WO2014193020A1 - Incremental launching method for concrete bridge using transport carts and winch - Google Patents

Incremental launching method for concrete bridge using transport carts and winch Download PDF

Info

Publication number
WO2014193020A1
WO2014193020A1 PCT/KR2013/005160 KR2013005160W WO2014193020A1 WO 2014193020 A1 WO2014193020 A1 WO 2014193020A1 KR 2013005160 W KR2013005160 W KR 2013005160W WO 2014193020 A1 WO2014193020 A1 WO 2014193020A1
Authority
WO
WIPO (PCT)
Prior art keywords
bridge
concrete
concrete girder
girder
trolley
Prior art date
Application number
PCT/KR2013/005160
Other languages
French (fr)
Korean (ko)
Inventor
김태희
Original Assignee
Kim Tae Hee
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kim Tae Hee filed Critical Kim Tae Hee
Publication of WO2014193020A1 publication Critical patent/WO2014193020A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • E01D21/065Incremental launching
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Definitions

  • the present invention relates to a concrete bridge traction extrusion method for constructing a concrete girder of a bridge, more specifically, it is possible to shorten the air and reduce costs in the traction extrusion of the concrete girder of the bridge, and to stick to the forward distance of the concrete girder It is about the concrete bridge traction extrusion method using the bogie and the hoist which can be installed without receiving and can prevent the damage of the concrete girder.
  • a bridge is a generic term for structures placed on them when crossing over roads, railways, valleys, lakes, shores, or other roads, railways, waterways, houses, towns, etc.
  • ILM initial launching method
  • the bridge extrusion method has a push type (push type), a lift and push type (pulling-out type) according to the extrusion method, the present invention is a double pulling type (pulling-out type) It is related to.
  • the concrete girder 20 is manufactured one by one at a mold fabrication site installed at the rear of the bridge or the first pier, and then using the tow jack 4 installed at the upper part of the bridge.
  • a construction method to construct a bridge while pushing a little bit (Fig. 1), it is widely used due to the advantages of excellent concrete quality control, economical and can be constructed regardless of the bridge under conditions.
  • the related technology can be found in Patent No. 10-0093125 (traction extruder of the bridge top plate), Patent No. 10-0103702 (bridge upper hole extrusion method using a bogie).
  • the conventional bridge extrusion method is expensive because the equipment for the extrusion of the concrete girder constituting the bridge is very expensive and it is not economical when the total extension of the bridge is about 500m or less, and it cannot be used when the span is more than 50m. There was.
  • the present invention can reduce the construction cost by using a cheap and easy to acquire equipment, in particular, concrete bridge traction extrusion method using a bogie and winch effective for reducing the cost of small and medium-sized bridge To provide.
  • the present invention in the traction extrusion of the concrete girder constituting the bridge, it is possible to omit the forward and backward repetitive work of the hydraulic jack can shorten the air, and can be efficiently constructed regardless of the forward distance of the concrete girder and To provide a concrete bridge traction extrusion method using a winch.
  • the present invention is to provide a concrete bridge traction extrusion method using a bogie and a hoist that can prevent the concrete girder or damage to the concrete girder due to the tensile force by not pulling the concrete girder or the propulsion nose directly in the traction extrusion method of the bridge.
  • the present invention provides a method for installing concrete girders between the piers installed in a line spaced apart from each other, (a) a plurality of pre-installed top plate at the rear of one piers Arranging the balances so that they are connected in line with each other; (b) placing a concrete girder on top of the bogie; (c) advancing the concrete girder to the other pier side by installing and fixing the winch on the upper side of the pier where the concrete girder is reached and installed, and connecting the towing wire of the winch to the fore bogie to pull the bogie forward; And (d) advancing the concrete girder to the other pier bridge position, releasing the traction wire, and placing the concrete girder on one pier bridge and the other pier bridge. It provides a concrete bridge traction extrusion method using a bogie and a hoist.
  • a propulsion nose is installed at the end of the concrete girder forward side, and the propulsion nose is in the step (d) It provides a concrete bridge traction extrusion method using a bogie and a winch, characterized in that the concrete girder is removed after being positioned on the upper side of the bridge piers and the other bridge piers.
  • the one side pier and the other pier is provided with a temporary support installed on the water-lifting pants or installed on the ground above the ground to support the bottom of the concrete girder while advancing the concrete girder It provides a concrete bridge traction extrusion method using a bogie and a hoist.
  • the bridge in the step (d), is provided with a hydraulic jack to move up and down, to move the concrete girder located between one pier and the other pier downwards to the hydraulic jack to be placed on the shoe installed on the bridge It provides a concrete bridge traction extrusion method using a bogie and a hoist.
  • the precast concrete girder is placed on the bogie or by installing a formwork on the bogie's upper surface, the concrete using the bogie and the hoist Provide bridge traction extrusion method.
  • step (c) if the fore trolley reaches one pier, the fore bogie is removed and the concrete girder is advanced by repeating the process of advancing the concrete girder by connecting the towing wire to the next bogie. It provides a concrete bridge traction extrusion method using a bogie and a hoist.
  • the girder is towed by a winch fixed to the other piers in front, it is possible to omit the repetitive forward and backward operations using the hydraulic jack, it is possible to shorten the air, and can be installed regardless of the forward distance of the concrete girder.
  • each concrete girder is switched from the cantilever beam to the support beam at both ends. Therefore, it is possible to economically design with optimized girder section by minimizing the influence of the parent moment acting on the concrete girder.
  • 1 is a view showing an extrusion method of a conventional concrete bridge.
  • FIGS. 2 to 9 are views showing a part of the step-by-step process of the concrete bridge traction extrusion method using the trolley and the hoist of the present invention, respectively.
  • FIG. 2 is a diagram illustrating a step of arranging the carts interconnected to the installed upper plate and placing the concrete girder on the upper part of the cart.
  • FIG 3 is a view illustrating a state in which a propulsion nose is installed at an end of a concrete girder forward side.
  • FIG. 4 is a view illustrating a state in which self-elevating pants and temporary supports are installed between adjacent piers.
  • FIG. 5 is a view showing a step of connecting the towing wire of the hoisting machine to the foremost bogie and towing the bogie to the hoisting machine.
  • FIG. 6 is a view showing a step in which the propulsion nose is positioned above the other pier by pulling the bogie with a winch.
  • FIG. 7 is a view showing the step of advancing the concrete girder to the other pier bridge position.
  • FIG. 8 is a view illustrating a state in which the concrete girder is moved downward by the hydraulic jack.
  • FIG. 9 is a view showing a state in which the installation of the bridge is completed by placing the concrete girder on the shoe upper portion.
  • Concrete bridge traction extrusion method using the bogie and winch of the present invention is a method for installing concrete girders between the piers installed in a line so as to be spaced apart by a predetermined interval, (a) a plurality of bogies on the pre-installed top plate behind the one side piers Arranging to be connected in line with each other; (b) placing a concrete girder on top of the bogie; (c) advancing the concrete girder to the other pier side by installing and fixing the winch on the upper side of the pier where the concrete girder is reached and installed, and connecting the towing wire of the winch to the fore bogie to pull the bogie forward; And (d) advancing the concrete girder to the other pier bridge position, releasing the traction wire, and placing the concrete girder on one pier bridge and the other pier bridge.
  • FIG. 2 is a view showing the step of placing the trolley 40 on the top plate 30 is already installed and positioning the concrete girder 20 on the upper portion of the trolley 40
  • Figure 3 is a concrete girder 20 at the forward end end It is a figure which shows the state which the propulsion nose 60 was installed.
