WO2002038888A1 - Method and apparatus for constructing a reinforcement of concrete structures - Google Patents

Method and apparatus for constructing a reinforcement of concrete structures Download PDF

Info

Publication number
WO2002038888A1
WO2002038888A1 PCT/KR2001/001929 KR0101929W WO0238888A1 WO 2002038888 A1 WO2002038888 A1 WO 2002038888A1 KR 0101929 W KR0101929 W KR 0101929W WO 0238888 A1 WO0238888 A1 WO 0238888A1
Authority
WO
WIPO (PCT)
Prior art keywords
fiber reinforced
reinforced composite
epoxy
supply path
cover
Prior art date
Application number
PCT/KR2001/001929
Other languages
French (fr)
Inventor
Hwa-Sun Lee
Original Assignee
Hwangwoo Total Co., Ltd.
Lee, Sung-Han
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from KR1020000067129A external-priority patent/KR20020037125A/en
Priority claimed from KR1020010069404A external-priority patent/KR20030038004A/en
Application filed by Hwangwoo Total Co., Ltd., Lee, Sung-Han filed Critical Hwangwoo Total Co., Ltd.
Priority to AU2002215250A priority Critical patent/AU2002215250A1/en
Publication of WO2002038888A1 publication Critical patent/WO2002038888A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G2023/0251Increasing or restoring the load-bearing capacity of building construction elements by using fiber reinforced plastic elements

