WO1999016685A1 - Method and apparatus for delivering asphalt-aggregate - Google Patents

Method and apparatus for delivering asphalt-aggregate Download PDF

Info

Publication number
WO1999016685A1
WO1999016685A1 PCT/GB1998/002926 GB9802926W WO9916685A1 WO 1999016685 A1 WO1999016685 A1 WO 1999016685A1 GB 9802926 W GB9802926 W GB 9802926W WO 9916685 A1 WO9916685 A1 WO 9916685A1
Authority
WO
WIPO (PCT)
Prior art keywords
container
aggregate
transport vehicle
outlet
vehicle
Prior art date
Application number
PCT/GB1998/002926
Other languages
French (fr)
Inventor
Anthony Kujawa
Original Assignee
Arc Limited
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Arc Limited filed Critical Arc Limited
Priority to AU92724/98A priority Critical patent/AU9272498A/en
Publication of WO1999016685A1 publication Critical patent/WO1999016685A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/02Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for preparing the materials
    • E01C19/08Apparatus for transporting and heating or melting asphalt, bitumen, tar, or the like
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D88/00Large containers
    • B65D88/26Hoppers, i.e. containers having funnel-shaped discharge sections
    • B65D88/30Hoppers, i.e. containers having funnel-shaped discharge sections specially adapted to facilitate transportation from one utilisation site to another