  • Concrete bridge traction extrusion method using the bogie and winch of the present invention relates to a method for installing the concrete girder 20 between the piers 10 installed in a row so as to be spaced apart from each other at regular intervals.
  • Construction of the piers 10 should be completed before the implementation of each step constituting the present invention. Construction of the pier 10 proceeds in consideration of the ground conditions and the impact on the surrounding environment.
  • the present invention comprises the steps of: (a) arranging a plurality of trucks (40) in line with each other in a pre-installed top plate 30 behind one side piers (10a); (b) placing a concrete girder 20 on top of the trolley 40; (c) The winch 50 is installed and fixed on the upper side of the other piers 10b in front of the concrete girder 20 to be installed, and the towing wire 51 of the winch 50 is connected to the fore bogie 40a.
  • the present invention (a) a plurality of trucks (40) arranged on the pre-installed top plate (30) behind one side piers (10a) to be connected to each other in line, (b) the truck 40 proceeds in the order of placing the concrete girder 20 on the top.
  • a plurality of bogies 40 are arranged so as to be connected in a row, the bogies 40 are arranged in parallel so as to have a plurality of rows, and the concrete girders 20 are positioned on the top of each bogie 40. , Installing a plurality of concrete girders 20 may be performed simultaneously or sequentially.
  • Concrete girder 20 in the present invention refers to the concrete girder 20 which is located on the upper surface of the pier 10 to form a bridge.
  • the concrete girder 20 may be constructed as a cast-in-place concrete girder 20 by placing the precast concrete girder 20 on the trolley 40 or by installing a formwork on the upper surface of the trolley 40. have.
  • the concrete girder 20 may be made in advance in the pre-fabrication girder to be placed on the trolley 40 with a heavy lifting.
  • the size of the concrete girder 20 is difficult to transport and lift, it may be installed by placing the formwork on the upper portion of the bogie 40 by site pouring.
  • the concrete girder 20 can be a variety of cross-sectional shape, it may be configured as a concrete box girder, such as square or formulation cross section.
  • the propulsion nose 60 to the forward side end of the concrete girder 20 to reduce the parent moment acting on the concrete girder 20 is extruded in the step (b). Can be installed.
  • the propulsion nose 60 is installed at the forward end of the concrete girder 20, after the concrete girder 20 is advanced a certain amount, the end of the propulsion nose 60 is the other pier 10b or temporary support 80 It is supported on the upper surface to convert the concrete girder 20 from the cantilever beam to both ends of the support beam. Therefore, by minimizing the influence of the parent moment and deflection acting on the concrete girder 20, in the traction process of the concrete girder 20 improves the structural safety and construction stability.
  • the propulsion nose 60 is preferably made of light steel truss skeleton.
  • FIG 4 is a view showing the self-elevating pants 70 and the temporary support 80 is installed between the adjacent piers 10
  • Figure 5 is a forklift wire (50) of the winch 50 in the front trolley (40a)
  • 51 is a view showing the step of connecting the cart 40 to the winch 50
  • Figure 6 is towing the cart 40 to the winch 50
  • the propelled nose (60b) to the top of the other side piers (10b) Is a diagram showing a step in which) is located.
  • the self-elevating pants 70 is installed between the one side piers (10a) and the other piers (10b) in the water,
  • the temporary support 80 is installed on the liftable pants 70 to support the lower portion of the concrete girder 20 while the concrete girder 20 moves forward.
  • the self-elevating pants (SEP pants: 70) is provided with a support at the corner, there is an advantage that the upper construction is not affected by tidal flow or waves because there is little up and down flow.
  • the prop of the self-elevating pants 70 is height adjustable according to the depth.
  • the self-elevating pants 70 is preferably fixed to the portion that becomes the center of the adjacent piers 10.
  • the self-elevating pants 70 and the temporary support 80 are temporary structures that are used while a part of the concrete girder 20 is mounted on the temporary support 80 for a period of time during the towing of the concrete girder 20.
  • the temporary support 80 is installed on the ground above the land.
  • the concrete girder 20 in the extrusion process of the concrete girder 20 is located on the upper surface of the temporary support (80). Therefore, the concrete girder 20 is converted from the cantilever beam to both ends of the support beam in the construction process, it is possible to minimize or not act as a parent to the concrete girder 20. And because the use of self-elevating pants with a low vertical flow, minimizing the generation of additional moments in the concrete girder 20 due to the fluctuation of the water level or the vertical flow due to the wave.
  • the roller is installed on the upper surface of the temporary support 80 for the effective movement of the concrete girder 20.
  • step (c) the concrete girders 20 is fixed to install the winch 50 on the top of the other side piers (10b) to be installed , By connecting the towing wire 51 of the winch 50 to the front trolley 40a and pulling the trolley 40 forward to advance the concrete girder 20 to the side of the other piers 10b.
  • the winch 50 is configured to pull the concrete girder 20, is fixedly installed on the other side piers (10b).
  • the present invention uses the low cost and easy to obtain winch 50 to traction extrusion the concrete girders 20. Therefore, it is efficient in terms of air and construction cost even for small and medium bridges.
  • step (c) when the front trolley 40a reaches one side of the piers 10a, the front trolley 40a is removed and the towing wire 51 is connected to the next trolley 40b to advance the concrete girder 20.
  • the process may be repeated to advance the concrete girder 20.
  • the propulsion nose 60 is gradually dismantled.
  • the winch 50 may be repositioned above the other pier adjacent to the other pier 10b.
  • FIG 7 is a view showing a step of advancing the concrete girder 20 to the position of the other pier bridge (11b)
  • Figure 8 is a view showing a state of moving the concrete girder 20 downward with the hydraulic jack 90
  • 9 is a view showing the concrete girder 20 is placed on the shoe 12, the installation of the bridge is completed.
  • step (d) advances the concrete girder 20 to the other pier bridge (11b) position, and then release the towing wire 51, concrete girder 20 one side pier bridge It is settled on the upper part of 11a and the other bridge bridge 11b.
  • the bridge 11 is provided with a hydraulic jack 90 that can be moved up and down, as shown in Figure 8 concrete girder located between one pier 10a and the other pier 10b 20 can be moved downward to the hydraulic jack 90, can be placed in the upper portion of the shoe 12 provided in the bridge 11 as shown in FIG.
  • the propulsion nose 60 when the propulsion nose 60 is installed at the forward side of the concrete girder 20 in the step (b), as shown in FIG. 7, the concrete girder 20 has one side pier bridge in the step (d). Remove the next propulsion nose (60a) located on the top (11a) and the other bridge piers (11b).
  • the concrete girder 20 may be positioned above the hydraulic jack 90, and the hydraulic jack 90 may be raised to support the lower portion of the concrete girder 20 in advance.
  • the hydraulic jack 90 supports the load of the concrete girder 20
  • the propulsion nose 60 is removed.
  • Concrete bridge traction extrusion method using the bogie and winch of the present invention is for the concrete bridge traction extrusion method for the construction of the concrete girder of the bridge has industrial applicability.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to an incremental launching method for a concrete bridge, for constructing concrete girders constituting the bridge. The incremental launching method for the concrete bridge using transport carts and a winch, according to the present invention, is a method for installing the concrete girders between bridge supports, which are installed in a line with a specific distance therebetween, comprising the steps of: (a) arranging a plurality of the transport carts so as to be connected in a line, and on an upper panel preinstalled behind a bridge support on one side; (b) positioning the concrete girder on top of the transport carts; (c) installing and fixing the winch on top of a front bridge support on the other side where the concrete girder will be installed upon arrival, and advancing the concrete girder toward the bridge support on the other side by connecting a pulling wire of the winch to the frontmost transport cart and pulling the transport carts forward; and (d) releasing the pulling wire after advancing the concrete girder to the position of a bridge bearing of the bridge support on the other side, and then placing the concrete girder on top of the bridge bearing of the bridge support on the one side and the bridge bearing of the bridge support on the other side.

