WO2005080875A1 - Circulating fluidized bed burning method for waste liquor of paper making, hide manufacture, printing and dyeing - Google Patents

Circulating fluidized bed burning method for waste liquor of paper making, hide manufacture, printing and dyeing Download PDF

Info

Publication number
WO2005080875A1
WO2005080875A1 PCT/CN2005/000059 CN2005000059W WO2005080875A1 WO 2005080875 A1 WO2005080875 A1 WO 2005080875A1 CN 2005000059 W CN2005000059 W CN 2005000059W WO 2005080875 A1 WO2005080875 A1 WO 2005080875A1
Authority
WO
WIPO (PCT)
Prior art keywords
waste liquid
coal
circulating fluidized
coal slurry
combustion
Prior art date
Application number
PCT/CN2005/000059
Other languages
French (fr)
Chinese (zh)
Inventor
Dawei Zhang
Original Assignee
Shenyang David International Machinery & Electric Equipment Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang David International Machinery & Electric Equipment Co., Ltd. filed Critical Shenyang David International Machinery & Electric Equipment Co., Ltd.
Publication of WO2005080875A1 publication Critical patent/WO2005080875A1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G7/00Incinerators or other apparatus for consuming industrial waste, e.g. chemicals
    • F23G7/04Incinerators or other apparatus for consuming industrial waste, e.g. chemicals of waste liquors, e.g. sulfite liquors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/006General arrangement of incineration plant, e.g. flow sheets
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/30Incineration of waste; Incinerator constructions; Details, accessories or control therefor having a fluidised bed

