WO2009137445A1 - Erection method for solar receiver and support tower - Google Patents

Erection method for solar receiver and support tower Download PDF

Info

Publication number
WO2009137445A1
WO2009137445A1 PCT/US2009/042794 US2009042794W WO2009137445A1 WO 2009137445 A1 WO2009137445 A1 WO 2009137445A1 US 2009042794 W US2009042794 W US 2009042794W WO 2009137445 A1 WO2009137445 A1 WO 2009137445A1
Authority
WO
WIPO (PCT)
Prior art keywords
support tower
solar receiver
tower insert
support
sections
Prior art date
Application number
PCT/US2009/042794
Other languages
French (fr)
Inventor
Dennis S. Fedock
Joe C. Roudebush
Thomas J. Studer
Original Assignee
Babcock & Wilcox Power Generation Group Inc.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Babcock & Wilcox Power Generation Group Inc. filed Critical Babcock & Wilcox Power Generation Group Inc.
Priority to EP09743431.0A priority Critical patent/EP2286046A4/en
Priority to AU2009244469A priority patent/AU2009244469B2/en
Priority to CA2723514A priority patent/CA2723514C/en
Priority to MX2010012068A priority patent/MX2010012068A/en
Priority to NZ588926A priority patent/NZ588926A/en
Priority to BRPI0912580A priority patent/BRPI0912580A2/en
Priority to CN200980116863.2A priority patent/CN102016202B/en
Publication of WO2009137445A1 publication Critical patent/WO2009137445A1/en
Priority to ZA2010/07678A priority patent/ZA201007678B/en
Priority to MA33298A priority patent/MA32279B1/en
Priority to IL209119A priority patent/IL209119A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/342Arrangements for stacking tower sections on top of each other
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10TTECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
    • Y10T29/00Metal working
    • Y10T29/49Method of mechanical manufacture
    • Y10T29/4935Heat exchanger or boiler making
    • Y10T29/49355Solar energy device making
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10TTECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
    • Y10T29/00Metal working
    • Y10T29/49Method of mechanical manufacture
    • Y10T29/49616Structural member making
    • Y10T29/49623Static structure, e.g., a building component
    • Y10T29/49625Openwork, e.g., a truss, joist, frame, lattice-type or box beam
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10TTECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
    • Y10T29/00Metal working
    • Y10T29/49Method of mechanical manufacture
    • Y10T29/49826Assembling or joining
    • Y10T29/49828Progressively advancing of work assembly station or assembled portion of work