Description

대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법Concrete Bridge Traction Extrusion Using Bogie and Hoist
본 발명은 교량의 콘크리트 거더를 시공하기 위한 콘크리트 교량 견인 압출 공법에 대한 것으로, 더욱 상세하게는 교량의 콘크리트 거더를 견인 압출하는데 있어 공기 단축과 비용의 절감이 가능하고, 콘크리트 거더의 전진 거리에 구애받지 않고 시공할 수 있으며, 콘크리트 거더의 손상을 방지할 수 있는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법에 대한 것이다.The present invention relates to a concrete bridge traction extrusion method for constructing a concrete girder of a bridge, more specifically, it is possible to shorten the air and reduce costs in the traction extrusion of the concrete girder of the bridge, and to stick to the forward distance of the concrete girder It is about the concrete bridge traction extrusion method using the bogie and the hoist which can be installed without receiving and can prevent the damage of the concrete girder.
교량(bridge)이란 도로, 철도, 계곡, 호수, 해안 등의 위를 건너거나 다른 도로, 철도, 수로, 가옥, 시가지 등의 위를 건너는 경우 이들 위에 가설하는 구조물을 총칭하는 것으로, 교량의 콘크리트 거더를 가설 시공하는 공법 중 하나로 압출 공법(incremental launching method, ILM)이 있다. A bridge is a generic term for structures placed on them when crossing over roads, railways, valleys, lakes, shores, or other roads, railways, waterways, houses, towns, etc. One of the construction methods for constructing an extrusion method (incremental launching method, ILM) is.
상기 교량 압출 공법은 압출 방식에 따라 푸시 타입(push type), 리프트 앤 푸시 타입(lift and push type) 및 견인 타입(pulling-out type)이 있으며, 본 발명은 이중 견인 타입(pulling-out type)과 관련된 것이다.The bridge extrusion method has a push type (push type), a lift and push type (pulling-out type) according to the extrusion method, the present invention is a double pulling type (pulling-out type) It is related to.
상기 교량 압출 공법은 콘크리트 거더(20)를 교대(橋臺) 또는 제1교각의 후방에 설치한 주형 제작장에서 1 세그먼트(segment)씩 제작한 다음, 교각 상부에 설치된 견인잭(4)을 이용하여 조금씩 밀어내면서 교량을 가설하는 공법으로(도 1), 콘크리트 품질 관리가 우수하고 경제적이며 교량 하부 조건에 무관하게 시공할 수 있는 등의 장점으로 인하여 널리 사용되고 있다. 그리고 특허 제10-0093125호(교량상판의 견인압출장치), 특허 제10-0103702호(대차를 이용한 교량 상부공 압출공법) 등에서 관련 기술을 확인할 수 있다.In the bridge extrusion method, the concrete girder 20 is manufactured one by one at a mold fabrication site installed at the rear of the bridge or the first pier, and then using the tow jack 4 installed at the upper part of the bridge. As a construction method to construct a bridge while pushing a little bit (Fig. 1), it is widely used due to the advantages of excellent concrete quality control, economical and can be constructed regardless of the bridge under conditions. And the related technology can be found in Patent No. 10-0093125 (traction extruder of the bridge top plate), Patent No. 10-0103702 (bridge upper hole extrusion method using a bogie).
그러나 종래의 교량 압출 공법은 교량을 구성하는 콘크리트 거더의 압출을 위한 장비가 매우 고가로 교량의 전체 연장이 500m 정도 이하인 경우에는 경제성이 없을 뿐 아니라, 지간이 50m 정도를 넘는 경우에는 사용할 수 없다는 한계가 있었다.However, the conventional bridge extrusion method is expensive because the equipment for the extrusion of the concrete girder constituting the bridge is very expensive and it is not economical when the total extension of the bridge is about 500m or less, and it cannot be used when the span is more than 50m. There was.
아울러 콘크리트 거더의 전방 또는 후방에서 콘크리트 거더를 압출할 경우, 유압잭 피치의 한계로 인하여 전진 거리에 한계가 있으며, 유압잭의 전진 및 후진 반복 작업이 수반되어 작업 시간이 많이 소요되는 단점이 있었다.In addition, when the concrete girder is extruded from the front or the rear of the concrete girder, there is a limit in the forward distance due to the limitation of the hydraulic jack pitch, there was a disadvantage in that a lot of work time due to the repeated forward and backward operations of the hydraulic jack.
또한, 종래 교량 압출 공법 중 콘크리트 거더를 전방에서 견인하는 견인 압출 공법의 경우에는 콘크리트 거더 또는 추진코(launching nose)를 직접 당기므로 콘크리트 거더에 인장력이 발생하여 인장력에 취약한 콘크리트 거더 자체를 손상시킬 수 있었다.In addition, in the conventional traction extrusion method of towing the concrete girder in the bridge extrusion method in front of the concrete girder or launching nose (pulling nose) directly pull the concrete girder can cause a tensile force to damage the concrete girder itself vulnerable to tensile force there was.
상기와 같은 과제를 해결하기 위하여 본 발명은 저렴하고 취득이 용이한 장비를 이용하여 시공 비용을 절감할 수 있는 것으로, 특히 중소 규모 교량의 비용 절감에 효과적인 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공하고자 한다.In order to solve the above problems, the present invention can reduce the construction cost by using a cheap and easy to acquire equipment, in particular, concrete bridge traction extrusion method using a bogie and winch effective for reducing the cost of small and medium-sized bridge To provide.
아울러 본 발명은 교량을 구성하는 콘크리트 거더를 견인 압출하는데 있어, 유압잭의 전후진 반복 작업을 생략할 수 있어 공기 단축이 가능하고, 콘크리트 거더의 전진 거리에 구애받지 않고 효율적으로 시공할 수 있는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공하고자 한다.In addition, the present invention in the traction extrusion of the concrete girder constituting the bridge, it is possible to omit the forward and backward repetitive work of the hydraulic jack can shorten the air, and can be efficiently constructed regardless of the forward distance of the concrete girder and To provide a concrete bridge traction extrusion method using a winch.
또한, 본 발명은 교량의 견인 압출 공법에서 콘크리트 거더 또는 추진코를 직접 당기지 않아 인장력으로 인한 콘크리트 거더의 손상을 방지할 수 있는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공하고자 한다. In addition, the present invention is to provide a concrete bridge traction extrusion method using a bogie and a hoist that can prevent the concrete girder or damage to the concrete girder due to the tensile force by not pulling the concrete girder or the propulsion nose directly in the traction extrusion method of the bridge.
상기와 같은 과제를 해결하기 위하여 바람직한 실시예에 따르면 본 발명은 상호 일정 간격 이격되도록 일렬로 설치된 교각들 사이에 콘크리트 거더를 설치하는 방법에 있어서, (a) 일측 교각 후방의 기설치된 상판에 복수의 대차를 상호 일렬로 연결되도록 배치하는 단계; (b) 상기 대차 상부에 콘크리트 거더를 위치시키는 단계; (c) 콘크리트 거더가 도달되어 설치될 전방의 타측 교각 상부에 권양기를 설치 고정하고, 권양기의 견인용 와이어를 최전방 대차에 연결하여 대차를 전방으로 견인함으로써 콘크리트 거더를 타측 교각 측으로 전진시키는 단계; 및 (d) 상기 콘크리트 거더를 타측 교각 교좌 위치까지 전진시킨 후 견인용 와이어를 해제하고, 콘크리트 거더를 일측 교각 교좌와 타측 교각 교좌 상부에 안치시키는 단계; 를 포함하여 이루어지는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공한다.According to a preferred embodiment of the present invention to solve the above problems, the present invention provides a method for installing concrete girders between the piers installed in a line spaced apart from each other, (a) a plurality of pre-installed top plate at the rear of one piers Arranging the balances so that they are connected in line with each other; (b) placing a concrete girder on top of the bogie; (c) advancing the concrete girder to the other pier side by installing and fixing the winch on the upper side of the pier where the concrete girder is reached and installed, and connecting the towing wire of the winch to the fore bogie to pull the bogie forward; And (d) advancing the concrete girder to the other pier bridge position, releasing the traction wire, and placing the concrete girder on one pier bridge and the other pier bridge. It provides a concrete bridge traction extrusion method using a bogie and a hoist.
다른 바람직한 실시예에 따르면 본 발명은 상기 (b) 단계에서 압출되는 콘크리트 거더에 작용하는 부모멘트를 감소시키기 위해 콘크리트 거더 전진측 단부에는 추진코가 설치되고, 상기 추진코는 상기 (d) 단계에서 콘크리트 거더가 일측 교각 교좌와 타측 교각 교좌 상부에 위치된 후 제거되는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공한다.According to another preferred embodiment of the present invention, in order to reduce the parent moment acting on the concrete girder extruded in the step (b), a propulsion nose is installed at the end of the concrete girder forward side, and the propulsion nose is in the step (d) It provides a concrete bridge traction extrusion method using a bogie and a winch, characterized in that the concrete girder is removed after being positioned on the upper side of the bridge piers and the other bridge piers.
