WO2013065896A1 PCT/KR2011/009070 KR2011009070W WO2013065896A1 WO 2013065896 A1 WO2013065896 A1 WO 2013065896A1 KR 2011009070 W KR2011009070 W KR 2011009070W WO 2013065896 A1 WO2013065896 A1 WO 2013065896A1
Authority
WO
WIPO (PCT)
Prior art keywords
building
house
polyurethane foam
formwork
air
Prior art date
Application number
PCT/KR2011/009070
Other languages
French (fr)
Korean (ko)
Inventor
호진원
Original Assignee
주식회사 에스피씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 에스피씨 filed Critical 주식회사 에스피씨
Publication of WO2013065896A1 publication Critical patent/WO2013065896A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/04Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for structures of spherical, spheroid or similar shape, or for cupola structures of circular or polygonal horizontal or vertical section; Inflatable forms
    • E04G11/045Inflatable forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/167Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with permanent forms made of particular materials, e.g. layered products
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/842Walls made by casting, pouring, or tamping in situ by projecting or otherwise applying hardenable masses to the exterior of a form leaf

Definitions

  • the present invention relates to a building construction method by applying polyurethane, and more specifically, when constructing a wall or a roof of a house or a building, the wall is embedded in a rigid polyurethane foam to be fixed to a floor plate, which will be integrated. Extrude the anchor on the floor plate, connect the reinforcing bar anchor, install the hardware to be the frame of the building, and support the gypsum board, which will be the inner surface of the building, to form the interior space of the building.
  • the rigid polyurethane foam By applying a rigid polyurethane to the appropriate thickness with a spray, the rigid polyurethane foam is cured, the rigid polyurethane foam itself forms the walls and roof body of the building to quickly construct walls and roofs of houses or buildings It relates to a building construction method by applying the foam.
  • the present invention when constructing the walls and roofs of houses or buildings, using a form of air-inflatable material inflates the form of houses or buildings using compressed air, and then sprays the polyurethane thereon It is possible to quickly construct walls and roofs of houses or buildings by removing the shrinkage form outside the polyurethane wall by applying it to the polyurethane, hardening the polyurethane firmly to form a shape, and then extracting air from the expanded form inside the polyurethane. It relates to a building construction method by applying a polyurethane foam.
  • Polyurethane is generally a synthetic compound of resin, fibrous, elasticity which belongs to the organic polymer series made by reacting diisocyanate (an organic compound containing two —NCO functional groups) with a bifunctional compound such as glycol.
  • diisocyanate an organic compound containing two —NCO functional groups
  • glycol a bifunctional compound such as glycol.
  • the most well known polyurethanes are rigid foams used in light structural materials such as elastic foams for decorative fabrics, mattresses and seam for airplane wings.
  • the foamed polyurethane is obtained by reacting an organic compound having a carboxyl group with a diisocyanate such as polyester, and carbon dioxide bubbles generated through this reaction are dispersed throughout the product.
  • a diisocyanate such as polyester
  • the use of polyethers or polyesters with hydroxy groups in the production of polyurethanes can produce elastic fibers or rubbers that are very resistant to ozone attack but weak to the action of acids and alkalis.
  • polyurethane In modern times, the use of polyurethane is used for various purposes from household goods such as shoes and mattresses to high-tech industries such as automobiles and electronics.
  • Rigid Foly-urethane Foam has particularly good thermal insulation performance due to its low thermal conductivity, good compressive strength, good durability, no water absorption, light weight, and fire resistance. It is relatively safe, so it is often used as a building material.
  • the polyurethane is easy to implement the shape to be molded by injecting into a mold, there is an advantage that can be made to the desired shape by spray molding by applying to the target surface by spraying method.
  • the construction of a house is somewhat different depending on the materials of construction and the construction method, but the foundation is made, the frame is built on it, the walls are made, the insulation is insulated, and the electricity and equipment required for the building are constructed. The process of finishing the inside and outside of the house is completed.
  • the present invention is a house in consideration of the heat insulating effect, the durability of the compressive strength, the safety against fire and water absorption due to the non-combustible characteristics of the rigid polyurethane foam (Rigid Foly-urethane Foam) presented above Alternatively, the present invention has been completed by creating a method for constructing a small building.
  • the present invention is to solve the above problems, when constructing a wall or roof of a house or building, to protrude a reinforcing anchor anchored on a rigid polyurethane foam to be integrated into the bottom plate to be fixed to the bottom plate on the bottom plate, After connecting to the reinforcing anchor and installing the hardware to be the frame of the building, support the gypsum board which will be the inner surface of the building to the framed steel to form the interior space of the building, and spray the hard polyurethane outside the gypsum board with the appropriate thickness.
  • Hard polyurethane foam is cured, and the rigid polyurethane foam itself forms the walls of the building and the main body of the building, and the polyurethane foam is applied to the walls and roofs of houses or buildings quickly and to reduce the cost of construction. To provide a construction method through the building.
  • the present invention when constructing the walls and roofs of houses or buildings, using a form of air-inflatable material inflates the form of houses or buildings using compressed air, and then sprays the polyurethane thereon
  • the polyurethane foam is applied to expedite the construction of walls and roofs of houses or buildings by removing air from the swelling formwork inside the polyurethane and removing the contracted form out of the polyurethane walls. To provide a construction method through the building.
  • a feature of the present invention for achieving the above object, by designating the location of the housing or building walls, pillars in the construction location for the construction of a house or building and proceeding the basic construction of the wall pillars using reinforcement and pouring concrete
  • a third step of forming a wall and a roof by spraying and foaming the polyurethane foam When the hard polyurethane foam is cured and the walls and roof of the house or building are completed, the surface of the hard polyurethane foam is trimmed and trimmed.
  • the exterior of the wall is finished with siding and the roof is finished with roof-shaped finish.
  • the interior is characterized in that it provides a building construction method through the polyurethane foam coating comprising a fourth process to finish the construction by painting or wallpaper.
  • the wall of the house or building, the bottom plate is attached to the floor and the upper part of the floor or the housing or building walls, a plurality of reinforcing bars and metal or wood Using a truss assembled with a long span that supports a large external load with a triangular or pentagonal linear member, it is firmly connected to the location of the walls and columns supported by the reinforcement to build the foundation of the house or building. It is preferably configured to finish.
  • the bottom plate is preferably made of a material of wood or iron plate to provide mobility after completion of the house or building.
  • the present invention can build a practical house such as a farm house or a weekend cottage at a relatively low price than the general construction method, in particular in the case of housing for underdeveloped countries or housing for refugees in disaster or conflict areas It can provide short-term and significantly reduced construction costs.
  • the present invention is to set the amount of polyurethane to be applied according to the type of house or building to ensure that the polyurethane is hardened to have a shape that can be installed in various forms of houses or buildings according to the user's choice and insulation of polyurethane foam It is possible to quickly provide a building with a water and waterproof effect.
  • the present invention is to apply a polyurethane spray on the air inflated to the wall and the roof of the desired thickness to form a rigid polyurethane foam, and then remove the form after curing the building having a heat insulation and waterproof effect of the polyurethane foam Can be provided quickly.
  • FIG. 1 is a flow chart showing a process of building construction method by applying polyurethane foam according to an embodiment of the present invention.
  • FIG. 2 is a view showing a state in which the construction of the foundation concrete deck and reinforcement anchor of the building as an embodiment of the present invention
  • FIG. 3 is a view illustrating a state in which the formwork inflated with air after the process of FIG.
  • FIG. 4 is a view showing a state in which the entire formwork surface after the process of Figure 3 as a gypsum board construction as an embodiment of the present invention
  • FIG. 5 is a view showing a state fixed to the wire mesh to fix the wall or roof of the building after the process of Figure 4 as an embodiment of the present invention
  • FIG. 6 is a view showing a state in which windows, doors, etc. of the building after the process of Figure 5 installed in one embodiment of the present invention
  • FIG. 7 is a view showing a state in which the internal electrical wiring and piping construction of the building after the process of Figure 6 as an embodiment of the present invention
  • 8a to 8c is a view showing a process of spraying a polyurethane plate after the process of FIG.
  • 9a to 9b is a view showing a state in which the building is completed by removing the internal formwork in accordance with the curing after polyurethane coating
  • FIG. 10 is a flowchart showing another process of the building construction method by applying a polyurethane foam according to another embodiment of the present invention.
  • FIG. 11 is a flow chart showing a process of building construction method by applying polyurethane foam according to an embodiment of the present invention.
  • 12a to 12b is a view showing a state of foundation work as a concrete floor slab and reinforcement of the building as an embodiment of the present invention
  • FIG. 13 is a view illustrating a state in which a gypsum board is installed inside a building after the process of FIG. 12 according to one embodiment of the present invention
