WO2015078195A1 - Live overhaul process for ± 500 kv double-loop dc power transmission line on same tower - Google Patents

Live overhaul process for ± 500 kv double-loop dc power transmission line on same tower Download PDF

Info

Publication number
WO2015078195A1
WO2015078195A1 PCT/CN2014/083325 CN2014083325W WO2015078195A1 WO 2015078195 A1 WO2015078195 A1 WO 2015078195A1 CN 2014083325 W CN2014083325 W CN 2014083325W WO 2015078195 A1 WO2015078195 A1 WO 2015078195A1
Authority
WO
WIPO (PCT)
Prior art keywords
ladder
worker
double
card
equipotential
Prior art date
Application number
PCT/CN2014/083325
Other languages
French (fr)
Chinese (zh)
Inventor
余雷
刘越
汤正汉
向文祥
刘继承
王星超
Original Assignee
国家电网公司
国网湖北省电力公司检修公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 国家电网公司, 国网湖北省电力公司检修公司 filed Critical 国家电网公司
Publication of WO2015078195A1 publication Critical patent/WO2015078195A1/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Definitions

  • the invention relates to the field of ultra-high voltage power transmission and transformation, in particular to a charging and repairing process for a ⁇ 500kV double-circuit direct current transmission line on the same tower. Background technique
  • the operation, maintenance and repair of transmission lines is an important means to master the operation of the power grid, to detect and deal with equipment defects in time, and to ensure the safe and stable operation of the line. Since the UHV grid is at the core of the operation of the national grid, the operation and overhaul of the EHV grid is of great significance for ensuring the safe, stable and reliable operation of the UHV grid and even the entire national grid.
  • the comprehensive transformation of Gehu DC is ⁇ 500kV Genan Line (Linfeng Line)
  • the same tower double-circuit DC transmission project is an innovative project for the development of DC transmission technology in the world. It is the first double-circuit DC transmission project in the same tower at home and abroad. The project is to transform the original Genan single-circuit line (capacity of 1200MW) into a double-circuit ⁇ 500kV capacity DC line (capacity of 2x3000MW). It is the implementation of the strong grid construction by the State Grid Corporation and the implementation of the national power transmission to the west.
  • Another key project of the development strategy is to have a positive significance for further expanding the scale of the Three Gorges and Sichuan hydropower transmission, enhancing the liaison between Huazhong and East China, and building a strong national grid.
  • the 500kV double-circuit line on the same tower is a brand-new operation mode of the DC line.
  • the line structure and window gap are quite different from other projects, especially the tower structure and the tensile-proof insulator type string assembly form. big change. Therefore, the traditional method of operation can not meet the needs of ⁇ 500kV double-circuit DC line maintenance on the same tower.
  • the first step is to study a set of scientific methods of operation, including the way of operation and the process flow. The research on the maintenance of ⁇ 500kV double-circuit DC line on the same tower, live working methods and working tools will be our urgent problems.
  • the electrification maintenance process includes an operation method of entering an equipotential
  • the operation method for entering the equipotential includes the following steps: the equipotential worker and the ground potential worker follow the dress code After wearing, carry the insulated transmission rope to the ground support to fasten the seat belt, and install the insulated pulley and the insulated transmission rope at the appropriate position on the working ground support; the ground worker transmits the insulation ladder and installs the insulation of the ladder control rope.
  • the ladder is attached to the ground potential worker position; the ground potential worker removes the anti-vibration hammer of the working side overhead ground line, and then the ladder ladder is reliably installed on the overhead ground line, and the ladder hook control rope is installed; the equipotential worker checks the shielding After the parts are well connected, fasten the insulation protection rope, board the insulation ladder and attach the safety belt to the insulation ladder. If it is a tensile tower, the ground potential worker uses the ladder head control rope to drive the insulation ladder along the overhead space. The line is moved to the parallel of the tensile clamp. If it is a straight tower, the ground potential worker uses the ladder to control the rope. The edge ladder moves about 5m along the overhead ground line.
  • the equipotential workers descend along the insulation ladder until the shoulders are flush with the upper sub-wires.
  • the ground workers use the insulated ladder tail rope to swing the insulation ladder.
  • the equipotential workers are about 0.5 from the live conductor. When you are at m, quickly reach and hold the wire for potential transfer.
  • the equipotential worker in the operation method of entering the equipotential, enters the potential and fastens the seat belt, and determines whether to release the insulation protection rope according to the operation requirement, and the equipotential worker checks and inspects the parts of the shielding suit. After the connection is good, board the insulation ladder and attach the seat belt to the insulation ladder.
  • the dress code includes an equipotential worker wearing a full set of rhinoceros garments and a shielded garment wearing a flame retardant garment, the rhinoceros garment including a rhinoceros cap, a shielded garment, a shielding glove, and a shielding sock.
  • the shielding shoes and rhinoceros masks, ground potential workers must wear a full set of static protective clothing and conductive shoes.
  • the equipotential is exited according to the following steps: After the equipotential worker checks and checks that the parts of the shielding suit are well connected, the boarding station is placed on the insulating ladder and the seat belt is attached to the insulating ladder. The equipotential worker loosens the wire and quickly withdraws the arm. The ground worker uses the insulated ladder tail rope to swing the insulation ladder, and the equipotential worker exits the equipotential; the ground potential worker uses the insulated ladder control rope to drive the insulation ladder along the overhead ground at the ground support.
  • the line is moved to the crossarm, the equipotential worker unfastens the seat belt attached to the insulating ladder, climbs up the cross arm and fastens the seat belt; the ground potential worker cooperates with the ground worker to remove all the tools and restore the ground line defense. Installation of the vibrating hammer; After the equipotential workers and the ground potential workers inspect the unretained objects on the tower, carry the insulated transmission rope to the lower tower.
  • the electrification overhaul process includes a method of replacing a linear double "V" insulator string, a hard-turn double “L” insulator string, the replacement of a straight double “V” insulator string, a hard turn double”
  • the operation method of the L" insulator string includes the following steps: Retaining the construction hole at the hanging point of the insulator string or the tower of the main material at the hanging point The upper fulcrum, the special clamp for the cross-arm of the pole tower is installed, and the large-knife card is installed by the side fulcrum of the wire side of the two-layer board of the wire-side tool; the wire-drawing device and the high-strength insulating tie rod are connected with the special fixture on the tower to form the insulator string.
  • the wire lifting device in the method of replacing the linear double “V” insulator string and the hard-turn double “L” insulator string, includes a mechanical screw and a hydraulic screw.
  • the electrification overhaul process includes a method of replacing a tensile-resistance insulator, the method of replacing the tensile-resistor insulator comprising the following steps: after entering the potential, two equipotential workers ⁇ Standing on the adjacent porcelain rod insulators in a back-to-back manner, using the traction plate and the parallel hanging plate as the fulcrum to install the cross-arm side-end special card, using the porcelain rod insulator steel cap as the fulcrum to install the closed card card
  • the hydraulic screw assembly is used to connect the tensile special card and the closed card to form the tight line system, and then the tripod assembly is installed for transferring the tool and the insulator; the front card of the closed card is separately installed by using the front and rear rod insulator steel cap as a fulcrum After the card, the front and rear cards of the closed card are connected by a hydraulic screw assembly to form a tight line system, and then the tripod assembly is installed for transferring the
  • the charging and repairing process of the ⁇ 500kV double-circuit direct current transmission line of the same tower of the present invention is the first research project of the live working application technology of the ultra-high voltage double-circuit direct current transmission line on the same tower at home and abroad, and the characteristics of the ⁇ 500kV double-circuit direct current transmission line on the same tower
  • the research has realized the completion of the project research work and the application of the research results, filling the gaps in the field of ultra-high voltage DC live working and live maintenance application technology at home and abroad.
  • Figure 1 is a schematic illustration of a method for entering an equipotential in a live overhaul process of a ⁇ 500 kV homotaxial double-circuit DC transmission line in accordance with a preferred embodiment of the present invention.
  • Figure 2 is a schematic diagram of the "positive wire drawing” method of replacing the insulator string.
  • 3A and 3B are respectively used to replace the linear double "V” insulator string and the hard-turn double “L” insulator string.
  • Figure 4 is a schematic diagram of the operation of replacing the linear double "V" insulator string and the hard-turn double "L” insulator string with the large knife card in Figure 3.
  • 5A and 5B are structural schematic views of the hydraulic closed card front and rear cards respectively used in the method of replacing the tensile-resistance insulator.
  • 6A and 6B are a partial cross-sectional view and a partial cross-sectional view of another cross-angle side airfoil card used in the method of replacing the tensile-resistance insulator.
  • Fig. 7 is a structural schematic view of a wire side airfoil card used in the method of replacing the tensile-resistance insulator. detailed description
  • entering the equipotential operation is the basic operation mode for live working, and is the basis for the realization of other live working items. Firstly, it breaks through the difficulty of entering the potential. According to the design structure of the ⁇ 500kV double-circuit DC transmission line of the same tower, the window window size and the gap form and air gap level required by the operation, the traditional cross-supporting ladder is vertically entered into the equipotential. The research and design of the working method of the horizontal swinging into the equipotential of the flying ladder.
  • the tower requires two workers on the tower, one of which is an equipotential electrician and the other is a tower-ground potential electrician.
  • equipotential workers Before entering the equipotential, equipotential workers must wear a full set of shielding clothing, including caps, underwear, gloves, socks and shoes, and wear a shielded mask. In addition, flame-retardant underwear should also be worn inside the shielded clothing. .
  • Ground potential workers must wear full static protective clothing and conductive shoes.
  • Equipotential workers and ground potential workers carry insulated transmission ropes to the ground support, fasten the seat belts, and install the insulated pulleys and insulated transmission ropes at appropriate positions on the working ground support.
  • the ground workers use the insulated ladder tail rope to swing the insulation ladder.
  • the equipotential workers are about 0.5m away from the live conductor, they quickly reach and hold the conductor for potential transfer.
  • the equipotential worker can exit the equipotential as follows:
  • the equipotential worker loosens the wire and quickly withdraws the arm.
  • the ground worker uses the insulated ladder tail rope to swing the insulation ladder, and the equipotential worker exits the equipotential.
  • the ground potential worker cooperates with the ground electrician to remove all the tools and restore the installation of the ground anti-vibration hammer (if any, the grounding wire is finally removed).
  • the components on the 500kV double-circuit DC transmission line on the same tower can be inspected. Since there are many work items in the 500kV double-circuit DC transmission line on the same tower, the repair methods of some components are the same as the previous operation methods, so I will not comment here. In the following, the key operation methods of the electrified maintenance process such as the live replacement insulator will be described in detail.
  • a wire lifting device (mechanical screw or hydraulic screw), a high-strength insulated tie rod, and a four-split wire feeder are connected to the wire to form a mechanical load transfer system of the insulator string.
  • the load transfer system is tightened by operating the mechanical screw or the hydraulic screw, and the wire is slowly lifted, so that the mechanical load of the repaired insulator string is transferred to the wire-raising system to realize the maintenance of the insulator string.
  • the mechanical load of the wire-lifting tool of the "positive wire-drawing" operation mode may cause the horizontal direction of the insulator-side insulator string to be weakened, thereby causing the wire to be offset in the opposite direction.
  • the hook end of the large knife card has a bayonet that is set on both sides of the inverted triangle two-plate, and the root platform of the bayonet is in contact with the bottom side of the inverted triangle two-plate.
  • a through hole for mounting a knurled screw is provided on both sides of the opening of the large knife card, and the through hole is used for the external screw.
  • the large knife card also has a groove at the waist. If it is necessary to carry out pre-maintenance and overhaul of the metal fitting on one side of the triangular joint board, firstly, the bayonet card of the large knife card is clamped on the bottom of the side of the inverted triangle two-piece board, and the hook is hooked in the inverted triangle.
  • the threaded screw of the center of the two-plate center, the root platform of the bayonet supports the end of the pre-maintenance and overhaul of the inverted triangle two-piece board, so that the other end of the side of the inverted triangle-connected board is the fulcrum, and the open end is the end of the lever .
  • the screw rod is externally connected to the open end, and the force is applied to the open end by manually adjusting the screw rod, so that the end of the lever, that is, the opening, only needs to exert a small force to be used on the pre-maintenance and overhaul end of the triangular joint plate. The heavy load is removed.
  • the mechanical load transfer system that constitutes the insulator string is connected by a wire lifting device (mechanical screw or hydraulic wire) and a high-strength insulating tie rod to the cross-arm clamp on the tower;
  • the wire lifting device is operated to perform a small-distance wire-lifting displacement, and the large-cutter card operating arm is driven to rotate, and the belt-operating arm transfers the load on the insulator string, so that the mechanical load of the insulative insulator string is transferred to the wire-drawing system to realize the maintenance of the insulator string.
  • the working load of the double "V” insulator string and the hard-turn double “L” insulator string card is 50KN.
  • the above process utilizes the principle of leverage, and the operation of the wire lifting device for the displacement of the wire at a small distance can drive the rotation of the large knife operation arm, and the action arm can transfer the load on the insulator string, and the double "V” insulator can be replaced conveniently and quickly.
  • String, hard turn double "L” insulator string is
  • the replacement of tensile insulators and insulator strings is a routine project for maintenance and live working of transmission lines, and is also a daily work for maintenance and repair of transmission lines.
  • the tensile insulators and the insulator strings are replaced by a conventional one.
  • the replacement of the tensile insulator method and the improved spinning method are used to replace the tensile insulator method.
  • the bottle holder method is to install a tight line system at both ends of the repair insulator string, and place a bottle holder under the tightness, tighten the wire system to protect the insulator string from the wire tension, and then disconnect the insulator string and the wire and the cross arm.
  • the spinning method is to first loosen the insulator with the insulator string tension adjuster, then use the traction system to pull the insulator to disengage the wire side porcelain bottle, and rotate the porcelain bottle string to the vertical position along the tower suspension point before placing it on the ground.
  • the reverse work process completes the maintenance work.
  • the double-circuit line insulator string on the same tower is designed as a horizontal glass insulator or a ceramic rod insulator.
  • the glass string is the smallest (light pollution area) 40 pieces, the length is 10.737 meters, the single string weight is 0.73T, the largest (heavy pollution area) 57 pieces, the length is 14.222 meters, the single string weight is about 0.97T; the porcelain rod insulator
  • the string consists of 7 pieces, which is 14.772 meters long and weighs about 0.95T in a single string.
  • the project is based on the double-strength design of the ⁇ 500kV double-circuit DC line project and the insulation form used in the same project.
  • the single-replacement operation mode is selected to focus on the design of the replaced ceramic rod insulator with short-zero value. In order to achieve the purpose of replacement.
  • the specific operation process is as follows:
  • the two equipotential workers stand in the "back to back" mode on the adjacent rod insulators, using the traction plate (QY-42S type) and the parallel hanging plate (P-42S) as the fulcrum installation.
  • the cross-arm side is resistant to the card (as shown in Figure 6), using a porcelain rod insulator steel cap as a fulcrum to install a closed card rear card (as shown in Figure 5), using a hydraulic screw assembly to connect the tensile card and The closed card forms a tight line system, and then the tripod assembly is mounted for the transfer of tools and insulators;
  • System then install a tripod assembly for transporting tools and insulators;
  • Single-piece replacement process for ordinary insulators Use the cross-arm side plate as the fulcrum, install the cross-arm side-resistant special card, use the insulator steel cap as the fulcrum, install the insulator closed card front card, and connect the tensile-resistant special card with the hydraulic screw.
  • the closed card form a tight line system
  • using the insulator steel cap as the fulcrum respectively installing the front card and the rear card of the insulator closed card, and connecting the front card and the rear card of the insulator closed card with the hydraulic screw to form a tight line system
  • Insulator steel cap as the fulcrum install the insulator closed card rear card, use the wire side joint plate ⁇ t fulcrum, install the wire side turn airfoil card, use the hydraulic screw to connect the closed card and the wire side turn with the airfoil card
  • the wire system operating the hydraulic screw to tighten the tight line system, transferring the mechanical load on the repaired insulator to achieve the replacement and maintenance of the insulator.
  • the charging and repairing process of the ⁇ 500kV double-circuit DC transmission line of the same tower of the present invention is the first research project of the first 500kV double-circuit live working application on the same tower at home and abroad, the completion of the project research work and the application of the research results. It fills the gaps in the field of live working and live maintenance application of ⁇ 500kV double-circuit DC transmission lines on the same tower at home and abroad.
  • the specific operation method in the charging and repairing process of the ⁇ 500kV double-circuit DC transmission line of the same tower of the present invention covers the inspection and repair of the ⁇ 500kV double-circuit DC transmission line on the same tower, and the routine maintenance work of the live working, wherein the porcelain rod insulator replacement tool,
  • the single-short-circuit replacement method for large-tonnage combined hydraulic screw is applied to live working, especially to the ⁇ 500kV double-circuit line operation method in the same tower. It is a major breakthrough in the field of live working application technology.
  • the invention has been described with reference to a few specific embodiments of the invention, which are not to be construed as limiting the scope of the invention. It should be noted that those skilled in the art can make various modifications and improvements without departing from the inventive concept, and these are all within the scope of the present invention. Therefore, the scope of the invention should be determined by the appended claims.

