WO2010025816A1 - An assembly and method for placing a cement plug - Google Patents

An assembly and method for placing a cement plug Download PDF

Info

Publication number
WO2010025816A1
WO2010025816A1 PCT/EP2009/005896 EP2009005896W WO2010025816A1 WO 2010025816 A1 WO2010025816 A1 WO 2010025816A1 EP 2009005896 W EP2009005896 W EP 2009005896W WO 2010025816 A1 WO2010025816 A1 WO 2010025816A1
Authority
WO
WIPO (PCT)
Prior art keywords
assembly
placing
cement
well
cement plug
Prior art date
Application number
PCT/EP2009/005896
Other languages
French (fr)
Inventor
Kévin MAUTH
Juan Carrasquilla
Original Assignee
Services Petroliers Schlumberger
Schlumberger Technology B.V.
Schlumberger Holdings Limited
Schlumberger Canada Limited
Prad Research And Development Limited
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Services Petroliers Schlumberger, Schlumberger Technology B.V., Schlumberger Holdings Limited, Schlumberger Canada Limited, Prad Research And Development Limited filed Critical Services Petroliers Schlumberger
Priority to US13/062,563 priority Critical patent/US20110162844A1/en
Publication of WO2010025816A1 publication Critical patent/WO2010025816A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • E21B33/14Methods or devices for cementing, for plugging holes, crevices or the like for cementing casings into boreholes