  • FIG. 14 is a view illustrating a state in which windows, doors, and the like of a building are installed after the process of FIG. 13 according to one embodiment of the present invention
  • FIG. 15 is a view showing a state in which the internal electrical wiring and piping construction of the building after the process of Figure 14 as an embodiment of the present invention
  • 16a to 16c are views showing a process of spraying a polyurethane board after the process of FIG.
  • FIG. 1 is a flow chart showing a process of building construction method by applying polyurethane foam according to an embodiment of the present invention. The construction method will be described based on FIGS. 2 to 9 according to the flowchart.
  • a flat concrete floor to be used should be provided, and the bottom plate 10 is made by pouring concrete of a suitable thickness at a location to be constructed. Position the house or building wall above this and fix the rebar anchor 20 by drawing the rebar at an appropriate height to the centerline of the wall (see step S20).
  • the bottom plate may be made of a material of wood or steel plate to move the house or building to a specific location after the house or building is completed, and to install the rebar anchor by pulling the rebar to the appropriate height as in step 20 Can be.
  • It can be used as a material of the wood and iron plate having a specific thickness of the timber flooring to provide the mobility of the fixed house or building structure and the finished structure of the concrete to the location desired by the user.
  • the reinforcing anchor 20 functions as an anchor for fixing and fixing the house or building constructed in accordance with the present invention so as not to be separated, the reinforcing bar is inserted into the concrete floor plate 10 and the polyurethane wall is not separated from each other It is to avoid.
  • the air formwork 30 having a housing or building shape is placed into the reinforcing anchor 20 (see step S30).
  • the air formwork 30 is a shape to be applied by spraying a polyurethane foam to make the body of the wall or roof of a house or building, made of a material that can be blown by blowing the material of the formwork 30 building If the mold is made in the shape of the building space to be blown and inflated by blowing air with an air compressor, the mold is inflated to the size of the inner space of the building.
  • the inlet opening air into the formwork is located at the door of the building so that it can be easily removed when demolded and removed.
  • the wire mesh reinforcement may be installed so as to be centered on the thickness of the polyurethane wall or roof in consideration of the thickness of the polyurethane to be applied on the formwork to reinforce the strength of the wall or roof to be formed of polyurethane.
  • the reinforcing bar is inserted together with the reinforcing anchor 20 so that the concrete floor plate 10 and the polyurethane wall and the roof are integrated to support and fix the housing or the building so as not to be separated.
  • steel frame or wire mesh can be selectively used according to the characteristics of the building.
  • gypsum board 40 is installed on the outer circumferential surface of the housing or building air formwork 30 is attached to one complete plate or a plurality of gypsum board according to the characteristics of the house or building to complete the entire formwork surface Can be.
  • the window 50 or the door 55 is installed in the upper part of the formwork as shown in FIG. 6 at a position determined according to the use or design of the house or building (see step S60). Or, depending on the purpose of the building electrical wiring 60, and the piping 65 for water and sewage work (see step S70).
  • the window 50 or the door 55 may be selectively carried out after the electrical wiring 60, the piping 65 is made of the process located on the formwork.
  • the polyurethane foam is solidified by spraying and foaming the rigid polyurethane 70 foam with a spray onto a house or building on which an air formwork is installed. And form a roof (see step S80).
  • the chemical reaction is completed after a predetermined time after the application according to the type and amount of the polyol or catalyst to form the rigid polyurethane foam. You can get the roof quickly.
  • the injection of the polyurethane foam can be injected by adjusting the injection amount according to the purpose, characteristics, such as a house or building.
  • step S90 When the hard polyurethane foam applied by the above process is hardened to have strength, the air is removed from the air formwork 30 as shown in FIG. 9A, and the mold is shrunk and then demolded, according to the characteristics of the polyurethane as shown in FIG. 9B. A building with a certain strength and adiabatic waterproofing function required by the building is completed. (See step S90.)
  • step S100 trim the surface sprayed with the rigid polyurethane foam, and the outside of the wall is finished with a siding, etc., and the roof is finished with a roof-shaped finish. Finish the construction by painting or wallpaper.
  • FIG. 10 is a flowchart illustrating another process of the building construction method by applying polyurethane foam according to another embodiment of the present invention, and the air of a house or building shape into the reinforcing anchor 20 in the process of FIG. 1.
  • Position the formwork 30 (see step S130), apply a release agent on the surface of the air formwork 30 to facilitate demolding (see step S140), and considering the thickness of the polyurethane to be constructed in the future as shown in Figure 5 wire mesh (25) proceed with the reinforcement procedure for the entire house or building (see step S150).
  • windows, doors and electrical wiring / piping can be provided, by applying a rigid polyurethane foam, and after curing the air formwork finish finishing can provide a building construction method by applying the polyurethane of the air formwork.
  • the rigid polyurethane foam is applied to the surface of the air formwork 30 without the process of installing the gypsum board 40 of FIG. 1 on the entire surface of the air formwork, and then a release agent is applied to facilitate the detachment. It is possible to selectively provide a building construction through the application.
  • FIG. 11 is a flowchart illustrating a process of a building construction method by applying polyurethane foam according to an embodiment of the present invention, and will be described with reference to FIGS. 12 to 16.
  • a flat concrete floor to be used as a foundation should be provided, and concrete having a suitable thickness is placed at a location to be constructed to make a bottom plate 10 (see step S210).
  • the reinforcing anchor 20 is led to the bottom plate 10 to proceed with the basic construction of the wall column, and the reinforcing anchor 20 )
  • the framework hardware (25) to join the position of the wall, column to finish the basic construction See step S220.
  • the wall supported by the framework hardware 25, etc. by using a truss (strus) assembled a structure having a long span to support a large external load of a triangular or pentagonal of several linear members of metal or wood, It can also be firmly joined to the location of the pillars to complete the foundation work for a house or building.
  • a truss strus
  • the bottom plate 10 is integrally formed by pouring concrete after fixing and supporting the reinforcing anchor 20 and the frame hardware 25 in the position of the building wall, column.
  • the present invention may be a reinforcement procedure by constructing the roof of the house or building with a reinforcing bar or wire mesh as shown in FIG.
  • the reinforcing bar is inserted through the truss, reinforcing bar or wire mesh through the finishing process of the basic construction, and the concrete floor plate 10 and the polyurethane wall and the roof are integrated to fix and support the house or building not to be separated.
  • the bottom plate may be installed by configuring the material of the wood or steel plate to move the house or building to a specific location after the house or building is completed.
  • It can be used as a material of the wood and iron plate having a specific thickness of the timber flooring to provide the mobility of the fixed house or building structure and the finished structure of the concrete to the location desired by the user.
  • the gypsum board 40 to provide the formwork function as shown in Figure 13 on the outer circumferential surface inside the house or building is laid on the entire surface (see step S230).
  • the configuration of the interior of the house or building to be formed after the application of the foam is formed.
  • the gypsum board 40 installed in the interior of the house or building shown in FIG. 13 may be attached to one complete plate or a plurality of gypsum boards according to the characteristics of the house or building to form the entire formwork surface.
  • the window 50 or the door 55 is installed to be positioned above the formwork at a position determined according to the use or design of the house or building.
  • the electrical wiring 65 and piping 60 for water and sewage work according to the purpose of the house or building.
  • the window 50 or the door 55 may be selectively carried out after the electrical wiring 60, the piping 65 is made of the process located on the formwork.
  • the rigid polyurethane foam when applied by spraying, it is cured after a certain period of time after the application according to the type and amount of the polyol or catalyst, etc., which forms the rigid polyurethane foam, and the chemical reaction is completed. It is possible to obtain thick walls and roofs quickly (see step S270).
  • the injection of the polyurethane foam can be injected by adjusting the injection amount according to the purpose, characteristics, such as a house or building.
  • Building construction method by applying the polyurethane coating of the present invention through the above process can reduce the construction cost while having the proper strength and waterproof insulation function required by the house or building can be built quickly above all.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Building Environments (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to a method for constructing a building by applying polyurethane foam. When constructing the walls and roof of a house or a building, a steel rod anchor which is to be embedded integrally into rigid polyurethane foam is protruded above a floor plate in order to fix the walls to the floor plate. After connecting and installing ironwork which is to become the framework of a building to the steel rod anchor, plaster boards which are to become the internal surfaces of the building are supported on the ironwork to form the inner space of the building, rigid polyurethane is applied to a suitable thickness by being sprayed on the outside of the plaster board, and the rigid polyurethane foam is hardened so that the rigid polyurethane foam itself forms the main portions of the walls and roof of the building. Thus, the walls and roof of a house or building can be quickly constructed.