Definitions

  • the invention relates to a method for treating sludge, waste liquid, cooking liquid (black liquid, red liquid), tail liquid and waste water produced in an industrial production process, and particularly relates to a circulating fluidized combustion method for treating papermaking, making The method of leather, printing and dyeing industry waste liquid and wastewater can treat and comprehensively utilize its tail liquid and sewage. Background technique
  • China's papermaking pollution control technology is mainly divided into four categories:
  • the present invention provides a method for treating waste liquid from papermaking, tanning, printing and dyeing industries by using a circulating fluidized combustion method.
  • the waste liquid, waste water and sludge produced in the process are treated and comprehensively utilized.
  • the technical solution of the present invention to solve the technical problems and achieve the objectives of the present invention is to provide a method for treating waste water from papermaking, tanning, and printing and dyeing industries by using a circulating fluidized combustion method, including the following steps:
  • Coal filter mud preparation step that is, the use of coal-based activated carbon and quicklime as adsorption and filter materials
  • the wastewater produced in the production process is subjected to adsorption, precipitation, and filtration treatment to produce a combustible substance that contains intermediate wastewater Slime
  • Waste liquid coal slurry preparation step that is, adding pulverized coal and dispersant to the prepared coal sludge, stirring, and then adding a stabilizer to prepare waste liquid coal slurry for use as boiler fuel;
  • Waste liquid coal slurry combustion step that is, the prepared waste liquid coal slurry is transported to a circulating fluidized bed boiler for combustion to produce steam or hot water.
  • the furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
  • the weight ratio of the coal powder and water in the waste liquid coal slurry is 7: 3.
  • a method for treating waste liquid of papermaking, tanning, and printing and dyeing industries by using a circulating fluidized combustion method including the following steps:
  • a waste liquid coal slurry preparation step that is, adding granular coal to waste liquid containing combustible substances, ball milling in a ball mill into a mixed coal slurry with a particle diameter of 50-150 ⁇ m, and then adding a stabilizer to stir Into a waste liquid coal slurry;
  • a waste liquid coal slurry combustion step that is, transporting the prepared waste liquid coal slurry to a circulating fluidized bed boiler for combustion to produce steam or hot water, wherein the furnace of the circulating fluidized bed boiler has Including fluidized media composed of quartz sand and limestone.
  • a circulating fluidized combustion method for treating papermaking, tanning, and printing.
  • the method for dyeing industrial waste liquid includes the following steps:
  • a waste liquid coal paddle preparation step that is, coal powder and waste liquid in a weight ratio of 6: 4 and a stabilizer are sent to a pulping tank for mixing and stirring to produce waste liquid coal slurry;
  • the waste liquid coal slurry combustion step that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water.
  • the furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
  • a method for treating papermaking, tanning, and printing and dyeing industrial waste liquids by using a circulating fluidized combustion method including the following steps-a.
  • a step for preparing liquid coal slurry that is, washing coal particles and black mud for papermaking , Waste water and dispersant, according to the washed coal particles, black mud and waste water in a ratio of 6: 2: 2, added to a ball mill for wet grinding, grind the washed coal particles into a mixed slurry with a particle diameter of 50-100 ⁇ m, and send it to the pulping tank. Add stabilizer to make waste liquid coal slurry;
  • the waste liquid coal slurry combustion step that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water.
  • the furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
  • the method further includes using a screw pump to supply the waste liquid coal slurry from the middle or top of the circulating fluidized bed boiler. Pulp injection. If the circulating fluidized bed boiler only uses waste liquid coal slurry as fuel, the spiral coal feeding equipment is eliminated. If the boiler uses coal and waste liquid coal slurry as fuel, the spiral coal feeder is retained.
  • the injection pressure of the waste liquid coal slurry is 0.3Mpa.
  • the combustion temperature of the circulating fluidized bed boiler is controlled at 850-950 ° C.
  • the method further includes placing unburned coal and garbage particles carried out by the hot flue gas in all places.
  • the combustion fluid outlet of the circulating fluidized bed boiler or the fly ash separator at the rear is separated and captured, and then sent back to the dense phase area of the combustion chamber for circulating combustion through a return device provided at the lower part of the separator.
  • the dust removal rate of circulating flow boilers can reach 99.9%, and the concentration of soot in the side gas is ⁇ 80mgm 3 .
  • the S (3 ⁇ 4 emission concentration in the flue gas is ⁇ 100mg m 3
  • the NOx concentration is less than 150mg m 3
  • the manganese blackness of the flue gas is ⁇ 1, which is in accordance with national standards for atmospheric environmental protection.
  • Circulating fluidized bed boilers can use hot water boilers, low pressure steam boilers or high and medium pressure steam boilers. It can be used by enterprises to produce steam, and can also be used for heating or power generation, forming the integration of wastewater treatment, steam use and power generation, in order to save a lot of energy costs and wastewater treatment costs.
  • the fly ash collected by the dust collector after the waste liquid coal propeller is combusted can be used. After the waste liquid coal slurry is suspended and cleaned and burned in a circulating fluidized bed boiler, the fly ash generated is collected by the dust collector and transported by a sealed conveying device to the In a sealed ash bin, after reaching a certain amount, it is transported away by pulverized coal, which saves the environment from flying, and the fly ash has a high comprehensive utilization value.
  • FIG. 1 is a process flow diagram of using a circulating fluidized combustion method to treat papermaking, tanning, printing and dyeing industrial wastewater, and preparing waste liquid coal slurry and burning the waste liquid coal slurry.
  • FIG. 2 is a process flow diagram of using the circulating fluidized combustion method to treat papermaking, tanning, and printing and dyeing industrial waste liquid (cooking liquid), sludge, and black mud to prepare waste liquid coal slurry and burn the waste liquid coal slurry.
  • Clean Water industrial waste liquid
  • sludge sludge
  • black mud waste liquid coal slurry
  • Wastewater is filtered, adsorbed, and settled to produce waste liquid coal slurry with effective energy substances.
  • the process flow is shown in Figure 1.
  • a circulating fluidized combustion method is used to treat papermaking and tanning.
  • a method for printing and dyeing industrial waste liquid including the following steps:
  • the coal filtering mud preparation step is made by using coal activated carbon and quicklime as adsorption and filtering materials, and absorbing, precipitating and filtering the wastewater generated in the production process.
  • the waste liquid coal paddle of fuel; the waste liquid coal paddle combustion step, that is, the prepared waste liquid coal slurry is sent to a circulating fluidized bed boiler for combustion to produce steam or hot water, and the furnace of the circulating fluidized bed boiler includes Fluidized medium consisting of quartz sand and limestone.
  • pulverized coal, coal-based activated carbon, and quicklime are added to the filter tank 3, and a multi-stage filter tank 3 can be constructed as required.
  • the pulverized coal, coal-based activated carbon, and quicklime added to the filter tank 3 have strong adsorption and flocculation properties as filter materials.
  • the wastewater flows through the filter tank 3 (or multi-stage filtration)
  • the wastewater contains Most of the fine fibers, lignin and other organic substances are filtered out and adsorbed in the filter material such as pulverized coal in the filter tank 3, and the remainder A part of the fine coal powder exists in the filtered water in the form of colloid, and flows into the sedimentation tank 6, and the sedimentation effect is generated by flocculation.
  • the fine short fibers, lignin and other organic substances in the wastewater are settled together with the coal powder, and the upper part of the sedimentation tank
  • the water flows into the treatment tank, and the coal slurry in the lower part of the sedimentation tank is transported to the bottom flow storage tank 5 of the wastewater sedimentation tank through the screw pump 14-1 in the lower part of the sedimentation tank.
  • the filter material such as coal powder in the filter pool is used to filter and adsorb a large amount of organic matter and suspended matter, to a certain extent, it reaches a saturated state, and does not play an adsorption role, and then becomes a coal filter mud, which saturates the filter pool 3
  • Coal sludge is transported to the bottom sedimentation tank 5 of the wastewater sedimentation tank through the screw pump 14-1, and the bottom sedimentation tank 5 of the wastewater sedimentation tank is used as the secondary sedimentation tank.
  • the water in the bottom sedimentation tank 5 of the wastewater sedimentation tank is discharged to the treatment tank 4.
  • the coal sludge in the lower part of the bottom flow storage tank 5 of the wastewater sedimentation tank is transported to the pulping tank 7 by the screw pump 14-2.
  • the filter material in the filter tank 3 contains a certain amount of coal-based activated carbon and calcium hydroxide, and at the same time as filtering, it also plays a role in denitrification, dephosphorization, decolorization, and deodorization of wastewater.
  • the coal filter sludge sent to the pulping tank 7 must be tested before each batch is added to check the water content, etc., and then a certain amount of coal powder or wastewater is added in proportion so that the coal to water ratio is 7: 3 Right and left, add the dispersant to start the stirrer on the top of the pulping tank, stir, then add the stabilizer to continue stirring, and then cut through the shearing conveying pump 14-3, mature, and then transport it to the waste liquid coal slurry storage tank 15 Medium storage.
  • the water in the treatment tank 4 is pumped to the original wastewater treatment equipment of the enterprise for further treatment, and then returned to the production system for use.
  • the process flow chart is shown in FIG. 2.
  • the equipment of the combustion part of the waste liquid coal slurry is the same as that in FIG. 1, and the same reference numerals are used.
  • the waste liquid coal slurry is produced by washing coal particles.
  • a method for treating the waste liquid of papermaking, tanning, and printing and dyeing by using a circulating fluidized combustion method is provided.
  • the method includes the following steps: a waste liquid coal slurry preparation step, that is, adding granular organic coal to the waste liquid containing organic substances, ball milling in a ball mill into a mixed coal slurry having a particle diameter of 50-150 ⁇ m, and then adding a stabilizer to stir The waste liquid coal slurry is burned.
