WO1996040549A1 - Buoyant platform - Google Patents

Buoyant platform Download PDF

Info

Publication number
WO1996040549A1
WO1996040549A1 PCT/GB1996/001323 GB9601323W WO9640549A1 WO 1996040549 A1 WO1996040549 A1 WO 1996040549A1 GB 9601323 W GB9601323 W GB 9601323W WO 9640549 A1 WO9640549 A1 WO 9640549A1
Authority
WO
WIPO (PCT)
Prior art keywords
raft
hull
vessel
platform
pontoons
Prior art date
Application number
PCT/GB1996/001323
Other languages
French (fr)
Inventor
Poul-Eric Christiansen
Original Assignee
Kvaerner Oil & Gas Limited
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kvaerner Oil & Gas Limited filed Critical Kvaerner Oil & Gas Limited
Priority to AU59055/96A priority Critical patent/AU5905596A/en
Publication of WO1996040549A1 publication Critical patent/WO1996040549A1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B35/4413Floating drilling platforms, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • B63B21/502Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers by means of tension legs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B77/00Transporting or installing offshore structures on site using buoyancy forces, e.g. using semi-submersible barges, ballasting the structure or transporting of oil-and-gas platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B1/00Hydrodynamic or hydrostatic features of hulls or of hydrofoils
    • B63B1/02Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement
    • B63B1/04Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with single hull
    • B63B2001/044Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with single hull with a small waterline area compared to total displacement, e.g. of semi-submersible type
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B39/00Equipment to decrease pitch, roll, or like unwanted vessel movements; Apparatus for indicating vessel attitude
    • B63B39/06Equipment to decrease pitch, roll, or like unwanted vessel movements; Apparatus for indicating vessel attitude to decrease vessel movements by using foils acting on ambient water
    • B63B2039/067Equipment to decrease pitch, roll, or like unwanted vessel movements; Apparatus for indicating vessel attitude to decrease vessel movements by using foils acting on ambient water effecting motion dampening by means of fixed or movable resistance bodies, e.g. by bilge keels

