the propeller shaft bracket, increase the safety of operation, and may further accurately control installation accuracy, shorten docking period, and save production costs.

Description

一种艉轴架安装方法Clamping frame mounting method 技术领域Technical field
本发明涉及船舶技术领域,尤其涉及一种艉轴架安装方法。The invention relates to the technical field of ships, and in particular to a method for installing a truss frame.
背景技术Background technique
含艉轴架轴系的特种型船一般为能跨度几个大合拢分段的长轴系,在艉轴架的安装过程中,控制轴系的精度难度较大。The special type of ship with the truss shaft system is generally a long shaft system capable of spanning several large closed sections. In the installation process of the truss frame, the precision of the control shaft system is difficult.
目前,艉轴架常用的安装方法是在船坞阶段将轴系分段搭载成型后,再根据轴线安装以及后续初拉线进行调整。由于单件艉轴架的尺寸较大,重量较重,例如:单件艉轴架的尺寸为2.4×7×8m(长×宽×高),重量达60t,相当于中型分段的规格,在船坞搭载阶段需要利用葫芦辅助提升的定位方法来进行艉轴架定位装焊。因此,传统的艉轴架安装方法存在着以下缺点:1、在装配的过程中,需要在外板的周部以及在艉轴架上临时安装多个吊码,在一些位置上的吊码装焊的过程中需要高空车全程配合,操作难度较大,并且在后期艉轴架的吊装中需重复地搭架和拆架,耗费大量的人力和物力,不利于节约生产成本。2、在安装的过程中需要将艉轴架提升10.8m,属于高空作业,作业的危险度较高、安全系数差,且艉轴架质量较重,装吊难度大。3、船坞是船厂的重要资源,利用传统的焊装方法需要花费较长的时间在船坞内进行装配和调整,延长了船坞周期。At present, the common installation method for the boring frame is to mount the shafting section in the docking stage, and then adjust according to the axis installation and the subsequent initial pulling line. Due to the large size and heavy weight of the single-piece boring frame, for example, the size of the single-piece boring frame is 2.4×7×8m (length×width×height) and the weight is 60t, which is equivalent to the specification of the medium-sized segment. In the docking stage, the positioning method of the boring frame is required to be carried out by using the hoist-assisted lifting positioning method. Therefore, the conventional boring frame mounting method has the following disadvantages: 1. During the assembly process, it is necessary to temporarily install a plurality of lifting codes on the periphery of the outer panel and on the boring frame, and hang the code at some positions. In the process of the high-altitude vehicle, it is difficult to operate, and it is necessary to repeatedly erect and disassemble in the hoisting of the truss frame in the later stage, which consumes a lot of manpower and material resources, which is not conducive to saving production costs. 2. In the process of installation, the truss frame needs to be lifted by 10.8m, which is a high-altitude operation. The danger of operation is high, the safety factor is poor, and the quality of the boring frame is heavy, and the installation is difficult. 3. The dock is an important resource for the shipyard. It takes a long time to assemble and adjust in the dock by using the traditional welding method, which extends the dock cycle.
发明内容Summary of the invention
本发明的一个目的在于:提供一种艉轴架安装方法,能够降低艉轴架的安 装难度,增加作业的安全性。An object of the present invention is to provide a method for mounting a creel frame, which can reduce the safety of the creel Difficulty in loading and increasing the safety of the work.
本发明的另一个目的在于:提供一种艉轴架安装方法,能够精确的控制安装精度,缩短船坞周期,节约生产成本。Another object of the present invention is to provide a pylon mounting method capable of accurately controlling installation accuracy, shortening the docking cycle, and saving production costs.
为达到此目的,本发明采用以下技术方案:To achieve this, the present invention employs the following technical solutions:
提供一种艉轴架安装方法,提供艉轴架,在分段组装阶段将所述艉轴架安装在所述分段上,然后再一起随所述分段吊至船坞进行大合拢装配。A creel mounting method is provided that provides a boring frame on which the creel is mounted during the staged assembly phase and then hangs together with the segment to the dock for large closure assembly.
作为所述的艉轴架安装方法的一种优选的技术方案,包括以下步骤:As a preferred technical solution of the mounting method of the creel, the following steps are included:
包括以下步骤:Includes the following steps:
步骤S10、所述分段制作;Step S10, the segmentation is performed;
步骤S20、所述艉轴架定位:在地样树立标杆,在所述标杆上划制高度检验线,所述高度检验线包括胎架水平基线和轴孔中心高度线,将所述艉轴架吊至所述分段处,并使其轴孔位于对应的所述标杆之间,根据所述轴孔中心高度线拉设钢丝,所述钢丝的一端与所述艉轴架的轴孔的一侧的所述标杆连接,另一端穿过所述艉轴架的轴孔与位于其另一侧的所述标杆连接,调整所述钢丝在所述标杆的位置,使所述钢丝与所述艉轴架的轴孔理论中心线重合,然后调整所述艉轴架的位置,使所述艉轴架的轴孔中心线沿水平和竖直方向偏移所述钢丝设定距离,再利用线锤调整所述艉轴架在所述分段的长度方向上的前后位置;Step S20: positioning the pylon frame: setting a pole on the ground, and drawing a height inspection line on the pole, the height inspection line including a horizontal base line of the tire frame and a center line height of the shaft hole, the yoke frame Hanging to the segment and having the shaft hole between the corresponding poles, pulling the wire according to the central line height line of the shaft hole, one end of the wire and one of the shaft holes of the boring frame The poles of the side are connected, the other end is connected to the pole on the other side through the shaft hole of the shank, and the position of the wire at the pole is adjusted to make the wire and the raft The theoretical center line of the shaft hole of the yoke is coincident, and then the position of the yoke frame is adjusted such that the center line of the shaft hole of the yoke frame is offset from the wire set distance in the horizontal and vertical directions, and then the wire hammer is used. Adjusting a front and rear position of the yoke frame in a length direction of the segment;