  • the waste liquid coal slurry is burned, that is, the prepared waste liquid coal slurry is sent to a circulating fluidized bed boiler for combustion to produce steam or hot water.
  • the furnace of the circulating fluidized bed boiler includes Fluidized medium consisting of quartz sand and limestone.
  • the washed coal particles are crushed and weighed by a crusher 19, and then sent to a ball mill 20 through a conveying device, and
  • the waste liquid in the waste liquid storage tank 8 is sent to the ball mill 20 through the screw pump 14-2 in proportion, and the coal particles are ground to a coal slurry with a particle size of 50 to 100 ⁇ m, and then the screw pump 14'-2 It is transported to the pulping tank 7 and added with a stabilizer for stirring. After being sheared and matured by a shearing conveying pump 14-3, it is transported to a waste liquid coal slurry storage tank 15 for storage.
  • a method for treating waste liquid of papermaking, tanning, printing and dyeing industry by using a circulating fluidized combustion method including the following steps: a waste liquid coal slurry preparation step, that is, a coal powder and a waste liquid are 6 by weight: 4 ratio and stabilizer are sent to the pulping tank for mixing and stirring to produce waste liquid coal slurry; the waste liquid coal slurry combustion step is to transport the prepared waste liquid coal slurry to a circulating fluidized bed boiler for combustion to produce steam or Hot water, in which the fluidized medium consisting of quartz sand and limestone is contained in the hearth of a circulating fluidized bed boiler.
  • the equipment such as the crusher 19 and the ball mill 20 must be removed, and the pulverized coal silo (not shown), the waste liquid storage tank 17 and the additive tank 9 should be directly transferred to the pulping tank 7.
  • waste liquid coal slurry Before the production of each batch of waste liquid coal slurry, the coal powder and waste liquid must be tested and a small test must be performed to determine the proportion of coal powder, waste liquid and additives.
  • the method includes the following steps: a step of preparing waste liquid coal slurry, that is, washing coal particles and black mud of papermaking, waste water, and dispersant; adding the washed coal particles, black mud, and waste water to a ball mill in a ratio of 6: 2: 2; The granule is ground into a mixed slurry with a particle diameter of 50-100 ⁇ m, and then sent to a pulping tank to add a stabilizer to prepare a waste liquid coal slurry.
  • the waste liquid coal slurry combustion step is to transport the prepared waste liquid coal slurry to a circulating stream.
  • a fluidized bed boiler is used for combustion to produce steam or hot water.
  • a furnace of a circulating fluidized bed boiler includes a fluidized medium composed of quartz sand and limestone.
  • the washed coal particles are crushed and weighed by the crusher 19, and then sent to the ball mill 20 through the conveying equipment, and the black mud (sludge) is fed to the ball mill 20 through the screw pump 14'-2, and the waste water and dispersant are proportionally added.
  • the coal particles After grinding the coal particles into coal paddles with a particle size of 50 — 100 ⁇ ⁇ m, they are sent to the pulping tank 7 ′ by the screw pump 14 ′ -2, and the stabilizer is stirred into the mouth, and then cut through Wi ⁇ l4,- 3 After shearing and aging, send to storage tank 15 for storage.
  • the present invention modifies the circulating fluidized bed boiler 1.
  • circulating fluidized bed boilers at home and abroad all use dry pulverized coal as fuel, and a screw conveyor is used at the lower part of the boiler to send coal into the furnace.
  • the circulating fluidized bed boiler 1 for burning waste liquid coal slurry is based on the original boiler design, and a waste liquid coal slurry supply port is installed at the top or middle of the boiler. If the circulating fluidized bed boiler 1 only uses waste liquid coal slurry as fuel, then The auger coal feeding equipment is abolished. If the boiler uses coal and waste liquid coal slurry as fuel, the auger coal feeder is retained.
  • the circulating fluidized bed boiler 1 of the waste liquid coal slurry is ignited by hot air flow. After the diesel is atomized by the ignition gun, it is burned in the pre-combustion cylinder. Air, heated high-temperature air enters the fluidized bed material layer through the air distribution plate. When the bed material is heated above 450 ° C, a small amount of waste liquid coal slurry is added to the circulating fluidized bed boiler 1. At this time, the furnace The temperature rises quickly. When the temperature in the circulating fluidized bed boiler 1 reaches 600 ° C, the amount of paddle supply can be gradually increased. The furnace temperature rises quickly, and the waste liquid coal slurry has been burned normally. At this time, the oil supply is stopped and the pre-heating is cut off. The combustion chamber completes the ignition and increases the supply of waste liquid coal slurry. »The fans 11 and induced draft fans 13 are adjusted to the air volume required for normal negative boating.
  • the waste liquid coal slurry is directly sent from the storage tank 15 to the circulating fluidized bed boiler 1 through the screw slurry pump 12 at a pressure of about 0.3 MPa. After entering the circulating fluidized bed boiler 1 through the slurry supply port, the waste liquid coal slurry becomes Drop-shaped, drop-shaped waste liquid coal slurry is in the furnace. It is turned into finer particles due to the fluidized hot air flow in the furnace. It is tumbling and falling down in the furnace at the temperature of 850-950 ° C. During the falling process, The droplets are heated, decomposed and started to burn, and then poured into a fluidized bed composed of quartz sand and limestone.
  • the precipitation of moisture and volatiles is quickly completed, and the fire and combustion Coke is burned, and the fine particles of granular waste liquid coal slurry mass further disintegrated in the fluidized state are taken out of the dense phase zone by the hot flue gas, enter the suspension chamber to continue burning, and there is a fly at the exit or rear of the combustion chamber.
  • the ash separation and return device, the media material carried out by the hot flue gas and the large unburned particles are separated and captured by the separator, and returned to the dense phase area of the combustion chamber through the return device provided at the bottom of the separator for cyclic combustion. ,
  • the combustion efficiency is 98%.
  • the waste liquid coal is burned in the furnace at 850-95CTC at low temperature, which effectively inhibits the generation of thermal NOx during the combustion process. Because quartz sand and limestone are added as media materials in the furnace, limestone is decomposed at high temperature to generate CaO and waste liquid coal.
  • the S0 2 formed after the sulfur in the pulverized coal in the slurry is combusted to generate CaS0 4 .
  • the response is:
  • the emission of so 2 in the flue gas is suppressed, and direct desulfurization in the circulating fluidized bed boiler 1 is achieved.
  • the particle size of the limestone (desulfurizing agent) added to the circulating fluidized bed boiler 1 is selected from about 1-2 mm, and the calcium / ⁇ molar ratio is 1.5-2.5 when the desulfurization efficiency of 85% -95% is reached.
  • Flammable organic materials such as lignin and hemicellulose contained in the waste liquid are converted into heat energy after being burned in the furnace. Other materials such as alkali generate sodium salts, sodium calcium and other materials during the combustion process and are mixed in the fly ash and discharged.
  • the circulating fluidized bed boiler 1 contains exhausted fly ash in the flue gas, which is collected by an electrostatic precipitator or a bag precipitator 2.
  • the dust removal rate can reach 99.9%, and the smoke concentration in the gas is ⁇ 80mg1 ⁇ 2 3 .
  • S (3 ⁇ 4 3 ⁇ 41 ⁇ 23 ⁇ 4g ⁇ 100mg / m 3 , NOx fiber concentration ⁇ 150mg m 3 , smoke manganese blackness ⁇ 1, which is the national standard for environmental protection requirements.
  • the circulating fluidized bed boiler 1 can be a hot water boiler, a low pressure steam boiler or a high or medium pressure steam boiler.
  • the produced steam can be used by enterprises to produce steam, and it can also be used for heating or power generation, forming a wastewater treatment, steam and power integration. It saves enterprises a lot of energy costs, waste water treatment costs, and increases revenue. Every 1 ton of black liquor burned in the paper industry (the calorific value in the black liquor of papermaking is 8.37-10.04MJ / kg) is equivalent to saving 0.28 ⁇ 0.34 tons of standard coal.
  • the fly ash collected by the dust collector 2 after the waste liquid coal slurry is combusted can be used. After the waste liquid coal slurry is burned by the circulating fluidized bed boiler 1, the fly ash generated is collected by the dust collector 2 and transported by a sealed conveying device. In the sealed ash bin 5, after reaching a certain amount, it is transported by pulverized coal, which completely saves the environmental pollution of the flying ash, and the flying ash has very high comprehensive utilization value. There are two main sheds:
  • Fly ash is gelatinous and contains CaS0 4. It is a substitute for slag and gypsum needed to make cement. It lacks sufficient slag resources. It is a raw material for making cement. It can be made into 325 with 50% each of cement clinker. # Cement, fly ash with high CaS0 4 content can make special cement and expansion agent.
  • the waste liquid coal slurry contains a large amount of alkali, lignin, glycan, calcium salts and the like, when burning in a furnace at 850 ⁇ 950 ° C, the above substances are converted into sodium salts, calcium salts, nitrogen, calcium phosphate
  • High-active materials such as high-active materials are discharged together with fly ash.
  • Fly ash containing high-active materials such as sodium salt, calcium salt, nitrogen, and calcium phosphate is not only a good base for organic fertilizers, but also can be used as an acid soil improver.
  • the waste liquid coal slurry is pumped into a circulating fluidized bed steam boiler with a screw pump.
  • the boiler burns 10.5 tons of waste liquid coal slurry per hour, and produces 75 tons per hour (the pressure is 1.6Mpa—3.82Mpa, temperature 240—450 ° C).
  • the flue gas after combustion is discharged by the electrostatic precipitator.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paper (AREA)
  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

A treatment method for waste liquor of paper making, hide manufacture, printing and dyeing uses a circulating fluidized bed burning method. Said method includes a filtered coal mud preparing step, a waste liquor and coal slurry preparing step, and a waste liquor and coal slurry burning step. In the filtered coal mud preparing step, coal active carbon and calcium lime is used as adsorbing and filtering material to treat the waste liquor by adsorbing depositing and filtering, to prepare filtered coal mud containing combustible substance from the waste liquor. In the waste liquor and coal slurry preparing step, pulverized coal, water and dispersing is added in the filtered coal mud, sludge and waste liquor, then stirred, then added in stabilizing agent, to prepare waste liquor and coal slurry for boiler. In the waste liquor and coal slurry burning step, quartz sand and limestone is used as fluidized medium in the chamber of the circulating fluidized bed boiler, and the waste liquor and coal slurry is fed into the circulating fluidized bed boiler to burn to produce steam and hot water. The treatment method uses circulating fluidized floating burning method to treat and utilize black liquor from production.