Definitions

  • An aspect of the invention relates to an assembly for placing a cement plug in a well- bore. Another aspect of the invention also relates to a corresponding cement plug placing method.
  • a particular application of the invention relates to the oilfield industry, for example in cementing operation.
  • the fluid injecting operations serves various purposes, for example delivering a cement slurry for borehole cementing operation. These operations are well known in the oilfield industry.
  • cement plug placement techniques recommend the use of a stinger for the section of the drill pipe immersed in the fluid in the borehole, the stinger having a diameter substantially smaller than the well-bore diameter.
  • the preferred mud removal technique namely turbulent flow is nearly impossible to achieve due to the important gap (annulus) existing between the stinger and the well- bore wall.
  • the cement sets with the drill pipe immersed in the well-bore.
  • the drill pipe is pulled through the cement plug which may result in contamination.
  • the plug placement assembly must be completely pulled out of the well-bore before resuming any further operation to be conducted in the well-bore, which leads to a loss in rig time.
  • the invention relates to an assembly for placing a cement plug in a well-bore comprising a landing and disconnecting collar, a shoe track, a circulation element, and a guide shoe, said elements forming an internal conduit, the circulation element comprising side conduits directed towards a well-bore wall.
  • the assembly diameter is such as to create a narrow annulus in which a fluid pumped through the side conduits circulates in the annulus according to a turbulent flow.
  • the assembly further comprises a sealing element comprising a bottom sealing element.
  • the landing and disconnecting collar, shoe track, circulation element, and guide shoe are made of material that are drillable, said elements forming the cement plug when a cement slurry is set into the annulus and the internal conduit.
  • the assembly may further comprise a top sealing element.
  • the material may be chosen among the group of material comprising Aluminum, fiberglass, cement, plastic, and carbon fiber reinforced material.
  • the assembly may further comprise a centralizer.
  • the guide shoe may further comprise a differential pressure valve for reducing any piston effect on a geological formation surrounding the well-bore.
  • the sealing element may be a flexible cup-like packer or an external casing packer.
  • the invention relates to a method of placing a cement plug in a well-bore comprising the steps of:
  • the length of the cement plug may be defined by coupling casing joints during the assembling step.
  • the drill pipe may be rotated for sweeping a whole circumference of the well-bore wall during the cleaning step.
  • the invention enables enhancing the safety and the quality of the cement plug placement operation.
  • the invention allows high pump rates throughout the operation, and avoids having to balance the plug. Furthermore, the invention eliminates contamination caused by pulling the drill pipe through the plug after placement, and reduces the risk of cementing the drill pipe in the well-bore.
  • Figure 1 schematically shows an onshore hydrocarbon well location
  • Figure 2 schematically shows the assembly for placing a cement plug in a well-bore
  • FIGS 3 to 7 schematically and partially illustrate the cement plug placement method and the fluid displacement during the cement plug placement operation.
  • FIG. 1 schematically shows an onshore hydrocarbon well location and equipments WE above a hydrocarbon geological formation GF after drilling operation has been carried out and after a drill pipe DP has been run.
  • the well-bore WB is an open-hole OH generally filled with various fluid mixtures (e.g. the drilling mud or the like).
  • the well-bore WB may also be partially cased CH.
  • the equipment WE comprises a drilling rig DR for running the drill pipe DP in the well-bore, cementing equipment comprising cement silo CR and pumping arrangement CP, and a well head and stuffing box arrangement WH providing a sealing for deploying the drill pipe DP or pumping down the cement into the generally pressurized well-bore WB.
  • cementing operations are generally undertaken to seal the annulus AN (i.e. the space between the well-bore WB and the casing where fluid can flow).
  • a first application is primary cementing which purpose is to achieve hydraulic isolation around the casing.
  • Other applications are remedial cementing which purposes are to stabilize the well-bore, to seal a lost circulation zone, to enable deflecting a subsequent drilling assembly into a different path than that previously drilled, to set a plug in an existing well or to plug a well so that it may be abandoned.
  • the cement may be pumped into the drill pipe DP through a plug placement assembly 1 near the bottom of the bore-hole after the assembly has been positioned at the desired location.
  • Cementing engineers prepare the cementing operations by determining the volume and physical properties of cement slurry and other fluids pumped before and after the cement slurry.
  • chemical additives are mixed with the cement slurry in order to modify the characteristics of the slurry or set cement.
  • Cement additives may be broadly categorized as accelerators (i.e. for reducing the time required for the set cement to develop sufficient compressive strength to enable further operations to be carried out), retarders (i.e. for increasing the thickening time of cement slurries to enable proper placement), dispersants (i.e. for reducing the cement slurry viscosity to improve fluid-flow characteristics), extenders (i.e.
  • weighting agents i.e. for increasing or lightening the slurry weight
  • fluid-loss or lost-circulation additives i.e. for controlling the loss of fluid to the formation through filtration
  • special additives designed for specific operating conditions.
  • FIG. 2 schematically shows the assembly 1 for placing a cement plug in a well-bore WB according to a cross-section view.
  • the plug placement assembly 1 comprises a landing and disconnecting collar 2, a shoe track 3, a circulation element 4, a guide shoe 5 and a sealing element 6. All these elements have a cylindrical section and define an internal conduit 10.
  • the landing collar and disconnecting 2 is installed immediately under the bottom of the casing string or the drill pipe DP.
  • the landing and disconnecting collar is a component on which the cementing plugs BP, TP land during the cementing operation.
  • the landing and disconnecting collar is coupled to the drill pipe via a releasing mechanism (not shown), for example through a known shear-pinned coupling.
  • the landing and disconnecting collar may be disconnected from the drill pipe by means of a downstream pressure bump, for example by breaking the shear- pinned coupling of the releasing mechanism.
  • the landing and disconnecting collar may comprise a valve arrangement (not shown).
  • the landing and disconnecting collar is made of plastics, cement, carbon fiber reinforced material or other high strength and drillable material.
  • the shoe track 3 is a closed space between the landing and disconnecting collar 2 and the guide shoe 5.
  • the principal function of this space is to ensure that the guide shoe is surrounded in high-quality cement such that any contamination that may bypass the top plug is safely contained within the shoe track.
  • the shoe track may be a casing portion, namely a casing joint, made of fiber glass, carbon fiber reinforced material, aluminum or any other high strength and drillable material.
  • the shoe track may comprise a plurality of casing joint coupled together.
  • the shoe track may be fitted with one or more centralizer 7 for keeping the bottom hole assembly in the center of the tubing, casing or well-bore (Figure 2 only show an embodiment comprising one centralizer).
  • the centralizer comprises bow-spring profile made of plastic or light metal like aluminum.
  • the circulation element 4 is a component that allows a direct communication between the shoe track 3 and the annulus AN.
  • the circulation element may comprise a circulation valve (not shown) that may be operated to open and close on demand.
  • the circulation element 4 comprises side conduits 8 extending radially from the internal conduit 10 towards the annulus AN2 and disposed all around the circulation element.
  • the circulation element enables the circulation of fluids, namely pumping of fluid or cement slurry from the casing string or drill pipe directly into the annulus for well-bore wall cleaning purposes or for placing a cement plug, respectively.
  • the side conduits 8 are represented as round holes in the Figures, they may have other shapes.