Definitions

  • the present invention relates to the field of power generation and industrial boiler design, including boilers or steam generators used in the production of steam used to generate electricity.
  • the present invention provides a new and useful method for erection of a solar receiver and support tower in an economical, efficient manner.
  • a solar receiver is a primary component of a solar energy generation system whereby sunlight is used as a heat source for the production of high quality steam that is used to turn a turbine generator, and ultimately generate electricity.
  • the receiver is permanently positioned on top of an elevated support tower that is strategically positioned in a field of heliostats, or mirrors, that collect rays of sunlight and reflect those rays back to target wall(s) in the receiver.
  • the height of the solar receiver support tower is established by the arrangement of the heliostat field and the operation of the heliostats in that field.
  • the construction of the solar receiver and its support tower employs heavy lift crawler cranes for placement of support tower sections on the tower foundation, and for placement of the assembled solar receiver on the tower. Due to the weight of the solar receiver, and the height of the tower above grade, required heavy lift cranes are, of necessity, very high capacity. High capacity mobile lift cranes are of limited availability, are high cost, and must operate on prepared ground capable of withstanding relatively high imposed bearing pressures. Because of their overall size, even though these heavy lift cranes are classified as mobile cranes, they are not readily repositioned between solar receiver placements in a typical solar energy generation installation. Transportation between operating positions at each receiver support tower requires assembly / disassembly / reassembly of the heavy lift crane.
  • the present invention eliminates the need for these heavy lift crawler cranes for erection of the solar receiver and its respective support tower.
  • the present invention provides an erection method for a solar receiver and support tower which employs a climbing assembly to raise the solar receiver to its final elevation by progressively jacking and installing support tower sections.
  • one aspect of the present invention is drawn to an erection method for a solar receiver and support tower comprising the steps of providing a climbing assembly on the support tower to raise the solar receiver to its final elevation by progressively jacking and installing support tower sections to erect the tower and support the solar receiver.
  • Another aspect of the present invention is drawn to a method for erecting a solar receiver and support tower therefor, the method comprising the steps of: (a) providing a solar receiver; (b) providing a support tower in the form of two of more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver; (c) providing a climbing assembly, wherein the climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver; (d) placing the solar receiver on top of the first support tower insert section; and (e) progressively jacking and installing one or more additional support tower insert sections between the first support tower insert section and the bottom of the solar receiver.
  • Yet another aspect of the present invention is drawn to a method for erecting a solar receiver and support tower therefor, the method comprising the steps of: (i) providing a solar receiver; (ii) providing a monorail secured adjacent the solar receiver; (iii) providing a support tower, wherein the support tower comprises two or more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver; (iv) providing a hydraulic climbing assembly, wherein the hydraulic climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver; (v) placing the solar receiver on top of the first support tower insert section; and (vi) progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver.
  • Still another aspect of the present invention is drawn to a method for erecting a solar receiver and support tower therefore, the method comprising the steps of: (A) providing a solar receiver; (B) providing a monorail secured adjacent the solar receiver (C) providing a support tower, wherein the support tower comprises two or more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver; (D) providing a hydraulic climbing assembly, wherein the climbing assembly is designed to completely encompass the at least one of the support tower insert sections and wherein the hydraulic climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver; (E) placing the solar receiver on top of the first support tower insert section; and (F) progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver.
  • FIG. 1 is a schematic illustration of a first step of the erection method according to the present invention, wherein a hydraulic crane is used for initial load handling operations;
  • FIG. 2 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a support tower insert section has been placed adjacent the tower;
  • FIG. 3 is a schematic illustration of a subsequent step of the erection method according to the present invention, after the first climbing sequence has taken place;
  • FIG. 4 is a schematic illustration of a subsequent step of the erection method according to the present invention, after the first climbing sequence has taken place, and wherein a support tower insert section is ready to be lifted;
  • FIG. 5 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a support tower insert section has been lifted to an upper portion of the support tower;
  • FIG. 6 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a support tower insert section is in the process of being inserted into an upper portion of the support tower;
  • FIG. 7 is a schematic illustration of a subsequent step of the erection method according to the present invention, illustrating the repositioned climbing assembly after the first climbing sequence has taken place;
  • FIG. 8 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a second support tower insert section is in the process of being inserted into an upper portion of the support tower.
  • FIG. 2 there is shown a schematic illustration of the equipment involved in the method for erection of a solar receiver and support tower according to the present invention.
  • climbing assembly 40 comprises a collar assembly 42, hydraulic cylinders 44, and a climber mechanism 46 which are all adapted into the design of support tower 20.
  • Climbing assembly 40 completely encompasses the periphery of support tower 20 framing members, such that the inside dimensions of climbing assembly 40 are approximately equal to the outside dimensions of support tower 20.
  • Collar assembly 42 is affixed to the framing members in place on four sides of tower 20, and forms the base that supports two hydraulic cylinders 44 positioned on opposite sides of support tower 20. Hydraulic cylinders 44 are connected to climber mechanism 46 on two sides.
  • Climber mechanism 46 is a structural framework that surrounds support tower 20 on four sides so as to be guided and stabilized by support tower 20 during a climbing operation.
  • the hydraulic cylinder sides of climber mechanism 46 are of a height that allows for installation of a support tower insert section 25 through the sides of climber mechanism 46 perpendicular to the hydraulic cylinder sides.
  • the first support tower insert section is designated 25a, the second 25b, the third 25c, etc.
  • each support tower insert section 25 is also provided with shop-fabricated stairs and landings to provide ready access over the height of the support tower 20.
  • the load of solar receiver 10 is assumed on the cylinder sides of climber mechanism 46, transferred to the hydraulic cylinders 44, and withstood by collar assembly 42 until the next support tower insert section 25 is installed.
  • Hydraulic cylinders 44 are powered by a hydraulic control unit 48 placed on a platform in support tower 20 in close proximity to cylinders 44.
  • Fig. 1 which is a schematic illustration of a first step of the erection method according to the present invention
  • hydraulic crane 50 is used for initial load handling operations at the start of construction.
  • hydraulic crane 50 is much smaller in dimension and capacity, more available, less costly and much more practical and expedient.