Description

循环流化燃烧法处理造纸、 制革、 印染工业废液的方法  Method for treating waste liquid of papermaking, tanning, printing and dyeing industry by circulating fluidized combustion method
技术领域 Technical field
本发明涉及一种对工业生产过程中产生的污泥、 废液、 蒸煮液(黑液、 红液) 、 尾液和废水进行处理的方法, 特别涉及一种循环流化燃烧法处理造纸、 制革、 印染工 业废液、 废水的方法, 可对其尾液、 污水进行治理及综合利用。 背景技术  The invention relates to a method for treating sludge, waste liquid, cooking liquid (black liquid, red liquid), tail liquid and waste water produced in an industrial production process, and particularly relates to a circulating fluidized combustion method for treating papermaking, making The method of leather, printing and dyeing industry waste liquid and wastewater can treat and comprehensively utilize its tail liquid and sewage. Background technique
目前造纸、 制革、 印染行业生产过程中产生的蒸煮液(黑液、 红液)、 废^、 尾 液、污泥等治理方法都存在着一定的缺欠,特别是造纸厂黑液的治理成为了世界性的 难题, 甚至由于污染治理不了, 使一些造纸厂只好停产。  At present, there are certain deficiencies in the treatment methods of cooking liquor (black liquor, red liquor), waste fluid, tail liquor, sludge and other treatment methods produced in the papermaking, tanning, printing and dyeing industries, especially the treatment of black liquor in paper mills. Because of the worldwide difficulties, some paper mills had to stop production because pollution could not be controlled.
目前我国造纸污染治理技术主要分为四大类:  At present, China's papermaking pollution control technology is mainly divided into four categories:
( 1 )碱回收技术, 该技术投资大、 运行费用高, 以及生产规模制约, 2万吨 /年 以下规模的造纸厂无法釆用, 已建成的碱回收生产线大约 55%没有投入使用。  (1) Alkali recovery technology. This technology has large investment, high operating costs, and production scale constraints. Paper mills below 20,000 tons / year cannot be used. About 55% of the already-built alkali recovery production line is not put into use.
(2) 物化加生化技术, 采用各种药剂进行沉淀、 絮凝、 气浮等物理及 学的方 法加上活性污泥曝气或厌氧发酵等进行生化处理, 此类技术投资多、 占地面积大、 运行费用高、 污染治理效果不好。  (2) Physical, chemical and biochemical technologies, which use various chemical and physical methods such as precipitation, flocculation, and air flotation, plus activated sludge aeration or anaerobic fermentation, etc. for biochemical treatment. Such technologies have a large investment and occupy a large area. Large, high operating costs, and poor pollution control.
(3 ) 蒸发、 浓缩技术, 这种方法将黑液蒸发、 浓缩、 干燥转化成产品, 但由于 转化成的产品市场未开发, 致使技术无法利用, 也有企业将黑液蒸发、浓缩后, 喷入 锅炉燃掉, 由于工艺复杂, 处理成本高, 技术无法推广。  (3) Evaporation and concentration technology. This method converts black liquor into products by evaporation, concentration, and drying. However, because the market for the converted products has not been developed, the technology cannot be used. There are also companies that spray and inject black liquor into The boiler is burned out. Due to the complicated process and high processing cost, the technology cannot be promoted.
(4) 目前国内利用回收废纸进行 的企业, ^过程产生大量的黑泥, 目前大多数 職 都无舰黑翻亍处理利用,只離腿埋, 5 t看,鹏 H ^已经处理,而这 种掩疆理方式实际上却对周围环境、 土壤和地下 7Xi J¾了长期的严重污染。  (4) At present, domestic enterprises using recycled waste paper produce a large amount of black mud. At present, most of the posts have no ship black turning 亍 processing and utilization, only buried from the legs, 5 t, Peng H ^ has been processed, and In fact, this method of covering up the border has actually caused long-term serious pollution to the surrounding environment, soil and underground.
综合起来, 目前典型的黑液、 废水污染治理工艺存在着以下问题:  Taken together, the current typical black liquor and wastewater pollution treatment processes have the following problems:
1、 投资大、 处理费用高、 中小造纸厂承担不起。 我国的造纸工业是在资金严重 短缺, 木材原料供应困难的条件下发展起来的, 以发展小型草类制浆造纸厂为主, 这 些企业规模小、 产品档次低、 装备水平和人员素质差、 利润低、 产污系数高, 治理污 染受到处理成本制约。 2、 已建成环保治理设施技术可靠性差, 不能保证正常运行, 更难保证达标排放, 致使企业白白浪费了投入的资金。 1. Large investment, high processing costs, and small and medium-sized paper mills cannot afford it. China's paper industry is developed under the severe shortage of funds and the difficult supply of wood raw materials. It is mainly based on the development of small grass pulp and paper mills. These enterprises are small in scale, low in product quality, poor in equipment and personnel, and profitable. Low, high pollution production coefficient, pollution control is limited by treatment costs. 2. The technical reliability of the completed environmental protection and treatment facilities is poor, and normal operation cannot be guaranteed, and it is more difficult to ensure compliance with emissions. As a result, enterprises have wasted their input funds.
3、 生化处理过程不能正常运行, 普遍靠加药絮凝剂来维持。  3. The biochemical treatment process cannot run normally, and it is generally maintained by adding flocculants.
4、 治污对企业缺乏综合利用价值, 不能为企业带来直接效益, 企业是被动治理, 缺乏主动性。 发明内容  4. Pollution control lacks comprehensive utilization value for enterprises and cannot bring direct benefits to enterprises. Enterprises are passively governed and lack initiative. Summary of the invention
针对现有的造纸、 制革、 印染行业废液、废水污染治理环保技术普遍存在的问题, 本 发明提供一种采用循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 对生产过 程中产生的废液、 废水、 污泥进行治理和综合利用。  Aiming at the general problems of the existing environmental protection technology of waste liquid and waste water pollution treatment in the papermaking, tanning, printing and dyeing industries, the present invention provides a method for treating waste liquid from papermaking, tanning, printing and dyeing industries by using a circulating fluidized combustion method. The waste liquid, waste water and sludge produced in the process are treated and comprehensively utilized.
本发明解决技术问题并实现发明目的的技术方案为,提供一种采用循环流化燃烧 法处理造纸、 制革、 印染工业废液的方法, 包括如下步骤:  The technical solution of the present invention to solve the technical problems and achieve the objectives of the present invention is to provide a method for treating waste water from papermaking, tanning, and printing and dyeing industries by using a circulating fluidized combustion method, including the following steps:
a. 煤滤泥制备步骤, 即通过利用煤质活性碳和生石灰作为吸附、 过滤材料, 将 生产生产过程中产生的废水经过吸附、 沉淀、 过滤处理而制成其内包含中段废水中的 可燃物质的煤泥;  a. Coal filter mud preparation step, that is, the use of coal-based activated carbon and quicklime as adsorption and filter materials, the wastewater produced in the production process is subjected to adsorption, precipitation, and filtration treatment to produce a combustible substance that contains intermediate wastewater Slime
b、 废液煤浆制备步骤, 即向己制备的煤滤泥中加入煤粉、 分散剂, 进行搅拌之 后再加入稳定剂, 以制成用做锅炉燃料的废液煤浆;  b. Waste liquid coal slurry preparation step, that is, adding pulverized coal and dispersant to the prepared coal sludge, stirring, and then adding a stabilizer to prepare waste liquid coal slurry for use as boiler fuel;
c 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石组成的流 化介质。  c Waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transported to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
在上述循环流化燃烧法处理造纸、制革、 印染工业废液的方法的废液煤浆制备步 骤中, 废液煤浆中的煤粉和水分的重量比为 7: 3。  In the waste liquid coal slurry preparation step of the above-mentioned circulating fluidized combustion method for treating papermaking, tanning, and printing and dyeing industry waste liquid, the weight ratio of the coal powder and water in the waste liquid coal slurry is 7: 3.
根据本发明的另一方面, 提供一种采用循环流化燃烧法处理造纸、 制革、 印染工 业废液的方法, 包括如下步骤:  According to another aspect of the present invention, a method for treating waste liquid of papermaking, tanning, and printing and dyeing industries by using a circulating fluidized combustion method is provided, including the following steps:
a. 废液煤浆制备步骤, 即将粒煤中加入其内还有可燃物质的废液中, 在球磨机 中球磨成颗粒直径为 50— 150 μ m的混合煤浆, 然后再加入稳定剂搅拌制成废液煤浆; b. 废液煤浆燃烧步骤, 即将己制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石组成的流 化介质。  a waste liquid coal slurry preparation step, that is, adding granular coal to waste liquid containing combustible substances, ball milling in a ball mill into a mixed coal slurry with a particle diameter of 50-150 μm, and then adding a stabilizer to stir Into a waste liquid coal slurry; b. A waste liquid coal slurry combustion step, that is, transporting the prepared waste liquid coal slurry to a circulating fluidized bed boiler for combustion to produce steam or hot water, wherein the furnace of the circulating fluidized bed boiler has Including fluidized media composed of quartz sand and limestone.
根据本发明更进一步的方面, 提供一种采用循环流化燃烧法处理造纸、 制革、 印 染工业废液的方法, 包括如下步骤: According to a further aspect of the present invention, a circulating fluidized combustion method is provided for treating papermaking, tanning, and printing. The method for dyeing industrial waste liquid includes the following steps:
a.废液煤桨制备步骤, 即将煤粉和废液按重量比为 6: 4的比例及稳定剂送入制浆 罐进行混合搅拌, 制作废液煤浆;  a waste liquid coal paddle preparation step, that is, coal powder and waste liquid in a weight ratio of 6: 4 and a stabilizer are sent to a pulping tank for mixing and stirring to produce waste liquid coal slurry;
b. 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石的流化介 质。  b. The waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
根据本发明再进一步的方面, 提供一种采用循环流化燃烧法处理造纸、 制革、 印 染工业废液的方法, 包括如下步骤- a. 废液煤浆制备步骤, 即将洗煤粒和造纸黑泥、 废水以及分散剂, 按洗煤粒、 黑泥和废水按 6: 2: 2的比例加入球磨机中湿磨, 将洗煤粒磨成颗粒直径为 50— 100 μ m的混合浆, 再送入制浆罐加入稳定剂, 制成废液煤浆;  According to a still further aspect of the present invention, a method for treating papermaking, tanning, and printing and dyeing industrial waste liquids by using a circulating fluidized combustion method is provided, including the following steps-a. A step for preparing liquid coal slurry, that is, washing coal particles and black mud for papermaking , Waste water and dispersant, according to the washed coal particles, black mud and waste water in a ratio of 6: 2: 2, added to a ball mill for wet grinding, grind the washed coal particles into a mixed slurry with a particle diameter of 50-100 μm, and send it to the pulping tank. Add stabilizer to make waste liquid coal slurry;
b. 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石的流化介 质。  b. The waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
