WO2016130643A1 - Method and apparatus for constructing a concrete structure - Google Patents

Method and apparatus for constructing a concrete structure Download PDF

Info

Publication number
WO2016130643A1
WO2016130643A1 PCT/US2016/017299 US2016017299W WO2016130643A1 WO 2016130643 A1 WO2016130643 A1 WO 2016130643A1 US 2016017299 W US2016017299 W US 2016017299W WO 2016130643 A1 WO2016130643 A1 WO 2016130643A1
Authority
WO
WIPO (PCT)
Prior art keywords
column
poured
cast concrete
cast
structure according
Prior art date
Application number
PCT/US2016/017299
Other languages
French (fr)
Inventor
Bryant ZAVITZ
Original Assignee
Tindall Corporation
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tindall Corporation filed Critical Tindall Corporation
Publication of WO2016130643A1 publication Critical patent/WO2016130643A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/43Floor structures of extraordinary design; Features relating to the elastic stability; Floor structures specially designed for resting on columns only, e.g. mushroom floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0645Shear reinforcements, e.g. shearheads for floor slabs

Definitions

  • the present invention relates to a method and apparatus for constructing a concrete structure.
  • the invention relates to constructing a concrete structure using pre-cast concrete components.
  • Natural gas is becoming a greater and greater share of the U.S. energy supply due to advances in hydraulic fracking. Natural gas is generally sent through a pipeline to a terminal, where it is compressed to liquefied natural gas (LNG) before loading it into tanks for transport.
  • LNG liquefied natural gas
  • This terminal generally includes a platform to support 4-7 compressors, each of which weighs several tons. Due to the increased supply of natural gas, additional terminals are needed to process the supply. However, the terminals are presently constructed by pouring concrete in place for all of the structure, which can take on the order of six months.
  • the present invention broadly comprises a method and apparats for constructing a concrete structure.
  • One embodiment of the invention may be implemented as an apparatus including a pre-cast concrete component and a poured in place concrete surface supported by the pre-cast concrete component.
  • FIGS. 1-8 illustrate a process for making a concrete structure according to an exemplary embodiment of the present invention
  • FIG. 9 illustrates several views of one embodiment of a column and a column cap
  • FIGS. 10 and 1 1 illustrate perspective views of embodiments of the column cap with floor portions stacked thereon;
  • FIG. 12 illustrates an top view of the floor sections supported by the column cap
  • FIGS. 13 and 14 show side views of the floor sections supported by the column cap.
  • FIG. 15 shows a perspective cutaway view of the floor sections supported by the column cap.
  • FIG. 16 shows close up side section views of the floor sections supported by the column cap. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
  • FIGS 1 -8 show exemplary process steps for constructing a structure 10 in accordance with the present invention.
  • Figure 8 shows the final structure 10 in one embodiment of the invention.
  • Structure 10 includes columns 20 to support the main surface 50.
  • Main surface 50 supports the compressors used to compress the LNG.
  • Main surface 50 includes apertures 52A, 52B, and 52C. These apertures allow pipes (not shown) to access the compressors from below main surface 50. These pipes may link the compressors to each other, as the compression is done in stages.
  • the pipes may also connect to storage tanks to pull off components of the natural gas that liquefy during a particular compression stage.
  • Figure 1 shows that the first step includes placing columns 20. Column caps 30 are then placed on the columns in Figure 2.
  • Figure 9 shows column 20 and column cap 30 in greater detail.
  • Figure 3 shows that side portions 40 and floor portions 42 are then placed on the column caps 20. All of these components are pre-cast concrete components, so this process can be done relatively quickly.
  • FIG 4 shows that the side portions 40 and floor portions 42 are assembled for the first third of the structure.
  • Floor portions 42 are designed to include the apertures 52A, 52B, and 52C.
  • concrete may now be poured to create the main surface 50 for the first third of the structure 10. These pours may be done incrementally, for example breaking each third into 5 pours as shown in Figure 1-8. This allows workers to begin constructing the middle third of the structure, as shown in Figure 5.
  • Figures 6 and 7 show the middle and final third of structure 10 being constructed in a similar manner as the first third. Finally, Figure 8 shows the completed structure.
  • Figure 9-16 provide greater detail of the pre-cast components 20, 30, 40 and 42.
  • Columns 20 may have steel reinforcement members 22, as shown in Figure 13.
  • Column caps 30 may also have steel reinforcement members 36, also shown in Figure 13.
  • Column caps also include support member 32 and alignment projection 34.
  • Support member 32 supports the floor portions 40 that are stacked on the column caps 30.
  • Alignment projections 34 allow the floor portions 40 to be locked into place on the column cap 30.
  • Figure 15 shows a perspective view of the floor portions 40 supported by support member 32 and aligned by alignment projections 34.
  • Floor portions 40 may also include steel reinforcement member 44, as shown in Figure 15.
  • Floor portions 40 are locked in place on the column caps by the alignment projections, and may also be linked to each other. Once main surface 50 is cast over the floor portions 44, all of the components are locked together by main surface 50.
  • the compressors used to compress the natural gas cause a reciprocating load on the supporting structure, which requires a support with isotropic load-bearing properties.
  • pre-cast components typically are not isotropic, pre-cast components have not been used to support these types of compressors before.
  • typical pre-cast components can support 4-5 times the load in a primary direction as opposed to the load that can be borne in secondary directions.
  • pre-cast bridge components typically can support 4-5 times as much load in the traffic direction as compared to the transverse direction.
  • the disclosed composite structure can support approximately the same load in all directions.
  • the present inventors have combined reinforced pre-cast components with a partial poured in place surface to create a composite structure that has the isotropic properties to support the compressors, while being capable of being constructed using much less time and labor than conventional poured in place structures.

