WO2010145684A1 - An arrangement for protecting equipment of a power system - Google Patents

An arrangement for protecting equipment of a power system Download PDF

Info

Publication number
WO2010145684A1
WO2010145684A1 PCT/EP2009/057350 EP2009057350W WO2010145684A1 WO 2010145684 A1 WO2010145684 A1 WO 2010145684A1 EP 2009057350 W EP2009057350 W EP 2009057350W WO 2010145684 A1 WO2010145684 A1 WO 2010145684A1
Authority
WO
WIPO (PCT)
Prior art keywords
electrical power
frequency
voltage
power system
electrical
Prior art date
Application number
PCT/EP2009/057350
Other languages
French (fr)
Inventor
Zoran Gajic
Original Assignee
Abb Technology Ag
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Abb Technology Ag filed Critical Abb Technology Ag
Priority to RU2012101239/07A priority Critical patent/RU2503111C2/en
Priority to CN200980159450.2A priority patent/CN102577006B/en
Priority to PCT/EP2009/057350 priority patent/WO2010145684A1/en
Priority to EP20090779747 priority patent/EP2443718B1/en
Publication of WO2010145684A1 publication Critical patent/WO2010145684A1/en
Priority to US13/326,597 priority patent/US8340930B2/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00004Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the power network being locally controlled
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • H02J2310/12The local stationary network supplying a household or a building
    • H02J2310/14The load or loads being home appliances
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment

Definitions

  • the present invention relates to an arrangement for protecting equipment of an AC electrical power system comprising:
  • first means configured to detect electrical power parameters of said power system
  • second means configured to, while considering said electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween , use values of said parameters detected to provide information relating to occurrence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretical electrical machines goes past 180°, and • third means configured to, based upon said information, carry out a control for protecting equipment of said electrical power system, as well as a method for protecting such an electrical power system according to the preamble of the appended independent method claim.
  • AC electrical power systems of any conceivable type is comprised , and such a system does typically, but not necessarily, among others include generators of electric power, transformers, converters and networks for transmitting electric power.
  • the present invention is not restricted to any particular levels of electrical powers, voltages or currents of such electrical power systems.
  • pole slip for such a condition , which accordingly is the same as "out-of- step condition”.
  • the excitation of elec- trical machines of the power system is generally intact, but there are strong oscillations of real and reactive power due to different rotational speed of involved machine rotors. Apart from the electrical phenomena, oscillations of mechanical masses also expose generators and/or other equipment of the power system to considerable pulsating mechanical stresses.
  • Fig 1 The theory of this approach for obtaining protection of an electrical power system will now be briefly explained while referring to the appended Figs 1 -3. It is shown in Fig 1 how the electrical power system is considered as an equivalent two machine system 1 having at each opposite ends thereof one theoretical electric machine 2, 3 with an electro-motive force and an interconnection 4 shown as an impedance.
  • the two machines have the electro-motive forces E 2 and E 3 shown in Fig 2 and here having the same magnitude. Furthermore, it is here assumed that the resistive part is quite small and thus negligible.
  • the cur- rent I flowing between the two machines lags the vector difference E 2 -E 3 by exactly 90° if it is assumed that the impedance is purely inductive.
  • the angle between the two electro-motive forces E 2 and E 3 is ⁇ .
  • is the angle between the voltage U and the current at a given location and varies along the connection between the two electric machines 2, 3, whereas Ucos ⁇ is constant along this connection.
  • the angle ⁇ between the electro-motive forces E 2 and E 3 of said theoretical machines is changing during a power swing, and if the power swing is non-recoverable this angle will finally go past 180°, which is defined as a pole slip.
  • Fig 3 is a graph showing the current I and Ucos ⁇ versus said angle ⁇ . It appears that
  • the other principle is based on detection of rate of change of the impedance of the interconnection of the two theoretical electric machines of the equivalent two machine system and is disclosed in for instance IEEE PSRC Tutorial 95 TP 102, "IEEE tutorial on the Protection of Synchronous Generators". This principle is among others based on the understanding that when a measured impedance point crosses a line in an impedance plane this will be the exact moment when a pole slip occurs. However, this theory is based upon a rather rough estimation of impedances of the electrical power systems.
  • the object of the present invention is to provide an arrangement of the type defined in the introduction being improved in at least some aspect with respect to such arrangements already known.
  • said first means is configured to measure the frequency of the current and voltage at at least one location in the electrical power system along said interconnection between said two theoretical electric machines
  • the arrangement comprises fourth means configured to use the values of the frequency of the current and voltage measured by said first means to determine whether a power swing has occurred in said electrical power system, a power swing being defined as a change of said angle between said electro-motive forces as a consequence of an occurrence of any disturbances of said electrical power system, and if an occurrence of a power swi ng has been determined determi ne whether said measuring location is located on a motor side or a generator side of a potential pole slip electrical centre along said interconnection, said centre being defined as the location where the voltage becomes zero during a said pole slip, is lo- cated and send this information further to said third means for use in said control for protecting the electrical power system.
  • the present invention is based on the new approach to use results of frequency measurements of current and voltage at at least one location in the electrical power system along the interconnection between said two theoretical electrical machines for determining where a potential pole slip electrical centre is located.
  • This determination of the location of the potential pole slip electrical centre will not be dependent upon any estimation of impedances of the electrical power system and will be very reliable.
  • said fourth means is configured to determine that a power swing occurs if said values of the frequency of the current and voltage delivered by said first means show that the measured current phasor start to rotate faster/slower than the measured voltage phasor and the relative angle thereof is continuously increasing/decreasing.
  • a power swing in fact occurs, so that it may be decided on which side, generator side or motor side, of said potential pole slip electrical centre the measuring location is located for use in protecting equipment of the electrical power system.
  • said fourth means is configured to, upon determination of occurrence of a said power swing, determine that said location is located on a motor side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means is higher than the frequency of the voltage at said location and determine that said location is located on a generator side of said potential pole slip electrical centre is located on a motor side of said location in said two machine system if the frequency of the current measured by said first means is lower than the frequency of the voltage at said location. It may by very simple and reliable means by use of the result of these frequency measurements be decided on which side of a potential pole slip electrical centre a said measuring location is located, so that appropriate actions may be taken for protecting the electrical power system.
  • the present inventor has by this provided a method for determining the location of a potential pole slip electrical centre for an AC electrical power system, in which this electrical power system is considered as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween, the frequency of the current and voltage at at least one location in the electrical power system along said interconnection between said two theoretical electrical machines are measured, the values of the frequency of the current and voltage measured are used to determine whether a power swing has occurred in said electrical power system, and if an occurrence of a power swing has been determined it is determined whether said measuring location is along said interconnection located on a motor side or a generator side of a potential pole slip electrical centre.
  • said first means is configured to measure the frequency of the current and voltage at a further said location
  • said fourth means is configured to, upon determination of occurrence of a power swing, determine that said further location is located on a motor side of said potential pole slip electrical centre in said two ma- chine system if the frequency of the current measured by said first means is higher than the frequency of the voltage at said further location and determine that said further location is located on a generator side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means is lower than the frequency of the voltage at said further location.
  • the arrangement is configured to protect an electrical power system having a block of a generator and a transformer connected through a high voltage station to a high voltage system for transmitting electric power, the arrangement comprises said first means located in t h e i n t e r c o nnection between said generator/transformer-block and said high voltage station, and said third means is configured to, upon receipt of information from said second means relating to occurrence of a pole slip and in- formation from said fourth means that the measuring location is located on the motor side of said electrical centre in the two machine system, influence equipment controlling the operation of said generator/transformer-block i n the d irection of obtaining stability of the electrical power system and/or control a member to disconnect said generator from said high voltage power system or stop the operation of said generator.
  • the two theoretical electric machines of the equivalent two machine system are here on one hand said generator/transformer-block and on the other said high voltage system, and it will by an arrangement of this type be early and reliably determined on which side of said potential pole slip electrical centre the measuring location is located. Furthermore, if it is determined that the measuring location is located on the motor side, the control systems of the generator may first be influenced for trying to obtain appropriate operation of the generator so as to recover balance i n the electrical power system and if this is not succeeded the gen- erator may be tripped and disconnected from the high voltage system before any pole slip occurs.
  • the arrangement is configured to protect an electrical power system having a synchronous machine operating as a motor connected through a high voltage station to a high voltage system for transmitting electric power, said first means is located in the interconnection between said synchronous machine and said high voltage station, and that said third means is configured to, upon receipt of information from said second means relating to occurrence of a pole slip and information from said fourth means that the measuring location is located on the generator side of said electrical centre in the two machine system, influence equipment controlling the operation of said synchronous machine in the direction of obtaining stability of the electrical power system and/or control a member to disconnect said synchronous machine from said high voltage power system or stop the operation of said synchronous machine.
  • the arrangement according to the invention has the same positive features for the case of a synchronous machine operating as a motor as for a generator.
  • the arrange- ment is configured to protect an electrical power system in the form of a main electrical power system including a first and a second electrical power system and an interconnection therebetween, said fourth means is located at one end of said interconnection connecting to said first electrical power system, that the arrangement comprises a device configured to use the values of the frequency of the current and voltage measured by said first means at said end of the interconnection and based upon information of properties of said interconnection stored in a memory carry out a calculation so as to estimate the voltage and current phasors prevailing at the other end of said interconnection con- necting to the second electrical power system, and said fourth means is configured to, upon determination of occurrence of a said power swing, determine a) that said electrical centre is located within said interconnection if the frequency of the current is higher than the voltage frequency on one end of the intercon- nection and at the same time the current frequency is lower than the voltage frequency on the other end of the interconnection and b) that said electrical centre is located in the electrical power system located at the interconnection
  • a potential pole slip electrical centre is located in which part of an electrical power system in the form of two interconnected electrical power systems a potential pole slip electrical centre is located may by simple means by this be reliably and early (see above) obtained, so that relevant measures for protecting equipment of the main electrical power system may be taken .
  • relevant measures for protecting equipment of the main electrical power system may be taken .
  • said third means is configured to, upon information from said second means relating to occurrence of a pole slip for a previous determination according to a) by said fourth means control a member to disconnect said interconnection from the electrical power systems before or after occurrence of a pole slip in order to minimize its impact on said two electrical power systems and for a previous determination according to b) by said fourth means influence equipment controlling the operation of components of said electrical power system having said electrical centre in the direction of obtaining stability of this system and/or control a member to disconnect this electrical power system from said interconnection.
  • the arrangement is configured to protect an electrical power system in the form of a meshed electrical power network
  • said first means is configured to measure the frequency of the current and volt- age at at least two locations in said meshed electrical power network, said measuring locations are selected so that measuring is carried out by said first means in the same power flow corridor within the network enabling said second means to consider said meshed electrical power network as an equivalent two ma- chine system
  • said fourth means is configured to, upon determination of occurrence of a said power swing, determine a) said electrical centre will be somewhere in between said two measurement locations within said meshed electrical power network if the current frequency is on one said measuring loca- tion higher than the voltage frequency and at the same time the current frequency is lower than the voltage frequency on said other location, and b) said electrical centre is located outside the part of the meshed electrical power network limited by said measurement locations and with respect thereto after the one of the two measuring locations with the smallest difference between the current frequency and the voltage frequency if at both said measuring locations the current has at the same
  • Measurements of frequency of voltage and current and evaluation of the result thereof may in this way be used for obtaining the main task for pole slip protection of a meshed electrical power network, i.e. to detect whether the potential pole slip electrical centre is located within the part of the electrical power network limited by the measurement locations. This information may then be used for deciding if any part of said meshed electrical power network between said measurement locations is to be disconnected or other type of correcting measures are to be taken.
  • Said fourth means may then be configured to determine that a power swing occurs in said meshed electrical power network if said values of the frequency of the current and voltage delivered by said first means show that the measured current phasor starts to rotate faster/slower than the measured voltage phasor at any of said two measuring locations and the relative angle of said current phasor and voltage phasor is continuously increasing/decreasing.