步骤S30、所述艉轴架焊接:将所述艉轴架与所述分段焊接,并在焊接的过程中进行监控,如有偏差则重新调整,以保证焊装的精确度。Step S30, the boring frame welding: welding the boring frame and the segment, and monitoring during the welding process, and re-adjusting if there is a deviation to ensure the accuracy of the welding.
作为所述的艉轴架安装方法的一种优选的技术方案,所述步骤S10具体包括:As a preferred technical solution of the mounting method of the creel, the step S10 specifically includes:
步骤S11、在所述地样上根据图纸划制所述分段的轮廓地样线、分段中心线、肋检线以及标杆位置线; Step S11, drawing, on the ground sample, the contoured contour line, the segment center line, the rib inspection line, and the benchmark position line of the segment according to the drawing;
步骤S12、在所述地样制作胎架,在所述胎架上制作所述分段;Step S12, preparing a tire frame on the ground sample, and forming the segment on the tire frame;
步骤S13、在所述分段的外板上划制所述艉轴架的轴孔理论中心线。Step S13: Draw a theoretical centerline of the shaft hole of the boring frame on the outer panel of the segment.
作为所述的艉轴架安装方法的一种优选的技术方案,在所述步骤S20与所述步骤S30之间还设置步骤S21:采用定位件对所述艉轴架进行加强定位。As a preferred technical solution of the mounting method of the creel, a step S21 is further disposed between the step S20 and the step S30: the locating frame is reinforced by the positioning member.
作为所述的艉轴架安装方法的一种优选的技术方案,所述步骤S20中:调整所述轴孔中心线后,使所述轴孔中心线沿竖直方向向上偏移所述钢丝0-2mm,再沿水平方向向远离舷侧方向偏移0-5mm,再利用线锤调整艉轴架在分段的长度方向上的前后位置。As a preferred technical solution of the mounting method of the boring frame, in step S20, after adjusting the center line of the shaft hole, the center line of the shaft hole is offset upward in the vertical direction. -2mm, then offset 0-5mm away from the side in the horizontal direction, and then use the line hammer to adjust the front and rear position of the yoke in the length direction of the segment.
作为所述的艉轴架安装方法的一种优选的技术方案,在所述步骤S30中,所述艉轴架与所述分段焊接前对两者的焊接位置进行预热并且在焊接后进行保温,其中,预热的温度为120℃~150℃。As a preferred technical solution of the creel mounting method, in the step S30, the yoke frame and the segment welding are preheated before welding and are performed after welding. Insulation, wherein the preheating temperature is from 120 ° C to 150 ° C.
作为所述的艉轴架安装方法的一种优选的技术方案,在预热后,对所述艉轴架同时进行左右对称焊接。As a preferred technical solution of the mounting method of the boring frame, after the preheating, the yoke frame is simultaneously welded symmetrically.
作为所述的艉轴架安装方法的一种优选的技术方案,所述艉轴架的焊接顺序为:先将所述分段上的分别与内支臂和外支臂的对接的肋板之间的对接处焊接,再将所述艉轴架的内支臂和外支臂与所述分段的肋板之间的角接位置焊接,然后将所述艉轴架的内支臂和外支臂与所述分段的外板的角接位置焊接,最后将散装外板与其他外板之间的对接缝焊接。As a preferred technical solution of the mounting method of the boring frame, the welding sequence of the boring frame is: firstly, the ribs on the segment that are respectively abutted with the inner and outer arms Welding between the butt joints, welding the inner and outer arms of the creel and the gussets of the segmented ribs, and then the inner arms of the yoke The arms are welded to the corner joints of the segmented outer plates, and finally the butt joints between the bulk outer plates and the other outer plates are welded.
作为所述的艉轴架安装方法的一种优选的技术方案,在所述艉轴架焊接过程进行精度监控,使所述轴孔中心线与所述艉轴架的轴孔理论中心线在焊接前的偏差为≤±1mm,焊接后的偏差为≤±2mm,所述轴孔的前后端面中心和理论中心的位置在焊接前的偏差为≤±2mm,焊接后的位置偏差为≤±3mm。As a preferred technical solution of the mounting method of the creel, the precision monitoring of the boring frame welding process is performed, and the center line of the shaft hole and the theoretical center line of the shaft hole of the boring frame are welded. The deviation before is ≤±1 mm, and the deviation after welding is ≤±2 mm. The deviation between the center of the front and rear end faces of the shaft hole and the position of the theoretical center before welding is ≤±2 mm, and the position deviation after welding is ≤±3 mm.
作为所述的艉轴架安装方法的一种优选的技术方案,所述步骤S30后设置 步骤S40:所述分段离开所述胎架前分别在所述分段和所述艉轴架上作出相应的标记,以供后续搭载使用,相应的标记包括:将所述地样上的分段中心线分别引至所述分段的艏艉位置以及所述艉轴架的轴孔的前后端面上,将所述肋检线引至轴孔的前后端面上以及将靠近标杆的肋位线引至艉轴架的外表面上,将所述轴孔中心线引至所述艉轴架的轴毂前后端面上。As a preferred technical solution of the mounting method of the creel, the step S30 is set. Step S40: Before the segment leaves the frame, respectively, corresponding marks are marked on the segment and the cymbal frame for subsequent loading, and the corresponding markings include: dividing the points on the ground. The segment center line is respectively led to the 艏艉 position of the segment and the front and rear end faces of the shaft hole of the yoke frame, and the rib line is led to the front and rear end faces of the shaft hole and the rib line adjacent to the pole Leading to the outer surface of the shank, guiding the center line of the shaft hole to the front and rear end faces of the hub of the yoke.
