USRE25199E - Method of constructing swimming pools - Google Patents

Method of constructing swimming pools Download PDF

Info

Publication number
USRE25199E
USRE25199E US25199DE USRE25199E US RE25199 E USRE25199 E US RE25199E US 25199D E US25199D E US 25199DE US RE25199 E USRE25199 E US RE25199E
Authority
US
United States
Prior art keywords
liner
cavity
water
swimming pool
mix
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
Publication date
Application granted granted Critical
Publication of USRE25199E publication Critical patent/USRE25199E/en
Expired legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H4/00Swimming or splash baths or pools

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Description

y 1962 c. A. BROWNELL, JR Re. 25,199
' METHOD OF CONSTRUCTING SWIMMING POOLS Original Filed June 28, 1955 2 SheetsSheet 1 "41M A V] w- 1, M I w W I F/g. u. dad-k HS v.- 4
Carl A. Browne/l, Jr:
INVEN TOR.
c. A. BROWNELL, JR Re. 25,199 METHOD OF CONSTRUCTING SWIMMING POOLS 2 6 9 1 7 1 1W mv 2 Sheets-Sheet 2 Original Filed June 28, 1955 Fig. 4
Fig. 5
Carl .4. Browne/l, J1:
INVENTOR.
United States Patent ()iilice Re. 25,199 Reissued July 17, 1962 Matter enclosed in heavy brackets appears in the original patent but forms no part of this reissue specification; matter printed in italics indicates the additions made by reissue.
This invention relates generally to swimming pool construction and more particularly to a novel process of constructing a swimming pool.
The primary object of the present invention resides in a method [the provision] of constructing a swimming pool which may be constructed in a simple and inexpensive manner to have [and which has] a suitable liner forming the surfacing of the pool.
[A further object of the invention resides in the provision of a swimming pool of great strength due to its shape and manner of construction and which does not require complex reinforcing arrangements for the mix used in molding the walls of the pool.
[The construction of this invention features the utilization of a liner of any suitable tough :and thin material such as a shell made from a synthetic plastic material or which may be formed of other suitable substances and which is supported on suitable members such as stakes or the like in spaced relationship to the sides of a cavity formed in the ground at the site of the pool. A cementitious mix is poured into the space between the walls of the cavity and the liner and forms a bond with the liner. Simultaneous with the pouring of the mix the liner is filled with water for the purpose of weighting the liner into bonding relationship with the mix] The method includes the steps of excavating an upwardly opening, relatively shallow cavity, positioning a liner of any suitable tough and thin material such as a shell made from a synthetic plastic material within the cavity while maintaining the liner in spaced relationship with the cavity such that there is substantially equidistant spacing between the liner and the walls of the cavity, and introducing a fill such as cement into the space between the liner and cavity while simultaneously introducing water into the liner.
These, together with the various ancillary objects and features of the invention which will become apparent as the following description proceeds, are attained by this [swimming pool and] method of construction [thereof], a preferred embodiment of the pool being shown in the accompanying drawings, by way of example, wherein:
FIGURE 1 is a perspective view illustrating the swimming pool;
FIGURE 2 is an exploded longitudinal sectional view of the liner forming one of the important elements of the invention;
FIGURE 3 is an enlarged sectional detail as taken along the plane of line 33 in FIGURE 1 and illustrating how segments of the swimming pool liner are joined together;
FIGURE 4 is a vertical sectional view illustrating the cavity formed at the site of the swimming pool to be constructed and illustrating the drain pipe in position prior to the placement of the liner, the position of the liner being shown in phantom lines;
FIGURE 5 is a vertical sectional view illustrating the swimming pool liner in position and suitably supported in spaced relationship to the walls of the cavity and further illustrating the manner in which the base of cementitious matter or the like is poured into the space between the liner and the walls of the cavity while the liner is filled simultaneously with water to weight the liner; and
FIGURE 6 is a vertical sectional detail view of the swimming pool shown in its completed state.
With continuing reference to the accompanying drawings wherein like reference numerals designate similar parts throughout the various views, reference numeral 10 generally designates the swimming pool constructed in accordance with the concepts of the present invention. This swimming pool includes a liner 12 bonded to a base 14 of concrete, asphalt, orother suitable cementitious or plastic material.
The liner 12 may be formed out of a single unitary molded member or may be formed in two or more sections which are bonded together as can be best seen in FIGURES '2 and 3. The sections of the liner 12 which are indicated at 16 land 18 may be joined together by an underlying strip 20 at the joint 22 between the abutting edges of the sections 16 and 18 of the liner 12 and the abutting edges may have beveled portions as at 24 and 26 so that a sealing strip 28 of generally triangular crosssection can be positioned thereon and bonded to the respective sections 1 6 and 18 to hold the sections 16 and 18 together while still providing a full surface for the liner 12.
In constructing the pool, the liner is positioned on stakes such as are indicated at 30 and supported in spaced relationship from the walls 32 formed by the cavity excavated at the site of the pool to be constructed.
After the liner 12 has been positioned on the stakes 30 so as to be held in spaced relationship with the walls of the cavity 32, simultaneously, a mix or slurry of cementitious material 34, an asphalt, or the like, is poured into such space while water is poured into the liner 12 at a corresponding weight, the water serving to force the liner 12 downwardly into the mix 34 and causing a settling [bonding] action. An outlet pipe 36 may be provided in the liner 12 at any suitable point for disposal of the water in the pool when desired.