Landscapes

  • Electric Cable Installation (AREA)
  • Insulators (AREA)

Abstract

A live overhaul process for a ± 500 kV double-loop DC power transmission line on the same tower. An operation method of entering equal potential comprises the steps of: after an equal potential worker and an earth potential worker carry insulated transmission ropes and climb to an earth wire peak and fasten safety belts, installing, by the equal potential worker and the earth potential worker, an insulated pulley and the insulated transmission ropes on the earth wire peak; transmitting, by a ground worker, an insulated flexible ladder and a hanging head of the insulated flexible ladder to the position of the earth potential worker; dismantling, by the earth potential worker, a damper of a working-side overhead earth wire, and reliably installing the hanging head of the insulated flexible ladder on the overhead earth wire; after checking the connection of various parts of screening clothing, the equal potential worker fastening an insulated protection rope, climbing to the insulated flexible ladder and fastening the safety belt to the insulated flexible ladder; and swinging, by the ground worker, the insulated flexible ladder using a tail rope of the insulated flexible ladder, and quickly reaching out for the wire to carry out potential transfer when the equal potential worker is about 0.5 m away from a live wire. The live overhaul process can improve the efficiency of line repairs.

Description

± 500kV同塔双回直流输电线路带电检修工艺 技术领域  ±500kV double-circuit DC transmission line on the same tower
本发明涉及超高压输变电领域, 尤其涉及一种 ± 500kV同塔双回直流输电线路带电 检修工艺。 背景技术  The invention relates to the field of ultra-high voltage power transmission and transformation, in particular to a charging and repairing process for a ±500kV double-circuit direct current transmission line on the same tower. Background technique
输电线路运行维护检修工作是掌握电网运行情况、 及时发现和处理设备缺陷的重要 手段, 也是确保线路安全稳定运行的基础工作。 由于超高压电网在整个国家电网运行中 处于核心地位, 因此超高压电网的运行检修工作对于保证超特高压电网乃至整个国家电 网的安全、 稳定、 可靠运行具有十分重要的意义。  The operation, maintenance and repair of transmission lines is an important means to master the operation of the power grid, to detect and deal with equipment defects in time, and to ensure the safe and stable operation of the line. Since the UHV grid is at the core of the operation of the national grid, the operation and overhaul of the EHV grid is of great significance for ensuring the safe, stable and reliable operation of the UHV grid and even the entire national grid.
葛沪直流综合改造即 ± 500kV葛南线 (林枫线) 同塔双回直流输电工程是世界直流 输电技术发展的创新工程, 是目前国内外首条同塔双回直流输电工程。 该工程是利用原 葛南单回线(容量为 1200MW )路径改造为双回 ±500kV增容直流线路(容量为 2x3000MW ) 的工程, 是国家电网公司实施坚强电网建设, 落实国家西电东送能源发展战略的又一重 点工程, 对于进一步扩大三峡和四川水电送出规模, 增强华中与华东地区的电网联络, 建设国家坚强电网具有积极意义。  The comprehensive transformation of Gehu DC is ± 500kV Genan Line (Linfeng Line) The same tower double-circuit DC transmission project is an innovative project for the development of DC transmission technology in the world. It is the first double-circuit DC transmission project in the same tower at home and abroad. The project is to transform the original Genan single-circuit line (capacity of 1200MW) into a double-circuit ±500kV capacity DC line (capacity of 2x3000MW). It is the implementation of the strong grid construction by the State Grid Corporation and the implementation of the national power transmission to the west. Another key project of the development strategy is to have a positive significance for further expanding the scale of the Three Gorges and Sichuan hydropower transmission, enhancing the liaison between Huazhong and East China, and building a strong national grid.
士 500kV同塔双回线路是直流线路一个全新的运行模式, 其线路结构、 窗口间隙等 与其它工程相比有很大区别, 尤其是杆塔结构、 耐张瓷棒式绝缘子串组装形式发生了很 大的变化。 因此, 传统的作业方法不能满足 ± 500kV同塔双回直流线路检修的需要。 如 要进行检修、 带电作业, 首先是必须研究一套科学的作业方法, 包括作业方式以及作业 工艺流程。 ± 500kV同塔双回直流线路检修、 带电作业方法及作业工器具的研究将是我 们目前亟待解决的问题。 该课题的研究成果将填补我国 ± 500kV同塔双回直流输电线路 检修及带电作业工器具研制和带电作业实用化技术上的空白。 对开创 ± 500kV同塔双回 直流线路检修, 提高线路检修效率, 保证设备的健康水平起到巨大的作用。 发明内容  The 500kV double-circuit line on the same tower is a brand-new operation mode of the DC line. The line structure and window gap are quite different from other projects, especially the tower structure and the tensile-proof insulator type string assembly form. big change. Therefore, the traditional method of operation can not meet the needs of ± 500kV double-circuit DC line maintenance on the same tower. For maintenance and live work, the first step is to study a set of scientific methods of operation, including the way of operation and the process flow. The research on the maintenance of ± 500kV double-circuit DC line on the same tower, live working methods and working tools will be our urgent problems. The research results of this subject will fill the blank of the overhaul of ± 500kV double-circuit DC transmission line on the same tower and the development of live working tools and practical technology for live working. It is of great significance to create a ± 500kV double-circuit DC line maintenance on the same tower, improve line maintenance efficiency, and ensure the health of the equipment. Summary of the invention
有鉴于此, 为克服现有技术的不足, 有必要提供一种适用于 ± 500kV同塔双回直流 输电线路的带电检修工艺。 In view of this, in order to overcome the deficiencies of the prior art, it is necessary to provide a double-circuit DC for the same tower of ± 500 kV. The electrification maintenance process of the transmission line.
一种 ± 500kV同塔双回直流输电线路带电检修工艺, 所述带电检修工艺包括进入等 电位的作业方法, 所述进入等电位的作业方法包括以下步骤: 等电位工人和地电位工人 按照着装规范穿戴完毕后, 携带绝缘传递绳登塔至地线支架处系好安全带, 将绝缘滑车 和绝缘传递绳安装在作业地线支架适当位置上; 地面工人传递绝缘软梯、 安装好软梯控 制绳的绝缘软梯挂头至地电位工人位置; 地电位工人拆除工作侧架空地线的防振锤, 然 后将软梯挂头可靠安装在架空地线上, 并装好软梯挂头控制绳; 等电位工人检查屏蔽服 各部分连接良好后, 系好绝缘保护绳, 登上绝缘软梯站好并将安全带系于绝缘软梯上, 若为耐张杆塔则地电位工人利用软梯挂头控制绳将绝缘软梯沿架空地线移至耐张线夹平 行处,若为直线杆塔则地电位工人利用软梯挂头控制绳将绝缘软梯沿架空地线外移约 5m, 等电位工人沿绝缘软梯下行, 至肩部与上子导线平齐时停止; 地面工人利用绝缘软梯尾 绳摆动绝缘软梯, 等电位工人距带电导线约 0.5m处时快速伸手握住导线进行电位转移。  A charging and repairing process for a ±500kV double-circuit DC transmission line on the same tower, the electrification maintenance process includes an operation method of entering an equipotential, and the operation method for entering the equipotential includes the following steps: the equipotential worker and the ground potential worker follow the dress code After wearing, carry the insulated transmission rope to the ground support to fasten the seat belt, and install the insulated pulley and the insulated transmission rope at the appropriate position on the working ground support; the ground worker transmits the insulation ladder and installs the insulation of the ladder control rope. The ladder is attached to the ground potential worker position; the ground potential worker removes the anti-vibration hammer of the working side overhead ground line, and then the ladder ladder is reliably installed on the overhead ground line, and the ladder hook control rope is installed; the equipotential worker checks the shielding After the parts are well connected, fasten the insulation protection rope, board the insulation ladder and attach the safety belt to the insulation ladder. If it is a tensile tower, the ground potential worker uses the ladder head control rope to drive the insulation ladder along the overhead space. The line is moved to the parallel of the tensile clamp. If it is a straight tower, the ground potential worker uses the ladder to control the rope. The edge ladder moves about 5m along the overhead ground line. The equipotential workers descend along the insulation ladder until the shoulders are flush with the upper sub-wires. The ground workers use the insulated ladder tail rope to swing the insulation ladder. The equipotential workers are about 0.5 from the live conductor. When you are at m, quickly reach and hold the wire for potential transfer.
在其中至少一个实施例中, 在所述进入等电位的作业方法中, 等电位工人进入电位 后系好安全带, 并根据作业需要确定是否解除绝缘保护绳, 等电位工人检查检查屏蔽服 各部分连接良好后, 登上绝缘软梯站好并将安全带系于绝缘软梯上。  In at least one of the embodiments, in the operation method of entering the equipotential, the equipotential worker enters the potential and fastens the seat belt, and determines whether to release the insulation protection rope according to the operation requirement, and the equipotential worker checks and inspects the parts of the shielding suit. After the connection is good, board the insulation ladder and attach the seat belt to the insulation ladder.
在其中至少一个实施例中, 所述着装规范包括, 等电位工人穿着全套犀蔽服装以及 屏蔽服装内穿阻燃内衣, 所述犀蔽服装包括犀蔽帽、 屏蔽衣裤、 屏蔽手套、 屏蔽袜、 屏 蔽鞋以及犀蔽面罩, 地电位工人必须穿着全套静电防护服装和导电鞋。  In at least one of the embodiments, the dress code includes an equipotential worker wearing a full set of rhinoceros garments and a shielded garment wearing a flame retardant garment, the rhinoceros garment including a rhinoceros cap, a shielded garment, a shielding glove, and a shielding sock. , shielding shoes and rhinoceros masks, ground potential workers must wear a full set of static protective clothing and conductive shoes.