在上述循环流化燃烧法处理造纸、制革、 印染工业废液的方法的废液煤浆燃烧步 骤中, 进一步包括利用螺杆泵将废液煤浆从循环流化床锅炉的中部或顶部的供浆口注 入。如果循环流化床锅炉仅以废液煤浆为燃料, 则取消螺旋给煤设备, 如果锅炉采 用煤和废液煤浆两种燃料, 则保留螺旋给煤机。  In the above-mentioned circulating fluidized combustion method for treating the waste liquid coal slurry combustion method of the papermaking, tanning, printing and dyeing industry waste liquid, the method further includes using a screw pump to supply the waste liquid coal slurry from the middle or top of the circulating fluidized bed boiler. Pulp injection. If the circulating fluidized bed boiler only uses waste liquid coal slurry as fuel, the spiral coal feeding equipment is eliminated. If the boiler uses coal and waste liquid coal slurry as fuel, the spiral coal feeder is retained.
在上述循环流化燃烧法处理造纸、制革、 印染工业废液的方法中, 所述废液煤浆 的注入压力为 0.3Mpa。  In the above-mentioned method for treating the waste liquid of papermaking, tanning, printing and dyeing industry by the circulating fluidized combustion method, the injection pressure of the waste liquid coal slurry is 0.3Mpa.
在上述循环流化燃烧法处理造纸、制革、 印染工业废液的方法中, 循环流化床锅 炉的燃烧温度控制在 850— 950°C。  In the above-mentioned method for treating the waste liquid of papermaking, tanning, printing and dyeing industry by the circulating fluidized combustion method, the combustion temperature of the circulating fluidized bed boiler is controlled at 850-950 ° C.
在上述循环流化燃烧法处理造纸、制革、 印染工业废液的方法的废液煤浆燃烧步 骤中, 进一步包括将被热烟气带出的未燃尽的煤和垃圾颗粒被设置在所述循环流化床 锅炉的燃烧室出口或后部的飞灰分离器分离、 捕捉, 再通过分离器下部设置的回送装 置送回燃烧室密相区进行循环燃烧。  In the above-mentioned cyclic fluidized combustion method for treating the waste liquid coal slurry combustion method of the papermaking, tanning, and printing and dyeing industry waste liquid, the method further includes placing unburned coal and garbage particles carried out by the hot flue gas in all places. The combustion fluid outlet of the circulating fluidized bed boiler or the fly ash separator at the rear is separated and captured, and then sent back to the dense phase area of the combustion chamber for circulating combustion through a return device provided at the lower part of the separator.
循环流 锅炉的除尘率可达 99.9%, 側气中的烟尘 傲浓度 <80mgm3。烟气中 S(¾ 排放浓 <100mg m3, ΝΟχ撤浓度 <150mg m3,烟气 曼黑度 <1, 翻国家标准的大气环 保要求。 The dust removal rate of circulating flow boilers can reach 99.9%, and the concentration of soot in the side gas is <80mgm 3 . The S (¾ emission concentration in the flue gas is <100mg m 3 , the NOx concentration is less than 150mg m 3 , and the manganese blackness of the flue gas is <1, which is in accordance with national standards for atmospheric environmental protection.
循环流化床锅炉可采用热水锅炉、低压蒸汽锅炉或高、 中压蒸汽锅炉, 生产的蒸汽 可供企业生产用汽, 也可以用来供暖或发电, 形成废水治理、 用汽和发电一体化, 为节 省了大量的能源费用、 废水处理费用。 Circulating fluidized bed boilers can use hot water boilers, low pressure steam boilers or high and medium pressure steam boilers. It can be used by enterprises to produce steam, and can also be used for heating or power generation, forming the integration of wastewater treatment, steam use and power generation, in order to save a lot of energy costs and wastewater treatment costs.
废液煤桨燃烧后经除尘器收集下来的粉煤灰可以被利用,废液煤浆经循环流化床 锅炉悬浮洁净燃烧后, 产生的飞灰由除尘器收集, 由密封的输送装置输送到密封的灰仓 内, 达到一定数量后, 由煤粉 运走, 完^ 免了飞^ t环境的污染, 并且飞灰具有很高 的综合利用价值。 附图说明  The fly ash collected by the dust collector after the waste liquid coal propeller is combusted can be used. After the waste liquid coal slurry is suspended and cleaned and burned in a circulating fluidized bed boiler, the fly ash generated is collected by the dust collector and transported by a sealed conveying device to the In a sealed ash bin, after reaching a certain amount, it is transported away by pulverized coal, which saves the environment from flying, and the fly ash has a high comprehensive utilization value. BRIEF DESCRIPTION OF THE DRAWINGS
图 1为采用循环流化燃烧法处理造纸、 制革、 印染工业废水, 制备废液煤浆及其 燃烧废液煤浆的工艺流程图。  FIG. 1 is a process flow diagram of using a circulating fluidized combustion method to treat papermaking, tanning, printing and dyeing industrial wastewater, and preparing waste liquid coal slurry and burning the waste liquid coal slurry.
图 2为采用循环流化燃烧法^理造纸、 制革、 印染工业废液 (蒸煮液)、 污泥、 黑泥, 制备废液煤浆及其燃烧废液煤浆的工艺流程图。 具体实施方式 下面参照附图说明本发明的优选实施例。 本发明主要由以下两部分组成: 一、 制备废液煤浆  FIG. 2 is a process flow diagram of using the circulating fluidized combustion method to treat papermaking, tanning, and printing and dyeing industrial waste liquid (cooking liquid), sludge, and black mud to prepare waste liquid coal slurry and burn the waste liquid coal slurry. Best Mode for Carrying Out the Invention Preferred embodiments of the present invention will be described below with reference to the drawings. The invention mainly consists of the following two parts: 1. Preparation of waste liquid coal slurry
根据使用的原料不同又可分为以下三个方案:  According to the different raw materials, it can be divided into the following three schemes:
( 1 ) 将废水经过滤、 吸附、 沉降后的有效能量物质制作废液煤浆, 工艺流程如 附图 1所示, 根据这一方案, 提供一种采用循环流化燃烧法处理造纸、 制革、 印染工 业废液的方法, 包括如下步骤: 煤滤泥制备步骤, 即通过利用煤质活性碳和生石灰作 为吸附、 过滤材料, 将生产过程中产生的废水经过吸附、 沉淀、 过滤处理而制成其内 包含废水中的可燃物质的煤滤泥; 废液煤浆制备步骤, 即向已制备的煤滤泥中加入煤 粉和分散剂, 进行搅拌之后再加入稳定剂, 以制成用做锅炉燃料的废液煤桨; 废液煤 桨燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行燃烧生产蒸汽或 热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石组成的流化介质。  (1) Wastewater is filtered, adsorbed, and settled to produce waste liquid coal slurry with effective energy substances. The process flow is shown in Figure 1. According to this scheme, a circulating fluidized combustion method is used to treat papermaking and tanning. A method for printing and dyeing industrial waste liquid, including the following steps: The coal filtering mud preparation step is made by using coal activated carbon and quicklime as adsorption and filtering materials, and absorbing, precipitating and filtering the wastewater generated in the production process. The coal sludge containing combustible substances in the waste water; the waste liquid coal slurry preparation step, that is, adding pulverized coal and dispersant to the prepared coal sludge, stirring, and then adding a stabilizer to make it to be used as a boiler The waste liquid coal paddle of fuel; the waste liquid coal paddle combustion step, that is, the prepared waste liquid coal slurry is sent to a circulating fluidized bed boiler for combustion to produce steam or hot water, and the furnace of the circulating fluidized bed boiler includes Fluidized medium consisting of quartz sand and limestone.
具体而言, 将过滤池 3中加入煤粉、 煤质活性碳和生石灰, 根据需要可建造多级 过滤池 3。 过滤池 3 中加入的煤粉、 煤质活性碳和生石灰, 作为过滤材料, 具有很强 的吸附性、絮凝性, 当废水流经过滤池 3 (或经过多级过滤)后, 将废水中含有的细小纤 维、 木质素等有机物大部分过滤出来, 吸附在过滤池 3 的煤粉等过滤材料中, 剩余部分 与部分细小的煤粉以胶体的形式存在于过滤水中, 流入沉降池 6 中, 通过絮凝作用产生 沉降效应, 使废水中细小的短纤维、 木质素等有机物质同煤粉一起沉降, 沉降池上部的 水流入处理水池中, 沉降池下部的煤浆体通过沉降池下部的螺杆泵 14-1输送到废水沉降 池底流贮池 5中。 Specifically, pulverized coal, coal-based activated carbon, and quicklime are added to the filter tank 3, and a multi-stage filter tank 3 can be constructed as required. The pulverized coal, coal-based activated carbon, and quicklime added to the filter tank 3 have strong adsorption and flocculation properties as filter materials. After the wastewater flows through the filter tank 3 (or multi-stage filtration), the wastewater contains Most of the fine fibers, lignin and other organic substances are filtered out and adsorbed in the filter material such as pulverized coal in the filter tank 3, and the remainder A part of the fine coal powder exists in the filtered water in the form of colloid, and flows into the sedimentation tank 6, and the sedimentation effect is generated by flocculation. The fine short fibers, lignin and other organic substances in the wastewater are settled together with the coal powder, and the upper part of the sedimentation tank The water flows into the treatment tank, and the coal slurry in the lower part of the sedimentation tank is transported to the bottom flow storage tank 5 of the wastewater sedimentation tank through the screw pump 14-1 in the lower part of the sedimentation tank.
过滤池中的煤粉等过滤材料经过一段时间使用, 过滤吸附了大量有机物、悬浮物, 到一定程度, 达到饱和状态, 不在起过吸附作用, 之后成为煤滤泥, 将过滤池 3中饱 和的煤滤泥, 通过螺杆泵 14-1输送到废水沉降池底流贮池 5中, 废水沉降池底流贮 池 5作为二级沉淀池, 废水沉降池底流贮池 5上部的水排到处理水池 4中, 废水沉降 池底流贮池 5下部的煤滤泥, 由螺杆泵 14-2输送到制浆罐 7中。  After a period of time, the filter material such as coal powder in the filter pool is used to filter and adsorb a large amount of organic matter and suspended matter, to a certain extent, it reaches a saturated state, and does not play an adsorption role, and then becomes a coal filter mud, which saturates the filter pool 3 Coal sludge is transported to the bottom sedimentation tank 5 of the wastewater sedimentation tank through the screw pump 14-1, and the bottom sedimentation tank 5 of the wastewater sedimentation tank is used as the secondary sedimentation tank. The water in the bottom sedimentation tank 5 of the wastewater sedimentation tank is discharged to the treatment tank 4. The coal sludge in the lower part of the bottom flow storage tank 5 of the wastewater sedimentation tank is transported to the pulping tank 7 by the screw pump 14-2.
过滤池 3中的过滤材料, 含有一定量的煤质活性碳和氢氧化钙, 在过滤的同时, 还对废水起到脱氮、 脱磷、 脱色、 除臭作用。  The filter material in the filter tank 3 contains a certain amount of coal-based activated carbon and calcium hydroxide, and at the same time as filtering, it also plays a role in denitrification, dephosphorization, decolorization, and deodorization of wastewater.
送入制浆罐 7中的煤滤泥, 每批加入前要进行化验, 检验其中的水份等, 然后按 比例加入一定量的煤粉或废水, 使煤和水份的比例在 7: 3左右, 加入分散剂启动制浆 罐顶部的搅拌器, 进行搅拌, 再加入稳定剂继续搅拌, 然后经剪切输送泵 14-3剪切、 熟化处理后, 然后输送到废液煤浆贮罐 15中贮存。  The coal filter sludge sent to the pulping tank 7 must be tested before each batch is added to check the water content, etc., and then a certain amount of coal powder or wastewater is added in proportion so that the coal to water ratio is 7: 3 Right and left, add the dispersant to start the stirrer on the top of the pulping tank, stir, then add the stabilizer to continue stirring, and then cut through the shearing conveying pump 14-3, mature, and then transport it to the waste liquid coal slurry storage tank 15 Medium storage.
处理水池 4中的水由泵输送到企业原有的废水处理设备中进行再一次处理后, 返 回生产系统使用。  The water in the treatment tank 4 is pumped to the original wastewater treatment equipment of the enterprise for further treatment, and then returned to the production system for use.