Definitions

  • the invention relates to a buoyant platform, and to a method of assembling such a platform for the development of an offshore oil/gas field.
  • the invention relates to a buoyant platform formed from an existing semisubmersible vessel secured to an upper surface of a purpose built raft held down against the action of its own buoyancy in the manner of a tension leg platform (TLP).
  • TLP tension leg platform
  • Semisubmersible vessels have been used for some years in the offshore industry for the purpose of drilling, production and marine operations. These semisubmersible vessels typically have two parallel spaced apart pontoons with buoyant columns upstanding from those pontoons to support a deck. In transit the vessel is deballasted so that it can float on the pontoons with the columns clear of the water. This allows the vessel to operate as a catamaran. For activities which require a stable offshore platform, the vessel is ballasted down so that the pontoons are submerged, and only the buoyant columns pierce the water surface - thus giving the semisubmersible vessel a substantial buoyancy with a small waterplane area.
  • the semisubmersible vessel is associated with another floating component, herein referred to as a "raft".
  • Deck oad and area limitations which would normally prevent heavy and bulky equipment from being carried, can be overcome by supporting the semisubmersible vessel on the raft. It may also be desirable to drill oil/gas wells at a certain location, and then leave those wells tied back to surface wellheads at that location, while the drilling equipment is removed and reused at another location.
  • the invention provides a floating platform comprising in combination a semisubmersible vessel having two or more pontoons, buoyant columns upstanding from those pontoons and a deck supported on the columns (the semisubmersible vessel being of a kind known per se); and a raft comprising a hull having a planform greater than the planform of the vessel and two or more buoyant caissons disposed at or near lateral extremities of the raft and configured so that the raft is capable of floating in a stable attitude with the hull of the raft submerged to such a depth that the vessel can float over the hull of the raft with only the buoyant caissons of the raft piercing the water surface, in which the pontoons of the vessel are secured to upper surfaces of the hull, and drilling facilities on the vessel can be used to drill and complete wells with surface wellheads which can subsequently be transferred to and connected to raft mounted production equipment.
  • the semisubmersible vessel can subsequently be released from and floated off the raft when drilling is completed.
  • the raft has means whereby after the semisubmersible vessel has been removed, the raft can be submerged to such a depth that no part of the raft pierces the water surface.
  • the raft is adapted to rest on the seabed.
  • the semisubmersible vessel may later be floated over and reconnected to the hull to retrieve the raft mounted wells and wellheads in order to carry out further drilling or workover activities.
  • the caissons of the raft have mooring clamps to secure the platform on station.
  • Mooring equipment for the platform may comprise vertical tensioned tethers.
  • the platform may incorporate dynamic positioning equipment. It is preferred that the vertical depth of the hull is less at points on the periphery of the hull than it is at the centre of the hull.
  • either or both of the upper and lower surfaces of the hull slope upwardly or downwardly (as the case may be) from the edge of the hull towards the centre of the hull.
  • Peripheral edges of the hull may be profiled to reduce resistance to wave and/or current loads.
  • the hull has compartments for the storage of oil, and there is provision for counterflooding to compensate for the accumulation or depletion of oil within the hull.
  • the invention also provides a method of developing an offshore oilfield which comprises the assembly of a platform as described above including the steps of deballasting a semisubmersible vessel so that it floats on its pontoons, ballasting a raft (of the kind described) sc 'hat the upper surface of its hull is submerged to a depth greater than the deballasted draft o ; ⁇ e vessel, floating the vessel over the hull of the raft, deballasting the raft so that the pontoons of the vessel are raised above water level, and then securing the pontoons of the vessel to upper surfaces of the hull; using drilling facilities on the vessel to drill and complete wells beneath the platform with surface wellheads; and then transferring the surface wellheads to the raft for connection to raft mounted production equipment.
  • the semisubmersible vessel is subsequently released from and floated off the raft when drilling is completed. It is further preferred that the semisubmersible vessel is floated over and reconnected to the hull to retrieve the raft mounted wells and wellheads, and further drilling or workover activities are carried out.
  • a floating platform includes a generally conventional semisubmersible drilling vessel, which is frequently referred to in the offshore industry as a Mobile Offshore Drilling Unit or MODU.
  • This MODU has two elongated pontoons 10, four buoyant columns 11 (upstanding from the ends of each of those pontoons), and a deck 12 supported on the columns.
  • the pontoons 10 are subdivided internally into selectively ballastable watertight compartments.
  • the MODU has anchor chain lockers within its corner columns, and there are winches (not shown) on the tops of those columns and fairleaders 15 near the bases of those columns for deploying mooring arrays.
  • the MODU illustrated by way of example is in fact a SEDCO 600 series semisubmersible drilling vessel, of which three were located worldwide in various operating roles at the time of making this application. This MODU is configured for end bay drilling.