  • the arrangement is configured to protect an electrical power system in the form of a meshed electrical power network having PMUs (Phasor Measurement Units) on a plurality of different locations within the meshed electrical power network, said second means is configured to consider, at each said location of a PMU, the two parts of said meshed electrical power network interconnected there as a said equivalent two machine system.
  • PMUs Phase Measurement Units
  • said second means is configured to consider, at each said location of a PMU, the two parts of said meshed electrical power network interconnected there as a said equivalent two machine system.
  • Said fourth means is then configured to use the values of the frequency of the current and voltage measured by said PMUs at each said location to determine whether a power swing has occurred in said meshed electrical power network and if an occur- rence of a power swing has been determined determine that a location of a PMU where a measured current frequency is higher than a measured voltage frequency is on a motor side of the meshed power electrical network and that a location of a PMU where a measured current frequency is lower than the measured voltage frequency is on a generator side of the meshed electri- cal power network, and according to another embodiment of the invention said fourth means is configured to utilise information from all said PMUs with respect to said locations on motor side or generator side to determine in which part of said meshed electrical power network a potential pole slip electrical centre is located.
  • Said fourth means is then configured to determine that a power swing has occurred within said meshed electrical power network if at any of said measuring locations the measured current phasor starts to rotate faster/slower than the measured voltage phasor and the relative angle of the current phasor and the voltage phasor is continuously increasing/decreasing.
  • the invention also relates to a method for protecting an AC electrical power system according to the appended independent method claim.
  • the method according to the invention is well suited to be carried out by a computer and the invention does therefor also re- late to a computer program and a computer program product according to appended claims therefor.
  • the invention also relates to an AC electrical power system comprising an arrangement for protecting equipment of said power system according to the invention as well as a use of such an arrangement for protecting equipment of an AC electrical power system.
  • Fig 1 is a very simplified view illustrating an AC electrical power system in the form of an equivalent two machine system
  • Fig 2 is a vector diagram relating to the system according to Fig 1 ,
  • Fig 3 is a graph showing Ucos ⁇ and I versus the angle ⁇ made by the electro-motive forces of the two machines in Fig 1 ,
  • Fig 4 is a simplified view of a said equivalent two machine system used for explaining the present invention
  • Fig 5 is a simplified graph of voltage versus time on differ- ent locations in Fig 4 during pole slip
  • Fig 6 is a simplified graph of frequency of the voltage versus the location on the interconnection shown in Fig 4, is a very simplified graph illustrating the influence of the magnitude of voltage at the two ends of the two machine system shown in Fig 4 upon the location of a potential pole slip electrical centre,
  • FIG. 1 is a simplified view illustrating an arrangement according to a first embodiment of the invention applied to an electrical power system having a block of a generator and a transformer connected through a high voltage station to a high voltage system for transmitting electric power,
  • FIG. 8 is a view similar to Fig 8 of an arrangement according to a second embodiment of the invention for protect- ing an electrical power system in the form of a main electrical power system including a first and a second electrical power system and an interconnection therebetween,
  • FIG. 1 is a simplified view illustrating how an arrangement according to a third embodiment of the invention may be applied to protect an electrical power system in the form of a meshed electrical power network
  • FIG. 10 is a view similar to Fig 8 of the equivalent two machine system of the network shown in Fig 10, and
  • FIG. 10 is a view similar to Fig 10 illustrating an arrangement according to a fourth embodiment of the invention for protecting an electrical power system in the form of a meshed electrical power network having PMUs distributed over a wide area.
  • Fig 4 illustrates a two machine system as shown in Fig 1 in the form of two electrical machines 2, 3 interconnected by an interconnection 4 having an impedance indicated by 5.
  • the two ends of the interconnection are indicated at 6 and 7, where the voltage is Ui and U 2 , respectively.
  • Monitored locations in this and following figures along the interconnection are marked with A, C and B.
  • the location C corresponds to the potential pole slip electrical centre of the system.
  • Fig 5 shows how the voltage magnitude U on the different locations varies over time during pole slip, and it appears that the voltage is zero in the location C, i.e. in said electrical centre, when pole slip occurs.
  • a power swing occurs if the values of the frequency of the current and the voltage show that the current phasor starts to rotate faster/slower than the voltage phasor and the relative angle thereof is continuously increasing/decreasing, and we do here assume that the frequency fi at the location 6 is higher than the frequency f 2 at the location 7 for explaining the power swing and pole slip phenomena.
  • the frequency of the current f cu is the same along the radial system as shown in the graph of Fig 6 and is the same as the mean frequency ((f1 +f2)/2) of the two voltages at 6 and 7.
  • Ucos ⁇ is at every moment constant along the radial link interconnecting the location 6 and 7.
  • phase angle difference between current and voltage measured at the potential pole slip electrical centre is almost constant, which means that these two quantities have the same rotational speed and accordingly identical frequency there.
  • said electrical centre C will be located where the frequency line of the voltage intersects the frequency line of the current (see Fig 6).
  • This understanding may be utilised to determine on which side of such an electrical centre a location for measuring the frequency of current and voltage will be lo- cated.
  • this location will be to the left of the electrical centre C, i.e. the side 100 referred to generator mode of operation during pole slip.
  • the measurement location will be to the right of the point C, i.e. the side 200 referred to motor mode of operation during pole slip.
  • Fig 7 illustrates how the location of said potential pole slip elec- trical centre is dependent upon the relative magnitude of the voltages at the two ends of the interconnection 4, and it is shown that this electrical centre will be located closer to the end with the lowest magnitude of the voltage.
  • FIG 8. An arrangement according to the first embodiment of the invention is very schematically illustrated in Fig 8. This arrangement is configured to protect an electrical power system having a block 10 of a generator 1 1 and a transformer 12 connected through a high voltage station 13 to a high voltage system 14 for transmitting electric power.
  • This high voltage system 14 may be considered as an electrical machine with infinite power in an equivalent two machine system.
  • the arrangement has first means 15 located in the interconnection between the generator/transformer block 10 and the high voltage station 13 and configured to measure the frequency of the current (15a) and voltage (15b) at this location 16.
  • the arrangement further comprises a relay in the form of an Intelligent Electronic Device IED 17 including second means 18 receiving values of frequency of the current and the voltage measured and configured to, while considering the electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween, use these values to provide information relating to occurrence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretically electric machines goes past 180° as disclosed above.
  • a relay in the form of an Intelligent Electronic Device IED 17 including second means 18 receiving values of frequency of the current and the voltage measured and configured to, while considering the electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween, use these values to provide information relating to occurrence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretically electric machines goes past 180° as disclosed above.
  • the arrangement also comprises fourth means 19 receiving said measurement values and configured to use these values of the frequency of the current and voltage measured to determine whether a power swing has occurred in said electrical power system, a power swing being defined as a change of the angle ⁇ between said electro-motive forces as a consequence of an occurrence of any disturbances of the electrical power system, and if an occurrence of a power swing has been determined determine whether said location 16 is along said interconnection located on the motor side or generator side of a said potential pole slip electrical centre, defined as the location where the voltage becomes zero during a said pole slip, is located. Accordingly, this is done by utilising the theory presented above with reference made es- pecially to Fig 6.
  • the fourth means will send this information further to third means 20 also included in said IED, which is configured to based upon information from the second and fourth means carry out a control for protecting equipment of the electrical power system.
  • third means 20 also included in said IED, which is configured to based upon information from the second and fourth means carry out a control for protecting equipment of the electrical power system.
  • Fig 9 illustrates an arrangement according to a second embodiment of the invention configured to protect an electrical power system in the form a main electrical power system including a first 2' and a second 3' electrical power system and an intercon- nection 4' therebetween.
  • the parts of the arrangement according to this embodiment corresponding to parts of the embodiment shown in Fig 8 are here provided with the same reference numerals with a prim added thereto.
  • the interconnection is here represented by an impedance.
  • Said first means 15' is configured to measure the frequency of current and voltage at a location 16' on one side of the intercon nection 4'.
  • the arrangement comprises a device 25 configured to use values of the frequency of current and voltage measured and based upon information of properties of the interconnection stored in a memory carry out a calculation while using any of different known models so as to estimate the voltage and current phasors prevailing at the other end of the interconnection 4'.
  • Said prop- erties are the three impedances 22, 4' and 23 shown in Fig 9.
  • the interconnection impedance 4' is fixed and well known while the two source impedances 22, 23 are varying and very much dependent on actual connection status of both power systems.
  • Said fourth means 19' included in said IED is configured to, upon determination of occurrence of a said power swing, determine a) that said electrical centre is lo- cated within said interconnection 4' if the frequency of the current is higher than the voltage frequency on one end of the interconnection and at the same time the current frequency is lower than the voltage frequency on the other end of the inter- connection and b) that said electrical centre is located in the electrical power system located at the interconnection end with the smallest difference between current frequency and voltage frequency if the current frequency is at both ends of said interconnections at the same time either higher or lower than the voltage frequency.
  • Fig 10 illustrates an electrical power system, the Swedish power system, in the form of a meshed electrical power network 30, and an arrangement according to a third embodiment of the invention is configured to protect this meshed electrical power network by selecting two locations 31 , 32 for measuring the fre- quency of the current and voltage by first means 34, 35 so that these measurements will be carried out in the same power flow corridor within the network enabling said second means to consider said meshed electrical power network as an equivalent two machine system as shown in Fig 1 1 . Accordingly, the system shown in Fig 1 1 only differs from that shown in Fig 9 by the fact that measurements are here carried out at two different locations, namely at each end of the interconnection.
  • Fig 12 illustrates an electrical power system in the form of a meshed electrical power network 40 extending over a wide area, here in Sweden and adjacent countries, having PMUs (Phasor Measurement Unit) 41 -46 on a plurality of different lo- cations within the meshed electrical power network. It is important to properly select locations for the PMUs in order to cover the entire network.
  • PMUs Phase Measurement Unit
  • PMUs makes it possible to measure the frequency of the current and voltage and determine the location of the current and voltage phasors in the complex plane with respect to a GPS signal, which means that the phase shift of these phasors on one location with respect to another location may be determined.
  • Said second means is configured to consider at each said location of a PMU the two parts of said meshed electrical power network interconnected there as a said equivalent two machine system and the fourth means is configured to use the values of the frequency of the current and voltage measured by the PMUs at each said location to determine whether a power swing has occurred in said meshed electrical power network and if an occurrence of a power swing has been determined determine that a location of a PMU where a measured current frequency is higher than a measured voltage frequency is on a motor side of the electrical power network and that a location of a PMU where a measured current frequency is lower than the measured voltage frequency is on a generator side of the meshed electric power network.
  • a computer 47 may through a suitable computer program carry out calculations for determining location of said potential pole slip electrical centre, so that any possible corrective actions may be taken before the first pole slip occurs in order to minimize its impact on the rest of the electrical power network. Such actions may be to disconnect parts of the network or any equipment thereof.
  • an arrangement according to the invention may be configured to protect other types of electrical power systems than those described above, and measuring of frequencies may be carried out on a different number of locations than shown in the figures.
  • the arrangement may be designed for protecting equipment of an AC electrical power system also having DC links connected thereto through converter stations.
  • the second, third and fourth means in the arrangement according to the invention have not to be physically separated parts, but they may be summarized in one single ob- ject, such as a computer appropriately programmed.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Protection Of Generators And Motors (AREA)
  • Control Of Multiple Motors (AREA)
  • Control Of Ac Motors In General (AREA)