Description

폴리우레탄 폼 도포를 통한 건축물 시공방법Building construction method by applying polyurethane foam
본 발명은 폴리우레탄 도포를 통한 건축물 시공방법에 관한 것으로, 보다 구체적으로는 주택 또는 건축물의 벽 및 지붕을 시공할 때, 벽이 바닥판에 고정하기 위하여 경질 폴리우레탄 폼에 매설되어 일체가 될 철근 앵커를 바닥판 위에 돌출 시키고, 그 철근 앵커에 연결하여 건물의 골조가 될 철물을 설치한 후, 건축물의 내부표면이 될 석고보드를 골조철물에 지지하여 건물 내부 공간을 형성하고, 석고보드 외부에 경질 폴리우레탄을 스프레이로 적절한 두께로 도포하여, 경질 폴리우레탄 폼이 경화되어 경질 폴리우레탄 폼 자체가 건물의 벽과 지붕 본체를 형성하여 주택 또는 건축물의 벽과 지붕을 신속하게 시공할 수 있는 폴리우레탄 폼 도포를 통한 건축물 시공방법에 관한 것이다.The present invention relates to a building construction method by applying polyurethane, and more specifically, when constructing a wall or a roof of a house or a building, the wall is embedded in a rigid polyurethane foam to be fixed to a floor plate, which will be integrated. Extrude the anchor on the floor plate, connect the reinforcing bar anchor, install the hardware to be the frame of the building, and support the gypsum board, which will be the inner surface of the building, to form the interior space of the building. By applying a rigid polyurethane to the appropriate thickness with a spray, the rigid polyurethane foam is cured, the rigid polyurethane foam itself forms the walls and roof body of the building to quickly construct walls and roofs of houses or buildings It relates to a building construction method by applying the foam.
또한, 본 발명은 주택 또는 건축물의 벽 및 지붕을 시공할 때, 공기로 부풀릴 수 있는 재질의 거푸집을 사용하여 주택 또는 건축물 형상의 거푸집을 압축공기를 이용하여 부풀린 후, 그 위에 폴리우레탄을 스프레이로 도포하고, 폴리우레탄이 단단하게 굳어 형상을 갖게 된 후, 폴리우레탄 내부에서 부풀어 있는 거푸집에서 공기를 빼내어 수축된 거푸집을 폴리우레탄 벽 밖으로 제거함으로서 주택 또는 건축물의 벽과 지붕을 신속하게 시공할 수 있는 폴리우레탄 폼 도포를 통한 건축물 시공방법에 관한 것이다.In addition, the present invention, when constructing the walls and roofs of houses or buildings, using a form of air-inflatable material inflates the form of houses or buildings using compressed air, and then sprays the polyurethane thereon It is possible to quickly construct walls and roofs of houses or buildings by removing the shrinkage form outside the polyurethane wall by applying it to the polyurethane, hardening the polyurethane firmly to form a shape, and then extracting air from the expanded form inside the polyurethane. It relates to a building construction method by applying a polyurethane foam.
일반적으로 폴리우레탄은 디이소시안산염(2개의 ―NCO 작용기를 포함하고 있는 유기화합물)과 글리콜처럼 이(二)작용기 화합물을 반응시켜 만드는 유기 중합체 계열에 속하는 수지·섬유성·탄성의 합성 화합물로서 가장 잘 알려진 폴리우레탄은 장식용 직물, 매트리스 등에 쓰이는 탄성 거품과 비행기 날개용 심과 같은 가벼운 구조재에 쓰이는 견고한 거품이다.Polyurethane is generally a synthetic compound of resin, fibrous, elasticity which belongs to the organic polymer series made by reacting diisocyanate (an organic compound containing two —NCO functional groups) with a bifunctional compound such as glycol. The most well known polyurethanes are rigid foams used in light structural materials such as elastic foams for decorative fabrics, mattresses and seam for airplane wings.
이와같이 거품구조를 갖는 폴리우레탄은 폴리에스테르와 같이 카르복시기를 가진 유기화합물을 디이소시안산염과 반응시켜 얻으며, 이 반응을 통해 발생되는 이산화탄소 기포는 생성물 전체에 걸쳐 분산된다. 폴리우레탄을 제조할 때 히드록시기를 가지고 있는 폴리에테르나 폴리에스테르를 사용하면 오존의 공격에는 매우 잘 견디지만 산과 알칼리의 작용에는 약한 탄성 섬유나 고무를 만들 수 있다.The foamed polyurethane is obtained by reacting an organic compound having a carboxyl group with a diisocyanate such as polyester, and carbon dioxide bubbles generated through this reaction are dispersed throughout the product. The use of polyethers or polyesters with hydroxy groups in the production of polyurethanes can produce elastic fibers or rubbers that are very resistant to ozone attack but weak to the action of acids and alkalis.
현대에 있어서 폴리우레탄의 용도는 신발이나 침대의 매트리스 등의 생활용품으로부터 자동차나 전자제품 등 첨단 산업까지 다양한 용도로 활용되고 있다. In modern times, the use of polyurethane is used for various purposes from household goods such as shoes and mattresses to high-tech industries such as automobiles and electronics.
이 중에서도 특히 경질 폴리우레탄 폼(Rigid Foly-urethane Foam)은 열전도율이 낮아 단열성능이 좋으며, 압축강도가 좋아 내구성이 좋고, 물을 흡수하지 않고, 가벼우며 화재특성상 준 불연성능으로 다른 고분자 물질보다는 화재에 비교적 안전하여 건축자재로서의 활용이 많다.Among them, Rigid Foly-urethane Foam has particularly good thermal insulation performance due to its low thermal conductivity, good compressive strength, good durability, no water absorption, light weight, and fire resistance. It is relatively safe, so it is often used as a building material.
또한 폴리우레탄은 몰드에 주입하여 성형하여 만들고자 하는 형상을 구현하기 쉬우며, 스프레이 방식으로 목적물 표면에 도포하여 발포 성형함으로써 원하는 형상을 만들 수 있는 장점이 있다.In addition, the polyurethane is easy to implement the shape to be molded by injecting into a mold, there is an advantage that can be made to the desired shape by spray molding by applying to the target surface by spraying method.
한편, 일반적으로 주택을 짓기 위해서는 구조체를 구성하는 재질이나 시공하는 공법에 따라 다소 차이가 있으나, 기초를 만들고 그 위에 골조를 세우고 벽을 만든 후 단열을 하고 건물에 필요한 전기 및 설비를 시공하고, 건물의 내 외부를 마감하여 완성되는 과정을 거치게 된다. On the other hand, in general, the construction of a house is somewhat different depending on the materials of construction and the construction method, but the foundation is made, the frame is built on it, the walls are made, the insulation is insulated, and the electricity and equipment required for the building are constructed. The process of finishing the inside and outside of the house is completed.
이러한 공정 중에서도 특히 골조를 세우고 벽을 만드는 일은 건축에 있어서 아주 중요한 공정이 된다. 이 공정에는 대부분 콘크리트와 시멘트 벽돌을 사용하고 있어, 시멘트 모르타르를 사용하여 벽돌을 쌓아올려 벽을 만들거나 또는 목재나 철재로 거푸집을 만들고 콘크리트를 타설하여 콘크리트 벽을 만들게 된다.Among these processes, the construction of the frame and the building of walls are especially important in architecture. Most of the process uses concrete and cement bricks, which use cement mortar to build bricks to form walls, or formwork from wood or steel and cast concrete to make concrete walls.
이후 양생하여 마감하게 되는데 이 공정은 많은 시간과 공기가 소용되는 문제가 있다. 이러한 구조물은 구조물 자체의 자중이 무겁고 따라서 자중을 지지하기 위하여 구조적으로 기둥이나 보가 큰 단면을 가져야 하는 단점도 있다.After curing and finishing, this process has a problem that a lot of time and air is used. Such a structure has a disadvantage in that the weight of the structure itself is heavy and therefore, the pillar or beam must have a large cross section structurally to support the weight.
그리고 골조와 벽이나 지붕이 완성되었다 하더라도 여기에 다시 단열작업 및 방수 작업을 하고 내부 마감공사를 하게 되어, 이 모든 공정을 거치게 되면, 결국에 주택 또는 작은 건축물을 짓는 일은 최소 수개월의 공기와 평당 수백만 원의 비용이 소요되는 문제점이 있다.And even if the frame, wall or roof is finished, it is then insulated, waterproofed, and internally finished. Once all of this is done, eventually building a house or small building is at least several months of air and millions of pyeong. There is a problem that the cost of the original cost.
또한, 최근에는 주택의 경우 목재를 사용하는 목조주택 또는 철골을 사용하는 스틸하우스가 있으나 이 또한 목조나 철골을 세우고 외벽과 지붕을 만들고 단열 방수공사로 마감을 하다 보면 많은 공기와 공사비가 소요된다.In addition, recently, there are wooden houses or steel houses using steel frames in the case of houses, but this also requires a lot of air and construction costs when building wooden or steel frames, making exterior walls and roofs, and finishing with insulation waterproofing.
따라서, 본원발명은 상기에 제시된 경질 폴리우레탄 폼(Rigid Foly-urethane Foam)의 특징인 단열효과, 압축강도의 내구성, 불연성에 따른 화재에 대한 안전성 및 물 흡수성을 방지할 수 있는 특징을 고려하여 집 또는 작은 건축물을 시공할 수 있는 방법을 창안하여 본 발명을 완성하였다.Therefore, the present invention is a house in consideration of the heat insulating effect, the durability of the compressive strength, the safety against fire and water absorption due to the non-combustible characteristics of the rigid polyurethane foam (Rigid Foly-urethane Foam) presented above Alternatively, the present invention has been completed by creating a method for constructing a small building.
본 발명은 상기의 문제점을 해결하기 위한 것으로, 주택 또는 건축물의 벽 및 지붕을 시공할 때, 벽이 바닥판에 고정하기 위하여 경질 폴리우레탄 폼에 매설되어 일체가 될 철근 앵커을 바닥판 위에 돌출 시키고, 그 철근 앵커에 연결하여 건물의 골조가 될 철물을 설치한 후, 건축물의 내부표면이 될 석고보드를 골조철물에 지지하여 건물 내부 공간을 형성하고, 석고보드 외부에 경질 폴리우레탄을 스프레이로 적절한 두께로 도포하여, 경질 폴리우레탄 폼이 경화되어 경질 폴리우레탄 폼 자체가 건물의 벽과 지붕 본체를 형성하여 주택 또는 건축물의 벽과 지붕을 신속하고, 시공에 따른 경비를 절감할 수 있는 폴리우레탄 폼 도포를 통한 건축물 시공방법을 제공하기 위한 것이다.The present invention is to solve the above problems, when constructing a wall or roof of a house or building, to protrude a reinforcing anchor anchored on a rigid polyurethane foam to be integrated into the bottom plate to be fixed to the bottom plate on the bottom plate, After connecting to the reinforcing anchor and installing the hardware to be the frame of the building, support the gypsum board which will be the inner surface of the building to the framed steel to form the interior space of the building, and spray the hard polyurethane outside the gypsum board with the appropriate thickness. Hard polyurethane foam is cured, and the rigid polyurethane foam itself forms the walls of the building and the main body of the building, and the polyurethane foam is applied to the walls and roofs of houses or buildings quickly and to reduce the cost of construction. To provide a construction method through the building.
또한, 본 발명은 주택 또는 건축물의 벽 및 지붕을 시공할 때, 공기로 부풀릴 수 있는 재질의 거푸집을 사용하여 주택 또는 건축물 형상의 거푸집을 압축공기를 이용하여 부풀린 후, 그 위에 폴리우레탄을 스프레이로 도포하고, 폴리우레탄이 단단하게 경화되면 폴리우레탄 내부에서 부풀어 있는 거푸집에서 공기를 빼내어 수축된 거푸집을 폴리우레탄 벽 밖으로 제거함으로서 주택 또는 건축물의 벽과 지붕을 신속하게 시공할 수 있는 폴리우레탄 폼 도포를 통한 건축물 시공방법을 제공하기 위한 것이다.In addition, the present invention, when constructing the walls and roofs of houses or buildings, using a form of air-inflatable material inflates the form of houses or buildings using compressed air, and then sprays the polyurethane thereon When the polyurethane hardens, the polyurethane foam is applied to expedite the construction of walls and roofs of houses or buildings by removing air from the swelling formwork inside the polyurethane and removing the contracted form out of the polyurethane walls. To provide a construction method through the building.