  • the side conduits 8 forming helical slots may be more efficient in distributing the fluid around the circumference of the cement plug placement assembly.
  • the circulation element is made of plastics, cement, carbon fiber reinforced material or other high strength and drillable material.
  • the guide shoe 5 is a tapered, e.g. having bullet-nosed element installed on the bottom of the assembly 1 , immediately under the circulation element 4.
  • the guide shoe function is to guide the drill pipe DP toward the center of the hole of the well- bore and minimizes problems associated with hitting rock ledges or washouts in the well-bore as the drill pipe is lowered into the well.
  • the external face of the guide shoe is made from steel, generally matching the assembly in size.
  • the inside part of the guide shoe is made of cement, plastic, carbon fiber reinforced material or other high strength and drillable material. It can be drilled out if the well is to be deepened beyond the cement plug point.
  • the guide shoe 5 may be replaced by a float shoe comprising an additional check valve.
  • the guide shoe 5 may comprise a differential pressure valve 9 that allows circulation of fluid through the guide shoe port reducing any piston effect on the formation GF.
  • the assembly may be sealed downwards by means with either a rubber wiper plug or a ball that seats in the guide shoe at the bottom of the assembly (not shown). When sealed downwards, the downward flow is shut off and the fluid flow is forced to flow out of the assembly via the side conduits 8 of the circulation element 4.
  • the sealing element 6 comprises a bottom sealing element 6A that seals the communication at the end of the casing shoe in order to prevent downward flow in the annulus behind the plug placement assembly.
  • the sealing element is a ring positioned around the casing shoe and/or the circulation element and contacting the well-bore wall WBW.
  • the sealing element is a flexible cup-like packer that may slide down the well-bore wall during running operations.
  • the sealing element may be made of HydrobonderTM manufactured by the company Weatherford.
  • the sealing element may be an external casing packer which offers self support to the assembly and hydraulic isolation in the annulus. The use of such sealing elements eliminates the need for viscous pills or other supporting means to support the cement plug.
  • the sealing element 6 may also comprise a top sealing element 6B, similar to the bottom sealing element 6A, that seals the communication at the top of the shoe track or at the landing collar in order to prevent upward flow in the annulus AN1 above the plug placement assembly.
  • a top sealing element 6B similar to the bottom sealing element 6A, that seals the communication at the top of the shoe track or at the landing collar in order to prevent upward flow in the annulus AN1 above the plug placement assembly.
  • the cement plug placement assembly 1 diameter is such as to create a narrow annulus portion AN2 compared to the standard annulus AN1 defined by the drill pipe DP.
  • a fluid pumped through the side conduits 8 circulates in the narrow annulus portion AN2 according to a turbulent flow.
  • FIG. 3 illustrates the assembly 1 as hereinbefore described after having been assembled and run at the desired depth, and during cleaning step.
  • the cement plug placing assembly 1 is assembled at the surface.
  • the assembly is coupled to the drill pipe DP.
  • the sealing elements are also made up as part of the assembly prior to running into the well- bore. The sealing elements slide down the well-bore wall.
  • the assembly also comprises the top sealing element 6B, the assembly is more difficult to run because it would prevent upwards circulation of the fluids.
  • this particular embodiment is preferably used on open-hole squeeze cementing applications.
  • a second step S2 the cement plug placing assembly 1 is run to the desired depth by means of the drill pipe DP of the corresponding length.
  • a cleaning process may begun by closing the circulation through the casing shoe 5 and circulating fluid F1 through the side conduits 8 of the circulation element 4.
  • the produced jetting effect towards the bore-hole wall WBW and turbulent flow TF in the annulus helps in removing the mud cake MC formed on the well-bore wall WBW.
  • the drill pipe DP may be rotated RT for sweeping the whole circumference of the well-bore wall WBW. Pumping fluids in turbulent flow allows better removal of the mud cake MC and thus will improve the cement bond with the well-bore wall WBW.
  • FIG. 4 illustrates the assembly 1 during a first displacement phase.
  • the cement slurry CS is mixed and pump into the drill pipe.
  • the bottom plug BP is launched upstream of the cement slurry CS to minimize contamination by fluids inside the drill pipe prior to cementing.
  • the top plug TP is launched downstream the cement slurry CS.
  • the top TP and bottom BP plugs are rubber or plastics plugs separating the cement slurry from other fluids present on the drill pipe.
  • the top and bottom plugs are usual cementing plug typically used in cementing operation.
  • the top plug comprises a solid core.
  • the bottom plug comprises a hollow core and a rupture diaphragm RD.
  • FIG. 5 illustrates the assembly 1 during a second displacement phase.
  • the bottom plug BP, cement slurry CS and top plug TP are displaced through the drill pipe DP towards the cement plug placement assembly 1.
  • the bottom plug BP already landed in the landing and disconnecting collar 2.
  • the cement slurry CS is pushed downwards by the top plug TP which is pushed by a fluid F2, e.g. a mud pumped downwards from the surface.
  • the diaphragm RD in the plug body ruptures to allow the cement slurry CS to pass through after the plug reaches the landing and disconnecting collar 2.
  • the cement slurry CS flows through the bottom plug BP, the internal conduit of the assembly 10. Then the cement slurry CS flows through the side conduits 8 into the annulus AN2 between the shoe track 3, the sealing element 6A, 6B and the wall WBW of the well- bore.
  • Figure 6 illustrates the assembly 1 at the end of the displacement phase.
  • the top plug TP lands onto the bottom plug BP.
  • This provides a sudden pressure bump PU giving a positive indication of contact with the landing and disconnecting collar 2 and the bottom plug BP.
  • the increase in pump pressure may be detected by an appropriate detector (not shown) at the surface.
  • the drill pipe DP is also disconnected from the landing and disconnecting collar 2 of the cement plug placement assembly 1.
  • the disconnection of the drill pipe DP from the landing and disconnecting collar 2 is triggered by the pressure bump.
  • Figure 7 illustrates the assembly 1 during disconnection.
  • a seventh step S7 the drill pipe DP is at least partially pulled out of the hole POOH of the well-bore. Since the whole assembly 1 is drillable, it is not necessary to pull the drill pipe DP completely out of the hole. Thus, the chance of contamination and the risk of the cement setting with the drill pipe DP immersed are also reduced. With the invention, there is no time spent in plug balancing. A fluid may be circulated through the drill pipe for cleaning purpose. Once the cement is set, the cement plug PG is formed by the cement filled in landing and disconnecting collar 2, shoe track 3, circulation element 4, guide shoe 5, internal conduit 10 and annulus portion AN2.
  • the cement plug CP may be used for a variety of applications including hydraulic isolation, provision of a secure mechanical platform, and in window-milling operations for sidetracking a new well-bore, or a horizontal or deviated well-bore.
  • the invention is not limited to onshore hydrocarbon well and can also be used in relation with offshore hydrocarbon well. Further, though a vertical well-bore has been depicted in the drawings, the invention may also apply in a horizontal or deviated well-bore.
  • the invention has been presented with a particular cementing application, it is not limited to the placement of a cement plug which purpose is to achieve hydraulic isolation at a particular location in the well-bore.
  • the invention may serve other purposes, for example in remedial cementing through the placement of drillable casing patch which purpose is to stabilize the well-bore or to seal a lost circulation zone, or to set a plug in an existing well so that it may be abandoned.
  • a particular application of the invention relating to the oilfield industry has been described.
  • the invention is also applicable to other kind of industry, e.g. the construction industry or the like.
  • the drawings and their description hereinbefore illustrate rather than limit the invention.