Definitions

  • This invention relates to a method and apparatus for delivering aggregate such as bituminous coated roadstone for the construction and repair of roads and pavements.
  • Bituminous coated roadstone is traditionally produced at either quarry sites or depots, which are often some distance from the market.
  • the coated roadstone material is then delivered to the customer by heavy goods vehicle (HGV) .
  • HBV heavy goods vehicle
  • These vehicles have insulated bodies and normally deliver a standard load to the customer of 16, 20, or 24 tonnes.
  • the product has to be delivered to the customer within a given time due to heat loss during transit and the minimum temperature required for laying the material. If the lorry is delayed on site the customer may be charged an additional cost of the waiting time for the vehicle. If excess material has been ordered this will often be wasted.
  • Different solutions have been developed to try to overcome these problems through the use of satellite storage facilities for coated materials at strategic sites .
  • the box comprises a simple heated and insulated structure with doors that open at the front and lids that raise up, permitting coated materials to be delivered by lorry and reloaded by shovel.
  • the main disadvantage with this design is the heat loss when the doors are opening and the need to use materials on a "last in first out” basis, which often results in wastage.
  • a loading shovel is required for re-loading vehicles.
  • a method of delivering aggregate comprising filling a container of a transport vehicle with aggregate at an aggregate manufacturing or bulk distribution plant, driving the container to a distribution site, demounting the container, loading a customer's vehicle with aggregate from the container, mounting the container on to the transport vehicle and returning it to the aggregate manufacturing or bulk distribution plant for reprocessing and/or refilling.
  • a transport vehicle container for transporting aggregate, the container comprising a rigid body having a base and a side wall, a screw conveyor being provided above the base of the container for selectively conveying the aggregate out of an outlet in the base or side wall of the container.
  • the screw conveyor or container is adapted to supply a metered amount of aggregate from the outlet.
  • the container is demounted on to a support which supports at least a portion of the container above the level of the customer's vehicle, such that the aggregate may be ejected from the container directly into the customer's vehicle.
  • a demountable transport vehicle container for transporting aggregate the container being provided with an outlet for unloading aggregate from the container, the container further comprising a retractable support which, when the container is demounted, is extended to support the outlet above the ground.
  • the retractable support props up the container such that the outlet from the screw conveyor is supported at a predetermined height above the ground when the container is demounted from the vehicle.
  • the aggregate may comprise construction material or agricultural aggregate such as lime, preferably it comprises paving material and more preferably comprises bituminous coated roadstone for the construction and repair of roads and pavements.
  • the container is filled whilst it is mounted on the transport vehicle.
  • the container body is filled whilst it is demounted and is then mounted on the transport vehicle for transport to the distribution site.
  • a plurality of containers are provided, so that whilst one container is being filled or is in transit, another is supplying aggregate at the distribution site.
  • the container is returned to the aggregate manufacturing or bulk distribution site when it is empty, when the temperature of the remaining aggregate has dropped below a preset value or when a preset time interval has elapsed since the container body was last filled.
  • a distribution site may comprise a retail sale outlet at which private individuals or small operators obtain small to medium size quantities of aggregate or may alternatively comprise a building site or work site at which the aggregate is to be used.
  • the container is insulated.
  • This insulation may be in the form of double skinned panels which comprise the base and/or side walls.
  • the insulation may comprise Rockwool (registered trade mark) and may be situated between the inner and outer skins of the container.
  • the container may also be heated, for example by means of gas burners.
  • solar panels may be fixed to the lid or side walls of the container.
  • the container comprises a container body and a subframe which is fixed to the container body and is adapted for use with a standard hook lift assembly. It had been found by the inventor that considerable heat loss occurred due to heat conduction from the container body to the subframe, so means are provided to thermally isolate the container body from the subframe.
  • the isolation means preferably comprises heat insulating spacers interposed between the container body and the subframe .
  • the spacers may for example comprise Ferodo (registered trade mark) packers formed from asbestos free brake lining material.
  • Figure 1 is a schematic diagram illustrating a method of delivering aggregate comprising a paving material
  • Figure 2 shows a lorry and container adapted for delivering the paving material
  • Figure 3 is a cross-section through the lorry and container of Figure 2.
  • Figure 4 shows the container demounted from the lorry.
  • Figure 1 shows a schematic diagram illustrating a method of delivering heated paving material such as bituminous coated roadstone (i.e. asphalt or tarmacadam) .
  • the main method steps are repeated in a continuous loop and are as follows:
  • FIG. 2 shows a lorry with a demountable container for the delivery of paving material.
  • the lorry 2 is of conventional form and comprises a chassis 4 to which is fitted a hydraulically powered hook lift assembly 6.
  • the container 8 comprises a base 10, two side walls 12, 14 and two end walls 16, 18.
  • the top of the container 8 is closed by a lid 20 such that the entire container 8 can be sealed in an air-tight fashion to retain heat and prevent the loss of the volatile component of the paving material.
  • Means (not shown) are provided to prevent unauthorised opening of the container 8.
  • a screw conveyor 22 comprising an Archimedes screw which is driven by a power supply 24 comprising an electric motor or internal combustion engine with suitable gearing.
  • the screw conveyor 22 may be driven by an external power take off (not shown) .