  • the MODU is releasably secured to a purpose built raft 21.
  • the raft has a generally flat hull 22 with a planform larger than the planform of the MODU.
  • the hull 22 has three caissons 23 (located at two adjacent corners and midway along its opposite side), and these caissons stand slightly higher above the upper surface of the hull 22 than the vertical draft of the pontoons 10 of the MODU in their deballasted condition.
  • a raft having a generally flat hull and at least two upstanding caissons at or near its lateral extremities will be referred to as a raft of the kind described.
  • the MODU is secured to the upper surface of the hull
  • the raft 21 gives additional buoyancy to the MODU, and also improves the stability characteristics of the MODU. Fixing the MODU to the raft 21 reduces the wave loads applied to the MODU, because these loads are reacted largely by the raft. Thus fatigue lives in structural elements of the MODU will be significantly improved.
  • the raft 21 may have internal compartments for ballast water and the storage of oil.
  • the raft is fitted with pipework and one or two pump rooms as required for ballast and oil transfer operations.
  • the raft pump rooms are typically located directly below the pump rooms in the MODU pontoons with watertight access from these pontoons. Electrical feeders and pipework to the raft pump rooms can therefore easily be run via the normal routes up through the columns of the MODU.
  • counter flooding arrangements would be necessary, so that sea water could replace or be replaced by oil as the compartments were emptied or filled.
  • a flexible compartment liner could physically separate the oil and the sea water to be used as ballast. Because of the large mass of a concrete raft, it is unlikely that counterflooding would be necessary. However, if dry oil storage was adopted, it might be necessary to fill the tops of the storage compartments with an inert gas.
  • the raft 21 has a moonpool through which drill strings 24 and subsequently rigid or flexible riser systems 25 can be run to the seabed, as shown particularly in Figure 1.
  • the drill strings 24 are deployed from a drilling derrick 32 on the deck 12 of the MODU.
  • the drilling equipment power supplies, mud tank etc.
  • the drilling equipment is mounted on the MODU, and only minimal facilities are mounted on the caissons 23 of the raft 21.
  • the raft will be required to remain on location over a drilling template or production manifold 26, which is secured to the seabed.
  • the wells and wellheads can be transferred (under tension) from the deck of the MODU to a caisson 23 of the raft 21.
  • the raft 21 is held down against the action of its own buoyancy in the manner of a Tension Leg Platform or TLP.
  • tethers 28 extend down from tensioning devices 29 beneath the caissons 23 to foundation templates 31 on the seabed.
  • Conventional mooring lines 20 are deployed from the winches of the MODU and through fairleaders 15 to anchors on the seabed.
  • the mooring lines 20 are set out to a conventional eight anchor mooring array (seen best in Figure 2).
  • the mooring lines 20 can be used to position the combined floating platform (i.e. MODU plus raft) over the required drilling location prior to commencement of drilling operations.
  • the fairieaders shown in Figure 1 can be repositioned on the caissons 23, and can be arranged to clamp the mooring lines 20, so that the mooring loads are carried in the raft 21 rather than in the MODU itself.
  • the winches (not shown) are used to adjust the mooring lines 20, which are then clamped in the fairleaders 15 on the caissons.
  • the hull 22 may be slightly dome shaped so that its draft at its centre is less than its draft around its periphery.
  • the purpose built raft 21 is of simple construction, and could be built in sections in conventional shipyards and then assembled in sheltered water.
  • the raft could be formed of concrete. Using conventional shipbuilding or concrete pouring techniques, the raft (with internal compartments for the storage of oil) could be constructed and assembled very economically.
  • the raft 21 would be ballasted down so that only the tops of the caissons 23 were above sea level.
  • the MODU would be de-ballasted so that it floated only on its pontoons 10, and would then be positioned over the raft 21.
  • the raft 21 would be deballasted so that the upper surface of its hull 22 was above sea level and the MODU was clear of the water. In this condition the pontoons of the MODU could be secured to the upper surface of the hull.
  • the MODU would be released from the raft 21, and floated off to another location.
  • the raft When the MODU has been released, the raft could be drawn down towards the seabed by selective ballasting and/or adjustment of its moorings. The raft would be totally submerged to a depth no deeper than that at which diver intervention on the wellheads is possible. The raft could either be secured at a mid water depth position, or could rest on the seabed if the depth of the sea at that point was shallow. This feature would be of value at locations which are threatened in winter months by drifting ice. The MODU could later return for further drilling or work over operations (e.g. during the following summer).
  • the raft - once in position on site - could be permanently located below the water surface.
  • the invention has the advantage that a single MODU can be used at several locations where surface or near surface wellheads are required.
  • the sophisticated mechanical equipment on the MODU could be used sequentially in combination with several low cost rafts.
  • the raft(s) provide extra buoyancy and greater stability to the MODU while drilling is in progress, so that drilling can continue in more severe sea states than would otherwise be possible.