Definitions

  • the present invention relates to a method and an apparatus for constructing reinforcements of concrete structures, which can prevent separation between concrete structures and fiber reinforced composites by removing air contained in the fiber reinforced composites and, at the same time, impregnating epoxy sufficiently, thereby increasing bonding force.
  • concrete structures such as beams, slabs and pillars serve to bear loads such as bending, compression and buckling.
  • Such concrete structures are repaired and reinforced because they cannot maintain their design strength due to defects such as cracks, and the reinforcing work is carried out by generally using fiber reinforced composites, such as carbon fiber or glass fiber suitable for making the concrete structures lightweight as well as reducing a construction period.
  • FIG. 1 illustrates a flow chart of a conventional method for reinforcing a concrete structure
  • FIG. 2 illustrates an enlarged sectional view of a conventional reinforcement configuration of the concrete structure.
  • defects such as cracks
  • FIGS. 1 and 2 in the conventional method for reinforcing the concrete structure, first, if there are defects, such as cracks, on reinforced surfaces 1 and 3 of the concrete structure, epoxy impregnant is inserted into the cracked parts to repair the cracked parts. After that, if there are foreign matters, such as dust or paint, on the reinforced surfaces 1 and 3, the foreign matters are removed and the reinforced surfaces 1 and 3 are adjusted.
  • Epoxy 9 is coated on the parts where the primer 7 is coated using a brush or a roller for coating, wherein the epoxy 9 serves to support compression force, as if concrete does, after being impregnated into the fiber reinforced composites 5.
  • the fiber reinforced composite 5 is adhered on the part where the epoxy 9 is first coated, and it can be varied according to the length of the reinforced surfaces 1 and 3, although it is adhered generally 5m in length.
  • the fiber reinforced composite 5 serves to support tension force like reinforced rods.
  • the epoxy 9 first coated on the fiber reinforced composite 5 is pressed by a mangle, so that epoxy 9 is impregnated and air that remained in the fiber reinforced composite is removed.
  • epoxy 11 is second coated on the fiber reinforced composite 5 in the same manner as the first coating of epoxy.
  • one fiber reinforced composite 5 is used, and two or more of fiber reinforced composites 5 can be piled up and used if the concrete structure is severely damaged.
  • a second fiber reinforced composite is adhered without curing, the second epoxy impregnation and the air removal are performed, and then, epoxy is third coated and cured on the second fiber reinforced composite.
  • a reinforcing work of multi-stage structure generally triple layer, can be performed.
  • the reinforce surfaces 1 and 3 are not in a straight line, for example, edge parts where the beam and the pillar meet, the reinforcing work, as shown in FIG. 1, must be performed after a veneered part 13 of epoxy injection or mortar is formed.
  • the reason is that when the fiber reinforced composite 5 is adhered on the reinforced surface 1 of the beam and then the fiber reinforced composite 5 is adhered on the reinforced surface 3 of the pillar, it is to prevent that the fiber reinforced composite 5 adhered on the reinforced surface 1 of the beam is pushed and separated from the edge part.
  • the fiber reinforced composite 5, in which epoxy 9 and 11 are impregnated can form structures like the reinforced concrete (the reinforced rod is epoxy, and concrete is fiber reinforced composite).
  • the conventional method for reinforcing the concrete structures has the following problems.
  • the fiber reinforced composite and the reinforced surface are not adhered closely to each other, and thereby an air layer may be formed between the fiber reinforced composite and the reinforced surface due to the remaining air.
  • the air layer may cause separation phenomenon, thereby separating the fiber reinforced composite from the reinforced surface to lower the reinforcing effect.
  • the reinforced surface has a curved part like the edge part, the veneered part causes loss of material and extension of construction period, thereby deteriorating its economical efficiency and production efficiency.
  • the fiber reinforced composites have to be adhered one after another, thereby lowering the construction efficiency and economical efficiency due to the increase in the number of construction processes.
  • the length of the reinforced surface (for example, more than 5m), it takes too much time in impregnating epoxy on the fiber reinforced composite and removing the air remaining in the fiber reinforced composite by the compression force of the roller, and thereby, epoxy which is not impregnated may be cured previously. Therefore, the length of the fiber reinforced composite is restricted.
  • an object of the present invention is to provide a method and an apparatus for constructing a reinforcement of concrete structures, which can completely remove the air remaining in reinforced surfaces and fiber reinforced composites to adhere the reinforced surface and the fiber reinforced composite closely to each other.
  • Another object of the present invention is to provide a method and an apparatus for constructing a reinforcement of concrete structures, which can perform a reinforcing construction at once without regard to the form of the reinforced surfaces or the length of the reinforced surface.
  • the present invention provides a method for reinforcing concrete structures, the method including the steps of: providing reinforced surfaces of the concrete structure; coating primer on the reinforced surfaces; mounting fiber reinforced composites on the coated reinforced surfaces in one or more folds; mounting a supply path at a side of the fiber reinforced composite and mounting a discharge path at the other side of the fiber reinforced composite to supply epoxy to the fiber reinforced composite; putting a cover on the supply path, the fiber reinforced composite and the discharge path and sealing a space between the reinforced surfaces and the cover; discharging the air formed between the reinforced surfaces and the cover through the discharge path by a pumping action and forming a vacuum condition; impregnating epoxy into the fiber reinforced composite by pressure difference when the vacuum condition is made between the reinforced surfaces and the cover; and performing a finishing work after impregnating epoxy into the fiber reinforced composite.
  • the air formed in the reinforced surface and the fiber reinforced composite can be removed completely to adhere them closely to each other.
  • the present invention provides an apparatus for reinforcing concrete structures, the apparatus including: fiber reinforced composites of one or more folds mounted on reinforced surfaces of the concrete structure coated with primer; a supply path mounted at a side of the fiber reinforced composite to supply epoxy to the fiber reinforced composite; a discharge path mounted at the other side of the fiber reinforced composite; a cover covering the supply path, the fiber reinforced composite and the discharge path and sealing them; and a vacuum pump mounted at the discharge path for forming a vacuum condition between the reinforced surfaces and the cover, the vacuum pump allowing epoxy to be impregnated into the fiber reinforced composite by pressure difference.
  • the reinforcement construction can be performed at once without regard to the form of the reinforced surface and the length of the reinforced surface.
  • a guide member is installed between the supply path and the fiber reinforced composite to make epoxy be impregnated into the fiber reinforced composite more smooth.
  • FIG. 1 illustrates a flow chart of a conventional method for reinforcing a concrete structure
  • FIG. 2 illustrates an enlarged sectional view of a conventional reinforcement configuration of the concrete structure
  • FIG. 3 illustrates a flow chart of a method for reinforcing concrete structures according to a preferred embodiment of the present invention
  • FIG. 4 illustrates a sectional view showing that a reinforcing device of the concrete structure is installed on a reinforced surface, according to the embodiment of the present invention
  • FIG. 5 illustrates a plan view of FIG. 4
  • FIG. 6 illustrates an enlarged sectional view showing reinforcement construction is performed according to the embodiment of the present invention
  • FIG. 7 illustrates a flow chart of a method for reinforcing concrete structures according to another preferred embodiment of the present invention.
  • FIG. 8 illustrates a sectional view showing that a reinforcing device of the concrete structure is installed on a reinforced surface, according to the second embodiment of the present invention.
  • FIG. 9 illustrates an enlarged sectional view showing reinforcement construction is performed according to the second embodiment of the present invention.
  • FIG. 3 illustrates a flow chart of a method for reinforcing concrete structures according to a preferred embodiment of the present invention.
  • FIG. 4 illustrates a sectional view showing that a reinforcing device of the concrete structure is installed on a reinforced surface, according to the embodiment of the present invention.
  • FIG. 5 illustrates a plan view of FIG. 4, and
  • FIG. 6 illustrates an enlarged sectional view showing reinforcement construction is performed according to the embodiment of the present invention.
  • FIGS. 3 through 6 in the method for reinforcing the concrete structure according to the present invention, first, like the conventional reinforcing method, cracks of reinforced surfaces 1 and 3 are repaired and adjusted, and primer 7 is coated on the reinforced surfaces 1 and 3. The coated primer 7 penetrates the adjusted surface to reinforce the reinforced surfaces 1 and 3 and to raise adhesion force between the reinforced surfaces 1 and 3 and epoxy 11.