Alternatively, the swimming pool may be constructed by first excavating a cavity at the site of the proposed swimming pool slightly larger in all dimensions than the pool to be constructed. Then, a quantity of cementitious material in its plastic or fluid form which will when hardened and cured have a high compression strength may be poured into the bottom of the cavity. While the cementitious material is still fluid the liner 12 of high tensile strength may be positioned on top of the cementitious material approximately equidistant away from the walls of the cavity. Then, water may be added inside the liner as necessary to sink the liner into the cementitious material so as to leave a quantity of the cementitious material under the bottom of the liner and adjusting and leveling the liner into its final position holding the liner in position by any conventional means. Then, the cementitious material may be permitted to cure until .it is sufficiently hard and firm to hold the liner in position after which additional cementitious material may be poured in one or more steps into the remaining cavity between the sides of the liner and the sides of the cavity until the cementitious material fills the cavity to the height of the top of the liner; Simultaneously with this final filling operation the liner can be filled with water to prevent the liner from floating or moving from its original position.
The liner 12 is similar in shape to half an egg thereby providing portions of different depth while assuring that great and unexpected strength for the pool will be achieved.
The foregoing is considered as illustrative only of the principles of the inventio Further, since numerous modifications and changes will readily occur to those skilled in the art, it is not desired to limit the invention to the exact construction and operation shown and described, and accordingly all suitable modifications and equivalents may be resorted to, falling within the scope of the invention as claimed.
What is claimed as new is as follows:
1. The process of constructing a swimming pool which :omprises the steps of excavating an upwardly opening and relatively shallow, dish-shaped cavity, placing a plu- 'ality of support members within such cavity, positionng a generally dish shaped, 'imperforate liner Within the :avity and upon the support members with substantially :quidistant spacing between the liner and the walls of he cavity, pouring a cementitious mix into the space he ween the liner and cavity while simultaneously introlucing water into the liner, and maintaining the flow of :einentitious mix and water at rates such that the volume tf water in the liner is always of a weight greater than he buoyant force of the cementitious mix on the liner.
2. A process of constructing a swimming pool, comvrising the steps of excavating an upwardly opening and elatively shallow dish-shaped cavity, pouring a cemenitious mix in the bottom of the cavity, positioning a hallow dish-shaped imperforate liner on the cementitious six in the bottom of the cavity before the mix has .ardened so that the sides of the liner are spaced from he sides of the cavity and simultaneously pouring water no the liner for Weighting the same, allowing said cementious mix to harden, then pouring additional cementious mix into the space between the sides of the liner nd the sides of the cavity and simultaneously pouring dditional water into the liner for Weighting the same 'hile maintaining the flow of the cementitious mix and iater at rates such that the volume of water in the liner always of a weight greater than the buoyant force of le cementitious mix on the liner.
3. The process of constructing a swimming pool which Jmprises the steps of excavating an upwardly opening 2d relatively shallow cavity, supporting a relatively iallow, imperforate liner within the cavity and positiong the liner to provide subsz antially equidistant spacing ztween the liner and the walls of the cavity, introducing a plastic fill into the space between the liner and cavity while simultaneously introducing water into the liner, and maintaining the flow of fill and water at rates such that the volume of water in the liner is always of a weight greater than the buoyant force of the fill on the liner.
4. The process of constructing a swimming pool which comprises the steps of excavating an upwardly opening and relatively shallow cavity, positioning a generally dishshaped, imperfora'te liner within the cavity while maintaining the liner in spaced relationship with the cavity so that the liner walls are spaced substantially equidistant from the walls of the cavity, introducing a slurry fill into the space between the liner and cavity while simultaneously introducing water into the liner, and maintaining the flow of fill and water at rates such that the volume of water in the liner is always of a weight greater ihe buoyant force of the fill on the liner.
5. The process of constructing a swimming pool which comprises the steps of excavating an upwardly opening and relatively shallow cavity, positioning a generally dishshaped, imperforate liner within the cavity while mainruining the liner in spaced relationship with the cavity so that the liner walls are spaced substantially equidistant from the walls of the cavity, introducing cement into the space between the liner and cavity while simultaneously introducing water into the liner, and maintaining the flow of cement and water at rates such that the volume of water in the liner is always of a weight greater than the buoyant force of the cement on the liner.
References Cited in the file of this patent or the original patent UNITED STATES PATENTS 1,372,856 Winterbottom Mar.'29, 1921 1,963,405 Eichelman et al June 19, 1934 2,333,315 Klingberg Nov. 2, 1943 2,376,414 Billner et al May 22, 1945 2,382,171 Pomyk ala Aug. 1-4, 1945 2,617,764 Hauber et al. Nov. 11, 1952 2,624,931 Billner Jan. 13, 1953 2,674,775 Wi llson Apr. 13, 1954
US25199D Method of constructing swimming pools Expired USRE25199E (en)