Abstract

A floating platform comprising in combination a semisubmersible vessel having two or more pontoons (10), buoyant columns (11) upstanding from those pontoons and a deck (12) supported on the columns (the semisubmersible vessel being of a kind known per se); and a raft (21) IN WHICH the raft comprises a hull (22) having a planform greater than the planform of the vessel and two or more buoyant caissons (23) disposed at or near lateral extremities of the raft (21) and configured so that the raft is capable of floating in a stable attitude with the hull of the raft submerged to such a depth that the vessel can float over the hull of the raft with only the buoyant caissons (23) of the raft piercing the water surface, in which the pontoons (10) of the vessel are secured to upper surfaces of the hull (22), and drilling facilities (32) on the vessel can be used to drill and complete wells (24) with surface wellheads which can subsequently be transferred to and connected to raft mounted production equipment (25).

Description

BUOYANT PLATFORM
Technical Field of the Invention
The invention relates to a buoyant platform, and to a method of assembling such a platform for the development of an offshore oil/gas field.
In particular the invention relates to a buoyant platform formed from an existing semisubmersible vessel secured to an upper surface of a purpose built raft held down against the action of its own buoyancy in the manner of a tension leg platform (TLP). Platforms of this type have been described and claimed in our PCT Application No. NO95/00016.
Background of the Invention
Semisubmersible vessels have been used for some years in the offshore industry for the purpose of drilling, production and marine operations. These semisubmersible vessels typically have two parallel spaced apart pontoons with buoyant columns upstanding from those pontoons to support a deck. In transit the vessel is deballasted so that it can float on the pontoons with the columns clear of the water. This allows the vessel to operate as a catamaran. For activities which require a stable offshore platform, the vessel is ballasted down so that the pontoons are submerged, and only the buoyant columns pierce the water surface - thus giving the semisubmersible vessel a substantial buoyancy with a small waterplane area.
This configuration - which is illustrated in U.K. Patent Specification 2068439A - provides a more stable platform for offshore operations than would be provided by a conventional ship shaped vessel. However, for severe seastates, even a semisubmersible vessel becomes subject to movements which are unacceptable for many offshore operations, including inter alia drilling and production. These unacceptable movements lead to 'downtime' during which all the costs of operating the semisubmersible vessel are incurred, but no useful work is done.
Development of offshore oil and gas fields in hostile areas (in terms of severe sea states) has led to requirements for drilling, production and marine operations to be carried out in progressively more severe sea states, with minimum downtime.
Thus there is a requirement for a buoyant platform which is capable of continued operation in more severe sea states than can be tolerated by semisubmersible vessels currently in use. This may be combined with a further requirement for oil storage at an open sea site. In some cases it may be advantageous to employ mobile drilling facilities on a semisubmersible vessel (which is already equipped with power supplies and drilling equipment) to enhance the capabilities of another floating vessel. An example of this enhancement is shown in U.K. Patent Specification 2250767A, in which two floating vessels are located beside each other.
In the present case the semisubmersible vessel is associated with another floating component, herein referred to as a "raft". Deck oad and area limitations, which would normally prevent heavy and bulky equipment from being carried, can be overcome by supporting the semisubmersible vessel on the raft. It may also be desirable to drill oil/gas wells at a certain location, and then leave those wells tied back to surface wellheads at that location, while the drilling equipment is removed and reused at another location.
Disclosure of the Invention
The invention provides a floating platform comprising in combination a semisubmersible vessel having two or more pontoons, buoyant columns upstanding from those pontoons and a deck supported on the columns (the semisubmersible vessel being of a kind known per se); and a raft comprising a hull having a planform greater than the planform of the vessel and two or more buoyant caissons disposed at or near lateral extremities of the raft and configured so that the raft is capable of floating in a stable attitude with the hull of the raft submerged to such a depth that the vessel can float over the hull of the raft with only the buoyant caissons of the raft piercing the water surface, in which the pontoons of the vessel are secured to upper surfaces of the hull, and drilling facilities on the vessel can be used to drill and complete wells with surface wellheads which can subsequently be transferred to and connected to raft mounted production equipment.
It is preferred that the semisubmersible vessel can subsequently be released from and floated off the raft when drilling is completed.