Abstract

An arrangement for protecting equipment of an AC electrical power system comprises first means (15) configured to measure the frequency of the current and voltage at at least one location (16) in the electrical power system along an interconnection between two theoretical electric machines of an equivalent two machine system. Fourth means (19) are configured to use the values of the frequency of the current and voltage measured to determine whether a power swing has occurred in said electrical power system and if an occurrence of a power swing has been determined determine whether the measuring location (16) is located on a motor side or a generator side of a potential pole slip electrical centre along said interconnection, said electrical cen- tre being defined as the location where the voltage becomes zero during a pole slip, and send this information further to third means (20) for use in a control for protecting equipment of the electrical power system.

Description

An arrangement for protecting equipment of a power system
TECHNICAL FIELD OF THE INVENTION AND BACKGROUND ART
The present invention relates to an arrangement for protecting equipment of an AC electrical power system comprising:
• first means configured to detect electrical power parameters of said power system,
• second means configured to, while considering said electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween , use values of said parameters detected to provide information relating to occurrence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretical electrical machines goes past 180°, and • third means configured to, based upon said information, carry out a control for protecting equipment of said electrical power system, as well as a method for protecting such an electrical power system according to the preamble of the appended independent method claim.
Protection of AC electrical power systems of any conceivable type is comprised , and such a system does typically, but not necessarily, among others include generators of electric power, transformers, converters and networks for transmitting electric power. Furthermore, the present invention is not restricted to any particular levels of electrical powers, voltages or currents of such electrical power systems.
Sudden events in such an electrical power system, such as large jumps in load , fault occurrence or slow fault clearance, which disturb the balance of energy in the system, can cause oscillations of mechanical masses, such as accelerations of rotors in electrical machines of the system, and such oscillations disturbing said balance are referred to and here defined as power swings. In a recoverable situation these oscillations will decay and stable operation will be resumed, which may be obtained by means of different control equipment of the electrical power system, such as control systems for an electrical generator being a part of the system. However, in a non-recoverable situation, the power swings become so severe that the synchro- nism is lost between different parts of the system, such as generators thereof, which is a condition referred to as pole slipping or out-of-step in the literature. We will hereinafter use "pole slip" for such a condition , which accordingly is the same as "out-of- step condition". In the case of a pole slip the excitation of elec- trical machines of the power system is generally intact, but there are strong oscillations of real and reactive power due to different rotational speed of involved machine rotors. Apart from the electrical phenomena, oscillations of mechanical masses also expose generators and/or other equipment of the power system to considerable pulsating mechanical stresses. Even though modern electrical power systems are designed and operate with high degree of security against power swings and even more against pole slipping , these two phenomena may occur especially during abnormal system conditions. If a pole slip is al- lowed to persist in one part of a power system then other electrical machines/equipment may follow and we do not only have an immediate risk of damaging bearings of rotors and other mechanical parts, but the stability of a complete electrical power system may be lost and complete blackout of the power system may be the final outcome.
It is from the above disclosure obvious that it is important to have arrangements for protecting equipment of electrical power systems against detrimental influences of power swings and pole slips, since these may otherwise cause enormous costs. In the case of severe faults it may be absolutely necessary to iso- late a part of the electrical power system from the rest thereof, but it is also of importance to be able to determine whether a power swing is recoverable or not, since false tripping of such a protecting arrangement must be avoided, since that would result in a waste of considerable costs. Arrangement of this type either isolating an electrical machine, such as a generator, from the rest of the system or splitting the system at predetermined points have for this sake been proposed.
It has in the past been found that it is suitable to try to consider the electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electrical machine with an electro-motive force and an interconnection therebetween for being able to provide information re- lating to occurrence of a pole slip, i.e. that pole slip may or will occur or has occurred. The application of this model is possible if the electrical power system may be divided into two parts interconnected by a radial link-like power flow path.
The theory of this approach for obtaining protection of an electrical power system will now be briefly explained while referring to the appended Figs 1 -3. It is shown in Fig 1 how the electrical power system is considered as an equivalent two machine system 1 having at each opposite ends thereof one theoretical electric machine 2, 3 with an electro-motive force and an interconnection 4 shown as an impedance. The two machines have the electro-motive forces E2 and E3 shown in Fig 2 and here having the same magnitude. Furthermore, it is here assumed that the resistive part is quite small and thus negligible. The cur- rent I flowing between the two machines lags the vector difference E2-E3 by exactly 90° if it is assumed that the impedance is purely inductive. The angle between the two electro-motive forces E2 and E3 is δ. φ is the angle between the voltage U and the current at a given location and varies along the connection between the two electric machines 2, 3, whereas Ucosφ is constant along this connection. The angle δ between the electro-motive forces E2 and E3 of said theoretical machines is changing during a power swing, and if the power swing is non-recoverable this angle will finally go past 180°, which is defined as a pole slip. Fig 3 is a graph showing the current I and Ucosφ versus said angle δ. It appears that
Ucosφ will decrease when a pole slip is approaching for being zero when δ is 180°, where then the current I is the highest, which may be very harmful for equipment of the electrical power system.
Thus, it is of importance to carry out measurement of such an electrical power system so as to detect electrical parameters of interest for providing information relating to occurrence of a pole slip, and this has so far mainly been done according to two principles.
One of these principles is based on detection of rate of change of Ucosφ, and this principle is further described in for instance "Innovations in the Detection of Power Swings in Electrical Networks", Brown Boveri Review Feb. 1981 (BBC Publication Number CH-ES 35-30.10E) by F. Mar. Different conditions to be met for declaring a pole slip are mentioned in that document, such as the rate of change of Ucosφ, which is typically in the order of 0.2-8 Hz for a pole slip condition, and passing of a threshold value of Ucosφ
The other principle is based on detection of rate of change of the impedance of the interconnection of the two theoretical electric machines of the equivalent two machine system and is disclosed in for instance IEEE PSRC Tutorial 95 TP 102, "IEEE Tutorial on the Protection of Synchronous Generators". This principle is among others based on the understanding that when a measured impedance point crosses a line in an impedance plane this will be the exact moment when a pole slip occurs. However, this theory is based upon a rather rough estimation of impedances of the electrical power systems.
It is of course an ongoing attempt to increase reliability of ar- rangements of the type defined in the introduction for only tripping equipment when absolutely necessary and then ensuring that this is obtained before any costly equipment of the system is harmed. It is also a desire to increase the possibilities to recover the balance of the electrical power system without discon- necting any parts thereof from the rest of the system when this is at all doable.
SUMMARY OF THE INVENTION
The object of the present invention is to provide an arrangement of the type defined in the introduction being improved in at least some aspect with respect to such arrangements already known.
This object is according to the invention obtained by providing such an arrangement with the following additional features: said first means is configured to measure the frequency of the current and voltage at at least one location in the electrical power system along said interconnection between said two theoretical electric machines, and the arrangement comprises fourth means configured to use the values of the frequency of the current and voltage measured by said first means to determine whether a power swing has occurred in said electrical power system, a power swing being defined as a change of said angle between said electro-motive forces as a consequence of an occurrence of any disturbances of said electrical power system, and if an occurrence of a power swi ng has been determined determi ne whether said measuring location is located on a motor side or a generator side of a potential pole slip electrical centre along said interconnection, said centre being defined as the location where the voltage becomes zero during a said pole slip, is lo- cated and send this information further to said third means for use in said control for protecting the electrical power system.
Thus, the present invention is based on the new approach to use results of frequency measurements of current and voltage at at least one location in the electrical power system along the interconnection between said two theoretical electrical machines for determining where a potential pole slip electrical centre is located. This determination of the location of the potential pole slip electrical centre will not be dependent upon any estimation of impedances of the electrical power system and will be very reliable. Furthermore, it may by this way of proceeding very early be determined where measures as isolation of equipment shall later on be taken would a pole slip occur and start of con- trol procedures for obtaining recovery of any unbalances may start early for, when possible, avoiding isolation or tripping of equipment of the electrical power system.
According to an embodiment of the invention said fourth means is configured to determine that a power swing occurs if said values of the frequency of the current and voltage delivered by said first means show that the measured current phasor start to rotate faster/slower than the measured voltage phasor and the relative angle thereof is continuously increasing/decreasing. Ac- cordingly, it may in this way be determined that a power swing in fact occurs, so that it may be decided on which side, generator side or motor side, of said potential pole slip electrical centre the measuring location is located for use in protecting equipment of the electrical power system.
According to another embodiment of the invention said fourth means is configured to, upon determination of occurrence of a said power swing, determine that said location is located on a motor side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means is higher than the frequency of the voltage at said location and determine that said location is located on a generator side of said potential pole slip electrical centre is located on a motor side of said location in said two machine system if the frequency of the current measured by said first means is lower than the frequency of the voltage at said location. It may by very simple and reliable means by use of the result of these frequency measurements be decided on which side of a potential pole slip electrical centre a said measuring location is located, so that appropriate actions may be taken for protecting the electrical power system.
Accordingly, the present inventor has by this provided a method for determining the location of a potential pole slip electrical centre for an AC electrical power system, in which this electrical power system is considered as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween, the frequency of the current and voltage at at least one location in the electrical power system along said interconnection between said two theoretical electrical machines are measured, the values of the frequency of the current and voltage measured are used to determine whether a power swing has occurred in said electrical power system, and if an occurrence of a power swing has been determined it is determined whether said measuring location is along said interconnection located on a motor side or a generator side of a potential pole slip electrical centre.
According to another embodiment of the invention said first means is configured to measure the frequency of the current and voltage at a further said location, and said fourth means is configured to, upon determination of occurrence of a power swing, determine that said further location is located on a motor side of said potential pole slip electrical centre in said two ma- chine system if the frequency of the current measured by said first means is higher than the frequency of the voltage at said further location and determine that said further location is located on a generator side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means is lower than the frequency of the voltage at said further location. By measuring on said further location and comparing the result of this measurement with the result of the measurement on the location first mentioned it may be determined on which side of these locations said potential pole slip electrical centre is located.