在其中至少一个实施例中, 在带电检修工作完成后, 按照以下步骤退出等电位: 等 电位工人检查检查屏蔽服各部分连接良好后, 登上绝缘软梯站好并将安全带系于绝缘软 梯上; 等电位工人松开导线并将手臂迅速收回, 地面工人利用绝缘软梯尾绳摆动绝缘软 梯, 等电位工人退出等电位; 地电位工人在地线支架处利用绝缘软梯控制绳将绝缘软梯 沿架空地线移至横担处,等电位工人解开系于绝缘软梯上的安全带,向上攀爬登上横担, 系好安全带; 地电位工人与地面工人配合拆除全部工具, 并恢复地线防振锤的安装; 等 电位工人、 地电位工人检查塔上无遗留物后, 携带绝缘传递绳下塔。  In at least one of the embodiments, after the electrification maintenance work is completed, the equipotential is exited according to the following steps: After the equipotential worker checks and checks that the parts of the shielding suit are well connected, the boarding station is placed on the insulating ladder and the seat belt is attached to the insulating ladder. The equipotential worker loosens the wire and quickly withdraws the arm. The ground worker uses the insulated ladder tail rope to swing the insulation ladder, and the equipotential worker exits the equipotential; the ground potential worker uses the insulated ladder control rope to drive the insulation ladder along the overhead ground at the ground support. The line is moved to the crossarm, the equipotential worker unfastens the seat belt attached to the insulating ladder, climbs up the cross arm and fastens the seat belt; the ground potential worker cooperates with the ground worker to remove all the tools and restore the ground line defense. Installation of the vibrating hammer; After the equipotential workers and the ground potential workers inspect the unretained objects on the tower, carry the insulated transmission rope to the lower tower.
在其中至少一个实施例中, 所述带电检修工艺包括更换直线双 "V" 绝缘子串、 硬 转双 "L" 绝缘子串的作业方法, 所述更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子 串的作业方法包括以下步骤: 利用绝缘子串挂点处预留施工孔或挂点处主材做工具的塔 上支点, 安装杆塔横担专用卡具, 利用导线侧二联板^ t工具的导线侧支点安装大刀卡; 通过提线装置、 高强度绝缘拉杆与塔上专用卡具相连, 组成绝缘子串的机械荷载转移系 统; 利用大刀卡的卡背与二联板接触处作为支点, 并将大刀卡分成作用臂和操作臂, 操 作提线装置进行小距离的提线变位, 驱动大刀卡操作臂转动, 带动作用臂转移绝缘子串 上荷载, 使被检修绝缘子串机械荷载转移到提线系统, 实现绝缘子串的检修和更换。 In at least one of the embodiments, the electrification overhaul process includes a method of replacing a linear double "V" insulator string, a hard-turn double "L" insulator string, the replacement of a straight double "V" insulator string, a hard turn double" The operation method of the L" insulator string includes the following steps: Retaining the construction hole at the hanging point of the insulator string or the tower of the main material at the hanging point The upper fulcrum, the special clamp for the cross-arm of the pole tower is installed, and the large-knife card is installed by the side fulcrum of the wire side of the two-layer board of the wire-side tool; the wire-drawing device and the high-strength insulating tie rod are connected with the special fixture on the tower to form the insulator string. Mechanical load transfer system; using the contact point of the card back and the two plates of the large knife card as a fulcrum, and dividing the large knife card into the working arm and the operating arm, operating the wire lifting device to carry out the wire movement of the small distance, driving the large knife card operating arm to rotate The action arm transfers the load on the insulator string, and transfers the mechanical load of the insulative insulator string to the wire lifting system to realize the inspection and replacement of the insulator string.
在其中至少一个实施例中, 在所述更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子 串的作业方法中, 所述提线装置包括机械丝杆、 液压丝杆。  In at least one of the embodiments, in the method of replacing the linear double "V" insulator string and the hard-turn double "L" insulator string, the wire lifting device includes a mechanical screw and a hydraulic screw.
在其中至少一个实施例中, 所述带电检修工艺包括更换耐张瓷棒式绝缘子的作业方 法, 所述更换耐张瓷棒式绝缘子的作业方法包括以下步骤: 进入电位后, 两位等电位工 人釆用背靠背的方式站位在相邻的瓷棒式绝缘子上, 利用牵引板和平行挂板做支点安装 横担侧耐张专用卡, 利用瓷棒式绝缘子钢帽做支点安装闭式卡后卡, 用液压丝杆组件连 接耐张专用卡和闭式卡组成紧线系统, 然后安装三角架组件用于传送工具及绝缘子; 利 用前后棒式绝缘子钢帽做支点分别安装闭式卡的前卡和后卡, 用液压丝杆组件连接闭式 卡的前卡和后卡组成紧线系统, 然后安装三角架组件用于传送工具及绝缘子; 利用绝缘 子钢帽 ^故支点安装闭式卡前卡, 利用联板^ t支点安装导线侧翼型卡, 用液压丝杆组件连 接闭式卡和导线侧翼型卡组成紧线系统, 然后安装三角架组件用于传送工具及绝缘子; 操作液压丝杆收紧紧线系统, 转移被检修瓷棒式绝缘子上的机械荷载, 实现绝缘子的更 换和检修。  In at least one of the embodiments, the electrification overhaul process includes a method of replacing a tensile-resistance insulator, the method of replacing the tensile-resistor insulator comprising the following steps: after entering the potential, two equipotential workers站Standing on the adjacent porcelain rod insulators in a back-to-back manner, using the traction plate and the parallel hanging plate as the fulcrum to install the cross-arm side-end special card, using the porcelain rod insulator steel cap as the fulcrum to install the closed card card The hydraulic screw assembly is used to connect the tensile special card and the closed card to form the tight line system, and then the tripod assembly is installed for transferring the tool and the insulator; the front card of the closed card is separately installed by using the front and rear rod insulator steel cap as a fulcrum After the card, the front and rear cards of the closed card are connected by a hydraulic screw assembly to form a tight line system, and then the tripod assembly is installed for transferring the tool and the insulator; and the closed card front card is used by the insulator steel cap; The joint plate side wing type card is installed on the joint plate, and the hydraulic screw rod assembly is used to connect the closed type card and the wire side wing type card to form a tight line system, and then install three The angle bracket assembly is used to transport the tool and the insulator; the hydraulic screw is tightened to tighten the wire system, and the mechanical load on the inspected porcelain rod insulator is transferred to realize the replacement and maintenance of the insulator.
本发明的 ± 500kV同塔双回直流输电线路带电检修工艺, 是国内外第一个超高压同 塔双回直流输电线路带电作业应用技术研究项目, 通过 ± 500kV同塔双回直流输电线路 的特点的研究, 实现了对项目研究工作的完成及研究成果的应用, 填补了国内外超高压 直流带电作业、 带电检修应用技术领域的空白。 附图说明  The charging and repairing process of the ±500kV double-circuit direct current transmission line of the same tower of the present invention is the first research project of the live working application technology of the ultra-high voltage double-circuit direct current transmission line on the same tower at home and abroad, and the characteristics of the ±500kV double-circuit direct current transmission line on the same tower The research has realized the completion of the project research work and the application of the research results, filling the gaps in the field of ultra-high voltage DC live working and live maintenance application technology at home and abroad. DRAWINGS
图 1为釆用本发明的较佳实施例 ± 500kV同塔双回直流输电线路带电检修工艺中进 入等电位的方法的示意图。  BRIEF DESCRIPTION OF THE DRAWINGS Figure 1 is a schematic illustration of a method for entering an equipotential in a live overhaul process of a ±500 kV homotaxial double-circuit DC transmission line in accordance with a preferred embodiment of the present invention.
图 2为 "正提线" 方法更换绝缘子串的示意图。  Figure 2 is a schematic diagram of the "positive wire drawing" method of replacing the insulator string.
图 3A、 3B分别为更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子串作业方法中釆 用的大刀卡的主视图和俯视图。 3A and 3B are respectively used to replace the linear double "V" insulator string and the hard-turn double "L" insulator string. The main view and top view of the large knife card used.
图 4为釆用图 3中的大刀卡更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子串的操 作示意图。  Figure 4 is a schematic diagram of the operation of replacing the linear double "V" insulator string and the hard-turn double "L" insulator string with the large knife card in Figure 3.
图 5A、 5B分别为更换耐张瓷棒式绝缘子的方法中所釆用的液压式闭式卡前卡和后 卡的结构示意图。  5A and 5B are structural schematic views of the hydraulic closed card front and rear cards respectively used in the method of replacing the tensile-resistance insulator.
图 6A、 6B分别为更换耐张瓷棒式绝缘子的方法中所釆用的横担侧翼型卡的局部剖 视图和另一角度的局部剖视图。  6A and 6B are a partial cross-sectional view and a partial cross-sectional view of another cross-angle side airfoil card used in the method of replacing the tensile-resistance insulator.
图 7为更换耐张瓷棒式绝缘子的方法中所釆用的导线侧翼型卡的结构示意图。 具体实施方式  Fig. 7 is a structural schematic view of a wire side airfoil card used in the method of replacing the tensile-resistance insulator. detailed description
为更好地理解本发明, 以下将结合附图和具体实例对发明进行详细的说明。  In order to better understand the present invention, the invention will be described in detail below with reference to the drawings and specific examples.
在对本发明的技术方案进行详细的介绍之前, 首先对项目研究的理论基础进行筒单 的陈述:  Before the detailed introduction of the technical solution of the present invention, the theoretical basis of the project research is first stated:
( 1 )依据中南电力设计院等设计单位提供的 ± 500kV直流同塔双回线路的杆塔结构、 绝缘子串型、 金具连接形式、 导地线布置方式以及线路机械荷载水平和空气间隙形式; (1) According to the design unit of Zhongnan Electric Power Design Institute, the tower structure of the ± 500kV DC double-circuit line on the same tower, the insulator string type, the fitting form of the gold fittings, the layout of the grounding line, and the mechanical load level and air gap form of the line;