本发明的有益效果为:在分段组装阶段完成艉轴架的安装能够降低艉轴架的安装难度;在安装过程中采用反造法安装,降低了施工的高度,避免高空作业,增加了施工的安全性,在艉轴架的安装过程中,施工人员可直接在分段上施工,无需另外搭载施工平台。其中,分别采用分段制作、艉轴架定位、艉轴架焊接的安装步骤,能够对艉轴架的安装精确进行控制,提高艉轴架的安装精度。The invention has the beneficial effects that the installation of the boring frame in the stage assembly stage can reduce the installation difficulty of the boring frame; the reverse manufacturing method is used in the installation process, the height of the construction is lowered, the work at height is avoided, and the construction is increased. Safety, in the installation process of the boring frame, the construction personnel can directly construct on the section, without the need to additionally carry the construction platform. Among them, the installation steps of segmentation, truss positioning, and boring frame welding can be used to accurately control the installation of the creel and improve the installation accuracy of the creel.
附图说明DRAWINGS
下面根据附图和实施例对本发明作进一步详细说明。The invention will now be described in further detail with reference to the drawings and embodiments.
图1为实施例所述艉轴架安装在所述分段上的剖视示意图。Figure 1 is a cross-sectional view showing the mounting of the creel bracket of the embodiment on the segment.
图2为实施例所述艉轴架在安装过程中的纵向剖视示意图(图中钢丝未示出)。Figure 2 is a longitudinal cross-sectional view of the creel frame of the embodiment during installation (the wire is not shown).
图3为实施例所述艉轴架在安装过程中的横向剖视示意图。Fig. 3 is a schematic transverse cross-sectional view showing the boring frame of the embodiment during installation.
图4为实施例所述地样线的划制简图。Fig. 4 is a schematic view showing the drawing of the ground line of the embodiment.
图中:In the picture:
1、分段;11、肋板;12、外板;2、艉轴架;21、内支臂;22、外支臂;23、轴孔;24、轴孔中心线;3、胎架水平基线;4、标杆;41、标杆位置线;5、轮廓地样线;6、分段中心线;7、肋检线;8、定位件;9、地面。 1, segment; 11, ribs; 12, outer plate; 2, truss frame; 21, inner arm; 22, outer arm; 23, shaft hole; 24, shaft hole center line; 3, tire frame level Baseline; 4, benchmark; 41, benchmark position line; 5, contour ground line; 6, segment center line; 7, rib line; 8, positioning parts; 9, ground.
具体实施方式Detailed ways
下面结合附图并通过具体实施方式来进一步说明本发明的技术方案。The technical solution of the present invention will be further described below with reference to the accompanying drawings and specific embodiments.
如图1~4所示,于本实施例中,本发明所述的一种艉轴架安装方法,提供艉轴架2,在分段组装阶段将所述艉轴架2安装在所述分段1上,然后再一起随所述分段1吊至船坞进行大合拢装配。As shown in FIGS. 1 to 4, in the present embodiment, a method for mounting a creel frame according to the present invention provides a creel 2 in which the yoke 2 is mounted at the stage of assembly. On the segment 1, and then together with the segment 1 to the dock to carry out a large collapse assembly.
在分段组装阶段完成艉轴架2的安装能够降低艉轴架2的安装难度,在安装过程中采用反造法安装,即在安装的过程中将分段1倒装使外板12位于远离地面9的一侧,甲板位于靠近地面9的一侧,降低了施工的高度,增加了施工的安全性,在艉轴架2的安装过程中,施工人员可直接在分段1上施工,无需另外搭载施工平台。采用反造法安装,在安装过程中方便调整艉轴架2的安装精度,减少拉线望光的工作量。在艉轴架2在分段1完成安装后,在一起随分段1吊至船坞进行大合拢装配,可在车间内完成转配艉轴架2的暗转工作,利用此方法能够减少占用船坞的时间,缩短了船坞的周期,提高了船坞的利用率,能够合理利用生产资源。The installation of the boring frame 2 in the stage assembly stage can reduce the installation difficulty of the boring frame 2, and is installed by reverse engineering during the installation process, that is, the segment 1 is flipped during the installation to keep the outer plate 12 away from the installation. On one side of the ground 9, the deck is located on the side close to the ground 9, which reduces the height of the construction and increases the safety of the construction. During the installation process of the truss 2, the construction personnel can directly construct on the section 1 without Also equipped with a construction platform. It is installed by the reverse manufacturing method, and it is convenient to adjust the installation precision of the boring frame 2 during the installation process, and reduce the workload of pulling the wire. After the boring frame 2 is installed in the section 1, the sling is hanged together with the section 1 to the dock for large-close assembly, and the darkening work of the boring boring frame 2 can be completed in the workshop, and the method can reduce the occupation of the dock. Time, shortening the dock cycle, improving the utilization of the dock, and making rational use of production resources.
其中,所述的艉轴架2安装方法包括以下步骤:Wherein, the mounting method of the boring frame 2 comprises the following steps:
步骤S10、所述分段1制作;Step S10, the segment 1 is made;
步骤S20、所述艉轴架2定位:在地样树立标杆4,在所述标杆4上划制高度检验线,所述高度检验线包括胎架水平基线3和轴孔中心高度线,将所述艉轴架2吊至所述分段1处,并使其轴孔23位于对应的所述标杆4之间,根据所述轴孔中心高度线拉设钢丝,所述钢丝的一端与所述艉轴架2的轴孔23的一侧的所述标杆4连接,另一端穿过所述艉轴架2的轴孔23与位于其另一侧的所述标杆4连接,调整所述钢丝在所述标杆4上的位置,使所述钢丝与所述轴孔理 论中心线重合,然后调整艉轴架2的位置,使所述艉轴架2的轴孔中心线沿水平和竖直方向偏移所述钢丝设定距离,再利用线锤调整艉轴架2在分段1的长度方向上的前后位置;Step S20, positioning the boring frame 2: setting a benchmark 4 on the scale, and drawing a height inspection line on the benchmark 4, the height inspection line including the horizontal baseline 3 of the tire frame and the center height line of the shaft hole, The shank 2 is hung to the segment 1 and has its axial hole 23 located between the corresponding poles 4, and the wire is drawn according to the central line height of the shaft hole, one end of the wire and the The rod 4 of one side of the shaft hole 23 of the pylon 2 is connected, and the other end is connected to the rod 4 on the other side thereof through the shaft hole 23 of the creel 2 to adjust the wire Position on the pole 4 to make the steel wire and the shaft hole The center line is coincident, and then the position of the yoke 2 is adjusted so that the center line of the shaft hole of the yoke 2 is offset from the wire set distance in the horizontal and vertical directions, and then the yoke 2 is adjusted by the wire hammer. Front and rear positions in the length direction of the segment 1;