상기의 목적을 달성하기 위한 본 발명의 특징에 따르면, 주택 또는 건축물 신축을 위해 시공위치에 주택 또는 건축물 벽, 기둥의 위치를 지정하고 철근을 이용하여 벽 기둥의 기초공사를 진행하고 콘크리트를 타설하여 주택 또는 건축물의 벽, 기둥이 부설된 바닥판을 구성하고, 철근 또는 와이어메쉬로 주택 또는 건축물의 지붕을 구성하는 보강절차를 통해 기초공사를 마무리하는 제 1 과정; 주택 또는 건축물의 기초공사에 따라 그 내부에 거푸집 기능을 제공하는 석고보드를 표면 전체에 부설하여 고정하는 제 2 과정; 주택 또는 건축물의 용도, 설계에 따라 정해진 위치에 전기배선, 상하수도를 위한 배관, 창호, 문을 거푸집 상부에 위치하도록 설치하고, 기초공사 된 거푸집이 부설된 주택 또는 건축물 위에 경질 폴리우레탄 폼을 스프레이로 분사 발포시켜 폴리우레탄 폼이 굳어 벽체와 지붕을 형성하는 제 3 과정; 및 도포된 경질 폴리우레탄 폼 경화가 되어 주택 또는 건축물의 벽과 지붕이 완성되면, 경질 폴리우레탄 폼을 스프레이한 면을 다듬어 정리하고 벽의 외부는 사이딩의 마감재로, 지붕은 지붕재 형상의 마감재로 마감하고, 내부는 도장이나 벽지로 마감 시공을 제 4 과정을 포함하여 이루어지는 폴리우레탄 폼 도포를 통한 건축물 시공방법을 제공하는 것을 특징으로 한다.According to a feature of the present invention for achieving the above object, by designating the location of the housing or building walls, pillars in the construction location for the construction of a house or building and proceeding the basic construction of the wall pillars using reinforcement and pouring concrete A first process of constructing a floor plate on which a wall or a column of a house or a building is attached, and finishing the foundation work through a reinforcement procedure of constructing a roof of the house or a building by reinforcing steel or wire mesh; A second process of laying and fixing gypsum board on the entire surface to provide formwork therein according to the basic construction of the house or building; Install electrical wiring, pipes for water and sewage, windows and doors in the upper part of the formwork according to the purpose and design of the house or building, and use a rigid polyurethane foam to spray on the house or building where the foundation work is installed. A third step of forming a wall and a roof by spraying and foaming the polyurethane foam; When the hard polyurethane foam is cured and the walls and roof of the house or building are completed, the surface of the hard polyurethane foam is trimmed and trimmed. The exterior of the wall is finished with siding and the roof is finished with roof-shaped finish. And, the interior is characterized in that it provides a building construction method through the polyurethane foam coating comprising a fourth process to finish the construction by painting or wallpaper.
이때, 본 발명의 부가적인 특징에 따르면, 상기 주택 또는 건축물의 벽, 기둥이 부설된 바닥판과 그 바닥판의 상부에 주택 또는 건축물 벽, 기둥의 위치에 구성된 철근과 금속이나 나무로 된 여러 개의 직선부재를 3각형 또는 5각형으로 큰 외부하중을 지지하는 긴 경간을 가진 구조물을 조립한 트러스(truss)을 이용하여 철근으로 지지된 벽, 기둥의 위치에 견고히 이음하여 주택 또는 건축물의 기초공사를 마무리하도록 구성되는 것이 바람직하다.At this time, according to an additional feature of the present invention, the wall of the house or building, the bottom plate is attached to the floor and the upper part of the floor or the housing or building walls, a plurality of reinforcing bars and metal or wood Using a truss assembled with a long span that supports a large external load with a triangular or pentagonal linear member, it is firmly connected to the location of the walls and columns supported by the reinforcement to build the foundation of the house or building. It is preferably configured to finish.
또한, 본 발명의 부가적인 특징에 따르면, 상기 바닥판은 주택 또는 건축물 완성 후 이동성을 제공하기 위해 나무 또는 철판의 재질로 구성되는 것이 바람직하다.In addition, according to an additional feature of the invention, the bottom plate is preferably made of a material of wood or iron plate to provide mobility after completion of the house or building.
본 발명의 실시예에 폴리우레탄 폼 도포를 통한 건축물 시공방법은 주택 또는 건축물의 벽 및 지붕을 시공할 때, 기초, 골조를 세우고 주택 또는 건축물의 내부에 마감재로 석고보드를 지지하여 그 위에 폴리우레탄을 스프레이로 도포하여 발포시켜 경화함으로써 건물의 벽과 지붕의 신속하게 시공함으로써 공사비를 절감할 수 있는 효과를 제공한다.Building construction method by applying the polyurethane foam in the embodiment of the present invention, when constructing the wall or roof of the house or building, the foundation, the frame and the plaster board as a finishing material in the interior of the house or building to support the polyurethane on it It is applied by spraying, foaming and curing to quickly construct the walls and roofs of the building, thus reducing the cost of construction.
또한, 본 발명은 농가주택이나 주말 별장 등 실용성 있는 집을 일반적인 건축방법보다 비교적 저렴한 가격에 건축할 수 있고, 특히 저개발 국가의 주택보급사업이나 재해지역이나 분쟁지역의 난민을 위한 주택의 경우에는 공기가 짧고 공사비가 획기적으로 절감된 주택을 제공할 수 있다.In addition, the present invention can build a practical house such as a farm house or a weekend cottage at a relatively low price than the general construction method, in particular in the case of housing for underdeveloped countries or housing for refugees in disaster or conflict areas It can provide short-term and significantly reduced construction costs.
또한, 본 발명은 주택 또는 건축물의 종류에 따라 도포되는 폴리우레탄 양을 설정하여 폴리우레탄이 단단하게 굳어 형상을 갖게 하여 사용자의 선택에 따라 다양한 형태의 주택 또는 건축물 시공이 가능하고 폴리우레탄 폼의 단열과 방수효과가 있는 건축물을 신속하게 제공할 수 있다.In addition, the present invention is to set the amount of polyurethane to be applied according to the type of house or building to ensure that the polyurethane is hardened to have a shape that can be installed in various forms of houses or buildings according to the user's choice and insulation of polyurethane foam It is possible to quickly provide a building with a water and waterproof effect.
또한, 본 발명은 공기로 부풀린 기푸집에 폴리우레탄을 스프레이를 원하는 두께의 벽과 지붕에 도포하여 경질 폴리우레탄 폼을 조성후, 경화 후 거푸집을 제거함으로써 폴리우레탄 폼의 단열과 방수효과가 있는 건축물을 신속하게 제공할 수 있다.In addition, the present invention is to apply a polyurethane spray on the air inflated to the wall and the roof of the desired thickness to form a rigid polyurethane foam, and then remove the form after curing the building having a heat insulation and waterproof effect of the polyurethane foam Can be provided quickly.
도 1은 본 발명의 일 실시예에 따른 폴리우레탄 폼 도포를 통한 건축물 시공방법의 과정을 도시한 흐름도.1 is a flow chart showing a process of building construction method by applying polyurethane foam according to an embodiment of the present invention.
도 2는 본 발명의 일 실시예로 건축물의 기초 콘크리트 바닥판 및 철근 앵커를 시공한 상태를 도시한 도면2 is a view showing a state in which the construction of the foundation concrete deck and reinforcement anchor of the building as an embodiment of the present invention
도 3은 본 발명의 일 실시예로 도 2의 공정후 공기로 부풀리는 거푸집을 앵커 내부에 위치한 상태를 도시한 도면3 is a view illustrating a state in which the formwork inflated with air after the process of FIG.
도 4는 본 발명의 일 실시예로 도 3의 공정후 거푸집 표면 전체를 석고보드로 시공한 상태를 도시한 도면4 is a view showing a state in which the entire formwork surface after the process of Figure 3 as a gypsum board construction as an embodiment of the present invention
도 5는 본 발명의 일 실시예로 도 4의 공정후 건축물의 벽 또는 지붕을 고정하기 위해 와이어 메쉬로 고정한 상태를 도시한 도면5 is a view showing a state fixed to the wire mesh to fix the wall or roof of the building after the process of Figure 4 as an embodiment of the present invention
도 6은 본 발명의 일 실시예로 도 5의 공정후 건축물의 창호, 문 등을 설치한 상태를 도시한 도면6 is a view showing a state in which windows, doors, etc. of the building after the process of Figure 5 installed in one embodiment of the present invention
도 7은 본 발명의 일 실시예로 도 6의 공정후 건축물의 내부 전기배선 및 배관을 시공한 상태를 도시한 도면7 is a view showing a state in which the internal electrical wiring and piping construction of the building after the process of Figure 6 as an embodiment of the present invention
도 8a 내지 8c는 도 7의 공정후 폴리우레판을 스프레이로 도포하는 공정을 도시한 도면8a to 8c is a view showing a process of spraying a polyurethane plate after the process of FIG.
도 9a 내지 도 9b는 폴리우레탄 도포후 경화에 따라 내부 거푸집을 제거하고 건축물이 완성된 상태를 도시한 도면9a to 9b is a view showing a state in which the building is completed by removing the internal formwork in accordance with the curing after polyurethane coating
도 10은 본 발명의 다른 실시예에 따른 폴리우레탄 폼 도포를 통한 건축물 시공방법의 다른 공정을 도시한 흐름도10 is a flowchart showing another process of the building construction method by applying a polyurethane foam according to another embodiment of the present invention.
도 11은 본 발명의 일 실시예에 따른 폴리우레탄 폼 도포를 통한 건축물 시공방법의 과정을 도시한 흐름도.11 is a flow chart showing a process of building construction method by applying polyurethane foam according to an embodiment of the present invention.
도 12a 내지 도 12b는 본 발명의 일 실시예로 건축물의 기초 콘크리트 바닥판 및 철근으로 기초공사 상태를 도시한 도면12a to 12b is a view showing a state of foundation work as a concrete floor slab and reinforcement of the building as an embodiment of the present invention
도 13은 는 본 발명의 일 실시예로 도 12의 공정 후 건축물 내부에 석고보드로 시공한 상태를 도시한 도면FIG. 13 is a view illustrating a state in which a gypsum board is installed inside a building after the process of FIG. 12 according to one embodiment of the present invention; FIG.
도 14는 본 발명의 일 실시예로 도 13의 공정 후 건축물의 창호, 문 등을 설치한 상태를 도시한 도면14 is a view illustrating a state in which windows, doors, and the like of a building are installed after the process of FIG. 13 according to one embodiment of the present invention;
도 15는 본 발명의 일 실시예로 도 14의 공정 후 건축물의 내부 전기배선 및 배관을 시공한 상태를 도시한 도면15 is a view showing a state in which the internal electrical wiring and piping construction of the building after the process of Figure 14 as an embodiment of the present invention
도 16a 내지 16c는 도 15의 공정후 폴리우레판을 스프레이로 도포하는 공정을 도시한 도면16a to 16c are views showing a process of spraying a polyurethane board after the process of FIG.