  • Wheels or rollers 21, 23 are provided in the base 10 of the container 8 to support the container 8 on the lorry 2 and to enable the container 8 to be moved around when it is demounted from the lorry 2.
  • Support legs 25 are pivotally mounted to the base 10 towards the front end 16 of the container.
  • the lower portions of the side walls 12, 14 and end walls 16, 18 taper inwardly towards the base 10, such that the container 8 as a whole has the shape of an elongated funnel.
  • the screw conveyor 22 lies in the neck of this funnel, so that any paving material put into the container 8 will be fed under gravity to the screw conveyor 22.
  • the base 10, side walls 12, 14, end walls 16, 18 and lid 20 of the container are of doubled skinned construction which is best shown in Figure 3.
  • the inner skin is formed from 3 mm steel sheets welded together and the outer skin is formed from 20 guage aluminium sheets fixed with rivets and sealed with silicone sealant and weatherproof outer cladding.
  • Insulating material such as a 150 mm layer of Rockwool (registered trade mark) is sandwiched between the inner and outer skins to enhance the insulation properties of the container 8. Furthermore, heating devices such as thermostatically controlled trace heating element may be provided between the inner and outer skins for heating the container and maintaining a desired temperature of the paving material. Referring to Figure 4, the front end of the base
  • the 10 of the container 8 is provided with an outlet 26 for paving material conveyed by the screw conveyor 22.
  • the outlet 26 is closed by a sliding gate arrangement such as a slide valve discharge door 28.
  • An electric geared motor (not shown) is used to open and close the door 28 and operates in conjunction with a belt weighter (not shown) to allow metered discharge of paving material from the container 8.
  • Temperature probe tubes 27 are provided through the end wall 16 and the side wall 14 for the measurement of the temperature of the paving material.
  • the container 8 is fixed to a subframe 30 which is adapted for use with the hook lift assembly 6.
  • the subframe 30 comprises stiffening rings 19 which are bolted to the container 8, and frame rails 21 which are fixed to the stiffening rings 19.
  • Heat insulating spacers (not shown) made from asbestos free brake lining material are interposed between the container 8 and the subframe 30.
  • the spacers may for example comprise Ferodo (registered trade mark) packers.
  • the lid 20 of the container is provided with at least one pair of insulated sliding loading doors 29 which are operated pneumatically.
  • the container 8 is demounted from the lorry 2 by means of the hook lift assembly 6.
  • the hook lift assembly 6 is of conventional design and hence is not described in detail. However, in essence the system operates as follows. A pair of hooks 31 engage on a bar 32 fixed to the container 8 and operation of hydraulic rams (not shown) lifts the front end 16 of the container 8 up and pushes the container 8 backwards off the chassis 4 of the lorry 2. Finally, the front end 16 of the container 8 is lowered until the wheels 21, 23 on the base 10 of the container 8 touch the ground or, with the support legs 25 extended, until the support legs 25 touch the ground.
  • the hooks 31 are then released from the container 8 and the hook lift assembly 6 is retracted back on to the chassis.
  • the lorry 2 can then be driven away to pick up another container 8.
  • the container 8 is lowered onto all four wheels 21, 23 so that it can be moved around to an appropriate position for storage or filling, by means of a loading shovel, bulldozer, fork lift or other suitable plant.
  • a system of rails or rollers may be provided along which the containers can be run.
  • the containers 8 may also be provided with tow hitches or hitching points.
  • the support legs 29 are extended from the base 10 of the container 8 to support the front end 16 of the container 8 above the ground.
  • a contractor's or customer's vehicle such as a dumper truck or pick-up truck can be reversed beneath the front end 16 of the container 8, such that its load bed is beneath the outlet 26.
  • the door 28 is then opened and the screw conveyor 22 operated to convey paving material onto the belt weigher which is positioned beneath the door 28.
  • the paving material is conveyed by the belt weigher into the truck.
  • the door 28 is closed automatically. If a belt weigher is not available, the amount of paving material loaded into the truck can be determined by weighing the truck before and after the paving material is loaded into it .
  • the lorry 2 returns and its hook lift assembly 6 is operated to mount the container 8 on the chassis 4. The lorry 2 is then returned to the paving material manufacturing or bulk distribution plant for reprocessing of the unused paving material and for refilling.
  • Filling of the container 8 is achieved by opening part or all of the lid 20 and pouring paving material directly into the container 8 from a hopper (not shown) or by use of a loading shovel or any other known means .
  • the method is applicable to any number of containers 8 and lorries 2.
  • ten containers 8 may be provided for use with three lorries 2.
  • one or more other containers will be supplying paving material at one or more distribution or work sites and one or more other containers will be in transit between the distribution and/or work sites and the manufacturing or bulk distribution plant.
  • the front end 16 of the container 8 is supported above the ground by means of support legs 25.
  • a permanent or temporary structure may be provided at the distribution site or work site on which the container 8 may be placed such that at least the outlet 26 from the screw conveyor 22 is supported above the ground.
  • the paving delivery method can be used to deliver a full container to a distribution site from which the paving material in the container can be sold in small quantities to individual customers, it is also envisaged that a full or even partially full container 8 may be supplied to a building site or road works for use as and when required.
  • a fresh container 8 of paving material is supplied to the site by a lorry 2 and the old partially used container 8 is returned to the manufacturing and/or bulk distribution plant for reprocessing and refilling.
  • the container 8 is weighed before it is supplied to the building site and after it has been returned to the manufacturing plant. In this way, the workers on the construction site are provided with a constant source of paving material which is within specification and are only charged for the paving material which they actually use. Furthermore there is little or no wastage and associated pollution, since the unused paving material is simply returned to the manufacturing plant, where it is reprocessed.