步骤S30、所述艉轴架2焊接:将艉轴架2与分段1焊接,并在焊接的过程中进行监控,如有偏差则重新调整,以保证焊装的精确度。Step S30, the boring frame 2 is welded: the boring frame 2 is welded to the segment 1 and monitored during the welding process, and if there is a deviation, it is re-adjusted to ensure the accuracy of the welding.
在施工前检查艉轴架2的制作精度并且确认加工余量,检查艉轴架2在轴孔23前后端面中心的标记,以便于后续的划线以及焊接。通过高度检验线能够确定为艉轴架2的安装高度,拉设钢丝能够辅助轴孔中心线24与轴孔理论中心线重合。在所述轴孔理论中心线沿水平和竖直方向偏移所述钢丝设定距离,充分考虑到了在艉轴架2与分段1焊接时的焊接收缩量,为焊接变形预留空间,确保了艉轴架2在水平方向和垂直方向的实际安装的精确度,然后利用线锤调整艉轴架2在分段1的长度方向上的前后位置,实现了在分段1的长度方上的精确度的控制。在步骤S30中对焊接的过程中进行监控,能够对焊接偏差及时的调整,减少后续的调整工作,确保了焊装精确性,提高了焊装的效率。Before the construction, the manufacturing accuracy of the boring frame 2 is checked and the machining allowance is confirmed, and the marks of the yoke 2 at the center of the front and rear end faces of the shaft hole 23 are inspected for subsequent scribing and welding. The height of the inspection line can be determined as the installation height of the creel 2, and the pulling wire can assist the center line 24 of the shaft hole to coincide with the theoretical center line of the shaft hole. Displaceing the wire set distance in the horizontal and vertical directions on the theoretical centerline of the shaft hole, fully taking into account the amount of welding shrinkage when the truss frame 2 and the segment 1 are welded, and providing space for welding deformation to ensure The accuracy of the actual installation of the boring frame 2 in the horizontal direction and the vertical direction is then adjusted by the wire hammer to adjust the longitudinal position of the creel 2 in the longitudinal direction of the segment 1 to achieve the length of the segment 1 Precision control. In step S30, the welding process is monitored, the welding deviation can be adjusted in time, the subsequent adjustment work is reduced, the welding accuracy is ensured, and the welding efficiency is improved.
在本实施例中,采用直径为0.6mm的钢丝拉设标杆4,为了对钢丝进行有效的定位在钢丝的两端挂重30kg,以减少钢丝定位的误差。In the present embodiment, the wire rod is pulled by a wire having a diameter of 0.6 mm. In order to effectively position the wire, a weight of 30 kg is applied to both ends of the wire to reduce the error of wire positioning.
在实施过程中,通过在轴孔23的端口位置处设置线锤,需要考虑加工余量以确保艉轴架2的定位的精确度。为了进一步提高艉轴架2的定位的精确度,需要重复测量轴孔23的端口位置到标杆4的距离以及轴孔23理论中心线偏移钢丝的高度。In the implementation, by providing a wire hammer at the port position of the shaft hole 23, it is necessary to consider the machining allowance to ensure the accuracy of the positioning of the creel 2. In order to further improve the accuracy of the positioning of the creel 2, it is necessary to repeatedly measure the distance from the port position of the shaft hole 23 to the target 4 and the height of the theoretical center line of the shaft hole 23.
具体的,所述步骤S10具体包括:步骤S11、在所述地样上根据图纸划制所述分段1的轮廓地样线8、分段1中心线、肋检线7以及标杆位置线41;Specifically, the step S10 specifically includes: step S11, drawing a contour sample line 8 of the segment 1 according to the drawing, a segment 1 center line, a rib line 7 and a pole position line 41 according to the drawing. ;
步骤S12、在所述地样制作胎架,在胎架上制作所述分段1; Step S12, making a tire frame in the ground sample, and forming the segment 1 on the tire frame;
步骤S13、在所述分段1的外板12上划制所述艉轴架2的轴孔理论中心线。Step S13, the theoretical centerline of the shaft hole of the boring frame 2 is drawn on the outer panel 12 of the segment 1.
将标杆4树立在地样所划制的标杆位置线41上,并采用固定件将标杆4加以固定,确保标杆4与水平面垂直,并保证在整个施工过程中标杆4不发生相对位移,保持良好的稳定性,避免影响所述艉轴架2的安装精度。在本实施例中,所述固定件为槽钢。The benchmark 4 is set on the benchmark position line 41 drawn by the ground sample, and the benchmark 4 is fixed by the fixing member to ensure that the benchmark 4 is perpendicular to the horizontal plane, and the relative displacement of the benchmark 4 is ensured during the whole construction process, and is maintained well. The stability is avoided to affect the installation accuracy of the creel 2 . In this embodiment, the fixing member is a channel steel.
在焊接过程中,为了防止艉轴架2在分段1上发生位移,在所述步骤S20与所述步骤S30之间还设置步骤S21:采用定位件对所述艉轴架2进行加强定位。通过定位件对艉轴架2进行定位,防止在焊接的过程中艉轴架2偏移,确保了艉轴架2的安装精度,并且方便将艉轴架2焊接在分段1上。In the welding process, in order to prevent the yoke 2 from being displaced on the segment 1, a step S21 is further provided between the step S20 and the step S30: the truss frame 2 is reinforced by the positioning member. The yoke 2 is positioned by the positioning member to prevent the yoke 2 from being displaced during the welding process, ensuring the mounting accuracy of the yoke 2, and facilitating the welding of the yoke 2 to the segment 1.