이하, 본 발명의 바람직한 실시 예의 상세한 설명은 첨부된 도면들을 참조하여 설명할 것이다. 하기에서 본 발명을 설명함에 있어서, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명을 생략할 것이다.Hereinafter, a detailed description of a preferred embodiment of the present invention will be described with reference to the accompanying drawings. In the following description of the present invention, detailed descriptions of well-known functions or configurations will be omitted when it is deemed that they may unnecessarily obscure the subject matter of the present invention.
도 1은 본 발명의 일 실시예에 따른 폴리우레탄 폼 도포를 통한 건축물 시공방법의 과정을 도시한 흐름도이다. 상기 흐름도에 따라 도 2 내지 도 9를 기초로 시공방법에 대해 설명하고자 한다.1 is a flow chart showing a process of building construction method by applying polyurethane foam according to an embodiment of the present invention. The construction method will be described based on FIGS. 2 to 9 according to the flowchart.
본 발명에 주택 또는 건축물을 신축하기 위해서는 도 2에 도시된 바와 같이 먼저 기초로 사용될 평편한 콘크리트 바닥을 구비하여야 하며, 시공할 위치에 적절한 두께의 콘크리트를 타설하여 바닥판(10)을 만든다.(S10 단계참조) 이 위에 주택 또는 건축물 벽의 위치를 지정하고 그 벽의 중심선에 적절한 높이로 철근을 뽑아서 철근 앵커(20)을 고정한다.(S20 단계참조)In order to construct a house or building in the present invention, as shown in FIG. 2, first, a flat concrete floor to be used should be provided, and the bottom plate 10 is made by pouring concrete of a suitable thickness at a location to be constructed. Position the house or building wall above this and fix the rebar anchor 20 by drawing the rebar at an appropriate height to the centerline of the wall (see step S20).
한편, 상기의 바닥판은 주택 또는 건축물이 완성된 후 주택 또는 건축물을 특정위치로 이동하기 위해 나무 또는 철판의 재질로 구성할 수 있고, 상기 20단계와 같이 적절한 높이로 철근을 뽑아서 철근 앵커를 설치할 수 있다.On the other hand, the bottom plate may be made of a material of wood or steel plate to move the house or building to a specific location after the house or building is completed, and to install the rebar anchor by pulling the rebar to the appropriate height as in step 20 Can be.
이는 콘크리트의 고정된 주택 또는 건축물 구조와 완성된 구조물을 사용자가 원하는 위치로 이동성을 제공하기 위해 바닥판을 목재의 특정 두께를 갖는 나무 및 철판을 재질로 사용할 수 있다.It can be used as a material of the wood and iron plate having a specific thickness of the timber flooring to provide the mobility of the fixed house or building structure and the finished structure of the concrete to the location desired by the user.
상기 철근 앵커(20)는 본 발명에 따라 시공된 주택 또는 건축물이 분리되지 않도록 고정 지지하는 앵커의 기능을 하는데, 철근이 삽입되어 콘크리트 바닥판(10)과 폴리우레탄 벽이 일체가 되어 서로 분리되지 않도록 하는 것이다.The reinforcing anchor 20 functions as an anchor for fixing and fixing the house or building constructed in accordance with the present invention so as not to be separated, the reinforcing bar is inserted into the concrete floor plate 10 and the polyurethane wall is not separated from each other It is to avoid.
이후, 첨부된 도 3과 같이 상기 철근 앵커(20) 안으로 주택 또는 건축물 형상의 공기 거푸집(30)을 위치한다.(S30 단계참조)Thereafter, as shown in FIG. 3, the air formwork 30 having a housing or building shape is placed into the reinforcing anchor 20 (see step S30).
상기 공기 거푸집(30)은 주택 또는 건축물의 벽과 지붕의 본체를 만들 폴리우레탄 폼을 스프레이로 도포할 형상으로, 거푸집(30)의 재질을 공기를 불어 넣어 부풀릴 수 있는 재질을 이용하여 만들되 건축하고자 하는 건물 공간의 형상으로 거푸집을 만들고 공기 압축기로 공기를 불어 넣어 부풀리면 건물의 내부공간 크기로 부풀린 거푸집을 얻을 수 있다. The air formwork 30 is a shape to be applied by spraying a polyurethane foam to make the body of the wall or roof of a house or building, made of a material that can be blown by blowing the material of the formwork 30 building If the mold is made in the shape of the building space to be blown and inflated by blowing air with an air compressor, the mold is inflated to the size of the inner space of the building.
이때 거푸집으로 공기가 들어가는 주입구는 건물의 문에 위치하여 탈형하여 제거할 때 손쉽게 제거할 수 있게 한다. At this time, the inlet opening air into the formwork is located at the door of the building so that it can be easily removed when demolded and removed.
상기와 같이 설치된 주택 또는 건축물 공기 거푸집(30)의 외주면에 도 4와 같이 석고보드(40)를 부설하여 거푸집 표면 전체를 시공한 후, 향후 시공될 폴리우레탄의 두께를 고려하여 도 5와 같이 와이어메쉬(25)로 주택 또는 건축물 전체를 보강절차를 진행한다.(S50 단계참조)After laying the gypsum board 40 as shown in FIG. 4 on the outer circumferential surface of the house or building air formwork 30 installed as described above, the entire surface of the formwork is constructed, and in consideration of the thickness of the polyurethane to be constructed in the future, as shown in FIG. 5. Reinforce the entire house or building with the mesh (25) (see step S50).
이때, 와이어메쉬 보강은 거푸집 위에 도포 될 폴리우레탄의 두께를 고려하여 폴리우레탄 벽이나 지붕의 두께에 중앙에 오도록 설치하여 폴리우레탄으로 형성될 벽이나 지붕의 강도를 보강할 수 있다. At this time, the wire mesh reinforcement may be installed so as to be centered on the thickness of the polyurethane wall or roof in consideration of the thickness of the polyurethane to be applied on the formwork to reinforce the strength of the wall or roof to be formed of polyurethane.
상기 와이어메쉬(25) 보강 작업시 상기 철근 앵커(20)와 함께 고정함으로써 철근이 삽입되어 콘크리트 바닥판(10)과 폴리우레탄 벽 및 지붕이 일체가 되어 주택 또는 건축물이 분리되지 않도록 고정 지지하게 된다.When the wire mesh 25 is reinforced, the reinforcing bar is inserted together with the reinforcing anchor 20 so that the concrete floor plate 10 and the polyurethane wall and the roof are integrated to support and fix the housing or the building so as not to be separated. .
또한, 와이어메쉬(25) 보강을 위해서 철골이나 철망 등을 건축물의 특징에 따라 선택적으로 사용할 수 있다.In addition, for reinforcing the wire mesh 25, steel frame or wire mesh can be selectively used according to the characteristics of the building.
한편, 첨부된 도 4에서 주택 또는 건축물 공기 거푸집(30)의 외주면에 부설되는 석고보드(40)는 주택 또는 건축물의 특성에 따라 1개의 완판 또는 다수개의 석고보드를 부착하여 거푸집 표면 전체를 시공할 수 있다.On the other hand, in the accompanying Figure 4 gypsum board 40 is installed on the outer circumferential surface of the housing or building air formwork 30 is attached to one complete plate or a plurality of gypsum board according to the characteristics of the house or building to complete the entire formwork surface Can be.
상기 와이어메쉬 보강작업 후 주택 또는 건축물의 용도, 설계에 따라 정해진 위치에 도 6과 같이 창호(50) 또는 문(55)을 거푸집 상부에 위치하도록 설치하고, (S60 단계참조) 도 7과 같이 주택 또는 건축물의 용도에 따라 전기배선(60), 및 상하수도를 위한 배관(65) 작업을 하게 된다.(S70 단계참조)After the wire mesh reinforcement work, the window 50 or the door 55 is installed in the upper part of the formwork as shown in FIG. 6 at a position determined according to the use or design of the house or building (see step S60). Or, depending on the purpose of the building electrical wiring 60, and the piping 65 for water and sewage work (see step S70).
한편, 상기 창호(50) 또는 문(55)을 거푸집 상부에 위치하는 공정을 전기배선(60), 배관(65)이 이루어진 후 선택적으로 실시할 수 있다.On the other hand, the window 50 or the door 55 may be selectively carried out after the electrical wiring 60, the piping 65 is made of the process located on the formwork.
상기의 일련의 공정이 마무리된 후 첨부된 도 8a 내지 도 8c에 도시된 바와 같이 공기 거푸집이 부설된 주택 또는 건축물 위에 경질 폴리우레탄(70) 폼을 스프레이로 분사하여 발포시켜 폴리우레탄 폼이 굳어 벽체와 지붕을 형성하게 된다.(S80 단계참조)After completion of the above series of processes, as shown in FIGS. 8A to 8C, the polyurethane foam is solidified by spraying and foaming the rigid polyurethane 70 foam with a spray onto a house or building on which an air formwork is installed. And form a roof (see step S80).
상기에 의해 경질 폴리우레탄 폼을 스프레이로 도포할 경우, 경질 폴리우레탄 폼을 조성하는 폴리올이나 촉매 등의 물질의 종류와 첨가량에 따라 도포 후 일정시간이 경과하면 화학반응이 완료되어 원하는 두께의 벽과 지붕을 신속하게 얻을 수 있다. According to the above, when the rigid polyurethane foam is applied by spraying, the chemical reaction is completed after a predetermined time after the application according to the type and amount of the polyol or catalyst to form the rigid polyurethane foam. You can get the roof quickly.
이때, 폴리우레탄 폼의 분사는 주택 또는 건축물 등의 그 목적, 특징에 따라 분사량을 조절하여 분사할 수 있다.At this time, the injection of the polyurethane foam can be injected by adjusting the injection amount according to the purpose, characteristics, such as a house or building.
상기 과정에 의해 도포된 경질 폴리우레탄 폼 경화가 되어 강도를 갖게 되면 도 9a와 같이 공기 거푸집(30)에 공기를 빼내어 거푸집을 수축한 후 탈형하면, 도 9b와 같이 폴리우레탄의 특징에 따라 주택 또는 건축물이 요구하는 일정 강도와 단열 방수기능을 가지는 건축물이 완성된다.(S90 단계참조)When the hard polyurethane foam applied by the above process is hardened to have strength, the air is removed from the air formwork 30 as shown in FIG. 9A, and the mold is shrunk and then demolded, according to the characteristics of the polyurethane as shown in FIG. 9B. A building with a certain strength and adiabatic waterproofing function required by the building is completed. (See step S90.)
즉, 상기 공기 거푸집에 공기를 배기할 때, 공기압축기를 반대로 돌려 거푸집에 바람을 뽑아서 거푸집이 탈형되도록 수축되고, 수축된 거푸집은 공기의 주입구가 설치된 건물의 문을 통해서 제거된다. 이 거푸집은 같은 방법으로 재사용할 수 있다.That is, when the air is exhausted to the air formwork, the air compressor is rotated in reverse to draw the wind to the formwork to shrink the formwork, the contracted formwork is removed through the door of the building in which the air inlet is installed. This formwork can be reused in the same way.
상기의 공정에 의해 주택 또는 건축물의 벽과 지붕이 완성되면, 경질 폴리우레탄 폼을 스프레이한 면을 다듬어 정리하고 벽의 외부는 사이딩 등의 마감재로, 지붕은 지붕재 형상의 마감재로 마감하고, 내부는 도장이나 벽지 등으로 마감 시공한다.(S100 단계참조)When the walls and the roof of the house or building are completed by the above process, trim the surface sprayed with the rigid polyurethane foam, and the outside of the wall is finished with a siding, etc., and the roof is finished with a roof-shaped finish. Finish the construction by painting or wallpaper. (See step S100)