Abstract

A method for delivering aggregate such as coated bituminous road stone, the method comprising filling a container (8) of a transport vehicle (2) with aggregate at an aggregate manufacturing or bulk distribution site, driving the container (8) to a distribution site, demounting the container (8), loading a customer's vehicle (not shown) with aggregate from the container (8), mounting the container (8) onto the transport vehicle (2) and returning it to the aggregate manufacturing or bulk distribution plant for reprocessing and/or refilling. The container (8) may be insulated or heated and may have a screw conveyor (22) for selectively conveying aggregate out of an outlet in the base (10) or sidewall (12, 14) of the container (8). Preferably, the container (8) is demounted onto a support (29) which supports at least a portion of the container (8) above the level of a customer's vehicle, so that the aggregate may be ejected from the container (8) directly into the customer's vehicle.

Description

METHOD AND APPARATUS FOR DELIVERING ASPHALT-AGGREGATE
This invention relates to a method and apparatus for delivering aggregate such as bituminous coated roadstone for the construction and repair of roads and pavements.
Bituminous coated roadstone is traditionally produced at either quarry sites or depots, which are often some distance from the market. The coated roadstone material is then delivered to the customer by heavy goods vehicle (HGV) . These vehicles have insulated bodies and normally deliver a standard load to the customer of 16, 20, or 24 tonnes. The product has to be delivered to the customer within a given time due to heat loss during transit and the minimum temperature required for laying the material. If the lorry is delayed on site the customer may be charged an additional cost of the waiting time for the vehicle. If excess material has been ordered this will often be wasted. Different solutions have been developed to try to overcome these problems through the use of satellite storage facilities for coated materials at strategic sites .
Some companies employ "hot boxes" that store coated roadstone materials. The box comprises a simple heated and insulated structure with doors that open at the front and lids that raise up, permitting coated materials to be delivered by lorry and reloaded by shovel. The main disadvantage with this design is the heat loss when the doors are opening and the need to use materials on a "last in first out" basis, which often results in wastage. A loading shovel is required for re-loading vehicles.
Another design is raised hot storage bins. This is a larger structure which requires a hopper for the delivery lorry to discharge into and an elevator to raise the materials into the bins. Lorries collect the stored materials from under the heated and insulated bins. The major problems with this system are the high capital costs and the overall height of the structure. According to a first aspect of the present invention there is provided a method of delivering aggregate, the method comprising filling a container of a transport vehicle with aggregate at an aggregate manufacturing or bulk distribution plant, driving the container to a distribution site, demounting the container, loading a customer's vehicle with aggregate from the container, mounting the container on to the transport vehicle and returning it to the aggregate manufacturing or bulk distribution plant for reprocessing and/or refilling.
According to a second aspect of the present invention, there is provided a transport vehicle container for transporting aggregate, the container comprising a rigid body having a base and a side wall, a screw conveyor being provided above the base of the container for selectively conveying the aggregate out of an outlet in the base or side wall of the container.
Preferably the screw conveyor or container is adapted to supply a metered amount of aggregate from the outlet.
Preferably the container is demounted on to a support which supports at least a portion of the container above the level of the customer's vehicle, such that the aggregate may be ejected from the container directly into the customer's vehicle. According to a third aspect of the present invention there is provided a demountable transport vehicle container for transporting aggregate, the container being provided with an outlet for unloading aggregate from the container, the container further comprising a retractable support which, when the container is demounted, is extended to support the outlet above the ground.
Preferably the retractable support props up the container such that the outlet from the screw conveyor is supported at a predetermined height above the ground when the container is demounted from the vehicle.
Although the aggregate may comprise construction material or agricultural aggregate such as lime, preferably it comprises paving material and more preferably comprises bituminous coated roadstone for the construction and repair of roads and pavements.
Preferably, the container is filled whilst it is mounted on the transport vehicle. Alternatively, the container body is filled whilst it is demounted and is then mounted on the transport vehicle for transport to the distribution site.
Preferably a plurality of containers are provided, so that whilst one container is being filled or is in transit, another is supplying aggregate at the distribution site.
Preferably the container is returned to the aggregate manufacturing or bulk distribution site when it is empty, when the temperature of the remaining aggregate has dropped below a preset value or when a preset time interval has elapsed since the container body was last filled.
A distribution site may comprise a retail sale outlet at which private individuals or small operators obtain small to medium size quantities of aggregate or may alternatively comprise a building site or work site at which the aggregate is to be used.