考虑到艉轴架2上的内支臂21和外支臂22焊接在分段1的收缩量,为了达到精确控制艉轴架2的安装精度的目的,所述步骤S20中,调整所述艉轴架2的轴孔中心线24与所述钢丝24重合后,使所述轴孔中心线24沿竖直方向向上偏移所述钢丝0-2mm,再沿水平方向向远离舷侧方向偏移0-5mm,再利用线锤调整艉轴架2在分段1的长度方向上的前后位置。通过此设计,能够对艉轴架2的安装精度进行控制,使得将艉轴架2与分段1焊接完成后,艉轴架2的轴线与钢丝24在误差允许的范围内重合,以符合安装精度的要求。在本实施例中,所述轴孔中心线24沿竖直方向向上偏移所述钢丝2mm,再沿水平方向向远离舷侧方向偏移5mm。当然在实际施工中,具体反变形的释放量即所述轴孔中心线24沿竖直方向向上偏移所述钢丝的距离以及所述轴孔中心线24沿水平方向向远离舷侧方向偏移的距离均根据艉轴架2的内支臂21、外支臂22的尺寸大小而设定,并根据船厂经验进行。Considering the amount of contraction of the inner arm 21 and the outer arm 22 on the pylon 2 welded to the segment 1, in order to achieve precise control of the mounting accuracy of the pylon 2, in the step S20, the 艉 is adjusted. After the shaft hole center line 24 of the yoke 2 overlaps with the wire 24, the shaft hole center line 24 is offset upward in the vertical direction by 0-2 mm, and then shifted in the horizontal direction away from the side of the ship. 0-5 mm, and then the line hammer is used to adjust the front and rear positions of the yoke 2 in the longitudinal direction of the segment 1. With this design, the mounting accuracy of the yoke 2 can be controlled such that after the boring frame 2 and the segment 1 are welded, the axis of the yoke 2 coincides with the wire 24 within the error tolerance to fit the installation. Precision requirements. In the present embodiment, the shaft hole center line 24 is offset upward by 2 mm in the vertical direction and then offset by 5 mm in the horizontal direction away from the side of the ship. Of course, in actual construction, the specific anti-deformation release amount, that is, the axial hole center line 24 is offset upward in the vertical direction by the distance of the steel wire, and the shaft hole center line 24 is offset in the horizontal direction away from the side of the ship. The distances are set according to the size of the inner arm 21 and the outer arm 22 of the boring frame 2, and are based on shipyard experience.
在所述步骤S30中,所述艉轴架2与所述分段1焊接前对两者的焊接位置进行预热并且在焊接后进行保温,其中,预热的温度为120℃~150℃,预热的 时间根据具体的施工情况而定。进行预热能减缓焊后的冷却度,避免金属中扩散氢的溢出,提高焊接处的抗裂性,降低焊接应力,有效地提到了焊接的质量。在焊接后进行保温,能过使焊接处收缩均匀,防止焊接处开裂。In the step S30, the boring frame 2 and the segment 1 are preheated before welding and are insulated after welding, wherein the preheating temperature is 120 ° C to 150 ° C. Preheated The time depends on the specific construction conditions. Preheating can slow down the cooling after welding, avoid the overflow of diffused hydrogen in the metal, improve the crack resistance of the weld, reduce the welding stress, and effectively mention the quality of the weld. Insulation after welding can make the weld shrink evenly and prevent cracking at the weld.
为了控制艉轴架2安装在分段1左右两侧的形变,在预热后,对所述艉轴架2同时进行左右对称焊接。将两艉轴架2同时左右对称焊接,能够同时控制分体左右两侧的形变量,使得分体的左右两侧能够保持一致,避免由于左右两侧先后焊接的顺序不同使得艉轴架2在分段1的左右两侧之间存在着差异而影响分段1的平衡性,提高了艉轴架2的使用性能。In order to control the deformation of the pylon frame 2 mounted on the left and right sides of the segment 1, after the preheating, the yoke frame 2 is simultaneously symmetrically welded to the left and right. Simultaneously welding the two trusses 2 to the left and right symmetry, which can simultaneously control the shape variables on the left and right sides of the split body, so that the left and right sides of the split body can be kept consistent, avoiding the difference of the order of welding on the left and right sides, so that the stern frame 2 is There is a difference between the left and right sides of the segment 1 which affects the balance of the segment 1 and improves the performance of the creel 2 .
优选的,所述内支臂21和所述外支臂22与所述分段1的焊接形式为全透焊。采用全透焊的焊接方式避免了在焊接处产生焊缝,满足所述艉轴架2在使用过程中对强度的要求,延长了其使用寿命。Preferably, the inner arm 21 and the outer arm 22 are welded to the segment 1 in a fully through-welded manner. The use of full penetration welding avoids the occurrence of welds at the welds, satisfies the strength requirements of the boring frame 2 during use, and prolongs its service life.
其中,所述艉轴架2的焊接顺序为:先将所述分段1上的分别与内支臂21和外支臂22的对接的肋板11之间的对接处焊接,再将所述艉轴架2的内支臂21和外支臂22与所述分段1的肋板11之间的角接位置焊接,然后将所述艉轴架2的内支臂21和外支臂22与所述分段1的外板12的角接位置焊接,最后将散装外板与其他外板之间的对接缝焊接。在制作分段的过程中,为了方便安装艉轴架2,在分段1上预留艉轴架2的焊接位置。具体的,将分段1上艉轴架2的对接位置先不安装的肋板11,在焊接艉轴架2的过程中再将未与分段1焊接的肋板11焊接带分段1上,能够确保与内支臂21和外支臂22对接的肋板1之间焊装良好的前提下,再将内支臂21和外支臂22与肋板11焊接。在分段1上与艉轴架1对接的位置预留安装口,为焊接施工预留空间,能够降低焊接难度,同时方便焊接艉轴架2。同时也能尽量地减少对焊接区域外的外板12的损坏,并且也方便的焊接的过程中对外板12的调整。 Wherein, the welding sequence of the creel 2 is: first, the butt joint between the ribs 11 on the segment 1 and the abutting ribs 11 of the inner arm 21 and the outer arm 22, respectively, The inner arm 21 and the outer arm 22 of the yoke 2 are welded to the gusset 11 between the ribs 11 of the segment 1, and then the inner arm 21 and the outer arm 22 of the yoke 2 are The corner joints of the outer panel 12 of the segment 1 are welded, and finally the butt joint between the bulk outer panel and the other outer panels is welded. In the process of making the segment, in order to facilitate the installation of the yoke 2, the welding position of the yoke 2 is reserved on the segment 1. Specifically, the rib 11 which is not installed at the abutting position of the boring frame 2 of the segment 1 is welded to the rib 11 which is not welded to the segment 1 during the welding of the yoke 2 The inner arm 21 and the outer arm 22 are welded to the rib 11 while ensuring good welding between the ribs 1 which are in contact with the inner arm 21 and the outer arm 22. The installation port is reserved at the position where the stern frame 1 is docked on the segment 1 to reserve space for the welding construction, which can reduce the welding difficulty and facilitate the welding of the yoke frame 2. At the same time, the damage to the outer panel 12 outside the welded area can be minimized, and the adjustment of the outer panel 12 during the convenient welding process is also facilitated.