  • a support tower insert section 25a has been placed adjacent the tower 20.
  • installation of the solar receiver support tower 20 begins via a method described herein.
  • a base tower section 27 is erected, leveled, aligned and plumbed on foundation 30.
  • Base tower section 27 is secured in a final position by tightening the base connection to anchor rods embedded in the concrete that forms foundation 30.
  • climbing assembly 40 is installed on base tower section 27.
  • base tower section 27 is not limited to any one specific height. Rather, base tower section 27 is designed to have the height needed to receive the combined length of climber mechanism 46, collar assembly 42 and the retracted length of hydraulic cylinders 44.
  • solar receiver 10 As tower foundation 30 is being constructed and base tower section 27 is being installed, the individual shipping components of solar receiver 10 can be ground assembled into a complete unit for lifting to final position after base tower section 27 is erected. If solar receiver 10 is already a substantially complete unit as- delivered from the manufacturing facility, solar receiver 10 can be lifted into place on top of base tower section 27, after base tower section 27 is erected.
  • a monorail 60 is incorporated into the support framing, secured adjacent to solar receiver 10, advantageously at the base of solar receiver 10, and cantilevers a distance approximately half the plan dimension of support tower 20. This arrangement permits support tower insert sections 25a, 25b, 25c, etc. to be raised to elevation immediately outboard of tower 20 in place.
  • monorail 60 is sized to provide lifting capacity equal to the rigging weight of support tower insert sections 25 above base tower section 27.
  • the hoisting mechanism provided for monorail 60 is powered by a base mounted two drum waterfall hoist 62 secured on a reinforced concrete foundation slab 64 near the base of solar receiver support tower 20.
  • Load lines 66 extend over the fair lead distance from the hoist to lead sheaves 68 mounted on the base of tower 20, are routed up the outside of tower 20 to sheaves 70 attached to the end of monorail 60, and finally routed along monorail 60 to fit to trolleys 72 and load blocks 74 operating on monorail 60. These load lines 66 are used to raise and/or lower the load and to position the trolleys along the length of monorail 60.
  • Figs. 3, 4, 5, 6 and 7. Once installation of base tower section 27 and climbing assembly 40 is completed, and solar receiver 10 with monorail 60 is in place, the first climbing sequence begins. With collar assembly 42 secured to base tower section 27, and climber mechanism 46 secured to solar receiver 10, hydraulic cylinders 44 extend to the length required to permit installation of the next support tower insert section 25. Fig. 3. Support tower insert section 25a is positioned on the ground adjacent to base tower section 27 in place, and beneath the hoisting hook on monorail 60. Fig. 4. The hoisting hook is attached to support tower insert section 25a, and section 25a is raised to an elevation just above the portion of base tower section 27 that is in place. Fig. 5.
  • support tower insert section 25a is trolleyed into position over base tower section 27 in place.
  • mating surfaces on base tower section 27 and support tower insert section 25a are brought into contact and securely connected.
  • Collar assembly 42 is disconnected from the tower framing, and is raised to its next upper point of securement as hydraulic cylinders 44 retract.
  • Fig. 7. At the retracted position of hydraulic cylinders 44, collar assembly 42 is reattached to the support tower framing, and the first climbing sequence is completed.
  • the second climbing sequence duplicates the first, as do all remaining sequences until all support tower insert sections 25b, 25c, etc. are in place and solar receiver 10 is at its final elevation.
  • Fig. 8. [0032] Upon attachment of solar receiver 10 to the topmost support tower insert section 25 and completion of support tower 20 erection, climbing assembly 40 is brought to the ground by reversing the sequence of climbing operations. Climber mechanism 46 is secured to support tower 20 and detached from solar receiver 10. Collar assembly 42 is detached from support tower 20's framing and is suspended from hydraulic cylinders 44. Hydraulic cylinders 44 extend and lower collar assembly 42 to its next lower point of securement.
  • Collar assembly 42 is reattached to support tower 20's framing and climber mechanism 46 is detached from support tower 20. Hydraulic cylinders 44 retract and lower climber mechanism 46 to its next lower point of securement to the support tower framing. Climber mechanism 46 is resecured, collar assembly 42 is detached, and the next lowering sequence proceeds in similar manner. Lowering sequences continue until climbing assembly 40 reaches its lowest position on support tower 20. At this lowest position, climbing assembly 40 is disassembled via use of hydraulic crane 50.
  • feed water and high pressure steam piping are appropriately routed up support tower 20 (e.g., on a side or sides of support tower 20).
  • the piping is constructed via the use of monorail 60 and the hoisting mechanism.
  • monorail 60 can be left in place. Alternatively, monorail 60 can be removed.
  • the hoisting mechanism including hoist 62 at grade, lead sheaves 68, 70, trolleys 72 and load blocks 74, can or cannot be left in place per the discretion of the owner.
  • the invention provides a safe, economical, efficient and practical means of erection of solar receivers and support towers.
  • the invention provides a means of erection of solar receivers and support towers that is independent of specific site constraints and restrictions.
  • the invention eliminates the need for high capacity, high cost, and limited availability heavy lift cranes for the erection of solar receivers and support towers. [0039] 4. The invention eliminates the need for project ground improvement for the placement of heavy lift cranes for the erection of solar receivers and support towers.
  • the invention uses the existing permanent construction of the solar receiver and support tower as the erection means for the solar receiver and support tower, and minimizes the need for any temporary installations.
  • the invention provides a means of solar receiver and support tower erection via the climbing assembly that is readily truck shippable to any site, with a minimum number of shipments.
  • the invention provides a means of completing solar receiver and support tower erection whereby critical rigging, handling and welding operations are performed at or near ground elevation.
  • the invention provides an integral means for installation of critical feed water and high pressure steam piping.
  • the invention provides a means of readily lowering and/or raising the solar receiver for any possible future maintenance operations.
  • the invention provides a means of erection of solar receivers and support towers of unlimited height.
  • the invention offers a "green benefit".
  • a heavy equipment list must be submitted for evaluation with regard to pollutant emissions. Eliminating the need for heavy lift crawler cranes reduces construction pollutant emissions and enhances the prospect for a favorable project evaluation with respect to this aspect.
  • the present invention overcomes the difficulties and reduces the cost and time required to erect a solar receiver and its support tower with conventional erection techniques which require expensive, [0048] While the principles of the present invention may be particularly applicable to new solar receiver installations, it will be appreciated that the present invention may be applied to construction involving the replacement, repair or modification of existing solar receivers. In some embodiments of the invention, certain features of the invention may sometimes be used to advantage without a corresponding use of the other features. Accordingly, while specific embodiments of the present invention have been shown and described in detail to illustrate the application and principles of the invention, it will be understood that it is not intended that the present invention be limited thereto and that the invention may be embodied otherwise without departing from such principles. All such changes and embodiments properly fall within the scope of the following claims.