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Earth Drilling (AREA)

Abstract

An assembly for placing a cement plug (1) in a well-bore comprises a landing and disconnecting collar (2), a shoe track (3), a circulation element (4), and a guide shoe (5), said elements forming an internal conduit (10), the circulation element (4) comprising side conduits (8) directed towards a well-bore wall (WBW). The assembly (1) diameter is such as to create a narrow annulus (AN2) in which a fluid pumped through the side conduits (8) circulates in the annulus according to a turbulent flow. The assembly (1) further comprises a sealing element (6) comprising a bottom sealing element (6A). The landing and disconnecting collar (2), shoe track (3), circulation element (4), and guide shoe (5) are made of material that are drillable, the elements forming the cement plug when a cement slurry (CS) is set into the annulus (AN2) and the internal conduit (10).

Description

AN ASSEMBLY AND METHOD FOR PLACING A CEMENT PLUG
FIELD OF THE INVENTION
An aspect of the invention relates to an assembly for placing a cement plug in a well- bore. Another aspect of the invention also relates to a corresponding cement plug placing method.
A particular application of the invention relates to the oilfield industry, for example in cementing operation.
BACKGROUND OF THE INVENTION
During a hydrocarbon well drilling operation and after a hydrocarbon well has been drilled, various fluid injecting operations are generally carried out. The fluid injecting operations serves various purposes, for example delivering a cement slurry for borehole cementing operation. These operations are well known in the oilfield industry.
Typically, cement plug placement techniques recommend the use of a stinger for the section of the drill pipe immersed in the fluid in the borehole, the stinger having a diameter substantially smaller than the well-bore diameter. In this condition, the preferred mud removal technique, namely turbulent flow is nearly impossible to achieve due to the important gap (annulus) existing between the stinger and the well- bore wall. Further, there is also a risk that the cement sets with the drill pipe immersed in the well-bore. Furthermore, after a cement plug has been placed, the drill pipe is pulled through the cement plug which may result in contamination. Finally, the plug placement assembly must be completely pulled out of the well-bore before resuming any further operation to be conducted in the well-bore, which leads to a loss in rig time.
SUMMARY OF THE INVENTION
It is an object of the invention to propose an assembly for placing a cement plug in a well-bore that overcomes one or more of the limitations of the existing cementing apparatus or method for well-bore.
According to an aspect, the invention relates to an assembly for placing a cement plug in a well-bore comprising a landing and disconnecting collar, a shoe track, a circulation element, and a guide shoe, said elements forming an internal conduit, the circulation element comprising side conduits directed towards a well-bore wall. The assembly diameter is such as to create a narrow annulus in which a fluid pumped through the side conduits circulates in the annulus according to a turbulent flow. The assembly further comprises a sealing element comprising a bottom sealing element. The landing and disconnecting collar, shoe track, circulation element, and guide shoe are made of material that are drillable, said elements forming the cement plug when a cement slurry is set into the annulus and the internal conduit. The assembly may further comprise a top sealing element. The material may be chosen among the group of material comprising Aluminum, fiberglass, cement, plastic, and carbon fiber reinforced material. The assembly may further comprise a centralizer.
The guide shoe may further comprise a differential pressure valve for reducing any piston effect on a geological formation surrounding the well-bore. The sealing element may be a flexible cup-like packer or an external casing packer.
According to a further aspect, the invention relates to a method of placing a cement plug in a well-bore comprising the steps of:
- assembling a cement plug placing assembly and coupling said assembly to a drill pipe at the surface,
- running the cement plug placing assembly to a desired depth,
- cleaning the well-bore wall by circulating fluid in said assembly by producing a jetting effect towards the well-bore wall and a turbulent flow in a limited annulus portion defined between the cement plug placing assembly and the well-bore wall, - mixing and pumping a cement slurry into the drill pipe,
- displacing the cement slurry towards the cement plug placing assembly and into the annulus portion, and
- disconnecting the drill pipe after a pressure bump at the end of the displacing step. The length of the cement plug may be defined by coupling casing joints during the assembling step.
The drill pipe may be rotated for sweeping a whole circumference of the well-bore wall during the cleaning step. The invention enables enhancing the safety and the quality of the cement plug placement operation.
Further, the invention allows high pump rates throughout the operation, and avoids having to balance the plug. Furthermore, the invention eliminates contamination caused by pulling the drill pipe through the plug after placement, and reduces the risk of cementing the drill pipe in the well-bore.
In addition, it is not necessary anymore to create a bottom support for the plug cement. These and other aspects of the invention will be apparent from and elucidated with reference to the embodiments described hereinafter.
BRIEF DESCRIPTION OF THE DRAWINGS
The present invention is illustrated by way of example and not limited to the accompanying figures, in which like references indicate similar elements:
Figure 1 schematically shows an onshore hydrocarbon well location;
Figure 2 schematically shows the assembly for placing a cement plug in a well-bore; and
Figures 3 to 7 schematically and partially illustrate the cement plug placement method and the fluid displacement during the cement plug placement operation.
DETAILED DESCRIPTION OF THE INVENTION
Figure 1 schematically shows an onshore hydrocarbon well location and equipments WE above a hydrocarbon geological formation GF after drilling operation has been carried out and after a drill pipe DP has been run. At this stage, the well-bore WB is an open-hole OH generally filled with various fluid mixtures (e.g. the drilling mud or the like). The well-bore WB may also be partially cased CH. The equipment WE comprises a drilling rig DR for running the drill pipe DP in the well-bore, cementing equipment comprising cement silo CR and pumping arrangement CP, and a well head and stuffing box arrangement WH providing a sealing for deploying the drill pipe DP or pumping down the cement into the generally pressurized well-bore WB. Subsequently, cementing operations are generally undertaken to seal the annulus AN (i.e. the space between the well-bore WB and the casing where fluid can flow). A first application is primary cementing which purpose is to achieve hydraulic isolation around the casing. Other applications are remedial cementing which purposes are to stabilize the well-bore, to seal a lost circulation zone, to enable deflecting a subsequent drilling assembly into a different path than that previously drilled, to set a plug in an existing well or to plug a well so that it may be abandoned. The cement may be pumped into the drill pipe DP through a plug placement assembly 1 near the bottom of the bore-hole after the assembly has been positioned at the desired location.