( 2 )依据国网电力科学研究院对士 500kV同塔双回直流输电线路过电压水平的分析 计算及士 500kV同塔双回直流线路带电作业间隙试验的研究, 提出的超高压同塔双回直 流线路带电作业最小安全距离、 最小组合间隙、 工具有效绝缘长度和有效绝缘子片数等 带电作业绝缘配合理论值; (2) According to the analysis and calculation of the overvoltage level of the 500kV double-circuit DC transmission line on the same tower of the State Grid Electric Power Research Institute and the gap test of the live operation of the 500kV double-circuit DC line on the same tower, the proposed ultra-high voltage double-circuit on the same tower The theoretical value of the insulation fit of the live working such as the minimum safe distance of the DC line live working, the minimum combined clearance, the effective insulation length of the tool and the number of effective insulators;
( 3 )依据国网公司 2009年新版《安规》及《±500kV直流输电线路带电作业技术导 则》所规定的带电作业最小安全距离、 最小组合间隙、 工具有效绝缘长度和有效绝缘子 片数等带电作业绝缘配合理论值;  (3) According to the new version of “Safety Regulations” of State Grid Corporation of 2009 and the “Technical Guidelines for Live Working of ±500kV DC Transmission Lines”, the minimum safety distance of live working, the minimum combined clearance, the effective insulation length of the tool and the number of effective insulators, etc. Insulation matching theoretical value of live working;
( 4 )依据国网电力科学研究院《士 500kV同塔双回直流线路带电作业实验研究》(高 电压技术 第 36卷 第二期 2010年 2月 28日)所计算得出的带电作业最小安全距离、最 小组合间隙等试验值。  (4) According to the State Grid Electric Power Research Institute "Study on the live operation of the 500kV double-circuit DC line on the same tower" (high voltage technology, Vol. 36, No. 2, February 28, 2010), the minimum safety of live working is calculated. Test values such as distance and minimum combined clearance.
± 500kV葛南 (林枫线) 同塔双回直流输电线路工程(即三沪二回直流输电工程) 作为国内首条同塔双回的超高压直流输电工程, 其输电线路检修、 带电作业工作在国内 外尚未开展, 其作业工艺及应用工具研制工作亟需解决。 ± 500kV葛南线(林枫线) 同塔双回直流输电线路总体结构是由杆塔、 绝缘子、 导 地线及连接金具组成, 比单回超高压直流线路塔增加了一层横担用于承担另一回线路。 设在深入消化了国网电力科学院关于士 500kV同塔双回直流线路带电作业技术研究成果 的基础上,认真分析了 ± 500kV同塔双回直流线路设计参数,充分探讨了与普通 ± 500kV 电压等级带电作业的差异性、 特殊性, 研究了同塔双回超高压直流线路检修作业、 带电 作业操作方法及操作工艺, 确定了 ± 500kV同塔双回直流线路带电作业绝缘配合参数, 重点对进入等电位的方法以及更换绝缘子的工艺流程进行了深入的研究, 验证带电作业 人员防护的具体措施。 ± 500kV Genan (Linfeng Line) The same tower double-circuit DC transmission line project (ie, Sanhu 2nd DC transmission project) As the first ultra-high voltage DC transmission project in the same tower in China, its transmission line maintenance and live working work It has not been carried out at home and abroad, and the development of its operation technology and application tools needs to be solved. ± 500kV Genan Line (Linfeng Line) The overall structure of the double-circuit DC transmission line of the same tower is composed of a tower, an insulator, a grounding wire and a connecting fitting. It adds a layer of crossbar to the single-circuit UHV DC line tower to bear another One line back. Based on the in-depth digestion of the research results of the 500kV twin-circuit DC line live working technology of the State Grid Electric Power Academy, the design parameters of the ±500kV double-circuit DC line on the same tower were carefully analyzed, and the voltage level of ±500kV was fully discussed. The difference and particularity of live working are studied. The overhaul operation of the double-circuit ultra-high voltage DC line on the same tower, the operation method and operation process of the live working, and the insulation coordination parameters of the live working of the ±500kV double-circuit DC line on the same tower are determined. The method of potential and the process flow for replacing the insulator have been thoroughly studied to verify the specific measures for protection of live workers.
首先, 进入等电位作业是带电作业基本作业方式, 又是其他带电作业项目实现的基 础。 首先突破进入电位的难关, 根据 ± 500kV同塔双回直流输电线路设计结构特点, 杆 塔窗口尺寸以及作业要求的间隙形式和空气间隙水平, 摒弃了传统的横担挂软梯垂直进 入等电位的方式, 研究设计了飞车软梯水平摆入等电位的作业方法。  First, entering the equipotential operation is the basic operation mode for live working, and is the basis for the realization of other live working items. Firstly, it breaks through the difficulty of entering the potential. According to the design structure of the ±500kV double-circuit DC transmission line of the same tower, the window window size and the gap form and air gap level required by the operation, the traditional cross-supporting ladder is vertically entered into the equipotential. The research and design of the working method of the horizontal swinging into the equipotential of the flying ladder.
以下将对飞车软梯水平摆入等电位的的作业方法进行详细地介绍。  The following is a detailed description of the working method in which the flying ladder is horizontally placed into the equipotential.
本方法的塔上作业人员需要两名, 其中一名为等电位电工, 另一名为塔上地电位电 工。 在进入等电位前, 等电位工人必须穿着全套屏蔽服装, 包括帽、 衣裤、 手套、 袜和 鞋, 并戴好屏蔽面罩。 此外, 屏蔽服装内还应穿阻燃内衣。。 地电位工人必须穿着全套静 电防护服装和导电鞋。  The tower requires two workers on the tower, one of which is an equipotential electrician and the other is a tower-ground potential electrician. Before entering the equipotential, equipotential workers must wear a full set of shielding clothing, including caps, underwear, gloves, socks and shoes, and wear a shielded mask. In addition, flame-retardant underwear should also be worn inside the shielded clothing. . Ground potential workers must wear full static protective clothing and conductive shoes.
等电位工人和地电位工人按照上述着装规范穿戴完毕后, 按照下面的步骤进入等电 位:  After the equipotential workers and the ground potential workers are dressed according to the above dress code, follow the steps below to enter the equipotential level:
( 1 )等电位工人、 地电位工人携带绝缘传递绳登塔至地线支架处, 系好安全带, 将 绝缘滑车和绝缘传递绳在作业地线支架适当位置安装好。  (1) Equipotential workers and ground potential workers carry insulated transmission ropes to the ground support, fasten the seat belts, and install the insulated pulleys and insulated transmission ropes at appropriate positions on the working ground support.
( 2 )地面工人传递绝缘软梯、 绝缘软梯挂头(安装好软梯控制绳)至地电位工人位 置。  (2) The ground workers pass the insulation ladder and the insulated ladder head (installed the ladder control rope) to the ground potential worker position.
( 3 )地电位工人拆除工作侧架空地线的防振锤 (若地线为绝缘架空地线, 工作前需 在不工作侧将绝缘架空地线可靠接地),然后将软梯挂头可靠安装在架空地线上,并装好 软梯挂头控制绳。  (3) The ground potential worker removes the anti-vibration hammer of the working side overhead ground wire (if the ground wire is insulated overhead ground wire, the insulated ground wire should be reliably grounded on the non-working side before work), and then the ladder hanger head is reliably installed. On the overhead ground line, install the ladder hanging head control rope.
( 4 )等电位工人检查屏蔽服各部分连接良好后, 系好绝缘保护绳, 登上绝缘软梯站 好并将安全带系于绝缘软梯上。 若为耐张杆塔, 地电位工人利用软梯挂头控制绳将绝缘 软梯沿架空地线移至耐张线夹平行处。 若为直线杆塔, 地电位工人利用软梯挂头控制绳 将绝缘软梯沿架空地线外移约 5m,等电位工人沿绝缘软梯下行,至肩部与上子导线平齐 时停止。 (4) After equipotential workers check that the parts of the shielding suit are well connected, fasten the insulation protection rope, board the insulation ladder and attach the safety belt to the insulation ladder. If it is a tensile tower, the ground potential worker will use the ladder to control the rope to insulate. Move the ladder along the overhead ground wire to the parallel of the tension clamp. In the case of a linear tower, the ground potential worker uses the ladder head control rope to move the insulation ladder along the overhead ground line by about 5 m, and the equipotential worker descends along the insulation ladder until the shoulder is flush with the upper sub-wire.
( 5 )地面工人利用绝缘软梯尾绳摆动绝缘软梯, 等电位工人距带电导线约 0.5m处 时快速伸手握住导线进行电位转移。  (5) The ground workers use the insulated ladder tail rope to swing the insulation ladder. When the equipotential workers are about 0.5m away from the live conductor, they quickly reach and hold the conductor for potential transfer.
( 6 )等电位工人进入电位后系好安全带, 并根据作业需要是否解除绝缘保护绳。 进入等电位后, 即可进行 ± 500kV同塔双回直流输电线路的带电检修工作。 例如, 带电更换导线防振锤、 带电更换耐张导线侧金具、 带电更换调整导线间隔棒以及带电更 换绝缘子等。 下文中将对其中部分部件的检修工艺进行详细地说明。  (6) When the equipotential worker enters the potential, fasten the seat belt and release the insulation protection rope according to the operation. After entering the equipotential, the live maintenance of the ±500kV double-circuit DC transmission line on the same tower can be carried out. For example, live replacement wire anti-vibration hammer, live replacement of tension-resistant wire side fittings, live replacement adjustment wire spacers, and live replacement insulators. The inspection process for some of the components will be described in detail below.
在带电检修工作完成后, 等电位工人可按照如下方法退出等电位:  After the live maintenance work is completed, the equipotential worker can exit the equipotential as follows:
( 1 )等电位工人检查检查屏蔽服各部分连接良好后,登上绝缘软梯站好并将安全带 系于绝缘软梯上(一手握绝缘软梯, 一手臂伸直握住导线)。  (1) Equipotential workers check that all parts of the shielding suit are well connected, board the insulation ladder and attach the seat belt to the insulating ladder (hold the insulated ladder in one hand and hold the wire in one arm).
( 2 )报经工作负责人同意后, 等电位工人松开导线并将手臂迅速收回, 地面工人利 用绝缘软梯尾绳摆动绝缘软梯, 等电位工人退出等电位。  (2) After the approval of the person in charge of the work, the equipotential worker loosens the wire and quickly withdraws the arm. The ground worker uses the insulated ladder tail rope to swing the insulation ladder, and the equipotential worker exits the equipotential.