  • fiber reinforced composite 5 is mounted on the reinforced surfaces 1 and 3 on which primer 7 is coated.
  • the area of the fiber reinforced composite 5 is equal to or larger than that of the reinforced surfaces 1 and 3, and one or more of the reinforced surfaces 1 and 3 can be folded and constructed according to the extent of damage of the reinforced surfaces 1 and 3.
  • a supply path 20 is mounted at a side of the fiber reinforced composites 5 mounted on the reinforced surfaces 1 and 3, and a discharge path 30 is mounted at the other side of the fiber reinforced composites 5.
  • the supply path 20 and the discharge length 30 have the same length as the fiber reinforced composites 5.
  • the supply path 20 is mounted at a lower portion of the reinforced surface 3 and the discharge path 30 is mounted at an upper portion of the reinforced surface 3.
  • the reason is to prevent impregnated epoxy 40, which will be described later, from being concentrated downward by gravity.
  • An inlet 22 of the supply path 20 is connected to a container (not shown) containing epoxy through a hose 24. Therefore, epoxy 40 is led to the supply path 20 by difference of pressure, and then impregnated on upper and lower surfaces of the fiber reinforced composite 5 uniformly along a width direction of the fiber reinforced composite 5.
  • an outlet 32 of the discharge path 30 is connected to a vacuum pump 50 through a hose 34 to discharge the air between the reinforced surfaces 1 and 3 and a cover 60, which will be described later, and to discharge epoxy 40 remaining after being impregnated into the fiber reinforced composite 5.
  • the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30 are disposed diagonally to each other to make compression of the cover 60 and movement of epoxy 40 smooth.
  • the cover is put on the supply path 20, the fiber reinforced composite 5 and the discharge path 30, which are mounted on the reinforced surfaces 1 and 3, and seals them. Therefore, a space between the reinforced surfaces 1 and 3 and the cover 60 is sealed excepting the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30. It is preferable that the inside of the cover 60 is sealed using an adhesive tape 70, which can fix it on the reinforced surfaces 1 and 3 while being isolated from the outside of the cover 60.
  • the vacuum pump 50 is operated to form a vacuum(including a state near to vacuum condition) between the reinforced surfaces 1 and 3 and the cover 60, the cover 60 is contracted to the utmost by suction force and the fiber reinforced composite 5 is compressed, and thereby not only the air formed in the fiber reinforced composite 5 but also the air contained in the cover 60 are completely removed through the discharge path 30.
  • epoxy 40 is injected into the inside of the cover 60 by pressure difference with the hose 24 put into the epoxy container. Epoxy 40 is moved to the supply path 20, and then, started to be impregnated into the upper and lower surfaces of the fiber reinforced composite 5 through the supply path 20 at the same time. By a repeated pumping action of the vacuum pump 50, epoxy 40 is impregnated into the whole fiber reinforced composite 5, and remaining epoxy 40 after the impregnation is discharged to the outside through the discharge path 30.
  • each hose 24 and 34 is curved and stops the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30.
  • a removable valve may be mounted at the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30.
  • a guide member 80 between the supply path 20 and the fiber reinforced composite 5 after the adhesion of the fiber reinforced composite 5. Also the guide member 80 is removed after the construction work. Furthermore, if the fiber reinforced composite 5 and the reinforced surfaces 1 and 3 are adhered far closer than the fiber reinforced composite 5 and the cover 60, epoxy 40 may be impregnated slowly between the fiber reinforced composite 5 and the reinforced surfaces 1 and 3. To prevent the above, a net type screen 85 may be mounted before the adhesion of the fiber reinforced composite 5. As described above, the guide member 80 and the screen 85 allow epoxy 40 to be impregnated into the fiber reinforced composite 5 smooth.
  • a packing 90 may be mounted on an outer circumference of the inlet 22 of the supply path 20 and on an outer circumference of the outlet 32 of the discharge path 30.
  • the apparatus for reinforcing the concrete structure according to the present invention includes one or more folds of fiber reinforced composites 5, which are installed on reinforced surfaces 1 and 3, a supply path 20, a discharge path 30, a cover 60 for sealing the reinforced surfaces 1 and 3, and a vacuum pump 50 mounted on the discharge path 30.
  • a screen 85 is mounted between the reinforced surfaces 1 and 3 and the fiber reinforced composite 5 to impregnate epoxy 40 smooth.
  • the screen 85 it is preferable to use a polyethylene net, a woven net, and so on.
  • the supply path 20 is a spring in the form of a coil having a predetermined pitch (e.g., 1 to 5mm) and mounted at a side of the fiber reinforced composite 5 to lead epoxy 40 and supply epoxy 40 into the fiber reinforced composite 5 uniformly.
  • the spring has enough strength to prevent contract and transformation due to vacuum pressure.
  • a pipe having a plurality of holes to discharge epoxy 40 may be mounted.
  • the inlet 22 formed at an end of the supply path 20 protrudes to the outside of the cover 60.
  • a guide member 80 may be mounted between the supply path 20 and the fiber reinforced composite 5 to impregnate epoxy 40 to upper and lower portions of the fiber reinforced composite 5 smooth.
  • the guide member 80 has to have a path to move epoxy 40 in the inside of the guide member 80, for example, nonwoven fabric.
  • the discharge path 30, like the supply path 20, is a spring or a pipe having a plurality of holes to discharge air or epoxy 40, and mounted at the other side of the fiber reinforced composite 5.
  • the cover 60 covers the supply path 20, the fiber reinforced composite 5 and the discharge path 30 and seals the inside thereof. It is preferable that the inside of the cover 60 is sealed by adhering an adhesive tape 70 on a border of the cover 60.
  • an adhesive tape 70 on a border of the cover 60.
  • transparent polyethylene film which can be separated from epoxy 40 well and allow a worker to observe the impregnation of epoxy 40 from the outside.
  • mount a packing 90 on an outer circumference of the inlet 22 of the supply path 20 and an outer circumference of the outlet 32 of the discharge path 30, which are in contact with the cover 60.
  • the vacuum pump 50 is to completely remove the air formed between the reinforced surfaces 1 and 3 and the cover 60, and vacuum pressure is 3 to 6kg/cm2 per lm2.
  • hatching 6 is formed on the reinforced surfaces 1' and 3' to achieve a complete adhesion between the reinforced surfaces and the fiber reinforced composites. It is shown in FIGS. 7 to 9.
  • the second embodiment is similar to the first embodiment, but different from the first embodiment in respect that the hatching 6 is formed with a grinder or a cutter before primer is coated on the reinforced surfaces. Therefore, because primer 7 is coated on the reinforced surfaces 1' and 3j' on which the hatching 6 is formed, penetration of primer 7 is better and the reinforced surfaces 1' and 3' can be reinforced better. Additionally, the hatching 6 serves as a guide path of epoxy 9, thereby improving adhesion efficiency between the reinforced surfaces 1' and 3' and the fiber reinforced composite 5, and serves as a guide path of air, thereby removing the air efficiently. Therefore, the second embodiment according to the present invention does not need the screen 85, thereby simplifying the construction process and apparatus configuration.
  • the method and apparatus for constructing a reinforcement of concrete structures according to the present invention have the following advantages.
  • epoxy filling the supply path by the pressure difference flows into the fiber reinforced composite and is impregnated into the fiber reinforced composite uniformly, thereby improving the reinforcing effect.
  • the thickness of the fiber reinforced composite is uniform.
  • the guide member mounted between the supply path and the fiber reinforced composite make the impregnation of epoxy into the fiber reinforced composite smooth.
  • the hatching formed on the reinforced surfaces increases the penetration effect of primer, thereby reinforcing the reinforced surfaces better.
  • the hatching serving as a guide path of epoxy and air allows epoxy to be impregnated sufficiently between the reinforced surfaces and the fiber reinforced composites and leads discharge of the air, and thereby the reinforced surfaces and the fiber reinforced composites can be adhered completely.
  • the screen mounted between the reinforced surfaces and the fiber reinforced composites forms clearance, thereby making the impregnation of epoxy smooth.
  • the reinforcement can be finished through once process, and thereby the reinforcing effect and construction efficiency are improved to raise economical efficiency and production efficiency.
  • the reinforced surfaces are not in straight line (e.g., a stepped structure), because the cover adheres the fiber reinforced composite completely, additional veneered part is not needed.
  • the reinforced composite can be constructed at once without cutting the reinforced composite even though the reinforced surfaces are long, the construction efficiency and the reinforcing effect are improved.
  • epoxy does not pollute the circumference of the construction site and is not stained on the worker's body.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