It is further preferred that the raft has means whereby after the semisubmersible vessel has been removed, the raft can be submerged to such a depth that no part of the raft pierces the water surface.
It is further preferred that the raft is adapted to rest on the seabed. In circumstances in which the semisubmersible can be released, the semisubmersible vessel may later be floated over and reconnected to the hull to retrieve the raft mounted wells and wellheads in order to carry out further drilling or workover activities. It is preferred that the caissons of the raft have mooring clamps to secure the platform on station.
Mooring equipment for the platform may comprise vertical tensioned tethers.
The platform may incorporate dynamic positioning equipment. It is preferred that the vertical depth of the hull is less at points on the periphery of the hull than it is at the centre of the hull.
It is also preferred that either or both of the upper and lower surfaces of the hull slope upwardly or downwardly (as the case may be) from the edge of the hull towards the centre of the hull. Peripheral edges of the hull may be profiled to reduce resistance to wave and/or current loads.
It is preferred that the hull has compartments for the storage of oil, and there is provision for counterflooding to compensate for the accumulation or depletion of oil within the hull.
The invention also provides a method of developing an offshore oilfield which comprises the assembly of a platform as described above including the steps of deballasting a semisubmersible vessel so that it floats on its pontoons, ballasting a raft (of the kind described) sc 'hat the upper surface of its hull is submerged to a depth greater than the deballasted draft o; ιe vessel, floating the vessel over the hull of the raft, deballasting the raft so that the pontoons of the vessel are raised above water level, and then securing the pontoons of the vessel to upper surfaces of the hull; using drilling facilities on the vessel to drill and complete wells beneath the platform with surface wellheads; and then transferring the surface wellheads to the raft for connection to raft mounted production equipment.
It is preferred that the semisubmersible vessel is subsequently released from and floated off the raft when drilling is completed. It is further preferred that the semisubmersible vessel is floated over and reconnected to the hull to retrieve the raft mounted wells and wellheads, and further drilling or workover activities are carried out.
Brief Description of the Drawings
A specific embodiment of the invention will now be described by way of example with reference to the accompanying drawings in which:- Figure 1 is a side view of a buoyant platform; Figure 2 is an end view of that platform; Description of the Specific Embodiment
As shown in Figure 1 , a floating platform includes a generally conventional semisubmersible drilling vessel, which is frequently referred to in the offshore industry as a Mobile Offshore Drilling Unit or MODU. This MODU has two elongated pontoons 10, four buoyant columns 11 (upstanding from the ends of each of those pontoons), and a deck 12 supported on the columns. The pontoons 10 are subdivided internally into selectively ballastable watertight compartments. The MODU has anchor chain lockers within its corner columns, and there are winches (not shown) on the tops of those columns and fairleaders 15 near the bases of those columns for deploying mooring arrays.
The MODU illustrated by way of example is in fact a SEDCO 600 series semisubmersible drilling vessel, of which three were located worldwide in various operating roles at the time of making this application. This MODU is configured for end bay drilling.
Following the invention, the MODU is releasably secured to a purpose built raft 21. The raft has a generally flat hull 22 with a planform larger than the planform of the MODU. The hull 22 has three caissons 23 (located at two adjacent corners and midway along its opposite side), and these caissons stand slightly higher above the upper surface of the hull 22 than the vertical draft of the pontoons 10 of the MODU in their deballasted condition. A raft having a generally flat hull and at least two upstanding caissons at or near its lateral extremities will be referred to as a raft of the kind described.
In the simplest form of the invention, the MODU is secured to the upper surface of the hull
22 between the caissons 23. In this way the raft 21 gives additional buoyancy to the MODU, and also improves the stability characteristics of the MODU. Fixing the MODU to the raft 21 reduces the wave loads applied to the MODU, because these loads are reacted largely by the raft. Thus fatigue lives in structural elements of the MODU will be significantly improved.
The raft 21 may have internal compartments for ballast water and the storage of oil.
These compartments are not shown in detail in the Figures, but if the raft were to be made of steel, these would be constructed like conventional compartments of an ocean going VLCC
(Very Large Crude Carrier). If the raft were to be made of concrete, the compartments would be formed like cells in a conventional concrete structure.