Abstract

The present invention broadly comprises a method and apparatus for constructing a concrete structure, where one embodiment of apparatus includes a pre-cast concrete component and a poured in place concrete surface supported by the pre-cast concrete component. A structure comprising: a pre-cast concrete component; and a poured in place concrete surface supported by the pre-cast concrete component.

Description

METHOD AND APPARATUS FOR CONSTRUCTING A CONCRETE STRUCTURE
CROSS-REFERENCE TO RELATED APPLICATIONS
[0001] This application claims priority to U.S. Patent Application No. 15/040,130, filed February 10, 2016 and under 35 U.S.C. §1 19(e) to U.S. Application No. 62/1 14,219, filed February 10, 2015, the entire content of each of which is incorporated into the present application by reference.
FIELD OF THE INVENTION
[0002] The present invention relates to a method and apparatus for constructing a concrete structure. In particular, the invention relates to constructing a concrete structure using pre-cast concrete components.
BACKGROUND OF THE INVENTION
[0003] Natural gas is becoming a greater and greater share of the U.S. energy supply due to advances in hydraulic fracking. Natural gas is generally sent through a pipeline to a terminal, where it is compressed to liquefied natural gas (LNG) before loading it into tanks for transport. This terminal generally includes a platform to support 4-7 compressors, each of which weighs several tons. Due to the increased supply of natural gas, additional terminals are needed to process the supply. However, the terminals are presently constructed by pouring concrete in place for all of the structure, which can take on the order of six months. SUMMARY OF THE INVENTION
[0004] The present invention broadly comprises a method and apparats for constructing a concrete structure. One embodiment of the invention may be implemented as an apparatus including a pre-cast concrete component and a poured in place concrete surface supported by the pre-cast concrete component.
BRIEF DESCRIPTION OF THE DRAWINGS
[0005] A full and enabling disclosure of the present subject matter, including the best mode thereof, directed to one of ordinary skill in the art, is set forth in the specification, which makes reference to the appended figures, in which:
[0006] FIGS. 1-8 illustrate a process for making a concrete structure according to an exemplary embodiment of the present invention;
[0007] FIG. 9 illustrates several views of one embodiment of a column and a column cap;
[0008] FIGS. 10 and 1 1 illustrate perspective views of embodiments of the column cap with floor portions stacked thereon;
[0009] FIG. 12 illustrates an top view of the floor sections supported by the column cap;
[0010] FIGS. 13 and 14 show side views of the floor sections supported by the column cap; and
[0011] FIG. 15 shows a perspective cutaway view of the floor sections supported by the column cap; and
[0012] FIG. 16 shows close up side section views of the floor sections supported by the column cap. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] Reference is presently made in detail to exemplary embodiments of the present subject matter, one or more examples of which are illustrated in or represented by the drawings. Each example is provided by way of explanation of the present subject matter, not limitation of the present subject matter. In fact, it will be apparent to those skilled in the art that various modifications and variations can be made in the present subject matter without departing from the scope or spirit of the present subject matter. For instance, features illustrated or described as part of one embodiment can be used with another embodiment to yield a still further embodiment. Thus, it is intended that the present subject matter covers such modifications and variations as come within the scope of the disclosure and equivalents thereof.
[0014] Figures 1 -8 show exemplary process steps for constructing a structure 10 in accordance with the present invention. Figure 8 shows the final structure 10 in one embodiment of the invention. Structure 10 includes columns 20 to support the main surface 50. Main surface 50 supports the compressors used to compress the LNG. Main surface 50 includes apertures 52A, 52B, and 52C. These apertures allow pipes (not shown) to access the compressors from below main surface 50. These pipes may link the compressors to each other, as the compression is done in stages. The pipes may also connect to storage tanks to pull off components of the natural gas that liquefy during a particular compression stage.