为了保证所述艉轴架2的安装精度,在所述艉轴架2焊接过程进行精度监控,使轴孔中心线24与轴孔理论中心线在焊接前的偏差为≤±1mm,焊接后的偏差为≤±2mm,轴孔23的前后端面中心和理论中心的位置在焊接前的偏差为≤±2mm,焊接后的位置偏差为≤±3mm。In order to ensure the installation accuracy of the boring frame 2, the precision of the welding process of the boring frame 2 is monitored, so that the deviation between the center line 24 of the shaft hole and the theoretical center line of the shaft hole before welding is ≤±1 mm, after welding The deviation is ≤±2 mm, and the position of the front and rear end faces of the shaft hole 23 and the position of the theoretical center is ≤±2 mm before welding, and the positional deviation after welding is ≤±3 mm.
为了配合在所述艉轴架2安装完成后将分段1吊装至船坞中进行船台大合装配的装配工序,所述步骤S30后设置步骤S40:分段1离开胎架前分别在分段1和艉轴架2上作出相应的标记,以供后续搭载使用,相应的标记包括:所述地样上的分段1中心线引分别至分段1的艏艉位置以及所述艉轴架2的轴孔23的前后端面上,将肋检线引至轴孔23的前后端面上以及将靠近标杆4的肋位线引至艉轴架2的外表面上,将所述轴孔中心线24引至所述艉轴架的轴孔23的前后端面上。在装配的过程中,将各分段1上的标记相对应合拢,减少了大合拢装配的工作量,提高了船舶的生产效率。In order to cooperate with the assembly process of lifting the segment 1 into the dock after the installation of the boring frame 2 is completed, the step S30 is followed by the step S40: the segment 1 is separated from the frame before the segment 1 Corresponding markings are made on the yoke 2 for subsequent loading. The corresponding markings include: the centerline of the segment 1 on the ground to the 艏艉 position of the segment 1 and the pylon 2 On the front and rear end faces of the shaft hole 23, the rib line is led to the front and rear end faces of the shaft hole 23 and the rib line near the pole 4 is led to the outer surface of the boring frame 2, and the shaft hole center line 24 is It is led to the front and rear end faces of the shaft hole 23 of the creel. In the process of assembly, the marks on each segment 1 are correspondingly closed, which reduces the workload of the large-close assembly and improves the production efficiency of the ship.
本发明所述的一种艉轴架安装方法所带来的经济效益:The economic benefit brought by the installation method of the boring frame of the invention:
1、由艉轴架的安装由船坞作业改为分段阶段,高空作业转地面,不仅节省了搭拆架费用,而且省去船坞脚手架搭设,按长16m×4m×12m的空间区域搭架计算,可节省人工费用约61440元。1. The installation of the boring frame is changed from the docking operation to the segmentation stage, and the aerial work is transferred to the ground, which not only saves the cost of the detaching frame, but also saves the construction of the scaffolding of the dock, and calculates the space area according to the length of 16m×4m×12m. , can save labor costs of about 61,440 yuan.
2、减少外板、艉轴架临时吊码约36个,即减少了相应的高空车配合、吊码装配焊接、探伤、拆除、打磨、修补、艉轴架探伤作业工序工序,节省的人工费用约为(40+60)×36×(1.5+2+0.5+1+2+1.5+0.5)=32400元。2. Reduce the temporary lifting code of the outer plate and the stern frame by about 36, which reduces the corresponding high-altitude car fitting, lifting code assembly welding, flaw detection, dismantling, grinding, repairing, boring frame inspection operation process, saving labor costs It is about (40+60)×36×(1.5+2+0.5+1+2+1.5+0.5)=32400 yuan.
3、采用传统的安装方法艉轴架定位过程中需大量起运人员、葫芦配合,提升至复位消耗时间至少3天,采用所述的艉轴架安装方法可节省人工费用约为10×300×3=9000元。3, using the traditional installation method 艉 艉 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位 定位= 9,000 yuan.
4、按照艉轴架在分段阶段安装,10个人花费6天完成,根据工时分段与船 坞1∶6计算,采用所述的艉轴架安装方法比传统的安装方法先比节省人工费用约为10×300×6×6=108000元。4, according to the truss frame installed in the segmentation stage, 10 people spend 6 days to complete, according to the working hours segment and the ship In the 1:6 calculation of the dock, the use of the above-mentioned boring frame mounting method saves labor costs by about 10×300×6×6=108,000 yuan compared with the conventional installation method.
5、缩短船坞建造(水下工程)周期至少10天。5. Shorten the construction of the dock (underwater engineering) for at least 10 days.
于本文的描述中,需要理解的是,术语“第一”、“第二”仅用于在描述上加以区分,不具有特殊含义。In the description herein, it is to be understood that the terms "first" and "second" are used only to distinguish between the description and have no special meaning.
需要声明的是,上述具体实施方式仅仅为本发明的较佳实施例及所运用技术原理,在本发明所公开的技术范围内,任何熟悉本技术领域的技术人员所容易想到的变化或替换,都应涵盖在本发明的保护范围内。 It is to be understood that the above-described embodiments are merely preferred embodiments of the invention and the technical principles of the invention, and any changes or substitutions that are readily apparent to those skilled in the art are within the scope of the presently disclosed technology. All should be covered by the scope of the present invention.