The raft is fitted with pipework and one or two pump rooms as required for ballast and oil transfer operations. The raft pump rooms are typically located directly below the pump rooms in the MODU pontoons with watertight access from these pontoons. Electrical feeders and pipework to the raft pump rooms can therefore easily be run via the normal routes up through the columns of the MODU. To compensate for changes in buoyancy in a steel raft, counter flooding arrangements would be necessary, so that sea water could replace or be replaced by oil as the compartments were emptied or filled. Advantageously a flexible compartment liner could physically separate the oil and the sea water to be used as ballast. Because of the large mass of a concrete raft, it is unlikely that counterflooding would be necessary. However, if dry oil storage was adopted, it might be necessary to fill the tops of the storage compartments with an inert gas.
The raft 21 has a moonpool through which drill strings 24 and subsequently rigid or flexible riser systems 25 can be run to the seabed, as shown particularly in Figure 1. The drill strings 24 are deployed from a drilling derrick 32 on the deck 12 of the MODU. The drilling equipment (power supplies, mud tank etc.) is mounted on the MODU, and only minimal facilities are mounted on the caissons 23 of the raft 21. In this case the raft will be required to remain on location over a drilling template or production manifold 26, which is secured to the seabed. Following the invention, when the wells and wellheads are completed, they can be transferred (under tension) from the deck of the MODU to a caisson 23 of the raft 21.
In a preferred method of keeping the platform on location, the raft 21 is held down against the action of its own buoyancy in the manner of a Tension Leg Platform or TLP. In this case tethers 28 extend down from tensioning devices 29 beneath the caissons 23 to foundation templates 31 on the seabed. Conventional mooring lines 20 are deployed from the winches of the MODU and through fairleaders 15 to anchors on the seabed. The mooring lines 20 are set out to a conventional eight anchor mooring array (seen best in Figure 2). The mooring lines 20 can be used to position the combined floating platform (i.e. MODU plus raft) over the required drilling location prior to commencement of drilling operations.
An important feature of the invention relates to an alternative mooring arrangement. The fairieaders shown in Figure 1 can be repositioned on the caissons 23, and can be arranged to clamp the mooring lines 20, so that the mooring loads are carried in the raft 21 rather than in the MODU itself. In use the winches (not shown) are used to adjust the mooring lines 20, which are then clamped in the fairleaders 15 on the caissons. in a variation of the basic configuration of the raft, the hull 22 may be slightly dome shaped so that its draft at its centre is less than its draft around its periphery. With a dome shaped raft, the platform will ride the waves better, and so in theory a smaller air gap would be required between the nominal sea level and the lowest elements of the deck. Turning now to the construction and assembly of the platform, many MODU's already exist which could be used as the upper part of the platform. The purpose built raft 21 is of simple construction, and could be built in sections in conventional shipyards and then assembled in sheltered water. Alternatively, the raft could be formed of concrete. Using conventional shipbuilding or concrete pouring techniques, the raft (with internal compartments for the storage of oil) could be constructed and assembled very economically.
To assemble the complete platform, the raft 21 would be ballasted down so that only the tops of the caissons 23 were above sea level. The MODU would be de-ballasted so that it floated only on its pontoons 10, and would then be positioned over the raft 21. The raft 21 would be deballasted so that the upper surface of its hull 22 was above sea level and the MODU was clear of the water. In this condition the pontoons of the MODU could be secured to the upper surface of the hull.
When drilling operations are completed, and the drilling derrick 32 and associated drilling equipment are no longer required at that particular location, the MODU would be released from the raft 21, and floated off to another location.
When the MODU has been released, the raft could be drawn down towards the seabed by selective ballasting and/or adjustment of its moorings. The raft would be totally submerged to a depth no deeper than that at which diver intervention on the wellheads is possible. The raft could either be secured at a mid water depth position, or could rest on the seabed if the depth of the sea at that point was shallow. This feature would be of value at locations which are threatened in winter months by drifting ice. The MODU could later return for further drilling or work over operations (e.g. during the following summer).
In one form of the invention, the raft - once in position on site - could be permanently located below the water surface.
Advantages of the Invention
The invention has the advantage that a single MODU can be used at several locations where surface or near surface wellheads are required. The sophisticated mechanical equipment on the MODU could be used sequentially in combination with several low cost rafts. The raft(s) provide extra buoyancy and greater stability to the MODU while drilling is in progress, so that drilling can continue in more severe sea states than would otherwise be possible.