According to another embodiment of the invention the arrangement is configured to protect an electrical power system having a block of a generator and a transformer connected through a high voltage station to a high voltage system for transmitting electric power, the arrangement comprises said first means located in t h e i n t e r c o nnection between said generator/transformer-block and said high voltage station, and said third means is configured to, upon receipt of information from said second means relating to occurrence of a pole slip and in- formation from said fourth means that the measuring location is located on the motor side of said electrical centre in the two machine system, influence equipment controlling the operation of said generator/transformer-block i n the d irection of obtaining stability of the electrical power system and/or control a member to disconnect said generator from said high voltage power system or stop the operation of said generator. Thus, the two theoretical electric machines of the equivalent two machine system are here on one hand said generator/transformer-block and on the other said high voltage system, and it will by an arrangement of this type be early and reliably determined on which side of said potential pole slip electrical centre the measuring location is located. Furthermore, if it is determined that the measuring location is located on the motor side, the control systems of the generator may first be influenced for trying to obtain appropriate operation of the generator so as to recover balance i n the electrical power system and if this is not succeeded the gen- erator may be tripped and disconnected from the high voltage system before any pole slip occurs. When on the other side it is determined that the measuring location is located on the generator side of said electrical centre in the two machine system it may be waited a predetermined period of time after occurrence of a said pole slip and when the electrical power system is then still unstable the generator/transformer-block will be disconnected from the high voltage power system. Thus, a possible positive result of any correction actions or the like carried out in said high voltage power system may be awaited , so that said generator/transformer-block is not disconnected before this is really necessary for protection thereof and by that such disconnection may be avoided if it is not absolutely necessary.
According to another embodiment of the invention the arrangement is configured to protect an electrical power system having a synchronous machine operating as a motor connected through a high voltage station to a high voltage system for transmitting electric power, said first means is located in the interconnection between said synchronous machine and said high voltage station, and that said third means is configured to, upon receipt of information from said second means relating to occurrence of a pole slip and information from said fourth means that the measuring location is located on the generator side of said electrical centre in the two machine system, influence equipment controlling the operation of said synchronous machine in the direction of obtaining stability of the electrical power system and/or control a member to disconnect said synchronous machine from said high voltage power system or stop the operation of said synchronous machine. The arrangement according to the invention has the same positive features for the case of a synchronous machine operating as a motor as for a generator.
According to another embodiment of the invention the arrange- ment is configured to protect an electrical power system in the form of a main electrical power system including a first and a second electrical power system and an interconnection therebetween, said fourth means is located at one end of said interconnection connecting to said first electrical power system, that the arrangement comprises a device configured to use the values of the frequency of the current and voltage measured by said first means at said end of the interconnection and based upon information of properties of said interconnection stored in a memory carry out a calculation so as to estimate the voltage and current phasors prevailing at the other end of said interconnection con- necting to the second electrical power system, and said fourth means is configured to, upon determination of occurrence of a said power swing, determine a) that said electrical centre is located within said interconnection if the frequency of the current is higher than the voltage frequency on one end of the intercon- nection and at the same time the current frequency is lower than the voltage frequency on the other end of the interconnection and b) that said electrical centre is located in the electrical power system located at the interconnection end with the smallest difference between current frequency and voltage frequency if the current frequency is at both ends of said interconnection at the same time either higher or lower than the voltage frequency. In which part of an electrical power system in the form of two interconnected electrical power systems a potential pole slip electrical centre is located may by simple means by this be reliably and early (see above) obtained, so that relevant measures for protecting equipment of the main electrical power system may be taken . Thus, it is only necessary to measure the frequency of voltage and current at one location and by means of information of properties of said interconnection determine where said electrical centre is located.
According to another embodiment of the invention being a further development of the embodiment last mentioned said third means is configured to, upon information from said second means relating to occurrence of a pole slip for a previous determination according to a) by said fourth means control a member to disconnect said interconnection from the electrical power systems before or after occurrence of a pole slip in order to minimize its impact on said two electrical power systems and for a previous determination according to b) by said fourth means influence equipment controlling the operation of components of said electrical power system having said electrical centre in the direction of obtaining stability of this system and/or control a member to disconnect this electrical power system from said interconnection.
According to a still further embodiment of the invention the arrangement is configured to protect an electrical power system in the form of a meshed electrical power network, said first means is configured to measure the frequency of the current and volt- age at at least two locations in said meshed electrical power network, said measuring locations are selected so that measuring is carried out by said first means in the same power flow corridor within the network enabling said second means to consider said meshed electrical power network as an equivalent two ma- chine system, and said fourth means is configured to, upon determination of occurrence of a said power swing, determine a) said electrical centre will be somewhere in between said two measurement locations within said meshed electrical power network if the current frequency is on one said measuring loca- tion higher than the voltage frequency and at the same time the current frequency is lower than the voltage frequency on said other location, and b) said electrical centre is located outside the part of the meshed electrical power network limited by said measurement locations and with respect thereto after the one of the two measuring locations with the smallest difference between the current frequency and the voltage frequency if at both said measuring locations the current has at the same time either higher or lower frequency than the voltage. Measurements of frequency of voltage and current and evaluation of the result thereof may in this way be used for obtaining the main task for pole slip protection of a meshed electrical power network, i.e. to detect whether the potential pole slip electrical centre is located within the part of the electrical power network limited by the measurement locations. This information may then be used for deciding if any part of said meshed electrical power network between said measurement locations is to be disconnected or other type of correcting measures are to be taken. Said fourth means may then be configured to determine that a power swing occurs in said meshed electrical power network if said values of the frequency of the current and voltage delivered by said first means show that the measured current phasor starts to rotate faster/slower than the measured voltage phasor at any of said two measuring locations and the relative angle of said current phasor and voltage phasor is continuously increasing/decreasing.
According to another embodiment of the invention the arrangement is configured to protect an electrical power system in the form of a meshed electrical power network having PMUs (Phasor Measurement Units) on a plurality of different locations within the meshed electrical power network, said second means is configured to consider, at each said location of a PMU, the two parts of said meshed electrical power network interconnected there as a said equivalent two machine system. By using distributed measurements from a suitable number of PMUs and considering the two parts of said meshed electrical power network interconnected at such a location as a said equivalent two machine system it may be possible to detect in which part of said meshed power electrical network a potential pole slip electrical centre is located. It is then important to properly select lo- cations for the PMUs in order to cover the entire network. Said fourth means is then configured to use the values of the frequency of the current and voltage measured by said PMUs at each said location to determine whether a power swing has occurred in said meshed electrical power network and if an occur- rence of a power swing has been determined determine that a location of a PMU where a measured current frequency is higher than a measured voltage frequency is on a motor side of the meshed power electrical network and that a location of a PMU where a measured current frequency is lower than the measured voltage frequency is on a generator side of the meshed electri- cal power network, and according to another embodiment of the invention said fourth means is configured to utilise information from all said PMUs with respect to said locations on motor side or generator side to determine in which part of said meshed electrical power network a potential pole slip electrical centre is located. It will by this be possible to take any conceivable corrective actions before the first pole slip occurs in order to minimize its impact on the rest of said meshed electrical power network. Said fourth means is then configured to determine that a power swing has occurred within said meshed electrical power network if at any of said measuring locations the measured current phasor starts to rotate faster/slower than the measured voltage phasor and the relative angle of the current phasor and the voltage phasor is continuously increasing/decreasing.
The invention also relates to a method for protecting an AC electrical power system according to the appended independent method claim. The advantages and the advantageous features thereof and of embodiments according to the invention of said method defined in dependent claims appear clearly from the above disclosure of the arrangement according to the present invention.
The method according to the invention is well suited to be carried out by a computer and the invention does therefor also re- late to a computer program and a computer program product according to appended claims therefor.
Furthermore, the invention also relates to an AC electrical power system comprising an arrangement for protecting equipment of said power system according to the invention as well as a use of such an arrangement for protecting equipment of an AC electrical power system.
Further advantages as well as advantageous features of the in- vention will appear from the following description.
BRIEF DESCRIPTION OF THE DRAWINGS
With reference to the appended drawings below follows a spe- cific description of embodiments of the invention cited as examples.
In the drawings:
Fig 1 is a very simplified view illustrating an AC electrical power system in the form of an equivalent two machine system,
Fig 2 is a vector diagram relating to the system according to Fig 1 ,
Fig 3 is a graph showing Ucosφ and I versus the angle δ made by the electro-motive forces of the two machines in Fig 1 ,
Fig 4 is a simplified view of a said equivalent two machine system used for explaining the present invention,
Fig 5 is a simplified graph of voltage versus time on differ- ent locations in Fig 4 during pole slip,
Fig 6 is a simplified graph of frequency of the voltage versus the location on the interconnection shown in Fig 4, is a very simplified graph illustrating the influence of the magnitude of voltage at the two ends of the two machine system shown in Fig 4 upon the location of a potential pole slip electrical centre,
is a simplified view illustrating an arrangement according to a first embodiment of the invention applied to an electrical power system having a block of a generator and a transformer connected through a high voltage station to a high voltage system for transmitting electric power,
is a view similar to Fig 8 of an arrangement according to a second embodiment of the invention for protect- ing an electrical power system in the form of a main electrical power system including a first and a second electrical power system and an interconnection therebetween,