制作前需进行小试, 以确定各种成份的比例或数量。 贮罐 15 中的废液 煤浆根据需要, 定期搅拌。  A small test is required before production to determine the proportion or quantity of various ingredients. The waste liquid coal slurry in the storage tank 15 is periodically stirred as required.
(2 ) 用废液 (蒸煮液) 制作废液煤浆  (2) Making waste liquid coal slurry with waste liquid (cooking liquid)
工艺流程图如附图 2所示, 废液煤浆的燃烧部分的设备与附图 1相同, 并使用相 同的附图标记。  The process flow chart is shown in FIG. 2. The equipment of the combustion part of the waste liquid coal slurry is the same as that in FIG. 1, and the same reference numerals are used.
根据使用煤不同又可分成两种不同制作方式- a、 采用洗煤粒制作废液煤浆, 根据该技术方案, 提供一种采用循环流化燃烧法 处理造纸、 制革、 印染工业废液的方法, 包括如下步骤: 废液煤浆制备步骤, 即将粒 煤中加入内含有机物质的废液中, 在球磨机中球磨成颗粒直径为 50— 150 μ πι 的混合 煤浆, 然后再加入稳定剂搅拌制成废液煤浆; 废液煤浆燃烧步骤, 即将已制备的废液 煤浆输送到循环流化床锅炉, 以进行燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉 膛内有包括石英砂和石灰石组成的流化介质。  It can be divided into two different production methods according to the use of coal-a. The waste liquid coal slurry is produced by washing coal particles. According to this technical solution, a method for treating the waste liquid of papermaking, tanning, and printing and dyeing by using a circulating fluidized combustion method is provided. The method includes the following steps: a waste liquid coal slurry preparation step, that is, adding granular organic coal to the waste liquid containing organic substances, ball milling in a ball mill into a mixed coal slurry having a particle diameter of 50-150 μm, and then adding a stabilizer to stir The waste liquid coal slurry is burned. The waste liquid coal slurry is burned, that is, the prepared waste liquid coal slurry is sent to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes Fluidized medium consisting of quartz sand and limestone.
具体而言, 将洗煤粒经破碎机 19破碎称重后, 通过输送设备送至球磨机 20, 将 废液贮罐 8,中的废液通过螺杆泵 14-2, 按比例送入球磨机 20中, 将煤粒磨至粒径在 50 — ΙΟΟ μ πι的煤浆后, 由螺杆泵 14'-2输送到制浆罐 7中, 加入稳定剂进行搅拌, 再经剪 切输送泵 14-3剪切并熟化后, 输送到废液煤浆贮存罐 15中贮存。 Specifically, the washed coal particles are crushed and weighed by a crusher 19, and then sent to a ball mill 20 through a conveying device, and The waste liquid in the waste liquid storage tank 8 is sent to the ball mill 20 through the screw pump 14-2 in proportion, and the coal particles are ground to a coal slurry with a particle size of 50 to 100 μm, and then the screw pump 14'-2 It is transported to the pulping tank 7 and added with a stabilizer for stirring. After being sheared and matured by a shearing conveying pump 14-3, it is transported to a waste liquid coal slurry storage tank 15 for storage.
b、
Figure imgf000008_0001
根据该技术方案, 提供一种采用循环流化燃烧法处理造 纸、 制革、 印染工业废液的方法, 包括如下步骤: 废液煤浆制备步骤, 即将煤粉和废 液按重量比为 6: 4的比例及稳定剂送入制浆罐进行混合搅拌, 制作废液煤浆; 废液煤浆 燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行燃烧生产蒸汽或热 水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石组成的流化介质。
b,
Figure imgf000008_0001
According to this technical solution, a method for treating waste liquid of papermaking, tanning, printing and dyeing industry by using a circulating fluidized combustion method is provided, including the following steps: a waste liquid coal slurry preparation step, that is, a coal powder and a waste liquid are 6 by weight: 4 ratio and stabilizer are sent to the pulping tank for mixing and stirring to produce waste liquid coal slurry; the waste liquid coal slurry combustion step is to transport the prepared waste liquid coal slurry to a circulating fluidized bed boiler for combustion to produce steam or Hot water, in which the fluidized medium consisting of quartz sand and limestone is contained in the hearth of a circulating fluidized bed boiler.
具体而言, 如附图 2所示, 但要去掉破碎机 19球磨机 20等设备, 把煤粉仓 (图 中未示), 废液贮罐 17及添加剂罐 9直接输送到制浆罐 7中, 按比例将煤粉以及废液 贮罐 8'中的废液, 通过输送设备送至制浆罐 7中进行搅拌后, 再加 Λ ^力 « 9'输送 来的稳 IJ, «3?«ί^ ΐ4,-3剪切、 rn j , m m m \y ^^ .  Specifically, as shown in FIG. 2, the equipment such as the crusher 19 and the ball mill 20 must be removed, and the pulverized coal silo (not shown), the waste liquid storage tank 17 and the additive tank 9 should be directly transferred to the pulping tank 7. , The pulverized coal and the waste liquid in the waste liquid storage tank 8 'are proportionally sent to the pulping tank 7 through the conveying equipment for stirring, and then the stabilized IJ conveyed by the ^^ force «9' is added,« 3? « ί ^ ΐ4, -3 cut, rn j, mmm \ y ^^.
每批废液煤浆制作前, 须对煤粉、 废液进行化验, 并进行小试, 确定煤粉、 废液 以及添加剂的比例, 废液 rat罐 15'中的废液煤浆须根据需要定期进行搅拌。  Before the production of each batch of waste liquid coal slurry, the coal powder and waste liquid must be tested and a small test must be performed to determine the proportion of coal powder, waste liquid and additives. The waste liquid coal slurry in the waste liquid tank 15 'must be used as required Stir regularly.
(3 ) 用污泥、 黑泥制作废液煤浆  (3) Making waste liquid coal slurry with sludge and black mud
根据使用煤不同又可分成两种不同制作方式:  According to the different coal used, it can be divided into two different production methods:
a、工艺流程也如附图 2所示,采用洗煤粒制作黑泥(污泥)煤浆,根据该技术方案, 提供一种采用循环流化燃烧法处理造纸、制革、 印染工业废液的方法, 包括如下步骤: 废液煤浆制备步骤, 即将洗煤粒和造纸黑泥、 废水以及分散剂, 按洗煤粒、 黑泥和废 水按 6: 2: 2的比例加入球磨机中湿磨, 将洗煤粒磨成颗粒直径为 50— 100 μ πι的混合 浆, 再送入制浆罐加入稳定剂, 制成废液煤浆; 废液煤浆燃烧步骤, 即将已制备的废 液煤浆输送到循环流化床锅炉, 以进行燃烧生产蒸汽或热水, 其中循环流化床锅炉的 炉膛内有包括石英砂和石灰石组成的流化介质。  a. The process flow is also shown in FIG. 2. Black mud (sludge) coal slurry is produced by washing coal particles. According to this technical solution, a method for treating the waste liquid of papermaking, tanning, and printing and dyeing by circulating fluidized combustion is provided. The method includes the following steps: a step of preparing waste liquid coal slurry, that is, washing coal particles and black mud of papermaking, waste water, and dispersant; adding the washed coal particles, black mud, and waste water to a ball mill in a ratio of 6: 2: 2; The granule is ground into a mixed slurry with a particle diameter of 50-100 μm, and then sent to a pulping tank to add a stabilizer to prepare a waste liquid coal slurry. The waste liquid coal slurry combustion step is to transport the prepared waste liquid coal slurry to a circulating stream. A fluidized bed boiler is used for combustion to produce steam or hot water. A furnace of a circulating fluidized bed boiler includes a fluidized medium composed of quartz sand and limestone.
具体而言, 将洗煤粒经破碎机 19破碎称重后, 通过输送设备送至球磨机 20, 将黑 泥(污泥) 通过螺杆泵 14'-2、 废水及分散剂按比例加到球磨机 20中, 将煤粒磨成 50 — ΙΟΟ μ πι粒径的煤桨后, 由螺杆泵 14'-2送至制浆罐 7'中, 力口入稳定剂进行搅拌, 再经 剪 Wi^ l4,-3剪切、 熟化后, 送至贮罐 15,中贮存。  Specifically, the washed coal particles are crushed and weighed by the crusher 19, and then sent to the ball mill 20 through the conveying equipment, and the black mud (sludge) is fed to the ball mill 20 through the screw pump 14'-2, and the waste water and dispersant are proportionally added. After grinding the coal particles into coal paddles with a particle size of 50 — 100 μ πm, they are sent to the pulping tank 7 ′ by the screw pump 14 ′ -2, and the stabilizer is stirred into the mouth, and then cut through Wi ^ l4,- 3 After shearing and aging, send to storage tank 15 for storage.
b、 采用煤粉制作黑泥 (污泥) 废液煤浆, 其工艺流程也如附图 2所示, 但要去 除破碎机 19球磨机 20等设备。 把煤粉仓 (图中未示) 黑泥贮罐 8'以及添加剂罐 9'直 接输送到制浆罐 7'上, 将煤粉、 黑泥贮罐 8'中的黑泥(污泥)通过螺杆泵 14'-2、 废水 和添加剂罐 9'输送来的分散剂按需要比例加到制浆罐 7'中进行搅拌, 再加进稳定剂继 续搅拌, 再经剪 «^ 14'-3剪切、 熟化后, 输送到贮罐 15'中贮存。 b. The process of making black mud (sludge) waste liquid coal slurry using pulverized coal is also shown in Figure 2, but the equipment such as crusher 19, ball mill 20, etc. must be removed. The pulverized coal silo (not shown) black mud storage tank 8 'and additive tank 9' are directly transferred to the pulping tank 7 ', and the black mud (sludge) in the pulverized coal and black mud storage tank 8' is passed through Screw pump 14'-2, wastewater The dispersant delivered from the additive tank 9 'is added to the pulping tank 7' according to the required ratio and stirred, and then the stabilizer is added to continue stirring, and then sheared ^^ 14'-3 after shearing and curing, and then transported to the storage Store in tank 15 '.
每批黑泥(污泥)煤浆制作前,须对煤或煤粉、黑泥(污泥)进行化验,并进行小试, 确定煤或煤粉、 黑泥(污泥)、 废水、 添加剂的比例。贮罐 15'中的用黑泥制作的废液煤 浆须根据需要定期搅拌。  Before the production of each batch of black mud (sludge) coal slurry, the coal or coal powder, black mud (sludge) must be tested, and small tests should be performed to determine the coal or coal powder, black mud (sludge), wastewater, and additives. proportion. The waste liquid coal slurry made from black mud in the storage tank 15 'must be periodically stirred as required.
二、 废液煤浆燃烧  Combustion of waste liquid coal slurry
为了适用废水、 废液 (黑液)、 黑泥等制作的废液煤浆作为燃料, 本发明对循环 流化床锅炉 1进行了改造。  In order to apply waste liquid coal slurry made from waste water, waste liquid (black liquor), black mud, etc. as fuel, the present invention modifies the circulating fluidized bed boiler 1.
目前国内国外的循环流化床锅炉都是以干煤粉为燃料,在锅炉下部采用螺旋输送 机, 将煤送入炉膛。 燃烧废液煤漿的循环流化床锅炉 1在原锅炉设计基础上, 在锅炉 顶部或中部加装废液煤浆供浆口, 如果循环流化床锅炉 1 仅以废液煤浆为燃料, 则取消螺旋给煤设备, 如果锅炉采用煤和废液煤浆两种燃料, 则保留螺旋给煤机。  At present, circulating fluidized bed boilers at home and abroad all use dry pulverized coal as fuel, and a screw conveyor is used at the lower part of the boiler to send coal into the furnace. The circulating fluidized bed boiler 1 for burning waste liquid coal slurry is based on the original boiler design, and a waste liquid coal slurry supply port is installed at the top or middle of the boiler. If the circulating fluidized bed boiler 1 only uses waste liquid coal slurry as fuel, then The auger coal feeding equipment is abolished. If the boiler uses coal and waste liquid coal slurry as fuel, the auger coal feeder is retained.