한편, 첨부된 도 10은 본 발명의 다른 실시예에 따른 폴리우레탄 폼 도포를 통한 건축물 시공방법의 다른 공정을 도시한 흐름도로서 상기 도 1의 공정에서 철근 앵커(20) 안으로 주택 또는 건축물 형상의 공기 거푸집(30)을 위치하고(S130 단계참조), 공기 거푸집(30) 표면에 탈형을 쉽게 하기 위해 이형제를 도포하고(S140 단계참조), 향후 시공될 폴리우레탄의 두께를 고려하여 도 5와 같이 와이어메쉬(25)로 주택 또는 건축물 전체를 보강절차를 진행한다.(S150 단계참조)Meanwhile, FIG. 10 is a flowchart illustrating another process of the building construction method by applying polyurethane foam according to another embodiment of the present invention, and the air of a house or building shape into the reinforcing anchor 20 in the process of FIG. 1. Position the formwork 30 (see step S130), apply a release agent on the surface of the air formwork 30 to facilitate demolding (see step S140), and considering the thickness of the polyurethane to be constructed in the future as shown in Figure 5 wire mesh (25) proceed with the reinforcement procedure for the entire house or building (see step S150).
이후, 창호, 문 및 전기배선/배관을 시공하고 경질 폴리우레탄 폼을 도포하고 경화후 공기 거푸집 제거 마감 시공함으로써 공기 거푸집의 폴리우레탄 도포를 통한 건축물 시공방법을 제공할 수 있다.Thereafter, windows, doors and electrical wiring / piping can be provided, by applying a rigid polyurethane foam, and after curing the air formwork finish finishing can provide a building construction method by applying the polyurethane of the air formwork.
즉, 도 1의 석고보드(40)를 공기 거푸집 전체 표면에 설치하는 공정없이 공기 거푸집(30) 표면에 경질 폴리우레탄 폼이 도포된 후 탈착을 용이하게 하기 위해 이형제를 도포하여 공기 거푸집의 폴리우레탄 도포를 통한 건축물 시공을 선택적으로 제공할 수 있다.That is, the rigid polyurethane foam is applied to the surface of the air formwork 30 without the process of installing the gypsum board 40 of FIG. 1 on the entire surface of the air formwork, and then a release agent is applied to facilitate the detachment. It is possible to selectively provide a building construction through the application.
또한, 도 11은 본 발명의 일 실시예에 따른 폴리우레탄 폼 도포를 통한 건축물 시공방법의 과정을 도시한 흐름도로서 도 12 내지 도 16을 참조하여 그 시공방법에 대해 설명하고자 한다.In addition, FIG. 11 is a flowchart illustrating a process of a building construction method by applying polyurethane foam according to an embodiment of the present invention, and will be described with reference to FIGS. 12 to 16.
먼저, 도 12에 도시된 바와 같이 먼저 기초로 사용될 평편한 콘크리트 바닥을 구비하여야 하며, 시공할 위치에 적절한 두께의 콘크리트를 타설하여 바닥판(10)을 만든다.(S210 단계참조) 이 위에 주택 또는 건축물 벽, 기둥의 위치를 지정하여 벽, 기둥이 바닥판(10)에 고정하기 위해 철근 앵커(20)을 바닥판(10)에 도출시켜 벽 기둥의 기초공사를 진행하고, 그 철근 앵커(20)에 골조 철물(25)을 설치하여 벽, 기둥의 위치에 이음하여 기초공사를 마무리한다.(S220 단계참조)First, as shown in FIG. 12, first, a flat concrete floor to be used as a foundation should be provided, and concrete having a suitable thickness is placed at a location to be constructed to make a bottom plate 10 (see step S210). In order to fix the wall and column to the bottom plate 10 by designating the position of the building wall and the column, the reinforcing anchor 20 is led to the bottom plate 10 to proceed with the basic construction of the wall column, and the reinforcing anchor 20 ) To install the framework hardware (25) to join the position of the wall, column to finish the basic construction. (See step S220)
이때, 금속이나 나무로 된 여려 개의 직선부재를 3각형 또는 5각형으로 큰 외부하중을 지지하는 긴 경간을 가진 구조물을 조립한 트러스(truss)을 이용하여 골조 철물(25) 등으로 지지된 벽, 기둥의 위치에 견고히 이음하여 주택 또는 건축물의 기초공사를 마무리할 수도 있다.At this time, the wall supported by the framework hardware 25, etc. by using a truss (strus) assembled a structure having a long span to support a large external load of a triangular or pentagonal of several linear members of metal or wood, It can also be firmly joined to the location of the pillars to complete the foundation work for a house or building.
상기의 바닥판(10)은 건축물 벽, 기둥의 위치에 철근 앵커(20) 및 골조 철물(25)과 고정 지지한 후 콘크리트를 타설하여 일체로 구성된다.The bottom plate 10 is integrally formed by pouring concrete after fixing and supporting the reinforcing anchor 20 and the frame hardware 25 in the position of the building wall, column.
또한, 본 발명은 도 12a의 철근 등을 이용해 주택 또는 건축물의 벽, 기둥 등의 기초공사후 도 12b에서 제시된 바와 같이 철근 또는 와이어메쉬로 주택 또는 건축물의 지붕을 구성하여 보강절차를 진행할 수도 있다.In addition, the present invention may be a reinforcement procedure by constructing the roof of the house or building with a reinforcing bar or wire mesh as shown in FIG.
상기 트러스, 철근 또는 와이어메쉬를 통해 기초공사 마무리 공정을 통해 철근이 삽입되어 콘크리트 바닥판(10)과 폴리우레탄 벽 및 지붕이 일체가 되어 주택 또는 건축물이 분리되지 않도록 고정 지지하게 된다.The reinforcing bar is inserted through the truss, reinforcing bar or wire mesh through the finishing process of the basic construction, and the concrete floor plate 10 and the polyurethane wall and the roof are integrated to fix and support the house or building not to be separated.
한편, 상기의 바닥판은 주택 또는 건축물이 완성된 후 주택 또는 건축물을 특정위치로 이동하기 위해 나무 또는 철판의 재질로 구성하여 설치할 수 있다.On the other hand, the bottom plate may be installed by configuring the material of the wood or steel plate to move the house or building to a specific location after the house or building is completed.
이는 콘크리트의 고정된 주택 또는 건축물 구조와 완성된 구조물을 사용자가 원하는 위치로 이동성을 제공하기 위해 바닥판을 목재의 특정 두께를 갖는 나무 및 철판을 재질로 사용할 수 있다.It can be used as a material of the wood and iron plate having a specific thickness of the timber flooring to provide the mobility of the fixed house or building structure and the finished structure of the concrete to the location desired by the user.
상기와 같이 설치된 주택 또는 건축물의 기초공사에 따라 주택 또는 건축물 내부의 외주면에 도 13과 같이 거푸집 기능을 제공하는 석고보드(40)를 표면 전체에 부설한다.(S230 단계 참조) 향후 시공될 폴리우레탄 폼의 도포 후 형성될 주택 또는 건축물의 내부의 구성이 형성되는 것이다.In accordance with the basic construction of the house or building installed as described above, the gypsum board 40 to provide the formwork function as shown in Figure 13 on the outer circumferential surface inside the house or building is laid on the entire surface (see step S230). The configuration of the interior of the house or building to be formed after the application of the foam is formed.
상기의 도 13에 제시된 주택 또는 건축물의 내부에 부설되는 석고보드(40)는 주택 또는 건축물의 특성에 따라 1개의 완판 또는 다수개의 석고보드를 부착하여 거푸집 표면 전체를 시공할 수 있다.The gypsum board 40 installed in the interior of the house or building shown in FIG. 13 may be attached to one complete plate or a plurality of gypsum boards according to the characteristics of the house or building to form the entire formwork surface.
이후, 상기의 석고보드(40)을 통해 거푸집 표면 전체 시공완료 후 주택 또는 건축물의 용도, 설계에 따라 정해진 위치에 도 14와 같이 창호(50) 또는 문(55)을 거푸집 상부에 위치하도록 설치하고,(S240 단계참조) 도 15과 같이 주택 또는 건축물의 용도에 따라 전기배선(65), 및 상하수도를 위한 배관(60) 작업을 하게 된다.(S250 단계참조)Subsequently, after completion of the entire formwork surface through the gypsum board 40, the window 50 or the door 55 is installed to be positioned above the formwork at a position determined according to the use or design of the house or building. (See step S240) As shown in FIG. 15, the electrical wiring 65 and piping 60 for water and sewage work according to the purpose of the house or building. (See step S250)
한편, 상기 창호(50) 또는 문(55)을 거푸집 상부에 위치하는 공정을 전기배선(60), 배관(65)이 이루어진 후 선택적으로 실시할 수 있다.On the other hand, the window 50 or the door 55 may be selectively carried out after the electrical wiring 60, the piping 65 is made of the process located on the formwork.
상기의 일련의 공정이 마무리된 후 첨부된 도 16a 내지 도 16c에 도시된 바와 같이 거푸집이 부설된 주택 또는 건축물 위에 경질 폴리우레탄(70) 폼을 스프레이로 분사하여 발포시켜 폴리우레탄 폼이 굳어 벽체와 지붕을 형성하게 된다.(S260 단계 참조)After completion of the above series of processes, as shown in Figures 16a to 16c attached to the housing or building on which the formwork is sprayed by spraying a rigid polyurethane (70) foam by spraying and foaming the polyurethane foam and the wall and A roof will be formed (see step S260).
상기에 의해 경질 폴리우레탄 폼을 스프레이로 도포할 경우, 경질 폴리우레탄 폼을 조성하는 폴리올이나 촉매 등의 물질의 종류와 첨가량에 따라 도포 후 일정시간이 경과하면 경화되고, 그 화학반응이 완료되어 원하는 두께의 벽과 지붕을 신속하게 얻을 수 있다.(S270 단계참조)According to the above, when the rigid polyurethane foam is applied by spraying, it is cured after a certain period of time after the application according to the type and amount of the polyol or catalyst, etc., which forms the rigid polyurethane foam, and the chemical reaction is completed. It is possible to obtain thick walls and roofs quickly (see step S270).
이때, 폴리우레탄 폼의 분사는 주택 또는 건축물 등의 그 목적, 특징에 따라 분사량을 조절하여 분사할 수 있다.At this time, the injection of the polyurethane foam can be injected by adjusting the injection amount according to the purpose, characteristics, such as a house or building.
상기 과정에 의해 도포된 경질 폴리우레탄 폼이 경화가 되어 강도를 갖게 되면 도 16c와 같이 폴리우레탄의 특징에 따라 주택 또는 건축물이 요구하는 일정 강도와 단열 방수기능을 가지는 건축물이 완성된다.When the rigid polyurethane foam applied by the above process is hardened to have strength, a building having a certain strength and heat insulation waterproof function required by a house or a building is completed according to the characteristics of the polyurethane as shown in FIG. 16C.
상기의 공정에 의해 주택 또는 건축물의 벽과 지붕이 완성되면, 경질 폴리우레탄 폼을 스프레이한 면을 다듬어 정리하고 벽의 외부는 사이딩 등의 마감재로, 지붕은 지붕재 형상의 마감재로 마감하고, 내부는 도장이나 벽지 등으로 마감 시공한다.(S280 단계참조)When the walls and the roof of the house or building are completed by the above process, trim the surface sprayed with the rigid polyurethane foam, and the outside of the wall is finished with a siding, etc., and the roof is finished with a roof-shaped finish. Finish the construction by painting or wallpaper. (See step S280)
상기의 공정을 통해 본 발명의 폴리우레탄 도포를 통한 건축물 시공방법은 주택 또는 건축물이 요구하는 적절한 강도와 단열 방수기능을 가지면서도 공사비를 절감할 수 있고 무엇보다도 신속하게 건축할 수 있다.Building construction method by applying the polyurethane coating of the present invention through the above process can reduce the construction cost while having the proper strength and waterproof insulation function required by the house or building can be built quickly above all.