Preferably the container is insulated. This insulation may be in the form of double skinned panels which comprise the base and/or side walls. The insulation may comprise Rockwool (registered trade mark) and may be situated between the inner and outer skins of the container. The container may also be heated, for example by means of gas burners. Alternatively solar panels may be fixed to the lid or side walls of the container. Preferably, the container comprises a container body and a subframe which is fixed to the container body and is adapted for use with a standard hook lift assembly. It had been found by the inventor that considerable heat loss occurred due to heat conduction from the container body to the subframe, so means are provided to thermally isolate the container body from the subframe. The isolation means preferably comprises heat insulating spacers interposed between the container body and the subframe . The spacers may for example comprise Ferodo (registered trade mark) packers formed from asbestos free brake lining material. According to a fourth aspect of the present invention, there is provided a transport vehicle container for transporting aggregate, the container comprising a container body and a subframe to which the container body is fixed, means being provided to thermally isolate the subframe from the container body.
For a better understanding of the present invention and to show how it may be carried into effect, reference will now be made, by way of example, to the accompanying drawings in which:
Figure 1 is a schematic diagram illustrating a method of delivering aggregate comprising a paving material; Figure 2 shows a lorry and container adapted for delivering the paving material;
Figure 3 is a cross-section through the lorry and container of Figure 2; and
Figure 4 shows the container demounted from the lorry.
Referring to the drawings, Figure 1 shows a schematic diagram illustrating a method of delivering heated paving material such as bituminous coated roadstone (i.e. asphalt or tarmacadam) . The main method steps are repeated in a continuous loop and are as follows:
A) loading a container at a paving material manufacturing plant;
B) driving the loaded container by lorry to a distribution or work site; C) demounting the container from the lorry at the distribution or work site;
D) loading customers' vehicles with paving material from the container at the distribution or work site; E) when the container is empty, a predetermined time interval has expired since the container was filled or the temperature of the remaining paving material has dropped below a threshold value, mounting the container on a lorry and driving it back to the paving material manufacturing plant;
F) recycling of unused material; and
G) refilling of the container as in step A above .
Figure 2 shows a lorry with a demountable container for the delivery of paving material. The lorry 2 is of conventional form and comprises a chassis 4 to which is fitted a hydraulically powered hook lift assembly 6.
The container 8 comprises a base 10, two side walls 12, 14 and two end walls 16, 18. The top of the container 8 is closed by a lid 20 such that the entire container 8 can be sealed in an air-tight fashion to retain heat and prevent the loss of the volatile component of the paving material. Means (not shown) are provided to prevent unauthorised opening of the container 8. Above the base 10 of the container 8 is situated a screw conveyor 22 comprising an Archimedes screw which is driven by a power supply 24 comprising an electric motor or internal combustion engine with suitable gearing. Alternatively, the screw conveyor 22 may be driven by an external power take off (not shown) .
Wheels or rollers 21, 23 are provided in the base 10 of the container 8 to support the container 8 on the lorry 2 and to enable the container 8 to be moved around when it is demounted from the lorry 2.
Support legs 25 are pivotally mounted to the base 10 towards the front end 16 of the container.
Referring to Figures 2 and 3, the lower portions of the side walls 12, 14 and end walls 16, 18 taper inwardly towards the base 10, such that the container 8 as a whole has the shape of an elongated funnel. The screw conveyor 22 lies in the neck of this funnel, so that any paving material put into the container 8 will be fed under gravity to the screw conveyor 22. The base 10, side walls 12, 14, end walls 16, 18 and lid 20 of the container are of doubled skinned construction which is best shown in Figure 3. The inner skin is formed from 3 mm steel sheets welded together and the outer skin is formed from 20 guage aluminium sheets fixed with rivets and sealed with silicone sealant and weatherproof outer cladding.
Insulating material such as a 150 mm layer of Rockwool (registered trade mark) is sandwiched between the inner and outer skins to enhance the insulation properties of the container 8. Furthermore, heating devices such as thermostatically controlled trace heating element may be provided between the inner and outer skins for heating the container and maintaining a desired temperature of the paving material. Referring to Figure 4, the front end of the base
10 of the container 8 is provided with an outlet 26 for paving material conveyed by the screw conveyor 22. The outlet 26 is closed by a sliding gate arrangement such as a slide valve discharge door 28. An electric geared motor (not shown) is used to open and close the door 28 and operates in conjunction with a belt weighter (not shown) to allow metered discharge of paving material from the container 8.
Temperature probe tubes 27 are provided through the end wall 16 and the side wall 14 for the measurement of the temperature of the paving material. The container 8 is fixed to a subframe 30 which is adapted for use with the hook lift assembly 6. The subframe 30 comprises stiffening rings 19 which are bolted to the container 8, and frame rails 21 which are fixed to the stiffening rings 19.
Heat insulating spacers (not shown) made from asbestos free brake lining material are interposed between the container 8 and the subframe 30. The spacers may for example comprise Ferodo (registered trade mark) packers.