Abstract

An erection method for a solar receiver and support tower the method comprising the steps of (a) providing a solar receiver, (b) providing a support tower in the form of two of more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver, (c) providing a climbing assembly, wherein the climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver, (d) placing the solar receiver on top of the first support tower insert section, and (e) progressively jacking and installing one or more additional support tower insert sections between the first support tower insert section and the bottom of the solar receiver.

Description

ERECTION METHOD FOR SOLAR RECEIVER & SUPPORT TOWER
CROSS-REFERENCE TO RELATED APPLICATION
[0001] The present invention claims priority from United States Provisional
Application for patent Serial No. 61/051 ,171 , filed May 7, 2008, the text of which is hereby incorporated by reference as though fully set forth herein.
FIELD AND BACKGROUND OF THE INVENTION
[0002] The present invention relates to the field of power generation and industrial boiler design, including boilers or steam generators used in the production of steam used to generate electricity. In particular, the present invention provides a new and useful method for erection of a solar receiver and support tower in an economical, efficient manner.
[0003] A solar receiver is a primary component of a solar energy generation system whereby sunlight is used as a heat source for the production of high quality steam that is used to turn a turbine generator, and ultimately generate electricity. The receiver is permanently positioned on top of an elevated support tower that is strategically positioned in a field of heliostats, or mirrors, that collect rays of sunlight and reflect those rays back to target wall(s) in the receiver. The height of the solar receiver support tower is established by the arrangement of the heliostat field and the operation of the heliostats in that field.
[0004] Conventionally, the construction of the solar receiver and its support tower employs heavy lift crawler cranes for placement of support tower sections on the tower foundation, and for placement of the assembled solar receiver on the tower. Due to the weight of the solar receiver, and the height of the tower above grade, required heavy lift cranes are, of necessity, very high capacity. High capacity mobile lift cranes are of limited availability, are high cost, and must operate on prepared ground capable of withstanding relatively high imposed bearing pressures. Because of their overall size, even though these heavy lift cranes are classified as mobile cranes, they are not readily repositioned between solar receiver placements in a typical solar energy generation installation. Transportation between operating positions at each receiver support tower requires assembly / disassembly / reassembly of the heavy lift crane.
SUMMARY OF THE INVENTION
[0005] The present invention eliminates the need for these heavy lift crawler cranes for erection of the solar receiver and its respective support tower.
[0006] The present invention provides an erection method for a solar receiver and support tower which employs a climbing assembly to raise the solar receiver to its final elevation by progressively jacking and installing support tower sections.
[0007] Accordingly, one aspect of the present invention is drawn to an erection method for a solar receiver and support tower comprising the steps of providing a climbing assembly on the support tower to raise the solar receiver to its final elevation by progressively jacking and installing support tower sections to erect the tower and support the solar receiver.
[0008] Another aspect of the present invention is drawn to a method for erecting a solar receiver and support tower therefor, the method comprising the steps of: (a) providing a solar receiver; (b) providing a support tower in the form of two of more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver; (c) providing a climbing assembly, wherein the climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver; (d) placing the solar receiver on top of the first support tower insert section; and (e) progressively jacking and installing one or more additional support tower insert sections between the first support tower insert section and the bottom of the solar receiver.
[0009] Yet another aspect of the present invention is drawn to a method for erecting a solar receiver and support tower therefor, the method comprising the steps of: (i) providing a solar receiver; (ii) providing a monorail secured adjacent the solar receiver; (iii) providing a support tower, wherein the support tower comprises two or more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver; (iv) providing a hydraulic climbing assembly, wherein the hydraulic climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver; (v) placing the solar receiver on top of the first support tower insert section; and (vi) progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver.
[0010] Still another aspect of the present invention is drawn to a method for erecting a solar receiver and support tower therefore, the method comprising the steps of: (A) providing a solar receiver; (B) providing a monorail secured adjacent the solar receiver (C) providing a support tower, wherein the support tower comprises two or more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver; (D) providing a hydraulic climbing assembly, wherein the climbing assembly is designed to completely encompass the at least one of the support tower insert sections and wherein the hydraulic climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver; (E) placing the solar receiver on top of the first support tower insert section; and (F) progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver.
[0011] In all of these aspects, the last Step in each of these methods is repeated until a desired number of support tower insert sections have been installed.
[0012] The various features of novelty which characterize the invention are pointed out with particularity in the claims annexed to and forming a part of this disclosure. For a better understanding of the invention, its operating advantages and the specific benefits attained by its uses, reference is made to the accompanying drawings and descriptive matter in which preferred embodiments of the invention are illustrated. BRIEF DESCRIPTION OF THE DRAWINGS [0013] In the Figures:
[0014] Fig. 1 is a schematic illustration of a first step of the erection method according to the present invention, wherein a hydraulic crane is used for initial load handling operations;
[0015] Fig. 2 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a support tower insert section has been placed adjacent the tower;
[0016] Fig. 3 is a schematic illustration of a subsequent step of the erection method according to the present invention, after the first climbing sequence has taken place;
[0017] Fig. 4 is a schematic illustration of a subsequent step of the erection method according to the present invention, after the first climbing sequence has taken place, and wherein a support tower insert section is ready to be lifted;
[0018] Fig. 5 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a support tower insert section has been lifted to an upper portion of the support tower;
[0019] Fig. 6 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a support tower insert section is in the process of being inserted into an upper portion of the support tower;
[0020] Fig. 7 is a schematic illustration of a subsequent step of the erection method according to the present invention, illustrating the repositioned climbing assembly after the first climbing sequence has taken place; and
[0021] Fig. 8 is a schematic illustration of a subsequent step of the erection method according to the present invention, wherein a second support tower insert section is in the process of being inserted into an upper portion of the support tower.
DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0022] Referring to the drawings generally, wherein like reference numerals designate the same or functionally similar elements throughout the several drawings, and to Fig. 2 in particular, there is shown a schematic illustration of the equipment involved in the method for erection of a solar receiver and support tower according to the present invention.
[0023] The method involves the use of a climbing assembly 40 to raise a solar receiver 10 to its final elevation by progressively jacking and installing support tower insert sections 25. As shown on Fig. 2, climbing assembly 40 comprises a collar assembly 42, hydraulic cylinders 44, and a climber mechanism 46 which are all adapted into the design of support tower 20. Climbing assembly 40 completely encompasses the periphery of support tower 20 framing members, such that the inside dimensions of climbing assembly 40 are approximately equal to the outside dimensions of support tower 20. Collar assembly 42 is affixed to the framing members in place on four sides of tower 20, and forms the base that supports two hydraulic cylinders 44 positioned on opposite sides of support tower 20. Hydraulic cylinders 44 are connected to climber mechanism 46 on two sides. Climber mechanism 46 is a structural framework that surrounds support tower 20 on four sides so as to be guided and stabilized by support tower 20 during a climbing operation. When hydraulic cylinders 44 are extended, the hydraulic cylinder sides of climber mechanism 46 are of a height that allows for installation of a support tower insert section 25 through the sides of climber mechanism 46 perpendicular to the hydraulic cylinder sides. In the Figs., the first support tower insert section is designated 25a, the second 25b, the third 25c, etc. Although not illustrated in the Figs., each support tower insert section 25 is also provided with shop-fabricated stairs and landings to provide ready access over the height of the support tower 20. The load of solar receiver 10 is assumed on the cylinder sides of climber mechanism 46, transferred to the hydraulic cylinders 44, and withstood by collar assembly 42 until the next support tower insert section 25 is installed. Hydraulic cylinders 44 are powered by a hydraulic control unit 48 placed on a platform in support tower 20 in close proximity to cylinders 44.