Claims (8)

  1. 주택 또는 건축물의 내부공간 형상을 갖도록 공기로 부풀릴 수 있는 재질의 공기 거푸집을 시공하고자 하는 주택 또는 건축물 공간 형상의 거푸집을 압축공기를 이용하여 부풀린 후, 그 위에 경질 폴리우레탄 폼을 스프레이로 분사하여 일정 두께의 벽과 지붕을 형성하고 폴리우레탄이 단단하게 경화된 후 거푸집에 공기를 빼내어 수축된 공기 거푸집을 폴리우레탄 벽 밖으로 탈형하여 주택 또는 건축물의 강도와 단열 방수기능을 가지며 공사비를 절감할 수 있도록 구성된 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법     After inflating the formwork of the house or building space to be constructed with the material that can be inflated with air to have the shape of the inside space of the house or building using compressed air, spray the hard polyurethane foam on it Form a wall and roof of a certain thickness and harden the polyurethane, and then blow out the air in the formwork to demold the contracted air formwork out of the polyurethane wall so that the house or building can have the strength and waterproof insulation and reduce the construction cost. Building construction method by applying polyurethane foam, characterized in that configured
  2. 주택 또는 건축물 신축을 위해 시공위치에 콘크리트를 타설하여 바닥판을 구성하고, 그 상부에 주택 또는 건축물 벽의 위치를 지정하고 그 벽의 중심선에 일정 높이의 철근앵커를 고정하는 제 1 과정;A first step of constructing a floor plate by placing concrete at a construction location for new construction of a house or a building, specifying a location of a wall of a house or a building at an upper part thereof, and fixing a reinforcement anchor having a predetermined height at a center line of the wall;
    주택 또는 건축물의 내부공간 형상을 갖도록 공기로 부풀릴 수 있는 재질의 공기 거푸집을 시공하고자 하는 주택 또는 건축물 공간 형상의 거푸집을 압축공기를 이용하여 부풀린 후 철근앵커 안으로 공기 거푸집을 위치하는 제 2 과정;A second step of placing the air formwork into the reinforcing anchors after inflating the formwork of the form of the house or building space to be constructed with air that can be inflated with air to have an internal space shape of the house or building using compressed air;
    주택 또는 건축물 내부공간 형상을 갖는 공기 거푸집의 외주면에 석고보드를 부설하여 거푸집 표면 전체를 시공하고, 와이어메쉬로 주택 또는 건축물 전체의 보강절차를 진행하는 제 3 과정; A third process of laying the gypsum board on the outer circumferential surface of the air formwork having the internal space of the house or the building to construct the entire formwork surface, and to perform the reinforcement procedure of the whole house or the building with a wire mesh;
    와이이메쉬 보강작업 후 주택 또는 건축물의 용도, 설계에 따라 정해진 위치에 전기배선, 상하수도를 위한 배관, 창호, 문을 거푸집 상부에 위치하도록 설치하고, 공기 거푸집이 부설된 주택 또는 건축물 위에 경질 폴리우레탄 폼을 스프레이로 분사 발포시켜 폴리우레탄 폼이 굳어 벽체와 지붕을 형성하는 제 4 과정; 및After Waimesh reinforcement work, install electrical wiring, pipes for water and sewage, windows and doors at the top of the formwork according to the purpose and design of the house or building, and install rigid polyurethane foam on the house or building where the formwork is installed. Spraying and foaming with a spray to form a polyurethane foam to harden the polyurethane foam; And
    도포된 경질 폴리우레탄 폼 경화가 되어 강도를 갖게 되면 공기 거푸집에 공기를 빼내어 거푸집이 탈형되도록 수축되고, 수축된 거푸집은 공기의 주입구가 설치된 건물의 문을 통해서 제거하는 제 5 과정;를 포함하여 이루어지는 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법.When the applied hard polyurethane foam is hardened to have strength, the air is removed from the air formwork to shrink the formwork, and the contracted form is removed through the door of the building in which the air inlet is installed; Building construction method by applying a polyurethane foam, characterized in that.
  3. 주택 또는 건축물 신축을 위해 시공위치에 콘크리트를 타설하여 바닥판을 구성하고, 그 상부에 주택 또는 건축물 벽의 위치를 지정하고 그 벽의 중심선에 일정 높이의 철근앵커을 고정하는 제 1 과정;A first step of constructing a bottom plate by placing concrete at a construction location for new construction of a house or building, designating a location of a wall of a house or building at an upper part thereof, and fixing a reinforcement anchor having a predetermined height at a center line of the wall;
    주택 또는 건축물의 내부공간 형상을 갖도록 공기로 부풀릴 수 있는 재질의 공기 거푸집을 시공하고자 하는 주택 또는 건축물 공간 형상의 거푸집을 압축공기를 이용하여 부풀린 후 철근 앵커 안으로 공기 거푸집을 위치하는 제 2 과정;A second step of placing the air formwork into the reinforcing bar anchor after inflating the formwork of the form of the house or building space to be constructed with air that can be inflated with air to have an internal space shape of the house or building using compressed air;
    주택 또는 건축물 내부공간 형상을 갖는 공기 거푸집 전체 표면에 폴리우레탄 분사에 따라 거푸집 탈형을 용이하게 하는 이형제를 도포하는 제 3 과정;A third process of applying a release agent that facilitates the mold demoulding upon spraying polyurethane on the entire surface of the air formwork having a shape of a space inside a house or a building;
    와이이메쉬 보강작업 후 주택 또는 건축물의 용도, 설계에 따라 정해진 위치에 전기배선, 상하수도를 위한 배관, 창호, 문을 거푸집 상부에 위치하도록 설치하고, 공기 거푸집이 부설된 주택 또는 건축물 위에 경질 폴리우레탄 폼을 스프레이로 분사 발포시켜 폴리우레탄 폼이 굳어 벽체와 지붕을 형성하는 제 4 과정; 및After Waimesh reinforcement work, install electrical wiring, pipes for water and sewage, windows and doors at the top of the formwork according to the purpose and design of the house or building, and install rigid polyurethane foam on the house or building where the formwork is installed. Spraying and foaming with a spray to form a polyurethane foam to harden the polyurethane foam; And
    도포된 경질 폴리우레탄 폼 경화가 되어 강도를 갖게 되면 공기 거푸집에 공기를 빼내어 거푸집이 탈형되도록 수축되고, 수축된 거푸집은 공기의 주입구가 설치된 건물의 문을 통해서 제거하는 제 5 과정을 포함하여 이루어지는 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법.When the hard polyurethane foam applied is hardened to have strength, the air is drawn out to the air formwork, and the formwork is shrunk so that the formwork is demolded. Building construction method by applying polyurethane foam characterized in that.
  4. 제 2 항 또는 제 3 항 중 어느 한 항에 있어서,The method according to claim 2 or 3,
    제 5 과정이 이루어진 후, 주택 또는 건축물의 벽과 지붕이 완성되면, 경질 폴리우레탄 폼을 스프레이한 면을 다듬어 정리하고 벽의 외부는 사이딩의 마감재로, 지붕은 지붕재 형상의 마감재로 마감하고, 내부는 도장이나 벽지로 마감 시공을 제 6 과정을 더 포함하여 구성되는 것을 특징으로 하는 공기 거푸집의 폴리우레탄 폼 도포를 통한 건축물 시공방법.After the fifth process is completed, when the walls and roof of the house or building are finished, trim the surface sprayed with rigid polyurethane foam, the exterior of the wall is finished with siding, the roof is finished with roof-shaped finish, and the interior is The building construction method by applying a polyurethane foam of the air formwork, characterized in that further comprises a sixth process of the finishing construction by painting or wallpaper.
  5. 제 2 항 또는 제 3 항 중 어느 한 항에 있어서,The method according to claim 2 or 3,
    상기 와이어메쉬 보강 작업시 상기 철근 앵커와 함께 고정함으로써 철근이 삽입되어 콘크리트 바닥판과 폴리우레탄 벽 및 지붕이 일체가 되어 주택 또는 건축물이 분리되지 않도록 고정 지지하도록 하고, When the wire mesh reinforcement work is secured together with the reinforcing anchor, the reinforcing bar is inserted so that the concrete floor plate, the polyurethane wall and the roof are integrated so as to be fixed and supported so that the house or the building is not separated.
    상기 와이어메쉬 보강을 위해서 주택 또는 건축물의 특징에 따라 철골이나 철망을 선택적으로 사용하고, Steel wire or wire mesh is selectively used according to the characteristics of a house or a building to reinforce the wire mesh,
    거푸집 위에 도포 될 폴리우레탄의 두께를 고려하여 폴리우레탄 벽이나 지붕의 두께에 중앙에 오도록 설치하여 폴리우레탄으로 형성될 벽이나 지붕의 강도를 보강할 수 있도록 구성된 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법.In consideration of the thickness of the polyurethane to be applied on the formwork to be installed in the center of the thickness of the polyurethane wall or roof through the polyurethane foam coating, characterized in that configured to reinforce the strength of the wall or roof to be formed of polyurethane Building construction method.
  6. 주택 또는 건축물 신축을 위해 시공위치에 주택 또는 건축물 벽, 기둥의 위치를 지정하고 철근을 이용하여 벽 기둥의 기초공사를 진행하고 콘크리트를 타설하여 주택 또는 건축물의 벽, 기둥이 부설된 바닥판을 구성하고, 철근 앵커, 골조 철물 또는 와이어메쉬로 주택 또는 건축물의 지붕을 구성하는 보강절차를 통해 기초공사를 마무리하는 제 1 과정;For the construction of a new house or building, designate the location of the house or building wall and column at the construction site, and proceed with the foundation work of the wall column using reinforcing bars, and cast concrete to construct the floor plate with the wall or column of the house or building. And a first process of finishing the basic construction through reinforcement procedures constituting the roof of the house or building with reinforcing anchors, framework hardware or wire mesh;
    주택 또는 건축물의 기초공사에 따라 그 내부에 거푸집 기능을 제공하는 석고보드를 표면 전체에 부설하여 고정하는 제 2 과정;A second process of laying and fixing gypsum board on the entire surface to provide formwork therein according to the basic construction of the house or building;
    주택 또는 건축물의 용도, 설계에 따라 정해진 위치에 전기배선, 상하수도를 위한 배관, 창호, 문을 거푸집 상부에 위치하도록 설치하고, 기초공사 된 거푸집이 부설된 주택 또는 건축물 위에 경질 폴리우레탄 폼을 스프레이로 분사 발포시켜 폴리우레탄 폼이 굳어 벽체와 지붕을 형성하는 제 3 과정; 및Install electrical wiring, pipes for water and sewage, windows and doors in the upper part of the formwork according to the purpose and design of the house or building, and use a rigid polyurethane foam to spray on the house or building where the foundation work is installed. A third step of forming a wall and a roof by spraying and foaming the polyurethane foam; And
    도포된 경질 폴리우레탄 폼 경화가 되어 주택 또는 건축물의 벽과 지붕이 완성되면, 경질 폴리우레탄 폼을 스프레이한 면을 다듬어 정리하고 벽의 외부는 사이딩의 마감재로, 지붕은 지붕재 형상의 마감재로 마감하고, 내부는 도장이나 벽지로 마감 시공을 제 4 과정;을 포함하여 구성되는 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법.When the hard polyurethane foam applied is hardened to finish the walls and roof of the house or building, trim the sprayed surface of the hard polyurethane foam, finish the siding finish on the outside of the wall, and finish the roof on the roof. The interior is a building construction method by applying a polyurethane foam, characterized in that comprises a; 4th process to finish construction by painting or wallpaper.
  7. 제 6 항에 있어서,The method of claim 6,
    상기 주택 또는 건축물의 벽, 기둥이 부설된 바닥판과 그 바닥판의 상부에 주택 또는 건축물 벽, 기둥의 위치에 구성된 철근과 금속이나 나무로 된 여러 개의 직선부재를 3각형 또는 5각형으로 큰 외부하중을 지지하는 긴 경간을 가진 구조물을 조립한 트러스(truss)을 이용하여 철근으로 지지된 벽, 기둥의 위치에 견고히 이음하여 주택 또는 건축물의 기초공사를 마무리하도록 구성되는 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법.The outside of the house or building wall, the base plate is attached to the top of the bottom plate and the reinforcing bars or metal or wood in a position of the house or building wall, pillars and a plurality of straight members of a large or triangular Polyurethane foam characterized in that it is configured to finish the basic construction of a house or building by using a truss to assemble a structure having a long span to support the load firmly connected to the position of the walls, columns supported by the rebar Building construction method by applying.
  8. 제 2 항, 제 3 항 또는 제 6 항 중 어느 한 항에 있어서,The method according to any one of claims 2, 3 or 6,
    상기 바닥판은 주택 또는 건축물 완성 후 이동성을 제공하기 위해 나무 또는 철판의 재질로 구성되는 것을 특징으로 하는 폴리우레탄 폼 도포를 통한 건축물 시공방법.The floor plate is a building construction method by applying a polyurethane foam, characterized in that consisting of a material of wood or iron plate to provide mobility after completion of the house or building.
PCT/KR2011/009070 2011-11-02 2011-11-25 Method for constructing a building by applying polyurethane foam WO2013065896A1 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
KR10-2011-0113162 2011-11-02
KR20110113162 2011-11-02
KR10-2011-0123542 2011-11-24
KR20110123542 2011-11-24