Disclosed are a method and an apparatus for constructing a reinforcement of concrete structures, which can prevent separation between a concrete structure and a fiber reinforced composite by removing air contained in the fiber reinforced composite and impregnating epoxy sufficiently , thereby increasing bonding force.

Description

METHOD AND APPARATUS FOR CONSTRUCTING A
REINFORCEMENT OF CONCRETE STRUCTURES
Technical Field The present invention relates to a method and an apparatus for constructing reinforcements of concrete structures, which can prevent separation between concrete structures and fiber reinforced composites by removing air contained in the fiber reinforced composites and, at the same time, impregnating epoxy sufficiently, thereby increasing bonding force.
Background Art
In general, concrete structures such as beams, slabs and pillars serve to bear loads such as bending, compression and buckling. Such concrete structures are repaired and reinforced because they cannot maintain their design strength due to defects such as cracks, and the reinforcing work is carried out by generally using fiber reinforced composites, such as carbon fiber or glass fiber suitable for making the concrete structures lightweight as well as reducing a construction period.
FIG. 1 illustrates a flow chart of a conventional method for reinforcing a concrete structure, and FIG. 2 illustrates an enlarged sectional view of a conventional reinforcement configuration of the concrete structure. As shown in FIGS. 1 and 2, in the conventional method for reinforcing the concrete structure, first, if there are defects, such as cracks, on reinforced surfaces 1 and 3 of the concrete structure, epoxy impregnant is inserted into the cracked parts to repair the cracked parts. After that, if there are foreign matters, such as dust or paint, on the reinforced surfaces 1 and 3, the foreign matters are removed and the reinforced surfaces 1 and 3 are adjusted.
Uneven parts, which may be formed on the adjusted reinforced surfaces 1
and 3, are filled up and primer 7 is coated in order to adhere fiber reinforced
composites 5 on the reinforced surfaces 1 and 3 thoroughly.
Epoxy 9 is coated on the parts where the primer 7 is coated using a brush or a roller for coating, wherein the epoxy 9 serves to support compression force, as if concrete does, after being impregnated into the fiber reinforced composites 5.
The fiber reinforced composite 5 is adhered on the part where the epoxy 9 is first coated, and it can be varied according to the length of the reinforced surfaces 1 and 3, although it is adhered generally 5m in length. The fiber reinforced composite 5 serves to support tension force like reinforced rods.
Next, the epoxy 9 first coated on the fiber reinforced composite 5 is pressed by a mangle, so that epoxy 9 is impregnated and air that remained in the fiber reinforced composite is removed.
After the impregnation of the epoxy 9 and the removal of the air, epoxy 11 is second coated on the fiber reinforced composite 5 in the same manner as the first coating of epoxy.
After the second coating of the epoxy 11, it is cured and the reinforcing work using the fiber reinforced composite 5 is finished.
In the reinforcing work, one fiber reinforced composite 5 is used, and two or more of fiber reinforced composites 5 can be piled up and used if the concrete structure is severely damaged. At this time, after the second epoxy coating, a second fiber reinforced composite is adhered without curing, the second epoxy impregnation and the air removal are performed, and then, epoxy is third coated and cured on the second fiber reinforced composite. By repetition of the above process, a reinforcing work of multi-stage structure, generally triple layer, can be performed. Meanwhile, if the reinforce surfaces 1 and 3 are not in a straight line, for example, edge parts where the beam and the pillar meet, the reinforcing work, as shown in FIG. 1, must be performed after a veneered part 13 of epoxy injection or mortar is formed. The reason is that when the fiber reinforced composite 5 is adhered on the reinforced surface 1 of the beam and then the fiber reinforced composite 5 is adhered on the reinforced surface 3 of the pillar, it is to prevent that the fiber reinforced composite 5 adhered on the reinforced surface 1 of the beam is pushed and separated from the edge part.
Like the above, the fiber reinforced composite 5, in which epoxy 9 and 11 are impregnated, can form structures like the reinforced concrete (the reinforced rod is epoxy, and concrete is fiber reinforced composite). However, the conventional method for reinforcing the concrete structures has the following problems.
First, because the work that the fiber reinforced composite is adhered on the reinforced surface through epoxy is carried out manually using the roller, if the compression force of the roller is not uniform, the fiber reinforced composite and the reinforced surface are not adhered closely to each other, and thereby an air layer may be formed between the fiber reinforced composite and the reinforced surface due to the remaining air. The air layer may cause separation phenomenon, thereby separating the fiber reinforced composite from the reinforced surface to lower the reinforcing effect. Second, if two or more of the fiber reinforced composites are folded and constructed, it is far more difficult to remove the air because weight of epoxy and fiber reinforced composite is added, and the reinforced effect drops because the remaining air layer accelerates the separation of the fiber reinforced composite adhered on the reinforced surface. Third, when the reinforced surface has a curved part like the edge part, the veneered part causes loss of material and extension of construction period, thereby deteriorating its economical efficiency and production efficiency.
Fourth, if two or more of the fiber reinforced composites are folded and constructed, the fiber reinforced composites have to be adhered one after another, thereby lowering the construction efficiency and economical efficiency due to the increase in the number of construction processes.
Fifth, if the length of the reinforced surface (for example, more than 5m), it takes too much time in impregnating epoxy on the fiber reinforced composite and removing the air remaining in the fiber reinforced composite by the compression force of the roller, and thereby, epoxy which is not impregnated may be cured previously. Therefore, the length of the fiber reinforced composite is restricted.
Sixth, because the compression force of the roller is varied at a place where epoxy is sufficient and at a place where epoxy is not sufficient when epoxy coated on the reinforced surface is impregnated into the fiber reinforced composite, the thickness of the fiber reinforced composite is not uniform and the reinforcing effect drops due to insufficient impregnation.
Seventh, when epoxy is coated and a worker adheres the fiber reinforced composite, if noxious epoxy drops on the worker's body, it injures the worker's skin and the circumference of the construction site may be polluted, and thereby, the environment of the construction site may be poor. Disclosure of the Invention
Accordingly, an object of the present invention is to provide a method and an apparatus for constructing a reinforcement of concrete structures, which can completely remove the air remaining in reinforced surfaces and fiber reinforced composites to adhere the reinforced surface and the fiber reinforced composite closely to each other.
Another object of the present invention is to provide a method and an apparatus for constructing a reinforcement of concrete structures, which can perform a reinforcing construction at once without regard to the form of the reinforced surfaces or the length of the reinforced surface.
To achieve the above objects, the present invention provides a method for reinforcing concrete structures, the method including the steps of: providing reinforced surfaces of the concrete structure; coating primer on the reinforced surfaces; mounting fiber reinforced composites on the coated reinforced surfaces in one or more folds; mounting a supply path at a side of the fiber reinforced composite and mounting a discharge path at the other side of the fiber reinforced composite to supply epoxy to the fiber reinforced composite; putting a cover on the supply path, the fiber reinforced composite and the discharge path and sealing a space between the reinforced surfaces and the cover; discharging the air formed between the reinforced surfaces and the cover through the discharge path by a pumping action and forming a vacuum condition; impregnating epoxy into the fiber reinforced composite by pressure difference when the vacuum condition is made between the reinforced surfaces and the cover; and performing a finishing work after impregnating epoxy into the fiber reinforced composite. Through the above method, the air formed in the reinforced surface and the fiber reinforced composite can be removed completely to adhere them closely to each other.