[0024] The method of erection using climbing assembly 40 is described on
Figs. 1 through 8 and as set forth in the following paragraphs.
[0025] As shown in Fig. 1 , which is a schematic illustration of a first step of the erection method according to the present invention, hydraulic crane 50 is used for initial load handling operations at the start of construction. In comparison to the heavy lift crane required for placement of a solar receiver 10 on top of the completed support tower 20, hydraulic crane 50 is much smaller in dimension and capacity, more available, less costly and much more practical and expedient.
[0026] As shown in Fig. 2, which is a schematic illustration of a subsequent step of the erection method according to the present invention, a support tower insert section 25a has been placed adjacent the tower 20. Following completion of a suitable tower foundation 30 and receipt of confirmation that the 28 day compressive strength of the foundation concrete has been attained, installation of the solar receiver support tower 20 begins via a method described herein. Via the use of a hydraulic crane 50, a base tower section 27 is erected, leveled, aligned and plumbed on foundation 30. Base tower section 27 is secured in a final position by tightening the base connection to anchor rods embedded in the concrete that forms foundation 30. Next, climbing assembly 40 is installed on base tower section 27.
[0027] The height of base tower section 27 is not limited to any one specific height. Rather, base tower section 27 is designed to have the height needed to receive the combined length of climber mechanism 46, collar assembly 42 and the retracted length of hydraulic cylinders 44.
[0028] As tower foundation 30 is being constructed and base tower section 27 is being installed, the individual shipping components of solar receiver 10 can be ground assembled into a complete unit for lifting to final position after base tower section 27 is erected. If solar receiver 10 is already a substantially complete unit as- delivered from the manufacturing facility, solar receiver 10 can be lifted into place on top of base tower section 27, after base tower section 27 is erected.
[0029] A monorail 60 is incorporated into the support framing, secured adjacent to solar receiver 10, advantageously at the base of solar receiver 10, and cantilevers a distance approximately half the plan dimension of support tower 20. This arrangement permits support tower insert sections 25a, 25b, 25c, etc. to be raised to elevation immediately outboard of tower 20 in place. In one embodiment, monorail 60 is sized to provide lifting capacity equal to the rigging weight of support tower insert sections 25 above base tower section 27. The hoisting mechanism provided for monorail 60 is powered by a base mounted two drum waterfall hoist 62 secured on a reinforced concrete foundation slab 64 near the base of solar receiver support tower 20. Load lines 66 extend over the fair lead distance from the hoist to lead sheaves 68 mounted on the base of tower 20, are routed up the outside of tower 20 to sheaves 70 attached to the end of monorail 60, and finally routed along monorail 60 to fit to trolleys 72 and load blocks 74 operating on monorail 60. These load lines 66 are used to raise and/or lower the load and to position the trolleys along the length of monorail 60.
[0030] Refer now to Figs. 3, 4, 5, 6 and 7. Once installation of base tower section 27 and climbing assembly 40 is completed, and solar receiver 10 with monorail 60 is in place, the first climbing sequence begins. With collar assembly 42 secured to base tower section 27, and climber mechanism 46 secured to solar receiver 10, hydraulic cylinders 44 extend to the length required to permit installation of the next support tower insert section 25. Fig. 3. Support tower insert section 25a is positioned on the ground adjacent to base tower section 27 in place, and beneath the hoisting hook on monorail 60. Fig. 4. The hoisting hook is attached to support tower insert section 25a, and section 25a is raised to an elevation just above the portion of base tower section 27 that is in place. Fig. 5. Once at the desired elevation, support tower insert section 25a is trolleyed into position over base tower section 27 in place. Fig. 6. Next, mating surfaces on base tower section 27 and support tower insert section 25a are brought into contact and securely connected. Collar assembly 42 is disconnected from the tower framing, and is raised to its next upper point of securement as hydraulic cylinders 44 retract. Fig. 7. At the retracted position of hydraulic cylinders 44, collar assembly 42 is reattached to the support tower framing, and the first climbing sequence is completed.
[0031] The second climbing sequence duplicates the first, as do all remaining sequences until all support tower insert sections 25b, 25c, etc. are in place and solar receiver 10 is at its final elevation. Fig. 8. [0032] Upon attachment of solar receiver 10 to the topmost support tower insert section 25 and completion of support tower 20 erection, climbing assembly 40 is brought to the ground by reversing the sequence of climbing operations. Climber mechanism 46 is secured to support tower 20 and detached from solar receiver 10. Collar assembly 42 is detached from support tower 20's framing and is suspended from hydraulic cylinders 44. Hydraulic cylinders 44 extend and lower collar assembly 42 to its next lower point of securement. Collar assembly 42 is reattached to support tower 20's framing and climber mechanism 46 is detached from support tower 20. Hydraulic cylinders 44 retract and lower climber mechanism 46 to its next lower point of securement to the support tower framing. Climber mechanism 46 is resecured, collar assembly 42 is detached, and the next lowering sequence proceeds in similar manner. Lowering sequences continue until climbing assembly 40 reaches its lowest position on support tower 20. At this lowest position, climbing assembly 40 is disassembled via use of hydraulic crane 50.
[0033] In conjunction with the assembly and/or erection of solar receiver 10 and support tower 20, feed water and high pressure steam piping (not shown) are appropriately routed up support tower 20 (e.g., on a side or sides of support tower 20). In one embodiment, the piping is constructed via the use of monorail 60 and the hoisting mechanism.
[0034] In one embodiment, monorail 60 can be left in place. Alternatively, monorail 60 can be removed. The hoisting mechanism, including hoist 62 at grade, lead sheaves 68, 70, trolleys 72 and load blocks 74, can or cannot be left in place per the discretion of the owner.
[0035] The advantages of the invention are many, and include:
[0036] 1. The invention provides a safe, economical, efficient and practical means of erection of solar receivers and support towers.
[0037] 2. The invention provides a means of erection of solar receivers and support towers that is independent of specific site constraints and restrictions.
[0038] 3. The invention eliminates the need for high capacity, high cost, and limited availability heavy lift cranes for the erection of solar receivers and support towers. [0039] 4. The invention eliminates the need for project ground improvement for the placement of heavy lift cranes for the erection of solar receivers and support towers.
[0040] 5. The invention uses the existing permanent construction of the solar receiver and support tower as the erection means for the solar receiver and support tower, and minimizes the need for any temporary installations.
[0041] 6. The invention provides a means of solar receiver and support tower erection via the climbing assembly that is readily truck shippable to any site, with a minimum number of shipments.
[0042] 7. The invention provides a means of completing solar receiver and support tower erection whereby critical rigging, handling and welding operations are performed at or near ground elevation.
[0043] 8. The invention provides an integral means for installation of critical feed water and high pressure steam piping.
[0044] 9. The invention provides a means of readily lowering and/or raising the solar receiver for any possible future maintenance operations.
[0045] 10. With some adaptation of the climbing assembly to suit the cross sectional dimensions of the support tower, the invention provides a means of erection of solar receivers and support towers of unlimited height.
[0046] 11. The invention offers a "green benefit". In order to get permits for construction in the state of California, for example, a heavy equipment list must be submitted for evaluation with regard to pollutant emissions. Eliminating the need for heavy lift crawler cranes reduces construction pollutant emissions and enhances the prospect for a favorable project evaluation with respect to this aspect.
[0047] It will thus be readily appreciated that the present invention overcomes the difficulties and reduces the cost and time required to erect a solar receiver and its support tower with conventional erection techniques which require expensive, [0048] While the principles of the present invention may be particularly applicable to new solar receiver installations, it will be appreciated that the present invention may be applied to construction involving the replacement, repair or modification of existing solar receivers. In some embodiments of the invention, certain features of the invention may sometimes be used to advantage without a corresponding use of the other features. Accordingly, while specific embodiments of the present invention have been shown and described in detail to illustrate the application and principles of the invention, it will be understood that it is not intended that the present invention be limited thereto and that the invention may be embodied otherwise without departing from such principles. All such changes and embodiments properly fall within the scope of the following claims.