[0015] In the embodiment shown in Figure 8, there are 6 stages to the compression process. Thus, there are 6 sets of apertures 52A, 52B, and 52C. The compression process compresses the natural gas from approximately 5-20 psi to approximately 1,700 psi. Natural gas is mostly methane, but does include other hydrocarbons. Thus, there are other components of the natural gas that liquefy before the methane does. Accordingly, some of the compressors are designed to pull off these other components as the natural gas is compressed. In this regard, the two left-most compressors on main surface 50 need three apertures to provide the piping necessary for their compression stage, while the other four compressors only need two apertures. However, any number of stages and access apertures are within the scope of the invention.
[0016] Figure 1 shows that the first step includes placing columns 20. Column caps 30 are then placed on the columns in Figure 2. Figure 9 shows column 20 and column cap 30 in greater detail. Figure 3 shows that side portions 40 and floor portions 42 are then placed on the column caps 20. All of these components are pre-cast concrete components, so this process can be done relatively quickly.
[0017] Figure 4 shows that the side portions 40 and floor portions 42 are assembled for the first third of the structure. Floor portions 42 are designed to include the apertures 52A, 52B, and 52C. As shown in Figure 5, concrete may now be poured to create the main surface 50 for the first third of the structure 10. These pours may be done incrementally, for example breaking each third into 5 pours as shown in Figure 1-8. This allows workers to begin constructing the middle third of the structure, as shown in Figure 5.
[0018] Figures 6 and 7 show the middle and final third of structure 10 being constructed in a similar manner as the first third. Finally, Figure 8 shows the completed structure.
[0019] Again, as most of the components are pre-cast components, construction can be completed much faster than a structure made of poured in place concrete. The present invention minimizes the used of poured in place concrete, allowing dramatic time savings over the present construction techniques.
[0020] Figure 9-16 provide greater detail of the pre-cast components 20, 30, 40 and 42. Columns 20 may have steel reinforcement members 22, as shown in Figure 13. Column caps 30 may also have steel reinforcement members 36, also shown in Figure 13. Column caps also include support member 32 and alignment projection 34. Support member 32 supports the floor portions 40 that are stacked on the column caps 30. Alignment projections 34 allow the floor portions 40 to be locked into place on the column cap 30. Figure 15 shows a perspective view of the floor portions 40 supported by support member 32 and aligned by alignment projections 34.
[0021] Floor portions 40 may also include steel reinforcement member 44, as shown in Figure 15. Floor portions 40 are locked in place on the column caps by the alignment projections, and may also be linked to each other. Once main surface 50 is cast over the floor portions 44, all of the components are locked together by main surface 50.
[0022] The compressors used to compress the natural gas cause a reciprocating load on the supporting structure, which requires a support with isotropic load-bearing properties. As pre-cast components typically are not isotropic, pre-cast components have not been used to support these types of compressors before. In this regard, typical pre-cast components can support 4-5 times the load in a primary direction as opposed to the load that can be borne in secondary directions. For example, pre-cast bridge components typically can support 4-5 times as much load in the traffic direction as compared to the transverse direction. In contrast, the disclosed composite structure can support approximately the same load in all directions. Thus, the present inventors have combined reinforced pre-cast components with a partial poured in place surface to create a composite structure that has the isotropic properties to support the compressors, while being capable of being constructed using much less time and labor than conventional poured in place structures.
[0023] The present written description uses examples to disclose the present subject matter, including the best mode, and also to enable any person skilled in the art to practice the present subject matter, including making and using any devices or systems and performing any incorporated and/or associated methods. While the present subject matter has been described in detail with respect to specific embodiments thereof, it will be appreciated that those skilled in the art, upon attaining an understanding of the foregoing may readily produce alterations to, variations of, and equivalents to such embodiments. Accordingly, the scope of the present disclosure is by way of example rather than by way of limitation, and the subject disclosure does not preclude inclusion of such modifications, variations and/or additions to the present subject matter as would be readily apparent to one of ordinary skill in the art.