In another aspect, the present invention provides an apparatus for reinforcing concrete structures, the apparatus including: fiber reinforced composites of one or more folds mounted on reinforced surfaces of the concrete structure coated with primer; a supply path mounted at a side of the fiber reinforced composite to supply epoxy to the fiber reinforced composite; a discharge path mounted at the other side of the fiber reinforced composite; a cover covering the supply path, the fiber reinforced composite and the discharge path and sealing them; and a vacuum pump mounted at the discharge path for forming a vacuum condition between the reinforced surfaces and the cover, the vacuum pump allowing epoxy to be impregnated into the fiber reinforced composite by pressure difference.
Through the above apparatus, the reinforcement construction can be performed at once without regard to the form of the reinforced surface and the length of the reinforced surface.
It is preferable that a guide member is installed between the supply path and the fiber reinforced composite to make epoxy be impregnated into the fiber reinforced composite more smooth.
Brief Description of the Drawings
Further objects and advantages of the invention can be more fully understood from the following detailed description taken in conjunction with the accompanying drawing in which:
FIG. 1 illustrates a flow chart of a conventional method for reinforcing a concrete structure; FIG. 2 illustrates an enlarged sectional view of a conventional reinforcement configuration of the concrete structure;
FIG. 3 illustrates a flow chart of a method for reinforcing concrete structures according to a preferred embodiment of the present invention; FIG. 4 illustrates a sectional view showing that a reinforcing device of the concrete structure is installed on a reinforced surface, according to the embodiment of the present invention;
FIG. 5 illustrates a plan view of FIG. 4;
FIG. 6 illustrates an enlarged sectional view showing reinforcement construction is performed according to the embodiment of the present invention;
FIG. 7 illustrates a flow chart of a method for reinforcing concrete structures according to another preferred embodiment of the present invention;
FIG. 8 illustrates a sectional view showing that a reinforcing device of the concrete structure is installed on a reinforced surface, according to the second embodiment of the present invention; and
FIG. 9 illustrates an enlarged sectional view showing reinforcement construction is performed according to the second embodiment of the present invention.
Preferred Embodiment of the Invention
The present invention will now be described in detail in connection with preferred embodiments with reference to the accompanying drawings. For reference, like reference characters designate corresponding parts throughout several views. <Embodiment 1>
FIG. 3 illustrates a flow chart of a method for reinforcing concrete structures according to a preferred embodiment of the present invention. FIG. 4 illustrates a sectional view showing that a reinforcing device of the concrete structure is installed on a reinforced surface, according to the embodiment of the present invention. FIG. 5 illustrates a plan view of FIG. 4, and FIG. 6 illustrates an enlarged sectional view showing reinforcement construction is performed according to the embodiment of the present invention. As shown in FIGS. 3 through 6, in the method for reinforcing the concrete structure according to the present invention, first, like the conventional reinforcing method, cracks of reinforced surfaces 1 and 3 are repaired and adjusted, and primer 7 is coated on the reinforced surfaces 1 and 3. The coated primer 7 penetrates the adjusted surface to reinforce the reinforced surfaces 1 and 3 and to raise adhesion force between the reinforced surfaces 1 and 3 and epoxy 11.
Next, fiber reinforced composite 5 is mounted on the reinforced surfaces 1 and 3 on which primer 7 is coated. The area of the fiber reinforced composite 5 is equal to or larger than that of the reinforced surfaces 1 and 3, and one or more of the reinforced surfaces 1 and 3 can be folded and constructed according to the extent of damage of the reinforced surfaces 1 and 3.
A supply path 20 is mounted at a side of the fiber reinforced composites 5 mounted on the reinforced surfaces 1 and 3, and a discharge path 30 is mounted at the other side of the fiber reinforced composites 5. Preferably, the supply path 20 and the discharge length 30 have the same length as the fiber reinforced composites 5.
Especially, in case of the reinforced surface 3 of a pillar, it is preferable that the supply path 20 is mounted at a lower portion of the reinforced surface 3 and the discharge path 30 is mounted at an upper portion of the reinforced surface 3. The reason is to prevent impregnated epoxy 40, which will be described later, from being concentrated downward by gravity.
An inlet 22 of the supply path 20 is connected to a container (not shown) containing epoxy through a hose 24. Therefore, epoxy 40 is led to the supply path 20 by difference of pressure, and then impregnated on upper and lower surfaces of the fiber reinforced composite 5 uniformly along a width direction of the fiber reinforced composite 5. Meanwhile, an outlet 32 of the discharge path 30 is connected to a vacuum pump 50 through a hose 34 to discharge the air between the reinforced surfaces 1 and 3 and a cover 60, which will be described later, and to discharge epoxy 40 remaining after being impregnated into the fiber reinforced composite 5. Preferably, the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30 are disposed diagonally to each other to make compression of the cover 60 and movement of epoxy 40 smooth. Furthermore, it is also possible to connect each epoxy container to both ends of the supply path 20 or connect each vacuum pump 50 to both ends of the discharge path 30.
The cover is put on the supply path 20, the fiber reinforced composite 5 and the discharge path 30, which are mounted on the reinforced surfaces 1 and 3, and seals them. Therefore, a space between the reinforced surfaces 1 and 3 and the cover 60 is sealed excepting the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30. It is preferable that the inside of the cover 60 is sealed using an adhesive tape 70, which can fix it on the reinforced surfaces 1 and 3 while being isolated from the outside of the cover 60.
Next, if the vacuum pump 50 is operated to form a vacuum(including a state near to vacuum condition) between the reinforced surfaces 1 and 3 and the cover 60, the cover 60 is contracted to the utmost by suction force and the fiber reinforced composite 5 is compressed, and thereby not only the air formed in the fiber reinforced composite 5 but also the air contained in the cover 60 are completely removed through the discharge path 30.
If the vacuum condition is formed between the reinforced surface 1 and 3 and the cover 60, epoxy 40 is injected into the inside of the cover 60 by pressure difference with the hose 24 put into the epoxy container. Epoxy 40 is moved to the supply path 20, and then, started to be impregnated into the upper and lower surfaces of the fiber reinforced composite 5 through the supply path 20 at the same time. By a repeated pumping action of the vacuum pump 50, epoxy 40 is impregnated into the whole fiber reinforced composite 5, and remaining epoxy 40 after the impregnation is discharged to the outside through the discharge path 30.
Finally, after the impregnation of epoxy 40 into the fiber reinforced composite 5, a finish work is performed. When epoxy 40 is completely impregnated into the fiber reinforced composite 5, each hose 24 and 34 is curved and stops the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30. Moreover, it will be appreciated that a removable valve may be mounted at the inlet 22 of the supply path 20 and the outlet 32 of the discharge path 30. After that, when epoxy 40 is impregnated into the fiber reinforced composite 5 sufficiently, epoxy 40 is cured. After the curing of the epoxy, the cover 60, the supply path 20 and the discharge path 30 are removed.