Publications (1)

Publication Number Publication Date
WO2013065896A1 true WO2013065896A1 (en) 2013-05-10

Family

ID=48192224

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2011/009070 WO2013065896A1 (en) 2011-11-02 2011-11-25 Method for constructing a building by applying polyurethane foam

Country Status (1)

Country Link
WO (1) WO2013065896A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005474A (en) * 2014-05-07 2014-08-27 苏运升 Method for building house through inflation molds and mold house
CN112031400A (en) * 2020-09-03 2020-12-04 北京市第三建筑工程有限公司 Construction method of concrete dome structure template

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07145643A (en) * 1993-02-03 1995-06-06 Fukuchi Kensou:Kk External heat insulation method in wooden residence
KR20000046448A (en) * 1998-12-31 2000-07-25 강동우 Construction method of building by using air film body
KR20070040765A (en) * 2007-03-14 2007-04-17 강동우 Air dome
KR20090079862A (en) * 2009-07-02 2009-07-22 강동우 Construction method of buidlings using flexible form

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07145643A (en) * 1993-02-03 1995-06-06 Fukuchi Kensou:Kk External heat insulation method in wooden residence
KR20000046448A (en) * 1998-12-31 2000-07-25 강동우 Construction method of building by using air film body
KR20070040765A (en) * 2007-03-14 2007-04-17 강동우 Air dome
KR20090079862A (en) * 2009-07-02 2009-07-22 강동우 Construction method of buidlings using flexible form

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005474A (en) * 2014-05-07 2014-08-27 苏运升 Method for building house through inflation molds and mold house
CN112031400A (en) * 2020-09-03 2020-12-04 北京市第三建筑工程有限公司 Construction method of concrete dome structure template
CN112031400B (en) * 2020-09-03 2021-06-11 北京市第三建筑工程有限公司 Construction method of concrete dome structure template

Similar Documents

Publication Publication Date Title
US4365455A (en) Method of building construction
CN101265723B (en) Architecture structure system assembled by composite building board and building method
US4678157A (en) Apparatus for the construction of a low cost structure
US6871466B2 (en) Structure formed of foaming cement and lightweight steel and a structural system and method of forming the structural system
CN102251662A (en) Cast-in-place process for ultra light foamed cement-based bearing heat insulation wallboard
WO2013065896A1 (en) Method for constructing a building by applying polyurethane foam
WO2006088364A1 (en) Building element and methods for manufacturing thereof
KR101370163B1 (en) Construction method of concrete structure house
US3520092A (en) Prefabricated house
EP1614822A2 (en) Wall structure and method for constructing same
EP3194680A1 (en) A building wall and a method for manufacture
KR100934415B1 (en) Construction method of buidlings using flexible form
KR100934413B1 (en) Construction method of buidlings using flexible form
CN203080767U (en) Cast-in-situ densely-ribbed beam assembly box hollow floor
KR200308707Y1 (en) Lightweight molder which reinforcing rod and molder take the shape of a matrix structure
CN114525883A (en) Precast simple partition wall board and manufacturing method thereof
WO1989000102A1 (en) Method and apparatus for the construction of a low cost structure
KR100934412B1 (en) Construction method of buidlings using flexible form
US11634900B2 (en) Concrete building construction using supported, fillable structures
KR20080093007A (en) Construction method of buidlings using flexible form
KR102441162B1 (en) The GRP wall for supporting bathroom shelf that is installed tile wall of unit bathroom
WO2008089414A1 (en) Building panel for walls, roofs and floors, buildings made therefrom and construction techniques using such panels
KR100463671B1 (en) Assembling panel for non-endurance wall of architecture
RU2439254C1 (en) Method to erect dome roof of religious building
KR100934414B1 (en) Construction method of buidlings using flexible form

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11875197

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 11875197

Country of ref document: EP

Kind code of ref document: A1