Claims

CLAIMS:
1. A structure comprising:
a pre-cast concrete component; and
a poured in place concrete surface supported by the pre-cast concrete component.
2. The structure according to claim 1, wherein the apparatus has isotropic load-bearing strengths.
3. The structure according to claim 1 , wherein the pre-cast concrete component is a column.
4. The structure according to claim 1, wherein the pre-cast concrete component is a cap on a top of a column.
5. The structure according to claim 4, wherein the pre-cast concrete component also includes a floor section that is supported by the cap on the top of the column.
6. The structure according to claim 1 , wherein the pre-cast concrete component is a floor section.
7. The structure according to claim 6, wherein the poured in place concrete surface is located over the floor section.
8. The structure according to claim 1, wherein the poured in place concrete surface includes several apertures that extend through the concrete surface.
9. A method for making a structure comprising:
providing a plurality of pre-cast concrete columns;
placing a plurality of pre-cast concrete column caps on the plurality of columns such that there is one column cap on each column;
placing a plurality of floor sections on support members of the plurality of column caps; and
pouring a poured in place concrete surface on the plurality of floor sections.
10. The method according to claim 9, wherein the pouring includes pouring the poured in place concrete surface on the plurality of floor sections with a plurality of apertures that extend through the concrete surface.
11. The method according to claim 9, wherein the plurality of floor sections are pre-cast concrete floor sections.
PCT/US2016/017299 2015-02-10 2016-02-10 Method and apparatus for constructing a concrete structure WO2016130643A1 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
US201562114219P 2015-02-10 2015-02-10
US62/114,219 2015-02-10
US15/040,130 2016-02-10
US15/040,130 US20160230386A1 (en) 2015-02-10 2016-02-10 Method and apparatus for constructing a concrete structure

Publications (1)

Publication Number Publication Date
WO2016130643A1 true WO2016130643A1 (en) 2016-08-18

Family

ID=56565754

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2016/017299 WO2016130643A1 (en) 2015-02-10 2016-02-10 Method and apparatus for constructing a concrete structure

Country Status (2)

Country Link
US (1) US20160230386A1 (en)
WO (1) WO2016130643A1 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3060622B1 (en) * 2016-12-21 2020-10-02 Electricite De France PERMANENT CONCRETE FORMWORK AND PROCESS FOR MANUFACTURING A METAL-CONCRETE COMPOSITE STRUCTURE USING SUCH FORMWORK
WO2019014256A1 (en) * 2017-07-10 2019-01-17 Tindall Corporation Methods and apparatuses for constructing a concrete structure
CN108824700B (en) * 2018-06-26 2020-10-16 江苏新龙兴建设集团有限公司 Construction method of equal cast-in-place assembled steel-concrete beam
WO2020132266A1 (en) * 2018-12-20 2020-06-25 Tindall Corporation Methods and apparatuses for constructing a concrete structure
CN109853739B (en) * 2019-02-27 2020-06-23 青岛理工大学 Assembled steel-wood combined node
CN110616808B (en) * 2019-09-04 2020-07-14 青岛理工大学 Assembled floor type steel-wood combined node and assembling method thereof
CN110644619B (en) * 2019-09-21 2020-10-09 青岛理工大学 Assembly type limiting reinforced steel-wood frosted sleeve combined node