Meanwhile, to prevent a slow supply of epoxy 40 into the fiber reinforced composite 5 due to the close adhesion between the supply path 20 and the cover 60, it is preferable to install a guide member 80 between the supply path 20 and the fiber reinforced composite 5 after the adhesion of the fiber reinforced composite 5. Also the guide member 80 is removed after the construction work. Furthermore, if the fiber reinforced composite 5 and the reinforced surfaces 1 and 3 are adhered far closer than the fiber reinforced composite 5 and the cover 60, epoxy 40 may be impregnated slowly between the fiber reinforced composite 5 and the reinforced surfaces 1 and 3. To prevent the above, a net type screen 85 may be mounted before the adhesion of the fiber reinforced composite 5. As described above, the guide member 80 and the screen 85 allow epoxy 40 to be impregnated into the fiber reinforced composite 5 smooth.
Additionally, to improve sealing efficiency of the cover 60, a packing 90 may be mounted on an outer circumference of the inlet 22 of the supply path 20 and on an outer circumference of the outlet 32 of the discharge path 30.
Hereinafter, an apparatus for reinforcing the concrete structure using the fiber reinforced composite according to the preferred embodiment of the present invention.
The apparatus for reinforcing the concrete structure according to the present invention includes one or more folds of fiber reinforced composites 5, which are installed on reinforced surfaces 1 and 3, a supply path 20, a discharge path 30, a cover 60 for sealing the reinforced surfaces 1 and 3, and a vacuum pump 50 mounted on the discharge path 30.
For the fiber reinforced composite 5, carbon fiber, glass fiber, aramid fiber, etc. may be used. Moreover, it is preferable that a screen 85 is mounted between the reinforced surfaces 1 and 3 and the fiber reinforced composite 5 to impregnate epoxy 40 smooth. For the screen 85, it is preferable to use a polyethylene net, a woven net, and so on.
It is preferable that the supply path 20 is a spring in the form of a coil having a predetermined pitch (e.g., 1 to 5mm) and mounted at a side of the fiber reinforced composite 5 to lead epoxy 40 and supply epoxy 40 into the fiber reinforced composite 5 uniformly. The spring has enough strength to prevent contract and transformation due to vacuum pressure. It is appreciated that instead of the spring, a pipe having a plurality of holes to discharge epoxy 40 may be mounted. The inlet 22 formed at an end of the supply path 20 protrudes to the outside of the cover 60.
Meanwhile, a guide member 80 may be mounted between the supply path 20 and the fiber reinforced composite 5 to impregnate epoxy 40 to upper and lower portions of the fiber reinforced composite 5 smooth. The guide member 80 has to have a path to move epoxy 40 in the inside of the guide member 80, for example, nonwoven fabric.
The discharge path 30, like the supply path 20, is a spring or a pipe having a plurality of holes to discharge air or epoxy 40, and mounted at the other side of the fiber reinforced composite 5.
The cover 60 covers the supply path 20, the fiber reinforced composite 5 and the discharge path 30 and seals the inside thereof. It is preferable that the inside of the cover 60 is sealed by adhering an adhesive tape 70 on a border of the cover 60. For the cover 60, it is preferable to use transparent polyethylene film, which can be separated from epoxy 40 well and allow a worker to observe the impregnation of epoxy 40 from the outside. Furthermore, to improve the sealing efficiency of the cover 60, it is preferable to mount a packing 90 on an outer circumference of the inlet 22 of the supply path 20 and an outer circumference of the outlet 32 of the discharge path 30, which are in contact with the cover 60.
The vacuum pump 50 is to completely remove the air formed between the reinforced surfaces 1 and 3 and the cover 60, and vacuum pressure is 3 to 6kg/cm2 per lm2. <Embodiment 2>
In a second preferred embodiment according to the present invention, without using the screen 85 of the first embodiment, which is mounted between the reinforced surfaces 1 and 3 and the fiber reinforced composite 5, hatching 6 is formed on the reinforced surfaces 1' and 3' to achieve a complete adhesion between the reinforced surfaces and the fiber reinforced composites. It is shown in FIGS. 7 to 9.
The second embodiment is similar to the first embodiment, but different from the first embodiment in respect that the hatching 6 is formed with a grinder or a cutter before primer is coated on the reinforced surfaces. Therefore, because primer 7 is coated on the reinforced surfaces 1' and 3j' on which the hatching 6 is formed, penetration of primer 7 is better and the reinforced surfaces 1' and 3' can be reinforced better. Additionally, the hatching 6 serves as a guide path of epoxy 9, thereby improving adhesion efficiency between the reinforced surfaces 1' and 3' and the fiber reinforced composite 5, and serves as a guide path of air, thereby removing the air efficiently. Therefore, the second embodiment according to the present invention does not need the screen 85, thereby simplifying the construction process and apparatus configuration.
Industrial Applicability
As described above, the method and apparatus for constructing a reinforcement of concrete structures according to the present invention have the following advantages.
First, because the air formed in the inside of the cover sealing the supply path, the fiber reinforced composite and the discharge path is removed completely by the pumping action of the vacuum pump and the inside of the cover is maintained in a vacuum condition, the complete adhesion between the reinforced surfaces and the fiber reinforced composites increases the reinforcing effect.
Second, epoxy filling the supply path by the pressure difference flows into the fiber reinforced composite and is impregnated into the fiber reinforced composite uniformly, thereby improving the reinforcing effect.
Third, because epoxy is impregnated in the state that the cover compresses the fiber reinforced composite uniformly by the vacuum condition, the thickness of the fiber reinforced composite is uniform. Fourth, the guide member mounted between the supply path and the fiber reinforced composite make the impregnation of epoxy into the fiber reinforced composite smooth.
Fifth, the hatching formed on the reinforced surfaces increases the penetration effect of primer, thereby reinforcing the reinforced surfaces better. Moreover, the hatching serving as a guide path of epoxy and air allows epoxy to be impregnated sufficiently between the reinforced surfaces and the fiber reinforced composites and leads discharge of the air, and thereby the reinforced surfaces and the fiber reinforced composites can be adhered completely.
Sixth, the screen mounted between the reinforced surfaces and the fiber reinforced composites forms clearance, thereby making the impregnation of epoxy smooth.
Seventh, because the air can be removed by the vacuum pump and epoxy can be impregnated by the pressure difference even though the fiber reinforced composites are constructed in two or more folds, the reinforcement can be finished through once process, and thereby the reinforcing effect and construction efficiency are improved to raise economical efficiency and production efficiency.
Eighth, if the reinforced surfaces are not in straight line (e.g., a stepped structure), because the cover adheres the fiber reinforced composite completely, additional veneered part is not needed. Ninth, because the reinforced composite can be constructed at once without cutting the reinforced composite even though the reinforced surfaces are long, the construction efficiency and the reinforcing effect are improved.
Tenth, because being impregnated and cured in the inside of the sealed cover, epoxy does not pollute the circumference of the construction site and is not stained on the worker's body.
While the present invention has been described with reference to the particular illustrative embodiments, it is not to be restricted by the embodiments but only by the appended claims. It is to be appreciated that those skilled in the art can change or modify the embodiments without departing from the scope and spirit of the present invention.