( 3 )地电位工人在地线支架处利用绝缘软梯控制绳将绝缘软梯沿架空地线移至横担 处。 等电位工人解开系于绝缘软梯上的安全带, 向上攀爬登上横担, 系好安全带。  (3) The ground potential worker uses the insulated ladder control rope to move the insulation ladder along the overhead ground line to the crossarm at the ground support. Equipotential workers unfasten the seat belt attached to the insulated ladder, climb up the crossbar, and fasten the seat belt.
( 4 )地电位工人与地面电工配合拆除全部工具, 并恢复地线防振锤的安装(如有则 最后拆除接地线)。  (4) The ground potential worker cooperates with the ground electrician to remove all the tools and restore the installation of the ground anti-vibration hammer (if any, the grounding wire is finally removed).
( 5 )等电位工人、 地电位工人检查塔上无遗留物后, 携带绝缘传递绳下塔。  (5) After the equipotential workers and the ground potential workers inspect the unretained objects on the tower, they carry the insulated transmission ropes to the lower tower.
根据上述进入和退出电位的方法, 即可对士 500kV同塔双回直流输电线路上的部件 进行检修。 由于士 500kV同塔双回直流输电线路中的作业项目多, 部分部件的检修方式 与之前的作业方法相同, 因此在此不做赞述。 下面将对带电更换绝缘子等带电检修工艺 的重点操作方法进行详细地说明。  According to the above method of entering and exiting the potential, the components on the 500kV double-circuit DC transmission line on the same tower can be inspected. Since there are many work items in the 500kV double-circuit DC transmission line on the same tower, the repair methods of some components are the same as the previous operation methods, so I will not comment here. In the following, the key operation methods of the electrified maintenance process such as the live replacement insulator will be described in detail.
首先, 对 "杠杆原理微提线法" 更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子串 的作业方法进行说明。  First, the operation method of replacing the linear double "V" insulator string and the hard-turn double "L" insulator string with "Leverage principle micro-lifting method" will be described.
± 500kV 葛南线 (林枫线) 同塔双回线路工程设计, 线路全部直线塔釆用双 "V" 绝缘子串和硬转塔釆用双 "L" 绝缘子串的组装方式。 当绝缘子串零部件出现缺陷时, 一般釆用 "正提线"方式转移绝缘子串的机械荷载,检修和更换绝缘子串。请参阅图 2, 所谓的 "正提线" 方式主要是指, 用导线联板正上方处预留施工孔(或主材)做工具的 塔上支点, 安装杆塔横担专用卡具(或连接工具), 通过连接提线装置(机械丝杆或液压 丝杆)、 高强度绝缘拉杆、 四分裂提线器相连与导线相连, 组成绝缘子串的机械荷载转移 系统。 通过操作机械丝杆或液压丝杆使荷载转移系统收紧受力, 緩慢将导线提起, 使被 检修绝缘子串机械荷载转移到提线系统, 实现绝缘子串的检修。 然而, 这种 "正提线" 的作业方式的提线工器具的机械荷载大,可能会造成检修侧绝缘子串水平方向受力变小, 从而使导线向相反方向偏移, 当且在检修有缺陷的绝缘子串时, 绝缘子串复位时还要釆 用防止导线横向位移措施 , 以免检修绝缘子串复位困难。 ± 500kV Genan Line (Linfeng Line) The design of the double-circuit line of the same tower, the line of all the linear towers with double "V" insulator strings and hard turrets with double "L" insulator strings. When there is a defect in the insulator string component, the mechanical load of the insulator string is generally transferred by "positive wire lifting", and the insulator string is repaired and replaced. Please refer to Figure 2, The so-called "positive lifting" method mainly refers to the use of a construction hole (or main material) directly above the wire joint plate as a fulcrum on the tower, and a special jig (or connecting tool) for the cross-arm of the tower is connected. A wire lifting device (mechanical screw or hydraulic screw), a high-strength insulated tie rod, and a four-split wire feeder are connected to the wire to form a mechanical load transfer system of the insulator string. The load transfer system is tightened by operating the mechanical screw or the hydraulic screw, and the wire is slowly lifted, so that the mechanical load of the repaired insulator string is transferred to the wire-raising system to realize the maintenance of the insulator string. However, the mechanical load of the wire-lifting tool of the "positive wire-drawing" operation mode may cause the horizontal direction of the insulator-side insulator string to be weakened, thereby causing the wire to be offset in the opposite direction. In the case of a defective insulator string, it is necessary to use a measure to prevent the lateral displacement of the conductor when the insulator string is reset, so as to avoid difficulty in repairing the insulator string.
因此, 根据 ± 500kV同塔双回直流输电线路设计的结构特点, 在本项目中更换直线 双 "V" 绝缘子串、 硬转双 "L" 绝缘子串作业釆用大刀卡并利用 "杠杆原理微提线作业 法" 转移绝缘子串的机械荷载。 大刀卡的结构如图 3A、 3B 中所示。 请结合参阅图 4, 大刀卡的一端为与倒三角二联板的穿心螺杆相匹配的挂钩, 另一端为用于外接丝杆的开 口。 连接挂钩和开口的腰部上设有与倒三角二联板的底侧面相接触的平台。 大刀卡的挂 钩端开有将其套装在倒三角二联板两侧的卡口, 卡口的根部平台与倒三角二联板底侧面 相接触。 大刀卡的开口两侧设有安装滚花螺钉的通孔, 该通孔用于外接丝杆。 大刀卡的 腰部还设有凹槽。如果需要在相对于三角二联板上某一侧面上的金具进行预维护和检修, 则首先将大刀卡的卡口卡装在倒三角二联板该侧面底部的同时, 挂钩勾住处于倒三角二 联板中心的穿心螺杆, 卡口的根部平台托起倒三角二联板的预维护和检修的一端, 这样 倒三角二联板上侧面的另一端即为支点, 开口端即为杠杆末端。 然后再在开口端外接丝 杆, 通过人工调节丝杆来对开口端施加力, 这样杠杆末端即开口处只需施加较小的力量 便可将三角二联板的预维护和检修的一端上的较重载荷卸掉。  Therefore, according to the structural characteristics of the ± 500kV double-circuit DC transmission line design of the same tower, in this project, the linear double "V" insulator string and the hard-turn double "L" insulator string are replaced with a large knife card and the "lever principle" is used. Linework method "Transfers the mechanical load of the insulator string. The structure of the large knife card is shown in Figures 3A and 3B. Referring to Figure 4, one end of the large knife card is a hook that matches the threaded screw of the inverted triangle, and the other end is the opening for the external screw. A platform is provided on the waist connecting the hook and the opening to contact the bottom side of the inverted triangular joint plate. The hook end of the large knife card has a bayonet that is set on both sides of the inverted triangle two-plate, and the root platform of the bayonet is in contact with the bottom side of the inverted triangle two-plate. A through hole for mounting a knurled screw is provided on both sides of the opening of the large knife card, and the through hole is used for the external screw. The large knife card also has a groove at the waist. If it is necessary to carry out pre-maintenance and overhaul of the metal fitting on one side of the triangular joint board, firstly, the bayonet card of the large knife card is clamped on the bottom of the side of the inverted triangle two-piece board, and the hook is hooked in the inverted triangle. The threaded screw of the center of the two-plate center, the root platform of the bayonet supports the end of the pre-maintenance and overhaul of the inverted triangle two-piece board, so that the other end of the side of the inverted triangle-connected board is the fulcrum, and the open end is the end of the lever . Then, the screw rod is externally connected to the open end, and the force is applied to the open end by manually adjusting the screw rod, so that the end of the lever, that is, the opening, only needs to exert a small force to be used on the pre-maintenance and overhaul end of the triangular joint plate. The heavy load is removed.
釆用大刀卡并利用 "杠杆原理微提线作业法" 更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子串的作业方法的具体操作如下:  具体 Use the big knife card and use the "lever principle micro-lifting line operation method" to replace the linear double "V" insulator string, hard turn double "L" insulator string operation method as follows:
( 1 )利用绝缘子串挂点处预留施工孔(或挂点处主材)做工具的塔上支点, 安装杆 塔横担卡具, 利用导线侧二联板做工具的导线侧支点安装大刀卡;  (1) Use the insulator hole to reserve the construction hole (or the main material at the hanging point) as the fulcrum on the tower of the tool, install the cross-clamp of the pole tower, and use the wire side two-plate to make the wire side fulcrum of the tool to install the large knife. Card
( 2 )通过提线装置 (机械丝杆或液压丝)、 高强度绝缘拉杆与塔上横担卡具相连, 组成绝缘子串的机械荷载转移系统;  (2) The mechanical load transfer system that constitutes the insulator string is connected by a wire lifting device (mechanical screw or hydraulic wire) and a high-strength insulating tie rod to the cross-arm clamp on the tower;
( 3 )利用大刀卡的卡背与二联板接触处作为支点,并将大刀卡分成作用臂和操作臂, 操作提线装置进行小距离的提线变位, 驱动大刀卡操作臂转动, 带动作用臂转移绝缘子 串上荷载, 使被检修绝缘子串机械荷载转移到提线系统, 实现绝缘子串的检修。 (3) using the contact of the card back and the second board of the large knife card as a fulcrum, and dividing the large knife card into the working arm and the operating arm, The wire lifting device is operated to perform a small-distance wire-lifting displacement, and the large-cutter card operating arm is driven to rotate, and the belt-operating arm transfers the load on the insulator string, so that the mechanical load of the insulative insulator string is transferred to the wire-drawing system to realize the maintenance of the insulator string.
在上述工艺中,双 "V"绝缘子串、硬转双 "L"绝缘子串大刀卡的工作负荷为 50KN。 上述工艺由于利用了杠杆原理, 操作提线装置进行小距离的提线变位, 即可驱动大刀卡 操作臂转动, 带动作用臂转移绝缘子串上荷载, 可方便、 快捷地更换双 "V"绝缘子串、 硬转双 "L" 绝缘子串。  In the above process, the working load of the double "V" insulator string and the hard-turn double "L" insulator string card is 50KN. The above process utilizes the principle of leverage, and the operation of the wire lifting device for the displacement of the wire at a small distance can drive the rotation of the large knife operation arm, and the action arm can transfer the load on the insulator string, and the double "V" insulator can be replaced conveniently and quickly. String, hard turn double "L" insulator string.
最后, 将对更换耐张绝缘子的作业方法进行详细的说明。  Finally, the method of replacing the tensile insulator will be described in detail.