다른 바람직한 실시예에 따르면 본 발명은 상기 일측 교각과 타측 교각의 사이에는 수상에 설치된 자주승강식 바지 상부 또는 육상의 지면 상부에 설치된 가설지지대가 구비되어 콘크리트 거더가 전진하는 동안 콘크리트 거더 하부를 지지하는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공한다.According to another preferred embodiment of the present invention is provided between the one side pier and the other pier is provided with a temporary support installed on the water-lifting pants or installed on the ground above the ground to support the bottom of the concrete girder while advancing the concrete girder It provides a concrete bridge traction extrusion method using a bogie and a hoist.
다른 바람직한 실시예에 따르면 본 발명은 상기 (d) 단계에서, 교좌에는 상하 이동하는 유압잭이 구비되어, 일측 교각과 타측 교각 사이에 위치한 콘크리트 거더를 유압잭으로 하향 이동시켜 교좌에 설치된 슈 상부에 안치시키는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공한다.According to another preferred embodiment of the present invention, in the step (d), the bridge is provided with a hydraulic jack to move up and down, to move the concrete girder located between one pier and the other pier downwards to the hydraulic jack to be placed on the shoe installed on the bridge It provides a concrete bridge traction extrusion method using a bogie and a hoist.
다른 바람직한 실시예에 따르면 본 발명은 상기 (b) 단계에서, 프리캐스트 콘크리트 거더를 대차 위에 안치시키거나 대차 상면에 거푸집을 설치하여 현장 타설 콘크리트 거더를 시공하는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공한다.According to another preferred embodiment of the present invention, in the step (b), the precast concrete girder is placed on the bogie or by installing a formwork on the bogie's upper surface, the concrete using the bogie and the hoist Provide bridge traction extrusion method.
다른 바람직한 실시예에 따르면 본 발명은 상기 (c) 단계에서, 최전방 대차가 일측 교각에 다다르면 최전방 대차를 제거하고 견인용 와이어를 다음 대차에 연결하여 콘크리트 거더를 전진시키는 과정을 반복하여 콘크리트 거더를 전진시키는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법을 제공한다.According to another preferred embodiment of the present invention, in the step (c), if the fore trolley reaches one pier, the fore bogie is removed and the concrete girder is advanced by repeating the process of advancing the concrete girder by connecting the towing wire to the next bogie. It provides a concrete bridge traction extrusion method using a bogie and a hoist.
상기와 같은 본 발명에 따르면 다음과 같은 효과가 있다.According to the present invention as described above has the following effects.
첫째, 교량을 구성하는 콘크리트 거더를 견인 압출 시공하는 데 있어 저렴하고 취득이 용이한 장비를 이용하여 비용을 절감할 수 있으며, 특히 중소 규모 교량의 비용 절감에 효과적이다.First, it is possible to reduce the cost by using cheap and easy-to-acquire equipment in the traction extrusion construction of the concrete girder constituting the bridge, especially effective for reducing the cost of small and medium-sized bridges.
둘째, 콘크리트 거더를 전방의 타측 교각에 고정된 권양기로 견인하기 때문에, 유압잭을 이용한 전후진 반복 작업을 생략할 수 있어 공기 단축이 가능하고, 콘크리트 거더의 전진 거리에 구애받지 않고 시공이 가능하다. Second, because the girder is towed by a winch fixed to the other piers in front, it is possible to omit the repetitive forward and backward operations using the hydraulic jack, it is possible to shorten the air, and can be installed regardless of the forward distance of the concrete girder.
셋째, 교량의 견인 압출 공법에서 콘크리트 거더 또는 추진코를 직접 당기지 않고 상부에 콘크리트 거더가 위치된 대차를 견인하기 때문에, 콘크리트 거더에 작용하는 인장력으로 인한 콘크리트 거더의 손상을 방지할 수 있다.Third, in the traction extrusion method of the bridge to pull the bogie with the concrete girders located on the top without directly pulling the concrete girder or propulsion nose, it is possible to prevent the damage of the concrete girder due to the tensile force acting on the concrete girder.
넷째, 추진코를 이용하여 콘크리트 거더를 일정량 전진시킨 후에는 추진코의 일단이 지지되기 때문에 각 콘크리트 거더가 캔틸레버 보에서 양단지지 보로 전환된다. 따라서 콘크리트 거더에 작용하는 부모멘트의 영향을 최소화하여 거더 단면을 최적화한 경제적인 설계가 가능하다. Fourth, since the end of the propulsion nose is supported after advancing the concrete girder by a certain amount using the propulsion nose, each concrete girder is switched from the cantilever beam to the support beam at both ends. Therefore, it is possible to economically design with optimized girder section by minimizing the influence of the parent moment acting on the concrete girder.
다섯째, 인접 교각 사이에 가설지지대를 설치함으로써 안정적이고 효율적으로 교량을 시공할 수 있다. 즉, 콘크리트 거더가 압출 과정에서 가설지지대 상면에 위치되게 되면 콘크리트 거더가 캔틸레버 보에서 양단지지 보로 전환되어 콘크리트 거더에 부모멘트를 최소화하거나 작용하지 않게 할 수 있으므로 경제적이고 효율적인 단면의 설계 및 시공이 가능하다.Fifth, it is possible to construct bridges stably and efficiently by installing temporary supports between adjacent piers. That is, when the concrete girders are placed on the upper surface of the temporary support during the extrusion process, the concrete girders can be switched from the cantilever beams to the both ends of the support beams, thereby minimizing or not acting on the parent girders in the concrete girders, thereby enabling the design and construction of economic and efficient sections Do.
도 1은 종래 콘크리트 교량의 압출 공법을 도시하는 도면이다.1 is a view showing an extrusion method of a conventional concrete bridge.
도 2 내지 도 9는 각각 본 발명의 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법의 단계별 공정 일부를 도시하는 도면이다.2 to 9 are views showing a part of the step-by-step process of the concrete bridge traction extrusion method using the trolley and the hoist of the present invention, respectively.
도 2는 기설치된 상판에 상호 연결된 대차를 배치하고 대차 상부에 콘크리트 거더를 위치시키는 단계를 도시하는 도면이다.FIG. 2 is a diagram illustrating a step of arranging the carts interconnected to the installed upper plate and placing the concrete girder on the upper part of the cart.
도 3은 콘크리트 거더 전진측 단부에 추진코가 설치된 모습을 도시하는 도면이다. 3 is a view illustrating a state in which a propulsion nose is installed at an end of a concrete girder forward side.
도 4는 인접 교각 사이에 자주승강식 바지 및 가설지지대가 설치된 모습을 도시하는 도면이다.4 is a view illustrating a state in which self-elevating pants and temporary supports are installed between adjacent piers.
도 5는 최전방 대차에 권양기의 견인용 와이어를 연결하고 대차를 권양기로 견인하는 단계를 도시하는 도면이다.5 is a view showing a step of connecting the towing wire of the hoisting machine to the foremost bogie and towing the bogie to the hoisting machine.
도 6은 대차를 권양기로 견인하여 타측 교각 상부로 추진코가 위치되는 단계를 도시하는 도면이다.6 is a view showing a step in which the propulsion nose is positioned above the other pier by pulling the bogie with a winch.
도 7은 콘크리트 거더를 타측 교각 교좌 위치까지 전진시키는 단계를 도시하는 도면이다.7 is a view showing the step of advancing the concrete girder to the other pier bridge position.
도 8은 유압잭으로 콘크리트 거더를 하향 이동시키는 모습을 도시하는 도면이다.8 is a view illustrating a state in which the concrete girder is moved downward by the hydraulic jack.
도 9는 콘크리트 거더가 슈 상부에 안치되어 교량의 설치가 완료된 모습을 도시하는 도면이다.9 is a view showing a state in which the installation of the bridge is completed by placing the concrete girder on the shoe upper portion.
본 발명의 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법은 상호 일정 간격 이격되도록 일렬로 설치된 교각들 사이에 콘크리트 거더를 설치하는 방법에 있어서, (a) 일측 교각 후방의 기설치된 상판에 복수의 대차를 상호 일렬로 연결되도록 배치하는 단계; (b) 상기 대차 상부에 콘크리트 거더를 위치시키는 단계; (c) 콘크리트 거더가 도달되어 설치될 전방의 타측 교각 상부에 권양기를 설치 고정하고, 권양기의 견인용 와이어를 최전방 대차에 연결하여 대차를 전방으로 견인함으로써 콘크리트 거더를 타측 교각 측으로 전진시키는 단계; 및 (d) 상기 콘크리트 거더를 타측 교각 교좌 위치까지 전진시킨 후 견인용 와이어를 해제하고, 콘크리트 거더를 일측 교각 교좌와 타측 교각 교좌 상부에 안치시키는 단계; 를 포함하여 이루어지는 것을 특징으로 한다.Concrete bridge traction extrusion method using the bogie and winch of the present invention is a method for installing concrete girders between the piers installed in a line so as to be spaced apart by a predetermined interval, (a) a plurality of bogies on the pre-installed top plate behind the one side piers Arranging to be connected in line with each other; (b) placing a concrete girder on top of the bogie; (c) advancing the concrete girder to the other pier side by installing and fixing the winch on the upper side of the pier where the concrete girder is reached and installed, and connecting the towing wire of the winch to the fore bogie to pull the bogie forward; And (d) advancing the concrete girder to the other pier bridge position, releasing the traction wire, and placing the concrete girder on one pier bridge and the other pier bridge. Characterized in that comprises a.