Claims

What Is Claimed Is:
1. A method for reinforcing concrete structures, the method comprising the steps of: providing reinforced surfaces of the concrete structure; coating primer on the reinforced surfaces; mounting fiber reinforced composites on the coated reinforced surfaces in one or more folds; mounting a supply path at a side of the fiber reinforced composite and mounting a discharge path at the other side of the fiber reinforced composite to supply epoxy to the fiber reinforced composite; putting a cover on the supply path, the fiber reinforced composite and the discharge path and sealing a space between the reinforced surfaces and the cover; discharging the air formed between the reinforced surfaces and the cover through the discharge path by a pumping action and forming a vacuum condition; impregnating epoxy into the fiber reinforced composite by pressure difference when the vacuum condition is made between the reinforced surfaces and the cover; and performing a finishing work after impregnating epoxy into the fiber reinforced composite.
2. The method according to claim 1, further comprising a step of mounting a guide member between the supply path and the fiber reinforced composite after mounting the fiber reinforced composite, to impregnate epoxy, which is supplied to the supply path, into the fiber reinforced composite.
3. The method according to claim 1 or 2, further comprising a step of forming hatching on the reinforced surfaces before coating primer.
4. The method according to claim 1 or 2, further comprising a step of mounting a screen between the reinforced surfaces and the fiber reinforced composite before mounting the fiber reinforced composite, to impregnate epoxy, which is supplied to the supply path, into the fiber reinforced composite smooth.
5. An apparatus for reinforcing concrete structures, the apparatus comprising: fiber reinforced composites of one or more folds mounted on reinforced surfaces of the concrete structure coated with primer; a supply path mounted at a side of the fiber reinforced composite to supply epoxy to the fiber reinforced composite; a discharge path mounted at the other side of the fiber reinforced composite; a cover covering the supply path, the fiber reinforced composite and the discharge path and sealing them; and a vacuum pump mounted at the discharge path for forming a vacuum condition between the reinforced surfaces and the cover, the vacuum pump allowing epoxy to be impregnated into the fiber reinforced composite by pressure difference.
6. The apparatus according to claim 5, further comprising a guide member mounted between the supply path and the fiber reinforced composite to impregnate epoxy, which is supplied to the supply path, into the fiber reinforced composite smooth.
7. The apparatus according to claim 6, wherein the supply path and the discharge path are a spring having a predetermined pitch.
8. The apparatus according to claim 6, wherein the supply path and the discharge path are a pipe having a plurality of holes.
9. The apparatus according to one of claims 5 to 8, wherein the reinforced surfaces have hatching.
10. The apparatus according to one of claims 5 to 8, further comprising a screen mounted between the reinforced surface and the fiber reinforced composite to impregnate epoxy, which is supplied to the supply path, into the fiber reinforced composite smooth.
PCT/KR2001/001929 2000-11-13 2001-11-13 Method and apparatus for constructing a reinforcement of concrete structures WO2002038888A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2002215250A AU2002215250A1 (en) 2000-11-13 2001-11-13 Method and apparatus for constructing a reinforcement of concrete structures