更换耐张绝缘子、 绝缘子串是输电线路检修和带电作业的常规项目, 也是输电线路 运行检修的日常工作。 一般的检修工艺中更换耐张绝缘子、 绝缘子串有传统的釆用托瓶 架更换耐张绝缘子法和改进后的旋放法更换耐张绝缘子法。 托瓶架法是, 在检修绝缘子 串两端安装紧线系统,并在其下方放置托瓶架,收紧紧线系统使绝缘子串免受导线张力, 然后脱开绝缘子串与导线、 横担的链接 , 然后通过绝缘吊绳用托瓶架将检修绝缘子串放 置地面, 之后反作业流程完成检修作业。 旋放法是, 先用绝缘子串张力调整器放松绝缘 子, 然后用牵引系统反牵绝缘子将导线侧瓷瓶脱开, 沿塔悬挂点旋放瓷瓶串至垂直位置 后再放至地面。 反作业流程完成检修作业。  The replacement of tensile insulators and insulator strings is a routine project for maintenance and live working of transmission lines, and is also a daily work for maintenance and repair of transmission lines. In the general maintenance process, the tensile insulators and the insulator strings are replaced by a conventional one. The replacement of the tensile insulator method and the improved spinning method are used to replace the tensile insulator method. The bottle holder method is to install a tight line system at both ends of the repair insulator string, and place a bottle holder under the tightness, tighten the wire system to protect the insulator string from the wire tension, and then disconnect the insulator string and the wire and the cross arm. Link, then use the insulated sling to place the repair insulator string on the ground with the bottle holder, and then complete the maintenance work in the reverse work process. The spinning method is to first loosen the insulator with the insulator string tension adjuster, then use the traction system to pull the insulator to disengage the wire side porcelain bottle, and rotate the porcelain bottle string to the vertical position along the tower suspension point before placing it on the ground. The reverse work process completes the maintenance work.
± 500kV葛南线(林枫线) 同塔双回线路耐张绝缘子串设计为水平玻璃绝缘子或瓷 棒式绝缘子双联串组装方式。 其中玻璃串最小(轻污区) 40片, 长达 10.737米, 单串重 量达 0.73T, 最大(重污区) 57片, 长达 14.222米, 单串重达约 0.97T; 瓷棒式绝缘子 串由 7支组成, 长达 14.772米, 单串重约 0.95T。 虽然整串更换的检修方式, 釆用传统 的耐张绝缘子串更换方法进行施工机具的组织和现场的实际操作在技术上都是可以实现 的,但作为常规检修,特别是釆取带电作业的方式进行检修还是有相当大的难度。因此, 本项目根据 ± 500kV同塔双回直流线路工程双联耐张的设计结构和釆用的绝缘形式, 选 用单支更换的作业方式重点研究设计通过短接零值的被更换瓷棒式绝缘子, 从而达到更 换的目的。 其具体的操作流程如下:  ± 500kV Genan Line (Linfeng Line) The double-circuit line insulator string on the same tower is designed as a horizontal glass insulator or a ceramic rod insulator. Among them, the glass string is the smallest (light pollution area) 40 pieces, the length is 10.737 meters, the single string weight is 0.73T, the largest (heavy pollution area) 57 pieces, the length is 14.222 meters, the single string weight is about 0.97T; the porcelain rod insulator The string consists of 7 pieces, which is 14.772 meters long and weighs about 0.95T in a single string. Although the whole series of replacement repair methods, the construction of the construction equipment and the actual operation of the field using the traditional tensile insulator string replacement method are technically achievable, but as a routine maintenance, especially the way of taking live work It is still quite difficult to carry out maintenance. Therefore, the project is based on the double-strength design of the ±500kV double-circuit DC line project and the insulation form used in the same project. The single-replacement operation mode is selected to focus on the design of the replaced ceramic rod insulator with short-zero value. In order to achieve the purpose of replacement. The specific operation process is as follows:
( 1 )进入电位后,两位等电位工人釆用 "背靠背"方式站位在相邻的棒式绝缘子上, 利用牵引板(QY-42S型)和平行挂板(P-42S )做支点安装横担侧耐张卡(如图 6中所 示), 利用瓷棒式绝缘子钢帽做支点安装闭式卡后卡(如图 5中所示), 用液压丝杆组件 连接耐张专用卡和闭式卡组成紧线系统, 然后安装三角架组件用于传送工具及绝缘子; ( 2 )利用前后棒式绝缘子钢帽做支点分别安装闭式卡的前卡和后卡(如图 5中所示), 用液压丝杆组件连接闭式卡的前卡和后卡组成紧线系统, 然后安装三角架组件用于传送 工具及绝缘子; (1) After entering the potential, the two equipotential workers stand in the "back to back" mode on the adjacent rod insulators, using the traction plate (QY-42S type) and the parallel hanging plate (P-42S) as the fulcrum installation. The cross-arm side is resistant to the card (as shown in Figure 6), using a porcelain rod insulator steel cap as a fulcrum to install a closed card rear card (as shown in Figure 5), using a hydraulic screw assembly to connect the tensile card and The closed card forms a tight line system, and then the tripod assembly is mounted for the transfer of tools and insulators; (2) Using the front and rear rod insulator steel caps as the fulcrum to install the front and rear cards of the closed card respectively (as shown in Figure 5), and connect the front and rear cards of the closed card with the hydraulic screw assembly to form a tight line. System, then install a tripod assembly for transporting tools and insulators;
( 3 )利用绝缘子钢帽做支点安装闭式卡前卡, 利用联板 ( LS-84600500S 型)做支 点安装导线侧专用翼型卡(如图 7中所示),用液压丝杆组件连接闭式卡和导线侧专用翼 型卡构成紧线系统, 然后安装三角架组件用于传送工具及绝缘子;  (3) Install the closed card front card with the insulator steel cap as the fulcrum, and use the joint plate (LS-84600500S type) as the fulcrum to install the wire-side special airfoil card (as shown in Figure 7), and connect it with the hydraulic screw assembly. The card and the wire-side special airfoil card form a tight wire system, and then the tripod assembly is installed for conveying the tool and the insulator;
( 4 )操作液压丝杆收紧紧线系统, 转移被检修瓷棒式绝缘子上的机械荷载, 实现绝 缘子的更换和检修。  (4) Operate the hydraulic screw to tighten the tight line system, transfer the mechanical load on the inspected porcelain rod insulator, and replace and repair the insulator.
普通绝缘子的单片更换过程: 利用横担侧联板做支点, 安装横担侧耐张专用卡, 利 用绝缘子钢帽做支点, 安装绝缘子闭式卡前卡, 用液压丝杆连接耐张专用卡和闭式卡组 成紧线系统; 利用绝缘子钢帽做支点, 分别安装绝缘子闭式卡的前卡和后卡, 用液压丝 杆连接绝缘子闭式卡的前卡和后卡组成紧线系统; 利用绝缘子钢帽做支点, 安装绝缘子 闭式卡后卡, 利用导线侧联板^ t支点, 安装导线侧转用翼型卡, 用液压丝杆连接闭式卡 和导线侧转用翼型卡组成紧线系统, 操作液压丝杆收紧紧线系统, 转移被检修绝缘子上 的机械荷载, 实现绝缘子的更换和检修。 通过上述工艺, 可实现对耐张绝缘子串的单片 更换, 保证了耐张绝缘子串作为常规检修的作业便捷度。  Single-piece replacement process for ordinary insulators: Use the cross-arm side plate as the fulcrum, install the cross-arm side-resistant special card, use the insulator steel cap as the fulcrum, install the insulator closed card front card, and connect the tensile-resistant special card with the hydraulic screw. And the closed card form a tight line system; using the insulator steel cap as the fulcrum, respectively installing the front card and the rear card of the insulator closed card, and connecting the front card and the rear card of the insulator closed card with the hydraulic screw to form a tight line system; Insulator steel cap as the fulcrum, install the insulator closed card rear card, use the wire side joint plate ^ t fulcrum, install the wire side turn airfoil card, use the hydraulic screw to connect the closed card and the wire side turn with the airfoil card The wire system, operating the hydraulic screw to tighten the tight line system, transferring the mechanical load on the repaired insulator to achieve the replacement and maintenance of the insulator. Through the above process, the single-piece replacement of the tensile insulator string can be realized, and the workability of the tensile insulator string as a routine maintenance is ensured.
综上所述, 本发明的 ± 500kV同塔双回直流输电线路带电检修工艺, 是国内外第一 个士 500kV同塔双回带电作业应用技术研究项目, 项目研究工作的完成及研究成果的应 用, 填补了国内外 ± 500kV同塔双回直流输电线路带电作业、 带电检修应用技术领域的 空白。 本发明的 ± 500kV同塔双回直流输电线路带电检修工艺中的具体的作业方法涵盖 了 ± 500kV同塔双回直流输电线路检修、 带电作业常规检修工作内容, 其中的瓷棒式绝 缘子更换工具、 大吨位组合液压丝杆的单支短接法更换的作业方法应用到带电作业, 特 别是应用到 ± 500kV同塔双回线路作业方法中, 是带电作业应用技术领域的重大突破 以上所述实施例仅表达了本发明的几种实施方式, 其描述较为具体和详细, 但并不能因 此而理解为对本发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说, 在不脱离本发明构思的前提下, 还可以做出若千变形和改进, 这些都属于本发明的保护 范围。 因此, 本发明专利的保护范围应以所附权利要求为准。  In summary, the charging and repairing process of the ±500kV double-circuit DC transmission line of the same tower of the present invention is the first research project of the first 500kV double-circuit live working application on the same tower at home and abroad, the completion of the project research work and the application of the research results. It fills the gaps in the field of live working and live maintenance application of ± 500kV double-circuit DC transmission lines on the same tower at home and abroad. The specific operation method in the charging and repairing process of the ±500kV double-circuit DC transmission line of the same tower of the present invention covers the inspection and repair of the ±500kV double-circuit DC transmission line on the same tower, and the routine maintenance work of the live working, wherein the porcelain rod insulator replacement tool, The single-short-circuit replacement method for large-tonnage combined hydraulic screw is applied to live working, especially to the ±500kV double-circuit line operation method in the same tower. It is a major breakthrough in the field of live working application technology. The invention has been described with reference to a few specific embodiments of the invention, which are not to be construed as limiting the scope of the invention. It should be noted that those skilled in the art can make various modifications and improvements without departing from the inventive concept, and these are all within the scope of the present invention. Therefore, the scope of the invention should be determined by the appended claims.