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4081935A (en) * 1976-07-26 1978-04-04 Johns-Manville Corporation Building structure utilizing precast concrete elements
US6442913B1 (en) * 2000-03-10 2002-09-03 Kenneth N. Mann Freestanding wall
US7028435B2 (en) * 2003-11-07 2006-04-18 Climatized Self-Storage Const. Co. Multi-story concrete slab construction
US20090057531A1 (en) * 2007-08-28 2009-03-05 Lance Waite Column forming apparatus and methods
CN202347393U (en) * 2011-11-30 2012-07-25 上海市城市建设设计研究总院 Precast assembled concrete upright post and pile cap structure
US20140000207A1 (en) * 2007-06-22 2014-01-02 Diversakore Llc Framing Structure

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US915421A (en) * 1908-07-06 1909-03-16 Theodore Augustus Eisen Construction of buildings.
US1380324A (en) * 1919-01-30 1921-05-31 William S Piggins Concrete construction
US4505087A (en) * 1983-03-14 1985-03-19 U.S. Filigree Wideslab, Inc. Method of construction of concrete decks with haunched supporting beams
US5507124A (en) * 1991-09-17 1996-04-16 The Board Of Regents Of The University Concrete framing system
US8011147B2 (en) * 2006-09-11 2011-09-06 Hanlon John W Building system using modular precast concrete components

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4081935A (en) * 1976-07-26 1978-04-04 Johns-Manville Corporation Building structure utilizing precast concrete elements
US6442913B1 (en) * 2000-03-10 2002-09-03 Kenneth N. Mann Freestanding wall
US7028435B2 (en) * 2003-11-07 2006-04-18 Climatized Self-Storage Const. Co. Multi-story concrete slab construction
US20140000207A1 (en) * 2007-06-22 2014-01-02 Diversakore Llc Framing Structure
US20090057531A1 (en) * 2007-08-28 2009-03-05 Lance Waite Column forming apparatus and methods
CN202347393U (en) * 2011-11-30 2012-07-25 上海市城市建设设计研究总院 Precast assembled concrete upright post and pile cap structure

Also Published As

Publication number Publication date
US20160230386A1 (en) 2016-08-11

Similar Documents

Publication Publication Date Title
US20160230386A1 (en) Method and apparatus for constructing a concrete structure
US10557264B2 (en) Methods and apparatuses for constructing a concrete structure
EP3121506B1 (en) Ground liquefied natural gas storage tank and method for manufacturing same
US8387334B2 (en) LNG containment system and method of assembling LNG containment system
US10364939B2 (en) Free-standing liner unit and method of building tank
US20220098883A1 (en) Load-carrying concrete floor structure and method for building the load-carrying concrete floor structure
US10597888B2 (en) Precast and prestressed concrete tank with temporary construction opening
WO2012099042A1 (en) Method for constructing cylindrical tank
US20180155951A1 (en) Method and apparatus for constructing a concrete tower
US20160097211A1 (en) Prestressed concrete roof for cylindrical tank
CN210067580U (en) LNG storage tank
KR101562767B1 (en) The temporary bridge using prestress steel materials and prestress tendon and foundation method of temporary bridge
PH12014000078A1 (en) Continuous girder bridge and method for construction of the same
WO2020132266A1 (en) Methods and apparatuses for constructing a concrete structure
CN212078224U (en) Anti-seismic reinforced concrete structure
Kim et al. Development of rapid construction technology for liquified natural gas storage tanks using precast concrete panels as a permanent form.
CN208329320U (en) Shear Behavior of R. c. Laminated Slabs precast construction
KR100457961B1 (en) The construction and the method of continuous prestressed concrete composite structure connected span-division point
GB2536959A (en) Construction method and structures built using such
JP2012001968A (en) Construction method of cylindrical tank
JP2017210743A (en) Construction method of inner tank of flat-bottomed cylindrical tank
JPH06313377A (en) Storage silo
JPH0524304B2 (en)

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 16749782

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 16749782

Country of ref document: EP

Kind code of ref document: A1