Referring to Figure 5, the lid 20 of the container is provided with at least one pair of insulated sliding loading doors 29 which are operated pneumatically. Referring to Figure 6, the container 8 is demounted from the lorry 2 by means of the hook lift assembly 6. The hook lift assembly 6 is of conventional design and hence is not described in detail. However, in essence the system operates as follows. A pair of hooks 31 engage on a bar 32 fixed to the container 8 and operation of hydraulic rams (not shown) lifts the front end 16 of the container 8 up and pushes the container 8 backwards off the chassis 4 of the lorry 2. Finally, the front end 16 of the container 8 is lowered until the wheels 21, 23 on the base 10 of the container 8 touch the ground or, with the support legs 25 extended, until the support legs 25 touch the ground. The hooks 31 are then released from the container 8 and the hook lift assembly 6 is retracted back on to the chassis. The lorry 2 can then be driven away to pick up another container 8. At the manufacturing plant, the container 8 is lowered onto all four wheels 21, 23 so that it can be moved around to an appropriate position for storage or filling, by means of a loading shovel, bulldozer, fork lift or other suitable plant. To facilitate movement of containers 8 around the manufacturing plant a system of rails or rollers may be provided along which the containers can be run. The containers 8 may also be provided with tow hitches or hitching points.
When a full container 8 is unloaded at the distribution or work site, as it is lowered from the back of the lorry 2, the support legs 29 are extended from the base 10 of the container 8 to support the front end 16 of the container 8 above the ground.
In this orientation, when the lorry 2 has been driven away, a contractor's or customer's vehicle such as a dumper truck or pick-up truck can be reversed beneath the front end 16 of the container 8, such that its load bed is beneath the outlet 26. The door 28 is then opened and the screw conveyor 22 operated to convey paving material onto the belt weigher which is positioned beneath the door 28. The paving material is conveyed by the belt weigher into the truck. When the required amount of paving material has been weighed out, the door 28 is closed automatically. If a belt weigher is not available, the amount of paving material loaded into the truck can be determined by weighing the truck before and after the paving material is loaded into it . Once all of the paving material in the container 8 has been used up, or a predetermined time has elapsed since the container 8 was last filled, or when the measured temperature of the paving material has fallen below a predetermined level such that the paving material is no longer within an acceptable specification, the lorry 2 returns and its hook lift assembly 6 is operated to mount the container 8 on the chassis 4. The lorry 2 is then returned to the paving material manufacturing or bulk distribution plant for reprocessing of the unused paving material and for refilling.
Filling of the container 8 is achieved by opening part or all of the lid 20 and pouring paving material directly into the container 8 from a hopper (not shown) or by use of a loading shovel or any other known means .
The method is applicable to any number of containers 8 and lorries 2. For example, ten containers 8 may be provided for use with three lorries 2. Thus as one container 8 is being filled, one or more other containers will be supplying paving material at one or more distribution or work sites and one or more other containers will be in transit between the distribution and/or work sites and the manufacturing or bulk distribution plant.
In the illustrated embodiment, the front end 16 of the container 8 is supported above the ground by means of support legs 25. As an alternative or in addition to this arrangement, a permanent or temporary structure may be provided at the distribution site or work site on which the container 8 may be placed such that at least the outlet 26 from the screw conveyor 22 is supported above the ground. Although it is envisaged that the paving delivery method can be used to deliver a full container to a distribution site from which the paving material in the container can be sold in small quantities to individual customers, it is also envisaged that a full or even partially full container 8 may be supplied to a building site or road works for use as and when required. In this application, after a predetermined time interval has elapsed or when the temperature of the paving material has dropped below a predetermined value, a fresh container 8 of paving material is supplied to the site by a lorry 2 and the old partially used container 8 is returned to the manufacturing and/or bulk distribution plant for reprocessing and refilling. The container 8 is weighed before it is supplied to the building site and after it has been returned to the manufacturing plant. In this way, the workers on the construction site are provided with a constant source of paving material which is within specification and are only charged for the paving material which they actually use. Furthermore there is little or no wastage and associated pollution, since the unused paving material is simply returned to the manufacturing plant, where it is reprocessed.
Although the above method has been described in relation to a road based transport system, it is equally applicable to any other form of transport and any other suitable vehicle, such as a rail carriage adapted to carry containers 8 or any combination of road, rail or other forms of transport by which containers 8 are supplied from the manufacturing plant to the distribution or work site.
It is to be understood that the invention is applicable to my transport system using demountable bodies such as "skip" containers as well as the "roll off" containers using a hook lift system described herein.