Claims (10)

  1. 一种艉轴架安装方法,其特征在于,提供艉轴架,在分段组装阶段将所述艉轴架安装在所述分段上,然后再一起随所述分段吊至船坞进行大合拢装配。A boring frame mounting method, characterized in that a truss frame is provided, and the boring frame is mounted on the segment in a stage assembling stage, and then hanged together with the segment to the dock for large closing assembly.
  2. 根据权利要求1所述的艉轴架安装方法,其特征在于,包括以下步骤:The creel mounting method according to claim 1, comprising the steps of:
    步骤S10、所述分段制作;Step S10, the segmentation is performed;
    步骤S20、所述艉轴架定位:在地样树立标杆,在所述标杆上划制高度检验线,所述高度检验线包括胎架水平基线和轴孔中心高度线,将所述艉轴架吊至所述分段处,并使其轴孔位于对应的所述标杆之间,根据所述轴孔中心高度线拉设钢丝,所述钢丝的一端与所述艉轴架的轴孔的一侧的所述标杆连接,另一端穿过所述艉轴架的轴孔与位于其另一侧的所述标杆连接,调整所述钢丝在所述标杆的位置,使所述钢丝与所述艉轴架的轴孔理论中心线重合,然后调整所述艉轴架的位置,使所述艉轴架的轴孔中心线沿水平和竖直方向偏移所述钢丝设定距离,再利用线锤调整所述艉轴架在所述分段的长度方向上的前后位置;Step S20: positioning the pylon frame: setting a pole on the ground, and drawing a height inspection line on the pole, the height inspection line including a horizontal base line of the tire frame and a center line height of the shaft hole, the yoke frame Hanging to the segment and having the shaft hole between the corresponding poles, pulling the wire according to the central line height line of the shaft hole, one end of the wire and one of the shaft holes of the boring frame The poles of the side are connected, the other end is connected to the pole on the other side through the shaft hole of the shank, and the position of the wire at the pole is adjusted to make the wire and the raft The theoretical center line of the shaft hole of the yoke is coincident, and then the position of the yoke frame is adjusted such that the center line of the shaft hole of the yoke frame is offset from the wire set distance in the horizontal and vertical directions, and then the wire hammer is used. Adjusting a front and rear position of the yoke frame in a length direction of the segment;
    步骤S30、所述艉轴架焊接:将所述艉轴架与所述分段焊接,并在焊接的过程中进行监控,如有偏差则重新调整,以保证焊装的精确度。Step S30, the boring frame welding: welding the boring frame and the segment, and monitoring during the welding process, and re-adjusting if there is a deviation to ensure the accuracy of the welding.
  3. 根据权利要求2所述的艉轴架安装方法,其特征在于,所述步骤S10具体包括:The boring frame mounting method according to claim 2, wherein the step S10 specifically comprises:
    步骤S11、在所述地样上根据图纸划制所述分段的轮廓地样线、分段中心线、肋检线以及标杆位置线;Step S11, drawing, on the ground sample, the contoured contour line, the segment center line, the rib inspection line, and the benchmark position line of the segment according to the drawing;
    步骤S12、在所述地样制作胎架,在所述胎架上制作所述分段;Step S12, preparing a tire frame on the ground sample, and forming the segment on the tire frame;
    步骤S13、在所述分段的外板上划制所述艉轴架的轴孔理论中心线。Step S13: Draw a theoretical centerline of the shaft hole of the boring frame on the outer panel of the segment.
  4. 根据权利要求2所述的艉轴架安装方法,其特征在于,在所述步骤S20与所述步骤S30之间还设置步骤S21:采用定位件对所述艉轴架进行加强定位。The boring frame mounting method according to claim 2, wherein a step S21 is further provided between the step S20 and the step S30: the locating frame is reinforced by the positioning member.
  5. 根据权利要求2所述的艉轴架安装方法,其特征在于,在所述步骤S20 中:调整所述轴孔中心线后,使所述轴孔中心线沿竖直方向向上偏移所述钢丝0-2mm,再沿水平方向向远离舷侧方向偏移0-5mm,再利用线锤调整艉轴架在分段的长度方向上的前后位置。The creel mounting method according to claim 2, wherein in the step S20 Medium: after adjusting the center line of the shaft hole, the center line of the shaft hole is offset upward in the vertical direction by 0-2 mm, and then offset from the side of the ship by 0-5 mm in the horizontal direction, and then the line is used. The hammer adjusts the front and rear positions of the creel in the longitudinal direction of the segment.
  6. 根据权利要求2所述的艉轴架安装方法,其特征在于,在所述步骤S30中,所述艉轴架与所述分段焊接前对两者的焊接位置进行预热并且在焊接后进行保温,其中,预热的温度为120℃~150℃。The creel mounting method according to claim 2, wherein in the step S30, the yoke frame and the segment welding are preheated before welding and are performed after welding Insulation, wherein the preheating temperature is from 120 ° C to 150 ° C.
  7. 根据权利要求6所述的艉轴架安装方法,其特征在于,在预热后,对所述艉轴架同时进行左右对称焊接。The creel mounting method according to claim 6, wherein after the preheating, the creel is simultaneously welded symmetrically.
  8. 根据权利要求7所述的艉轴架安装方法,其特征在于,所述艉轴架的焊接顺序为:先将所述分段上的分别与内支臂和外支臂的对接的肋板之间的对接处焊接,再将所述艉轴架的内支臂和外支臂与所述分段的肋板之间的角接位置焊接,然后将所述艉轴架的内支臂和外支臂与所述分段的外板的角接位置焊接,最后将散装外板与其他外板之间的对接缝焊接。The pylon mounting method according to claim 7, wherein the yoke is welded in the order of ribs on the segments that are respectively abutted with the inner and outer arms. Welding between the butt joints, welding the inner and outer arms of the creel and the gussets of the segmented ribs, and then the inner arms of the yoke The arms are welded to the corner joints of the segmented outer plates, and finally the butt joints between the bulk outer plates and the other outer plates are welded.
  9. 根据权利要求8所述的艉轴架安装方法,其特征在于,在所述艉轴架焊接过程进行精度监控,使所述轴孔中心线与所述艉轴架的轴孔理论中心线在焊接前的偏差为≤±1mm,焊接后的偏差为≤±2mm,所述轴孔的前后端面中心和理论中心的位置在焊接前的偏差为≤±2mm,焊接后的位置偏差为≤±3mm。The pylon mounting method according to claim 8, wherein the precision monitoring of the boring frame welding process is performed such that the center line of the shaft hole and the theoretical center line of the shaft hole of the boring frame are welded The deviation before is ≤±1 mm, and the deviation after welding is ≤±2 mm. The deviation between the center of the front and rear end faces of the shaft hole and the position of the theoretical center before welding is ≤±2 mm, and the position deviation after welding is ≤±3 mm.
  10. 根据权利要求3所述的艉轴架安装方法,其特征在于,所述步骤S30后设置步骤S40:所述分段离开所述胎架前分别在所述分段和所述艉轴架上作出相应的标记,以供后续搭载使用,相应的标记包括:将所述地样上的分段中心线分别引至所述分段的艏艉位置以及所述艉轴架的轴孔的前后端面上,将所述肋检线引至轴孔的前后端面上以及将靠近标杆的肋位线引至艉轴架的外表面上,将所述轴孔中心线引至所述艉轴架的轴毂前后端面上。 The creel mounting method according to claim 3, wherein the step S30 is followed by a step S40: the segments are respectively made on the segment and the boring frame before leaving the frame Corresponding markings for subsequent loading, the corresponding markings include: guiding the segment centerline on the ground to the 艏艉 position of the segment and the front and rear end faces of the yoke Leading the rib inspection line to the front and rear end faces of the shaft hole and guiding the rib line near the pole to the outer surface of the boring frame, and guiding the center line of the shaft hole to the hub of the boring frame On the front and rear end faces.
PCT/CN2017/108826 2017-06-28 2017-10-31 Method for installing propeller shaft bracket WO2019000750A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710505644.XA CN107323608A (en) 2017-06-28 2017-06-28 A kind of propeller shaft bracket installation method
CN201710505644.X 2017-06-28