이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.
도 2는 기설치된 상판(30)에 대차(40)를 배치하고 대차(40) 상부에 콘크리트 거더(20)를 위치시키는 단계를 도시하는 도면이고, 도 3은 콘크리트 거더(20) 전진측 단부에 추진코(60)가 설치된 모습을 도시하는 도면이다. 2 is a view showing the step of placing the trolley 40 on the top plate 30 is already installed and positioning the concrete girder 20 on the upper portion of the trolley 40, Figure 3 is a concrete girder 20 at the forward end end It is a figure which shows the state which the propulsion nose 60 was installed.
본 발명의 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법은 상호 일정 간격 이격되도록 일렬로 설치된 교각(10)들 사이에 콘크리트 거더(20)를 설치하는 방법에 대한 것이다.Concrete bridge traction extrusion method using the bogie and winch of the present invention relates to a method for installing the concrete girder 20 between the piers 10 installed in a row so as to be spaced apart from each other at regular intervals.
따라서 본 발명을 구성하는 각 단계의 실시 이전에 교각(10)의 시공이 완료되어야 한다. 교각(10)의 시공은 지반 여건 및 주위 환경에 미치는 영향 등을 고려하여 진행한다. Therefore, the construction of the piers 10 should be completed before the implementation of each step constituting the present invention. Construction of the pier 10 proceeds in consideration of the ground conditions and the impact on the surrounding environment.
본 발명은 (a) 일측 교각(10a) 후방의 기설치된 상판(30)에 복수의 대차(40)를 상호 일렬로 연결되도록 배치하는 단계; (b) 상기 대차(40) 상부에 콘크리트 거더(20)를 위치시키는 단계; (c) 콘크리트 거더(20)가 도달되어 설치될 전방의 타측 교각(10b) 상부에 권양기(50)를 설치 고정하고, 권양기(50)의 견인용 와이어(51)를 최전방 대차(40a)에 연결하여 대차(40)를 전방으로 견인함으로써 콘크리트 거더(20)를 타측 교각(10b) 측으로 전진시키는 단계; 및 (d) 상기 콘크리트 거더(20)를 타측 교각 교좌(11b) 위치까지 전진시킨 후 견인용 와이어(51)를 해제하고, 콘크리트 거더(20)를 일측 교각 교좌(11a)와 타측 교각 교좌(11b) 상부에 안치시키는 단계; 를 포함하여 이루어지는 것을 특징으로 한다.The present invention comprises the steps of: (a) arranging a plurality of trucks (40) in line with each other in a pre-installed top plate 30 behind one side piers (10a); (b) placing a concrete girder 20 on top of the trolley 40; (c) The winch 50 is installed and fixed on the upper side of the other piers 10b in front of the concrete girder 20 to be installed, and the towing wire 51 of the winch 50 is connected to the fore bogie 40a. Advancing the concrete girder 20 to the other pier 10b side by pulling the cart 40 forward; And (d) advancing the concrete girder 20 to the position of the other pier bridge 11b, releasing the traction wire 51, and placing the concrete girder 20 at the one bridge bridge 11a and the other bridge bridge 11b. Resting on top; Characterized in that comprises a.
도 2에서 볼 수 있는 바와 같이, 본 발명은 (a) 일측 교각(10a) 후방의 기설치된 상판(30)에 복수의 대차(40)를 상호 일렬로 연결되도록 배치한 다음, (b) 상기 대차(40) 상부에 콘크리트 거더(20)를 위치시키는 순서로 진행된다.As can be seen in Figure 2, the present invention (a) a plurality of trucks (40) arranged on the pre-installed top plate (30) behind one side piers (10a) to be connected to each other in line, (b) the truck 40 proceeds in the order of placing the concrete girder 20 on the top.
상기 (a) 단계에서 대차(40)는 복수 개가 일렬로 연결되도록 배치되나, 상기 대차(40)를 복수 열이 되도록 병렬로 배치하고, 각 대차(40) 상부에 콘크리트 거더(20)를 위치시켜, 복수 개의 콘크리트 거더(20) 설치 작업을 동시 또는 순차적으로 진행할 수도 있다.In the step (a), a plurality of bogies 40 are arranged so as to be connected in a row, the bogies 40 are arranged in parallel so as to have a plurality of rows, and the concrete girders 20 are positioned on the top of each bogie 40. , Installing a plurality of concrete girders 20 may be performed simultaneously or sequentially.
본 발명에서 콘크리트 거더(20)는 교량을 구성하는 것으로 교각(10) 상면에 위치되는 콘크리트 거더(20)를 의미한다. Concrete girder 20 in the present invention refers to the concrete girder 20 which is located on the upper surface of the pier 10 to form a bridge.
상기 (b) 단계에서 콘크리트 거더(20)는 프리캐스트 콘크리트 거더(20)를 대차(40) 위에 안치시키거나, 대차(40) 상면에 거푸집을 설치하여 현장 타설 콘크리트 거더(20)로 시공할 수 있다.In the step (b), the concrete girder 20 may be constructed as a cast-in-place concrete girder 20 by placing the precast concrete girder 20 on the trolley 40 or by installing a formwork on the upper surface of the trolley 40. have.
즉, 상기 콘크리트 거더(20)는 프리캐스트 콘크리트 거더를 미리 제작장에서 제작하여 양중기로 대차(40) 상부에 안치시킬 수 있다. 그러나 콘크리트 거더(20)의 규모가 커서 운반, 양중이 곤란한 경우에는 대차(40) 상부에 거푸집을 설치하여 현장 타설로 설치할 수도 있다.That is, the concrete girder 20 may be made in advance in the pre-fabrication girder to be placed on the trolley 40 with a heavy lifting. However, when the size of the concrete girder 20 is difficult to transport and lift, it may be installed by placing the formwork on the upper portion of the bogie 40 by site pouring.
상기 콘크리트 거더(20)는 다양한 단면 형상이 가능하며, 사각형 또는 제형 단면 등의 콘크리트 박스 거더로 구성할 수도 있다.The concrete girder 20 can be a variety of cross-sectional shape, it may be configured as a concrete box girder, such as square or formulation cross section.
본 발명은 도 3에서 볼 수 있는 바와 같이, 상기 (b) 단계에서 압출되는 콘크리트 거더(20)에 작용하는 부모멘트를 감소시키기 위해 콘크리트 거더(20)의 전진측 단부에 추진코(60)를 설치할 수 있다. As can be seen in Figure 3, the propulsion nose 60 to the forward side end of the concrete girder 20 to reduce the parent moment acting on the concrete girder 20 is extruded in the step (b). Can be installed.
상기 추진코(60)는 콘크리트 거더(20)의 전진측 단부에 설치되어, 콘크리트 거더(20)가 일정량 전진한 다음에는 추진코(60)의 단부가 타측 교각(10b) 또는 가설지지대(80) 상면에 지지되어 콘크리트 거더(20)를 캔틸레버 보에서 양단지지 보로 전환되게 한다. 따라서 콘크리트 거더(20)에 작용하는 부모멘트와 처짐의 영향을 최소화하여, 콘크리트 거더(20)의 견인 과정에서 구조적 안전성 및 시공의 안정성을 향상시킨다.The propulsion nose 60 is installed at the forward end of the concrete girder 20, after the concrete girder 20 is advanced a certain amount, the end of the propulsion nose 60 is the other pier 10b or temporary support 80 It is supported on the upper surface to convert the concrete girder 20 from the cantilever beam to both ends of the support beam. Therefore, by minimizing the influence of the parent moment and deflection acting on the concrete girder 20, in the traction process of the concrete girder 20 improves the structural safety and construction stability.
상기 추진코(60)는 가벼운 철골 트러스 골조로 제작함이 바람직하다.The propulsion nose 60 is preferably made of light steel truss skeleton.
도 4는 인접 교각(10) 사이에 자주승강식 바지(70) 및 가설지지대(80)가 설치된 모습을 도시하는 도면이고, 도 5는 최전방 대차(40a)에 권양기(50)의 견인용 와이어(51)를 연결하고 대차(40)를 권양기(50)로 견인하는 단계를 도시하는 도면이며, 도 6은 대차(40)를 권양기(50)로 견인하여 타측 교각(10b) 상부로 추진코(60)가 위치되는 단계를 도시하는 도면이다.4 is a view showing the self-elevating pants 70 and the temporary support 80 is installed between the adjacent piers 10, Figure 5 is a forklift wire (50) of the winch 50 in the front trolley (40a) 51 is a view showing the step of connecting the cart 40 to the winch 50, Figure 6 is towing the cart 40 to the winch 50, the propelled nose (60b) to the top of the other side piers (10b) Is a diagram showing a step in which) is located.
교량이 수상 구간에 설치되는 경우 본 발명은 도 4에서 볼 수 있는 바와 같이, 상기 일측 교각(10a)과 타측 교각(10b)의 사이에 자주승강식 바지(70)가 수상에 설치되고, 상기 자주승강식 바지(70) 상부에 가설지지대(80)가 설치되어 콘크리트 거더(20)가 전진하는 동안 콘크리트 거더(20) 하부를 지지하는 것을 특징으로 한다.When the bridge is installed in the water section, the present invention as shown in Figure 4, the self-elevating pants 70 is installed between the one side piers (10a) and the other piers (10b) in the water, The temporary support 80 is installed on the liftable pants 70 to support the lower portion of the concrete girder 20 while the concrete girder 20 moves forward.