is a simplified view illustrating how an arrangement according to a third embodiment of the invention may be applied to protect an electrical power system in the form of a meshed electrical power network,
is a view similar to Fig 8 of the equivalent two machine system of the network shown in Fig 10, and
is a view similar to Fig 10 illustrating an arrangement according to a fourth embodiment of the invention for protecting an electrical power system in the form of a meshed electrical power network having PMUs distributed over a wide area. DETAILED DESCRIPTION OF EMBODIMENTS OF THE INVENTION
The theory upon which the present invention is based, i.e. to measure the frequency of the current and voltage at at least one location in an electrical power system along an interconnection between two theoretical electrical machines of an equivalent two machine system for determining the location of a potential pole slip electrical centre will now be explained while referring to Figs 4-7. Fig 4 illustrates a two machine system as shown in Fig 1 in the form of two electrical machines 2, 3 interconnected by an interconnection 4 having an impedance indicated by 5. The two ends of the interconnection are indicated at 6 and 7, where the voltage is Ui and U2, respectively. Monitored locations in this and following figures along the interconnection are marked with A, C and B. The location C corresponds to the potential pole slip electrical centre of the system. Fig 5 shows how the voltage magnitude U on the different locations varies over time during pole slip, and it appears that the voltage is zero in the location C, i.e. in said electrical centre, when pole slip occurs.
We define that a power swing occurs if the values of the frequency of the current and the voltage show that the current phasor starts to rotate faster/slower than the voltage phasor and the relative angle thereof is continuously increasing/decreasing, and we do here assume that the frequency fi at the location 6 is higher than the frequency f2 at the location 7 for explaining the power swing and pole slip phenomena. The frequency of the current fcu is the same along the radial system as shown in the graph of Fig 6 and is the same as the mean frequency ((f1 +f2)/2) of the two voltages at 6 and 7. Ucosφ is at every moment constant along the radial link interconnecting the location 6 and 7. The phase angle difference between current and voltage measured at the potential pole slip electrical centre is almost constant, which means that these two quantities have the same rotational speed and accordingly identical frequency there. This means that said electrical centre C will be located where the frequency line of the voltage intersects the frequency line of the current (see Fig 6). This understanding may be utilised to determine on which side of such an electrical centre a location for measuring the frequency of current and voltage will be lo- cated. Thus, if such a measurement is carried out and the voltage phasor rotates faster than the current phasor in the complex plane, this location will be to the left of the electrical centre C, i.e. the side 100 referred to generator mode of operation during pole slip. This does then mean that if the current phasor rotates faster than the voltage phasor in the complex plane, the measurement location will be to the right of the point C, i.e. the side 200 referred to motor mode of operation during pole slip.
Fig 7 illustrates how the location of said potential pole slip elec- trical centre is dependent upon the relative magnitude of the voltages at the two ends of the interconnection 4, and it is shown that this electrical centre will be located closer to the end with the lowest magnitude of the voltage.
An arrangement according to the first embodiment of the invention is very schematically illustrated in Fig 8. This arrangement is configured to protect an electrical power system having a block 10 of a generator 1 1 and a transformer 12 connected through a high voltage station 13 to a high voltage system 14 for transmitting electric power. This high voltage system 14 may be considered as an electrical machine with infinite power in an equivalent two machine system. The arrangement has first means 15 located in the interconnection between the generator/transformer block 10 and the high voltage station 13 and configured to measure the frequency of the current (15a) and voltage (15b) at this location 16. The arrangement further comprises a relay in the form of an Intelligent Electronic Device IED 17 including second means 18 receiving values of frequency of the current and the voltage measured and configured to, while considering the electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electro-motive force and an interconnection therebetween, use these values to provide information relating to occurrence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretically electric machines goes past 180° as disclosed above. The arrangement also comprises fourth means 19 receiving said measurement values and configured to use these values of the frequency of the current and voltage measured to determine whether a power swing has occurred in said electrical power system, a power swing being defined as a change of the angle δ between said electro-motive forces as a consequence of an occurrence of any disturbances of the electrical power system, and if an occurrence of a power swing has been determined determine whether said location 16 is along said interconnection located on the motor side or generator side of a said potential pole slip electrical centre, defined as the location where the voltage becomes zero during a said pole slip, is located. Accordingly, this is done by utilising the theory presented above with reference made es- pecially to Fig 6. The fourth means will send this information further to third means 20 also included in said IED, which is configured to based upon information from the second and fourth means carry out a control for protecting equipment of the electrical power system. When a power swing occurs and it is determined that the measuring location 16 is located on the motor side of said electrical centre equipment controlling the operation of the generator/transformer-block may be influenced in the direction of obtaining stability of the electrical power system and/or a member 21 , such as a breaker or a disconnector may be controlled to disconnect the generator from the high voltage power system, or the operation of the generator may be stopped. To the contrary, if it is determined that the measuring location 16 is located on the generator side of said potential pole slip electrical centre it will be possible to wait a predeter- mined period of time after occurrence of a said pole slip, possibly until 2 or 3 pole slips have occurred and then disconnect the generator/transformer-block from the high voltage power system for protecting this block if the electrical power system is still unstable. This also means that if the balance of the electrical power system is recovered after a first pole slip said block will never be disconnected because this is not necessary for protecting it, which results in a considerable saving of costs with respect to prior art arrangements which may disconnect the block as soon as a pole slip occurrence has been determined without considering the location of the pole slip electrical centre.
Fig 9 illustrates an arrangement according to a second embodiment of the invention configured to protect an electrical power system in the form a main electrical power system including a first 2' and a second 3' electrical power system and an intercon- nection 4' therebetween. The parts of the arrangement according to this embodiment corresponding to parts of the embodiment shown in Fig 8 are here provided with the same reference numerals with a prim added thereto. The interconnection is here represented by an impedance. Thus, the two power systems and the interconnection form a radial link, so that the two machine theory is fully applicable. Said first means 15' is configured to measure the frequency of current and voltage at a location 16' on one side of the intercon nection 4'. Furthermore, the arrangement comprises a device 25 configured to use values of the frequency of current and voltage measured and based upon information of properties of the interconnection stored in a memory carry out a calculation while using any of different known models so as to estimate the voltage and current phasors prevailing at the other end of the interconnection 4'. Said prop- erties are the three impedances 22, 4' and 23 shown in Fig 9. However, in the practise only the interconnection impedance 4' is fixed and well known while the two source impedances 22, 23 are varying and very much dependent on actual connection status of both power systems. Said fourth means 19' included in said IED is configured to, upon determination of occurrence of a said power swing, determine a) that said electrical centre is lo- cated within said interconnection 4' if the frequency of the current is higher than the voltage frequency on one end of the interconnection and at the same time the current frequency is lower than the voltage frequency on the other end of the inter- connection and b) that said electrical centre is located in the electrical power system located at the interconnection end with the smallest difference between current frequency and voltage frequency if the current frequency is at both ends of said interconnections at the same time either higher or lower than the voltage frequency. By gaining knowledge in which part of the electrical power system said potential pole slip electrical centre is located appropriate measures may be taken for protecting the system as disclosed above.
Fig 10 illustrates an electrical power system, the Swedish power system, in the form of a meshed electrical power network 30, and an arrangement according to a third embodiment of the invention is configured to protect this meshed electrical power network by selecting two locations 31 , 32 for measuring the fre- quency of the current and voltage by first means 34, 35 so that these measurements will be carried out in the same power flow corridor within the network enabling said second means to consider said meshed electrical power network as an equivalent two machine system as shown in Fig 1 1 . Accordingly, the system shown in Fig 1 1 only differs from that shown in Fig 9 by the fact that measurements are here carried out at two different locations, namely at each end of the interconnection. This means that it is not necessary to be aware of the value of any impedances of said interconnection or of the two sources, but it may be relied only upon said frequency measurements for determining in which part of the equivalent two machine system shown in Fig 1 1 a potential pole slip electrical centre is located. A communication link 33 is here required for exchanging measurement values between the two locations 31 and 32. Finally, Fig 12 illustrates an electrical power system in the form of a meshed electrical power network 40 extending over a wide area, here in Sweden and adjacent countries, having PMUs (Phasor Measurement Unit) 41 -46 on a plurality of different lo- cations within the meshed electrical power network. It is important to properly select locations for the PMUs in order to cover the entire network. These PMUs makes it possible to measure the frequency of the current and voltage and determine the location of the current and voltage phasors in the complex plane with respect to a GPS signal, which means that the phase shift of these phasors on one location with respect to another location may be determined. Said second means is configured to consider at each said location of a PMU the two parts of said meshed electrical power network interconnected there as a said equivalent two machine system and the fourth means is configured to use the values of the frequency of the current and voltage measured by the PMUs at each said location to determine whether a power swing has occurred in said meshed electrical power network and if an occurrence of a power swing has been determined determine that a location of a PMU where a measured current frequency is higher than a measured voltage frequency is on a motor side of the electrical power network and that a location of a PMU where a measured current frequency is lower than the measured voltage frequency is on a generator side of the meshed electric power network. This information from all the PMUs with respect to said locations on motor side or generator side may then be used to determine in which part of said meshed power electrical network a potential pole slip electrical centre is located. A computer 47 may through a suitable computer program carry out calculations for determining location of said potential pole slip electrical centre, so that any possible corrective actions may be taken before the first pole slip occurs in order to minimize its impact on the rest of the electrical power network. Such actions may be to disconnect parts of the network or any equipment thereof. The invention is of course not in any way restricted to the embodiments described above, but many possibilities to modifications thereof would be apparent to a person with skill in the art without departing from the scope of the invention as defined in the appended claims.
As already mentioned above an arrangement according to the invention may be configured to protect other types of electrical power systems than those described above, and measuring of frequencies may be carried out on a different number of locations than shown in the figures.
The arrangement may be designed for protecting equipment of an AC electrical power system also having DC links connected thereto through converter stations.
It is pointed out that the second, third and fourth means in the arrangement according to the invention have not to be physically separated parts, but they may be summarized in one single ob- ject, such as a computer appropriately programmed.