Cementing engineers prepare the cementing operations by determining the volume and physical properties of cement slurry and other fluids pumped before and after the cement slurry. In many situations, chemical additives are mixed with the cement slurry in order to modify the characteristics of the slurry or set cement. Cement additives may be broadly categorized as accelerators (i.e. for reducing the time required for the set cement to develop sufficient compressive strength to enable further operations to be carried out), retarders (i.e. for increasing the thickening time of cement slurries to enable proper placement), dispersants (i.e. for reducing the cement slurry viscosity to improve fluid-flow characteristics), extenders (i.e. for decreasing the density or increasing the yield of a cement slurry), weighting agents (i.e. for increasing or lightening the slurry weight), fluid-loss or lost-circulation additives (i.e. for controlling the loss of fluid to the formation through filtration) and special additives designed for specific operating conditions.
Figure 2 schematically shows the assembly 1 for placing a cement plug in a well-bore WB according to a cross-section view. The plug placement assembly 1 comprises a landing and disconnecting collar 2, a shoe track 3, a circulation element 4, a guide shoe 5 and a sealing element 6. All these elements have a cylindrical section and define an internal conduit 10.
The landing collar and disconnecting 2 is installed immediately under the bottom of the casing string or the drill pipe DP. The landing and disconnecting collar is a component on which the cementing plugs BP, TP land during the cementing operation. The landing and disconnecting collar is coupled to the drill pipe via a releasing mechanism (not shown), for example through a known shear-pinned coupling. The landing and disconnecting collar may be disconnected from the drill pipe by means of a downstream pressure bump, for example by breaking the shear- pinned coupling of the releasing mechanism. The landing and disconnecting collar may comprise a valve arrangement (not shown). The landing and disconnecting collar is made of plastics, cement, carbon fiber reinforced material or other high strength and drillable material.
The shoe track 3 is a closed space between the landing and disconnecting collar 2 and the guide shoe 5. The principal function of this space is to ensure that the guide shoe is surrounded in high-quality cement such that any contamination that may bypass the top plug is safely contained within the shoe track. The shoe track may be a casing portion, namely a casing joint, made of fiber glass, carbon fiber reinforced material, aluminum or any other high strength and drillable material. The shoe track may comprise a plurality of casing joint coupled together. The shoe track may be fitted with one or more centralizer 7 for keeping the bottom hole assembly in the center of the tubing, casing or well-bore (Figure 2 only show an embodiment comprising one centralizer). The centralizer comprises bow-spring profile made of plastic or light metal like aluminum. The circulation element 4 is a component that allows a direct communication between the shoe track 3 and the annulus AN. The circulation element may comprise a circulation valve (not shown) that may be operated to open and close on demand. The circulation element 4 comprises side conduits 8 extending radially from the internal conduit 10 towards the annulus AN2 and disposed all around the circulation element. The circulation element enables the circulation of fluids, namely pumping of fluid or cement slurry from the casing string or drill pipe directly into the annulus for well-bore wall cleaning purposes or for placing a cement plug, respectively. Though, the side conduits 8 are represented as round holes in the Figures, they may have other shapes. As an example, the side conduits 8 forming helical slots may be more efficient in distributing the fluid around the circumference of the cement plug placement assembly. The circulation element is made of plastics, cement, carbon fiber reinforced material or other high strength and drillable material. The guide shoe 5 is a tapered, e.g. having bullet-nosed element installed on the bottom of the assembly 1 , immediately under the circulation element 4. The guide shoe function is to guide the drill pipe DP toward the center of the hole of the well- bore and minimizes problems associated with hitting rock ledges or washouts in the well-bore as the drill pipe is lowered into the well. The external face of the guide shoe is made from steel, generally matching the assembly in size. The inside part of the guide shoe is made of cement, plastic, carbon fiber reinforced material or other high strength and drillable material. It can be drilled out if the well is to be deepened beyond the cement plug point. The guide shoe 5 may be replaced by a float shoe comprising an additional check valve. The guide shoe 5 may comprise a differential pressure valve 9 that allows circulation of fluid through the guide shoe port reducing any piston effect on the formation GF. The assembly may be sealed downwards by means with either a rubber wiper plug or a ball that seats in the guide shoe at the bottom of the assembly (not shown). When sealed downwards, the downward flow is shut off and the fluid flow is forced to flow out of the assembly via the side conduits 8 of the circulation element 4. The sealing element 6 comprises a bottom sealing element 6A that seals the communication at the end of the casing shoe in order to prevent downward flow in the annulus behind the plug placement assembly. The sealing element is a ring positioned around the casing shoe and/or the circulation element and contacting the well-bore wall WBW. Advantageously, the sealing element is a flexible cup-like packer that may slide down the well-bore wall during running operations. As an example, the sealing element may be made of Hydrobonder™ manufactured by the company Weatherford. As another example (not shown), the sealing element may be an external casing packer which offers self support to the assembly and hydraulic isolation in the annulus. The use of such sealing elements eliminates the need for viscous pills or other supporting means to support the cement plug. In an alternate embodiment, the sealing element 6 may also comprise a top sealing element 6B, similar to the bottom sealing element 6A, that seals the communication at the top of the shoe track or at the landing collar in order to prevent upward flow in the annulus AN1 above the plug placement assembly. Thus, the cement slurry pumped into the annulus AN2 tends to be contained between the bottom 6A and top 6B sealing elements. This is also practical for placement of cement plugs in horizontal wells. The cement plug placement assembly 1 diameter is such as to create a narrow annulus portion AN2 compared to the standard annulus AN1 defined by the drill pipe DP. Thus, a fluid pumped through the side conduits 8 circulates in the narrow annulus portion AN2 according to a turbulent flow.