상기 자주승강식 바지(SEP 바지: self elevated pontoon barge)(70)는 모서리에 지주가 구비된 것으로, 상하 유동이 적어 조류나 파도의 영향을 받지 않고 상부 시공이 가능한 장점이 있다. 상기 자주승강식 바지(70)의 지주는 수심에 따라 높이 조절이 가능하다. The self-elevating pants (SEP pants: 70) is provided with a support at the corner, there is an advantage that the upper construction is not affected by tidal flow or waves because there is little up and down flow. The prop of the self-elevating pants 70 is height adjustable according to the depth.
상기 자주승강식 바지(70)는 바람직하게는 인접 교각(10)의 중앙이 되는 부분에 고정한다.The self-elevating pants 70 is preferably fixed to the portion that becomes the center of the adjacent piers 10.
상기 자주승강식 바지(70)와 가설지지대(80)는 콘크리트 거더(20)의 견인 과정에서 콘크리트 거더(20)의 일부분이 가설지지대(80)에 일정 기간 거치되는 동안 활용되는 임시 구조물이다.The self-elevating pants 70 and the temporary support 80 are temporary structures that are used while a part of the concrete girder 20 is mounted on the temporary support 80 for a period of time during the towing of the concrete girder 20.
교량이 육상 구간에 설치되는 경우에는 상기 가설지지대(80)가 육상의 지면 상부에 설치된다.When the bridge is installed in the land section, the temporary support 80 is installed on the ground above the land.
본 발명은 상기 가설지지대(80)를 이용함으로써, 콘크리트 거더(20)의 압출 과정에서 콘크리트 거더(20)가 가설지지대(80) 상면에 위치되게 된다. 따라서 시공 과정에서 콘크리트 거더(20)가 캔틸레버 보에서 양단지지 보로 전환되어, 콘크리트 거더(20)에 부모멘트를 최소화하거나 작용하지 않게 할 수 있다. 그리고 상하 유동이 적은 자주승강식 바지를 이용하기 때문에, 수위의 변동이나 파랑으로 인한 상하 유동으로 인하여 콘크리트 거더(20)에 추가 모멘트가 발생되는 것을 최소화한다.In the present invention, by using the temporary support 80, the concrete girder 20 in the extrusion process of the concrete girder 20 is located on the upper surface of the temporary support (80). Therefore, the concrete girder 20 is converted from the cantilever beam to both ends of the support beam in the construction process, it is possible to minimize or not act as a parent to the concrete girder 20. And because the use of self-elevating pants with a low vertical flow, minimizing the generation of additional moments in the concrete girder 20 due to the fluctuation of the water level or the vertical flow due to the wave.
상기 가설지지대(80) 상면에는 콘크리트 거더(20)의 효과적인 이동을 위하여 롤러가 설치됨이 바람직하다. The roller is installed on the upper surface of the temporary support 80 for the effective movement of the concrete girder 20.
한편, 상기 (b) 단계가 완료된 다음에는 도 5 내지 도 6에서와 같이, (c) 콘크리트 거더(20)가 도달되어 설치될 전방의 타측 교각(10b) 상부에 권양기(50)를 설치 고정하고, 권양기(50)의 견인용 와이어(51)를 최전방 대차(40a)에 연결하여 대차(40)를 전방으로 견인함으로써 콘크리트 거더(20)를 타측 교각(10b) 측으로 전진시킨다. On the other hand, after the step (b) is completed, as shown in Figures 5 to 6, (c) the concrete girders 20 is fixed to install the winch 50 on the top of the other side piers (10b) to be installed , By connecting the towing wire 51 of the winch 50 to the front trolley 40a and pulling the trolley 40 forward to advance the concrete girder 20 to the side of the other piers 10b.
상기 (c) 단계에서 권양기(50)는 콘크리트 거더(20)를 당기기 위한 구성으로, 타측 교각(10b) 상부에 고정 설치된다. In the step (c), the winch 50 is configured to pull the concrete girder 20, is fixedly installed on the other side piers (10b).
본 발명은 고가이고 복잡한 압출 장비를 이용하는 대신, 저렴하고 취득이 용이한 권양기(50)를 이용하여 콘크리트 거더(20)를 견인 압출 시공한다. 따라서 중소형 교량에 이용하더라도 공기 및 공사비 면에서 효율적이다. Instead of using expensive and complicated extrusion equipment, the present invention uses the low cost and easy to obtain winch 50 to traction extrusion the concrete girders 20. Therefore, it is efficient in terms of air and construction cost even for small and medium bridges.
상기 (c) 단계에서는 최전방 대차(40a)가 일측 교각(10a)에 다다르면 최전방 대차(40a)를 제거하고 견인용 와이어(51)를 다음 대차(40b)에 연결하여 콘크리트 거더(20)를 전진시키는 과정을 반복하여 콘크리트 거더(20)를 전진시킬 수 있다.In the step (c), when the front trolley 40a reaches one side of the piers 10a, the front trolley 40a is removed and the towing wire 51 is connected to the next trolley 40b to advance the concrete girder 20. The process may be repeated to advance the concrete girder 20.
그리고 도 6에서와 같이 대차(40)를 권양기(50)로 견인하여 타측 교각(10b) 상부에 콘크리트 거더(20) 또는 추진코(60)가 위치되면, 추진코(60) 전방을 단계적으로 해체하거나 타측 교각(10b)에 인접한 다른 교각 상부로 권양기(50)를 재위치시킬 수 있다.And as shown in FIG. 6, when the concrete girder 20 or the propelling nose 60 is positioned above the other pier 10b by towing the bogie 40 to the winch 50, the propulsion nose 60 is gradually dismantled. Alternatively, the winch 50 may be repositioned above the other pier adjacent to the other pier 10b.
도 7은 콘크리트 거더(20)를 타측 교각 교좌(11b) 위치까지 전진시키는 단계를 도시하는 도면이고, 도 8은 유압잭(90)으로 콘크리트 거더(20)를 하향 이동시키는 모습을 도시하는 도면이며, 도 9는 콘크리트 거더(20)가 슈(12) 상부에 안치되어 교량의 설치가 완료된 모습을 도시하는 도면이다.7 is a view showing a step of advancing the concrete girder 20 to the position of the other pier bridge (11b), Figure 8 is a view showing a state of moving the concrete girder 20 downward with the hydraulic jack 90, 9 is a view showing the concrete girder 20 is placed on the shoe 12, the installation of the bridge is completed.
본 발명에서는 상기 (c) 단계 이후, (d) 상기 콘크리트 거더(20)를 타측 교각 교좌(11b) 위치까지 전진시킨 후 견인용 와이어(51)를 해제하고, 콘크리트 거더(20)를 일측 교각 교좌(11a)와 타측 교각 교좌(11b) 상부에 안치시킨다. In the present invention, after the step (c), (d) advances the concrete girder 20 to the other pier bridge (11b) position, and then release the towing wire 51, concrete girder 20 one side pier bridge It is settled on the upper part of 11a and the other bridge bridge 11b.
이때, 상기 (d) 단계에서는 도 7에서와 같이 교좌(11)에는 상하 이동 가능한 유압잭(90)이 구비되어, 도 8에서와 같이 일측 교각(10a)과 타측 교각(10b) 사이에 위치한 콘크리트 거더(20)를 유압잭(90)으로 하향 이동시켜, 도 9에서와 같이 교좌(11)에 설치된 슈(12) 상부에 안치시킬 수 있다.At this time, in the step (d) as shown in Figure 7 the bridge 11 is provided with a hydraulic jack 90 that can be moved up and down, as shown in Figure 8 concrete girder located between one pier 10a and the other pier 10b 20 can be moved downward to the hydraulic jack 90, can be placed in the upper portion of the shoe 12 provided in the bridge 11 as shown in FIG.
물론, 상기 (b) 단계에서 콘크리트 거더(20) 전진측 단부에 추진코(60)를 설치한 경우에는 도 7에서 볼 수 있는 바와 같이, (d) 단계에서 콘크리트 거더(20)가 일측 교각 교좌(11a)와 타측 교각 교좌(11b) 상부에 위치된 다음 추진코(60)를 제거하도록 한다. Of course, when the propulsion nose 60 is installed at the forward side of the concrete girder 20 in the step (b), as shown in FIG. 7, the concrete girder 20 has one side pier bridge in the step (d). Remove the next propulsion nose (60a) located on the top (11a) and the other bridge piers (11b).
즉, 콘크리트 거더(20)의 견인 과정이 완료되어 콘크리트 거더(20)를 유압잭(90) 상부에 위치시킨 후 유압잭(90)을 상승시켜 미리 콘크리트 거더(20) 하부를 지지하도록 할 수 있다. 이렇게 유압잭(90)이 콘크리트 거더(20)의 하중을 지지하게 되면 추진코(60)를 제거한다. That is, the towing process of the concrete girder 20 is completed, the concrete girder 20 may be positioned above the hydraulic jack 90, and the hydraulic jack 90 may be raised to support the lower portion of the concrete girder 20 in advance. When the hydraulic jack 90 supports the load of the concrete girder 20, the propulsion nose 60 is removed.
아울러 도 4에서와 같이, 상기 일측 교각(10a)과 타측 교각(10b)의 사이에 자주승강식 바지(70)와 가설지지대(80)를 설치한 경우에는 상기 (d) 단계에서 가설부재인 이들 구성을 제거하여야 할 것이다.In addition, as shown in Figure 4, when the self-elevating pants 70 and the temporary support 80 is installed between the one side piers (10a) and the other side piers (10b) these temporary members in step (d) You will need to remove the configuration.
본 발명의 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법은 교량의 콘크리트 거더를 시공하기 위한 콘크리트 교량 견인 압출 공법에 대한 것으로 산업상 이용가능성이 있다.Concrete bridge traction extrusion method using the bogie and winch of the present invention is for the concrete bridge traction extrusion method for the construction of the concrete girder of the bridge has industrial applicability.