燃废液煤浆的循环流化床锅炉 1釆用热风流态点火,将柴油经点火枪雾化后,在预燃 筒内燃烧, 产生的高温烟气送入等压风室加热送风道中的空气, 被加热的高温空气经由布 风板进入流态化的床料层中, 当床料加热超过 450°C时, 向循环流化床锅炉 1内加入少量 废液煤浆, 此时炉温上升较快, 当循环流化床锅炉 1内温度达到 600°C时, 可逐步加大供 桨量, 炉温很快上升, 废液煤浆已正常燃烧, 这时停止供油, 切断预燃室, 完成点火, 增 加废液煤浆的供应, »风机 11和引风机 13调到正常负艇行需要的风量。  The circulating fluidized bed boiler 1 of the waste liquid coal slurry is ignited by hot air flow. After the diesel is atomized by the ignition gun, it is burned in the pre-combustion cylinder. Air, heated high-temperature air enters the fluidized bed material layer through the air distribution plate. When the bed material is heated above 450 ° C, a small amount of waste liquid coal slurry is added to the circulating fluidized bed boiler 1. At this time, the furnace The temperature rises quickly. When the temperature in the circulating fluidized bed boiler 1 reaches 600 ° C, the amount of paddle supply can be gradually increased. The furnace temperature rises quickly, and the waste liquid coal slurry has been burned normally. At this time, the oil supply is stopped and the pre-heating is cut off. The combustion chamber completes the ignition and increases the supply of waste liquid coal slurry. »The fans 11 and induced draft fans 13 are adjusted to the air volume required for normal negative boating.
m m p \ m- m m., 大、 中型锅炉(35吨 29MW ¾±的功率)在中部, 设有二 口,将 e«ifAm 中、 / 锅 炉顶體, mm^ 用了锅炉的高度, 加快了废¾^中的水份轉发 i^wf出, 辩 火。  mmp \ m- m m., large and medium-sized boilers (35 tons 29MW ¾ ± power) in the middle, with two ports, e «ifAm middle, / boiler top, mm ^ uses the height of the boiler to speed up The moisture in the waste ¾ ^ is forwarded to i ^ wf, and the fire is debated.
废液煤浆由贮罐 15,经螺杆输浆泵 12以 0.3Mpa左右的压力直接送至循环流化床 锅炉 1, 废液煤浆经供浆口进入循环流化床锅炉 1后, 变成滴状, 滴状废液煤浆在 炉膛内, 由于炉膛内的流化热气流扰动, 变成更细小的颗粒, 在 850— 950°C温度的 炉膛中向下翻腾、 坠落, 在坠落过程, 浆滴被加热、 分解并开始燃烧, 再迸入由石英 砂和石灰石构成的流化床中, 在炽热的流化床料的继续加热过程中, 迅速完成析出 水分、 挥发份, 并着火燃烧及焦碳燃烧, 并在流化状态下颗粒状的废液煤浆团进一 步解体的细颗粒, 被热烟气带出密相区, 进入悬浮室继续燃烧, 在燃烧室出口或后 部设有飞灰分离和回送装置, 被热烟气带出的媒体物料和较大的未燃尽颗粒被分离器 分离、 捕捉, 通过分离器下部设置的回送装置, 送回燃烧室密相区, 进行循环燃烧, 燃烧效率达 98%。 The waste liquid coal slurry is directly sent from the storage tank 15 to the circulating fluidized bed boiler 1 through the screw slurry pump 12 at a pressure of about 0.3 MPa. After entering the circulating fluidized bed boiler 1 through the slurry supply port, the waste liquid coal slurry becomes Drop-shaped, drop-shaped waste liquid coal slurry is in the furnace. It is turned into finer particles due to the fluidized hot air flow in the furnace. It is tumbling and falling down in the furnace at the temperature of 850-950 ° C. During the falling process, The droplets are heated, decomposed and started to burn, and then poured into a fluidized bed composed of quartz sand and limestone. During the continued heating of the hot fluidized bed material, the precipitation of moisture and volatiles is quickly completed, and the fire and combustion Coke is burned, and the fine particles of granular waste liquid coal slurry mass further disintegrated in the fluidized state are taken out of the dense phase zone by the hot flue gas, enter the suspension chamber to continue burning, and there is a fly at the exit or rear of the combustion chamber. The ash separation and return device, the media material carried out by the hot flue gas and the large unburned particles are separated and captured by the separator, and returned to the dense phase area of the combustion chamber through the return device provided at the bottom of the separator for cyclic combustion. , The combustion efficiency is 98%.
废液煤 在炉膛内 850— 95CTC低温燃烧, 有效地抑制了燃料在燃烧过程中热力型 NOx的生成,由于炉膛内加石英砂和石灰石作为媒体物料,石灰石在高温下分解生成 CaO 与废液煤浆中的煤粉中的硫燃烧后生成的 S02反应生成 CaS04。 其反应是: The waste liquid coal is burned in the furnace at 850-95CTC at low temperature, which effectively inhibits the generation of thermal NOx during the combustion process. Because quartz sand and limestone are added as media materials in the furnace, limestone is decomposed at high temperature to generate CaO and waste liquid coal. The S0 2 formed after the sulfur in the pulverized coal in the slurry is combusted to generate CaS0 4 . The response is:
S02+CaO+l/202― CaS04 S0 2 + CaO + l / 20 2 ― CaS0 4
抑制了烟气中 so2的排放, 实现了在循环流化床锅炉 1内直接脱硫。 循环流化床锅 炉 1加入的石灰石(脱硫剂) 的粒径选择在 1— 2mm左右, 在达到 85%— 95%脱硫效率 时钙 /^摩尔比为 1.5— 2.5。 废液中所含的木质素、 半纤维素等可燃有机物质在炉膛内燃 烧后转化成热能, 碱等其它物质在燃烧过程中生成钠盐、 钠钙等物质, 混合在飞灰中排 出。 The emission of so 2 in the flue gas is suppressed, and direct desulfurization in the circulating fluidized bed boiler 1 is achieved. The particle size of the limestone (desulfurizing agent) added to the circulating fluidized bed boiler 1 is selected from about 1-2 mm, and the calcium / ^ molar ratio is 1.5-2.5 when the desulfurization efficiency of 85% -95% is reached. Flammable organic materials such as lignin and hemicellulose contained in the waste liquid are converted into heat energy after being burned in the furnace. Other materials such as alkali generate sodium salts, sodium calcium and other materials during the combustion process and are mixed in the fly ash and discharged.
循环流化床锅炉 1烟气中含有已燃尽的飞灰, 用静电除尘器或布袋除尘器 2收集, 除尘 率可达 99.9%, 气中的烟尘 浓度 <80mg½3。烟气中 S(¾ ¾½¾g<100mg/m3, ΝΟχ 纖浓度 <150mg m3, 烟气概曼黑度 <1, 翻国家标准的大气环保要求。 The circulating fluidized bed boiler 1 contains exhausted fly ash in the flue gas, which is collected by an electrostatic precipitator or a bag precipitator 2. The dust removal rate can reach 99.9%, and the smoke concentration in the gas is <80mg½ 3 . In the flue gas, S (¾ ¾½¾g <100mg / m 3 , NOx fiber concentration <150mg m 3 , smoke manganese blackness <1, which is the national standard for environmental protection requirements.
循环流化床锅炉 1可采用热水锅炉、低压蒸汽锅炉或高、 中压蒸汽锅炉, 生产的蒸 汽可供企业生产用汽, 也可以用来供暖或发电, 形成废水治理、 用汽和发电一体化, 为 企业节省大量的能源费用、 废水处理费用, 增加了收入, 造纸业每烧去 1 吨黑液(造纸 黑液中的热值为 8.37—10.04MJ/kg)相当于为企业节省 0.28~0.34吨标准煤。  The circulating fluidized bed boiler 1 can be a hot water boiler, a low pressure steam boiler or a high or medium pressure steam boiler. The produced steam can be used by enterprises to produce steam, and it can also be used for heating or power generation, forming a wastewater treatment, steam and power integration. It saves enterprises a lot of energy costs, waste water treatment costs, and increases revenue. Every 1 ton of black liquor burned in the paper industry (the calorific value in the black liquor of papermaking is 8.37-10.04MJ / kg) is equivalent to saving 0.28 ~ 0.34 tons of standard coal.
废液煤浆燃烧后经除尘器 2收集下来的粉煤灰可以被利用,废液煤浆经循环流化 床锅炉 1燃烧后, 产生的飞灰由除尘器 2收集, 由密封的输送装置输送到密封的灰仓 5 内, 达到一定数量后, 由煤粉 运走, 完^ 免了飞^环境的污染, 并且飞灰具有很髙 的综合利用价值。 主要可以有两大棚途:  The fly ash collected by the dust collector 2 after the waste liquid coal slurry is combusted can be used. After the waste liquid coal slurry is burned by the circulating fluidized bed boiler 1, the fly ash generated is collected by the dust collector 2 and transported by a sealed conveying device. In the sealed ash bin 5, after reaching a certain amount, it is transported by pulverized coal, which completely saves the environmental pollution of the flying ash, and the flying ash has very high comprehensive utilization value. There are two main sheds:
a、 飞灰具有胶凝性, 含有 CaS04, 是制造水泥所需的矿渣和石膏的替代品, 补 充矿渣资源不足,是制造水泥的原料,与水泥熟料各 50%,即可制成 325#水泥, CaS04 含量高的飞灰可制作特种水泥和膨胀剂。 a. Fly ash is gelatinous and contains CaS0 4. It is a substitute for slag and gypsum needed to make cement. It lacks sufficient slag resources. It is a raw material for making cement. It can be made into 325 with 50% each of cement clinker. # Cement, fly ash with high CaS0 4 content can make special cement and expansion agent.
b、 由于废液煤浆中含有大量的碱、 木质素、 聚糖、 钙盐等物质, 在 850~950°C 的炉膛中燃烧时, 上述物质转化成钠盐、 钙盐、 氮、 磷酸钙等高活性物质, 随飞灰一 起排出, 含有钠盐、 钙盐、 氮、 磷酸钙等高活性物质的飞灰, 不仅是制作有机肥的良 好基料, 也可以作为酸性土壤改良剂。  b. Because the waste liquid coal slurry contains a large amount of alkali, lignin, glycan, calcium salts and the like, when burning in a furnace at 850 ~ 950 ° C, the above substances are converted into sodium salts, calcium salts, nitrogen, calcium phosphate High-active materials such as high-active materials are discharged together with fly ash. Fly ash containing high-active materials such as sodium salt, calcium salt, nitrogen, and calcium phosphate is not only a good base for organic fertilizers, but also can be used as an acid soil improver.
应用实例  Applications
以年产 1.5万吨草浆造纸厂为例, 每天排出黑液 100吨, 采用循环流化燃烧法对 其生产过程中产生的黑液进行治理和综合利用。 Taking a straw pulp paper mill with an annual output of 15,000 tons as an example, 100 tons of black liquor are discharged every day. The black liquor produced in the production process is used for treatment and comprehensive utilization.
^一台 75 小 环流 ½^废¾«^¾锅炉, 大同发 i¾it 29.3MJ/kg, 灰份 6%, 粒径 50— 100 μ ιη的煤粉, 按煤粉: 黑液 =6:4比例通过计量装置后输入到制浆 罐 7。 制浆罐 7上安装有搅拌器, 为双螺带杆式结构, 其转数为 Μ=5— 50r/min, 周 边线速度为 2m/s, 由于黑液就起到了分散剂的作用,无需再加入分散剂,经过搅拌后, mn^m , mm, 然^ 切、 m /s, ^ ,其固^ i65-7o%, 水份^ A 75 small circulation ½ ^ waste ¾ «^ ¾ boiler, Datongfa i¾it 29.3MJ / kg, 6% ash, pulverized coal with a particle size of 50-100 μm, according to pulverized coal: black liquor = 6: 4 ratio After passing through the metering device, it is input to the pulping tank 7. The agitator is installed on the pulping tank 7 and has a double spiral belt structure. Its rotation speed is M = 5-50 r / min and the peripheral linear speed is 2 m / s. Because the black liquor acts as a dispersant, No need to add dispersant, after stirring, mn ^ m, mm, then ^ cut, m / s, ^, its solid ^ i65-7o%, moisture
35— 30%。 将废液煤浆用螺杆泵送入循环流化床蒸汽锅炉, 锅炉每小时燃烧废液煤浆 10.5吨, 每小时生产 75吨 (压力为 1.6Mpa— 3.82Mpa, 温度 240— 450°C ) 蒸汽供 造纸厂使用。 燃烧后的烟气经静电除尘器除尘后排出。 35—30%. The waste liquid coal slurry is pumped into a circulating fluidized bed steam boiler with a screw pump. The boiler burns 10.5 tons of waste liquid coal slurry per hour, and produces 75 tons per hour (the pressure is 1.6Mpa—3.82Mpa, temperature 240—450 ° C). For use in paper mills. The flue gas after combustion is discharged by the electrostatic precipitator.
尽管对本发明的一些优选实施例进行了图示和描述, 也己经说明和讨论了本发明特 殊的 iSffl和示范的«例, 来为以各种^ 本发明 一个基础。在本发明范围之内可 能有许多^。但本领域技术人员将会理解在不偏离本发明的原理和实质的情况下, 可 对这些实施例进行改变, 其保护范围限定在本发明的权利要求及其等同替换内。  Although some preferred embodiments of the present invention have been illustrated and described, the special iSffl and exemplary «examples of the present invention have also been illustrated and discussed to form a basis for various inventions. Many are possible within the scope of the invention. However, those skilled in the art will understand that these embodiments can be changed without departing from the principle and essence of the present invention, and the scope of protection is limited to the claims of the present invention and their equivalents.