Claims

1. A floating platform comprising in combination a semisubmersible vessel having two or more pontoons (10), buoyant columns (11) upstanding from those pontoons and a deck (12) supported on the columns (the semisubmersible vessel being of a kind known per se); and a raft (21) IN WHICH the raft comprises a hull (22) having a planform greater than the planform of the vessel and two or more buoyant caissons (23) disposed at or near lateral extremities of the raft (21) and configured so that the raft is capable of floating in a stable attitude with the hull of the raft submerged to such a depth that the vessel can float over the hull of the raft with only the buoyant caissons (23) of the raft piercing the water surface, in which the pontoons (10) of the vessel are secured to upper surfaces of the hull (22), and drilling facilities (32) on the vessel can be used to drill and complete wells (24) with surface wellheads which can subsequently be transferred to and connected to raft mounted production equipment (25).
2. A floating platform as claimed in Claim 1 in which the semisubmersible vessel can subsequently be released from and floated off the raft when drilling is completed.
3. A floating platform as claimed in Claim 2, in which the raft has means whereby after the semisubmersible vessel has been removed, the raft can be submerged to such a depth that no part of the raft pierces the water surface.
4. A floating platform as claimed in Claim 3, in which the raft is adapted to rest on the seabed.
5. A floating platform as claimed in any one of Claims 2 to 4 in which the semisubmersible vessel can be floated over and reconnected to the hull to retrieve the raft mounted wells and wellheads in order to carry out further drilling or workover activities.
6. A floating platform as claimed in any one of the preceding claims in which the caissons of the raft have mooring clamps to secure the platform on station.
7. A floating platform as claimed in any one of the preceding claims in which mooring equipment comprises vertical tensioned tethers.
8. A floating platform as claimed in any one of the preceding claims in which the platform incorporates dynamic positioning equipment.
9. A floating platform as claimed in any one of the preceding claims in which the vertical depth of the hull is less at points on the periphery of the hull than it is at the centre of the hull.
10. A floating platform as claimed in any one of the preceding claims in which either or both of the upper and lower surfaces of the hull slope upwardly or downwardly (as the case may be) from the edge of the hull towards the centre of the hull.
11. A floating platform as claimed in any one of the preceding claims in which peripheral edges of the hull are profiled to reduce resistance to wave and/or current loads.
12. A floating platform as claimed in any one of the preceding claims in which the hull has compartments for the storage of oil, and there is provision for counterflooding to compensate for the accumulation or depletion of oil within the hull.
13. A method of developing an offshore oilfield which comprises the assembly of a platform as claimed in any one of the preceding claims including the steps of deballasting a semisubmersible vessel so that it floats on its pontoons, IN WHICH further steps include ballasting a raft (21) (of the kind described) so that the upper surface of its hull (22)is submerged to a depth greater than the deballasted draft of the vessel, floating the vessel over the hull of the raft, deballasting the raft so that the pontoons (10) of the vessel are raised above water level, and then securing the pontoons of the vessel to upper surfaces of the hull (22); using drilling facilities (32) on the vessel to drill and complete wells (24) beneath the platform with surface wellheads; and then transferring the surface wellheads to the raft for connection to raft mounted production equipment (25).
14. A method as claimed in Claim 13 in which the semisubmersible vessel is subsequently released from and floated off the raft when drilling is completed.
15. A method as claimed in Claim 14 in which the semisubmersible vessel is floated over and reconnected to the hull to retrieve the raft mounted wells and wellheads, and further drilling or workover activities are carried out.
PCT/GB1996/001323 1995-06-07 1996-06-05 Buoyant platform WO1996040549A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU59055/96A AU5905596A (en) 1995-06-07 1996-06-05 Buoyant platform

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
GBGB9511541.6A GB9511541D0 (en) 1995-06-07 1995-06-07 Buoyant Platform
GB9511541.6 1995-06-07

Publications (1)

Publication Number Publication Date
WO1996040549A1 true WO1996040549A1 (en) 1996-12-19

Family

ID=10775681

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/GB1996/001323 WO1996040549A1 (en) 1995-06-07 1996-06-05 Buoyant platform

Country Status (4)

Country Link
AU (1) AU5905596A (en)
GB (2) GB9511541D0 (en)
MY (1) MY132193A (en)
WO (1) WO1996040549A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2475407C1 (en) * 2011-11-10 2013-02-20 Российская Федерация, от имени которой выступает государственный заказчик Министерство промышленности и торговли Российской Федерации (Минпромторг России) Marine semisubmersible helideck
US8523491B2 (en) 2006-03-30 2013-09-03 Exxonmobil Upstream Research Company Mobile, year-round arctic drilling system