Claims

CLAIMSWe claim:
1. A method for erecting a solar receiver and support tower therefor, the method comprising the steps of:
(a) providing a solar receiver;
(b) providing a support tower in the form of two of more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver;
(c) providing a climbing assembly, wherein the climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver;
(d) placing the solar receiver on top of the first support tower insert section; and
(e) progressively jacking and installing one or more additional support tower insert sections between the first support tower insert section and the bottom of the solar receiver.
2. The method of claim 1 , wherein the solar receiver is completely assembled prior to being placed on top of the first support tower insert section.
3. The method of claim 1 , wherein the solar receiver is assembled piecemeal on top of the first support tower insert section.
4. The method of claim 1 , wherein the climbing assembly is designed to completely encompass the at least one of the support tower insert sections.
5. The method of claim 4, wherein the climbing assembly is comprised of a lattice structure that is designed to permit the ingress of at least one support tower insert section into the interior thereof.
6. The method of claim 1 , wherein the climbing assembly is a hydraulically operated climbing assembly.
7. The method of claim 1 , further comprising the step of providing a monorail secured adjacent the solar receiver, the monorail being designed to permit the installation of one or more additional support tower insert sections between the base of the solar receiver and the first support tower insert section.
8. The method of claim 1 , further comprising repeating Step (e) until a desired number of support tower insert sections have been installed.
9. A method for erecting a solar receiver and support tower therefor, the method comprising the steps of:
(i) providing a solar receiver;
(ii) providing a monorail secured adjacent the solar receiver;
(iii) providing a support tower, wherein the support tower comprises two or more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver;
(iv) providing a hydraulic climbing assembly, wherein the hydraulic climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver;
(v) placing the solar receiver on top of the first support tower insert section; and
(vi) progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver.
10. The method of claim 9, wherein the solar receiver is completely assembled prior to being placed on top of the first support tower insert section.
11. The method of claim 9, wherein the solar receiver is assembled piecemeal on top of the first support tower insert section.
12. The method of claim 9, wherein the climbing assembly is designed to completely encompass the at least one of the support tower insert sections.
13. The method of claim 12, wherein the climbing assembly is comprised of a lattice structure that is designed to permit the ingress of at least one support tower insert section into the interior thereof.
14. The method of claim 9, further comprising repeating Step (vi) until a desired number of support tower insert sections have been installed.
15. A method for erecting a solar receiver and support tower therefore, the method comprising the steps of:
(A) providing a solar receiver;
(B) providing a monorail secured adjacent the solar receiver;
(C) providing a support tower, wherein the support tower comprises two or more support tower insert sections and wherein at least one of the support tower insert sections is designed to finally receive and support the solar receiver;
(D) providing a hydraulic climbing assembly, wherein the climbing assembly is designed to completely encompass the at least one of the support tower insert sections and wherein the hydraulic climbing assembly is designed to raise the solar receiver to a final height by progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver;
(E) placing the solar receiver on top of the first support tower insert section; and
(F) progressively jacking and installing support tower insert sections between a first support tower insert section and the bottom of the solar receiver.
16. The method of claim 15, wherein the solar receiver is completely assembled prior to being placed on top of the first support tower insert section.
17. The method of claim 15, wherein the solar receiver is assembled piecemeal on top of the first support tower insert section.
18. The method of claim 15, wherein the climbing assembly is comprised of a lattice structure that is designed to permit the ingress of at least one support tower insert section into the interior thereof.
19. The method of claim 15, further comprising repeating Step (F) until a desired number of support tower insert sections have been installed.
20. An erection method for a solar receiver and support tower comprising the steps of providing a climbing assembly on the support tower to raise the solar receiver to its final elevation by progressively jacking and installing support tower sections to erect the tower and support the solar receiver.
PCT/US2009/042794 2008-05-07 2009-05-05 Erection method for solar receiver and support tower WO2009137445A1 (en)

Priority Applications (10)

Application Number Priority Date Filing Date Title
EP09743431.0A EP2286046A4 (en) 2008-05-07 2009-05-05 Erection method for solar receiver and support tower
AU2009244469A AU2009244469B2 (en) 2008-05-07 2009-05-05 Erection method for solar receiver and support tower
CA2723514A CA2723514C (en) 2008-05-07 2009-05-05 Erection method for solar receiver & support tower
MX2010012068A MX2010012068A (en) 2008-05-07 2009-05-05 Erection method for solar receiver and support tower.
NZ588926A NZ588926A (en) 2008-05-07 2009-05-05 Lifting a load by an expanding a frame on the tower being assembled and inserting a new tower segment underneath
BRPI0912580A BRPI0912580A2 (en) 2008-05-07 2009-05-05 mounting method for solar receiver and support tower
CN200980116863.2A CN102016202B (en) 2008-05-07 2009-05-05 Erection method for solar receiver and support tower
ZA2010/07678A ZA201007678B (en) 2008-05-07 2010-10-27 Erection method for solar receiver and support tower
MA33298A MA32279B1 (en) 2008-05-07 2010-11-01 Enlightenment process for solar receiver and supportive
IL209119A IL209119A (en) 2008-05-07 2010-11-04 Erection method for solar receiver and support tower

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US5117108P 2008-05-07 2008-05-07
US61/051,171 2008-05-07

Publications (1)

Publication Number Publication Date
WO2009137445A1 true WO2009137445A1 (en) 2009-11-12

Family

ID=41264944

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2009/042794 WO2009137445A1 (en) 2008-05-07 2009-05-05 Erection method for solar receiver and support tower

Country Status (13)