Claims

1. A method of delivering aggregate, the method comprising filling a container of a transport vehicle with aggregate at an aggregate manufacturing or bulk distribution plant, driving the container to a distribution site, demounting the container, loading a customer's vehicle with aggregate from the container, mounting the container on to the transport vehicle and returning it to the aggregate manufacturing or bulk distribution plant for reprocessing and/or refilling.
2. A method as claimed in claim 1, in which the container is filled whilst it is mounted on the transport vehicle.
3. A method as claimed in claim 1 or 2, in which the container is returned to the aggregate manufacturing or bulk distribution site when it is empty, when the temperature of the remaining aggregate has dropped below a preset value or when a preset time interval has elapsed since the container was last filled.
4. A method as claimed in any one of claims 1 to 3 , in which the aggregate comprises bituminous coated roadstone .
5. A transport vehicle container for transporting aggregate, the container comprising a rigid body having a base and a side wall, a screw conveyor being provided above the base of the container for selectively conveying the aggregate out of an outlet in the base or side wall of the container.
6. A container as claimed in claim 5, further comprising a support which when extended supports at least a portion of the container above the ground.
7. A container as claimed in claim 5 or 6, in which the base and/or the side walls are double skinned.
8. A container as claimed in claim 7, in which insulation material is situated between the inner and outer skins of the container body.
9. A demountable transport vehicle container for transporting aggregate, the container being provided with an outlet for unloading aggregate from the container, the container further comprising a retractable support which, when the container is demounted, is extended to support the outlet above the ground.
10. A container as claimed in claim 9, in which the retractable support props up the container such that the outlet from the screw conveyer is supported at a predetermined height above the ground when the container is demounted from the vehicle.
11. A container as claimed in any one of claims 5 to 10, further comprising means for metering the amount of aggregate supplied from the outlet.
12. A container as claimed in any one of claims 5 to 11, in which the aggregate comprises bituminous coated road stone.
13. A container as claimed in any one of claims 5 to 11, comprising a container body and a subframe to which the container body is fixed, means being provided to thermally insolate the subframe from the container body.
14. A container as claimed in claim 13, in which the isolating means comprises heat insulating spacers interposed between the subframe and the container body.
15. A method of delivering aggregate substantially as described herein with reference to the accompanying drawings .
16. A transport vehicle container substantially as described herein, with reference to and as shown in the accompanying drawings .
PCT/GB1998/002926 1997-09-29 1998-09-29 Method and apparatus for delivering asphalt-aggregate WO1999016685A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU92724/98A AU9272498A (en) 1997-09-29 1998-09-29 Method and apparatus for delivering asphalt-aggregate

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
GB9720686.6 1997-09-29
GB9720686A GB2329631A (en) 1997-09-29 1997-09-29 Method and apparatus for delivering aggregate.

Publications (1)

Publication Number Publication Date
WO1999016685A1 true WO1999016685A1 (en) 1999-04-08

Family

ID=10819797

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/GB1998/002926 WO1999016685A1 (en) 1997-09-29 1998-09-29 Method and apparatus for delivering asphalt-aggregate

Country Status (3)

Country Link
AU (1) AU9272498A (en)
GB (1) GB2329631A (en)
WO (1) WO1999016685A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102862761A (en) * 2012-10-23 2013-01-09 江苏省交通科学研究院股份有限公司 Device for storing finished rubber asphalts
CN106192675A (en) * 2016-07-19 2016-12-07 柳州首光科技有限公司 A kind of environment-friendly type lift Colophonium automatic heating mechanism

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1619149B1 (en) * 2004-07-23 2009-05-13 Rüdiger Christophel Method for loading an object on a transport means
WO2010123917A1 (en) * 2009-04-20 2010-10-28 Volvo Construction Equipment Ab Integrated paving system and method
CN102660917B (en) * 2012-05-25 2014-06-25 鞍山森远路桥股份有限公司 Heat insulation recycling transport vehicle for hot air circulation asphalt mixture
JP6905345B2 (en) * 2017-02-01 2021-07-21 世紀東急工業株式会社 Management device for paving materials
NL2020029B1 (en) * 2017-12-06 2019-06-18 Koninklijke Bam Groep Nv method for transporting asphalt and asphalt holder.
BE1026812B1 (en) 2018-11-28 2020-06-29 Hoogmartens Wegenbouw N V Buffer system for storing asphalt

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4162766A (en) * 1977-09-16 1979-07-31 Cuson Stanley N Vehicular spreader for icy roads and the like
GB2058178A (en) * 1979-08-30 1981-04-08 Tarmac Roadstone Holdings Ltd Transporting Hot Road-making Material
EP0071291A2 (en) * 1981-07-29 1983-02-09 Pietro Regaldo Apparatus, loadable onto a vehicle, for optionnally distributing solid, liquid or solute road or soil treating substances
DE8507455U1 (en) * 1985-03-14 1985-06-13 Wilhelm Riewe, Fahrzeug- und Apparatebau, 4830 Gütersloh Spreading device
DE3829624A1 (en) * 1988-09-01 1990-03-15 Pietsch Max Kg Gmbh & Co Attachable automatic gritting machine for distributing gritting materials on highways
DE9111681U1 (en) * 1991-09-19 1993-02-18 Westhydraulik-Becker Behaelter-, Apparate- Und Stahlbau Dresden Gmbh, O-8020 Dresden, De