The method of the invention will now be described in relation with Figures 3 to 7 schematically illustrating certain steps of the method and the fluid displacement during the cement plug placement operation. Figure 3 illustrates the assembly 1 as hereinbefore described after having been assembled and run at the desired depth, and during cleaning step. In a first step S1 , the cement plug placing assembly 1 is assembled at the surface. In particular, as many standardized casing joints as desired plug length are assembled to form the shoe track 3. The assembly is coupled to the drill pipe DP. The sealing elements are also made up as part of the assembly prior to running into the well- bore. The sealing elements slide down the well-bore wall. When the assembly also comprises the top sealing element 6B, the assembly is more difficult to run because it would prevent upwards circulation of the fluids. Thus, this particular embodiment is preferably used on open-hole squeeze cementing applications.
In a second step S2, the cement plug placing assembly 1 is run to the desired depth by means of the drill pipe DP of the corresponding length.
In a third step S3, a cleaning process may begun by closing the circulation through the casing shoe 5 and circulating fluid F1 through the side conduits 8 of the circulation element 4. The produced jetting effect towards the bore-hole wall WBW and turbulent flow TF in the annulus helps in removing the mud cake MC formed on the well-bore wall WBW. The drill pipe DP may be rotated RT for sweeping the whole circumference of the well-bore wall WBW. Pumping fluids in turbulent flow allows better removal of the mud cake MC and thus will improve the cement bond with the well-bore wall WBW.
Figure 4 illustrates the assembly 1 during a first displacement phase. In a fourth step S4, the cement slurry CS is mixed and pump into the drill pipe. The bottom plug BP is launched upstream of the cement slurry CS to minimize contamination by fluids inside the drill pipe prior to cementing. The top plug TP is launched downstream the cement slurry CS. The top TP and bottom BP plugs are rubber or plastics plugs separating the cement slurry from other fluids present on the drill pipe. The top and bottom plugs are usual cementing plug typically used in cementing operation. The top plug comprises a solid core. The bottom plug comprises a hollow core and a rupture diaphragm RD. The plugs prevent the slurry from depositing on the internal wall of the drill pipe, reduce contamination and maintain predictable slurry performance. Shorter thickening time cement slurry could be utilized to reduce the time waiting on cement (WOC). Other kind of cement slurries may be used for specific applications. Figure 5 illustrates the assembly 1 during a second displacement phase. In a fifth step S5, the bottom plug BP, cement slurry CS and top plug TP are displaced through the drill pipe DP towards the cement plug placement assembly 1. In Figure 5, the bottom plug BP already landed in the landing and disconnecting collar 2. The cement slurry CS is pushed downwards by the top plug TP which is pushed by a fluid F2, e.g. a mud pumped downwards from the surface. The diaphragm RD in the plug body ruptures to allow the cement slurry CS to pass through after the plug reaches the landing and disconnecting collar 2. The cement slurry CS flows through the bottom plug BP, the internal conduit of the assembly 10. Then the cement slurry CS flows through the side conduits 8 into the annulus AN2 between the shoe track 3, the sealing element 6A, 6B and the wall WBW of the well- bore.
Figure 6 illustrates the assembly 1 at the end of the displacement phase. In a sixth step S6, at the end of the displacement, the top plug TP lands onto the bottom plug BP. This provides a sudden pressure bump PU giving a positive indication of contact with the landing and disconnecting collar 2 and the bottom plug BP. The increase in pump pressure may be detected by an appropriate detector (not shown) at the surface.
The drill pipe DP is also disconnected from the landing and disconnecting collar 2 of the cement plug placement assembly 1. The disconnection of the drill pipe DP from the landing and disconnecting collar 2 is triggered by the pressure bump. Figure 7 illustrates the assembly 1 during disconnection.
In a seventh step S7, the drill pipe DP is at least partially pulled out of the hole POOH of the well-bore. Since the whole assembly 1 is drillable, it is not necessary to pull the drill pipe DP completely out of the hole. Thus, the chance of contamination and the risk of the cement setting with the drill pipe DP immersed are also reduced. With the invention, there is no time spent in plug balancing. A fluid may be circulated through the drill pipe for cleaning purpose. Once the cement is set, the cement plug PG is formed by the cement filled in landing and disconnecting collar 2, shoe track 3, circulation element 4, guide shoe 5, internal conduit 10 and annulus portion AN2. The cement plug CP may be used for a variety of applications including hydraulic isolation, provision of a secure mechanical platform, and in window-milling operations for sidetracking a new well-bore, or a horizontal or deviated well-bore. FINAL REMARKS
It is to be mentioned that the invention is not limited to onshore hydrocarbon well and can also be used in relation with offshore hydrocarbon well. Further, though a vertical well-bore has been depicted in the drawings, the invention may also apply in a horizontal or deviated well-bore.
Furthermore, though, the invention has been presented with a particular cementing application, it is not limited to the placement of a cement plug which purpose is to achieve hydraulic isolation at a particular location in the well-bore. The invention may serve other purposes, for example in remedial cementing through the placement of drillable casing patch which purpose is to stabilize the well-bore or to seal a lost circulation zone, or to set a plug in an existing well so that it may be abandoned. Also, a particular application of the invention relating to the oilfield industry has been described. However, the invention is also applicable to other kind of industry, e.g. the construction industry or the like. The drawings and their description hereinbefore illustrate rather than limit the invention.
Any reference sign in a claim should not be construed as limiting the claim. The word "comprising" does not exclude the presence of other elements than those listed in a claim. The word "a" or "an" preceding an element does not exclude the presence of a plurality of such element.