Claims

权利要求 书 claims
1、一种 ± 500kV同塔双回直流输电线路带电检修工艺, 所述带电检修工艺包括进入 等电位的作业方法, 所述进入等电位的作业方法包括以下步骤: 1. A live maintenance process for a ±500kV double-circuit DC transmission line on the same tower. The live maintenance process includes an operation method of entering equal potential. The operation method of entering equal potential includes the following steps:
等电位工人和地电位工人按照着装规范穿戴完毕后, 携带绝缘传递绳登塔至地线支 架处系好安全带, 将绝缘滑车和绝缘传递绳安装在作业地线支架适当位置上; After the equipotential workers and ground potential workers have finished dressing in accordance with the dress code, they carry the insulating transfer rope up the tower to the ground wire support and fasten their safety belts, and install the insulating pulley and the insulating transfer rope at the appropriate position of the working ground wire support;
地面工人传递绝缘软梯、 安装好软梯控制绳的绝缘软梯挂头至地电位工人位置; 地电位工人拆除工作侧架空地线的防振锤,然后将软梯挂头可靠安装在架空地线上, 并装好软梯挂头控制绳; The workers on the ground transfer the insulated ladder and the insulated ladder hanging head with the ladder control rope installed to the ground potential worker's position; the ground potential worker removes the anti-vibration hammer of the overhead ground wire on the working side, and then reliably installs the ladder hanging head on the overhead ground wire, and Install the ladder hanging head control rope;
等电位工人检查屏蔽服各部分连接良好后, 系好绝缘保护绳, 登上绝缘软梯站好并 将安全带系于绝缘软梯上, 若为耐张杆塔则地电位工人利用软梯挂头控制绳将绝缘软梯 沿架空地线移至耐张线夹平行处, 若为直线杆塔则地电位工人利用软梯挂头控制绳将绝 缘软梯沿架空地线外移约 5m,等电位工人沿绝缘软梯下行,至肩部与上子导线平齐时停 止; After the equipotential workers check that all parts of the shielding suit are well connected, they fasten the insulating protective rope, climb onto the insulating ladder and stand up, and tie the safety belt to the insulating ladder. If it is a tension pole tower, the ground potential worker uses the ladder hanging head to control the rope. Move the insulated ladder along the overhead ground wire to the parallel point of the tension clamp. If it is a straight pole tower, the ground potential worker will use the ladder hanging head control rope to move the insulated ladder outward about 5m along the overhead ground wire. The equipotential worker will go down the insulated ladder to Stop when the shoulder is flush with the upper sub-wire;
地面工人利用绝缘软梯尾绳摆动绝缘软梯,等电位工人距带电导线约 0.5m处时快速 伸手握住导线进行电位转移。 Ground workers use the tail rope of the insulated ladder to swing the insulated ladder. When the equipotential worker is about 0.5m away from the live wire, he quickly reaches out to hold the wire to perform potential transfer.
2、根据权利要求 1所述的 ± 500kV同塔双回直流输电线路带电检修工艺,其特征在 于: 在所述进入等电位的作业方法中, 等电位工人进入电位后系好安全带, 并根据作业 需要确定是否解除绝缘保护绳, 等电位工人检查检查屏蔽服各部分连接良好后, 登上绝 缘软梯站好并将安全带系于绝缘软梯上。 2. The live maintenance process of ±500kV double-circuit DC transmission lines on the same tower according to claim 1, characterized in that: in the operation method of entering the equipotential, the equipotential workers fasten their safety belts after entering the potential, and according to The operation needs to determine whether to remove the insulating protective rope. After the potential equalization worker checks that all parts of the shielding suit are well connected, he should stand on the insulating ladder and tie the safety belt to the insulating ladder.
3、根据权利要求 1所述的 ± 500kV同塔双回直流输电线路带电检修工艺,其特征在 于: 所述着装规范包括, 等电位工人穿着全套犀蔽服装以及犀蔽服装内穿阻燃内衣, 所 述犀蔽服装包括犀蔽帽、 屏蔽衣裤、 屏蔽手套、 屏蔽袜、 屏蔽鞋以及犀蔽面罩, 地电位 工人必须穿着全套静电防护服装和导电鞋。 3. The live maintenance process of ±500kV double-circuit DC transmission lines on the same tower according to claim 1, characterized in that: the dress code includes: equipotential workers wear a full set of protective clothing and wear flame-retardant underwear under the protective clothing, The shielding clothing includes a shielding hat, shielding clothes and pants, shielding gloves, shielding socks, shielding shoes and a shielding mask. Ground potential workers must wear a full set of electrostatic protective clothing and conductive shoes.
4、根据权利要求 1所述的 ± 500kV同塔双回直流输电线路带电检修工艺,其特征在 于在带电检修工作完成后, 按照以下步骤退出等电位: 4. The ±500kV same-tower double-circuit DC transmission line live maintenance process according to claim 1, characterized by: After the live maintenance work is completed, follow the following steps to exit equipotential:
等电位工人检查检查屏蔽服各部分连接良好后, 登上绝缘软梯站好并将安全带系于 绝缘软梯上; After the potential equalization worker checks that all parts of the shielding suit are well connected, he climbs onto the insulating ladder and stands up, and fastens the safety belt to the insulating ladder;
等电位工人松开导线并将手臂迅速收回,地面工人利用绝缘软梯尾绳摆动绝缘软梯, 等电位工人退出等电位; The equipotential worker loosens the wire and retracts his arm quickly. The ground worker uses the tail rope of the insulated ladder to swing the insulated ladder, and the equipotential worker exits the equipotential level;
地电位工人在地线支架处利用绝缘软梯控制绳将绝缘软梯沿架空地线移至横担处, 等电位工人解开系于绝缘软梯上的安全带, 向上攀爬登上横担, 系好安全带; The ground potential worker uses the insulated ladder control rope at the ground wire support to move the insulated ladder along the overhead ground wire to the cross arm. The equipotential worker unties the safety belt fastened to the insulated ladder, climbs up and onto the cross arm, and fastens it. safety belt;
地电位工人与地面工人配合拆除全部工具, 并恢复地线防振锤的安装; Ground potential workers cooperate with ground workers to remove all tools and restore the installation of ground wire anti-vibration hammers;
等电位工人、 地电位工人检查塔上无遗留物后, 携带绝缘传递绳下塔。 After checking that there is nothing left on the tower, the equipotential workers and ground potential workers carry the insulating transfer rope down the tower.
5、根据权利要求 1至 5中任一项所述的士 500kV同塔双回直流输电线路带电检修工 艺, 其特征在于, 所述带电检修工艺包括更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘 子串的作业方法, 所述更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子串的作业方法包 括以下步骤: 5. The live maintenance process of the taxi 500kV double-circuit DC transmission line on the same tower according to any one of claims 1 to 5, characterized in that the live maintenance process includes replacing the linear double "V" insulator string, hard-rotating the double The operation method of "L" insulator string, the operation method of replacing the straight double "V" insulator string and the hard-rotating double "L" insulator string includes the following steps:
利用绝缘子串挂点处预留施工孔或挂点处主材做工具的塔上支点, 安装杆塔横担专 用卡具, 利用导线侧二联板^ t工具的导线侧支点安装大刀卡; Use the construction holes reserved at the insulator string hanging points or the main material at the hanging points to serve as the fulcrum on the tower for tools, install special clamps for the pole tower cross arms, and use the conductor side fulcrum of the conductor side double plate to install the large knife clamp;
通过提线装置、 高强度绝缘拉杆与塔上专用卡具相连, 组成绝缘子串的机械荷载转 移系统; The mechanical load transfer system of the insulator string is formed by connecting the wire lifting device and high-strength insulating tie rods to the special clamps on the tower;
利用大刀卡的卡背与二联板接触处作为支点, 并将大刀卡分成作用臂和操作臂, 操 作提线装置进行小距离的提线变位, 驱动大刀卡操作臂转动, 带动作用臂转移绝缘子串 上荷载, 使被检修绝缘子串机械荷载转移到提线系统, 实现绝缘子串的检修和更换。 Use the contact point between the card back of the large knife card and the two-joint plate as the fulcrum, and divide the large knife card into an action arm and an operating arm. Operate the thread lifting device to perform a small distance lifting displacement, drive the operating arm of the large knife card to rotate, and drive the action arm to transfer. The load on the insulator string transfers the mechanical load of the insulator string to be repaired to the wire lifting system to realize the maintenance and replacement of the insulator string.
6、根据权利要求 6所述的 ± 500kV同塔双回直流输电线路带电检修工艺,其特征在 于: 在所述更换直线双 "V" 绝缘子串、 硬转双 "L" 绝缘子串的作业方法中, 所述提线 装置包括机械丝杆和液压丝杆。 6. The live maintenance process of ±500kV double-circuit DC transmission lines on the same tower according to claim 6, characterized in that: in the operation method of replacing linear double "V" insulator strings and hard-rotating double "L" insulator strings , the thread lifting device includes a mechanical screw rod and a hydraulic screw rod.
7、根据权利要求 1至 5中任一项所述的 ± 500kV同塔双回直流输电线路带电检修工 艺, 其特征在于, 所述带电检修工艺包括更换耐张瓷棒式绝缘子的作业方法, 所述更换 耐张瓷棒式绝缘子的作业方法包括以下步骤: 7. The live maintenance process of the ±500kV double-circuit DC transmission line on the same tower according to any one of claims 1 to 5, characterized in that the live maintenance process includes the operation method of replacing the tension-resistant porcelain rod insulator, so replacement The operation method of tension-resistant porcelain rod insulators includes the following steps:
进入电位后, 两位等电位工人釆用背靠背的方式站位在相邻的瓷棒式绝缘子上, 利 用牵引板和平行挂板做支点安装横担侧耐张专用卡, 利用瓷棒式绝缘子钢帽做支点安装 闭式卡后卡, 用液压丝杆组件连接耐张专用卡和闭式卡组成紧线系统, 然后安装三角架 组件用于传送工具及绝缘子; After entering the potential, two equipotential workers stood back-to-back on the adjacent porcelain rod insulators. They used the traction plate and the parallel hanging plate as fulcrums to install the special tensile card on the side of the cross arm, and used the porcelain rod insulator steel. The cap is used as a fulcrum to install the closed card and the rear card, and a hydraulic screw assembly is used to connect the tension-resistant special card and the closed card to form a tight line system, and then a tripod assembly is installed for conveying tools and insulators;
利用前后棒式绝缘子钢帽做支点分别安装闭式卡的前卡和后卡, 用液压丝杆组件连 接闭式卡的前卡和后卡组成紧线系统, 然后安装三角架组件用于传送工具及绝缘子; 利用绝缘子钢帽做支点安装闭式卡前卡, 利用联板做支点安装导线侧翼型卡, 用液 压丝杆组件连接闭式卡和导线侧翼型卡组成紧线系统, 然后安装三角架组件用于传送工 具及绝缘子; Use the front and rear rod insulator steel caps as fulcrums to install the front and rear clamps of the closed card respectively. Use the hydraulic screw assembly to connect the front and rear clamps of the closed card to form a tight line system. Then install the tripod assembly for conveying tools. and insulators; use the insulator steel cap as a fulcrum to install the closed card front card, use the connecting plate as a fulcrum to install the conductor side wing card, use a hydraulic screw assembly to connect the closed card and conductor side wing card to form a tight line system, and then install the tripod Components are used for conveying tools and insulators;
操作液压丝杆收紧紧线系统, 转移被检修瓷棒式绝缘子上的机械荷载, 实现绝缘子 的更换和检修。 Operate the hydraulic screw rod to tighten the cable system, transfer the mechanical load on the porcelain rod insulator to be repaired, and realize the replacement and maintenance of the insulator.
PCT/CN2014/083325 2013-11-27 2014-07-30 Live overhaul process for ± 500 kv double-loop dc power transmission line on same tower WO2015078195A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201310616162.3 2013-11-27
CN201310616162.3A CN103618249B (en) 2013-11-27 2013-11-27 ± 500kV common-tower double-return DC power transmission line hotline maintenance techniques