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
KR1020000067129A KR20020037125A (en) 2000-11-13 2000-11-13 method for constructing a reinforcement of concrete structures and apparatus for constructing the reinforcement of concrete structures
KR2000/67129 2000-11-13
KR1020010069404A KR20030038004A (en) 2001-11-08 2001-11-08 method for constructing a reinforcement of concrete structures and apparatus for constructing the reinforcement of concrete structures
KR2001/69404 2001-11-08

Publications (1)

Publication Number Publication Date
WO2002038888A1 true WO2002038888A1 (en) 2002-05-16

Family

ID=26638530

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2001/001929 WO2002038888A1 (en) 2000-11-13 2001-11-13 Method and apparatus for constructing a reinforcement of concrete structures

Country Status (2)

Country Link
AU (1) AU2002215250A1 (en)
WO (1) WO2002038888A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT1425475B1 (en) * 2014-08-01 2016-11-03
JP2020041353A (en) * 2018-09-12 2020-03-19 株式会社アル・テックス Coating repair method for freezing damage of corrosion missing part of jacket material formed by freezing damage in building structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3138667A1 (en) * 1981-09-29 1983-04-21 Manfred 6081 Mörfelden Hirler Method for pressure-grouting cracks in prestressed concrete members and pressure-grouting packer for carrying out the method
JPH0381467A (en) * 1989-08-24 1991-04-05 Maeda Corp Repair method for crack and adhesive injection device used for said method
JPH03235876A (en) * 1990-02-09 1991-10-21 Takenaka Komuten Co Ltd Cavity repairing method for concrete filled steel pipe
JPH05272244A (en) * 1992-03-25 1993-10-19 Tadao Isshiki Stone and treating method thereof and execution method using the stone
JPH06129112A (en) * 1992-10-16 1994-05-10 Mitsubishi Kasei Corp Repairing method for cement panel
JPH10246001A (en) * 1997-03-07 1998-09-14 Sanko Techno Kk Forming method for fiber-reinforced plastic reinforcement for building of construction structure
JP2001020532A (en) * 1999-07-06 2001-01-23 Shoei Kenso Kk Method for modifying and reinforcing concrete

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3138667A1 (en) * 1981-09-29 1983-04-21 Manfred 6081 Mörfelden Hirler Method for pressure-grouting cracks in prestressed concrete members and pressure-grouting packer for carrying out the method
JPH0381467A (en) * 1989-08-24 1991-04-05 Maeda Corp Repair method for crack and adhesive injection device used for said method
JPH03235876A (en) * 1990-02-09 1991-10-21 Takenaka Komuten Co Ltd Cavity repairing method for concrete filled steel pipe
JPH05272244A (en) * 1992-03-25 1993-10-19 Tadao Isshiki Stone and treating method thereof and execution method using the stone
JPH06129112A (en) * 1992-10-16 1994-05-10 Mitsubishi Kasei Corp Repairing method for cement panel
JPH10246001A (en) * 1997-03-07 1998-09-14 Sanko Techno Kk Forming method for fiber-reinforced plastic reinforcement for building of construction structure
JP2001020532A (en) * 1999-07-06 2001-01-23 Shoei Kenso Kk Method for modifying and reinforcing concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT1425475B1 (en) * 2014-08-01 2016-11-03
JP2020041353A (en) * 2018-09-12 2020-03-19 株式会社アル・テックス Coating repair method for freezing damage of corrosion missing part of jacket material formed by freezing damage in building structure

Also Published As

Publication number Publication date
AU2002215250A1 (en) 2002-05-21

Similar Documents

Publication Publication Date Title
US6692595B2 (en) Carbon fiber reinforcement system
EP3621788B1 (en) Pultruded strips
JP7075343B2 (en) Adhesion structure and bonding method of FRP material to the structure
KR101988470B1 (en) Method and apparatus for reworking structures
US6843242B2 (en) Method for consolidating natural stone blocks
JP2695023B2 (en) Method of manufacturing reinforced panels from building material blocks such as stone
RU2507071C1 (en) Method of producing triply polymer composite (tpc)
US5738741A (en) Pre-fabricated vacuum bag and vacuum bag process to externally reinforce structural members with advanced composites
WO2002038888A1 (en) Method and apparatus for constructing a reinforcement of concrete structures
EP1718454B1 (en) Vacuum resin process using draining layer for marble blocks
JP3799119B2 (en) Structure reinforcement method
KR100405033B1 (en) Rehabilitation of Concrete Structures with Composites by Vacuum Bag Method
WO2008029794A1 (en) Method of reinforcing existing structure with carbon fiber
JP2005271247A (en) Frp reinforcing and repairing method
EP0962430B1 (en) Method for consolidation of natural stone blocks or recomposed blocks
CN110125606A (en) A kind of metal structure holes damaged composite material bonding repair method
KR100986727B1 (en) Apparatus and the method for impregnating glass fibre reinforcements with resins by using a vacuum chamber
JPH0334947B2 (en)
CN114030205A (en) Packing box and manufacturing method thereof
EP3450150B1 (en) In-situ rebuild method for in-situ rebuilding and repairing pipes and containment structures
KR20030038004A (en) method for constructing a reinforcement of concrete structures and apparatus for constructing the reinforcement of concrete structures
KR20020037125A (en) method for constructing a reinforcement of concrete structures and apparatus for constructing the reinforcement of concrete structures
KR200232866Y1 (en) Fiber Reinforced Composite Skin for Euroform Regeneration and Euroform Plywood
KR101672303B1 (en) Structures with reinforcements
JP4638850B2 (en) Method for reinforcing existing structures with carbon fiber

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ PH PL PT RO RU SD SE SG SI SK SL TJ TM TR TT TZ UA UG US UZ VN YU ZA ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 69(1) EPC ( EPO FORM 1205 DATED 01.09.03)

122 Ep: pct application non-entry in european phase
NENP Non-entry into the national phase

Ref country code: JP

WWW Wipo information: withdrawn in national office

Country of ref document: JP