Publications (1)

Publication Number Publication Date
USRE25199E true USRE25199E (en) 1962-07-17

Family

ID=2093882

Family Applications (1)

Application Number Title Priority Date Filing Date
US25199D Expired USRE25199E (en) Method of constructing swimming pools

Country Status (1)

Country Link
US (1) USRE25199E (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3302407A (en) * 1964-04-20 1967-02-07 Continental Oil Co Subterranean storage facilities and method of constructing such facilities
US3318059A (en) * 1966-05-16 1967-05-09 Universal Building Products Co Wall foundation construction involving block having mortar retention means
US3380252A (en) * 1965-03-18 1968-04-30 Renshaw Clarence Installation for preserving fresh-water supply
US3461673A (en) * 1967-10-23 1969-08-19 Phillips Petroleum Co Lined pit having wind resistant liner therein and method
US3501782A (en) * 1967-10-03 1970-03-24 Hendon Construction Co Swimming pool assembly including rigid liner for sidewalls of pool with interlocking sections
US6669876B2 (en) * 2000-11-30 2003-12-30 Bruce Torrance Method of preparing smooth, watertight concrete surfaces on concrete pools

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3302407A (en) * 1964-04-20 1967-02-07 Continental Oil Co Subterranean storage facilities and method of constructing such facilities
US3380252A (en) * 1965-03-18 1968-04-30 Renshaw Clarence Installation for preserving fresh-water supply
US3318059A (en) * 1966-05-16 1967-05-09 Universal Building Products Co Wall foundation construction involving block having mortar retention means
US3501782A (en) * 1967-10-03 1970-03-24 Hendon Construction Co Swimming pool assembly including rigid liner for sidewalls of pool with interlocking sections
US3461673A (en) * 1967-10-23 1969-08-19 Phillips Petroleum Co Lined pit having wind resistant liner therein and method
US6669876B2 (en) * 2000-11-30 2003-12-30 Bruce Torrance Method of preparing smooth, watertight concrete surfaces on concrete pools

Similar Documents

Publication Publication Date Title
US2887759A (en) Method of constructing swimming pools
US3610564A (en) Construction means for the construction of a swimming pool
US20210395971A1 (en) Method of making molded concrete blocks having simulated brick or stone outer surfaces
USRE25199E (en) Method of constructing swimming pools
CZ281344B6 (en) Process for producing a panel-like concrete element
US3568392A (en) Method of installing a one piece swimming pool
US3768266A (en) Shoreline construction for artificial water bodies
US4232491A (en) Swimming pool deck
US2140978A (en) Swimming pool
US1610341A (en) Concrete breakwater and method of installing same
KR910001393B1 (en) Method of constructing a rigid structure upon the bottom of a body of water as well as lost casing fbottom of a body of mater as well as lost casting or performing said method for preforming baid method
US4818142A (en) Method and apparatus for constructing a walled pool excavation
US2315732A (en) Porous concrete construction and method of making the same
JPH0475966B2 (en)
CN110424439B (en) Prefabricated ceramsite concrete hollow slab shaping tire membrane and construction method thereof
JPS6055110A (en) Construction of concrete structure
GB2087947A (en) Permanent Formwork for Building Retaining Walls
US3200548A (en) Precast shell coping and method of construction for swimming pools
FR2370842A1 (en) Swimming bath with prefabricated reinforced concrete sides - has bottom ledge all around with connections and projecting rods for adjoining bottom
JPS5536548A (en) Construction method for prefabricated concrete retaining-wall and stay rod member
US3324207A (en) Method of placing concrete with a predetermined selected placement of aggregate
JPH05112911A (en) Back-filling construction
JPH09151470A (en) Work execution method for underground structure
JPH0754354A (en) Precast concrete slab for foundation and construction method of foundation using this precast concrete slab
KR960011006A (en) Concrete pouring in trench using Styropole ball