Claims (6)

  1. 상호 일정 간격 이격되도록 일렬로 설치된 교각(10)들 사이에 콘크리트 거더(20)를 설치하는 방법에 있어서,In the method for installing the concrete girder 20 between the piers 10 installed in a line spaced apart from each other by a certain interval,
    (a) 일측 교각(10a) 후방의 기설치된 상판(30)에 복수의 대차(40)를 상호 일렬로 연결되도록 배치하는 단계;(a) arranging the plurality of trucks 40 to be connected to each other in a line in the pre-installed upper plate 30 behind the one side piers 10a;
    (b) 상기 대차(40) 상부에 콘크리트 거더(20)를 위치시키는 단계;(b) placing a concrete girder 20 on top of the trolley 40;
    (c) 콘크리트 거더(20)가 도달되어 설치될 전방의 타측 교각(10b) 상부에 권양기(50)를 설치 고정하고, 권양기(50)의 견인용 와이어(51)를 최전방 대차(40a)에 연결하여 대차(40)를 전방으로 견인함으로써 콘크리트 거더(20)를 타측 교각(10b) 측으로 전진시키는 단계; 및(c) The winch 50 is installed and fixed on the upper side of the other piers 10b in front of the concrete girder 20 to be installed, and the towing wire 51 of the winch 50 is connected to the fore bogie 40a. Advancing the concrete girder 20 to the other pier 10b side by pulling the cart 40 forward; And
    (d) 상기 콘크리트 거더(20)를 타측 교각 교좌(11b) 위치까지 전진시킨 후 견인용 와이어(51)를 해제하고, 콘크리트 거더(20)를 일측 교각 교좌(11a)와 타측 교각 교좌(11b) 상부에 안치시키는 단계; 를 포함하여 이루어지는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법.(d) After advancing the concrete girder 20 to the position of the other pier bridge 11b, the traction wire 51 is released, and the concrete girder 20 is connected to the one bridge bridge 11a and the other bridge bridge 11b. Placing it on top; Concrete bridge traction extrusion method using a trolley and hoisting machine comprising a.
  2. 제1항에 있어서,The method of claim 1,
    상기 (b) 단계에서 압출되는 콘크리트 거더(20)에 작용하는 부모멘트를 감소시키기 위해 콘크리트 거더(20) 전진측 단부에는 추진코(60)가 설치되고, In order to reduce the parent moment acting on the concrete girder 20, which is extruded in the step (b), the propulsion nose 60 is installed at the forward end of the concrete girder 20,
    상기 추진코(60)는 상기 (d) 단계에서 콘크리트 거더(20)가 일측 교각 교좌(11a)와 타측 교각 교좌(11b) 상부에 위치된 후 제거되는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법.The propulsion nose 60 is a concrete bridge using a bogie and a hoist, characterized in that the concrete girder 20 is removed after the concrete girder 20 is positioned on one side of the bridge bridge (11a) and the other bridge bridge (11b) in the step (d). Traction extrusion method.
  3. 제1항에 있어서,The method of claim 1,
    상기 일측 교각(10a)과 타측 교각(10b)의 사이에는 수상에 설치된 자주승강식 바지(70) 상부 또는 육상의 지면 상부에 설치된 가설지지대(80)가 구비되어 콘크리트 거더(20)가 전진하는 동안 콘크리트 거더(20) 하부를 지지하는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법.Between the one pier (10a) and the other pier (10b) is provided with a temporary support (80) installed on the self-lifting pants 70 installed on the water surface or the upper surface of the land while the concrete girder 20 is moving forward Concrete bridge traction extrusion method using a trolley and a hoist, characterized in that for supporting the bottom of the concrete girder (20).
  4. 제1항에 있어서,The method of claim 1,
    상기 (d) 단계에서, 교좌(11)에는 상하 이동하는 유압잭(90)이 구비되어, 일측 교각(10a)과 타측 교각(10b) 사이에 위치한 콘크리트 거더(20)를 유압잭(90)으로 하향 이동시켜 교좌(11)에 설치된 슈(12) 상부에 안치시키는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법.In the step (d), the bridge 11 is provided with a hydraulic jack 90 to move up and down, to move the concrete girder 20 located between the one piers (10a) and the other piers (10b) downwards to the hydraulic jack (90). Concrete bridge traction extrusion method using a trolley and hoisting machine, characterized in that it is placed in the upper portion of the shoe 12 installed on the bridge (11).
  5. 제1항에 있어서,The method of claim 1,
    상기 (b) 단계에서, 프리캐스트 콘크리트 거더(20)를 대차(40) 위에 안치시키거나 대차(40) 상면에 거푸집을 설치하여 현장 타설 콘크리트 거더(20)를 시공하는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법.In the step (b), the precast concrete girder 20 is placed on the trolley 40 or by installing a formwork on the upper surface of the trolley 40, the bogie and hoisting machine, characterized in that the construction of the site cast concrete girder 20 Concrete bridge traction extrusion method
  6. 제1항에 있어서,The method of claim 1,
    상기 (c) 단계에서, 최전방 대차(40a)가 일측 교각(10a)에 다다르면 최전방 대차(40a)를 제거하고 견인용 와이어(51)를 다음 대차(40b)에 연결하여 콘크리트 거더(20)를 전진시키는 과정을 반복하여 콘크리트 거더(20)를 전진시키는 것을 특징으로 하는 대차 및 권양기를 이용한 콘크리트 교량 견인 압출 공법.In the step (c), when the front trolley 40a reaches the one side piers 10a, the front trolley 40a is removed and the towing wire 51 is connected to the next trolley 40b to advance the concrete girder 20. Concrete bridge traction extrusion method using a bogie and hoist, characterized in that to advance the concrete girder 20 by repeating the process.
PCT/KR2013/005160 2013-05-30 2013-06-12 Incremental launching method for concrete bridge using transport carts and winch WO2014193020A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR20130061456A KR101492914B1 (en) 2013-05-30 2013-05-30 Pulling-out method of concrete bridge using trolley and winch
KR10-2013-0061456 2013-05-30