Country Link
US (1) US8240051B2 (en)
EP (1) EP2286046A4 (en)
CN (1) CN102016202B (en)
AU (1) AU2009244469B2 (en)
BR (1) BRPI0912580A2 (en)
CA (1) CA2723514C (en)
EG (1) EG26711A (en)
IL (1) IL209119A (en)
MA (1) MA32279B1 (en)
MX (1) MX2010012068A (en)
NZ (1) NZ588926A (en)
WO (1) WO2009137445A1 (en)
ZA (1) ZA201007678B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669956A (en) * 2012-09-19 2014-03-26 阿尔斯通技术有限公司 Concentrated solar tower assembly and method
EP3208405A1 (en) * 2016-02-18 2017-08-23 Technische Hochschule Mittelhessen Device and method for assembling tower-like structures from pre-fabricated elements

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9163857B2 (en) 2009-02-12 2015-10-20 Babcock Power Services, Inc. Spray stations for temperature control in solar boilers
WO2010093748A2 (en) 2009-02-12 2010-08-19 Babcock Power Services Inc. Panel support system for solar boilers
US8517008B2 (en) 2009-02-12 2013-08-27 Babcock Power Services, Inc. Modular solar receiver panels and solar boilers with modular receiver panels
US8356591B2 (en) 2009-02-12 2013-01-22 Babcock Power Services, Inc. Corner structure for walls of panels in solar boilers
US8397710B2 (en) 2009-02-12 2013-03-19 Babcock Power Services Inc. Solar receiver panels
US9134043B2 (en) 2009-02-12 2015-09-15 Babcock Power Services Inc. Heat transfer passes for solar boilers
US8316843B2 (en) 2009-02-12 2012-11-27 Babcock Power Services Inc. Arrangement of tubing in solar boiler panels
US8893714B2 (en) 2009-02-12 2014-11-25 Babcock Power Services, Inc. Expansion joints for panels in solar boilers
US8443571B2 (en) * 2009-09-19 2013-05-21 Btpatent Llc Wind power equipment and assembly
US20110297206A1 (en) * 2010-06-08 2011-12-08 Timothy Devine Concentrated solar power receiver maintenance system
US8573196B2 (en) 2010-08-05 2013-11-05 Babcock Power Services, Inc. Startup/shutdown systems and methods for a solar thermal power generating facility
US20120199117A1 (en) * 2011-02-09 2012-08-09 Babcock Power Services, Inc. Systems and methods for solar boiler construction
US9038624B2 (en) 2011-06-08 2015-05-26 Babcock Power Services, Inc. Solar boiler tube panel supports
US8584429B2 (en) * 2011-09-30 2013-11-19 Tindall Corporation Tower erection system and method
US9562367B2 (en) * 2012-04-25 2017-02-07 Ampjack Industries Ltd. Utility tower lifting apparatus and method
US9945585B2 (en) 2014-05-15 2018-04-17 Alliance For Sustainable Energy, Llc Systems and methods for direct thermal receivers using near blackbody configurations
US9499954B2 (en) 2015-02-10 2016-11-22 Ambor Structures, Inc. Tower support structure
BE1023694B1 (en) * 2015-11-30 2017-06-16 Cockerill Maintenance & Ingenierie S.A. METHOD AND SYSTEM FOR MAINTENANCE FOR SOLAR RECEIVER
US10422552B2 (en) 2015-12-24 2019-09-24 Alliance For Sustainable Energy, Llc Receivers for concentrating solar power generation
US20180080217A1 (en) 2016-09-21 2018-03-22 Skyrise Global, Llc Structure and method of making the same
US11303243B2 (en) * 2019-10-03 2022-04-12 Ojjo, Inc. Systems and methods for constructing solar power plants with electrified heavy equipment
CN112429666B (en) * 2020-10-16 2022-07-08 中国能源建设集团湖南火电建设有限公司 Installation method and installation system device of megawatt tower type photo-thermal power generation heat collector

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6430692B1 (en) * 1998-09-25 2002-08-06 International Business Machines, Corporation Series-parallel battery array conversion
US6843030B2 (en) * 2003-05-13 2005-01-18 David Zingerman Self-lifting vertically rising mast
US20070283633A1 (en) * 2006-06-12 2007-12-13 Amos Klein Deployable watchtower

Family Cites Families (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3211427A (en) * 1961-01-03 1965-10-12 Jr William T Bristow Erection apparatus
DE1228040B (en) * 1961-09-19 1966-11-03 Markus Schmidt Tychsen Derrick Crane whose column is built up from a plurality of mast elements
DE2252836C2 (en) * 1972-10-27 1974-06-20 Liebherr, Hans, Dr.-Ing. E.H., 7950 Biberach Tower crane
US4196814A (en) * 1974-02-08 1980-04-08 E. H. Hans Liebherr Vertical telescoping lower crane
US3924604A (en) * 1974-05-31 1975-12-09 Schjeldahl Co G T Solar energy conversion system
DE2520717C2 (en) * 1975-05-09 1977-02-03 Hans Tax PROCEDURE FOR ERECTING A TOWER CRANE
US4013885A (en) * 1976-01-08 1977-03-22 Sanders Associates, Inc. Solar energy sun tracker
JPS5613345Y2 (en) * 1976-10-15 1981-03-27
SU831714A1 (en) * 1979-02-07 1981-05-23 Центральное Конструкторское Бюро"Строймаш" Device for extending crane tower
US4274542A (en) * 1979-02-26 1981-06-23 Fmc Corporation Method for transfer of crane from tower
SU1126530A1 (en) * 1983-08-12 1984-11-30 Научно-Производственное Объединение "Ленстроймаш" Device for section-by-section change of height of tower crane
US5263835A (en) * 1989-02-08 1993-11-23 Lubeca Construction Systems Pty. Ltd. Building construction system
JPH0321777A (en) * 1989-06-19 1991-01-30 Ishikawajima Harima Heavy Ind Co Ltd Construction method of iron-frame pillar
JPH08311818A (en) * 1995-05-18 1996-11-26 Tomoe Corp Climbing type lift-up construction method of building and device thereof
DE19647515B4 (en) * 1996-11-16 2010-04-15 Gerd-Albrecht Otto Wind converter mounting device
US5983634A (en) * 1998-03-18 1999-11-16 Drucker; Ernest R. Solar energy powerplant with mobile reflector walls
US6430892B1 (en) * 2000-10-02 2002-08-13 Geometrica, Inc. Apparatus and method for building a domed structure
JP3732414B2 (en) * 2001-02-15 2006-01-05 株式会社巴技研 Method and apparatus for constructing tower structure
US20030213647A1 (en) * 2002-05-20 2003-11-20 Andre St-Germain Removable tower sleeve
US6868646B1 (en) * 2002-12-13 2005-03-22 Valmont Industries, Inc. Method and means for erecting a wind energy tower
US7115851B2 (en) * 2004-08-30 2006-10-03 Yaoming Zhang Heliostat device
JP3905103B2 (en) * 2004-09-09 2007-04-18 三井住友建設株式会社 Tower-like building erection method and erection device
US7690377B2 (en) * 2006-05-11 2010-04-06 Brightsource Energy, Inc. High temperature solar receiver
EP1857670B1 (en) * 2006-05-20 2011-07-20 W2E Wind to Energy GmbH System for erecting a wind turbine tower consisting of tower segments
US8011098B2 (en) * 2008-08-19 2011-09-06 Vorhies Roger W Wind turbine erector
US8544237B2 (en) * 2009-01-07 2013-10-01 Aerojet Rocketdyne Of De, Inc. Lifting system for solar power tower components