Claims

1. An assembly for placing a cement plug (1) in a well-bore comprising a landing and disconnecting collar (2), a shoe track (3), a circulation element (4), and a guide shoe (5), said elements forming an internal conduit (10), the circulation element (4) comprising side conduits (8) directed towards a well-bore wall (WBW)1 wherein the assembly (1) diameter is such as to create a narrow annulus (AN2) in which a fluid pumped through the side conduits (8) circulates in the annulus according to a turbulent flow, wherein the assembly (1) further comprises a sealing element (6) comprising a bottom sealing element (6A), and wherein the landing and disconnecting collar (2), shoe track (3), circulation element (4), and guide shoe (5) are made of material that are drillable, said elements forming the cement plug when a cement slurry (CS) is set into the annulus (AN2) and the internal conduit (10).
2. An assembly for placing a cement plug (1) according to claim 1 , wherein the assembly further comprises a top sealing element (6B).
3. An assembly for placing a cement plug (1) according to claim 1 or 2, wherein the material is chosen among the group of material comprising Aluminum, fiberglass, cement, plastic, and carbon fiber reinforced material.
4. An assembly for placing a cement plug (1) according to any one of the preceding claims, wherein the assembly further comprises a centralizer (7).
5. An assembly for placing a cement plug (1) according to any one of the preceding claims, wherein the guide shoe (5) further comprises a differential pressure valve (9) for reducing any piston effect on a geological formation (GF) surrounding the well- bore (WB).
6. An assembly for placing a cement plug (1) according to any one of the preceding claims, wherein the sealing element (6) is a flexible cup-like packer or an external casing packer.
7. A method of placing a cement plug in a well-bore comprising the steps of:
- assembling (S1) a cement plug placing assembly (1) and coupling said assembly to a drill pipe (DP), - running (S2) the cement plug placing assembly (1) to a desired depth,
- cleaning (S3) the well-bore wall (WBW) by circulating fluid in said assembly by producing a jetting effect towards the well-bore wall and a turbulent flow in a limited annulus (AN2) portion defined between the cement plug placing assembly (1) and the well-bore wall (WBW), - mixing and pumping (S4) a cement slurry into the drill pipe,
- displacing (S5) the cement slurry towards the cement plug placing assembly (1) and into the annulus (AN2) portion, and
- disconnecting (S6) the drill pipe after a pressure bump at the end of the displacing step.
8. A method of placing a cement plug according to claim 7, wherein a length of the cement plug is defined by coupling casing joints during the assembling step.
9. A method of placing a cement plug according to claim 7, wherein the drill pipe (DP) is rotated for sweeping a whole circumference of the well-bore wall (WBW) during the cleaning step.
PCT/EP2009/005896 2008-09-08 2009-08-12 An assembly and method for placing a cement plug WO2010025816A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US13/062,563 US20110162844A1 (en) 2008-09-08 2009-08-12 Assembly and method for placing a cement plug

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
EP08163842.1 2008-09-08
EP08163842A EP2161405A1 (en) 2008-09-08 2008-09-08 An assembly and method for placing a cement plug

Publications (1)

Publication Number Publication Date
WO2010025816A1 true WO2010025816A1 (en) 2010-03-11

Family

ID=40297834

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2009/005896 WO2010025816A1 (en) 2008-09-08 2009-08-12 An assembly and method for placing a cement plug

Country Status (3)