Publications (1)

Publication Number Publication Date
WO2015078195A1 true WO2015078195A1 (en) 2015-06-04

Family

ID=50168952

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2014/083325 WO2015078195A1 (en) 2013-11-27 2014-07-30 Live overhaul process for ± 500 kv double-loop dc power transmission line on same tower

Country Status (2)

Country Link
CN (1) CN103618249B (en)
WO (1) WO2015078195A1 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103618249B (en) * 2013-11-27 2017-03-15 国家电网公司 ± 500kV common-tower double-return DC power transmission line hotline maintenance techniques
CN104201616A (en) * 2014-09-26 2014-12-10 陕西省地方电力(集团)有限公司南郑县供电分公司 Low-voltage power distribution overhead line strain power pole fitting connecting structure and connecting method
CN104638565A (en) * 2015-01-30 2015-05-20 国家电网公司 Method for performing equipotential live line work by putting +/-800kV tangent tower electric transmission line into electric field
CN104600629A (en) * 2015-02-12 2015-05-06 中国南方电网有限责任公司超高压输电公司百色局 Compact-circuit six-bundled conductor linkage plate fixture and application thereof
CN104979776A (en) * 2015-07-10 2015-10-14 中国电力科学研究院 Method for entering equipotential level for tension support of UHV transmission line
CN105591314A (en) * 2015-09-09 2016-05-18 国家电网公司 UHV DC transmission line strain tower electrified processing hardware fitting fall-off field operation process
CN108649481A (en) * 2018-04-25 2018-10-12 中国电力科学研究院有限公司 Transmission line of alternation current livewire work personnel's equipotential safe transfer method
CN109830913A (en) * 2019-02-11 2019-05-31 国家电网有限公司 The combination tool and method of vertical rotary method replacement direct current grounding pole line tension string
CN110165600B (en) * 2019-06-03 2020-09-04 国家电网有限公司 Device and method for entering and exiting electric field of double-loop same-tower power transmission line
CN114877781A (en) * 2022-06-07 2022-08-09 广东骏亚电子科技股份有限公司 Manufacturing method of stepped groove

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101728787A (en) * 2008-10-29 2010-06-09 国网电力科学研究院 Equipotential access method of 500kV same-tower four-circuit transmission line tangent tower live-wire work
CN102842867A (en) * 2012-08-31 2012-12-26 辽宁省电力有限公司鞍山供电公司 Method for electrically disconnecting or connecting disconnector with drainage wire between buses
CN103199474A (en) * 2013-03-15 2013-07-10 辽宁省电力有限公司辽阳供电公司 Method for 500KV large cross-section wire hot-line installation of phase to phase spacers
JP2013188060A (en) * 2012-03-09 2013-09-19 Chugoku Electric Power Co Inc:The Repair method for transmission line
CN103618249A (en) * 2013-11-27 2014-03-05 国家电网公司 technology for electrified overhaul of +-500kV double-circuit direct-current power transmission lines on same tower

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101728787A (en) * 2008-10-29 2010-06-09 国网电力科学研究院 Equipotential access method of 500kV same-tower four-circuit transmission line tangent tower live-wire work
JP2013188060A (en) * 2012-03-09 2013-09-19 Chugoku Electric Power Co Inc:The Repair method for transmission line
CN102842867A (en) * 2012-08-31 2012-12-26 辽宁省电力有限公司鞍山供电公司 Method for electrically disconnecting or connecting disconnector with drainage wire between buses
CN103199474A (en) * 2013-03-15 2013-07-10 辽宁省电力有限公司辽阳供电公司 Method for 500KV large cross-section wire hot-line installation of phase to phase spacers
CN103618249A (en) * 2013-11-27 2014-03-05 国家电网公司 technology for electrified overhaul of +-500kV double-circuit direct-current power transmission lines on same tower

Also Published As

Publication number Publication date
CN103618249A (en) 2014-03-05
CN103618249B (en) 2017-03-15

Similar Documents

Publication Publication Date Title
WO2015078195A1 (en) Live overhaul process for ± 500 kv double-loop dc power transmission line on same tower
WO2015078279A1 (en) Live overhaul process for ±800 kv ultra-high voltage dc power transmission line
WO2016023141A1 (en) Process for live replacement of tension hard-tube bus-bar jumper insulator of +/- 800kv ultra-high-voltage dc transmission line
WO2012088987A1 (en) Maintenance tool for insulator of direct current transmission line
CN101640391B (en) Live-wire operation method for replacing insulator for 35kV distribution circuit
CN103618252A (en) Operation method for replacing tension insulator for 35kV overhead line in electrified mode
CN102185265B (en) Construction method for replacing cross arm of 35kV line linear rod
CN105932601B (en) Disconnected strand of overhead grounding wire method for repairing and mending
CN106450835A (en) Shoe manufacturer high voltage wire landing device
CN104242153B (en) Change UHVDC Transmission Lines anchor support monolithic 550kN glass insulator construction technologies
CN106025888A (en) 10-220kV multifunctional insulating operating rod
CN109256721A (en) A kind of helicopter live-line maintenance operation hanging basket
CN104113007A (en) Operation method for replacing strain insulator of 35kV overhead distribution line in live state
CN207098443U (en) A kind of helicopter live-line maintenance operation hanging basket
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN206712336U (en) Shaft tower cable platform work protective cradle
CN202186862U (en) Push-open device for gap of iron tower
CN105186344B (en) Outdoor switch suspender
CN106848921A (en) A kind of livewire work method of ultra-high-tension power transmission line
CN203423430U (en) Insulator maintenance device
CN102358593A (en) Iron tower gap propping device and preparation method thereof
CN106013927A (en) Double-circuit cable terminal steel pipe rod with double-B-shape cable overhauling platform
CN102290738A (en) Construction method for replacing 35kV line tension pole cross arm
CN205452910U (en) Electrified disappearing of GW7 type plug -in strip lacks specialized tool
CN106992464B (en) A kind of strain insulator drainage overlap joint ladder

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 14865070

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 14865070

Country of ref document: EP

Kind code of ref document: A1