Claims

权 利 要 求 Rights request
1、 一种采用循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 包括如下 步骤: 1. A method for treating waste liquid from papermaking, tanning, and printing and dyeing industries by using a circulating fluidized combustion method, including the following steps:
a. 煤滤泥制备步骤, 即通过利用煤质活性碳和生石灰作为吸附、 过滤材料, 将 生产过程中产生的废水经过吸附、 沉淀、 过滤处理而制成其内包含废水中的可燃物质 的煤滤泥;  a. Coal filter sludge preparation step, that is, the use of coal activated carbon and quicklime as adsorption and filter materials, the waste water produced in the production process is subjected to adsorption, precipitation, filtration treatment to produce coal containing combustible substances in wastewater Filter mud
b、 废液煤浆制备步骤, 即向已制备的煤滤泥、 污泥、 废液中加入煤粉和分散剂, 进行搅拌之后再加入稳定剂, 以制成用做锅炉燃料的废液煤浆;  b. Waste liquid coal slurry preparation step, that is, adding pulverized coal and dispersant to the prepared coal filter sludge, sludge, waste liquid, stirring, and then adding a stabilizer to make waste liquid coal used as boiler fuel Pulp
c 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石组成的流 化介质。  c Waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transported to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
2、 根据权利 1所述的循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 其中:  2. A method for treating waste water from papermaking, tanning, and printing and dyeing industries by the circulating fluidized combustion method according to claim 1, wherein:
在废液煤浆制备步骤中, 废液煤浆中的煤粉和水分的重量比为 7: 3。  In the waste liquid coal slurry preparation step, the weight ratio of coal powder and water in the waste liquid coal slurry is 7: 3.
3、 一种采用循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 包括如下 步骤:  3. A method for treating waste liquid of papermaking, tanning, printing and dyeing industry by using circulating fluidized combustion method, including the following steps:
a. 废液煤浆制备步骤, 即将粒煤中加入其内还有可燃物质的废液中, 在球磨机 中球磨成颗粒直径为 50— 150 μ m的混合煤浆, 然后再加入稳定剂搅拌制成废液煤浆;  a waste liquid coal slurry preparation step, that is, adding granular coal to waste liquid containing combustible substances, ball milling in a ball mill into a mixed coal slurry with a particle diameter of 50-150 μm, and then adding a stabilizer to stir Into waste liquid coal slurry;
b. 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石的流化介 质。  b. The waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
4、 一种采用循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 包括如下 步骤- a.废液煤浆制备步骤, 即将煤粉和废液按重量比为 6: 4的比例及稳定剂送入制浆 罐进行混合搅拌, 制作成废液煤桨;  4. A method for treating waste liquid of papermaking, tanning, printing and dyeing industry by circulating fluidized combustion method, including the following steps-a. Waste liquid coal slurry preparation step, that is, coal powder and waste liquid in a weight ratio of 6: 4 Proportion and stabilizer are sent to the pulping tank for mixing and stirring to make waste liquid coal paddles;
b. 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石的流化介 质。  b. The waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
5、 一种采用循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 包括如下 步骤: 5. A method for treating waste liquid of papermaking, tanning, printing and dyeing industry by using circulating fluidized combustion method, including the following: Steps:
a. 废液煤浆制备步骤, 即将洗煤粒和造纸黑泥、 废水以及分散剂, 按洗煤粒、 黑泥和废水按 6: 2: 2的比例加入球磨机中湿磨, 将洗煤粒磨成颗粒直径为 50— 100 μ πι的混合浆, 再送入制浆罐加入稳定剂, 制成废液煤浆;  a waste liquid coal slurry preparation step, that is, washing coal particles and papermaking black mud, waste water and dispersant, according to the washing coal particles, black mud and waste water are added to a ball mill for wet grinding at a ratio of 6: 2: 2, and the washed coal particles are ground into particles The mixed slurry with a diameter of 50-100 μm is sent to a pulping tank to add a stabilizer to make a waste liquid coal slurry;
b. 废液煤浆燃烧步骤, 即将已制备的废液煤浆输送到循环流化床锅炉, 以进行 燃烧生产蒸汽或热水, 其中循环流化床锅炉的炉膛内有包括石英砂和石灰石的流化介 质。  b. The waste liquid coal slurry combustion step, that is, the prepared waste liquid coal slurry is transferred to a circulating fluidized bed boiler for combustion to produce steam or hot water. The furnace of the circulating fluidized bed boiler includes quartz sand and limestone. Fluidizing medium.
6、 根据权利 1、 3、 4、 5中的任一项所述的循环流化燃烧法处理造纸、 制革、 印 染工业废液的方法,  6. A method for treating waste water from papermaking, tanning, and printing and dyeing industry by the circulating fluidized combustion method according to any one of claims 1, 3, 4, and 5,
在所述废液煤浆燃烧步骤中,进一步包括利用螺杆泵将废液煤浆从循环流化床锅 炉的中部或顶部的供浆口注入。 如果循环流化床锅炉仅以废液煤浆为燃料, 则取消 螺旋给煤设备, 如果锅炉采用煤和废液煤浆两种燃料, 则保留螺旋给煤机。  In the step of burning the waste liquid coal slurry, the method further includes injecting the waste liquid coal slurry from a slurry supply port in the middle or top of the circulating fluidized bed boiler by using a screw pump. If the circulating fluidized bed boiler only uses waste liquid coal slurry as fuel, then the spiral coal feeding equipment is eliminated. If the boiler uses coal and waste liquid coal slurry as fuel, the spiral coal feeder is retained.
7、 根据权利 1、 3、 4、 5中的任一项所述的循环流化燃烧法处理造纸、 制革、 印 染工业废液的方法,  7. A method for treating waste water from papermaking, tanning, and printing and dyeing industry by the circulating fluidized combustion method according to any one of claims 1, 3, 4, and 5,
其中, 所述废液煤浆的注入压力为 0.3Mpa。  The injection pressure of the waste liquid coal slurry is 0.3 MPa.
8、 根据权利 6所述的循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 其中, 循环流化床锅炉的燃烧温度控制在 850— 950°C。  8. The method for treating waste liquid from papermaking, tanning, printing and dyeing industry by the circulating fluidized combustion method according to claim 6, wherein the combustion temperature of the circulating fluidized bed boiler is controlled at 850-950 ° C.
9、 根据权利 7所述的循环流化燃烧法处理造纸、 制革、 印染工业废液的方法, 在所述废液煤浆燃烧步骤中,进一步包括将被热烟气带出的未燃尽的煤和垃圾颗 粒被设置在所述循环流化床锅炉的燃烧室出口或后部的飞灰分离器分离、 捕捉, 再通 过分离器下部设置的回送装置送回燃烧室密相区进行循环燃烧。  9. The method for treating waste liquid from papermaking, tanning, and printing and dyeing industry by the circulating fluidized combustion method according to claim 7, wherein in the step of burning the waste liquid coal slurry, the method further comprises unburned exhausted by hot flue gas. The coal and garbage particles are separated and captured by the fly ash separator at the exit of the combustion chamber of the circulating fluidized bed boiler or at the rear, and then sent back to the dense phase area of the combustion chamber for circulating combustion through the return device provided at the lower part of the separator. .
PCT/CN2005/000059 2004-01-15 2005-01-14 Circulating fluidized bed burning method for waste liquor of paper making, hide manufacture, printing and dyeing WO2005080875A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CNB2004100210612A CN100408918C (en) 2004-01-15 2004-01-15 Method for dealing with discharge liquid from paper, leather and dye printing industry using circulating fluidized combustion method
CN200410021061.2 2004-01-15

Publications (1)

Publication Number Publication Date
WO2005080875A1 true WO2005080875A1 (en) 2005-09-01

Family

ID=34351897

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2005/000059 WO2005080875A1 (en) 2004-01-15 2005-01-14 Circulating fluidized bed burning method for waste liquor of paper making, hide manufacture, printing and dyeing

Country Status (2)

Country Link
CN (1) CN100408918C (en)
WO (1) WO2005080875A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108692306A (en) * 2017-04-11 2018-10-23 广东科达洁能股份有限公司 It is a kind of to produce superheated steam system and method using Slurry Combustion
CN114315025A (en) * 2021-12-27 2022-04-12 浙江升华云峰新材股份有限公司 Treatment method and system for technical wood production wastewater

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101270309B (en) * 2008-05-03 2011-04-20 何敏 Preparation of slurries with primary slime and sodium lignosulfonic acid powder
CN101440317B (en) * 2008-09-03 2012-08-15 何秀院 Environment protection type coal water slurry and preparation thereof
CN101613633B (en) * 2009-08-07 2012-11-21 盛虹集团有限公司 Fuel containing dyeing waste water sludge and method for preparing same
CN101664616B (en) * 2009-09-04 2011-12-07 谭鼎昌 Alkali recovery boiler pulse spay-blow purifying and dedusting system with various black liquid processing abilities
CN103375806B (en) * 2012-04-26 2015-10-14 月岛机械株式会社 The treated object transport method of pressurized flow furnace system
CN105042601A (en) * 2014-12-13 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Method and apparatus for treating high-concentration organic waste water in foodstuff industry
CN106500115A (en) * 2016-12-20 2017-03-15 青岛特利尔环保股份有限公司 A kind of processing system and handling process containing sodium salt waste water
CN109401808A (en) * 2018-09-30 2019-03-01 中国水利水电科学研究院 The method of leather-making waste water harmless treatment preparation biomass energy sludge fuel
CN111810954A (en) * 2020-07-14 2020-10-23 山东大学 Waste engine oil treatment method and treatment system
CN112301781A (en) * 2020-10-14 2021-02-02 福建省青山纸业股份有限公司 Method for performing mixed combustion by adding coal water slurry into concentrated black liquor in alkali recovery furnace

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4448589A (en) * 1980-01-23 1984-05-15 Kansas State University Research Foundation Pyrolytic conversion of carbonaceous solids to fuel gas in quartz sand fluidized beds
CN1113901A (en) * 1994-05-24 1995-12-27 中国科学院福建物质结构研究所 Preparing method for calcium silicate fertilizer
JPH11237035A (en) * 1998-02-23 1999-08-31 Chugoku Electric Power Co Inc:The Device for supplying coal, limestone, and water paste fuel
CN1313247A (en) * 2000-12-19 2001-09-19 河南中原环保工程有限公司 Process for treating waste mother liquid of H acid in dye factory

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5030766A (en) * 1990-05-04 1991-07-09 Technology Corporation Catalysts for producing 1,3-diols and/or 3-hydroxyaldehydes, and processes for making and using same
US5284550A (en) * 1992-06-18 1994-02-08 Combustion Engineering, Inc. Black liquier gasification process operating at low pressures using a circulating fluidized bed
CN2426571Y (en) * 2000-06-20 2001-04-11 广西绿洲热能设备有限公司 Organic waste liquid heat-pipe evaporating concentrating burning boiler

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4448589A (en) * 1980-01-23 1984-05-15 Kansas State University Research Foundation Pyrolytic conversion of carbonaceous solids to fuel gas in quartz sand fluidized beds
CN1113901A (en) * 1994-05-24 1995-12-27 中国科学院福建物质结构研究所 Preparing method for calcium silicate fertilizer
JPH11237035A (en) * 1998-02-23 1999-08-31 Chugoku Electric Power Co Inc:The Device for supplying coal, limestone, and water paste fuel
CN1313247A (en) * 2000-12-19 2001-09-19 河南中原环保工程有限公司 Process for treating waste mother liquid of H acid in dye factory

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108692306A (en) * 2017-04-11 2018-10-23 广东科达洁能股份有限公司 It is a kind of to produce superheated steam system and method using Slurry Combustion
CN114315025A (en) * 2021-12-27 2022-04-12 浙江升华云峰新材股份有限公司 Treatment method and system for technical wood production wastewater

Also Published As

Publication number Publication date
CN1558143A (en) 2004-12-29
CN100408918C (en) 2008-08-06

Similar Documents

Publication Publication Date Title
WO2005080875A1 (en) Circulating fluidized bed burning method for waste liquor of paper making, hide manufacture, printing and dyeing
WO2005085143A1 (en) A method for sewage sludge treatment by using circulating fluidized bed combustion
CN101551108B (en) Incineration treatment method of municipal sludge and device thereof
CN103359898B (en) Method and apparatus for sludge deep treatment and resource utilization
CN103090396A (en) Two-stage drying and incineration method for sludge
CN203683345U (en) System for drying domestic sludge by using afterheat of dry process cement kiln and carrying out direct blending combustion treatment
CN101797468B (en) Method for desulfurating coal slime fluidized bed boiler by utilizing papermaking white mud and black liquor
CN107056013A (en) A kind of device and method for handling sludge
CN102423608A (en) Desulfurizer prepared by causticized white mud and method thereof for flue gas desulphurization
CN101886811A (en) Method for coprocessing sludge with high moisture content by novel dry-process rotary kiln
CN101914405B (en) Sludge briquette fuel as well as production method and production system thereof
CN107143864A (en) A kind of technique of full combustion slime circulating fluidized bed boiler burning sludge
US6666154B2 (en) Methods for controlling ignitability of organic waste with mineral by-products
WO2015010406A1 (en) Method for recycling water-contained sludge and/or waste
CN103776037A (en) High-concentration organic waste innocent treatment system and process
WO2008061430A1 (en) A mixed fuel of sludge and coal and method using it
JP4306334B2 (en) Carbide processing method and apparatus
KR20110012918A (en) Device for producing fuel of dyeing wastewater sludge in coal-fired power utility boiler plant and method thereof
JPH10267221A (en) Desulfurization method of exhaust gas of fluidized bed furnace
CN212476506U (en) System for treating coal slime sludge by utilizing fan coal mill
CN101586047B (en) Boiler biomass fuel and preparation method thereof
CN102863137B (en) Comprehensive utilization method and comprehensive utilization system for biochemical sludge
CN1152827C (en) Process for treating waste mother liquid of H acid in dye factory
CN113181758A (en) Gypsum wet flue gas desulfurization method and system
CN209978054U (en) Sludge incinerator for chain grate coal-fired boiler

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): BW GH GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LT LU MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
NENP Non-entry into the national phase

Ref country code: DE

WWW Wipo information: withdrawn in national office

Country of ref document: DE

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 69(1)EPC

122 Ep: pct application non-entry in european phase