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6430692B1 (en) * 1998-09-25 2002-08-06 International Business Machines, Corporation Series-parallel battery array conversion
US6843030B2 (en) * 2003-05-13 2005-01-18 David Zingerman Self-lifting vertically rising mast
US20070283633A1 (en) * 2006-06-12 2007-12-13 Amos Klein Deployable watchtower

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP2286046A4 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669956A (en) * 2012-09-19 2014-03-26 阿尔斯通技术有限公司 Concentrated solar tower assembly and method
EP2711487A1 (en) * 2012-09-19 2014-03-26 Alstom Technology Ltd Concentrated solar tower assembly and method
CN103669956B (en) * 2012-09-19 2016-03-16 阿尔斯通技术有限公司 Centralized solar column assembly and method
US9366456B2 (en) 2012-09-19 2016-06-14 Alstom Technology Ltd. Concentrated solar tower assembly and method
EP3208405A1 (en) * 2016-02-18 2017-08-23 Technische Hochschule Mittelhessen Device and method for assembling tower-like structures from pre-fabricated elements

Also Published As

Publication number Publication date
IL209119A (en) 2013-06-27
AU2009244469A2 (en) 2011-01-06
MA32279B1 (en) 2011-05-02
AU2009244469A1 (en) 2009-11-12
EP2286046A4 (en) 2014-06-25
CA2723514C (en) 2016-07-05
ZA201007678B (en) 2011-07-27
US8240051B2 (en) 2012-08-14
US20090276993A1 (en) 2009-11-12
CA2723514A1 (en) 2009-11-12
CN102016202A (en) 2011-04-13
EP2286046A1 (en) 2011-02-23
NZ588926A (en) 2013-02-22
MX2010012068A (en) 2010-12-06
CN102016202B (en) 2014-02-26
AU2009244469B2 (en) 2014-10-30
EG26711A (en) 2014-06-15
IL209119A0 (en) 2011-01-31
BRPI0912580A2 (en) 2019-07-16

Similar Documents

Publication Publication Date Title
CA2723514C (en) Erection method for solar receiver & support tower
US8297025B2 (en) Method of building a hybrid tower for a wind generator
EP1518053B1 (en) Method and crane for installing, maintaining, and decommissioning wind turbines
EP2454427B1 (en) Telescopic tower assembly and method
US8959870B2 (en) Fluid-actuated telescoping tower for supporting heavy loads
CN108050018B (en) Wind turbine tower erection system
JP2007071097A (en) Construction method of wind power generation tower
CN103243961B (en) Titanium plate steel inner tank reversed construction device for chimney of thermal power station
KR19990072014A (en) Lift-up method for building buildings from above to the ground
WO2005028781A2 (en) Composite tower for a wind turbine and method of assembly
US20120304588A1 (en) Method for Erecting a Wind Turbine Tower
EP3130796A1 (en) Wind turbine assembly system and related method
CN113348289A (en) Multi-column wind turbine tower and erection method
CN110745714B (en) Self-lifting installation method of hoisting tower system
CN115163417A (en) Truss type large wind turbine generator set, self-jacking installation device and method
JPH10205429A (en) Construction method for wind power generator
DK2748100T3 (en) COMPONENT OF A WINDOW INSTALLATION FOR RENT FOR THE HANDLING OF THE COMPONENT AND CARRIERS FOR HANDLING THE COMPONENTS OF A WINDOW INSTALLATION
CN114046083B (en) Construction method for building steel inner cylinder chimney
CN217841894U (en) Truss type large wind turbine generator and self-jacking installation device
EP4100354A1 (en) Crane system for assembling a wind turbine and a method for using the crane system
CN111315947A (en) Method for building a tower having a multi-part tower segment and segments in a multi-part tower segment of a tower
WO2013024203A1 (en) Method and arrangement for erecting wind power plant
AU2011201502B8 (en) Method of building a hybrid tower for a wind generator
WO2022103348A1 (en) A multi-pod support structure for a wind turbine tower

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 200980116863.2

Country of ref document: CN

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 09743431

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 2009244469

Country of ref document: AU

WWE Wipo information: entry into national phase

Ref document number: 4042/KOLNP/2010

Country of ref document: IN

WWE Wipo information: entry into national phase

Ref document number: 588926

Country of ref document: NZ

REEP Request for entry into the european phase

Ref document number: 2009743431

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2723514

Country of ref document: CA

Ref document number: MX/A/2010/012068

Country of ref document: MX

Ref document number: 2009743431

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2009244469

Country of ref document: AU

Date of ref document: 20090505

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: DZP2010000747

Country of ref document: DZ

REG Reference to national code

Ref country code: BR

Ref legal event code: B01E

Ref document number: PI0912580

Country of ref document: BR

Free format text: APRESENTE NOVAS VIAS DA CESSAO DA PRIORIDADE REIVINDICADA UMA VEZ QUE NA PETICAO 020100120590 DE 27/12/2010 FOI APRESENTADA APENAS A TRADUCAO SEM OS ORIGINAIS DA CESSAO.

ENP Entry into the national phase

Ref document number: PI0912580

Country of ref document: BR

Kind code of ref document: A2

Effective date: 20101104