Publications (1)

Publication Number Publication Date
WO2014193020A1 true WO2014193020A1 (en) 2014-12-04

Family

ID=51989023

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2013/005160 WO2014193020A1 (en) 2013-05-30 2013-06-12 Incremental launching method for concrete bridge using transport carts and winch

Country Status (2)

Country Link
KR (1) KR101492914B1 (en)
WO (1) WO2014193020A1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350459A (en) * 2015-11-20 2016-02-24 中建交通建设集团有限公司 Large steel beam gliding device and construction method thereof
CN105544412A (en) * 2016-02-01 2016-05-04 中铁四局集团钢结构有限公司 Incremental launching construction method for three-main-truss rigid suspension cable stiffening continuous steel truss girder with stiffening chord
CN105568862A (en) * 2016-01-20 2016-05-11 湖南省第五工程有限公司 Girder erecting device and girder erecting method
CN108442252A (en) * 2018-03-08 2018-08-24 中交武汉港湾工程设计研究院有限公司 A kind of long range curved section girder pushing method
IT201700053808A1 (en) * 2017-05-18 2018-11-18 Cimolai S P A EQUIPMENT AND PROCEDURE TO TRANSLATE A STRUCTURE OF CONSIDERABLE DIMENSIONS AND WEIGHT, AS THE BRANCH OF A BRIDGE, A VIADUCT, A CAVALCAVIA, OR SIMILAR MANUFACTURED
CN111139747A (en) * 2020-01-18 2020-05-12 中交二航局第四工程有限公司 Long-distance pushing construction system for large-span steel-concrete composite beam
CN112030768A (en) * 2020-09-08 2020-12-04 浙江世润建创科技发展有限公司 Bailey beam suspension structure and construction method applying same
CN113863154A (en) * 2021-10-27 2021-12-31 中铁一局集团有限公司 Traction assembly method of large-span steel box girder crossing river channel
CN113863164A (en) * 2021-11-06 2021-12-31 中交路桥建设有限公司 Traction sliding installation method for large-span steel box girder passing through existing overwater bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060827A (en) * 1996-08-14 1998-03-03 P S Co Ltd Shifter for segment block
JP2001172918A (en) * 1999-12-15 2001-06-26 Otaki Yuatsu:Kk Erection costruction method for bridge
JP2004116205A (en) * 2002-09-27 2004-04-15 Otaki Yuatsu:Kk Launching erection method for girder
JP2006028734A (en) * 2004-07-12 2006-02-02 Kawasaki Heavy Ind Ltd Launching erection method for bridge girder, using traveling staging
JP2011174241A (en) * 2010-02-23 2011-09-08 Hokuto Tekko:Kk Method for laying floor slab onto bridge girder

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR950032907A (en) * 1994-05-17 1995-12-22 김성남 Bridge top hole extrusion method using bogie
KR100719305B1 (en) * 2005-01-21 2007-05-18 박순근 construction method of prestressed concrete beam
KR100665680B1 (en) * 2006-03-20 2007-01-09 (주)청석엔지니어링 Bridge construction method by incremental launching of long span superstructure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060827A (en) * 1996-08-14 1998-03-03 P S Co Ltd Shifter for segment block
JP2001172918A (en) * 1999-12-15 2001-06-26 Otaki Yuatsu:Kk Erection costruction method for bridge
JP2004116205A (en) * 2002-09-27 2004-04-15 Otaki Yuatsu:Kk Launching erection method for girder
JP2006028734A (en) * 2004-07-12 2006-02-02 Kawasaki Heavy Ind Ltd Launching erection method for bridge girder, using traveling staging
JP2011174241A (en) * 2010-02-23 2011-09-08 Hokuto Tekko:Kk Method for laying floor slab onto bridge girder

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350459A (en) * 2015-11-20 2016-02-24 中建交通建设集团有限公司 Large steel beam gliding device and construction method thereof
CN105350459B (en) * 2015-11-20 2017-03-22 中建交通建设集团有限公司 Large steel beam gliding device and construction method thereof
CN105568862A (en) * 2016-01-20 2016-05-11 湖南省第五工程有限公司 Girder erecting device and girder erecting method
CN105544412A (en) * 2016-02-01 2016-05-04 中铁四局集团钢结构有限公司 Incremental launching construction method for three-main-truss rigid suspension cable stiffening continuous steel truss girder with stiffening chord
CN105544412B (en) * 2016-02-01 2017-04-19 中铁四局集团钢结构有限公司 Incremental launching construction method for three-main-truss rigid suspension cable stiffening continuous steel truss girder with stiffening chord
IT201700053808A1 (en) * 2017-05-18 2018-11-18 Cimolai S P A EQUIPMENT AND PROCEDURE TO TRANSLATE A STRUCTURE OF CONSIDERABLE DIMENSIONS AND WEIGHT, AS THE BRANCH OF A BRIDGE, A VIADUCT, A CAVALCAVIA, OR SIMILAR MANUFACTURED
CN108442252A (en) * 2018-03-08 2018-08-24 中交武汉港湾工程设计研究院有限公司 A kind of long range curved section girder pushing method
CN108442252B (en) * 2018-03-08 2019-11-12 中交武汉港湾工程设计研究院有限公司 A kind of long range curved section girder pushing method
CN111139747A (en) * 2020-01-18 2020-05-12 中交二航局第四工程有限公司 Long-distance pushing construction system for large-span steel-concrete composite beam
CN112030768A (en) * 2020-09-08 2020-12-04 浙江世润建创科技发展有限公司 Bailey beam suspension structure and construction method applying same
CN113863154A (en) * 2021-10-27 2021-12-31 中铁一局集团有限公司 Traction assembly method of large-span steel box girder crossing river channel
CN113863154B (en) * 2021-10-27 2023-02-14 中铁一局集团有限公司 Traction assembly method of large-span steel box girder crossing river channel
CN113863164A (en) * 2021-11-06 2021-12-31 中交路桥建设有限公司 Traction sliding installation method for large-span steel box girder passing through existing overwater bridge

Also Published As

Publication number Publication date
KR101492914B1 (en) 2015-02-12
KR20140140728A (en) 2014-12-10

Similar Documents

Publication Publication Date Title
WO2014193020A1 (en) Incremental launching method for concrete bridge using transport carts and winch
CN100543235C (en) The method and system of erecting steel trusses by stay cable auxiliary complete cantilever
CN112726409B (en) Hoisting device for bridge water surface pile tie beam and construction method thereof
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN109778700B (en) Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN210684480U (en) Steel arch assembling and transverse moving system for deck type arch bridge construction
CN112267369A (en) Non-span upright post steel trestle structure, pushing installation device and construction method
CN110396942B (en) Steel arch frame assembling and traversing system and method for upper bearing arch bridge construction
CN201991011U (en) Hoisting and releasing system for construction of underwater pier bearing platform double-wall steel cofferdam
CN212612030U (en) Pile bridge erection construction all-in-one
CN103806374B (en) The overall track erection supplying system of assembly type steel bridge on highway and erection push technique
CN110438908B (en) Deck-type box-type arch bridge reconstruction construction method
CN210856954U (en) Support-free cable hoisting construction structure of steel arch center for deck arch bridge
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
KR100627102B1 (en) Upper bridge structure construcion method with precast segment deck or box using a lifting traveller
CN110438906B (en) Arch rib construction method for deck box type arch bridge
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN216515141U (en) Novel cantilever construction creeping formwork device
CN110438907B (en) Deck type arch bridge construction method based on steel arch frame
CN214935303U (en) Hoisting device of steel reinforcement cage
CN212426772U (en) Suspended bracket system for cast-in-place bridge deck of steel plate composite beam
CN111395850A (en) Assembled tower frame for cable hoisting system and erection method
CN212582675U (en) Walking pile driver
CN109457618B (en) Cast-in-place construction method for concrete main beam

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13885709

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 13885709

Country of ref document: EP

Kind code of ref document: A1