Claims

1 . An arrangement for protecting equipment of an AC electrical power system comprising:
• first means (15, 15', 34, 35, 41 -46) configured to detect electrical power parameters of said power system,
• second means (18, 18') configured to, while considering said electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine (2, 3, 2', 3') with an electro-motive force and an interconnection (4, 4') therebetween, use values of said parameters detected to provide information relating to occurrence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretical electrical machines goes past 180°, and
• third means (20, 20') configured to, based upon said information, carry out a control for protecting equipment of said electrical power system, characterized in that said first means is configured to measure the frequency of the current and voltage at at least one location (16, 16', 31 , 32) in the electrical power system along said interconnection between said two theoretical electric machines, and that the arrangement comprises fourth means (19, 19') configured to use the values of the frequency of the current and voltage measured by said first means to determine whether a power swing has occurred in said electrical power system, a power swing being defined as a change of said angle between said electro-motive forces as a consequence of an occurrence of any disturbances of said electrical power system, and if an occurrence of a power swing has been determined determine whether said measuring location is located on a motor side or a generator side of a potential pole slip electrical centre along said inter- connection, said centre being defined as the location where the voltage becomes zero during a said pole slip, and send this in- formation further to said third means (20, 20') for use in said control for protecting the electrical power system.
2. An arrangement according to claim 1 , characterized in that said fourth means (19, 19') is configured to determine that a power swing occurs if said values of the frequency of the current and voltage delivered by said first means show that the measured current phasor start to rotate faster/slower than the measured voltage phasor and the relative angle thereof is continu- ously increasing/decreasing.
3. An arrangement according to claim 1 or 2, characterized in that said fourth means (19, 19') is configured to, upon determination of occurrence of a said power swing, determine that said location (16, 16', 31 , 32) is located on a motor side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means (15, 15', 34, 35, 41 -46) is higher than the frequency of the voltage at said location and determine that said location is located on a generator side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means is lower than the frequency of the voltage at said location.
4. An arrangement according to claim 3, characterized in that said first means (15) is configured to measure the frequency of the current and voltage at a further said location, and that said fourth means (19) is configured to, upon determination of occurrence of a power swing, determine that said further location is located on a motor side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured by said first means is higher than the frequency of the voltage at said further location and determine that said further location is located on a generator side of said potential pole slip electrical centre in said two machine system if the fre- quency of the current measured by said first means is lower than the frequency of the voltage at said further location.
5. An arrangement according to claim 3, characterized in that it is configured to protect an electrical power system having a block (10) of a generator (1 1 ) and a transformer (12) connected through a high voltage station (13) to a high voltage system (14) for transmitting electric power, that it comprises said first means (15) l ocated i n th e i nterconnection between said genera- tor/transformer-block and said high voltage station, and that said third means (20) is configured to, upon receipt of information from said second means (18) relating to occurrence of a pole slip and information from said fourth means (19) that the measuring location is located on the motor side of said electrical centre in the two machine system, influence equipment controlling the operation of said generator/transformer-block in the direction of obtaining stability of the electrical power system and/or control a member (21 ) to disconnect said generator from said high voltage power system or stop the operation of said generator.
6. An arrangement according to claim 5, characterized in that said third means (20) is configured to, upon receipt of information from said second means (18) relating to occurrence of a pole slip and information from said fourth means (19) that the measuring location is located on the generator side of said electrical centre in the two machine system, wait a predetermined period of time after occurrence of a said pole slip and when said second means then still delivers information that said electrical power system is unstable control said member (21 ) to disconnect said generator/transformer-block from sa i d h ig h voltage power system.
7. An arrangement according to claim 3, characterized in that it is configured to protect an electrical power system having a synchronous machine operating as a motor connected through a high voltage station to a high voltage system for transmitting electric power, that said first means (15) is located in the interconnection between said synchronous machine and said high voltage station (13), and that said third means (20) is configured to, upon receipt of information from said second means (18) relating to occurrence of a pole slip and information from said fourth means that the measuring location is located on the generator side of said electrical centre in the two machine system, influence equipment controlling the operation of said synchro- nous machine in the direction of obtaining stability of the electrical power system and/or control a member (21 ) to disconnect said synchronous machine from said high voltage power system or stop the operation of said synchronous machine.
8. An arrangement according to any of claims 1 -3, characterized in that it is configured to protect an electrical power system in the form of a main electrical power system including a first (2!) and a second (3!) electrical power system and an interconnection (4!) therebetween , that said fourth means (19') is lo- cated at one end of said interconnection connecting to said first electrical power system (2!), that the arrangement comprises a device (25) configured to use the values of the frequency of the current and voltage measured by said first means (15') at said end of the interconnection and based upon information of prop- erties of said interconnection stored in a memory carry out a calculation so as to estimate the voltage and current phasors prevailing at the other end of said interconnection connecting to the second electrical power system (3!), and that said fourth means (19') is configured to, upon determination of occurrence of a said power swing, determine a) that said electrical centre is located within said interconnection (4') if the frequency of the current is higher than the voltage frequency on one end of the interconnection and at the same time the current frequency is lower than the voltage frequency on the other end of the inter- connection and b) that said electrical centre is located in the electrical power system located at the interconnection end with the smallest difference between current frequency and voltage frequency if the current frequency is at both ends of said interconnection at the same time either higher or lower than the voltage frequency.
9. An arrangement according to claim 8, characterized in that said third means (20') is configured to, upon information from said second means (18') relating to occurrence of a pole slip for a previous determination according to a) by said fourth means (19') control a member (21 ') to disconnect said interconnection from the electrical power systems before or after occurrence of a pole slip in order to minimize its impact on said two electrical power systems and for a previous determination according to b) by said fourth means influence equipment controlling the opera- tion of components of said electrical power system having said electrical centre in the direction of obtaining stability of this system and/or control a member to disconnect this electrical power system from said interconnection.
10. An arrangement according to any of claims 1 -3, characterized in that it is configured to protect an electrical power system in the form of a meshed electrical power network (30), that said first means (34, 35) is configured to measure the frequency of the current and voltage at at least two locations (31 , 32) in said meshed electrical power network, that said measuring locations are selected so that measuring is carried out by said first means in the same power flow corridor within the network enabling said second means to consider said meshed electrical power network as an equ ivalent two machi ne system , and that said fourth means is configured to, upon determination of occurrence of a said power swing, determine a) that said electrical centre will be somewhere in between said two measurement locations (31 , 32) within said meshed electrical power network if the current frequency is on one said measuring location higher than the volt- age frequency and at the same time the current frequency is lower than the voltage frequency on said other location, and b) that said electrical centre is located outside the part of the meshed electrical power network limited by said measurement locations and with respect thereto after the one of the two measuring location with the smallest difference between the current frequency and the voltage frequency if at both said measuring locations the current has at the same time either higher or lower frequency than the voltage.
1 1 . An arrangement according claim 10, characterized in that said fourth means is configured to determine that a power swing occurs in said meshed electrical power network if said values of the frequency of the current and voltage delivered by said first means (34, 35) show that the measured current phasor start to rotate faster/slower than the measured voltage phasor at any of said two measuring locations and the relative angle of said current phasor and voltage phasor is continuously increasing/decreasing.
12. An arrangement according to any of claims 1 -3, character- ized in that it is configured to protect an electrical power system in the form of a meshed electrical power network (40) having PMUs (41 -46) (Phasor Measurement Units) on a plurality of different locations within the meshed electrical power network, and that said second means is configured to consider at each said location of a PMU the two parts of said meshed electrical power network interconnected there as a said equivalent two machine system.
13. An arrangement according to claim 12, characterized in that said fourth means is configured to use the values of the frequency of the current and voltage measured by said PMUs (41 - 46) at each said location to determine whether a power swing has occurred in said meshed electrical power network and if an occurrence of a power swing has been determined determine that a location of a PMU where a measured current frequency is higher than a measured voltage frequency is on a motor side of the meshed electrical power network and that a PMU where a measured current frequency is lower than the measured voltage frequency is on a generator side of the meshed electrical power network.
14. An arrangement according to claim 13, characterized in that said fourth means is configured to utilise information from all said PMUs (41 -46) with respect to said locations on motor side or generator side to determine in which part of said meshed electrical power network (40) a potential pole slip electrical centre is located.
15. An arrangement according to any of claims 12-14, characterized in that in that said fourth means is configured to deter- mine that a power swing has occurred within said meshed electrical power network (40) if at any of said measuring locations the measured current phasor starts to rotate faster/slower than the measured voltage phasor and the relative angle of the current phasor and the voltage phasor is continuously increas- ing/decreasing.
16. A method for protecting an AC electrical power system comprising the steps of: a) detecting electrical power parameters of said power system, b) considering said electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine (2, 3, 2', 3') with an electro-motive force and an interconnection (4, 4') therebetween and using said parameters detected to provide information relating to occur- rence of a pole slip in the electric power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretical electric machine goes past 180°, and c) carrying out a control, based upon said information, for protecting equipment of said electrical power system, characterized in that said detecting in step a) comprises measuring of the frequency of the current and voltage at at least one location in the electrical power system along said interconnection between said two theoretical electric machines, that it comprises a further step d) carried out between step a) and b), or between step b) and c) and comprising determining, while using the values of the frequency of the current and voltage measured, whether a power swing has occurred in said electrical power system, a power swing being defined as a change of said angle between said electro-motive forces as a consequence of an occurrence of any disturbances of said electrical power sys- tern, and a step e) carried out if an occurrence of a power swing has been determined i n step d ) and comprising determining whether said measuring location is located on a motor side or a generator side of a potential pole slip electrical centre along said interconnection, said electrical centre being defined as the location where the voltage becomes zero during said pole slip, is located, and that in step c) information relating to the location of said potential pole slip electrical centre thus determined is used in said control for protecting the electrical power system.
17. A method according to claim 16, characterized in that in step e) it is determined that a power swing occurs if said values of the frequency of the current and voltage measured show that the measured current phasor starts to rotate faster/slower than the measured voltage phasor and the relative angle thereof is continuously increasing/decreasing.
18. A method according to claim 16 or 17, characterized in that upon determination of occurrence of a said power swing in step d) it is in step e) determined that the measuring location (16, 16') is located on a motor side of said potential pole slip electrical centre in said two machine system if the frequency of the current measured is higher than the frequency of the voltage at said location and determined that the measuring location is located on a generator side of said potential pole slip electrical centre in said two machine system if the frequency of the cur- rent measured is lower than the frequency of the voltage at said location.
19. A computer program loadable directly into the internal mem- ory of a computer, which computer program comprises computer program code for causing the computer, for an AC electrical power system:
- to obtain detection of electrical power parameters of said power system, - to calculate, while considering said electrical power system as an equivalent two machine system having at each of opposite ends thereof one theoretical electric machine with an electromotive force and an interconnection therebetween and while using said parameters detected, data relating to occurrence of a pole slip in the electrical power system defined as a condition in which a mutual angle of the electro-motive forces of said two theoretical electric machine goes past 180°,
- to obtain a control, based upon said data, for protecting equipment of said electrical power system, - to obtain said detecting by obtaining measuring of the frequency of the current and voltage at at least one location in the electrical power system along said interconnection between said two theoretical electric machines,
- to obtain determining, while using the values of the frequency of the current and voltage measured , whether a power swing has occurred in said electrical power system , a power swing being defined as a change of said angle between said electromotive forces as a consequence of an occurrence of any disturbances of said electrical power system, - to obtain determining whether said measuring location is located on a motor side or a generator side of a potential pole slip electrical centre along said interconnection, said centre being defined as the location where the voltage becomes zero during said pole slip, is located, and - to obtain said control for protecting the electrical power system by using information relating to the location of said potential pole slip electrical centre thus determined.
20. A computer program product comprising a data storage medium readable by an electronic unit, a computer program according to claim 19 being stored on said data storage medium.
21 . An AC electrical power system, characterized in that it comprises an arrangement for protecting equipment of said power system according to any of claims 1 -15.
22. Use of an arrangement according to any of claims 1 -15 for protecting equipment of an AC electrical power system.
PCT/EP2009/057350 2009-06-15 2009-06-15 An arrangement for protecting equipment of a power system WO2010145684A1 (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
RU2012101239/07A RU2503111C2 (en) 2009-06-15 2009-06-15 Device for protection of equipment of power system
CN200980159450.2A CN102577006B (en) 2009-06-15 2009-06-15 An arrangement for protecting equipment of a power system
PCT/EP2009/057350 WO2010145684A1 (en) 2009-06-15 2009-06-15 An arrangement for protecting equipment of a power system
EP20090779747 EP2443718B1 (en) 2009-06-15 2009-06-15 An arrangement for protecting equipment of a power system
US13/326,597 US8340930B2 (en) 2009-06-15 2011-12-15 Arrangement for protecting equipment of a power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/EP2009/057350 WO2010145684A1 (en) 2009-06-15 2009-06-15 An arrangement for protecting equipment of a power system