Publications (1)

Publication Number Publication Date
WO2019000750A1 true WO2019000750A1 (en) 2019-01-03

Family

ID=60198448

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2017/108826 WO2019000750A1 (en) 2017-06-28 2017-10-31 Method for installing propeller shaft bracket

Country Status (2)

Country Link
CN (1) CN107323608A (en)
WO (1) WO2019000750A1 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109238106B (en) * 2018-09-20 2020-10-23 中船黄埔文冲船舶有限公司 Tail shaft bracket inspection method and structure
CN109263804A (en) * 2018-09-30 2019-01-25 广船国际有限公司 A kind of ship underwater observation structure
CN110510059A (en) * 2019-07-15 2019-11-29 沪东中华造船(集团)有限公司 A kind of method of tail fin end support installation
CN111268054B (en) * 2020-03-20 2021-01-01 浙江国际海运职业技术学院 Method for welding front stay wire of stern push base
CN113525622A (en) * 2021-08-12 2021-10-22 招商局金陵船舶(江苏)有限公司 Method for mounting single-arm and double-arm shaft support of roll-on-roll-off ship

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55110683A (en) * 1979-02-14 1980-08-26 Mitsubishi Heavy Ind Ltd Method of fitting shaft bracket
CN101100218A (en) * 2007-07-30 2008-01-09 黄润樟 Mounting method for shaft tube peculiar to vessel
CN102059461A (en) * 2010-12-15 2011-05-18 广州中船黄埔造船有限公司 High precision welding method for rudder horn, propeller shaft bracket and intermediate shaft bracket of long shaft ship
CN102303176A (en) * 2011-08-11 2012-01-04 扬帆集团股份有限公司 Assembly welding process for propeller shaft bracket
CN102390484A (en) * 2011-10-06 2012-03-28 山东中复船艇科技发展有限公司 Installation method for tail shaft support of glass fiber reinforced plastics ship
CN102431626A (en) * 2011-10-18 2012-05-02 沪东中华造船(集团)有限公司 Installation method of overlong twin-skeg structure segment and shaft bracket dock

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101264790A (en) * 2007-12-28 2008-09-17 广州文冲船厂有限责任公司 Method for mounting stern herringbone bracket
CN102407921B (en) * 2011-09-01 2014-02-26 广州中船黄埔造船有限公司 Mounting method for sectional inversely hung rudder arm
CN103072667B (en) * 2011-10-25 2015-06-03 上海船厂船舶有限公司 Method for locating tail pipe supporting seat in subsection
CN104608878B (en) * 2015-03-02 2017-05-24 启东丰顺船舶重工有限公司 Mounting technology of rudder horn of transport ship for liquified natural gas (LNG)

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55110683A (en) * 1979-02-14 1980-08-26 Mitsubishi Heavy Ind Ltd Method of fitting shaft bracket
CN101100218A (en) * 2007-07-30 2008-01-09 黄润樟 Mounting method for shaft tube peculiar to vessel
CN102059461A (en) * 2010-12-15 2011-05-18 广州中船黄埔造船有限公司 High precision welding method for rudder horn, propeller shaft bracket and intermediate shaft bracket of long shaft ship
CN102303176A (en) * 2011-08-11 2012-01-04 扬帆集团股份有限公司 Assembly welding process for propeller shaft bracket
CN102390484A (en) * 2011-10-06 2012-03-28 山东中复船艇科技发展有限公司 Installation method for tail shaft support of glass fiber reinforced plastics ship
CN102431626A (en) * 2011-10-18 2012-05-02 沪东中华造船(集团)有限公司 Installation method of overlong twin-skeg structure segment and shaft bracket dock

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
QIN, HANQIANG: "The Block Pre-assembly Process of Ship Stern Shaft Bracket and the Assembly Practice of Real Ship", CHINA WATER TRANSPORT, vol. 13, no. 12, 15 December 2013 (2013-12-15), pages 1, 2, ISSN: 1006-7973 *

Also Published As

Publication number Publication date
CN107323608A (en) 2017-11-07

Similar Documents

Publication Publication Date Title
WO2019000750A1 (en) Method for installing propeller shaft bracket
CN109094723B (en) Anchor chain cylinder and anchor platform manufacturing and mounting method
WO2019000751A1 (en) Method for mounting lateral thrust device
CN110723263B (en) Ship rudder blade refitting process
CN102029473B (en) Aerological welding method of steel sleeve
CN102407921A (en) Mounting method for sectional inversely hung rudder arm
CN108995764B (en) Method for installing rudder sleeve of LNG (liquefied Natural gas) transport ship
CN102102444A (en) Assembling and positioning construction method of large steel casting members
CN113148058B (en) Process for installing and positioning double rudder sleeve and tail casting in stage of sectional construction
CN116100182A (en) Welding method for C-shaped marine LNG storage tank anti-moving block
CN103203589A (en) Manufacturing method of pre-baking aluminium cell shell
CN113814589B (en) Method for controlling splicing precision of oversized flange
CN113320659B (en) Method for assembling flange and barrel of double-angle steering oar of ship
CN111976916B (en) Full-rotation telescopic push mounting process for engineering ship
CN104590487B (en) A kind of working ship is with large-scale stern cylinder flange disk high precision assembling and welding process
CN102493347B (en) Method for machining and mounting flanges between sections of steel pipe arch
CN110877682A (en) Ship unbalanced anchor lip preassembling process
CN105438400A (en) Mounting method for large movable ramp
CN111604643B (en) Manufacturing and mounting process of crane upright column for ship and ocean engineering
CN110498007B (en) Installation method for inverted installation and lateral pushing of horizontal sectional material
CN113928504A (en) Shaft-rudder integrated sectional construction process
CN108661238B (en) Girder and end beam structure manufacturing process
CN110104546B (en) Construction method for rigid legs of gantry crane
CN110466494B (en) Hovercraft air guide sleeve and processing method thereof
CN115627806B (en) Pile leg lengthening process

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17915916

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 17915916

Country of ref document: EP

Kind code of ref document: A1