Country Link
US (1) US20110162844A1 (en)
EP (1) EP2161405A1 (en)
WO (1) WO2010025816A1 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130008671A1 (en) * 2011-07-07 2013-01-10 Booth John F Wellbore plug and method
GB2511068B (en) 2013-02-21 2017-11-01 Alice Isaksen Inger Apparatus and method for setting a cementitious material plug
AU2017444251B2 (en) 2017-12-22 2024-04-04 Halliburton Energy Services, Inc. Fiber deployment system and communication
US10914132B1 (en) * 2019-10-26 2021-02-09 Petro-King Energy Technology (Huizhou) Co., Ltd. Large-diameter soluble bridge plug
US11473397B2 (en) 2020-07-09 2022-10-18 Saudi Arabian Oil Company Cementing across loss circulation zones utilizing a smart drillable cement stinger
US11851959B2 (en) * 2020-07-28 2023-12-26 Saudi Arabian Oil Company Method and apparatus for the exact placement of resin and cement plugs
US11519241B2 (en) 2021-02-18 2022-12-06 Saudi Arabian Oil Company Drill assembly having a stinger with downward oriented cups
CN117266788B (en) * 2023-11-22 2024-01-12 中国石油集团渤海钻探工程有限公司 Erosion-resistant cement-filled floating shoe

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3111171A (en) * 1961-03-17 1963-11-19 Willie W Farrar Combination float shoe and spiral cement mlxer
US5437330A (en) * 1994-07-27 1995-08-01 Baker Hughes Incorporated Liner cementing system and method
EP0969183A2 (en) * 1995-04-26 2000-01-05 Weatherford/Lamb Inc. Plug
US6082451A (en) * 1995-04-26 2000-07-04 Weatherford/Lamb, Inc. Wellbore shoe joints and cementing systems
US20010003314A1 (en) * 1999-11-30 2001-06-14 Caber Holdings Inc. Rotating casing assembly and method
WO2004038172A1 (en) * 2002-10-23 2004-05-06 Downhole Products Plc Cement flow control tool
US20060237186A1 (en) * 2001-10-01 2006-10-26 Mondelli Juan C Cementing system for wellbores

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3126060A (en) * 1964-03-24 L loiacano
US2811208A (en) * 1955-08-26 1957-10-29 California Research Corp Well cementing apparatus
US2925865A (en) * 1956-11-13 1960-02-23 Halliburton Oil Well Cementing Full flow packer cementing shoe
US4326586A (en) * 1980-07-03 1982-04-27 Standard Oil Company (Indiana) Method for stressing thermal well casings
US5040602A (en) * 1990-06-15 1991-08-20 Halliburton Company Inner string cementing adapter and method of use
US5937955A (en) * 1997-05-28 1999-08-17 Atlantic Richfield Co. Method and apparatus for sealing a well bore and sidetracking a well from the well bore
US6401824B1 (en) * 2000-03-13 2002-06-11 Davis-Lynch, Inc. Well completion convertible float shoe/collar
US20080149351A1 (en) * 2006-12-20 2008-06-26 Schlumberger Technology Corporation Temporary containments for swellable and inflatable packer elements

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3111171A (en) * 1961-03-17 1963-11-19 Willie W Farrar Combination float shoe and spiral cement mlxer
US5437330A (en) * 1994-07-27 1995-08-01 Baker Hughes Incorporated Liner cementing system and method
EP0969183A2 (en) * 1995-04-26 2000-01-05 Weatherford/Lamb Inc. Plug
US6082451A (en) * 1995-04-26 2000-07-04 Weatherford/Lamb, Inc. Wellbore shoe joints and cementing systems
US20010003314A1 (en) * 1999-11-30 2001-06-14 Caber Holdings Inc. Rotating casing assembly and method
US20060237186A1 (en) * 2001-10-01 2006-10-26 Mondelli Juan C Cementing system for wellbores
WO2004038172A1 (en) * 2002-10-23 2004-05-06 Downhole Products Plc Cement flow control tool

Also Published As

Publication number Publication date
US20110162844A1 (en) 2011-07-07
EP2161405A1 (en) 2010-03-10

Similar Documents

Publication Publication Date Title
US20110162844A1 (en) Assembly and method for placing a cement plug
EP1701000B1 (en) A method and apparatus for consolidating a wellbore
US8091641B2 (en) Method and apparatus to cement a perforated casing
US20170044864A1 (en) Method of sealing wells by squeezing sealant
US8789582B2 (en) Apparatus and methods for well cementing
CA2547481C (en) Retractable joint and cementing shoe for use in completing a wellbore
US8267173B2 (en) Open hole completion apparatus and method for use of same
US7624803B2 (en) Injection apparatus for injecting an activated fluid into a well-bore and related injection method
US8789621B2 (en) Hydrocarbon well completion system and method of completing a hydrocarbon well
US7654324B2 (en) Reverse-circulation cementing of surface casing
RU2728157C2 (en) Annular barrier and well system for low pressure zone
EP2128378B1 (en) An injection apparatus and method
US8479818B2 (en) Method and apparatus to cement a perforated casing
US10060210B2 (en) Flow control downhole tool
US20040007354A1 (en) System for running tubular members
CN109690016A (en) Stage cementing tool
EP3199747A1 (en) Annular barrier and downhole system for low pressure zone
US11867010B2 (en) Deploying a liner in a wellbore
US12012823B2 (en) Cement retainer for remedial operations
US20230258057A1 (en) Systems and methods for wellbore liner installation under managed pressure conditions
US9556705B2 (en) Casing joint assembly for producing an annulus gas cap

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 09811074

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 09811074

Country of ref document: EP

Kind code of ref document: A1