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US13/326,597 Continuation US8340930B2 (en) 2009-06-15 2011-12-15 Arrangement for protecting equipment of a power system

Publications (1)

Publication Number Publication Date
WO2010145684A1 true WO2010145684A1 (en) 2010-12-23

Family

ID=41786494

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2009/057350 WO2010145684A1 (en) 2009-06-15 2009-06-15 An arrangement for protecting equipment of a power system

Country Status (5)

Country Link
US (1) US8340930B2 (en)
EP (1) EP2443718B1 (en)
CN (1) CN102577006B (en)
RU (1) RU2503111C2 (en)
WO (1) WO2010145684A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014094985A1 (en) 2012-12-21 2014-06-26 Abb Technology Ag A method of out of step detection in electrical power network
CN104459460A (en) * 2014-11-06 2015-03-25 中国南方电网有限责任公司 Electric system out-of-step oscillation section capture method

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9270120B2 (en) * 2012-10-09 2016-02-23 Abb Research Ltd. Methods, systems, and computer readable media for adaptive out of step protection for power generators with load resynchronization capability
US10024920B2 (en) 2013-08-16 2018-07-17 General Electric Company Systems and methods for swing angle estimation in an electrical power system
US10436823B2 (en) 2013-08-16 2019-10-08 General Electric Company Systems and methods for swing angle estimation in an electrical power system
CN110850232B (en) * 2019-11-13 2021-10-01 云南电网有限责任公司 Power grid fault diagnosis system and method based on relay protection auxiliary decision system
CN110889602B (en) * 2019-11-13 2022-04-15 云南电网有限责任公司 Relay protection multi-source master station fusion decision rapid support system and method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001082444A1 (en) * 2000-04-20 2001-11-01 The Power Generation Company Ltd. Generator protection apparatus
US20030200038A1 (en) * 2002-04-17 2003-10-23 Schweitzer Edmund O. Protective relay with synchronized phasor measurement capability for use in electric power systems
WO2007048045A2 (en) * 2005-10-21 2007-04-26 Schweitzer Engineering Laboratories, Inc. System and method for detecting power system conditions
US20090089608A1 (en) * 2007-09-28 2009-04-02 Armando Guzman-Casillas Systems and methods for power swing and out-of-step detection using time stamped data

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3048744A (en) * 1953-08-25 1962-08-07 English Electric Co Ltd Electrical protective relay systems
US3535591A (en) * 1968-01-02 1970-10-20 Sola Basic Ind Inc Monitoring system for polyphase electric supply system
CH612046A5 (en) * 1977-04-01 1979-06-29 Bbc Brown Boveri & Cie
CH623963A5 (en) * 1977-10-28 1981-06-30 Bbc Brown Boveri & Cie
JPS5854824A (en) * 1981-09-29 1983-03-31 株式会社東芝 Protective relay unit
FR2690573B1 (en) * 1992-04-28 1997-05-09 Merlin Gerin DEVICE FOR CONTROLLING HOMOPOLAR FAULT IN AN ELECTRICAL DISTRIBUTION NETWORK.
US7457088B2 (en) * 2004-09-29 2008-11-25 Schweitzer Engineering Laboratories, Inc. Systems and methods for protection of electrical networks
RU2316098C1 (en) * 2006-06-20 2008-01-27 Общество с ограниченной ответственностью "Пассат" (ООО "Пассат") Method for detecting asynchronous mode in power system
ATE523938T1 (en) * 2006-06-29 2011-09-15 Abb Technology Ltd DISTANCE PROTECTION METHOD AND DISTANCE PROTECTION RELAYS
US8655608B2 (en) * 2007-09-28 2014-02-18 Schweitzer Engineering Laboratories Inc Symmetrical component amplitude and phase comparators for line protection using time stamped data
BRPI0722142A2 (en) * 2007-10-25 2014-04-15 Abb Technology Ag DIFFERENTIAL PROTECTION METHOD, SYSTEM AND DEVICE

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001082444A1 (en) * 2000-04-20 2001-11-01 The Power Generation Company Ltd. Generator protection apparatus
US20030200038A1 (en) * 2002-04-17 2003-10-23 Schweitzer Edmund O. Protective relay with synchronized phasor measurement capability for use in electric power systems
WO2007048045A2 (en) * 2005-10-21 2007-04-26 Schweitzer Engineering Laboratories, Inc. System and method for detecting power system conditions
US20090089608A1 (en) * 2007-09-28 2009-04-02 Armando Guzman-Casillas Systems and methods for power swing and out-of-step detection using time stamped data

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014094985A1 (en) 2012-12-21 2014-06-26 Abb Technology Ag A method of out of step detection in electrical power network
CN104459460A (en) * 2014-11-06 2015-03-25 中国南方电网有限责任公司 Electric system out-of-step oscillation section capture method

Also Published As

Publication number Publication date
US8340930B2 (en) 2012-12-25
RU2012101239A (en) 2013-07-27
CN102577006B (en) 2014-10-01
US20120081817A1 (en) 2012-04-05
CN102577006A (en) 2012-07-11
RU2503111C2 (en) 2013-12-27
EP2443718A1 (en) 2012-04-25
EP2443718B1 (en) 2014-04-23

Similar Documents

Publication Publication Date Title
US8340930B2 (en) Arrangement for protecting equipment of a power system
US9784781B2 (en) Islanding detection reliability in electricity distribution network
Lagos et al. Microgrid protection against internal faults: Challenges in islanded and interconnected operation
US9494635B2 (en) Islanding detection in electricity distribution network
US20080211511A1 (en) Method of Generating Fault Indication in Feeder Remote Terminal Unit for Power Distribution Automation System
CN105207178B (en) A kind of based on the DG Distribution Network Failure accessed location and isolated island division methods
Nagpal et al. Protection challenges and practices for interconnecting inverter based resources to utility transmission systems
Godoy et al. Tutorial on single-pole tripping and reclosing
Memon et al. Microgrid protection with conventional and adaptive protection schemes
CN104377722A (en) Systems and methods for power swing angle estimation in an electrical power system
Nagpal et al. BC hydro protection interconnection practices for sources with inverter or converter interface
Alahäivälä et al. Analysis of open phase condition influence on an induction motor
Salehi et al. Developing virtual protection system for control and self-healing of power system
Chan et al. An impact study of ROCOF relays for islanding detection
Kobet et al. Justifying pilot protection on transmission lines
Brucoli Fault behaviour and fault detection in islanded inverter-only microgrids
Sanaye-Pasand et al. Study, comparison and simulation of power system swing detection and prediction method
Miller et al. Fault contribution considerations for wind plant system design and power system protection issues
Paunescu et al. Out of step protection in modern power networks
Penaloza et al. Performance analysis of a communication-supported earth fault protection system of medium voltage loop and meshed networks
Olofsson Transmission line protection performance in presence of power electronic-interfaced devices: Impact and needed countermeasures in the Swedish transmission system
Ruppert et al. Inverter-Based Radial Distribution System and Associated Protective Relaying
Kumpulainen et al. Loss-of-mains protection–still an issue with distributed generation
Usta A power based digital algorithm for the protection of embedded generators
Banu Power Distribution System Protection Methodologies with Inverter-Based Resources Integrated Microgrids

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 200980159450.2

Country of ref document: CN

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 09779747

Country of ref document: EP

Kind code of ref document: A1

DPE1 Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101)
WWE Wipo information: entry into national phase

Ref document number: 2009779747

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 305/CHENP/2012

Country of ref document: IN

WWE Wipo information: entry into national phase

Ref document number: 2012101239

Country of ref document: RU