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO982585L (en) * 1998-06-05 1999-12-06 Navion As System for use in offshore work operations, on lakes eaalaa
NO984968L (en) * 1998-10-26 2000-04-27 Lmg Marin Device for positioning vessels
WO2000073135A1 (en) * 1999-05-27 2000-12-07 Aktieselskabet Dampskibsselskabet Svendborg A method of establishing and/or operating a bore well in a seabed and a drilling vessel for use in connection therewith
GB2538275B (en) 2015-05-13 2018-01-31 Crondall Energy Consultants Ltd Floating production unit and method of installing a floating production unit
CN113879472B (en) * 2021-11-03 2024-01-30 江苏科技大学 Semi-submersible drilling platform system with pose compensation capability and control method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2735619A1 (en) * 1976-09-13 1978-03-16 Jose Marco Fayren FLOATING BODY WITH AT LEAST ONE WORK PLATFORM AND PROCEDURE FOR ITS ASSEMBLY
GB2207892A (en) * 1987-08-12 1989-02-15 Goetaverken Arendal Ab A reinforcement element for offshore work vessels
GB2250767A (en) * 1990-12-10 1992-06-17 Shell Int Research Method and system for conducting offshore well operations
GB2285773A (en) * 1994-01-21 1995-07-26 Kvaerner Earl & Wright Floating platform with buoyant raft

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2735619A1 (en) * 1976-09-13 1978-03-16 Jose Marco Fayren FLOATING BODY WITH AT LEAST ONE WORK PLATFORM AND PROCEDURE FOR ITS ASSEMBLY
GB2207892A (en) * 1987-08-12 1989-02-15 Goetaverken Arendal Ab A reinforcement element for offshore work vessels
GB2250767A (en) * 1990-12-10 1992-06-17 Shell Int Research Method and system for conducting offshore well operations
GB2285773A (en) * 1994-01-21 1995-07-26 Kvaerner Earl & Wright Floating platform with buoyant raft

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8523491B2 (en) 2006-03-30 2013-09-03 Exxonmobil Upstream Research Company Mobile, year-round arctic drilling system
RU2475407C1 (en) * 2011-11-10 2013-02-20 Российская Федерация, от имени которой выступает государственный заказчик Министерство промышленности и торговли Российской Федерации (Минпромторг России) Marine semisubmersible helideck

Also Published As

Publication number Publication date
GB9611740D0 (en) 1996-08-07
MY132193A (en) 2007-09-28
AU5905596A (en) 1996-12-30
GB2301800A (en) 1996-12-18
GB9511541D0 (en) 1995-08-02
GB2301800B (en) 1999-03-24

Similar Documents

Publication Publication Date Title
US5791819A (en) Buoyant platform
EP2726362B1 (en) Offshore platform with outset columns
US5964550A (en) Minimal production platform for small deep water reserves
US4995762A (en) Semisubmersible vessel with captured constant tension buoy
US4966495A (en) Semisubmersible vessel with captured constant tension buoy
US4768984A (en) Buoy having minimal motion characteristics
US6666624B2 (en) Floating, modular deepwater platform and method of deployment
US8707882B2 (en) Offshore platform with outset columns
RU2141427C1 (en) Low-draft floating drilling and oil production off-shore platform (versions)
GB2147549A (en) Minimum heave offshore structure
US20070224000A1 (en) Deep draft semi-submersible offshore floating structure
WO1996040549A1 (en) Buoyant platform
EP0732258B1 (en) Semisubmersible vessel with forward mounted crane
US20080014024A1 (en) Method for fabricating a reduced-heave floating structure
GB2253813A (en) Production buoy
GB2306186A (en) Mooring arrangement for buoyant platform
GB2323619A (en) Substructure for an offshore platform and method of installation
GB2333117A (en) Offshore platform
GB2335221A (en) Method of forming a substructure for an offshore platform
MXPA96002827A (en) Float platform
JPS62258014A (en) Method for setting off-shore platform

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AU BR CA CN DK ES GB JP KR LK MX NO NZ PT RU SG US VN

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LU MC NL PT SE BF BJ CF CG CI CM GA GN ML MR NE SN TD TG

DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
121 Ep: the epo has been informed by wipo that ep was designated in this application
122 Ep: pct application non-entry in european phase
NENP Non-entry into the national phase

Ref country code: CA