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3364605D1 (en) * 1983-03-07 1986-08-28 Bernard Desourdy Roadable container for storage of bituminous mix
US4810159A (en) * 1985-11-06 1989-03-07 Rudi Stegmuller Batching system
DE9201539U1 (en) * 1992-02-07 1993-06-09 Rupp, Josef, 7071 Heuchlingen, De
GB2304334A (en) * 1995-08-16 1997-03-19 Richard Ian Johnston Transportable Skips

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4162766A (en) * 1977-09-16 1979-07-31 Cuson Stanley N Vehicular spreader for icy roads and the like
GB2058178A (en) * 1979-08-30 1981-04-08 Tarmac Roadstone Holdings Ltd Transporting Hot Road-making Material
EP0071291A2 (en) * 1981-07-29 1983-02-09 Pietro Regaldo Apparatus, loadable onto a vehicle, for optionnally distributing solid, liquid or solute road or soil treating substances
DE8507455U1 (en) * 1985-03-14 1985-06-13 Wilhelm Riewe, Fahrzeug- und Apparatebau, 4830 Gütersloh Spreading device
DE3829624A1 (en) * 1988-09-01 1990-03-15 Pietsch Max Kg Gmbh & Co Attachable automatic gritting machine for distributing gritting materials on highways
DE9111681U1 (en) * 1991-09-19 1993-02-18 Westhydraulik-Becker Behaelter-, Apparate- Und Stahlbau Dresden Gmbh, O-8020 Dresden, De

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102862761A (en) * 2012-10-23 2013-01-09 江苏省交通科学研究院股份有限公司 Device for storing finished rubber asphalts
CN102862761B (en) * 2012-10-23 2014-12-10 江苏省交通科学研究院股份有限公司 Device for storing finished rubber asphalts
CN106192675A (en) * 2016-07-19 2016-12-07 柳州首光科技有限公司 A kind of environment-friendly type lift Colophonium automatic heating mechanism

Also Published As

Publication number Publication date
AU9272498A (en) 1999-04-23
GB2329631A (en) 1999-03-31
GB9720686D0 (en) 1997-11-26

Similar Documents

Publication Publication Date Title
US5580211A (en) Container transportation system
US10662006B2 (en) Proppant discharge system having a container and the process for providing proppant to a well site
US3753506A (en) Unitized refuse transfer station
US3251484A (en) Portable concrete batching plant
MX2015001055A (en) Support apparatus for moving proppant from a container in a proppant discharge system.
MX2015001054A (en) Proppant discharge system and a container for use in such a proppant discharge system.
US20150259864A1 (en) Pothole repair product and mobile apparatus and method of manufacturing an asphalt patch
US6929393B1 (en) Asphalt production plant
US6709219B2 (en) Rear-load transfer system
US3498486A (en) Multiple hopper vehicle
WO1999016685A1 (en) Method and apparatus for delivering asphalt-aggregate
US11866888B2 (en) Material transfer vehicle with ground operator station
US5236261A (en) Conditioned ash surge bin
US2703227A (en) Material pickup and handling vehicle
US2896771A (en) Portable concrete batcher
US3162316A (en) Portable batch plant
US3782566A (en) Nutting truck unloading arrangement for mail bag loading apparatus
AU2018328001A1 (en) Combination door/platform for maintenance access for conveyor of material transfer vehicle
US20200047992A1 (en) Mobile storage container for bulk goods
WO2000018667A1 (en) Self raising hopper for delivering aggregate
US20120296781A1 (en) Compartmentalized Delivery and Removal Container System for Construction Materials
GB2073708A (en) Container traffic container
US3090501A (en) Cement mixing plant
GB2058178A (en) Transporting Hot Road-making Material
US1177353A (en) Transfer-unloader for dump-wagons.

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AL AM AT AU AZ BA BB BG BR BY CA CH CN CU CZ DE DK EE ES FI GB GD GE GH GM HR HU ID IL IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MD MG MK MN MW MX NO NZ PL PT RO RU SD SE SG SI SK SL TJ TM TR TT UA UG US UZ VN YU ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW SD SZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE BF BJ CF CG CI CM GA GN GW ML MR NE SN TD TG

DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
121 Ep: the epo has been informed by wipo that ep was designated in this application
NENP Non-entry into the national phase

Ref country code: KR

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

NENP Non-entry into the national phase

Ref country code: CA

122 Ep: pct application non-entry in european phase